Documente Academic
Documente Profesional
Documente Cultură
Rev.
VOITH Document No.
Commissioning Instruction 版本
2AEP02-0000-02296008
Generator [U16] 1
Project Document No.
Electrical Protection
TAR4-600F-9493-00
Commissioning Instruction
Generator
Electrical Protection
[U16]
(WET COMMISSIONING)
Employer’s
Representative:
__________________________ _____________________
Muhammad Idrees, Dy. Director (Electrical) Sikander Shah, Director (Electrical)
Engineer’s
Representative:
_______________________ _______________________
Muhammad Iqbal, Pr. Engineer (C&I) Todor Dimitrov, RE Commissioning
Voith
Representative:
_____________________ _____________________
Kennedy Herrera Varujan COCYAN
Commissioning Engineer Lead Commissioning Engineer
1/43
Tarbela 4th Extension HP
Rev.
VOITH Document No.
Commissioning Instruction 版本
2AEP02-0000-02296008
Generator [U16] 1
Project Document No.
Electrical Protection
TAR4-600F-9493-00
TABLE OF CONTENTS
1. PURPOSE OF TESTS..................................................................................................................................4
2/43
Tarbela 4th Extension HP
Rev.
VOITH Document No.
Commissioning Instruction 版本
2AEP02-0000-02296008
Generator [U16] 1
Project Document No.
Electrical Protection
TAR4-600F-9493-00
3/43
Tarbela 4th Extension HP
Rev.
VOITH Document No.
Commissioning Instruction 版本
2AEP02-0000-02296008
Generator [U16] 1
Project Document No.
Electrical Protection
TAR4-600F-9493-00
1. PURPOSE OF TESTS
The purpose of these test, is to verify the correct operation of protective and control system together, also
verify current and voltage circuits, having in consideration secondary circuits and the polarity of current and
voltage transformers.
Also, with this test will verify the stability of the protection differential of generator, the protection differential
of transformer.
Current document summarize basic considerations for protection primary tests of generator with running
machine.
2. REFERENCE DOCUMENT
The used documents for elaborate this procedure are integrate of the followed:
[1] No. 2PPE05-0101- Rev. D Overall Single Line Diagram Power House and 220/500kV
01303012 Switchyard
[2] No. 2PPE05-0101- Rev. C Main Single Line Diagram Unit 15 to 17 and 500kV Switchyard
01303013 Bay 19 to 21
[3] No. 2PPE05-0101- Rev. L Single Line Relay & Metering Diagram Unit 15-16 and 500kV
01303014 Switchyard Bay 19-20; Unit 17 and 500kV Switchyard Bay
[4] No. 2AEP02-0000- Rev. G Setting Calculation and Parameterization Unit 15/16/17 and
01740949 Overhead Line and 500kV Switchyard Protection
[5] No. 2AEP02-0100- Rev. - Unit Protection System Main Protection System
01819165
[6] No. 2AEP02-0100- Rev. - Unit Protection System Back-Up Protection System
01819168
[7] No. 2AEP02-0100- Rev. - Unit 17 Protection System Protection System Accessory
01819170
3. SCOPE OF TEST
Scope includes the following tests to be done:
Short Circuit Generator Protection Test.
4/43
Tarbela 4th Extension HP
Rev.
VOITH Document No.
Commissioning Instruction 版本
2AEP02-0000-02296008
Generator [U16] 1
Project Document No.
Electrical Protection
TAR4-600F-9493-00
5. GENERAL RECOMENDATIONS
Before attempting any maneuver related to energizing, switchyard area must be checked for the
presence of any provisional ground, equipment or material used during erection works, such like
ladders, ropes tools, etc.
All responsible person and coordinators, must informed of the exact time when energizing
manoeuvres will be initiated.
When measuring voltage at terminals connections, special care with the handling of bridges &
groundings has to be taken. Do not leave loose connections or open terminals.
Special care has to be taken when working at terminals with current, with the use of links or short
circuit bridges. For no reason should leave CT’s in open circuit; then, should verify continuosly to avoid
loose connections or open terminals.
5/43
Tarbela 4th Extension HP
Rev.
VOITH Document No.
Commissioning Instruction 版本
2AEP02-0000-02296008
Generator [U16] 1
Project Document No.
