Egbaoma Gas Processing Plant - New Level IV Schedule-latest 16-Jul-15 15:25

Activity ID Activity Name Original Start Finish 2014 2015 2016


Duration Q3
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
14234-3 Eg
Egbaoma Gas Processing Plant - New 586 05-Aug-14 A 04-Apr-16 04-Apr-16,

14234-3.Contract About Contract


14234-3.Co 459 05-Aug-14 A 04-Apr-16 04-Apr-16,
A21270 Kick Off Meeting 0 05-Aug-14 A Kick Off Meeting, 05-Aug-14 A
A21280 Commencement of Project Work 0 05-Aug-14 A Commencement of Project Work, 05-Aug-14 A
A21790 HAZOP 8 17-Dec-14 A 24-Dec-14 A HAZOP
A21800 Engineering Completion 0 21-Sep-15 Engineering Completion,
A21810 Procurement Completion 0 26-Oct-15 Procurement Completion,
A21820 Site Modification, Construction & Erection Works Completion 0 24-Feb-16 Site Modification
A21830 Pre-Commissioning & Commissioning Works Completion 0 29-Feb-16 Pre-Commissio
A21840 First Gas In & Successful Test Run 0 29-Feb-16 First Gas In &
A21940 Performance Test 3 29-Feb-16 03-Mar-16 Performance T
A21950 Reliability Test 30 03-Mar-16 04-Apr-16 Reliability T
A21960 Project Closing 0 04-Apr-16 Project Clo
14234-3.Engineering Engineering
14234-3.En 398 18-Aug-14 A 02-Oct-15 02-Oct-15, 14234-3.Engineering

14234-3.Engineering.1 Process
14234-3.En 341 18-Aug-14 A 19-Apr-15 A 19-Apr-15 A, 14234-3.Engineering.1 Process
A21350 Process Design Completion 0 19-Apr-15 A Process Design Completion,
14234-3.E
14234-3.Engineering.1.1 Documents and Reports 341 18-Aug-14 A 19-Apr-15 A 19-Apr-15 A, 14234-3.Engineering.1.1 Documents a
14234-3.Engineering.1.2 Drawings
14234-3.E 326 27-Aug-14 A 25-Mar-15 A 25-Mar-15 A, 14234-3.Engineering.1.2 Drawings
14234-3.Engineering.2 Mechanical Static
14234-3.En 377 21-Aug-14 A 15-Apr-15 A 15-Apr-15 A, 14234-3.Engineering.2 Mechanical Stat
A21360 Mechanical Static Design Completion 0 15-Apr-15 A Mechanical Static Design Completion,
14234-3.E
14234-3.Engineering.2.2 Design Calculation Book 286 17-Sep-14 A 15-Apr-15 A 15-Apr-15 A, 14234-3.Engineering.2.2 Design Calcul
14234-3.Engineering.2.3
14234-3.E Drawings 367 21-Aug-14 A 09-Apr-15 A 09-Apr-15 A, 14234-3.Engineering.2.3 Drawings
14234-3.Engineering.2.4
14234-3.E Datasheet 295 17-Sep-14 A 09-Apr-15 A 09-Apr-15 A, 14234-3.Engineering.2.4 Datasheet
14234-3.Engineering.2.1
14234-3.E Documents 277 11-Sep-14 A 10-Mar-15 A 10-Mar-15 A, 14234-3.Engineering.2.1 Documents
14234-3.Engineering.4 Piping
14234-3.En 366 11-Sep-14 A 04-May-15 A 04-May-15 A, 14234-3.Engineering.4 Piping
A21380 Piping Design Start 0 11-Sep-14 A Piping Design Start, 11-Sep-14 A
A21670 Piping Design Completion 0 30-Mar-15 A Piping Design Completion,
14234-3.E
14234-3.Engineering.4.3 Skid General Arrangement Drawing 366 02-Oct-14 A 30-Mar-15 A 30-Mar-15 A, 14234-3.Engineering.4.3 Skid General Ar
14234-3.Engineering.4.1 Documents
14234-3.E 81 03-Nov-14 A 04-Feb-15 A 04-Feb-15 A, 14234-3.Engineering.4.1 Documents
14234-3.Engineering.4.2 General Drawings
14234-3.E 292 11-Sep-14 A 04-May-15 A 04-May-15 A, 14234-3.Engineering.4.2 General Dr
