Sunteți pe pagina 1din 8

PROJECT: TEMPORARY WORKS CAMP & INFRASTRUCTURE WORKS, RAPID

JOB SAFETY ANALYSIS

PROJECT: TEMPORARY WORKS ACTIVITY : Construction of U-Drain PREPARED BY : Chung May Lynn
CAMP & INFRASTRUCTURE
WORKS, RAPID REV. NO : 00 REVIEWED BY :
LOCATION : Package 20Ai DATE : PAGES : 1 of 8 APPROVED BY:

Probable Hazards Risk Assessment


No. Job sequence / Steps Consequences Risk Control Responsibility
Identified P S Rating
1. Mobilization of plant and  Movement of Serious injuries 3 4 12  Ensure traffic management in order  Project Manager
machineries to the site machinery/ Fatality with traffic controller assistance  Construction Manager
contact with Property damage  Ensure adequate working clearance  SH Officer/ Supervisor
machinery space  Traffic Management
 Poor access to  Competent machinery operator/ Officer / Supervisor
the designated driver  Project Engineer
working area  Apply vehicle, plant, equipment,  Site Supervisor
 Insufficient of machinery inspections  Machinery operator/
traffic  Good physical condition of vehicle, supplier
management plant, equipment, machinery  Workers / helpers
equipment  Machinery must be inspected and
approved before start work
 Machinery with valid insurance
coverage
 Plant & machinery shall be
equipped and comply with all
authorities and client’s
requirement

 Ensure Safe Working Load is


 Lifting Struck by falling 3 4 12 followed
materials objects
 Loads slung correctly
using crane Struck by struck
 Personnel kept clear during crane
objects
operation
Crane overturn
 Apply PTW
PROJECT: TEMPORARY WORKS CAMP & INFRASTRUCTURE WORKS, RAPID

JOB SAFETY ANALYSIS

PROJECT: TEMPORARY WORKS ACTIVITY : Construction of U-Drain PREPARED BY : Chung May Lynn
CAMP & INFRASTRUCTURE
WORKS, RAPID REV. NO : 00 REVIEWED BY :
LOCATION : Package 20Ai DATE : PAGES : 2 of 8 APPROVED BY:

Probable Hazards Risk Assessment


No. Job sequence / Steps Consequences Risk Control Responsibility
Identified P S Rating
 Incompetent Serious injuries 4 4 16  Operators shall have valid license/  Incompetent
machinery Fatality competency machinery operator
operator Property damage  Operator shall have proper training
records
 Operator shall be physically and
mentally fit to perform works
2. Delivery of work materials  Movement of Serious injuries 3 4 12  Ensure traffic management in order  Project Manager
to site machinery/ Fatality with traffic controller assistance  Construction Manager
contact with Property damage  Ensure adequate working clearance  SH Officer/ Supervisor
machinery space  Traffic Management
 Insufficient of Officer / Supervisor
traffic  Site Supervisor
management  Ensure Safe Working is followed
equipment  Loads slung correctly
 Personnel kept clear during crane
 Unloading / Struck by falling 3 4 12 operation  Machinery operator/
lifting objects  Apply PTW supplier
materials Struck by struck
using crane objects  Operators shall have valid license/
Crane overturn competency
 Operator shall have proper training
 Incompetent Serious injuries 4 4 16 records  Incompetent
machinery Fatality  Operator shall be physically and machinery operator
operator Property damage mentally fit to perform works
PROJECT: TEMPORARY WORKS CAMP & INFRASTRUCTURE WORKS, RAPID

JOB SAFETY ANALYSIS

PROJECT: TEMPORARY WORKS ACTIVITY : Construction of U-Drain PREPARED BY : Chung May Lynn
CAMP & INFRASTRUCTURE
WORKS, RAPID REV. NO : 00 REVIEWED BY :
LOCATION : Package 20Ai DATE : PAGES : 3 of 8 APPROVED BY:

Probable Hazards Risk Assessment


No. Job sequence / Steps Consequences Risk Control Responsibility
Identified P S Rating
3. Preliminary Survey  Movement of Serious injuries 4 4 16  Wear high visibility vest with  Project Manager
vehicles / Fatality reflector  Construction Manager
traffic along  Walking facing incoming traffic flow  SH Officer/ Supervisor
highway / / inside guard rail  Traffic Management
road  Placement of traffic / warning Officer / Supervisor
signage  Project Engineer
 Apply and obtain PTW prior to work  Site Supervisor
 Practice buddy system (min of 2  Surveyor
Serious injuries 4 3 12 persons)  Workers / helpers
 Biological Fatality  Standby emergency facility/ vehicle
hazard (bitten  Notify respective person in charge
by fauna) (ie Project Manager) before start
 Strike by work
lightning  Stop work during bad weather
 Provide proper and safe rest area

