Sunteți pe pagina 1din 3

SAUDI ARAMCO ID/PID FORM REV 1 - 010109 (Standards Cutoff - June 2014) Rev 8 30-Jun-14

SATIP No. APPROVED DATE DISCIPLINE:


SAUDI ARAMCO TYPICAL INSPECTION PLAN
Storm Water Drainage System SATIP-S-030-01 31-Dec-14 PLUMBING
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. & ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

1.0 DOCUMENT REVIEW

RTR & Thermoplastic Installers See See


1.1 See SATIP-S-070-03 RTR Piping and Thermoplastic
Qualifications Remarks Remarks

See See
1.2 Piping material traceability See SATIP-L-350-01 On-Plot Metallic Piping
Remarks Remarks

Welding Procedures and Welders See See


1.3 See SATIP-W-011-01 Welding On-Plot Piping
Qualifications Remarks Remarks

2.0 MATERIAL RECEIVING

Piping and Fittings See See See SATIP-S-070-03 RTR Piping and Thermoplastic &
2.1
Receiving Inspection Remarks Remarks and SATIP-L-350-01 as applicable

Pipe and Fittings Handling, Storage See See See SATIP-S-070-03 RTR Piping and Thermoplastic
2.2
and Preservation Remarks Remarks and SATIP-L-350-01 as applicable

Sewer Manhole SAIC SAIC


2.3
Receiving Inspection S-4001 S-4001 H W

Sewer Manhole SAIC SAIC


2.4
Handling, Storage and preservation S-4001 S-4001 W S Contractor QA/QC to perform Weekly Inspection

3.0 INSTALLATION

See See Refer to SATIP-S-070-01 Excavation and Backfill for


3.1 Trench Inspection
Remarks Remarks Underground Utilities

Thermoplastic Piping Installation and See See


3.2 See SATIP-S-070-03 RTR Piping and Thermoplastic
Assembly Inspection Remarks Remarks

RTR piping Laying and Assembly See See


3.3 See SATIP-S-070-03 RTR Piping and Thermoplastic
Inspection Remarks Remarks

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PID FORM REV 1 - 010109 (Standards Cutoff - June 2014) Rev 8 30-Jun-14
SATIP No. APPROVED DATE DISCIPLINE:
SAUDI ARAMCO TYPICAL INSPECTION PLAN
Storm Water Drainage System SATIP-S-030-01 31-Dec-14 PLUMBING
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. & ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

See See
3.4 Metallic Piping See SATIP-L-350-01 Metallic On-Plot Piping
Remarks Remarks

Storm Drain Piping and Manhole Lay- SAIC SAIC See SATIP-S-020-01 for Installation of storm drains
3.5
out S-4060 S-4060 H W that are a part of an oily water system

See SATIP-L-350-01 Metallic On-Plot Piping


See See
3.6 Metallic Piping and SATIP-L-350-07 Cement Lined Piping Installation
Remarks Remarks
as applicable

See See
3.7 Lift Station See SATIP-S-010-02 & SATIP-S-020-01 as applicable
Remarks Remarks

SATR SAIC Only storm drains that are part of the oily water system
3.8 Storm Drain Line Hydrostatic Test H H
S-4060 S-4060 sewer shall be hydrostatically tested

Retaining Structures (Catch Basins, SATR SAIC


3.9 H H
Manholes, etc.) HydrostaticTest S-4002 S-4002

3.10 Grout See SATIP-Q-010-01

Backfill Placement and Compaction See See Refer to SATIP-S-070-01 Excavation and Backfill for
3.11
Inspection Remarks Remarks Underground Utilities

4.0 PRE-COMMISSIONING

4.1 Not Applicable

GENERAL NOTES
The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may
1 adjust the levels of Saudi Aramco participation based upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization.

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PID FORM REV 1 - 010109 (Standards Cutoff - June 2014) Rev 8 30-Jun-14
SATIP No. APPROVED DATE DISCIPLINE:
SAUDI ARAMCO TYPICAL INSPECTION PLAN
Storm Water Drainage System SATIP-S-030-01 31-Dec-14 PLUMBING
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. & ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC
3 organization representative is not present.
Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in
4 attendance.
5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.

LEGEND
H Hold Point for QC Inspection/ Test R Review of Documents
W Witness Inspection/Test RH Review and Approval of Documents
S Surveillance I 100% Contractor Inspection

Saudi Aramco: Company General Use

S-ar putea să vă placă și