14234-3.Engineering.3 Mechanical Rotating
14234-3.En 177 06-Jan-15 A 19-Apr-15 A 19-Apr-15 A, 14234-3.Engineering.3 Mechanical Rot
A21370 Mechanical Rotating Design Completion 0 19-Apr-15 A Mechanical Rotating Design Completion,
14234-3.Engineering.3.1 Datasheets
14234-3.E 177 06-Jan-15 A 19-Apr-15 A 19-Apr-15 A, 14234-3.Engineering.3.1 Datasheets
14234-3.Engineering.5 Electrical
14234-3.En 202 02-Oct-14 A 02-Oct-15 A 02-Oct-15 A, 14234-3.Engineerin
A21390 Electrical System Design Completion 0 14-Apr-15 A Electrical System Design Completion,
14234-3.E
14234-3.Engineering.5.2 Documents 194 02-Oct-14 A 02-Oct-15 A 02-Oct-15 A, 14234-3.Engineerin
14234-3.Engineering.5.1 Data Sheets
14234-3.E 101 07-Jan-15 A 03-Feb-15 A 03-Feb-15 A, 14234-3.Engineering.5.1 Data Sheets
14234-3.Engineering.5.3 Drawings
14234-3.E 103 26-Jan-15 A 14-Apr-15 A 14-Apr-15 A, 14234-3.Engineering.5.3 Drawings
14234-3.Engineering.6 Instrumentation
14234-3.En 314 05-Nov-14 A 09-Jul-15 A 09-Jul-15 A, 14234-3.Engineering.6 Instrum
A21400 Instrumentation System Design Completion 0 15-Apr-15 A Instrumentation System Design Completion,
14234-3.E
14234-3.Engineering.6.2 Documents 186 05-Nov-14 A 09-Jul-15 A 09-Jul-15 A, 14234-3.Engineering.6.2 Docu
14234-3.Engineering.6.1 Data Sheets
14234-3.E 176 07-Jan-15 A 12-May-15 A 12-May-15 A, 14234-3.Engineering.6.1 Data Shee
14234-3.Engineering.6.30 Layouts & Drawings
14234-3.E 183 25-Feb-15 A 22-Apr-15 A 22-Apr-15 A, 14234-3.Engineering.6.30 Layouts & D
14234-3.Engineering.7 Civil & Structure
14234-3.En 360 21-Aug-14 A 12-Aug-15 12-Aug-15, 14234-3.Engineering.7 Civ

Actual Level of Effort Remaining Work Page 1 of 7 TASK filter: All Activities
Actual Work Critical Remaini... © Oracle Corporation
Egbaoma Gas Processing Plant - New Level IV Schedule-latest 16-Jul-15 15:25
Activity ID Activity Name Original Start Finish 2014 2015 2016
Duration Q3
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
A21410 Civil & Structure Design Completion 0 12-Aug-15 Civil & Structure Design Completion,
14234-3.E
14234-3.Engineering.7.2 Drawings 360 21-Aug-14 A 12-Aug-15 12-Aug-15, 14234-3.Engineering.7.2 D
14234-3.Engineering.7.1 Document
14234-3.E 78 03-Nov-14 A 29-Jan-15 A 29-Jan-15 A, 14234-3.Engineering.7.1 Document
14234-3.Engineering.8 HSE
14234-3.En 306 20-Aug-14 A 22-Jun-15 A 22-Jun-15 A, 14234-3.Engineering.8 HSE
A21420 HSE Documentation Completion 0 22-Jun-15 A HSE Documentation Completion,
14234-3.Engineering.8.1 Document
14234-3.E 306 20-Aug-14 A 22-Jun-15 A 22-Jun-15 A, 14234-3.Engineering.8.1 Docum
14234-3.Engineering.9 QAQC
14234-3.En 147 20-Aug-14 A 10-Mar-15 A 10-Mar-15 A, 14234-3.Engineering.9 QAQC
A21430 QAQC Documentation Completion 0 10-Mar-15 A QAQC Documentation Completion,
14234-3.Engineering.9.1 Document
14234-3.E 59 20-Aug-14 A 10-Mar-15 A 10-Mar-15 A, 14234-3.Engineering.9.1 Document
14234-3.Engineering.10 Commissioning
14234-3.En 244 05-Nov-14 A 21-Sep-15 21-Sep-15, 14234-3.Engineering.1
A21440 Commissioning Documentation Completion 0 21-Sep-15 Commissioning Documentation Co
