Sunteți pe pagina 1din 3

Woqod

WOQOD Comments Approval Contractor Response Remarks (internal)


Code

Comment incorporated.
- Woqod Approved PQR No. PT/PQR/43 to be included in the Test Pack for review. Ariel – pls refer to my email dated 24-10-18
Woqod Approved PQR No. PT/PQR/43 inserted

- WPS no. PT/WPS/44911 and supporting PQR to be submitted signed by PetroServ for Woqod Comment incorporated.
Ariel – pls refer to my email dated 24-10-18
approval Signed documents inserted
Ariel – project specific welder certificate is ready
- All the welders certificates to be submitted with PetroServ and Woqod logos and clear refrence to
Comment incorporated. here in Ummsalal office. Please collect it from
the project for approval and signature
me and get woqod signature.
- UT is done in lieu of RT for this package, Woqod documented approval to be attached to the
Woqod’s email confirmation attached. Attach email.
package

- NDT (RT) personnel Certificates along with cover page of NDT (RT) procedures to be submitted Woqod approved RT procedure along with
Attach procedure and certificate
by PetroServ for Woqod approval technicians certificates inserted in test pack

NDT requirements as per approved drawings


already fulfilled.
5% RT for shop joints and welder ratio also
- RT Percentage (5%) is not covered, Total 269 But joints which require 14 RT shots, 2 more
covered.
weldments need to be done
100% MT done on field joints
UT not applicable for 2" pipe with thickness less
than 6mm.
C
- Report no. PSL-5084-QC-M-02-F-02 for electrode backing and issuance along with electrode Vacuum pack electrodes are being used at site.
batch certificates to be included Backing not applicable.

- Line List to be included in the package, last revision of line list to be Submitted by PetroServ for
Latest revision line list attached. Attach latest line list
Woqod approval. Design and test pressure has been changed to be 8.8 and 9.86 bar respectively

- All valves MTCs to be included in the package and site verification to be arranged. Valve MTCs included. Attach valve MTC

Details of received 2” pipes are as below


– JSL/Q/J17/TX2017005370/A01 to A24
(Heat No. 3703759) – 718.8 mtrs. (120
pieces)
- 2" Pipes Material Certificate Reference No. JSL/Q/J17/TX2017005370/A01 (Heat No. 3703759)
– JSL/Q/J17/TX2017005800/A01 to A10
only covers 29.95 Mtrs. (5 Pipes of 6 Mtrs each) which is very less compared with the actual
(Heat No. 3703759) – 294.20 mtrs. (49 Attach all other MIRs
amount of pipes being used to fabricate the HC. MTCs for 2" Pipes with actual Heat Nos. used for
pieces)
fabrication to be included in the package and site verification to be arranged.
– JSL/Q/J17/TX2017005370/B01 to B65
(Heat No. 3703760) – 1929.66 mtrs. (323
pieces)
Test pack updated accordingly.
Heat numbers mentioned in welding reports
remains same.
- All Welding History reports & Material Receiving Reports to be modified according to the actual
Material receiving inspection reports for the Attach all other MIRs
heat Nos. used in Fabrication and resubmitted to Woqod for review
additional quantity pipes (same heat number)
included in the test pack

Comment incorporated.
- Woqod Approved PQR No. PT/PQR/43 to be included in the Test Pack for review.
Woqod Approved PQR No. PT/PQR/43 inserted

- WPS no. PT/WPS/44911 and supporting PQR to be submitted signed by PetroServ for Woqod Comment incorporated.
approval Signed documents inserted

- All the welders certificates to be submitted with PetroServ and Woqod logos and clear refrence to
Comment incorporated.
the project for approval and signature

NDT requirements as per approved drawings


already fulfilled.
5% RT for shop joints and welder ratio also
- RT Percentage (5%) is not covered, Total 267 But joints which require 14 RT shots, 3 more
covered.
weldments need to be done
100% MT done on field joints
UT not applicable for 2" pipe with thickness less
than 6mm.

- NDT (RT) personnel Certificates along with cover page of NDT (RT) procedures to be submitted Woqod approved RT procedure along with
by PetroServ for Woqod approval technicians certificates inserted in test pack
C
- Report no. PSL-5084-QC-M-02-F-02 for electrode backing and issuance along with electrode Vacuum pack electrodes are being used at site.
batch certificates to be included Backing not applicable.

- Line List to be included in the package, last revision of line list to be Submitted by PetroServ for
Latest revision line list attached.
Woqod approval. Design and test pressure has been changed to be 8.8 and 9.86 bar respectively

- All valves MTCs to be included in the package and site verification to be arranged. Valve MTCs included.

Details of received 2” pipes are as below


– JSL/Q/J17/TX2017005370/A01 to A24
(Heat No. 3703759) – 718.8 mtrs. (120
pieces)
- 2" Pipes Material Certificate Reference No. JSL/Q/J17/TX2017005370/A01 (Heat No. 3703759)
– JSL/Q/J17/TX2017005800/A01 to A10
only covers 29.95 Mtrs. (5 Pipes of 6 Mtrs each) which is very less compared with the actual
(Heat No. 3703759) – 294.20 mtrs. (49
amount of pipes being used to fabricate the HC. MTCs for 2" Pipes with actual Heat Nos. used for
pieces)
fabrication to be included in the package and site verification to be arranged.
– JSL/Q/J17/TX2017005370/B01 to B65
(Heat No. 3703760) – 1929.66 mtrs. (323
pieces)
Test pack updated accordingly.
Heat numbers mentioned in welding reports
remains same.
- All Welding History reports & Material Receiving Reports to be modified according to the actual
Material receiving inspection reports for the
heat Nos. used in Fabrication and resubmitted to Woqod for review
additional quantity pipes (same heat number)
included in the test pack

S-ar putea să vă placă și