Documente Academic
Documente Profesional
Documente Cultură
Internship Report
On
Power Generation, Transmission and Distribution
At
United Power Generation and Distribution Company Ltd. (UPGD)
By
Anadi Ranjan Barai (Roll: 121061)
Md. Rysul Kibria Badhon (Roll: 121076)
Submitted To
Md. Mamunur Rashid
Lecturer, Department of Electrical and Electronic Engineering
Rajshahi University of Engineering and Technology
_______________________ ________________________
1
Department of Electronic and Electrical Engineering, RUET
Internship Report
On
Power Generation, Transmission and Distribution
At
United Power Generation and Distribution Company Ltd. (UPGD)
2
Undergraduate Internship Report
INDEX
I Acknowledgement 6
II Executive Summary 7
1. Chapter 1
2. Chapter 2
2.1 Background of United Power Generation and Distribution Company Ltd. (UPGD) 10
2.2 Features 10
2.6 Summary 11
3. Chapter 3
4.1 Introduction 21
4. Chapter 4
5. Chapter 5
3
Department of Electronic and Electrical Engineering, RUET
6. Chapter 6
6.3.1 Overview 36
6.7.2 KW control 40
4
Undergraduate Internship Report
6.14 Shutdown 43
7. Chapter 7
Conclusion 44
5
Department of Electronic and Electrical Engineering, RUET
Acknowledgement
First of all we would like to thank the Almighty and also those who supported us to complete
the report successfully.
We would like to thank the General Manager (Operations and Maintenance) Mr. Shamim Reza
Khan, UEPSL; Plant Manager Mr. Shamer Ahmed Chowdhury, DEPZ Plant, UPGD Ltd. as
well as Md. Razib Uddin, Assistant Plant Manager for their overall kind cooperation. In
addition, we would like to express our gratitude to Mr. Sheikh Ashraf Hossain, Chief Operating
Officer for the correspondence.
We also like to thank to all engineers working on the plant especially Mr. Rabbiul Hasan Ripon
and Mr. Muhammad Tarik to assist and willing to take part in their field duty otherwise our
practical knowledge would be limited so again my cordially thanks to them.
We would like to send our best regards to our academic supervisor Md. Mamunur Rashid as
he permitted us to visit this plant. But for his assist and suggestion we would not go this far.
Also we like to thank our head of department Prof. Dr. Md. Jahurul Islam Sarker and Md. Selim
Hossain, Assistant Professor, without their keen interest and earnest endeavor we would not be
able to initiate our industrial attachment course. Finally we like to thank our honourable Vice
Chancellor Prof. Dr. Md. Rafiqul Alam Beg.
6
Undergraduate Internship Report
Executive Summary
I did my internship at United Power Generation Company Ltd (UPGD) at DEPZ 20th of June
to 3rd of July and this internship report is the result of those 14 days attachment with the UPGD.
United Power Generation Company Ltd (UPGD)) provides electricity in DEPZ area
Bangladesh. United Power Generation Company Ltd (UPGD) fulfills about all of power
requirements in DEPZ. The installed capacity by its 9 units is 88 MW.
My duration of stay was divided to work in five sections as generator, sub-station, I & C and
operation. During my internship I gathered practical knowledge about production of electricity,
operation, major equipments e.g. Generator, Transformer and Switchgear equipments required
for distribution and protection of the system.
Protection and controlling of the equipments of the power station is a very important and
complicated task. With the help of the plant engineers I observed the control room and
protective equipments such as: relays (digital and electrical), circuit breakers etc very closely
and understood the functions and controlling system of those equipments.
Substation is an important part of a power station to distribute power and protection purpose. I
acquired knowledge about various types of transformers, bus-bars, circuit breakers (SF6 and
Oil), lightning arresters, CT, PT and other equipments of the substation which were clearly
taught and shown by the senior engineers of the substation of UPGD.
7
Department of Electronic and Electrical Engineering, RUET
Chapter 1
Introduction
8
Undergraduate Internship Report
Chapter 2
Company Profile
2.2 Features:
Number of Generators: 4 units each of capacity 8.73 MW
units each of capacity 2 MW
units each of capacity 9.34 MW
Genset Model:
Wartsila Finland 20V34SG
MTU Germany AOE20V4000L62
Rolls-Royce Norway B35:40V20AG2
Capacity: 88 Megawatts (Total)
Commercial Operation Date (COD): 35 MW, December 26th, 2008
MW, October 24th, 2010
47 MW, July 2013
Clientele: Dhaka Export Processing Zone
Rural Electrification Board
9
Department of Electronic and Electrical Engineering, RUET
2.6 Summary:
SL. PARTICULARS PRESENT STATUS
No.
