Documente Academic
Documente Profesional
Documente Cultură
539]
539
Delivered by ICEVirtualLibrary.com to:
IP: 147.8.84.109
On: Fri, 29 Jul 2011 09:29:35
Charles, J. A. (2008). Géotechnique 58, No. 7, 541–570 [doi: 10.1680/geot.2008.58.7.541]
The engineering behaviour of fill materials: the use, misuse and disuse
of case histories
J. A . C H A R L E S *
A number of developments in our modern world, includ- Un certain nombre de développements survenant dans
ing increasing urbanisation, major land reclamation notre monde moderne, y compris l’augmentation de
schemes and the disposal of vast quantities of solid waste l’urbanisation, la présence d’importants plans d’amén-
generated by mining and industrial activities, should agement du territoire ainsi que l’élimination de quantités
ensure that, for the foreseeable future, fills will be of considérables de déchets solides, produits par les exploi-
increasing significance in geotechnical engineering. An tations minières et les activités industrielles, devraient
engineered fill, which has been heavily compacted in thin assurer que, dans un avenir prévisible, les terrains rap-
layers under closely controlled conditions, should be a portés auront une importance toujours majeure en géo-
relatively uniform material and have behaviour that is technique. Un terrain rapporté spécialement aménagé,
easily predicted on the basis of average properties. In fortement compacté en couches de faible épaisseur et
contrast, poorly compacted fill dumped with little control dans des conditions contrôlées de très près, devrait être
in deep lifts is likely to be in a loose state and exhibit un matériau relativement uniforme, présentant un com-
great diversity in its geotechnical properties: the behav- portement facilement prévisible sur la base de propriétés
iour of such heterogeneous fill will bear little relation to moyennes. Par contraste, un terrain rapporté mal com-
average properties, and will be controlled largely by pacté, rempli de façon peu contrôlée avec des couches
zones of fill in a metastable state with unpredictable profondes est susceptible d’être peu compacté et de pré-
behaviour. Case histories that include field measure- senter une grande diversité de propriétés géotechniques :
ments—that is, quantitative data—are of particular value le comportement de ces terrains rapportés a très peu en
in gaining an understanding of the performance of fill commun avec ces propriétés moyennes, et sera déterminé
materials. Case histories of fill behaviour are examined en grande partie par des zones de remplissage à l’état
in four areas of practical interest to the geotechnical métastable et au comportement imprévisible. On examine
engineer: (a) the geotechnical behaviour of opencast des études de cas de comportement de terrains rapportés
mining backfills; (b) the performance of rockfill dams; dans quatre d’intérêt pratique pour le géotechnicien :
(c) the effectiveness of ground treatment; and (d) the (a) le comportement géotechnique de remblais de mises à
condition assessment of embankment dams. In each of ciel ouvert ; (b) le comportement de barrages en enroche-
these areas the lecture focuses on the results of long-term ment ; (c) l’efficacité du traitement du sol ; et (d) évalua-
field monitoring at a number of sites, from which some tion de l’état de barrages en remblai. Dans chacune de
general conclusions are drawn. Discernment is required ces catégories, la communication se penche sur les résul-
in the study of case histories, but despite shortcomings, tats de contrôles à long terme sur le terrain dans un
they provide a much needed counterweight to excessive certain nombre de sites, et à partir desquels elle tire des
theorisation. conclusions générales. L’examen d’études de cas nécessite
un certain discernement, mais en dépit de ses insuffi-
KEYWORDS: case history; compressibility; dams; deformation; sances, il fournit une compensation bien nécessaire à une
embankments; field instrumentation; ground improvement; tendance excessive aux grandes théories.
monitoring; rockfill; settlement; time dependence
541
Delivered by ICEVirtualLibrary.com to:
IP: 147.8.88.187
On: Mon, 30 May 2011 13:59:48
542 CHARLES
impartial records of events, but inevitably will be uous history of geotechnical research at BRE has made it
influenced by the perspective of the writer in the possible to undertake long-term measurements of ground
selection and presentation of material. movements associated with many types of buildings and
(c) The subjects of case histories will tend to be the civil engineering works (Charles et al., 1996).
unusual, and the neglect of the ordinary case will mean
that they are unlikely to be representative.
tieth century fills were placed on an unprecedented scale to installed during construction in embankment dams
construct embankment dams and road embankments, to form (Penman & Charles, 1973a, 1982). Descriptions of the
sites for buildings by infilling excavations, and in other instrumentation can be found in references cited in the
forms of land reclamation. In the late twentieth century the text.
