PROPOSED BRINELINE FOR PUTATAN WATER

TREATMENT PLANT 2

CONTRACT NO. : WS-17-WTP-03

1
A.C. MOJARES
CONSTRUCTION,
INC.
2
PERMITS STATUS REMARKS

BRGY Released Ok

MTMB Released Ok

ESC Released Ok

CITY Submitted all document On process by Engr.


requirement to city engg Elizabeth
office
DPWH Released Ok

LLDA Requested a copy of a new MWSI to provide for the


Discharge Permit copy
MMDA
PROJECT LOCATION
PROP. 630mmØ
STD. PIPELAYING
PROP. 630mmØ
TRENCHLESS
ENTRY/EXIT PIT
UNDERWATER
PIPELAYING
HORIZONTAL DIRECTIONAL DRILLING
HDD Machine
 Brand/Supplier : AMERICAN AUGERS
 Model/ Machine Type : DD10 (SN:DD10-010400)
 Max. Jacking/ Drilling Force : 95407lb or 425 kN
 Max. Length : 300 meters
 Work Rate/ Const. Durations : 30 c.d.
 Applicable Soil Conditions : clay, silt , sandy
hard adobe, solid rock
 Staging Area : 6.00m x 3.50m
EXPERIENCE OF TRENCHLESS
OPERATOR
 DARI Trenchless was established since 2001
 Trenchless Operator : DANIEL I. PATRICIO
 Trenchless Operator : GIOVANNI RICO
 Work Experience : 16 years
 Project Involvement & Completed : Drilling Engineer
 Types of Soils Encountered : All types (Clay, Sandy,
Silt, Gravel, Medium to
Hard Rock)
 Length of Trenchless Pipelaying Driven: 2km to 12km
STAGING AREA (approx. 6m x 3.5m)
ENTRY/EXIT PIT
STAGING AREA (approx. 6m x 3.5m)
ENTRY/EXIT PIT
TRENCHLESS METHODOLOGY
 Permits and Right of Way acquisition from the National
Government Agencies (such as the Department of Public
Works & Highways, MMDA, etc.); Local Government Units,
Public Utility Companies (Water Districts, Globe/Smart/Digitel,
PLDT/Eastern, etc.) and the Barangay Units concerned;

 Coordination with the Heads of National Government


Agencies and Local Government Executives, Local Barangay
Officials and affected Private Property Owners and the
Technical Staff of the affected Public Utility Companies
regarding project implementation;

 Provision of Construction Health and Safety Program (Project


ID, Traffic Advisory, Board-ups, Safety Signage, PPE, etc.)
1. SURVEYING WORKS

 Delineation of the exact location, depth, alignment and alignment of the


proposed pathway for the 630mm HDPE Pipeline in order to avoid any existing
underground utilities and structures;
 Determination of the prevailing soil-type conditions along NIA Road based on
the Geotechnical Analysis Report/ Soil Testing;
 Survey of the Road Surface elevations along the proposed drilling pathway
with 1-meter reference point along NIA Road;
 Test Pits along the proposed drilling pathway at NIA Road to determine, actual
location, depth, alignment of existing underground public utilities;

26
 Supply and Delivery of 630mm diameter HDPE Pipes SDR 13.6 at
least Three hundred Eighty Five (385) meters HDD total length;

 Provision of Butt-fusion Machines capable to butt-fuse 630mmØ


size of HDPE pipes;

 Provision of Technicians or Operators for the Butt-Fusion Machines;

 Provision of Generator Sets for the power supply of the Butt-fusion


Welding machines;

 Supply and Delivery of All Fittings (630mm HDPE Stub Flange End
Transition Fitting, Flanges, Rubber gaskets, Bolts & Nuts, etc.) for
Hydro Tests and Interconnection;
2. EXCAVATION OF ENTRY PIT AND EXIT PIT

 Excavation of HDD Entry and Exit Pits (3.0-m L x 2.0-m W)


 Depth of Excavation (2.0m to 3.0m)
31
ENTRY/EXIT PIT
LOCATION 1

PROP. ENTRY/EXIT PIT


ENTRY/EXIT PIT
LOCATION 2

PROP. ENTRY/EXIT PIT


2. EXCAVATION OF ENTRY PIT AND EXIT PIT
 Placement of MWSI-approved board-ups, bollards, and
directional signs for safety at the drilling site;

 Set-up and preparation of the HDD Machine and HDD Support


Equipment at the drilling site;

 Calibration and Settings of the HDD Transmitter & Receiver


devices;

 Procurement of Water Supply for continuous use in HDD


operations;

 Formulation of Bentonite mud with Drilling fluid Additives to be


suitable for the prevailing soft to hard adobe soil type
conditions at the drilling sites;
3. MOB. OF HDD MACHINE, HDD SUPPORT EQUIPMENT,
LOGISTICS, HDD DRILLING TEAM AND TECHNICAL SUPPORT

36
4. BUTT-FUSION OF HDPE PIPES

Butt fusion Machine

39
4. BUTT-FUSION OF HDPE PIPES
4. BUTT-FUSION OF HDPE PIPES
4. BUTT-FUSION OF HDPE PIPES
4. BUTT-FUSION OF HDPE PIPES
 Pilot Drilling for two (2) Drill shots of 630mmØ HDPE pipes
SDR 13.6 from the designated HDD Entry Pits crossing
under and along NIA Road to the target HDD Exit Pits at
the given HDD lengths above;

