Documente Academic
Documente Profesional
Documente Cultură
Professional Practice II
Ee Hui Teng
Vivian Tay Huey Shuen
Set-off
- Deduct/ compensate/ counter-balance something for something else
- Deduction by the Employer of debt owed by the contractor arising from some
breach of his obligations
- Employer’s common law rights to claim for compensation for certain breach such
as defective works
- Triggered when Contractor commits a breach of his obligations and fails/ refuses
to rectify the defects as instructed
Matters subject to an appropriate set-off (Clause 30.4)
- Clause 2.4: Failure to comply with AI
- Clause 4.4: Failure to pay fees, levies or charges
- Clause 5.1: Failure to set out correctly
- Clause 6.5: Failure to carry out works in accordance with contract
- Clause 6.7: Failure to comply with AI regarding defective work and materials not
in accordance with contract
- Clause 14.4: Submission of false warranty of title of goods and material which are
not free from encumbrances and of which are already been paid under the interim
certification
Matters subject to an appropriate set-off (Clause 30.4)
- Clause 15.3(b): Failure to comply with his undertaking to rectify minor defects
and employ other Person to execute
- Clause 15.3(c): Failure to comply with his undertaking to rectify minor defects and
accept defects
- Clause 15.4: Failure to attend to defects during DLP
- Clause 15.5: Failure to attend critical defects which needs urgent rectification
within reasonable time during DLP
- Clause 19.5: Failure to insure/ continue to insure works for public liability
- Clause 20.A.3: Failure to insure works for new building under Contractor All Risk
Pre-conditions for setting-off
1. Architect/ QS submit detailed assessment of such set-off to contractor
2. Architect/ Employer shall give written notice within 28 days by hand/ register
post to contractor stating:
- Employer’s intention to set-off
- Grounds & reasons of set-off
3. Employer is not entitled to set off unless amount has been agreed by the
Contractor/ adjudicator
Setting off Procedure
1. Employer shall give a written notice to the contractor within 28 days before any
set off can be deducted.
2. Deliver written notice by hand or registered post. (For Malaysia- normally by
hand)
3. Set-off can be deducted the latest by final certificate.
4. Not entitled to set off UNLESS amount is agreed by contractor/adjudicator.
Setting-off Conditions
1. No time frame in the conditions to submit assessment of Set-off.
2. Clause 30.4(b) states that : when employer want to set off an amount, a written notice must
be given to the contractor within 28 days. We can only DDT actual amount after that 28
days. However, we can reduce this period in other contract documents like preliminaries
and Letter of Award.
4. Clause 30.4(a) states that: AR or QS must submit complete details of assessment of any set
off. Must define and explain: Or else, will lack clarity and open opportunity for dispute by
contractor!
How contractor can recover from Set-off?
3 WAYS to recover:
1. Accept amount stated in the written When receive contractor’s notice of dispute,
notice within 28 days. employer can:
2. Carry out dispute within 21 days of
getting the set off notice. 1. Accept the disagreement and go with
- State why he disagree disputed amount within 21 days of
- Give his own evaluation (supporting notice.
documents and calculations. 2. Both parties agree on an amount.
3. If unable to agree: Seek adjudicator
(Clause 34.1)
Dispute to Adjudication (Clause 34.1)
1. If either parties have disputes regarding set-off, they can refer to adjudication.
2. Adjudicator will decide set off amount, not the employer.
3. Adjudication is a rough justice: If decision by adjudicator is disputed, parties still must
comply with the adjudicator’s decision (bound by practical completion). This ‘pay now,
argue later’ concept is so that work can be proceeded with the temporary decision.
4. If disputed parties want to dispute adjudicator’s decision to arbitration (second chance),
they must give a written notice to the other party to refer to ‘dispute to arbitration’ within 6
weeks from the adjudicator’s decision.
5. If disputing party fail to refer to ‘dispute to arbitration’ within 6 weeks from the
adjudicator’s decision, HIS decision will be final & binding!
What is restricting the employer rights from setting off?
RESTRICTION: CANNOT SET OFF UNLESS:
2. LD is the ONLY item not subjected to set-off procedure. But, the contract doesn’t define
meaning of set-off, so we can interpret it widely.
Clause 30.4 states that employer will be entitled to remedies in terms of set-off if contractor are
in breach of:
❖ Clause 15.3(b): where failure to comply with his undertaking to rectify minor defects, employer can
engage other Person to execute the works to give effect to the contractor’s said undertaking. All cost
including loss and expense shall be set-off by the employer.
❖ Clause 15.3(c): where contractor fails to rectify minor defects, employer can accept the defects as it is but
subject to an appropriate set-off against the contractor.
If the Contractor installed a window that is not in compliance with the
contract specifications, what are the remedies available to the Employer?
(Part 2)
Clause 30.4 states that employer will be entitled to remedies in terms of set-off if contractor are in breach of:
❖ Clause 6.5(e), where contractor fails to carry out work in accordance with the contract, employer may
accept such works as they are but subject to an appropriate set off by employer and the contractor
remain liable for the same.
❖ Clause 6.7, where contractor refuse or fails to comply with AI regarding defective work and materials
not in accordance with contract, then employer may engage other Person to rectify the defect to
comply with the AI and any loss and expense shall be set-off by the employer.
Remedies include:
Clause 6.5(b): demolish and reconstruct such work to comply with the contract
Clause 6.5(c): to rectify such work as instructed by the Architect with no adjustment to the Contract Sum
Q2. What are the remedies available
to the Contractor if he is dissatisfied
with the Adjudicator’s decision on a
set-off dispute? What are the
conditions that trigger a set-off
actions by the Employer?
Remedies available if Contractor is dissatisfied with
Adjudicator’s decision
- ‘Pay now argue later’: Decision of adjudicator must be complied until practical
completion
- Contractor can refer dispute to arbitration by giving written notice to Employer
within 6 weeks from the adjudicator’s decision
Conditions that trigger a set-off action by the Employer
- When the contractor commits a breach of his obligation
- When the contractor fails/ refuses to rectify defects as instructed
Q3. Why are set-off and Liquidated
Damages taken up by the Employer
separately and is not stated in the
Interim Certificate? Can the Employer
refer a set-off dispute to arbitration
during the construction period?
Q3. Why are set-off and Liquidated Damages taken up by
the Employer separately and is not stated in the Interim
Certificate? (Part 1)
❖ LD is not stated in in Clause 30.4 and 22.1, therefore, not subjected to set-off procedure.
❖ LD is the ONLY item not subjected to set-off procedure. However, the contract doesn’t
define meaning of set-off, so we can interpret it widely.