90 m high Brianne Dam, which is the highest dam in Great
Britain, was built in Wales. Elsewhere in the world much
higher embankment dams have been constructed: the 300 m Scope of the lecture
high Nurek Dam, which was built in the old Soviet Union, Having emphasised the growing significance of fill and
is the highest dam in the world. the importance of case histories, it is appropriate to move
These engineered fill structures are quite small compared from general comments to particular case histories of fill
with the vast quantities of non-engineered fills being dumped behaviour in four areas of practical interest to the geo-
as mining, industrial, chemical, building, dredging, commer- technical engineer:
cial and domestic wastes. The total volume of mining waste
(a) the geotechnical behaviour of opencast mining backfills
currently produced annually in the world is probably of the
(b) the performance of rockfill dams
order of 10 billion cubic metres (10 3 109 m3 ). This not
(c) the effectiveness of ground treatment
only dwarfs the volumes of engineered fill used on the
(d ) the condition assessment of embankment dams.
largest dam projects, but is also greatly in excess of the 194
3 106 m3 placed in the massive land reclamation works for Since these are all large subjects that cannot be dealt with in
Chek Lap Kok Airport in Hong Kong. a comprehensive manner, each section focuses on the results
of BRE field monitoring at a number of sites, from which
some general conclusions are drawn.
Use and nature of field measurements
In studying case histories of fill behaviour that include
field measurements, three basic questions need to be ad- GEOTECHNICAL BEHAVIOUR OF OPENCAST MINING
dressed: What can be obtained from field measurements? BACKFILLS
What types of properties or behaviour should be measured? In 1949 the Building Research Station (now BRE) pub-
How can field measurements be made? lished Digest No. 9, Building on made-up ground or filling,
which stated that
(a) Benefits of field measurements. The most important
Suitable sites for new buildings and estates in industrial
benefit for those responsible for the design, construction
areas are becoming more difficult to find and it is more
and subsequent performance of an instrumented struc-
frequently necessary to build on made-up ground or filling.
ture is that its behaviour can be better assessed.
Assuming that the case history is made publicly The passing of nearly 60 years has not invalidated this
available, the measured behaviour can also provide a statement, but the qualifying phrase ‘in industrial areas’ is
benchmark for use in calibrating the behaviour of now no longer needed. Opencast mining has been a major
similar structures. The monitoring results also should producer of deep fills whose geotechnical behaviour is of
enhance the general understanding of geotechnical critical importance when restored opencast sites are consid-
behaviour. ered for building development. The principal practical inter-
(b) Geotechnical properties and behaviour to be monitored. est concerns the potential for long-term settlement of the
In different situations, pore water pressure, total stress, backfill. Where use of a restored site for building purposes
vertical and horizontal displacement and strain may be is foreseen prior to backfilling, the fill should be placed in
measured. Settlement is often the simplest parameter to layers and heavily compacted to an appropriate specification
measure, and in many cases it is the most critical under controlled conditions: such an engineered fill should
performance criterion. be reasonably uniform, with a potential for settlement that is
(c) Instrumentation and equipment. Reliable and accurate both limited and predictable. Where such a future use is not
field measurements on large civil engineering sites are foreseen, or was ignored and backfilling was carried out
difficult to achieve, requiring not only considerable with little control and without systematic compaction, the
skill, experience and perseverance in difficult condi- situation is very different.
tions, but also significant expenditure. In the case
histories that are presented here, surface settlement has
generally been measured using precise levelling techni- Creep settlement soil model
ques, but in some situations a theodolite has also been Early work on the settlement of fill was carried out at
used. Subsurface movements have been monitored using BRE by Meyerhof (1951), who, from a literature review,
magnet extensometers installed in boreholes in opencast presented the long-term creep settlement data shown in Fig.
mining backfills (Marsland & Quarterman, 1974; 2. Although the settlement of the fill materials varied from
Charles et al., 1977) and horizontal plate gauges 30% for domestic refuse to less than 1% for compacted
3. Lightly compacted
15 clay and chalk
20 4. Uncompacted sand
5. Uncompacted clay
25
6. Well-compacted
6
30 mixed refuse
rockfill, the creep rate of all the fills diminished with time, ranged from 0.2% to 1.1%, where Æ is the compression
leading to the conclusion that, if fill is left long enough, the occurring during one logarithmic cycle of time. This behav-
rate of settlement of the ground surface will become negli- iour is similar to the secondary compression of clay soils.
