Kanban process
June 20, 2016 | 2,894 Views |
Former Member
share
0 share tweet share
Follow
Kanban process
https://blogs.sap.com/2016/06/20/kanban-process/ 1/33
10/2/2018 Kanban process | SAP Blogs
The KANBAN method for controlling production and material flow is based on the actual stock quantity
in production. Material that is required on a regular basis is continually provided in small quantities in
production. Replenishment or the production of a material is only triggered when a higher production
level actually requires the material. This replenishment is triggered directly in production using
previously maintained master data.
Master data
Select new entries, Enter plant, supply area, storage location and person responsible
https://blogs.sap.com/2016/06/20/kanban-process/ 2/33
10/2/2018 Kanban process | SAP Blogs
Enter planning strategy as 10 (make to stock) and availability check as 02, save the material.
https://blogs.sap.com/2016/06/20/kanban-process/ 3/33
10/2/2018 Kanban process | SAP Blogs
3. Create semi-finished material for which the Kanban process will be in-house, using Tcode MM01
Enter storage location for EP (where the material will be stored after its procurement), Default supply
area
(From where the material will get utilized for production) and production storage location (Storage
location assigned to supply area) and save the material
https://blogs.sap.com/2016/06/20/kanban-process/ 4/33
10/2/2018 Kanban process | SAP Blogs
4. Create semi-finished material for which the Kanban process will be in-house, using Tcode MM01
Enter storage location for EP (where the material will be stored after its procurement), Default supply
area (From where the material will get utilized for production) and production storage location (Storage
location assigned to supply area) and save the material
https://blogs.sap.com/2016/06/20/kanban-process/ 5/33
10/2/2018 Kanban process | SAP Blogs
5. Extend both the semi-finished materials for production storage location using Tcode MM01
Here enter the storage location as production storage location and enter, system will extend the material
for production storage location also, save both the materials
https://blogs.sap.com/2016/06/20/kanban-process/ 6/33
10/2/2018 Kanban process | SAP Blogs
6. Create purchase info record for vendor material combination, for semi-finished material with external
procurement using Tcode ME11
https://blogs.sap.com/2016/06/20/kanban-process/ 7/33
10/2/2018 Kanban process | SAP Blogs
Here in organization data tab, enter planed delivery time, purchasing group, standard quantity and net
price then save the record.
https://blogs.sap.com/2016/06/20/kanban-process/ 8/33
10/2/2018 Kanban process | SAP Blogs
https://blogs.sap.com/2016/06/20/kanban-process/ 9/33
10/2/2018 Kanban process | SAP Blogs
Enter the required indicator which specifies the following for the status (e.g. EMPTY) in the
corresponding status sequence:
whether it is mandatory +
whether it is recommended *
Whether it is optional .
whether it is prohibited –
https://blogs.sap.com/2016/06/20/kanban-process/ 10/33
10/2/2018 Kanban process | SAP Blogs
Enter require goods movement for goods receipt, in this case 101
https://blogs.sap.com/2016/06/20/kanban-process/ 11/33
10/2/2018 Kanban process | SAP Blogs
And planed orders as ‘No planed orders’ and save the strategy
https://blogs.sap.com/2016/06/20/kanban-process/ 12/33
10/2/2018 Kanban process | SAP Blogs
Enter control type as ‘working with purchase orders’ and order type as ‘NB’
Enter goods movement for goods receipt as 101 and save the replenishment strategy
https://blogs.sap.com/2016/06/20/kanban-process/ 13/33
10/2/2018 Kanban process | SAP Blogs
Enter material plant and supply area and select ‘classic Kanban’
https://blogs.sap.com/2016/06/20/kanban-process/ 14/33
10/2/2018 Kanban process | SAP Blogs
https://blogs.sap.com/2016/06/20/kanban-process/ 15/33
10/2/2018 Kanban process | SAP Blogs
On flow control tab, enter the status sequence and save the control cycle
https://blogs.sap.com/2016/06/20/kanban-process/ 16/33
10/2/2018 Kanban process | SAP Blogs
Enter external procurement replenishment strategy, Purchasing org and vendor for external procurement
On
https://blogs.sap.com/2016/06/20/kanban-process/ 17/33
10/2/2018 Kanban process | SAP Blogs
https://blogs.sap.com/2016/06/20/kanban-process/ 18/33
10/2/2018 Kanban process | SAP Blogs
1. Set the Kanban to EMPTY and FULL by using Tcode PK13N (Demand source overview) and PK12N
(Supply source overview)
Enter plant, production supply area, person responsible and production storage location and enter
https://blogs.sap.com/2016/06/20/kanban-process/ 19/33
10/2/2018 Kanban process | SAP Blogs
Select first cycle and the Kanban container, select ‘To EMPTY’ tab
System will change the status of Kanban container from full to empty (color will change from green to
red)
https://blogs.sap.com/2016/06/20/kanban-process/ 20/33
10/2/2018 Kanban process | SAP Blogs
Now double click on the Kanban container, here the system will show the production order that got
generated for in-house production of material
https://blogs.sap.com/2016/06/20/kanban-process/ 21/33
10/2/2018 Kanban process | SAP Blogs
Now go to production order change using Tcode Co02 and release the order.
