Test of 66 KV Incoming Line LA:

1) Insulation Resistance Test of LA:

Test Connection Test R Y B


Voltege. Phase (GΩ) Phase (GΩ) Phase(GΩ)
Pri to Earth 5 KV 314 344 597
Pri to Base Plate 1 KV >200 >200 >200
Base Plate to Earth 1 KV >200 >200 >200

2) Test of LA Counter:

Counter Reading
Reading R Phase Y Phase B Phase
1 6 6 6
2 6 6 6
3 6 6 6

1
Page

Name of Substation: 66 KV 25 MW ASTRA


SOLTRAN
Date of Testing: 13/04/2017
Tested By: Rakesh Patel
Approved By: Naresh Soni
Test of 66 KV Transformer-1 LA:

1) Insulation Resistance Test of LA:

Test Connection Test R Y B


Voltege. Phase (GΩ) Phase (GΩ) Phase(GΩ)
Pri to Earth 5 KV >1T >1T >1T
Pri to Base Plate 1 KV >200 >200 >200
Base Plate to Earth 1 KV >200 >200 >200

2) Test of LA Counter:

Counter Reading
Reading R Phase Y Phase B Phase
1 6 6 6
2 6 6 6
3 6 6 6

2
Page

Name of Substation: 66 KV 25 MW ASTRA


SOLTRAN
Date of Testing: 13/04/2017
Tested By: Rakesh Patel
Approved By: Naresh Soni