Health Task Name Assigned To

Project 2
Phase 1
Green Gather Permits Diego Martinez
Green Submit Permits Dyna Appforth
Green Finalize Blueprints Kiran Gupta
Green Break Ground Tamika Marshall
Phase 2
Red Foundation Paul Finley
Yellow Structure Kai Senjima
Blue Inspection Diego Martinez
Blue Clearance Dyna Appforth
Phase 3
Blue Roofing Kiran Gupta
Blue Exteriors Tamika Marshall
Blue Windows & Doors Paul Finley
Blue Final Inspection Kai Senjima
Task Category State Start Date End Date % Complete Completion P
12/01/17 09/20/19 16% Empty
12/01/17 02/08/18 100% Full
Capital Construction Complete 12/01/17 12/15/17 100% Full
Capital Construction Complete 12/18/17 01/19/18 100% Full
Capital Construction Complete 01/22/18 02/07/18 100% Full
Component Complete 02/08/18 02/08/18 100% Full
02/09/18 03/27/19 9% Empty
Component In Progress 02/09/18 08/07/18 20% Empty
Component In Progress 08/08/18 11/23/18 2% Empty
Major Maintenance Not Started 11/26/18 01/29/19 0% Empty
Major Maintenance Not Started 01/30/19 03/27/19 0% Empty
03/28/19 09/20/19 0% Empty
Major Maintenance Not Started 03/28/19 05/21/19 0% Empty
Major Maintenance Not Started 05/22/19 06/28/19 0% Empty
Major Maintenance Not Started 07/01/19 08/21/19 0% Empty
Major Maintenance Not Started 08/22/19 09/20/19 0% Empty
PredecessorsDuration
471d
50d
11d
3 25d
4 13d
5 1d
294d
6 128d
8 78d
9 47d
10 41d
127d
11 39d
13 28d
14 38d
15 22d
If today is past the scheduled end date, and project is not checked complete, then status = RED
Row 1 If the "% Complete" is zero, and the start date is in the past, then status = RED
Tyler Owens 02/07/17 7:59 AM