14234-3.Engineering.10.1 Documents
14234-3.E 244 05-Nov-14 A 21-Sep-15 21-Sep-15, 14234-3.Engineering.1
14234-3.Engineering.11 General
14234-3.En 194 15-Sep-14 A 25-Mar-15 A 25-Mar-15 A, 14234-3.Engineering.11 General
A21450 General Documentation Completion 0 25-Mar-15 A General Documentation Completion,
14234-3.Engineering.11.1 Documents
14234-3.E 107 15-Sep-14 A 25-Mar-15 A 25-Mar-15 A, 14234-3.Engineering.11.1 Documents
14234-3.Procourment Procurement
14234-3.Pr 310 19-Oct-14 A 26-Oct-15 26-Oct-15, 14234-3.Procourm
A21460 Procurement Completion 0 26-Oct-15 Procurement Completion,
14234-3.Procourment.1 Issuance of PO for major buyout Items
14234-3.Pr 216 19-Oct-14 A 22-Jan-15 A 22-Jan-15 A, 14234-3.Procourment.1 Issuance of PO for majo
A21570 PO Placed for all Major Items 0 22-Jan-15 A PO Placed for all Major Items,
14234-3.P
14234-3.Procourment.1.2 Deethanizer OH Condenser E-401 71 19-Oct-14 A 19-Oct-14 A 19-Oct-14 A, 14234-3.Procourment.1.2 Deethanizer OH Condenser E-40
14234-3.Procourment.1.3 Condensate Stabilization Column C-3001
14234-3.P 7 19-Oct-14 A 19-Oct-14 A 19-Oct-14 A, 14234-3.Procourment.1.3 Condensate Stabilization Column
14234-3.Procourment.1.6 Gas/Gas Exchanger E-300A
14234-3.P 7 19-Oct-14 A 19-Oct-14 A 19-Oct-14 A, 14234-3.Procourment.1.6 Gas/Gas Exchanger E-300A
14234-3.Procourment.1.7 Gas/Gas Exchanger E-300B
14234-3.P 7 19-Oct-14 A 19-Oct-14 A 19-Oct-14 A, 14234-3.Procourment.1.7 Gas/Gas Exchanger E-300B
14234-3.Procourment.1.8 Gas/Liquid Exchanger E-302A
14234-3.P 54 19-Oct-14 A 08-Dec-14 A 08-Dec-14 A, 14234-3.Procourment.1.8 Gas/Liquid Exchanger E-30
14234-3.Procourment.1.10 Regeneration Gas Cooler E-303
14234-3.P 54 19-Oct-14 A 04-Jan-15 A 04-Jan-15 A, 14234-3.Procourment.1.10 Regeneration Gas Coo
14234-3.Procourment.1.11 Water Degassing Boot V-3401
14234-3.P 7 19-Oct-14 A 19-Oct-14 A 19-Oct-14 A, 14234-3.Procourment.1.11 Water Degassing Boot V-3401
14234-3.Procourment.1.12 CPI Separator V-3402
14234-3.P 7 19-Oct-14 A 19-Oct-14 A 19-Oct-14 A, 14234-3.Procourment.1.12 CPI Separator V-3402
14234-3.Procourment.1.13 On Spec Condensate Storage Tank T-3301
14234-3.P 7 21-Jan-15 A 22-Jan-15 A 22-Jan-15 A, 14234-3.Procourment.1.13 On Spec Condensate
14234-3.Procourment.1.14 Off Spec Condensate Storage Tank T-3302
14234-3.P 7 21-Jan-15 A 22-Jan-15 A 22-Jan-15 A, 14234-3.Procourment.1.14 Off Spec Condensate
14234-3.Procourment.1.15 Bulk Materials
14234-3.P 17 08-Dec-14 A 08-Dec-14 A 08-Dec-14 A, 14234-3.Procourment.1.15 Bulk Materials
14234-3.Procourment.1.9 Gas/Liquid Exchanger E-302B
14234-3.P 54 19-Oct-14 A 08-Dec-14 A 08-Dec-14 A, 14234-3.Procourment.1.9 Gas/Liquid Exchanger E-30
14234-3.Procourment.1.1 Chiller E-301
14234-3.P 46 19-Oct-14 A 19-Oct-14 A 19-Oct-14 A, 14234-3.Procourment.1.1 Chiller E-301
14234-3.Procourment.1.5 Condensate Reboiler E-3001
14234-3.P 7 19-Oct-14 A 19-Oct-14 A 19-Oct-14 A, 14234-3.Procourment.1.5 Condensate Reboiler E-3001
14234-3.Procourment.1.4 Propane Receiver V-706
14234-3.P 7 19-Oct-14 A 19-Oct-14 A 19-Oct-14 A, 14234-3.Procourment.1.4 Propane Receiver V-706
