NOMBRE DEL PIP : CONSTRUCCION E IMPLEMENTACION DE CENTROS VIRTUALES PILOTO PARA EL LOGRO DEL APRENDIZAJE DE CONTENIDOS CURRICULARES EN EL NIVEL SECUNDARIO - REGION APURIMAC
AVANCE TRIMESTRAL PROGRAMADO GLOBAL (%) 1.45% 0.00% 0.50% 0.05% 0.00% 0.00% 0.42% 24.00% 16.27% 24.42% 7.33% 6.25% 15.00% 3.31% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
AVANCE TRIMESTRAL PROGRAMADO ACUMULADO (%) 1.45% 1.45% 1.95% 2.00% 2.00% 2.00% 2.42% 26.42% 42.69% 67.10% 74.44% 80.69% 95.69% 99.00% 99.00% 99.00% 99.00% 99.00% 99.00% 99.00% 99.00% 99.00% 99.00% 99.00% 99.00% 99.00% 99.00% 99.00% 99.00%
Nota :
Trimestre : Periodo comprendido entre, Enero-Marzo (1º); Abril-Junio (2º); Julio-Setiembre (3º) y Octubre-Diciembre (4º).
Los componentes y actividades deben estar conforme a la propuesta seleccionada o ficha del banco del proyecto.
El avance físico programado para cada actividad debe ser expresado en porcentaje (%).
En la elaboración del Expediente Técnico / Estudio Definitivo debe considerarse el tiempo de la selección del consultor / contratista.
Trimestre Trimestre Trimestre Trimestre Trimestre Trimestre Trimestre Trimestre Trimestre Trimestre
1º (%) 2º (%) 3º (%) 4º (%) 1º (%) 2º (%) 3º (%) 4º (%) 1º (%) 2º (%)
1.00% 1.00%
50.00% 50.00%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.50% 0.50%
99.00% 99.00% 99.00% 99.00% 99.00% 99.00% 99.00% 99.00% 99.50% 100.00%
FORMATO Nº 05-B
PLAN DE EJECUCIÓN FÍSICA Y FINANCIERA DE PROYECTO
B. CRONOGRAMA DE EJECUCIÓN FINANCIERA
NOMBRE DEL PIP : CONSTRUCCION E IMPLEMENTACION DE CENTROS VIRTUALES PILOTO PARA EL LOGRO DEL APRENDIZAJE DE CONTENIDOS CURRICULARES EN EL NIVEL SECUNDARIO - REGION APURIMAC
N° SNIP: 90748
REGIÓN: APURIMAC MODALIDAD DE EJECUCIÓN DEL DIRECTA INDIRECTA
PROVINCIA: MULTIPROVINCIAL PIP( Marcar X): X
DISTRITO: MULTIDISTRITAL
NOMBRE DEL PRESIDENTE REGIONAL
TOTAL 0 0 13,927 9,464 1,200 0 9,665 2,031,762 1,389,964 299,770 415,887 326,225 2,345,459 0 3,000 300,000 31,301 0 0 0 0 0 0 0 0 0 0
AVANCE TRIMESTRAL PROGRAMADO c= (a+b) 0 0 13,927 9,464 1,200 0 9,665 2,031,762 1,389,964 299,770 415,887 326,225 2,345,459 0 3,000 300,000 31,301 0 0 0 0 0 0 0 0 0 0
AVANCE TRIMESTRAL ACUMULADO 0 0 13,927 23,391 24,591 24,591 34,256 2,066,018 3,455,982 3,755,752 4,171,640 4,497,865 6,843,324 6,843,324 6,846,324 7,146,324 7,177,625 7,177,625 7,177,625 7,177,625 7,177,625 7,177,625 7,177,625 7,177,625 7,177,625 7,177,625 7,177,625
AVANCE TRIMESTRAL PROGRAMADO (%) 0% 0% 0.19% 0.13% 0.02% 0% 0.13% 28% 19% 4% 6% 5% 33% 0% 0.04% 4% 0.44% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
AVANCE PROGRAMADO ACUMULADO ( %) 0% 0% 0% 0% 0% 0% 0% 29% 48% 52% 58% 63% 95% 95% 95% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
FUENTE DE FINANCIAMIENTO 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 TOTAL
FONIPREL 0 0 1,752,875 2,990,176 332,129 0 0 0 0 0 0 5,075,180
GR 0 24,591 1,678,516 397,166 2,172 0 0 0 0 0 0 2,102,445
GL
Otros
COSTO TOTAL 0 24,591 3,431,391 3,387,342 334,301 0 0 0 0 0 0 7,177,625
Nota.-
Trimestre : Periodo comprendido entre, Enero-Marzo (1º); Abril-Junio (2º); Julio-Setiembre (3º) y Octubre-Diciembre (4º).
Los importes a colocar en el cuadro de avance financiero contendrán los costos totales. Firma y Sello del Presidente Regional
8
FORMATO Nº 05-B
FÍSICA Y FINANCIERA DE PROYECTO
MA DE EJECUCIÓN FINANCIERA
PRESUPUESTO
2016 2017 2018 2019 TOTAL
PROGRAMADO
(S/.)
Trimestre Trimestre Trimestre Trimestre Trimestre Trimestre Trimestre Trimestre Trimestre Trimestre
Trimestre 3º Trimestre 4º
1º 2º 3º 4º 1º 2º 3º 4º 1º 2º
44,334.30
4,214,871.26
36,118.45
36,118.45
133,602.00
2,177,956.12
147,484.10
124,072.50
25,740.00
157,865.50
6,542.80
72,919.22
0 0 0 0 0 0 0 0 0 0 0 0 7,177,625
0 0 0 0 0 0 0 0 0 0 0 0 5,075,180
0 0 0 0 0 0 0 0 0 0 0 0 2,102,445
0 0 0 0 0 0 0 0 0 0 0 0 7,177,625
7,177,625 7,177,625 7,177,625 7,177,625 7,177,625 7,177,625 7,177,625 7,177,625 7,177,625 7,177,625 7,177,625 7,177,625 7,177,625
0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 100%
100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%