gible. This comforting conclusion suggests a simple solution The value of Æ was not related to the type or strength of the
to developing a filled site: leave the site for long enough parent rock, the form of dam construction (e.g. the position
and significant settlement will cease. But is this so, and if it of the watertight element), or the embankment height. The
is so, for how long must the site be left? significant factor was the method of placement of the rock-
For many rockfill dams in the United States, Sowers et al. fill. The greatest Æ values were obtained where rockfill had
(1965) found an approximately linear relationship between been dumped, whereas in the dam with the smallest Æ value
crest settlement and the logarithm of time that had elapsed the rockfill had been compacted by rolling while being
since the middle of the construction period, as shown in Fig. sluiced. In all these dams the upstream location of the
3. The values of the creep compression rate parameter Æ watertight element meant that crest settlement would be little
affected by changes in stress in the rockfill embankment due
Time from middle of construction period: years to fluctuations in reservoir level or the consolidation of a
0·5 1 2 5 10 20 35 low-permeability core.
0
For most types of fill there is a linear relation between
Lewis Smith creep compression and the logarithm of time that has
elapsed since the load was applied, and a simple settlement
Crest settlement as percentage of height of embankment
Location w: % wP : % wL : % cu : kPa
Mean Range
The table presents typical values of geotechnical properties to give an indication of fill type, but it
should be noted that the most significant property of these non-engineered fills is their heterogeneity.
rd , dry density; rs , particle density; n, porosity; Va , percentage air voids; w, water content; wP, plastic
limit; wL, liquid limit; cu , undrained shear strength.
Gauge Ground level: Rockhead: Fill depth: Fill date Inundated Settlement: m Fill condition
mAOD mAOD m depth: m
1974–1977 1973–1992†
1974 1976 1978 1980 1982 1984 1986 1988 1990 1992 Time since fill placement: years
0 5 10 20 30
0
100
C11
C11
200
A9 0·5
400
Settlement: mm
(a)
B2
0
100
D1
1·0
200
300
400
1·5
500 E12
B2
600
200 was completed at C11, and it is likely that there was large
settlement in the early years when excess pore pressures
9 (19·7 m) were dissipating.
300 Although the rise in groundwater level had a major influ-
ence on settlement behaviour, there were large variations in
collapse compression as fill was submerged at gauges A9,
400 10 (13·8 m) B2 and D15, as seen in Fig. 11, where it could have been
expected that similar behaviour would be observed. The
heterogeneity of the fill has effectively masked any correla-
13 (0 m)
500 tion between collapse compression and vertical stress in the
stress range 250 to 800 kPa.
(a)
8
30
the top 16 m of the backfill was systematically compacted
on the line of the road. Fill on either side of the road
6 corridor did not receive any systematic compaction. The
40 typical density of the uncompacted fill is given in Table
2(a). The whole of the Blindwells opencast site was dewa-
4 tered prior to the start of excavation, and the water table
50
was held down below the maximum excavation depth.
Magnet extensometers were installed in August 1984.
60 Fill During the first 13 years of monitoring 0.5 m settlement
was measured in fill that had not been systematically
1 Bedrock
(b)
compacted and 0.2 m where the upper zone had been
compacted (Watts & Charles, 2003). Typical Æ values in the
Fig. 7. Relationship between settlement at different depths in uncompacted fill were about 1%. In 1997 the groundwater
the fill and rise in groundwater level at gauge B2, Horsley, level began to rise, and there was an increase in surface
1973–1992 (after Charles et al., 1993) settlement of 0.3 m during the period in which the ground-
water level rose by 15 m. Most of this settlement can be
1973 1974 1975 1976 1977 1978 1979 related to a vertical compression of 1.4% in the submerged
⫺0·5
(a) fill, as seen in Fig. 12. Clearly, the long delay between fill
placement and the rise in groundwater level did not signifi-
0
cantly reduce collapse potential.