14234-3.Procourment.2 Receipt of Head & Shell Materials at SPEC Facility
14234-3.Pr 253 19-Oct-14 A 22-Feb-15 A 22-Feb-15 A, 14234-3.Procourment.2 Receipt of Head & S
A21560 Fabrication Material Received @ SPEC Fabrication Facility 0 22-Feb-15 A Fabrication Material Received @ SPEC Fabrication Facility,
14234-3.P
14234-3.Procourment.2.1 Chiller E-301 17 19-Oct-14 A 02-Dec-14 A 02-Dec-14 A, 14234-3.Procourment.2.1 Chiller E-301
14234-3.Procourment.2.2 Deethanizer OH Condenser E-401
14234-3.P 17 19-Oct-14 A 02-Dec-14 A 02-Dec-14 A, 14234-3.Procourment.2.2 Deethanizer OH Condenser
14234-3.Procourment.2.3 Condensate Stabilization Column C-3001
14234-3.P 17 19-Oct-14 A 02-Dec-14 A 02-Dec-14 A, 14234-3.Procourment.2.3 Condensate Stabilization Co
14234-3.Procourment.2.4 Propane Receiver V-706
14234-3.P 17 19-Oct-14 A 02-Dec-14 A 02-Dec-14 A, 14234-3.Procourment.2.4 Propane Receiver V-706
14234-3.Procourment.2.5 Condensate Reboiler E-3001
14234-3.P 17 19-Oct-14 A 02-Nov-14 A 02-Nov-14 A, 14234-3.Procourment.2.5 Condensate Reboiler E-3001
14234-3.Procourment.2.6 Gas/Gas Exchanger E-300A
14234-3.P 40 19-Oct-14 A 02-Dec-14 A 02-Dec-14 A, 14234-3.Procourment.2.6 Gas/Gas Exchanger E-300A
14234-3.Procourment.2.7 Gas/Gas Exchanger E-300B
14234-3.P 40 19-Oct-14 A 02-Dec-14 A 02-Dec-14 A, 14234-3.Procourment.2.7 Gas/Gas Exchanger E-300B
14234-3.Procourment.2.8 Gas/Liquid Exchanger E-302A
14234-3.P 47 19-Oct-14 A 30-Dec-14 A 30-Dec-14 A, 14234-3.Procourment.2.8 Gas/Liquid Exchanger E
14234-3.Procourment.2.9 Gas/Liquid Exchanger E-302B
14234-3.P 47 19-Oct-14 A 30-Dec-14 A 30-Dec-14 A, 14234-3.Procourment.2.9 Gas/Liquid Exchanger E
14234-3.Procourment.2.10 Regeneration Gas Cooler E-303
14234-3.P 47 19-Oct-14 A 05-Jan-15 A 05-Jan-15 A, 14234-3.Procourment.2.10 Regeneration Gas Coo

Actual Level of Effort Remaining Work Page 2 of 7 TASK filter: All Activities
Actual Work Critical Remaini... © Oracle Corporation
Egbaoma Gas Processing Plant - New Level IV Schedule-latest 16-Jul-15 15:25
Activity ID Activity Name Original Start Finish 2014 2015 2016
Duration Q3
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
14234-3.P
14234-3.Procourment.2.11 Water Degassing Boot V-3401 21 19-Oct-14 A 07-Dec-14 A 07-Dec-14 A, 14234-3.Procourment.2.11 Water Degassing Boot V- 3
14234-3.Procourment.2.12
14234-3.P CPI Separator V-3402 21 19-Oct-14 A 07-Dec-14 A 07-Dec-14 A, 14234-3.Procourment.2.12 CPI Separator V-3402
14234-3.Procourment.2.13
14234-3.P On Spec Condensate Storage Tank T-3301 49 22-Jan-15 A 22-Feb-15 A 22-Feb-15 A, 14234-3.Procourment.2.13 On Spec Conden
14234-3.Procourment.2.14
14234-3.P Off Spec Condensate Storage Tank T-3302 49 22-Jan-15 A 22-Feb-15 A 22-Feb-15 A, 14234-3.Procourment.2.14 Off Spec Conden
14234-3.Procourment.2.15
14234-3.P Bulk Materials 21 08-Dec-14 A 30-Dec-14 A 30-Dec-14 A, 14234-3.Procourment.2.15 Bulk Materials
14234-3.Procourment.3 Successful Vessel Hydro Test
14234-3.Pr 22 02-Apr-15 A 16-Aug-15 16-Aug-15, 14234-3.Procourment.3 S
A21550 Hydrotesting of Vessels Completion 0 16-Aug-15 Hydrotesting of Vessels Completion,