https://blogs.sap.com/2016/06/20/kanban-process/ 22/33
10/2/2018 Kanban process | SAP Blogs
Now do the goods issue for production order from the issue storage location using Tcode MB1A
https://blogs.sap.com/2016/06/20/kanban-process/ 23/33
10/2/2018 Kanban process | SAP Blogs
https://blogs.sap.com/2016/06/20/kanban-process/ 24/33
10/2/2018 Kanban process | SAP Blogs
After saving the confirmation, system will automatically post the goods issue in production storage
location.
Now go to Tcode PK13N n system will automatically change the status of container as FULL
Select the Kanban cycle and container and set status as empty by selecting ‘To Empty’ tab
https://blogs.sap.com/2016/06/20/kanban-process/ 25/33
10/2/2018 Kanban process | SAP Blogs
Once the status is changed to empty (Red color), system will generate the purchase order for
procurement from vendor.
Now go to ‘supply source overview’ using Tcode PK12N, Enter person responsible, plant and vendor
and enter
Select the Kanban cycle and container and select ‘status in transit’ tab.
https://blogs.sap.com/2016/06/20/kanban-process/ 26/33
10/2/2018 Kanban process | SAP Blogs
The status will get changed from ‘EMPTY’ to ‘IN TRANSIT’ (from red color to yellow)
Select the cycle and container and change the status to ‘FULL’ by selecting ‘To full’ tab, this will trigger
the goods receipt of material from vendor (yellow color to green)
By double clicking on Kanban container the material and accounting documents can be checked if
necessary
https://blogs.sap.com/2016/06/20/kanban-process/ 27/33
10/2/2018 Kanban process | SAP Blogs
Enter the required quantity on desired date and save the PIR
https://blogs.sap.com/2016/06/20/kanban-process/ 28/33
10/2/2018 Kanban process | SAP Blogs
Go to stock/requirement list using Tcode MD04 and check the order report.
4. Conversion of planed order to production order (co02) and order confirmation (CO11N) for finished
product
https://blogs.sap.com/2016/06/20/kanban-process/ 29/33
10/2/2018 Kanban process | SAP Blogs
Convert the planed order to production order, release the order and save
https://blogs.sap.com/2016/06/20/kanban-process/ 30/33
10/2/2018 Kanban process | SAP Blogs
Save the confirmation, system will back flush the components and goods receipt of finished product will
get posted automatically as mentioned in control key.
Finished material stock will get updated in unrestricted use stock at the given storage location
https://blogs.sap.com/2016/06/20/kanban-process/ 31/33
10/2/2018 Kanban process | SAP Blogs
Alert Moderator
1 Comment
https://blogs.sap.com/2016/06/20/kanban-process/ 32/33
10/2/2018 Kanban process | SAP Blogs
Former Member
Hello, Prathamesh, please, can you let me know Tcode for Replenishment strategy – Define In-house production strategies,
Define External Procurement Startegies and Define Stock Transfer Strategies. Unfortunately, I cannot find it in SAP Menu.
thank you, Mia