Oracle 1z0-348 : Practice Exam
Question No : 1

During a Manufacturing Cloud implementation, the customer request to develop Oracle


Transactional Business Intelligence reports that are not available out-of- the box.

Identify the tool that is available to the Report Developer in Manufacturing Cloud to develop
the reports.

A. Oracle Business Intelligence Standard Edition


B. Oracle Business Intelligence Publisher
C. Oracle Business Intelligence Enterprise Edition
D. Oracle Business Intelligence Application

Answer: B

Question No : 2

In a manufacturing plant, two purchase components P1 and P2 and a resource R1 are


required to assemble a product. The cost of the assembly is calculated by using the
standard costing method. The work definition and resource rates of the assembly have
been defined as required.

A cost accountant is estimating cost of the assembly, analyzing rolled-up costs before
finally publishing estimates as frozen standards to cost accounting by using a cost planning
scenario. While reviewing rolled up costs, the extended costs of purchase components are
not included in a rolled-up scenario.

Identify the reason.

A. Purchase components P1 and P2 are not associated with Material cost plan of the cost
planning scenario.
B. Costs for purchase components P1 and P2 are not defined in cost accounting.
C. Create Accounting was not initiated.
D. Create Accounting Distributions was not initiated.

Answer: D

Question No : 3

Leaders in it certification 2
Oracle 1z0-348 : Practice Exam
To reduce the subassembly stock with no impact on material planning of child components
of the subassemblies stock, you need to modify the multilevel item structure of a product.

Identify the action that meets this requirement.

A. Change the Supply Type = Push in Item definition and Work Definition, for
subassemblies having high inventory stock.
B. Change the Supply Type = Phantom in Item definition and Work Definition, for
subassemblies having high inventory stock.
C. Change the Supply Type = Assembly Pull in Item definition and Work Definition, for
subassemblies having high inventory stock.
D. Change the Supply Type = Operation Pull in Item definition and Work Definition, for
subassemblies having high inventory stock.

Answer: C

Question No : 4

You are reviewing the production status of your manufacturing plant shop floor as a
production supervisor. Your production manager wants a report on a work order status
which is reserved against a particular customer. The final assembly of the work order is
serialized.

Which option shows the steps to complete the task using the mobile application?

A. Use your mobile camera to scan the bar coded serial number of the final assembly>
Upload the barcode to open the work order details page > Click Actions and select the E-
mail icon> Select required work orders> Select the e-mail client, enter the recipient’s e-
mail, and click Send.
B. Select the infotile Customer to open the work order details page> Click Actions and
select the E-mail icon> Select required work orders>Select the e-mail client, enter the
recipient’s e-mail, and click Send.
C. Use your mobile camera to scan the bar coded serial number of the final assembly>
Upload the barcode to open the work order details page> Select required work orders>
Click Social icon (OSN) > Select recipient, and click Share.
D. Search the work order by customer name to open the work order details page> Click
Actions and select the E-mail icon> Select required work orders> Select the e-mail client,
enter the recipient’s e-mail, and click Send.

Answer: A

Leaders in it certification 3
Oracle 1z0-348 : Practice Exam
Question No : 5

Your customer runs two daily shifts in her plant: Morning Shift and Evening Shift. A
resource LATHE is assigned to the work center W1. There are five units of LATHE
available, of which three units are available for the Morning Shift and the remaining units
are available for the Evening Shits.

Which two actions must you perform to associate LATHE with W1?

A. Do not select the Available 24 Hours check box and in the Resource Availability region,
enter 3 against the resource LATHE in the Morning Shift column.
B. Select the Available 24 Hours check box and in the Resource Availability region, enter 3
against the resource LATHE in the Morning Shift column.
C. Select the Available 24 Hours check box and in the Resource Availability region, enter 2
against the resource LATHE in the Evening Shift column.
D. Do not select the Available 24 Hours check box and in the Resource Availability region,
enter 2 against the resource LATHE in the Evening Shift column.
E. Do not select the Available 24 Hours check box and in the Resource Availability region,
enter 60% against the resource LATHE in the Morning Shift column.
F. Do not select the Available 24 Hours check box and in the Resource Availability region,
enter 40% against the resource LATHE in the Evening Shift column.

Answer: B,E

Question No : 6

The Plant Manager informs you that they have bought several machines for their
manufacturing plant ABC. The plant has been set up with a separate cost element set ABC
in Manufacturing Cloud. You are requested to configure these machines in such a way that
those are costed to the work order for which operations are performed on these machines.

Identify the correct setup that you will advise to the Plant Manager.

A. Set up the machines as cost element type of “Resource” by selecting Cost Element set
ABC.
B. Set up the machines as cost element type of “Overhead” by selecting Cost Element set
ABC.
C. Set up the machines as cost element type of “Overhead” by selecting Cost Element set
Common.
D. Set up the machines as cost element type of “Resource” by selecting Cost Element set
Common.

Leaders in it certification 4
Oracle 1z0-348 : Practice Exam
Answer: D

Question No : 7

During a Manufacturing Cloud implementation, the Production Supervisor wants to close


the work orders for last month and wants to make sure that the work orders include the
correct cost.

Identify the approach to be taken by the Production Supervisor.

A. The Production Supervisor need not include cost variances while costing last month’s
work orders because those can be applied directly in subledger accounting.
B. The Production Supervisor needs to include all costs and variances in last month’s work
orders and close them; however, the work orders where updates are expected, should not
be closed.
C. The Production Supervisor should make sure that all costs are included while closing
last month’s work orders; however, variances can be included after closing the work orders.
D. Work order costs can be updated anytime regardless of the status of the work order.

Answer: B

Question No : 8

In a Manufacturing Cloud post production support environment, a user wants to update


some of the operations in the work orders by using the Midpoint Scheduling feature.
However, the user is unable to update any of the orders.

Identify two reasons.

A. The work order operations do not have operations start or completion date.
B. The scheduled resources are not part of the organization selected by the user.
C. None of the operations include scheduled resources.
D. The operations are missing sequence.

Answer: C,D

Question No : 9

Leaders in it certification 5
Oracle 1z0-348 : Practice Exam
As a production supervisor, you require immediate access to critical shop floor execution
systems to take action while on the go.

Which four work order related actions can be taken in the Manufacturing Supervisor mobile
application?

A. Executing standard work order and updating item and resource usage
B. Creating a new standard or non standard work order
C. Searching for work orders and sending them through e-mail
D. Releasing work orders using quick swipe details
E. Reviewing operation, component, and resource detail
F. Reviewing customer information of work orders

Answer: C,D,E,F

Question No : 10

Identify the two capabilities that the Application Development Framework Desktop
Integration (ADFDI) framework provides for Work Definitions in Manufacturing Cloud.

A. You can mass create and update work definitions and their operations, items, and
resources.
B. You can mass create and update work definitions and their operations, items only and
cannot add resources in work definitions.
C. You can mass create and update work definitions and their operations only and cannot
add items and resources in work definitions.
D. You can copy work definitions form one organization to another organization.

Answer: A,D