METHOD STATEMENT
Contract No.9631U-G-CS02-2001-0002
Note: SP/CPY comments incorporated. Pages modified under this revision: 3,5,7,9
Date
Rev
DD-MMM-YY
STATUS WRITTEN BY CHECKED BY APPROVED BY
IKRA Project –
Integrated Vinyl Plant Nizhny Novgorod
Contents
1) PURPOSE ............................................................................................................................................... 3
2) REFERENCES .......................................................................................................................................... 3
3) SCOPE OF WORK ................................................................................................................................... 4
4) JOB CHECKLIST ...................................................................................................................................... 4
5) SEQUENCING OF ACTIVITIES .................................................................................................................. 4
6) MATERIAL AND EQUIPMENT.................................................................................................................. 6
7) PERSONNEL AND QUALIFICATION .......................................................................................................... 8
8 ) JOB SAFETY ANALYSIS ............................................................................................................................. 9
IKRA Project –
Integrated Vinyl Plant Nizhny Novgorod
1) PURPOSE
This document describes the methods proposed to be used for the HVAC (Heating Ventilation Air
Conditioning) rectangular duct fabrication and fittings fabrication at site activities within RusVinyl
IKRA Project.
2) REFERENCES
3) SCOPE OF WORK
4) JOB CHECKLIST
5) SEQUENCING OF ACTIVITIES
Step of work
The sheet metal (coated galvanize) within the form of roll or plate will be cut by arm operated sheet
shear machine or scissor according to manufacturing dimensions.
The cut material’s one side will be sent through the lock machine. Every 25 cm intervals the cut
material will be bent by sheet folder machine. Later the material is formed into rectangular shape.
Rectangular shaped sheet metal’s flat side and bent side will be locked hammering by metal
hammer.
The joint profiles are cut according to dimension of the ducts by using rotary saw. The cut joint
profiles are connected to ducts using corner pieces by the tack welding machine or electrical screw
driver.
IKRA Project –
Integrated Vinyl Plant Nizhny Novgorod
The openings within the corner pieces are sealed by silicone application. After curing of the
silicone, the duct is ready for installation.
• Micrometer
IKRA Project –
Integrated Vinyl Plant Nizhny Novgorod
• Lock machine
• Silicon gun
• Silicon
• Hammer
• Circular saw
• Screw driver
PPE REQUIREMENTS
• Site Engineer
• 1 Foreman
• ~ 2 HSE Officers
• ~ 2 HSE Workers
• 3-4 helpers
IKRA Project –
Integrated Vinyl Plant Nizhny Novgorod
Prevention,
Steps of Task (Sequencing as Residual
Hazards: Risks Protection,
per Method Statement): Risks
Mitigation Measures
Muscular Pain Responsible supervisor shall
conduct the STARRT
Hand injuries meeting before start to work
Working with hand tools
( Shear machine, sheet Hand Cuts which includes hazards, risks
folder mac) and mitigation measures.
After meeting workers shall
put their signatures.
To give time to rest for
workers prevention muscular
5.1) Galvanized coated sheet pain. Safety gloves (anti-cut
metal cutting ) required. All those
equipment includes passport
and Poisoned schemes
attached.
Prevention,
Steps of Task (Sequencing as Residual
Hazards: Risks Protection,
per Method Statement): Risks
Mitigation Measures
Electric Shock Do not use damaged
Working electrical tools hand tools.
Use Monthly color coding
system.Put label all
equipment showing the
inspection details
Visuial inspection needed.
SAFETY CHECKLIST
YES NO
1. PPE CONTROL X
2. EQUIPMENT CONTROL X