14234-3.P
14234-3.Procourment.3.1 Chiller E-301 1 16-Aug-15 16-Aug-15 16-Aug-15, 14234-3.Procourment.3.1
14234-3.Procourment.3.2 Deethanizer OH Condenser E-401
14234-3.P 1 16-Aug-15 16-Aug-15 16-Aug-15, 14234-3.Procourment.3.2
14234-3.Procourment.3.3 Condensate Stabilization Column C-3001
14234-3.P 1 03-Apr-15 A 03-Apr-15 A 03-Apr-15 A, 14234-3.Procourment.3.3 Condensate S
14234-3.Procourment.3.4 Propane Receiver V-706
14234-3.P 1 03-Apr-15 A 03-Apr-15 A 03-Apr-15 A, 14234-3.Procourment.3.4 Propane Rece
14234-3.Procourment.3.5 Condensate Reboiler E-3001
14234-3.P 1 03-Apr-15 A 03-Apr-15 A 03-Apr-15 A, 14234-3.Procourment.3.5 Condensate R
14234-3.Procourment.3.6 Gas/Gas Exchanger E-300A
14234-3.P 1 16-Aug-15 16-Aug-15 16-Aug-15, 14234-3.Procourment.3.6
14234-3.Procourment.3.7 Gas/Gas Exchanger E-300B
14234-3.P 1 16-Aug-15 16-Aug-15 16-Aug-15, 14234-3.Procourment.3.7
14234-3.Procourment.3.8 Gas/Liquid Exchanger E-302A
14234-3.P 1 16-Aug-15 16-Aug-15 16-Aug-15, 14234-3.Procourment.3.8
14234-3.Procourment.3.9 Gas/Liquid Exchanger E-302B
14234-3.P 1 16-Aug-15 16-Aug-15 16-Aug-15, 14234-3.Procourment.3.9
14234-3.Procourment.3.10 Regeneration Gas Cooler E-303
14234-3.P 1 16-Aug-15 16-Aug-15 16-Aug-15, 14234-3.Procourment.3.10
14234-3.Procourment.3.11 Water Degassing Boot V-3401
14234-3.P 1 02-Apr-15 A 02-Apr-15 A 02-Apr-15 A, 14234-3.Procourment.3.11 Water Degas
14234-3.Procourment.3.12 CPI Separator V-3402
14234-3.P 1 02-Apr-15 A 02-Apr-15 A 02-Apr-15 A, 14234-3.Procourment.3.12 CPI Separato
14234-3.Procourment.4 Equipment FAT at SPEC Facility
14234-3.Pr 41 16-Aug-15 25-Oct-15 25-Oct-15, 14234-3.Procourm
A21540 Equipment FAT Completion 0 25-Oct-15 Equipment FAT Completion,
14234-3.P
14234-3.Procourment.4.1 Gas/Gas Exchanger (E-300A/B) Skid 1 10-Sep-15 13-Sep-15 13-Sep-15, 14234-3.Procourment.4
14234-3.Procourment.4.2
14234-3.P Gas Liquid Exchanger (E-302A/B) Skid 1 27-Aug-15 30-Aug-15 30-Aug-15, 14234-3.Procourment.4.2
14234-3.Procourment.4.3
14234-3.P Regeneration Gas Cooler (E-303) Skid 1 10-Sep-15 13-Sep-15 13-Sep-15, 14234-3.Procourment.4
14234-3.Procourment.4.4
14234-3.P Gas Metering Package 1 25-Oct-15 25-Oct-15 25-Oct-15, 14234-3.Procourm
14234-3.Procourment.4.5
14234-3.P NGL Stabilization Package 1 25-Oct-15 25-Oct-15 25-Oct-15, 14234-3.Procourm
14234-3.Procourment.4.6
14234-3.P NGL Loading Pump Package 1 30-Aug-15 30-Aug-15 30-Aug-15, 14234-3.Procourment.4.6
14234-3.Procourment.4.7
14234-3.P Water Degassing Boot & CPI Separator Package 1 16-Aug-15 16-Aug-15 16-Aug-15, 14234-3.Procourment.4.7
14234-3.Procourment.4.8
14234-3.P ESD/FGS Panel 2 27-Sep-15 28-Sep-15 28-Sep-15, 14234-3.Procourmen
14234-3.Procourment.5 Shipping Readiness of Materials from SPEC Facility
14234-3.Pr 41 17-Aug-15 26-Oct-15 26-Oct-15, 14234-3.Procourm
A21530 Shipping Readiness of Materials @ SPEC Facility 0 26-Oct-15 Shipping Readiness of Materia
14234-3.P
14234-3.Procourment.5.1 Gas/Gas & Gas/Liquid Exchangers Package 2 13-Sep-15 16-Sep-15 16-Sep-15, 14234-3.Procourment.
