Documente Academic
Documente Profesional
Documente Cultură
Report
Long Island Power Authority (LIPA)
NCR 07133
Site Visit Conducted
July 23-24, 2015
May 25, 2016
TOPs have a primary responsibility for maintaining the real-time reliability of the local system, and operate, or direct the
operations of the transmission facilities. Acceptable reliability levels can be maintained only if the TOPs, and other entities
that make up the Interconnection, function in accordance with good operating practices and reliability criteria defined by
the NERC Reliability Standards. Good operating practices include, but are not limited to, full compliance with the NERC
Reliability Standards without regard to economic consideration or burdening neighboring systems.
Certification Team
Following notification of LIPA’s request for certification and registration as a TOP, which was received on September 29,
2014, a CT was formed and a Certification evaluation date was selected to perform an on-site visit. An on-site review was
held at the LIPA’s primary Control Center on July 23-24, 2015. The rosters for members of the CT, LIPA, and PSEG (LIPA
Service Providers) are listed in Attachment 1.
On August 28, 2015, an Interim Report was issued, identifying certain items that were required to be completed before a
recommendation on Certification could be made. Because the effective date was fixed as July 1, 2016 by the
Implementation of the new BES definition, a schedule for completion of the Certification process was set to coincide with
that date.
Overall Conclusion
The certification process was completed in accordance with the NERC Rules of Procedure (ROP) to determine if LIPA has the
necessary processes, procedures, tools, training and personnel to perform the function as a NERC-certified TOP. Prior to
and during the initial on-site review, LIPA presented evidence related to the applicable standards/requirements for the CT
to review. Based on this evidentiary review, the CT had reasonable assurance that LIPA would have the processes,
procedures, tools, training and personnel in place to reliably perform the TOP function.
The CT found the LIPA operators to be equipped with the necessary operating tools, and they are prepared to perform the
TOP operations. All of LIPA’s operators are NERC-certified operators.
Findings
No findings which would prevent LIPA from being certified as a NERC-certified TOP were identified by the CT as of the
issuance of this Final Report.
Positive Observations
The CT noted the following positive aspects that will enhance LIPA’s performance as a TOP:
LIPA owns an electric transmission and distribution system located in its service area, which includes the New York Counties
of Nassau and Suffolk (with certain limited exceptions) and a small portion of Queens County, New York known as the
Rockaways. LIPA is a member of the New York Independent System Operator (NYISO) which serves as the registered
Transmission Operator (TOP) for the LIPA-owned transmission system defined by NPCC as part of the “Bulk Electric System”
(BES). LIPA operates the non-BES portion of its transmission system. LIPA also owns an 18% interest in the Nine Mile Point
2 nuclear generating facility located in Oswego, New York, for which Nine Mile Point Nuclear Station, LLC is registered with
NPCC and NERC as the Generator Owner (GO) and Generator Operator (GOP).
Since 1998 LIPA has contracted with a private company to manage, operate and maintain its T&D System (“Service
Provider”). As of January 1, 2014 PSEG Long Island (“PSEG LI”) is the Service Provider, pursuant to the Amended and
Restated Operations Services Agreement, (the “OSA”). The OSA has a base term of 12 years and expires on December 31,
2025.
PSEG LI is required to provide operations services for the T&D System on behalf of LIPA at all times in accordance with the
standards set forth in the OSA. Under the OSA, except for certain rights and responsibilities reserved to LIPA, PSEG LI
assumes and undertakes the rights and responsibilities for management, operation and maintenance of the T&D System
and the establishment of policies, programs and procedures with respect thereto, including: all electric transmission,
distribution and load servicing activities for the safe and reliable operation and maintenance of the T&D System; day-to-day
Under the OSA, as the owner of the T&D System, LIPA retains the ultimate authority and control over the assets comprising
the T&D System. In connection therewith, LIPA has continuing oversight responsibilities with respect to the operation and
maintenance of the T&D System. LIPA’s Director of T&D System Oversight, serves as the LIPA Compliance Officer and
oversees compliance related activities that are implemented on a day-to-day basis by PSEG LI.
