PUESTO EN OBRA
PRECIO DE LA EMULSION MODIFICADA= 5.95 SOLES/GALON + I.G.V. PUESTO EN PLANTA LIMA
PRECIO EMULSION STANDAR = 4.9 SOLES/GALON + I.G.V. PUESTO EN PLANTA LIMA
1 SOLES
BASE ESTABILIZADA CON EMULSION ASFALTICA CSS - 1h Costo unitario m2= 13.67 13.67
2000 m2/día
ESPESOR 10 cm
PESO UNIT ARIDO 1700 Kg/m3 ESPONJAMIENTO 25 %
% EMULSION CSS-1h 3 %
% AGUA 3 %
MATERIALES 10.63
Material Granular M3 0.1250 30.00 3.75
Agua M3 0.0024 5.00 0.01
Emulsión asfáltica CSS-1h gl 1.3474 5.10 6.87
MICROPAVIMENTO (MICROSURFACING)
ESPESOR 15 mm RENDIMIENTO 3000 m2/dia
PESO UNIT ARIDO 1700 Kg/m3 ESPONJAMIENTO 25 %
% EMULSION CQS-1p 14 %
% AGUA 10 %
% FILLER 2 % COSTO/M2= 7.76
DESCRIPCION
INSUMO UNIDAD CUADRILLA CANTIDAD PRECIO PARCIAL
PIEDRA CHANCADA M3 0.01875 30.00 0.56
EMULSION CQS-1p GAL 0.9432 5.74 5.41
AGUA GAL 0.4491 0.02 0.01
CEMENTO PORTLAND TIPO I BOLS 0.0120 18 0.22
6.20
MANO DE OBRA
CAPATAZ HH 1 0.0027 12.26 0.03
OPERARIO HH 2 0.0053 9.2 0.05
OFICIAL HH 2 0.0053 8.5 0.05
PEON HH 4 0.0107 7.62 0.08
0.21
MAQUINARIA Y EQUPO
MAQUINA EXTENDEDORA DE MORTERO HM 1 0.0027 231 0.62
CARGADOR FRONTAL HM 0.5 0.0013 175 0.23
CISTERNA DE EMULSION 8000 GAL HM 0.5 0.0013 130 0.17
CISTERNA DE AGUA 5000 GAL HM 0.5 0.0013 90 0.12
BARREDORA MECANICA O COMPRESORA DE AIRE HM 0.5 0.0013 150 0.20
HERRAMIENTAS MANUALES HM 0.010 0.010
1.35