KTPS 3X660 MW LOADABILITY CONSTRA

Unit System/Auxiliary Constraint Planned to start

C/Mill 8A 15/01/2019
C/Mill 8A, 8B & 8C are due for
8 COAL CYCLE C/Mill 8B 10 /12/2018
package overhaul C/Mill 8C 05/10/2018

CM# 9C, 9D are due for package C/Mill 9C - 10th FEB 2019
9 COAL CYCLE overhaul C/Mill 9D - 10th MAR 2019

10 COAL CYCLE

8 RAPH RAPH 8A/8B


8 ESP Fields availability

8 Fly ash Fly ash evacuation

8 Bottom Ash System Grinder availability

9 ESP Fields availability

9 Fly ash Fly ash evacuation

9 Bottom Ash System Grinder availability


10 ESP Fields availability

10 Fly ash Fly ash evacuation

10 Bottom Ash System Grinder availability

AHP
common Ash Slurry System Ash slurry Pump series availability
System

AHP
common HCSD Silo. Ash storage Silo
System
AHP
common HCSD Silo. Ash storage Silo
System

Unit-8,9 TDBFP Availability Unit-8,9&10


&10

CWP Availability Unit-8,9&10

CEP Vibrations Unit-8,9&10


Debris Filter System Unit-10

ACW Pumps Unit-8,9&10


BILITY CONSTRAINT FOR RATED LOAD
Planning for Work & Spares Target Date
Grinding media available
Spare Journal assembly PO placed,
mat. Awaited.
C/Mill discharge pipes PO placed,
mat. Awaited.
Hoisting system is to be restored, 30th NOV 2018
tender in process.
C/Mill lub oil pumps procurement in
process. 31st OCT 2018

C/Mill Hydraulic Loading system 10th NOV 2018


pumps procurement in process.
CM# 9C & 9D Package Overhaul
Grinding media available
Spare Journal assembly PO placed,
mat. Awaited.
Hoisting system is to be restored,
tender in process. 30th NOV 2019

CM discharge pipes PO placed, mat.


Awaited. 15th NOV 2019

CM Loading Hydraulic systems pumps


procurement in process.
31st OCT 2018
CM lub oil pumps procurement in
process.

Hoisting system is to be restored,


tender in process.
CM Loading Hydraulic systems pumps st
procurement in process. 31 DEC 2018

CM lub oil pumps procurement in


process.

PA header pressure is not adequate &


PA loading is increasing.
To sort out the
problem (1) Cold end baskets are to
be cleaned by removing & hot end / JUN 2019 DURING UNIT AOH
intermediate baskets are to be
cleaned in position. (2) Seal
replacement & Seal setting is to be
done. (3) Sector plate repairing
To avoid the loosening & detachment
of collecting panels from top tad
pole, modification by providing
additional clamping is in process.
Already first 3 fields of all pass work Tender - 2 months’ Work - AOH/SD
completed.

Tender proposed for supply & works


of remaining fields.

To avoid the moisture formation in


conveying air, receiver tanks are to be
installed additionally as well as after
cooler will be provided to reduce the
temperature of conveying air. Root 6 months
valve which are having dome type are
to be replaced by double disc type.
Few valves have been replaced by
double disc type.

At present 05 nos. clinker grinders


are in service. 01 no grinder will be 15 days
made available very soon

To avoid the loosening & detachment


of collecting panels from top tad
pole, modification by providing
additional clamping is in process.
Already 'A' pass 3 field work During Unit S/D
completed.

Tender proposed for supply & works


of remaining fields.

To avoid the moisture formation in


conveying air, receiver tanks are to be
installed additionally as well as after
cooler will be provided to reduce the
temperature of conveying air. Root 6 months
valve which are having dome type are
to be replaced by double disc type.
Few valves have been replaced by
double disc type.

At present 05 nos. clinker grinders


are in service. 01 no grinder will be 15 days
made available very soon
At Present all ESP fields are available
from mechanical. To avoid the
loosening & detachment of collecting
panels from top tad pole,
modification by providing additional Nil
clamping is in process. Tender
proposed for supply & works of
remaining fields.

To avoid the moisture formation in


conveying air, air receiver tanks are to
be installed additionally as well as
after cooler will be provided to
reduce the temperature of conveying Receiver - 15 Double disc - In progress
air. Root valve which are having dome
type are to be replaced by double
disc type. Few valves have been
replaced by double disc type.

At present 05 nos. clinker grinders


are in service. 01 no grinder is not Nil
provided by project till date.

Ash slurry pump series-A, Erection


and commissioning work was not
carried out by Project therefore work
is taken up by O & M on risk and cost
basis. Work will be completed within
15 days.
2 months

Ash slurry pipeline for above series


proposed from O & M on risk and
cost basis.

Material procurement is in process.

To avoid pressurization of Silo,


following works are planned and
under process.

1) Replacement of suitable vent fans.


PO Placed and material is awaited.

2) Replacement of bag filter mother


plate. Proposal under process. 2 months
2 months

3) Providing purging air receiver and


modification of purging system for
effective purging of bag filters and
prevent premature failure of filter
bags work in progress.

If any one of the units TDBFP fails:


Spare repaired Cartridge is available
with us. Booster pump spares are not
available with us. Presently, all
TDBFP's available in all units.

All CW Pumps are in service & no


major issues except CW pump 10B,
having mechanical seal leakage. PO
under process & needs HO approval.
In view of OEM proposal, HO
approval and material availability at 15th Dec-18.
site up to Nov-18 end. After receipt of
material, CWP-10B Mechanical Seal
replacement work will be taken and
work will be completed in ten days.
The critical spares of CWP proposal,
sent to HO is under process.

Presently all CEP's are available.


Spares are available with us if any
emergency occurred. Only High
vibration problems in all units,
particularly CEP-B. But all are in
within limit. However to reduce
vibration level, modification plan is
under execution. Replacement of 15th Mar 2018
existing Cardon shaft by tubular shaft
is planned & material procurement is
proposed. The said proposal is in
process and PO will be finalized up to
Dec-18. After receipt of material,
work will be taken and optimize the
vibration level.
Debris filter system-B stream found
choke up. Choke up removal freeness
work is in progress, but still DP is
maintaining higher side. Due to this During next possible opportunity.
choke up, CW back pressure
increased up to 3.25 kg/cm2. But
there is no vibration in CW Pump-
10B.

All ACW pumps are available and


vibrations are in within limit. Ok