1 Installed capacity 88 MW
MTU (3*2) = 6 MW
3 No of substation (11/33KV) 01
4 No of feeder 16
5 No of Power Transformer 03
10
Undergraduate Internship Report
Chapter 3
UPGD Power Plant
In the plants there are 3 types of engines operates every day for the sake of generate mechanical power
to generators. They are:
11
Department of Electronic and Electrical Engineering, RUET
Wartsila
Rolls-Royce
MTU
As all engine operates as per as the same principle we just describe the parts of Wartsila Engine.
In the model no. W refers to Wartsila, 20V means 20 V shaped cylinder, 34 means 34 cm bore radius S
means spark ignition and G means gas engine. The main parts of the Wartsila engine is composed of :
Pre-chamber
The pre-chamber is the ignition source for the main fuel charge, and is an essential component of a
leanburn spark-ignited gas engine. It should be as small as possible to deliver low NOX values, but big
12
Undergraduate Internship Report
enough for rapid and reliable combustion. Extensive calculations and simulations had to be performed
to scale-up the size and shape of the combustion pre-chamber in order to ensure the best combustion
process. In addition to the size and shape of the pre-chambers, some of the key design parameters
considered were: the mixing of air and fuel; gas velocities and turbulence at the spark plug; cooling of
pre-chamber and spark plug; and the selection of material. Advanced three-dimensional, computerized
fluid dynamics were used during design to deliver:
The engines use a ported gas admission system, whereby gas is admitted to the pre-chamber through a
mechanical, hydraulic-driven valve. The gas admission valves are located immediately upstream, and
are electronically actuated and controlled to feed the correct amount of gas to each cylinder. Since the
gas valve is timed independently of the inlet valve, the cylinder can be scavenged without risk of the
gas escaping from the inlet directly to the exhaust. Various parameters, such as engine load, speed, and
cylinder exhaust temperatures, are monitored and used as input to the Engine Control System (ECS).
The ECS is Wärtsilä’s latest UNIC (Unified Controls) C3 system, which controls the entire engine. This
solution has proved to be extremely reliable and it results in an excellent mixture in the pre-chamber.
Ignition system
The Wärtsilä 34SG ignition system has been specifically designed for the new engine and is closely
integrated with the ECS. The ignition module communicates with the main control module, which then
determines the global ignition timing. The ignition module controls the cylinder-specific ignition timing
based on the combustion quality. The cylinder specific control ensures optimum combustion in every
cylinder with respect to reliability and efficiency. The ignition coil is located in the cylinder cover and
is integrated into the spark plug extension. The coil-on-plug design minimizes the number of joints
between the spark plug and the ignition coil, and thus increases reliability. The spark plug has been
13
Department of Electronic and Electrical Engineering, RUET
specially developed for long life, and to withstand the high cylinder pressure and temperature resulting
from the high engine output.
Engine frame
The engine frame is based on the proven design of the Wärtsilä 50DF, and the block is made from cast
iron. The engine has an under slung crankshaft, which imparts high stiffness to the engine block and
provides excellent conditions for maintenance. The engine block has large crankcase doors to enable
easy maintenance.
Cooling system
The Wärtsilä 34SG is designed with a Wärtsilä open interface cooling system for optimal cooling and
heat recovery. The system has four cooling circuits: the cylinder cooling circuit (jacket), the low
temperature charge air (LTCA) and high temperature (HTCA) cooling circuits, and the circuit for the
lube oil cooler (LO) built onto the auxiliary module. The LTCA cooling circuit and jacket cooling
circuit have water pumps integrated within the cover module at the free end of the engine coolers, and
the temperature of the water exiting the jacket cooling circuit is controlled by external thermostatic
valves. The default cooling system is a single circuit radiator unit whereby the cooling circuits on the
engine are connected in series. For heat recovery applications, each cooler can be individually
connected to an external cooling system.
The engine has an engine-driven lubricating oil pump and is provided with a wet sump oil system.
Before entering the engine, the oil passes through a full-flow automatic back flushing filter. A duplex
cartridge filter is installed in the back flushing line, and both filters are equipped with differential
pressure switches. A separate pre-lubricating system is used before the engine is started to avoid engine
wear.
14
Undergraduate Internship Report
Pistons
The pistons are of the low-friction, composite type, with a forged steel top and nodular cast iron skirt.
Their long life is ensured through the use of a skirt lubrication system, a piston crown with shaker-
15
Department of Electronic and Electrical Engineering, RUET
The two compression rings and the oil control ring are located in the piston crown. This three-ring
concept has proven its efficiency in all Wärtsilä engines. Most of the frictional loss from a combustion
engine originates from the piston rings. A three-ring pack has proven to be the optimal solution, offering
both function and efficiency. In a three pack, each ring is dimensioned and profiled for the task it must
perform.
