CATALOGO DE OBRA
HOJA A-1
DATOS GENERALES
PROYECTO: VIVIENDA UNIFAMILIAR
RESPONSABLE: UNIV. MARCO ANTONIO BALLESTEROS PATON
FECHA: 4/28/2017
MONEDA: BOLIVIANOS [Bs]
CATALOGO DE OBRA
TOTAL MATERIALES 0
2. MANO DE OBRA.-
CODIGO DESCRIPCION UNIDAD CANTIDAD P.U. IMPORTE
001-LPZA AYUDANTE HORAS 0.08 hrs/M2 11.25 Bs/hrs 0.95 Bs
COMPUTO METRICO
PLANILLA 1.1
DATOS GENERALES
PROYECTO: VIVIENDA DE DOS PLANTAS
RESPONSABLE: UNIV. MARCO ANTONIO BALLESTEROS PATON
ITEM: 100
DESCRIPCION: LIMPIEZA DE TERRENO
UNIDAD: M2
MONEDA: BOLIVIANOS [Bs]
INSUMOS
CODIGO DESCRIPCION CANTIDAD RENDIMIENTO TOTAL A COMPRAR
MANO DE OBRA
CODIGO DESCRIPCION CANT JORNAL [Bs] RENDIMIENTO CANTIDAD TIEMPO TOTAL TOTAL M.O.
A001 AYUDANTE 2 Bs 90 0.08 hrs/M2 377.86 M2 32.00 hrs Bs360.00
HERRAMIENTAS Y EQUIPOS
CODIGO DESCRIPCION CANTIDAD PRECIO DESGASTE
H001 HERRAMIENTAS M 1 5% DE M.O.
MEMORIA DE CALCULO
DATOS
AREA 377.86 M2
No. DE AYUDANTES 2 PEONES COSTO DE LIMPIEZA Bs 360.00
DURACION 2 DÍAS
JORNAL 90 Bs/DÍA 11.25 Bs/hrs
RESUMEN
PU CANTIDAD TOTAL
COSTO DIREC Bs1.01 377.86 Bs381.60
COSTO TOTAL 1.12 377.86 Bs422.14
Bs2.13 377.86 Bs803.74
COMPUTO METRICO
PLANILLA 1
DATOS GENERALES
PROYECTO: VIVIENDA DE DOS PLANTAS
RESPONSABLE: UNIV. MARCO ANTONIO BALLESTEROS PATON
ITEM: 101
DESCRIPCION: INSTALACION DE FAENA
UNIDAD: GLB
MONEDA: BOLIVIANOS [Bs]
INSUMOS
CODIGO DESCRIPCION CANTIDAD RENDIMIENTO TOTAL A COMPRAR
MANO DE OBRA
CODIGO DESCRIPCION JORNAL [Bs] RENDIMIENTO CANTIDAD TIEMPO TOTAL TOTAL M.O.
HERRAMIENTAS Y EQUIPOS
CODIGO DESCRIPCION CANTIDAD PRECIO DESGASTE
MEMORIA DE CALCULO
RESUMEN
PU CANTIDAD TOTAL
COSTO DIRECTO Bs2,000.00 1 Bs2,000.00
COSTO TOTAL 2058.61 1 Bs2,058.61
Bs4,058.61
COMPUTO METRICO
PLANILLA 1
DATOS GENERALES
PROYECTO: VIVIENDA DE DOS PLANTAS
RESPONSABLE: UNIV. MARCO ANTONIO BALLESTEROS PATON
ITEM: 102
DESCRIPCION: REPLANTEO
UNIDAD: M2
MONEDA: BOLIVIANOS [Bs]
INSUMOS
CODIGO DESCRIPCION CANTIDAD UNID RENDIMIENTO P.U.
102-1 LISTON 290 P2 0.76748002 4.5
102-2 RIPA 47 P2 0.12438469 4.5
102-3 CLAVOS 1 KG 0.00264648 12
102-4 NYLON 1 ROLLO 0.00264648 6
102-5 PINTURA 1 Ltr 0.00264648
MANO DE OBRA
CODIGO DESCRIPCION CANT JORNAL [Bs] RENDIMIENT CANTIDAD TIEMPO TOTAL TOTAL M.O.
A001 AYUDANTE 2 Bs 90 0.05 hrs/M2 336.94 M2 17.39 hrs 195.64 Bs/M2
M001 MAESTRO 1 Bs 130 0.03 hrs/M2 336.94 M2 8.70 hrs 141.30 Bs/M2
ÑÑÑÑ-L.
MEMORIA DE CALCULO
MANO DE OBRA
DATOS
AREA 336.94 M2
No. DE AYUDANTES 2 PEONES COSTO DE REPLANTEO Bs 310.00
No DE MAESTRO 1 ALBAÑIL
DURACION 1 DÍAS
JORNAL AYUDANTE 90 Bs/DÍA 11.25 Bs/hrs
JORNAL MAESTRO 130 Bs/DÍA 16.25 Bs/hrs
1.- CONVERSION DE DIAS DE TRABAJO A HORAS Y CALCULO DE RENDIMIENTO
INICIO MAÑANA FIN MAÑANA INICIO TARDE FIN TARDE TOTAL HORASSEMANA
LUNES A VIERNES 8 12 14 18 8 40
SABADOS 7 15 0 0 8 8
48
INICIO DE ITEM LUNES 3 DE ABRIL
DIAS FECHAS HORAS COSTO M.O. RND. UNI. % RND. COSTO
LUNES 4/6/2017 8 AYUDANTE 180.00 Bs 0.92 Bs/M2 0.58 0.05 hrs/M2
MAESTRO 130.00 Bs 0.92 Bs/M2 0.42 0.03 hrs/M2
8 310.00 Bs 1.00
INSUMOS
EJE MADERA
CANTIDAD LONGITUD CABALLETE # LISTONES # RIPAS LONG. LIST LONG. RIPA
Y 11 20.14 22 44 22 6600 2200
X 11 16.73 22 44 22 6600 2200
TOTAL 22 36.87 44 88 44 13200 4400
100.00 cm LISTON
h2
b2
RIPAS
h1
L b2
h 150.00 cm
b
NYLON
RESUMEN
PU METRADO TOTAL
COSTO DIREC Bs5.12 377.86 Bs1,935.03
COSTO TOTAL 5.27 377.86 Bs1,991.74
Bs3,926.77
COMPUTO METRICO
PLANILLA 1
DATOS GENERALES
PROYECTO: VIVIENDA DE DOS PLANTAS
RESPONSABLE: UNIV. MARCO ANTONIO BALLESTEROS PATON
ITEM: 104
DESCRIPCION: RELLENO Y COMPACTADO
UNIDAD: M3
MONEDA: BOLIVIANOS [Bs]
INSUMOS
CODIGO DESCRIPCION CANTIDAD RENDIMIENTO TOTAL A COMPRAR
MANO DE OBRA
CODIGO DESCRIPCION JORNAL [Bs] RENDIMIENTOCANTIDAD TIEMPO TOTAL TOTAL M.O.
HERRAMIENTAS Y EQUIPOS
CODIGO DESCRIPCION CANTIDAD PRECIO DESGASTE
MEMORIA DE CALCULO
RESUMEN
PU CANTIDAD TOTAL
COSTO DIREC Bs2,000.00 1 Bs2,000.00
COSTO TOTAL 2058.61 1 Bs2,058.61
Bs4,058.61