Vertical compression: %
6–7
⫹0·5 13 GL
7–8
12 5–6
11 Settlement of opencast mining backfill at Tamworth
⫹1·0
10
9
Backfilling at an opencast coal mining site at Tamworth
8
9–10
in the English Midlands was completed in 1972. The
63 m
7
6
Fill
8–9 excavation was backfilled mainly by scrapers, with some end
⫹1·5 5
4 tipping, and the maximum depth of fill was 32 m. The fill
3 (c)
2 was composed of clay and shale fragments, and the site was
⫹2·0
1 Bedrock
restored with a sloping ground surface. Monitoring of
ground movements and water levels within the fill com-
3 4 5 6 7 8 9 (b)
menced in 1977 and continued until surcharge operations
Fig. 8. Vertical strain and groundwater level at gauge B2, began in 1995, prior to development of the site for housing
Horsley, 1973–1979 (after Charles et al., 1993) (Charles & Burford, 1987; Watts & Charles, 2003).
In Fig. 13 the settlement measured within the deepest part
of the backfill is shown in relation to the change in ground-
that settlement has been particularly small over the 19-year water level within the fill. Surface settlement between June
monitoring period at both these gauges compared with the and December 1977 was small, equivalent to a creep rate of
settlement monitored at B2 (Fig. 9). Settlement attributable about 10 mm per year. In early 1978 the rate of creep
to the rise in groundwater level was very small in the wet increased significantly, and a further 40 mm of settlement
fill at C11 and in the preloaded fill at D1 (Table 3). The fill occurred during the following two years. During 1980 a
that had been preloaded with a 30 m high surcharge of fill at substantial rise in the rate of settlement was recorded, and
gauge D1 could be expected to settle least, as the fill is by the beginning of 1983 about 250 mm of settlement had
Rise in
groundwater
level
40
60
Fig. 9. Settlement and vertical compression against depth at gauge B2, Horsley
Settlement: mm 1000
100 200 0 100 200
0 10 11
10
9
D1
9
10 8 800
Depth below ground level: m
7
20
7
6
C11
Vertical stress: kPa
600
5 6
30
4 5
40 3 400
4
2 3
50 1
2
1 200
0
0 1·0 2·0
occurred. Surface settlement then continued at a rate of Collapse compression: %
almost 40 mm per year for the next 10 years.
Such movements are greatly in excess of any anticipated Fig. 11. Effect of submergence on Horsley backfill at settlement
creep settlement. It seems likely that groundwater was gauges A2, B9 and D15
penetrating into the opencast backfill from old unsealed
workings and then seeping through the fill. A rise in ground-
water level in 1994–1995 between magnet markers D and E collapse compression of opencast backfills that are predomi-
caused a significant increase in settlement at that depth, nantly clay has been investigated at sites at Ilkeston and
confirming that the backfill had some collapse potential. Corby, and some typical properties are given in Table 2(b).
Ground treatment by preloading with a 7 m high surcharge The stiff clay backfill at Ilkeston was placed by scrapers
of fill was carried out in 1995 and induced some 0.2 m of without any additional systematic compaction in 1959. There
surface settlement. was no water table within the backfill.
In 1973 a newly constructed block of eight two-storey
houses suffered some settlement when excavation for drains
Settlement of opencast mining backfill at Ilkeston began close to the north gable end and, following heavy
The opencast coal mining backfills at Horsley, Blindwells rain, further movement took place in the centre of the row
and Tamworth were essentially granular, as illustrated by the of houses. Soon all the houses in the block were affected,
typical properties given in Table 2(a). The susceptibility to and movements continued, although underpinning and pres-
1985
1986
1987
1988
1989
1990
1991
1992
1993
1994
1995
1996
1997
1998
1999
2000
2001
2002
2003
in 24 h of filling the trenches with water, additional settle-
0 ments of up to 50 mm had been recorded, confirming that
water penetrating into the opencast backfill via surface
200
trenches could cause significant collapse compression. Fig.
