Vol As of 3rd March 2018 BoQ

Conc Start Finish Days M3/D Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19
Upper Reservoir inlet structure & Head Race 668 08-02-19 18-07-19 161 4 91 114 137 137 137 46
Lower Reservoir Inlet structure & Tail Race 931 15-05-19 25-08-19 102 9 100 301 281 251
Penstock - Encase 1778 14-12-18 07-02-19 56 16 175 437 175 175 524 437 437 402
Penstock - Thrust 1000 19-07-19 14-11-19 119
Powerhouse – RL 46.5 to 65.75 External Walls 8058 01-02-19 04-04-19 97 83 3,198 3,198 1,645
Powerhouse – Internal Slabs & Concrete around mechanical elements  4058 16-05-19 17-08-19 93 44 480 1,440 1,632 480
Powerhouse – RL 65.75 to top of Wall External Walls 8126 01-03-19 15-05-19 75 108 2,384 2,860 2,860
M3/D 8 20 157 151 81 115 163 219 111 53 20
Mthly Total 175 437 3,464 3,312 1,782 2,521 3,578 4,822 2,437 1,168 437
Cum Total 175 611 4,075 7,388 9,169 11,690 15,268 20,089 22,526 23,694 24,130

Structural Concrete Demand


6,000 30,000

5,000 25,000

4,000 20,000

3,000 15,000

2,000 10,000

1,000 5,000

- -
Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19

S-ar putea să vă placă și