14234-3.Procourment.5.2
14234-3.P Gas Metering Package 1 26-Oct-15 26-Oct-15 26-Oct-15, 14234-3.Procourm
14234-3.Procourment.5.3
14234-3.P Condensate Stabilization Package 1 26-Oct-15 26-Oct-15 26-Oct-15, 14234-3.Procourm
14234-3.Procourment.5.4
14234-3.P Condensate Loading Pump Package 1 31-Aug-15 31-Aug-15 31-Aug-15, 14234-3.Procourment.5.
14234-3.Procourment.5.5
14234-3.P Water Degassing Boot & CPI Separator Package 1 17-Aug-15 17-Aug-15 17-Aug-15, 14234-3.Procourment.5.5
14234-3.Procourment.5.6
14234-3.P ESD/FGS Panel 1 29-Sep-15 29-Sep-15 29-Sep-15, 14234-3.Procourmen
14234-3.Project Constraints Project Constraints
14234-3.Pr 137 09-Jul-15 27-Nov-15 27-Nov-15, 14234-3.Proje
A23989 Project Activities Resumed 0 09-Jul-15 Project Activities Resumed, 09-Jul-15
A23990 First Shipment Despatch from HFZ 5 15-Aug-15* 20-Aug-15 First Shipment Despatch from HFZ
A24000 First Shipment Receiving on Site 65 20-Aug-15 27-Oct-15 First Shipment Receiving on S
A24040 Overhaul of Compressors & Generators 80 15-Aug-15* 06-Nov-15 Overhaul of Compressors &
A24050 Procurement of MCC Enclosure & Component 5 15-Jul-15* 20-Jul-15 Procurement of MCC Enclosure & Compo
A24060 Material Deliveries, Assembly, & FAT 65 20-Jul-15 25-Sep-15 Material Deliveries, Assembly, & F
A24080 Procurement of Synchornization Controller + Delivery to HFZ 25 15-Aug-15* 10-Sep-15 Procurement of Synchornization Co
A24100 Pumps Receiving in HFZ 45 09-Jul-15 24-Aug-15 Pumps Receiving in HFZ

Actual Level of Effort Remaining Work Page 3 of 7 TASK filter: All Activities
Actual Work Critical Remaini... © Oracle Corporation
Egbaoma Gas Processing Plant - New Level IV Schedule-latest 16-Jul-15 15:25
Activity ID Activity Name Original Start Finish 2014 2015 2016
Duration Q3
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
A24101 Procurement of Commissioning Spare 5 01-Sep-15* 05-Sep-15 Procurement of Commissioning Spa
A24102 Commissioning Spares Receiving In HFZ 25 05-Sep-15 01-Oct-15 Commissioning Spares Receiving
A24150 Procurement of Electrical & Instrumentation Cables 5 30-Jul-15* 04-Aug-15 Procurement of Electrical & Instrumenta
A24160 Electrical & Instrumentation Cables Ex. Works Readiness & Receiving on Site 92 04-Aug-15 07-Nov-15 Electrical & Instrumentation C
A24161 DPR Visit - Hydro for 2nd Lot of Vessels and FAT for 1s t lot Skid Pac kages 14 25-Aug-15* 08-Sep-15 DPR Visit - Hydro for 2nd Lot of Ves
A24162 Punch List Close Out + Shipping Readiness 3 08-Sep-15 11-Sep-15 Punch List Close Out + Shipping Re
A24170 2nd Shipment Dispatch from UAE 5 11-Sep-15 16-Sep-15 2nd Shipment Dispatch from UAE
A24180 2nd Shipment Receiving on Site 50 16-Sep-15 06-Nov-15 2nd Shipment Receiving on S
A24181 DPR Visit - FAT for 2nd Lot of Skid Packages 13 15-Sep-15* 28-Sep-15 DPR Visit - FAT for 2nd Lot of Ski