Settlement: mm
1991
1982
1992
1977
1980
1984
1987
1990
1994
1978
1979
1983
1986
1988
1989
1993
1985
1995
D
first 10 days of the experiment about 90 m3 of water was
400 absorbed by the backfill, but comparatively little was ab-
sorbed subsequently. About half this volume was lost from
E
600 one trench. The largest settlement was measured at a magnet
extensometer that was only 2 m from this trench, and, as
F shown in Fig. 15, settlement continued after the trenches
800 H
had been backfilled. Prior to the inundation test the ground
0 H surface settled at about 1 mm per month, whereas during the
Water level: m below ground level
f
wall was 0.065 m out of plumb. The houses were never 100
f 12 m
e
Backfill
occupied, and the block was demolished in 1982, by which d
time there was an estimated total settlement of 0.3 m.
c
It was suspected that water penetrating into the fill Natural
gh b ground
through drain trenches had initiated collapse compression a
within the backfill, and a field inundation test was carried 200 Inundation
test
out (Charles & Burford, 1987). When 3 m deep trenches
were filled with water to a depth of 1.8 m, the rates at which
water levels fell in the different trenches varied from as little Fig. 14. Inundation test on opencast mining backfill at Ilkeston,
as 0.04 m/h (0.08 m3 /h) to as much as 1 m/h (2 m3 /h). With- 1974–1981 (after Charles & Burford, 1987)
c
b Natural
f a ground
40 Settlement
Settlement: mm
due to
200 deep
House mining
construction 60
Trenches
backfilled
Inundation test
gh
300 commenced 80
100
Fig. 15. Inundation test on opencast mining backfill at Corby,
1974–1986 (after Charles & Burford, 1987)
120
rd , dry density of fill; rs , particle density; n, porosity; Va , percentage air voids; w, water
content.
2 1
3
4
h/H
0·5 (a)
S
Me W
2 1
3
3
0 (b)
0 0·5 1·0
Settlement: m
(c)
Top of
embankment
Fig. 21. Contours of constructional vertical strain (%):
(a) Brianne; (b) Scammonden; (c) Winscar
80
70
60
0·3
50
Downstream movement 0·4
Settlement 0·5
40
0·6
0·3 0·2 0·1
30
20 (a)
10
Base of 0
embankment 0 0·5 1·0 1·5 0 0·5 1·0
Movement: m Movement: m 0·1 0 ⫺0·1
(a) (b) ⫺0·2
⫺0·2
Fig. 20. Construction movements at (a) core/fine filter interface 0 0
and (b) downstream slope at Brianne dam (after Penman & (b)
Charles, 1973b)
construction both dams had a pore pressure ratio (ru ¼ u/ªh) ⫺0·2
⫺0·4
as high as 0.7 at some locations in their cores. The clay 0
cores were much less stiff than the rockfill shoulders, and 0
the differences in embankment behaviour can be attributed
(c)
largely to the positions of the clay cores (Penman & Charles,
1973c; Charles, 1975). The horizontal strains show the major Fig. 22. Contours of constructional horizontal strain (%):
influence of the lateral thrust of the soft central clay core on (a) Brianne; (b) Scammonden; (c) Winscar
the whole of the downstream shoulder at Brianne, with a
maximum compression of a little more than 0.6%, and the
much more limited effect of the upstream sloping core on The stress–strain properties of rockfills measured in one-
the downstream rockfill at Scammonden owing to the width dimensional compression tests are generally non-linear, but
of the crest and the upstream location of the clay core. At the internal distribution of settlement during embankment
Winscar virtually the whole embankment cross-section has construction can be predicted with little error using a
negative horizontal strain (i.e. extension), with a maximum constant equivalent compressibility, and the maximum settle-
of just over 0.4% in the centre of the embankment (Penman ment occurring during construction can be related to the
et al., 1982). constrained modulus (D). Assuming that a large-diameter
:
For D ¼ k(v )0 5 :
!
ªH2
smax ¼ 0:195 (4)
Dª H
Elevation: m AOD
C
where smax is the maximum settlement during construction 240
of an embankment of height H, ª is the bulk unit weight of
the fill, and Dª H is the secant-constrained modulus for a
vertical stress v ¼ ªH. Fig. 23 shows that the measured
values of smax have mostly closely corresponded to equation
(4), which therefore can be used to give an initial prediction B
of construction settlement. This approach works reasonably
well because stress changes during construction generally 220
correspond to an increase in mean effective stress while the
principal effective stress ratio remains roughly constant, but
during reservoir impounding stress changes are much more
complex. A
200
Post-construction deformations
Subsequent to the construction of a rockfill dam, move-
ments will occur because of
0 100 200
(a) stress changes associated with reservoir impounding
Settlement during reservoir impounding: mm
(b) consolidation of a clay core
(a)
(c) creep compression in the rockfill.