Cylinder head
The engine uses four-screw cylinder head technology. At high cylinder pressures this technology has
proven to be superior, especially when liner roundness and dynamic behaviour are considered. In
addition to easier maintenance and reliability, it provides the freedom to employ the most efficient air
inlet and exhaust outlet channel port configurations. A distributed water flow pattern is used for proper
cooling of the exhaust valves, the cylinder head flame plate, and the pre-chamber. This minimizes
thermal stress and guarantees a sufficiently low exhaust valve temperature. Both inlet and exhaust
valves are fitted with rotators for even thermal and mechanical loading.
The cylinder liner features an anti-polishing ring, which reduces lube oil consumption and wear. The
bore-cooled collar design of the liner ensures minimum deformation and efficient cooling. Each
cylinder liner has two temperature sensors for continuous monitoring of piston and cylinder liner
behavior.
The connecting rod is designed for optimal bearing performance. It features a threepiece design, in
which combustion forces are distributed over a maximum bearing area, and relative movements
between mating surfaces are minimized. The design also allows the compression ratio to be varied to
suit gases with different knocking resistance. The three-piece design reduces the height required for
piston overhauling. Piston overhaul is possible without touching the big-end bearing, and the big-end
bearing itself can be inspected without removing the piston. The big-end bearing housing is
hydraulically tightened, resulting in a distortion-free bore for the corrosion-resistant precision bearing.
16
Undergraduate Internship Report
The crank gear has to be able to operate reliably at high cylinder pressures. The crankshaft must be
robust and the specific bearing loads maintained at acceptable levels. This is achieved by careful
optimization of the crank throw dimensions and fillets. The specific bearing loads are conservative and
the cylinder spacing, which is important for the overall length of the engine, is minimized. In addition
to low bearing loads, the other crucial factor for safe bearing operation is oil film thickness. Ample oil
film thickness in the main bearings is ensured by optimal balancing of the rotational masses, and in the
big-end bearing by un-grooved bearing surfaces in the critical areas.
The Wärtsilä 34SG is equipped with a single pipe exhaust turbo charging system designed for minimum
flow losses on both the exhaust and air sides. The interface between the engine and turbocharger is
streamlined, the engine uses high-efficiency turbochargers, with the engine lubricating oil also being
used for the turbocharger.
streamlined, the engine uses high-efficiency turbochargers, with the engine lubricating oil also being
used for the turbocharger.
Automation
17
Department of Electronic and Electrical Engineering, RUET
All engine functions are controlled by the UNIC C3 engine control system, a microprocessor-based
distributed control system mounted on the engine. The various electronic modules are dedicated and
optimized for specific functions.
Each cylinder is equipped with a pressure sensor. The cylinders can be individually set to run at their
optimum point to achieve the highest engine power and efficiency. This also applies if operating
conditions change, as in the case of varying methane numbers and ambient temperatures. Additionally,
this means that the engine can be run with increased safety and reliability. Cylinder pressure
measurements provide significantly improved engine control. From the signal emitted by the pressure
sensors, UNIC can instantaneously determine the rate of heat release, the magnitude and location of
peak pressures and the knock severity. The sensors can also be used to determine the indicated mean
effective pressure, which is essentially a measure of the power developed in each cylinder. The sensor
is designed to withstand high cylinder temperatures and pressures – up to 300°C and 300 bar. The
maintenance interval of the sensor equals that for the cylinder head overhaul, i.e. around 16,000 hours.
The location of the pressure sensor is also important. The measuring membrane of each sensor is flush-
mounted in the combustion chamber, to ensure measurement of correct and reliable data.
The core of the engine control system is the main control module. This is responsible for ensuring the
engine’s reliable operation and for keeping the engine at optimum performance in all operating
conditions, including varying ambient temperatures and fluctuating gas quality. The main control
module reads the information sent by all the other modules. Using this information, it adjusts the
engine’s speed and load control by determining reference values for the main gas admission, air-fuel
ratio, and ignition timing. The main control module automatically controls the start and stop sequences
of the engine and the safety system. The module also communicates with the plant control system.
18
Undergraduate Internship Report
Each cylinder control module monitors and controls three cylinders. The cylinder control module
controls the cylinder specific air-fuel ratio by individually adjusting the gas admission for each cylinder.
The cylinder control module measures the knock intensity, i.e. uncontrolled combustion in the cylinder,
which is used to control the cylinder specific ignition timing and gas admission.
