The drawings for foundations of the columns for production buildings should be started immediately

after the go-ahead signal and action taken for the procurement of cement and reinforcement rods.
The construction of production sheds can proceed simultaneously. On receipt of foundation load and
other data, lying of foundations for the Mini Blast Furnace, transformer and all other equipment can
be taken up simultaneously before the equipment arrive at the site. The laying of internal roads and
drainage system should be completed expeditiously to facilitate transportation of structural materials,
equipment, raw materials, etc. Work on the construction of ancillary buildings and facilities should
proceed simultaneously.