Movements monitored during reservoir impounding illus- F
U E
trate the determining influence of the position and nature of D
the watertight element within the embankment. At Brianne
the continuing settlement of the crest was largely a function C
of the behaviour of the central clay core—that is, primary
B
consolidation due to dissipation of excess pore pressures
followed by secondary compression. The upstream fill was A
submerged during impounding, thus reducing the effective
stresses within the fill. While in theory this should cause the
rockfill to undergo a slight expansion or heave, in practice (b)
any small creep movements or collapse compression will
negate such a tendency. Fig. 24(a) shows that the points Fig. 24. Settlement during first filling of reservoir at Brianne
labelled U on the upstream slope settled a very similar dam (after Charles, 1987)
amount to monuments E and F on the downstream slope
during reservoir impounding, indicating that the rockfill had
little if any collapse potential. The location of these surface
1·0
settlement stations is shown in Fig. 24(b).
S
Because of its wide crest and upstream-sloping clay core,
W
much of the rockfill at Scammonden was not significantly
affected by either reservoir impounding or consolidation of
the clay core. The approximately linear relationship between
smax: m
B5 0
18
100
16
0 120
140 80
60
40
Movement 20
scale
(a)
0 50 mm
A6
0·2
0·4
0·6
0·8
1·0 0·2
(b)
80 3 July 1994 32
settlement rate eventually reduced with time (Hopkins et al.,
D
would not have been any collapse potential. The two dashed
lines for sample ‘b’ on the figure give estimates of the
0·1 behaviour of sample ‘b’ if it was not inundated at all and if
it was inundated before any load was applied. The initial
density and water content of sample ‘b’ were close to the
average field values (Table 6).
In Fig. 32 the crest settlement data for the five dams are
plotted using a logarithmic timescale. There is generally a
uam
cf
Ma Time since end of construction: years
0 5 10 15 20
0
0 0·5 1 M
smax: m
0·4 W
tion went only part way up the upstream slope: the hollow
circle in Fig. 29 represents the maximum measured deflec-
tion, and the solid circle is the estimated maximum deflec- 0·6 B
tion on the assumption that the deflected shape of the
membrane at Roadford was similar to that measured at R
Winscar. The dashed line on the graph corresponds to a ratio
of nmax /smax ¼ 0.25, which would be expected if the con- 0·8
strained modulus controlling the deformation due to reser- Fig. 30. Post-construction long-term settlement of crests of
voir impounding was about twice as large as the modulus dams: B, Brianne; M, Megget; R, Roadford; S, Scammonden;
controlling construction settlement. W, Winscar; s, crest settlement; H, height of embankment
a
horizontal plate gauge system. At Scammonden much less
5 than one third of the long-term compression of the embank-
ment is located in the top third of the embankment (Fig.
25). Stress dependence of creep settlement is explored in
Fig. 33, where the measured distribution of long-term settle-
b ment with height within the embankments at Scammonden
Inundation and Winscar is compared with what would be expected if
10
(a) Æ was a constant and not dependent on vertical stress, or
(b) Æ was proportional to vertical stress. The results are
Fig. 31. Compressibility of Roadford rockfill measured in 1 m generally closer to the latter assumption than to the former.
diameter oedometer
Conclusions
Table 6. Properties of Roadford rockfill in 1 m diameter Field measurements have confirmed that carefully con-
oedometer tests and in the field trolled placement and compaction can produce rockfills with
relatively uniform geotechnical properties and predictable
rd : Mg/m3 w: % n: % Va: % behaviour. The case histories go some way towards establish-
ing benchmarks for normal behaviour of different types of
Test a 2.16 7.9 21 4 rockfill dam. The monitored movements give a good indica-
Test b 2.05 4.7 25 15 tion of the deformations likely to occur during successive
Field 2.07 4.4 24 15 stages in the life of a rockfill dam, and substantial depar-
tures from such behaviour in a dam could indicate the onset
rd , dry density of fill; w, water content; n, porosity; Va , percentage
of unsatisfactory behaviour.
air voids.