Electrical Protection
TAR4-600F-9493-00
6/43
Tarbela 4th Extension HP
Rev.
VOITH Document No.
Commissioning Instruction 版本
2AEP02-0000-02296008
Generator [U16] 1
Project Document No.
Electrical Protection
TAR4-600F-9493-00
7/43
Tarbela 4th Extension HP
Rev.
VOITH Document No.
Commissioning Instruction 版本
2AEP02-0000-02296008
Generator [U16] 1
Project Document No.
Electrical Protection
TAR4-600F-9493-00
To UNIT 15
UNIT 16
8/43
Tarbela 4th Extension HP
Rev.
VOITH Document No.
Commissioning Instruction 版本
2AEP02-0000-02296008
Generator [U16] 1
Project Document No.
Electrical Protection
TAR4-600F-9493-00
9/43
Tarbela 4th Extension HP
Rev.
VOITH Document No.
Commissioning Instruction 版本
2AEP02-0000-02296008
Generator [U16] 1
Project Document No.
Electrical Protection
TAR4-600F-9493-00
Three phases short circuit is installed at the 18kV IPB duct, see drawing above.
Check that the short circuit can withstand the unit nominal current 16743 A.
10/43
Tarbela 4th Extension HP
Rev.
VOITH Document No.
Commissioning Instruction 版本
2AEP02-0000-02296008
Generator [U16] 1
Project Document No.
Electrical Protection
TAR4-600F-9493-00
11/43
Tarbela 4th Extension HP
Rev.
VOITH Document No.
Commissioning Instruction 版本
2AEP02-0000-02296008
Generator [U16] 1
Project Document No.
Electrical Protection
TAR4-600F-9493-00
A A/ kA A/ kA A/ kA A/ kA PASS
B A/ kA A/ kA A/ kA A/ kA PASS
C A/ kA A/ kA A/ kA A/ kA PASS
A A/ kA A/ kA A/ kA PASS
B A/ kA A/ kA A/ kA PASS
C A/ kA A/ kA A/ kA PASS
A A/ kA A/ kA PASS
B A/ kA A/ kA PASS
C A/ kA A/ kA PASS
12/43
Tarbela 4th Extension HP
Rev.
VOITH Document No.
Commissioning Instruction 版本
2AEP02-0000-02296008
Generator [U16] 1
Project Document No.
Electrical Protection
TAR4-600F-9493-00
13/43
Tarbela 4th Extension HP
Rev.
VOITH Document No.
Commissioning Instruction 版本
2AEP02-0000-02296008
Generator [U16] 1
Project Document No.
Electrical Protection
TAR4-600F-9493-00
7.6. CURRENT UNBALANCE (46) MAIN PROTECTION TEST -F311 / MICOM P345
Increase slowly the generator current until the 46 – alarm stage I2 @ 1200 A, t=20s.
Check the alarm Negative Phase Sequence O/C Alarm on Automation Panel.
Increase slowly the generator current until the 46 – trip stage I2 @ 6000 A, t=100s.
14/43
Tarbela 4th Extension HP
Rev.
VOITH Document No.
Commissioning Instruction 版本
2AEP02-0000-02296008
Generator [U16] 1
Project Document No.
Electrical Protection
TAR4-600F-9493-00
7.7. CURRENT UNBALANCE (46) BACKUP PROTECTION TEST -F312/ MICOM P342
Increase slowly the generator current until the 46 – alarm stage I2 @ 1200 A, t=20s.
Check the alarm Negative Phase Sequence O/C Alarm on Automation Panel.
Increase slowly the generator current until the 46 – trip stage I2 @ 6000 A, t=100s.
15/43
Tarbela 4th Extension HP
Rev.
VOITH Document No.
Commissioning Instruction 版本
2AEP02-0000-02296008
Generator [U16] 1
Project Document No.
Electrical Protection
TAR4-600F-9493-00
After the Short circuit generator characteristic test, put back the protection settings
Unit Protection Backup, MICOM P643, -F321:
Remove three phases short circuit is installed at the 18kV IPB duct.
16/43
Tarbela 4th Extension HP
Rev.
VOITH Document No.