Monitoring modules
Monitoring modules are located close to groups of sensors, which reduces the amount of cabling on the
engine. The monitored signals are transmitted to the main control module, and are used for the engine
control and safety systems. The monitored values are also transferred to the Wärtsilä Operators Interface
System (WOIS) on the plant automation system.
19
Department of Electronic and Electrical Engineering, RUET
Chapter 4
Substation
4.1 Introduction
A substation is a part of an electrical generation, transmission, and distribution system. Substations
transform voltage from high to low, or the reverse, or perform any of several other important functions.
Between the generating station and consumer, electric power may flow through several substations at
different voltage levels.
Substations may be owned and operated by an electrical utility, or may be owned by a large industrial
or commercial customer. Generally substations are unattended, relying on SCADA for remote
supervision and control.
The 11 kV line from the bus bar of the circuit breaker comes directly to the substation. In the only
substation of UPGD there are following components:
Power transformer
Underground cables
Auxiliary transformer
Zigzag transformer
Transform of power is done by electromagnetic induction between the windings or circuits, depending
upon the size and turns of the windings values of voltage and current are changed from primary (source)
to secondary (load) with constant frequency.
Transformer Principal
Grid Transformer
In grid, Step down power transformer is used where it transforms the generated electricity and
transmitted to the substation parts. In Bangladesh most of this power transformers are of OIL
immerge type transformers. Usually in Grid, 50/75 MVA ranged transformers are used.
Substation Transformer
20
Undergraduate Internship Report
Like grid transformers, here also step down power transformer is used where it transforms 33 KV
transmitted voltage to 11 KV. After this transformation the 11KV is transmitted to the distribution part
where in the transmission lines the distribution transformers take place to lower down the voltage
(11KV to 230V). This three substation transformers in the UPGD: two of them has the rating of 16/20
MVA and another has 25/36 MVA. But the distribution transformers are usually of 200KVA.
I. Terminals
In oil or liquid type transformer, terminal means of bringing the electrical connection from the inside
to the outside of the tank.
II. Bushings
Terminal device in form of bushings brings the connection from the transformer insulation medium to
the external insulation medium which in most cases is air, but can also be oil in a cable termination box
or Sf6 in gas insulated switchgear.
21
Department of Electronic and Electrical Engineering, RUET
III. Coolers
The cooling equipment collects hot oil at the top of the tank and returns cooled oil lower down on the
side. Two circuits- the inner circuit transfers the loss energy from the heat producing surface to the oil.
In the outer circuit, the oil transfers the heat to a secondary cooling medium (air).
A tap changer is a connection point along a transformer winding that allows a certain number of turns
to be selected. By this means, a transformer with a variable turn’s ratio is produced, enabling voltage
regulation of the output. The tap selection is made via a tap changer mechanism.
22
Undergraduate Internship Report
V. Conservator
Conservator is the part of the transformer is kept in case of the transformer oil expansion is occurred
and then the expanded oil is placed in here automatically. For this reason usually the oil filled up limit
is 50% of the conservator and rest is kept empty.
A dehydrating breather removes most of the moisture from the air, which is drawn into the conservator
as the transformer cools down. The absence of moisture in the air largely eliminates any reduction in
the breakdown strength of the insulation oil and prevents any buildup of condensation (sludge) in the
conservator. Therefore, the dehydrating breather contributes to safe and reliable operation of the
transformer. It contains a drying agent usually silica gel. The property of silica gel is high absorption
power of humidity.
Grounding transformer is the neutral grounding transformer – star connected on the primary and has an
open delta on secondary. Open Delta has two terminals. A resistor is connected across these two
terminals.
23
Department of Electronic and Electrical Engineering, RUET
Zig-Zag or inter connected star grounding transformer has normal magnetising impedance of high value
but for E/F, currents flow in windings of the same - core in such a manner that the ampere turn cancel
and hence offer lower impedance.
In cases where the neutral point of three phase system is not accessible like the system connected to the
delta connected side of a electrical power transformer, an artificial neutral point may be created with
help of a zigzag connected earthing transformer.
This is a core type transformer with three limbs. Every phase winding in zigzag connection is divided
into two equal halves. One half of which is wound on one limb and other half is wound on another limb
of the core of transformer.
24
Undergraduate Internship Report
Chapter 5
Protection System
1. Differential protection.
3. Buchhloz Trip.
a) Winding temperature
b) Oil temperature
External Faults
25
Department of Electronic and Electrical Engineering, RUET
These are due to overload conditions and external short circuits. Time graded Over-current & Earth
Fault relays are employed for external short circuit conditions. Fuses are provided for Distribution
transformers.
Internal Faults
Internal faults are of two types. These two types of faults are described below:
Electrical Faults
Electrical Faults are the faults which cause immediate serious damage in the system. Such as phase
to earth or phase to phase faults, short circuits between turns of high voltage and low voltage
windings, etc.