Although rockfill behaviour is not elastic and not linear,
movements during embankment construction can be pre-
dicted using simple linear elastic models. The limiting factor
Time since end of construction: years in making such predictions is not the sophistication of the
0·5 1 2 5 10 20 soil model used in the calculations, but rather the difficulty
0 of establishing representative soil parameters for a fill mate-
M
rial containing large rock fragments. Movements during
1·0
0·2
S
Scammonden
Winscar
0·4
W
R B
Height above foundation
0·6
s/H: %
0·5
0·8
1·0
Creep rate
proportional to
vertical stress
1·2
0
1·4 0 0·5 1·0
Long-term settlement
Fig. 32. Post-construction long-term settlement of crests of dams Long-term crest settlement
with time plotted on a logarithmic scale; B, Brianne; M,
Megget; R, Roadford; S, Scammonden; W, Winscar; s, crest Fig. 33. Creep rate of sandstone rockfill at Scammonden and
settlement; H, height of embankment Winscar dams as a function of vertical stress
Height of fill: m
Time since dynamic compaction: months 10
1 3 10 30 100 300
0
5
Settlement subsequent to dynamic
10 0
May June July August
0 10 m depth
compaction: mm
20
30
Settlement: mm
200
Mean settlement of experimental 4·3 m depth
40 houses (measured at dpc level)
Mean settlement of adjacent ground
50 (measured 1 m below ground level) 400 2·2 m depth
Surface
2 construction of 3 m high
embankment
20
0·5
Settlement: mm
the density of the surcharge is similar to the density of the 0 100 200 300
0
in situ fill.
The data presented in Table 7 illustrate the effectiveness
of surcharging the clay fill at Snatchill: the settlement of
houses built on untreated fill was about three times as great Dynamic
as the settlement of houses built on clay fill that had been compaction
subjected to a 9 m high temporary surcharge. However,
Depth below ground level: m
Dynamic compaction
The repeated dropping of a heavy weight onto the ground
surface is one of the most basic methods of compacting 10
loose, partially saturated fill. The development of heavy civil
engineering plant has made dynamic compaction practical
on a large scale. The effectiveness of this treatment method
has been monitored by BRE at several filled sites (Charles
et al., 1981). Although dynamic compaction will reduce the Fig. 40. Comparison of settlement induced in clay fill by
creep compression rate parameter Æ, it effectively creates a dynamic compaction and 5.7 m high surcharge
H, height of embankment; ucb, upstream clay blanket; cpcc, central puddle clay core.
cac, central asphaltic core; cpcc, central puddle clay core; crcc, central rolled clay core;
ucb, upstream clay blanket; urcc, upstream rolled clay core; H, height of embankment; SI ,
settlement index.
1988 1989 1990 pressure with consequent heave of the upstream slope, with
0 a maximum value halfway down the slope and virtually no
movement at the crest. This pattern of behaviour assumes
Reservoir level:
m below crest
5
that the upstream watertight element is fully effective, and
10
that reservoir level changes have no effect on pore water
pressures in the upstream fill. Fig. 44 presents the same
15 information in terms of the vertical movements induced on
Empty
the upstream slope for partial as well as full reservoir
20 drawdown, assuming a constrained modulus of 100 MPa for
the upstream fill. It should not be forgotten that in certain
circumstances rapid drawdown could cause upstream slope
0 instability.
Monitoring of crest settlement has an important role in
assessing the long-term performance and safety of embank-
20 18·5 m ment dams, and in collaboration with Yorkshire Water BRE
Settlement: mm
(50%) 25 m
δ50%
δ100%
(100%)
(a)
(a)
0·25 0
(50%)
25 m
0·19 0 δ100%
δ50%
(100%)
(b) (b)
Fig. 43. Vertical movements in upstream shoulder during Fig. 44. Vertical movements of upstream slope during reservoir
reservoir drawdown for dams with watertight element (after drawdown for dams with watertight element (after Tedd et al.,
Charles, 1993): (a) in centre of embankment; (b) on upstream 1997b): (a) in centre of embankment; (b) on upstream slope (:
slope calculated displacement of upstream slope)
10
20
0
Crest settlement: mm
25
50
75
(a) (b)
Fig. 45. Monitored crest settlement during reservoir drawdown of dams with watertight element (after Tedd et al.,
2002): (a) Walshaw Dean Lower, central puddle clay core; (b) Holmestyles, upstream clay blanket
0·3
Initial
0·2 loading
3·4
sp /H
0·1
sr /H
0·0 3·6 B
Vertical strain: %
0 5 10 15 20 25
Initial
Drawdown depth: m
unloading
Permanent
BRE–Yorkshire Water monitoring programme (Tedd et al., 4·0 strain due to
1997b). Further data published by Tedd et al. (2002) con- 4 minor
reloading–
firmed the general pattern of drawdown behaviour. Settle- unloading
ments are large compared with those associated with creep, cycles
and an analysis of the settlement of puddle core dams that
ignores the effect of reservoir drawdown could lead to the
4·2
diagnosis of a problem where none exists. However, it could
be questioned whether the disproportionately large increase Fig. 47. Effect of minor and major unloading–reloading cycles
in settlement with a major drawdown should be of concern. in oedometer test on mudstone fill from Ogden dam (after Tedd
The magnitude of the deformations produced by reservoir et al., 1997b)
failure, will be only too ready to point out the failure of the knowledged. A substantial part of the research work on
designer to heed lessons from the past. opencast coal mining backfills was carried out in collabora-
The misuse of case histories—that is, the failure to draw tion with the NCB Opencast Executive, and the experimental
correct conclusions from case histories—is a more difficult work at Corby with the Corby Development Corporation.