Commissioning Instruction 版本
2AEP02-0000-02296008
Generator [U16] 1
Project Document No.
Electrical Protection
TAR4-600F-9493-00
To UNIT 15
UNIT 16
17/43
Tarbela 4th Extension HP
Rev.
VOITH Document No.
Commissioning Instruction 版本
2AEP02-0000-02296008
Generator [U16] 1
Project Document No.
Electrical Protection
TAR4-600F-9493-00
Install the three phases short circuit with the temporary earthing kits at the 500kV Switchyard.
See drawing above.
Check that the short circuit can withstand the generator nominal current 603A, 500 kV side.
GSU Transformer disconnected from the 500kV Switchyard. (=B19+Q10 are open position).
Increase slowly the current up to 10 % of the nominal (LV: 1674A, HV: 60.3A).
Increase slowly the current up to 20 % of the nominal current (LV: 8372A, HV: 302A).
18/43
Tarbela 4th Extension HP
Rev.
VOITH Document No.
Commissioning Instruction 版本
2AEP02-0000-02296008
Generator [U16] 1
Project Document No.
Electrical Protection
TAR4-600F-9493-00
A A/ A A/ A A/ A PASS
B A/ A A/ A A/ A PASS
C A/ A A/ A A/ A PASS
A A/ A A/ A A/ A PASS
B A/ A A/ A A/ A PASS
C A/ A A/ A A/ A PASS
19/43
Tarbela 4th Extension HP
Rev.
VOITH Document No.
Commissioning Instruction 版本
2AEP02-0000-02296008
Generator [U16] 1
Project Document No.
Electrical Protection
TAR4-600F-9493-00
20/43
Tarbela 4th Extension HP
Rev.
VOITH Document No.
Commissioning Instruction 版本
2AEP02-0000-02296008
Generator [U16] 1
Project Document No.
Electrical Protection
TAR4-600F-9493-00
21/43
Tarbela 4th Extension HP
Rev.
VOITH Document No.
Commissioning Instruction 版本
2AEP02-0000-02296008
Generator [U16] 1
Project Document No.
Electrical Protection
TAR4-600F-9493-00
22/43
Tarbela 4th Extension HP
Rev.
VOITH Document No.
Commissioning Instruction 版本
2AEP02-0000-02296008
Generator [U16] 1
Project Document No.
Electrical Protection
TAR4-600F-9493-00
To UNIT 15
UNIT 16
23/43
Tarbela 4th Extension HP
Rev.
VOITH Document No.
Commissioning Instruction 版本
2AEP02-0000-02296008
Generator [U16] 1
Project Document No.
Electrical Protection
TAR4-600F-9493-00
Check that the short circuit can withstand the generator nominal current 603A, 500 kV side.
GSU Transformer disconnected from the 500kV Switchyard. (=B19+Q10 are open position).
Increase slowly the current up to 10 % of the nominal (LV: 1674A, HV: 60.3A).
Increase slowly the current up to 20 % of the nominal (LV: 3348A, HV: 120.6A).
N A/ A A/ A N/A
24/43
Tarbela 4th Extension HP
Rev.
VOITH Document No.
Commissioning Instruction 版本
2AEP02-0000-02296008
Generator [U16] 1
Project Document No.
Electrical Protection
TAR4-600F-9493-00
In the -F321 Protection, put back the normal setting of the protections:
In the -F322 Protection, put back the normal setting of the protections:
25/43
Tarbela 4th Extension HP
Rev.
VOITH Document No.
Commissioning Instruction 版本
2AEP02-0000-02296008
Generator [U16] 1
Project Document No.
Electrical Protection
TAR4-600F-9493-00
To UNIT 15
M
95% Stator E/F Test
Temporary Connection
Bridge Disconneted. Phase to Ground
Exc. Trf. connected to
temporary source.
UNIT 16
26/43
Tarbela 4th Extension HP
Rev.
VOITH Document No.
Commissioning Instruction 版本
2AEP02-0000-02296008
Generator [U16] 1
Project Document No.
Electrical Protection
TAR4-600F-9493-00
GSU Transformer disconnected from the 500kV Switchyard. (=B19+Q10 are open position).
Excitation system connected to temporarily auxiliary feed.