Incipient Faults
Incipient faults are initially minor faults, causing slowly developing damage such as a poor
electrical connection of conductors or breakdown of insulation etc.
The following relays are employed to protect the transformer against internal faults:
Buchholz relays
Differential relays
Pressure relief relays
Over current and earth fault relays
26
Undergraduate Internship Report
condition within the tank and send an alarm or trip signal. Under normal conditions the relay is
completely full of oil. Operation occurs when floats are displaced by an accumulation of gas, or a flap
is moved by a surge of oil. Almost all large oil-filled transformers are equipped with a Buchholz relay.
Ingress of air into the oil system Intense heat taking places
The operating principle employed by transformer differential protection is the Merz-Price circulating
current system as shown below. This current say I1 and I2 circulates in the pilot wires. Under normal
conditions or external fault I1and I2 are equal and opposite such that the resultant current through the
27
Department of Electronic and Electrical Engineering, RUET
relay is zero. An internal fault produces an unbalance or 'spill' current that is detected by the relay,
leading to operation.
During normal condition and external fault the protection system is balanced and the CT’s rations are
such that secondary currents are equal. The vector differential current, I1 - I2 =0 (normal condition and
external fault). This current are flows throws the relay coil is zero. [4] For external fault the relay may
loss it’s stability for through the fault. To overcome this condition, the Percentage Differential Relay,
or Based Differential Relay is used. It is essentially a circulating current differential relay with
additional restraining coil. The current flowing in restraining coil is proportional to (I1+ I2)/2 and this
restraining current prevents the operation during external faults. Because, with the rise in current, the
restraining torque increase and I1- I2 arising out of difference in CT ratio is not enough to cause the
relay operation.
• Reduces the pressure in the tank by instantaneously opening the connecting port.
• Secondly, along with above mentioned function, it operates a switch which can be used to initiate
precautionary electrical system.
28
Undergraduate Internship Report
Over current protection includes short-circuit protection. Short circuits are phase faults, earth faults or
winding faults. The basic element in Over-current protection is an Over-current relay which picks up
when the magnitude of current exceeds the pickup level. The over-current relays are connected to the
system, normally by means of CT’s.
The over current protection is needed to protect the transformer from sustained overloads and short
circuits. Induction type over current relays are used which in addition to providing overload protection
acts as back up relays for protection of transformer winding fault. The earth fault protection is used to
provide protection against any earth fault in the windings of the transformer.
It works on the principle that when the transformer winding is sound the currents in all the three phases
will balance and no current will spill into the earth fault relay. The arrangement is such that the relay
does not respond to any out of balance current between windings caused by tap changing arrangement.
2) Main relay give sense to trip coil of the Circuit Breaker (CB).
29
Department of Electronic and Electrical Engineering, RUET
4) After tripping of CB, main relay will get reset but indication/flag will persist, this is to be reset
locally.
5) Trip relay normally resetting by ESC, it can possible locally also but local reset only to be carried
out in local mode.
The relief valve is enclosed within a cast iron casing that is secured to the cylinder head by
threaded studs and hex nuts. It consists of the following components;
It is fitted inside the casing being held in position by the top and bottom ring keeps.
The Valve and Stem
The valve and stem are manufactured from high grade stainless steel, the valve being seated
on an integral seat/machined landing that is open to the combustion chamber. The stem is
not connected to the valve, but sits atop of it; protruding through the centre of the spring
and terminating in a threaded portion outside the top of the casing. The threaded portion
contains the locknuts that are used to adjust the spring tension, via the top spring collar.
This allows the lifting pressure of the valve to be set at 20% over maximum internal
combustion pressure.
30
Undergraduate Internship Report
Maintenance consists of cleaning and inspecting all the components at the same intervals as
cylinder head overhaul. The valve seat should be examined and re-ground; the spring being
checked for cracks and its free length measured under no-load conditions.
After the assembly the valve should be set to the correct lifting pressure before being subjected
to pressure and leak testing.
At Harland and Wolff; we used to leak-test the seat by pouring paraffin oil into the valve casing.
Any sign of a leak-no matter how insignificant and the valve was stripped, the seat reground
then retested. Pressure testing was carried out on a bench mounted test rig consisting of a high
pressure air compressor, air pressure control valve, and calibrated gauges. The relief valve was
bolted to the compressor accumulator flange and the air pressure increased until the valve lifted.
The certifying authority at the time was DNV and Lloyds of London and they witnessed the
testing of every one we assembled before they were bolted to the cylinder heads of the engines.
Mind you, that was 1964, but I suppose the setting and testing procedures are much the same
today.