matter to rectify. The available case histories of a particular
type of geotechnical structure may not be representative. No
case history will be fully comprehensive: it will not provide
NOTATION
us with all the facts, and each case history will be influ- B width of surcharge
enced by the writer’s technical understanding, or lack of it. cu undrained shear strength
In some cases evidence may have been carefully selected to D constrained modulus
make a point that would not be supported by a more Dª H secant-constrained modulus for v ¼ ªH
balanced presentation of the evidence. H height of embankment or surcharge
Discernment is required in the study of case histories, but h height of fill
despite their shortcomings they provide a much needed hw reservoir head
counterweight to excessive theorisation. This study of the n porosity
engineering behaviour of fill materials has attempted to nmax maximum deflection of upstream membrane during reservoir
filling
demonstrate the value of case histories, particularly those
ru pore pressure ratio
that include long-term field measurements. SI settlement index
s settlement
smax maximum settlement during embankment construction
ACKNOWLEDGEMENTS sm maximum settlement on reservoir drawdown
In theoretical studies it is quite possible for an individual sp permanent settlement on reservoir drawdown
to make a major contribution with relatively little help from sr recovered settlement on reservoir drawdown
others, whereas fieldwork of necessity is a team effort, and t time since fill placement or loading
in the work on the engineering behaviour of fill materials at u pore pressure ratio
Va percentage air voids
BRE many people have been involved. Initially I had the
w water content
privilege of working for Dr Arthur Penman; at a later stage I wL liquid limit
collaborated with Dr Paul Tedd and latterly with Hilary wP plastic limit
Skinner. Many of the early field surveying measurements ze depth of effectiveness of ground treatment
were made by Don Burford. Not only did Ken Watts carry Æ creep compression rate parameter
out much of the later fieldwork, but he also provided help in ª bulk unit weight
the preparation of this lecture. Much of the work had its ª9 effective unit weight of submerged fill
origin in the time when Professor John Burland was Head of ªd dry unit weight
the Geotechnics Division. To all these colleagues, and to ªs unit weight of surcharge fill
others who have rendered assistance, I acknowledge my debt ªw unit weight of water
v vertical strain
and express my gratitude. Thanks are also due to Dr Peter r bulk density
Bonfield, the Chief Executive of BRE, and to other members rd dry density
of the senior management for the use of BRE facilities in rs particle density
preparing this lecture. v vertical stress
Field measurements require the collaboration of the own-
ers of the structures and their consulting engineers, and
these are listed in Table 10 for the research work on the
various dams. Most of these owners and consulting engi- REFERENCES
Atkinson, J. H., Charles, J. A. & Mhach, H. K. (1990). Examination
neers have changed their names during the long periods that
of erosion resistance of clays in embankment dams. Q. J. Engng
BRE has taken measurements, and it seemed appropriate to Geol. 23, No. 2, 103–108.
acknowledge their assistance using their earlier rather than Baines, J. A., Newman, V. G., Hannah, I. W., Douglas, T. H.,
their later names. Much of the work on dams was carried Carlyle, W. J., Jones, I. L., Eaton, D. M. & Zeronian, G. (1983).
out in Yorkshire, and the help given by Jim Claydon and Dinorwig pumped storage scheme. Proc. Instn Civil Engrs, Part
Andrew Robertshaw of Yorkshire Water is gratefully ac- 1 74, No. 4, 635–718 (Discussion, 1985, 78, August, 919–957).