System Overview
LIPA’s service area includes approximately 1.1 million customers, and had a peak usage of 5,915 MW in the summer of
2011. Long Island is divided into four counties: Kings, Queens, Nassau and Suffolk; with land area totaling 1,377 square
miles. The LIPA service territory consists of most of Nassau and Suffolk counties and the Rockaway Peninsula in Queens.
LIPA’s service territory covers about 1,230 square miles, encompassing nearly 90 percent of Long Island’s total land area.
The area closer to Kings/Queens Counties is urbanized and the area to the eastern portion is rural. Three small
independent municipal electric systems - Freeport, Rockville Centre, and Greenport - are located within the LIPA service
territory.
The LIPA owned transmission system includes approximately 1,366 miles of overhead and underground lines with voltage
levels ranging from 23 kV to 345 kV. LIPA operates its transmission system (classified by NPCC as non-BES) at voltages from
138 kV to 23 kV. The NYISO is registered with NPCC and NERC as the Transmission Operator (TOP) with responsibility for
LIPA-owned transmission system elements classified by NPCC as BES elements.
The following table identifies the LIPA-owned circuit miles at voltage levels of 100 kV and above:
Voltage Circuit Miles
345 8
138 447
LIPA’s distribution system has approximately 13,715 circuit miles of overhead and underground lines (9,020 overhead and
4,695 underground) and approximately 187,032 line transformers with a total capacity of approximately 12,168 MVA. There
are approximately 180 substations used to step the voltages to 13 kV for distribution.
Interconnections.
With respect to the NPCC-defined BES elements, there are two BES elements connecting LIPA to Consolidated Edison.
LIPA has seven transmission interconnections to neighboring electric systems. Five are AC and two are HVDC.
The SCADA EMS consists of 2 production systems, 2 test environments and a Dispatch Training Simulator
Documentation List
Copies of all supporting LIPA documents were collected as evidence of LIPA’s preparedness, and will be kept as a record of
evidence to support the CT’s recommendation. These documents will be retained at NPCC’s offices in New York, NY for a
period of six (6) years from issuance of the Certification.
None of the documents listed below are included with the distribution of this final report. Per the NERC Rules of
Procedure, and due to the confidential nature of this material, these documents are available for review at NPCC’s offices
after proper authorization is obtained through NPCC and NERC:
• LIPA TOP Questionnaire
• LIPA TOP Master Matrix
• LIPA’s various TOP evidence files
• Presentations made by the CT and LIPA
• Internal Compliance Program and Internal Controls Documentation
LIPA Personnel
Name Position
John D. OConnell Mg Dir & VP - Electric Operations, Long Island T&D Operations
The TOP Master Matrix is a spreadsheet created using the VRF Matrix available on NERC’s website under the Standards
link, and eliminating all functions other than the TOP function. Using the TOP Master Matrix spreadsheet, the CT cataloged
the documentation evidence provided by LIPA. The spreadsheet contains all the applicable NERC Standards and associated
Requirements for an entity to be evaluated as a NERC-certified TOP. In the Certification Process, the CT inserted the
appropriate LIPA document references in which evidence provided by LIPA met the applicable Standards and Requirements.
Applications Review
The on-site visit focused on reviewing documentation, evaluating control centers’ configurations, interview of LIPA’s
operators and other appropriate personnel, evaluating the TOP EMS applications and operator toolset that LIPA has
available for their operators.
1. Signed CFR agreement and matrix should be provided to the CT for review.
2. Review whether there are new BES Cyber Systems identified as essential to the TOP function and whether they are
compliant with CIPV5.
3. Finalize and implement the SOL Methodology.
4. Establish procedures to coordinate all new protective systems and all protective system changes with neighboring
Transmission Operators and Balancing Authorities. (PRC-001-1.1(ii), Requirement 3.2)
5. Verify NERC Certifications are all current prior to 7/1/16 (PER-003-1 R2)
6. Develop and implement a Systematic Approach to Training (SAT) for both Operators and Operations Support
Personnel. Identify reliability related tasks. Verify capabilities of operations personnel as required. (Per-005-2)