A sketch showing the components of a typical cylinder relief valve is shown below; please click
on image to enlarge.
Operating Principles
"Normal" lifting of the relief valve can occur in the following situation, and should give no
cause for concern;
When too much fuel is supplied by the engineer when on starting the engine; I have done this
a few times!
If air is being used to stop engine in “emergency stop" situation.
Running engine full astern for a prolonged period, in this case the bridge should be informed
that astern running is at its limit.
31
Department of Electronic and Electrical Engineering, RUET
However, there are situations that could lead to a relief valve lifting while engine is operating
under normal load and conditions and warrant a full inspection.
Faulty fuel pump or incorrectly set fuel injector delivering excessive fuel.
Badly leaking fuel injector; through loose nozzle or enlarged injection holes.
Water leaking into the combustion chamber.
Scavenge fire.
Large Marine Diesel Engines are started using high pressure compressed air. The air is admitted
into the cylinder when the piston is just past TDC and continued until just before the exhaust
valve opens. There is always more than one air start valve open: - a situation known as overlap.
This ensures that the engine will start in any position. The opening of the main air start valves
is controlled by a set of pilot valves located in the air start distributor, which in turn are timed
to operate by a drive linked to the main camshaft. In the example shown, a small camshaft is
used to control the opening and closing of the air start pilot valves.
32
Undergraduate Internship Report
depend on the size and capacity of the engine. For example, a large slow speed diesel engine
consists of two door type relief valves fitted to each crankcase, whereas in a medium speed
diesel engine only one valve is used. So basically the relief valve is a one-way entry which only
allows inside pressure to escape when excess, without allowing the other way round.
As shown in the figure, an explosion relief valve consists of a light spring that holds the valve
closely against its seat. The whole arrangement is enclosed in a cover, which is tightly bolted
from all the sides. The assembly is mounted on the door of the crankcase. On the outside of the
valve a deflector is fitted which safeguards the personnel from escaping pressurized gases. On
the inside of the engine, an oil wetted gaze acts as a flame trap to prevent any flame leaving the
crankcase.
33
Department of Electronic and Electrical Engineering, RUET
Oil Mist detectors are used for this purpose. Crankcase of each cylinder is connected to the
OMD, which continuously checks the air sample from each cylinder. If the amount of mist
increases, OMD raises an alarm.
When the forward button in ill. 6 is pressed, coil F is energized and the normally open (NO)
contact F closes to hold in the forward contactor. Because the normally closed (NC) contacts
are used in the forward and reverse push-button units, there is no need to press the stop button
before changing the direction of rotation. If the reverse button is pressed while the motor is
running in the forward direction, the forward control circuit's de-energized and the reverse
contactor is energized and held closed.
Repeated reversals of the direction of motor rotation are not recommended. Such reversals may
cause the overload relays and starting fuses to overheat; this disconnects the motor from the
circuit. The driven machine may also be damaged. It may be necessary to wait until the motor
has coasted to a standstill.
34
Undergraduate Internship Report
Chapter 6
Switchgear and Control system
ABB
Unipower
Rated voltage max. 690V 50 /60 Hz
Rated currents 1600 - 5000 A
Short-circuit withstand busbars 50 - 100 kA 1s
35
Department of Electronic and Electrical Engineering, RUET
Control & Relay Panels facilitate centralized control of the related controlled equipment in power
stations, switching stations and industrial plant. The panels are bolted together to form a board. This
approach permits replacements, extensions, rearrangement and addition when necessary.
The panel incorporates control switches and indicator lamps for remote control of controlled equipment.
A “remote/supervisory” selector switch is also provided for selection of supervisory control from
remote control center.
Fig: 2
6.3.1 Overview
36
Undergraduate Internship Report
This power plant is designed for a predetermined number of genset(s).The instruments and controls
needed for operation of the genset(s) are located in control panels in the power stations control
room. The standard configuration and marking of the push-buttons, control switches and indication
lamps for the common control cabinet (CFA901) are as shown. The unit is referred to as M2 in this
manual.
Markings in the M2 panel are as follows:
• S1 synchronizing mode auto - 0 - manual
• S2 frequency decrease - increase
• S3 voltage decrease - increase
• S4 breaker close
• S5 lamp test
For the control appliances in the genset(s) (CFC__1) control cabinet refer to Fig. 2. The unit is referred
to as M1 in this manual. Markings in the
Engine(s) can be controlled (see Fig. 3) with commands given from the Operator Station(s) and/or
with switches and push-buttons from genset control panel(s) (CFC__1). Each genset has a control
panel (CFC__1) in the control room. This panel contains various meters from the process and
genset control push buttons. From the genset control panel it is possible for the operator to start/stop
the engine, load/unload the genset and open/close the genset circuit breaker (CB). It is also possible
to control the generator and synchronize it from this panel. Emergency stop can also be activated
from this panel as well as resetting of engine shutdown and emergency stop circuit and circuit
breaker trip circuit.