 Pullback Reaming procedure to enlarge the pilot tunnel


holes of the two (2) drill shots in order to insert the fused
630mmØ HDPE pipeline per tunnel hole;

Simultaneously during Pullback Reaming procedure, the


1st-run of the 630mm HDPE pipeline is being butt-fused
near the Exit Pit;
 Removal of excess soil materials during pipe reaming for
hauling and disposals;

 Continuous dewatering of the entry and exit pits are


done during the entire pipe reaming procedure;

 Hauling and Disposal of sludge/soil materials during Pipe


Reaming operations;

 HDPE Pipeline Pulling for insertion of the fused 630mmØ


HDPE pipeline into the tunnel hole per drill shot from
target HDD Exit Pit crossing under and along NIA Road to
the designated HDD Entry Pit;
5. HDD WORKS SUCH AS PILOT DRILLING PROCESS FROM
TEMPORARY HDD

HDD Rig Machine

Pilot Drilling

46
5. HDD WORKS SUCH AS PILOT DRILLING PROCESS FROM
TEMPORARY HDD
5. HDD WORKS SUCH AS PILOT DRILLING PROCESS FROM
TEMPORARY HDD
5. HDD WORKS SUCH AS PULL-BACK REAMING PROCESS
FROM TEMPORARY HDD
5. HDD WORKS SUCH AS PULL-BACK REAMING PROCESS
FROM TEMPORARY HDD

50
5. HDD WORKS SUCH AS PULL-BACK REAMING PROCESS
FROM TEMPORARY HDD

51
5. HDD WORKS SUCH AS PULL-BACK REAMING PROCESS
FROM TEMPORARY HDD

52
5. HDD WORKS SUCH AS PULL-BACK REAMING PROCESS
FROM TEMPORARY HDD

53
5. HDD WORKS SUCH AS PULL-BACK REAMING PROCESS
FROM TEMPORARY HDD

54
5. HDD WORKS SUCH AS PULL-BACK REAMING PROCESS
FROM TEMPORARY HDD

55
5. HDD WORKS SUCH AS PULL-BACK REAMING PROCESS
FROM TEMPORARY HDD

Change of Pilot Bit/Reamer

56
5. HDD WORKS SUCH AS PULL-BACK REAMING PROCESS
FROM TEMPORARY HDD

Start of back reaming

57
5. HDD WORKS SUCH AS PULL-BACK REAMING PROCESS
FROM TEMPORARY HDD
5. HDD WORKS SUCH AS PIPE PULLING
5. HDD WORKS SUCH AS PIPE PULLING
5. HDD WORKS SUCH AS PIPE PULLING
5. HDD WORKS SUCH AS PIPE PULLING
5. HDD WORKS SUCH AS PIPE PULLING
5. HDD WORKS SUCH AS PULL-BACK REAMING PROCESS
FROM TEMPORARY HDD

Installation of HDPE Pipe

64
5. HDD WORKS SUCH AS PULL-BACK REAMING PROCESS
FROM TEMPORARY HDD

65
5. HDD WORKS SUCH AS PULL-BACK REAMING PROCESS
FROM TEMPORARY HDD

66
5. HDD WORKS SUCH AS PULL-BACK REAMING PROCESS
FROM TEMPORARY HDD

67
5. HDD WORKS SUCH AS PULL-BACK REAMING PROCESS
FROM TEMPORARY HDD

68
6. INSTALLATION OF TEMPORARY END CAP

69
6. INSTALLATION OF TEMPORARY END CAP

Installation of End cap for Hydro-testing

70
7. TESTING OF PIPES

Hydro-testing Activity

74
7. TESTING OF PIPES

Excavation of soil to straighten the pipe

75
8. REMOVAL OF TEMPORARY END CAP AFTER
TESTING OF PIPES

Removal of end cap

76
77
9. INSTALLATION OF STUB FLANGE END TRANSITION FITTINGS

Stub Flange Transition Fitting

78
9. INSTALLATION OF STUB FLANGE TRANSITION FITTINGS

79
10. BACKFILLING

Sand Filling

80
11. RESTORATION

Compacting using road roller

Application of Sub-Base Course and Base-Course

81
11. RESTORATION

82
11. RESTORATION

Restoration of Test pit

83
11. RESTORATION

84
SIMILAR PROJECT

Contract No. : E16-0273-02- ESWWRL-SJM-M13

Project Title : Design and Construction of Sta. Ana Sewer Network


and Lift Station Upgrade

Type of Project : Trenchless Pipe Laying (Sewer Line)

Scope of Work : Laying of 200mmØ HDPE, 2606m total length

Client : Manila Water Company, Inc.

Contract Value : Php 98,479,498.97


SIMILAR PROJECT

Contract No. : SS-12-06

Project Title : Proposed Sewerage Interceptor and Ancillary Works


for Talayan STP

Type of Project : Trenchless & Open Trench Pipe Laying (Sewer Line)

Scope of Work : Laying of 200mmØ HDPE & 400mmØ

Client : Maynilad Water Services, Inc.

Contract Value : Php 19,431,872.13