4. Excavation Works  Contact with Serious injuries 4 2 8  To perform mapping and marking  Project Manager
existing Fatality of utilities area  Construction Manager
utilities/ Property damage  Obtain approval from utilities  SH Officer/ Supervisor
services provider/ owner before start work  Project Engineer
 If necessary relocation of utilities  Site Supervisor
are carried out  Machinery operator
 Workers / helpers
PROJECT: TEMPORARY WORKS CAMP & INFRASTRUCTURE WORKS, RAPID

JOB SAFETY ANALYSIS

PROJECT: TEMPORARY WORKS ACTIVITY : Construction of U-Drain PREPARED BY : Chung May Lynn
CAMP & INFRASTRUCTURE
WORKS, RAPID REV. NO : 00 REVIEWED BY :
LOCATION : Package 20Ai DATE : PAGES : 4 of 8 APPROVED BY:

Probable Hazards Risk Assessment


No. Job sequence / Steps Consequences Risk Control Responsibility
Identified P S Rating
 Movement of Serious injuries 3 4 12  Ensure traffic management in order  Project Manager
machinery/ Fatality with traffic controller assistance  Construction Manager
contact with Property damage  Ensure adequate working clearance  SH Officer/ Supervisor
machinery space  Traffic Management
 Competent machinery operator/ Officer / Supervisor
driver  Project Engineer
 Apply PTW  Site Supervisor
 Machinery must be inspected and  Machinery operator
approved before start work  Workers / helpers
 Machinery with valid insurance
coverage
 machinery shall be equipped and
comply with all authorities and
client’s requirement
 Inadequate Serious injuries 3 4 12  Ensure machinery do not carry out  Site Supervisor
machinery for Fatality work more than its capacity  Machinery operator
excavation Property damage  Competent machinery operator
 Fall of person Injury 3 4 12  Installation of safety barrier  Project Manager
into Fatality surrounding excavation area for  Construction Manager
excavation pit/ depth >1.0m  SH Officer/ Supervisor
area  Put up safety / warning signage  Project Engineer
 Excavation shall be consider as  Site Supervisor
restricted work area
PROJECT: TEMPORARY WORKS CAMP & INFRASTRUCTURE WORKS, RAPID

JOB SAFETY ANALYSIS

PROJECT: TEMPORARY WORKS ACTIVITY : Construction of U-Drain PREPARED BY : Chung May Lynn
CAMP & INFRASTRUCTURE
WORKS, RAPID REV. NO : 00 REVIEWED BY :
LOCATION : Package 20Ai DATE : PAGES : 5 of 8 APPROVED BY:

Probable Hazards Risk Assessment


No. Job sequence / Steps Consequences Risk Control Responsibility
Identified P S Rating
 Failure of Engulfment hazard 4 4 16  Ensure safe degree of slope  Project Manager
excavate slope Topple of machinery cutting/ platform  Construction Manager
 Deep excavation shall provide  SH Officer/ Supervisor
temporary work ie shoring  Project Engineer
 Safe distance from machinery to  Site Supervisor
excavated area  Machinery operator
 Excavated earth to be pile  Workers / helpers
minimum of 3m from the slope
 Machinery shall be sit on top of
steel plate when perform works at
weak GROUND
 To properly level the ground before
machinery start excavation works
5. Laying of bedding  Movement of Serious injuries 3 4 12  Ensure traffic management in order  Project Manager
materials machinery/ Fatality with traffic controller assistance  Construction Manager
contact with  Ensure adequate working clearance  SH Officer/ Supervisor
machinery space  Traffic Management
 Competent machinery operator Officer / Supervisor
 Apply PTW  Project Engineer
 Machinery must be inspected and  Site Supervisor
approved before start work  Machinery operator
 Machinery with valid insurance  Workers / helpers
coverage
 machinery shall be equipped and
comply with all authorities and
client’s requirement
PROJECT: TEMPORARY WORKS CAMP & INFRASTRUCTURE WORKS, RAPID