Disconnecting E/S GS620, GS610 are in open position.
Generator Disconnecting GS210 in open position. (Dummy closed position)
GCB GS100 in remote and available for operation.
Excitation breaker in OFF position.
Generator Stopped.
Install one 10mm2 wire between phase “RED” and ground in Generator side.
Phase “RED” connected to ground was installed at the 18kV side, as drawing above.
9.3. 100% STATOR EARTH FAULT (64S) PROTECTION -F311 AT GENERATION SIDE
27/43
Tarbela 4th Extension HP
Rev.
VOITH Document No.
Commissioning Instruction 版本
2AEP02-0000-02296008
Generator [U16] 1
Project Document No.
Electrical Protection
TAR4-600F-9493-00
Increase slowly the generator voltage until 5%Vn (trip V0 ≅ 850V, t=1.0s trip).
Check the alarm 95% Stator Earth Fault Protection Trip on Automation Panel.
Remove 10mm2 wire between phase “RED” and ground in the Generator side.
28/43
Tarbela 4th Extension HP
Rev.
VOITH Document No.
Commissioning Instruction 版本
2AEP02-0000-02296008
Generator [U16] 1
Project Document No.
Electrical Protection
TAR4-600F-9493-00
9.5. 100% STATOR EARTH FAULT (64S) PROTECTION -F311 AT NEUTRAL SIDE
Generator Stopped.
Install one 10mm2 wire between generator neutral point and ground.
Check the alarm 100% Stator Earth Fault Protection Trip on Automation Panel.
Remove 10mm2 wire between neutral and ground in the generator earthing compartment.
29/43
Tarbela 4th Extension HP
Rev.
VOITH Document No.
Commissioning Instruction 版本
2AEP02-0000-02296008
Generator [U16] 1
Project Document No.
Electrical Protection
TAR4-600F-9493-00
GSU Transformer disconnected from the 500kV Switchyard. ( =B19+Q10 are open position).
Generator Stopped.
30/43
Tarbela 4th Extension HP
Rev.
VOITH Document No.
Commissioning Instruction 版本
2AEP02-0000-02296008
Generator [U16] 1
Project Document No.
Electrical Protection
TAR4-600F-9493-00
Result
+17MKC10 +17MEY11 +16BAA20
PHASE (Excitation) (Governor) -Spare
(Pass/Fail)
31/43
Tarbela 4th Extension HP
Rev.
VOITH Document No.
Commissioning Instruction 版本
2AEP02-0000-02296008
Generator [U16] 1
Project Document No.
Electrical Protection
TAR4-600F-9493-00
Increase slowly the generator voltage until alarm stage, 60%Un ≅ 10800V, t=2.9s
Increase slowly the generator voltage at until trip stage, 70%Un ≅ 12600V, t=0.1s
32/43
Tarbela 4th Extension HP
Rev.
VOITH Document No.
Commissioning Instruction 版本
2AEP02-0000-02296008
Generator [U16] 1
Project Document No.
Electrical Protection
TAR4-600F-9493-00
33/43
Tarbela 4th Extension HP
Rev.
VOITH Document No.
Commissioning Instruction 版本
2AEP02-0000-02296008
Generator [U16] 1
Project Document No.
Electrical Protection
TAR4-600F-9493-00
34/43
Tarbela 4th Extension HP
Rev.
VOITH Document No.
Commissioning Instruction 版本
2AEP02-0000-02296008
Generator [U16] 1
Project Document No.
Electrical Protection
TAR4-600F-9493-00
35/43
Tarbela 4th Extension HP
Rev.
VOITH Document No.
Commissioning Instruction 版本
2AEP02-0000-02296008
Generator [U16] 1
Project Document No.
Electrical Protection
TAR4-600F-9493-00
Decrease slowly the generator voltage at until alarm stage, 15380V, t=3s.
Decrease slowly the generator voltage at until trip stage 13580, t=0.1s
After circuit generator characteristic test, put back the normal setting of the protections:
36/43
Tarbela 4th Extension HP
Rev.
VOITH Document No.
Commissioning Instruction 版本
2AEP02-0000-02296008
Generator [U16] 1
Project Document No.
Electrical Protection
TAR4-600F-9493-00
10. ANNEX
37/43