37
Department of Electronic and Electrical Engineering, RUET
system collect and scale data from the inputs and sends the data to the operator’s station through
the internal communication protocols of the control system. The operator’s station shows analog
measurements and digital indications from the process. The process pictures in the operator’s
station can be printed out on the hardcopy printer. Alarms are also showed in an alarm list and
automatically printed out by the alarm printer. The analog data is logged by the operator’s station
and the logged data can be viewed as trends. The trends can also be printed on the hard copy printer.
The operator’s station is based on Windows XP operating system and In Touch HMI software. The
report system collects data, of the process, from the operator’s station. Reports of the processes
can be view and printed from the report station. MANUAL-AUTO selector switch (S1).
Starting Conditions
Engine start is enabled when the following starting conditions are met:
The engine can be started by pressing the start push button S7 located on the M1 panel or from the
engine control picture in the operator station.
Start Preparations
When start request is given the PLC start the starting preparations. During the starting preparations the
pre lubrication is started, the exhaust gas pipe is ventilated and the valves in the gas regulating unit are
tested. When these preparations have been successfully performed theengine is started.
Start Failure
38
Undergraduate Internship Report
The start-up of the engine is interrupted and an alarm is given if the start preparations fail. If the start
fails the engine does not reach nominal speed and WECS does not give start permission.
During manual synchronization the check synchronizer allows the circuit breaker to be closed when
the following conditions are met:
•• The frequency deviation is smaller than the Δfmax setting of the check synchronizer.
• The generator frequency must be higher than the bus bar frequency.
• The phase angle deviation is in accordance with the breaker closure time plus the operating time
for extra relays.
When synchronizing in manual mode the operator manually adjusts the frequency and voltage and
gives circuit breaker close command when all the conditions are met.
39
Department of Electronic and Electrical Engineering, RUET
After the engine is started and synchronized the operator can load and unload the genset. This is
made from the control panel CFC__1 in the control room. The operator can make load and unload
commands for genset by giving fuel decrease/increase orders. Fuel decrease/increase orders are
made from control switch S4 .
The operator can manually control the loading of the genset when the following conditions are met:
• Manual mode is selected with switch S1 • The genset is connected
parallel with grid
• Generator circuit breaker is closed.
•
6.7 Engine control in manual mode
The operator can select the operation mode of the engine when the engine is in manual mode.
Either speed droop or kW mode can be selected. The kW mode is not activated before the
engine is running in parallel with grid. The control methods are described shortly below:
6.7.2 KW control
• Base loading means that the unit is running at a constant load and
its output will not be affected by variations in the system load.
• Base loading is intended to be used when running in parallel with
public supply. The controller is given a parallel with grid signal and
will automatically change over to VOLTAGE droop mode if the
genset is disconnected from the public supply.
• In kW control mode the controller looks at the output directly and
matches it to a given reference, therefore kW control is not affected
by frequency changes in the grid and a steady base loading is
achieved.
• In kW control the engine output can be controlled with control
switch S4 (Fig. 2).
40
Undergraduate Internship Report
Generator controls are made from the control panel CFC__1 in the control room. Generator
control mode can be selected between voltage droop and power factor mode (PF). Power
factor mode is enabled only when following conditions are valid:
• The genset is on parallel with grid
• The generator circuit breaker is closed
Otherwise the generator control is selected automatically to voltage droop. The operator
can manually control the generator with control switch S5 (Fig. 2) excitation
decrease/increase, when manual mode is selected. The generator control mode changes
automatically from voltage mode to power factor mode if the engine control mode is
selected as auto and the following conditions are valid:
• The genset is on parallel with grid
• The generator circuit breaker is closed
•
6.8 Operation in Auto Mode
When automatic synchronization is used the automatic synchronizer performs the actual
synchronization by regulating the frequency and the voltage of the unit to be synchronized.
When the synchronization conditions are in order the automatic synchronizer will operate
and give a close order to the circuit breaker. The auto synchronizer is placed in common
control panel CFA901. The operation of the auto synchronizer can be controlled by its
settings:
• ΔVmax : Maximum voltage difference
• Δfmax : Maximum frequency difference
• Tbc : Breaker closing time
• Xp : Proportional band for frequency controller
• Tn : Length of relay impulses from the controller.