JOB SAFETY ANALYSIS

PROJECT: TEMPORARY WORKS ACTIVITY : Construction of U-Drain PREPARED BY : Chung May Lynn
CAMP & INFRASTRUCTURE
WORKS, RAPID REV. NO : 00 REVIEWED BY :
LOCATION : Package 20Ai DATE : PAGES : 6 of 8 APPROVED BY:

Probable Hazards Risk Assessment


No. Job sequence / Steps Consequences Risk Control Responsibility
Identified P S Rating
 Inadequate Serious injuries 3 4 12  Ensure machinery do not carry out  Site Supervisor
machinery for Fatality work more than its capacity  Machinery operator
excavation Property damage  Competent machinery operator

 Fall of person Injury 3 4 12  Installation of safety barrier  Project Manager


into Fatality surrounding excavation area for  Construction Manager
excavation pit/ depth >1.0m  SH Officer/ Supervisor
area  Put up safety / warning signage  Project Engineer
 Excavation shall be consider as  Site Supervisor
restricted work area
6. Installation of U-Drain  Lifting Struck by falling 3 4 12  Ensure Safe Working Load is  Project Manager
materials objects followed  Construction Manager
using crane Struck by struck  Loads slung correctly  SH Officer/ Supervisor
objects  Personnel kept clear during crane  Project Engineer
operation  Site Supervisor
  Machinery operator
 Movement of Serious injuries 3 4 12  Ensure traffic management in order  Project Manager
machinery/ Fatality with traffic controller assistance  Construction Manager
contact with  Ensure adequate working clearance  SH Officer/ Supervisor
machinery space  Traffic Management
 Competent machinery operator Officer / Supervisor
 Apply PTW  Project Engineer
 Machinery must be inspected and  Site Supervisor
PROJECT: TEMPORARY WORKS CAMP & INFRASTRUCTURE WORKS, RAPID

JOB SAFETY ANALYSIS

PROJECT: TEMPORARY WORKS ACTIVITY : Construction of U-Drain PREPARED BY : Chung May Lynn
CAMP & INFRASTRUCTURE
WORKS, RAPID REV. NO : 00 REVIEWED BY :
LOCATION : Package 20Ai DATE : PAGES : 7 of 8 APPROVED BY:

Probable Hazards Risk Assessment


No. Job sequence / Steps Consequences Risk Control Responsibility
Identified P S Rating
approved before start work  Machinery operator
 Machinery with valid insurance  Workers / helpers
coverage
 machinery shall be equipped and
comply with all authorities and
client’s requirement
 Fall of person Injury 3 4 12  Installation of safety barrier  Project Manager
into Fatality surrounding excavation area for  Construction Manager
excavation pit/ depth >1.0m  SH Officer/ Supervisor
area  Put up safety / warning signage  Project Engineer
 Excavation shall be consider as  Site Supervisor
restricted work area
7. Backfilling  Movement of Serious injuries 3 4 12  Ensure traffic management in order  Project Manager
machinery/ Fatality with traffic controller assistance  Construction Manager
contact with  Ensure adequate working clearance  SH Officer/ Supervisor
machinery space  Traffic Management
 Competent machinery operator Officer / Supervisor
 Apply PTW  Project Engineer
 Machinery must be inspected and  Site Supervisor
approved before start work  Machinery operator
 Machinery with valid insurance  Workers / helpers
coverage
 machinery shall be equipped and
comply with all authorities and
client’s requirement
PROJECT: TEMPORARY WORKS CAMP & INFRASTRUCTURE WORKS, RAPID

JOB SAFETY ANALYSIS

PROJECT: TEMPORARY WORKS ACTIVITY : Construction of U-Drain PREPARED BY : Chung May Lynn
CAMP & INFRASTRUCTURE
WORKS, RAPID REV. NO : 00 REVIEWED BY :
LOCATION : Package 20Ai DATE : PAGES : 8 of 8 APPROVED BY:

Probable Hazards Risk Assessment


No. Job sequence / Steps Consequences Risk Control Responsibility
Identified P S Rating
 Fall of person Injury 3 4 12  Installation of safety barrier  Project Manager
into Fatality surrounding excavation area for  Construction Manager
excavation pit/ depth >1.0m  SH Officer/ Supervisor
area  Put up safety / warning signage  Project Engineer
 Excavation shall be consider as  Site Supervisor
restricted work area

S-ar putea să vă placă și