Features of the synchronizing device:
• Permission for synchronizing is possible only if the frequency of
the synchronized unit is higher than the reference frequency.
switchgear for some reason deviates too much from the generator voltage; the voltage can be
adjusted with control switch S5 when control switch S3 is in voltage droop position. The
synchronizing voltages can be read on the double voltage meter in CFA901 panel.
41
Department of Electronic and Electrical Engineering, RUET
Direct protection devices, e.g. temperature and pressure switches, protection relays, etc. generate
alarm information directly to operator stations trough a PLC or WECS. PLC or WECS initiated
protection signals are normally calculated from an analog measurement or concluded from several
signals or situations from the process.
The plant is equipped with voice based alarm device located in the control room. The audible alarm
device is used to inform operator that a new alarm is received in the operator’s station. The alarm
bell is acknowledged/silenced from the operator station.
found and removed before the circuit breaker is re closed. If a protection relay has operated the trip
also has to be acknowledged from the front display of the relay.
42
Undergraduate Internship Report
6.14 Shutdown
In case of an engine shutdown the generator breaker is opened and stop command is given to the
engine. Engine shutdown can be initiated from PLC or from WECS.
In case of a plant shutdown all engines are stopped. The power plant shutdown circuit activates the
emergency stop circuit of all engines. Power plant shutdown can be initiated from a push button
located on the CFA901 panel in the control room. Power plant shutdown is also activated in case
of a fire alarm or a level 2 gas alarm.
problems are major then operation team inform that mechanical section to solve the problem. With
the help and information sharing between all of the sections the major problems are solved.
The operation and maintenance team checks various parameters (temperature, pressure, load etc.)
continuously and detects problem. From the control room various data are collected, monitored and
checked with the help of SCADA system. When abnormality occurs, alarm rings and the specific
area of abnormality become red. The operation and maintenance team then detects the problem and
discusses the situation and finds out the reason behind the abnormality. Some figures of checking
parameters are given in the appendix II section.
43
Department of Electronic and Electrical Engineering, RUET
CHAPTER 7
CONCLUSION
Power is an indispensable part of our daily life. In our modern life style, a single day without power
is horrible to think. Power is the key to industrialization as well as the development of the country.
If a country can meet the power demands of its inhabitants, no matter what happens, its economy
i.e. the entire country will be so developed within a fewest possible time. If the power crisis can be
handled first, then all other crisis can be solved easily. In Bangladesh, the power crisis is so high;
even we the inhabitants don’t get our minimum demand. The term “Load-shedding” has become a
common part of our life now a day. For this only reason, our country cannot make any progress in
the development race of the third world countries. Our economy is getting weaker day by day in
comparison to the developed countries. So, we the so called conscious society people should come
forward to help the government to solve the problem.
In recent years, the government has taken necessary steps to solve the power crisis. It granted
permission to several private power plants along with the government owned power plants. They
are playing a vital role in solving the present power crisis. Government has taken many other power
projects to meet the power crisis and there will create a lot of employment in this sector where I
will be able to apply my proficiency.
Future Works:
United Group is one of the leading companies in Bangladesh. United Power Generation and
Distribution Company Ltd. is an enterprise of United Group. I had the opportunity to work for this
company during my internship program. I have worked in Operation and Maintenance department
of UPGD, DEPZ plant. During this time I have got an opportunity to observe the overall activities
of Operation and Maintenance environment. There is a good news that government has taken
initiative to improve the power generation to 14000 MW within 2014.This is because there is a
great career opportunity in this sector. Finally, I would say that this internship at UPGD has
increased my practical knowledge of Operation and Maintenance and made my education more
complete and applied.
44
Undergraduate Internship Report
REFERENCES
1. http://www.united.com.bd/#masthead
2. Boylestad, R. L. 1994, Introductory Circuit Analysis (5th ed.), Universal Book Stall Publications,
India
3. Mehta, V.K., 1998 Principles of Power System (2nd ed.), S. Chand $ Company Ltd., Ramnagar,
New Delhi-110055, Publications, India.
4. Theraja B.L. and. Theraja, A.K., A Text Book of Electrical Technology, Twenty Second Edition
1989, Publications divisions of Nirja Construction & Development Co. (P) Ltd.. New-Delhi-
110055
5. Web site: www.powercell .gov.bd.
6. http://www.powerdivision.gov.bd/user/yearwise
7. http://en.wikipedia.org/wiki/Electrical_substation
8. http://en.wikipedia.org/wiki/Lightning_arrester
9. http://en.wikipedia.org/wiki/Current_transformer
10. http://www.electricityforum.com/electrical-transformers/potential-transformer
11. http://www.scribd.com/doc/17648889/Introduction-to-Power-System Protection-Relays
12. http://www.transformerworld.co.uk/diffprot.htm
45