A24182 Punch List Close Out + Shipping Readiness 3 28-Sep-15 01-Oct-15 Punch List Close Out + Shipping
A24190 3rd Shipment Dispatch from UAE 5 01-Oct-15 07-Oct-15 3rd Shipment Dispatch from UAE
A24200 3rd Shipment Receiving on Site 50 07-Oct-15 27-Nov-15 3rd Shipment Receiving on
14234-3.Construction Site Modification, Construction & Erection W
14234-3.Co 222 21-Jan-15 A 24-Feb-16 24-Feb-16, 142
A21880 Site Modification, Construction & Erection Completion 0 24-Feb-16 Site Modification
14234-3.Construction.2 Site Construction & Erection Works
14234-3.C 222 21-Jan-15 A 24-Feb-16 24-Feb-16, 142
A21510 Site Construction & Erection Works Completion 0 24-Feb-16 Site Constructio
14234-3.C
14234-3.Construction.2.1 Foundation for Gas Metering Package 56 12-Aug-15 09-Oct-15 09-Oct-15, 14234-3.Constructio
14234-3.Construction.2.2 Foundation for Water Degassing Boot & CPI Separator Sk
14234-3.C 56 12-Aug-15 09-Oct-15 09-Oct-15, 14234-3.Constructio
14234-3.Construction.2.3 Foundation for NGL Storage Tank T-3101
14234-3.C 56 21-Jan-15 A 05-Sep-15 05-Sep-15, 14234-3.Construction.2
14234-3.Construction.2.4 Foundation for Condensate Stabilization Skid
14234-3.C 56 12-Aug-15 09-Oct-15 09-Oct-15, 14234-3.Constructio
14234-3.Construction.2.5 Foundation for Condensate Transfer Pump Skid
14234-3.C 56 12-Aug-15 09-Oct-15 09-Oct-15, 14234-3.Constructio
14234-3.Construction.2.6 Foundation for Gas/Gas Exchanger (E-300A/B) Skid
14234-3.C 42 21-Sep-15 03-Nov-15 03-Nov-15, 14234-3.Constru
14234-3.Construction.2.7 Foundation for Gas Liquid Exchanger (E-302(A/B Skid
14234-3.C 56 12-Aug-15 09-Oct-15 09-Oct-15, 14234-3.Constructio
14234-3.Construction.2.8 Foundation for Regeneration Gas Cooler (E-303) Skid
14234-3.C 42 21-Sep-15 04-Nov-15 04-Nov-15, 14234-3.Constru
14234-3.Construction.2.9 Foundation for Lighting Poles
14234-3.C 56 12-Aug-15 09-Oct-15 09-Oct-15, 14234-3.Constructio
14234-3.Construction.2.26 Erection of Gas Metering Skid
14234-3.C 5 14-Nov-15 20-Nov-15 20-Nov-15, 14234-3.Const
14234-3.Construction.2.10 Foundation for NGL Storage Tank T-3102
14234-3.C 56 09-Jul-15 05-Sep-15 05-Sep-15, 14234-3.Construction.2
14234-3.Construction.2.28 Erection of NGL Storage Tank T-3101
14234-3.C 126 09-Jul-15 16-Nov-15 16-Nov-15, 14234-3.Constr
14234-3.Construction.2.27 Erection of NGL Storage Tank T-3102
14234-3.C 126 09-Jul-15 16-Nov-15 16-Nov-15, 14234-3.Constr
14234-3.Construction.2.11 Erection of Water Degassing Boot & CPI Separator Skid
14234-3.C 7 14-Nov-15 23-Nov-15 23-Nov-15, 14234-3.Cons
14234-3.Construction.2.12 Erection of Condensate Stabilization Skid
14234-3.C 14 27-Nov-15 11-Dec-15 11-Dec-15, 14234-3.Con
14234-3.Construction.2.13 Erection of NGL Transfer Pump Skid
14234-3.C 7 27-Nov-15 04-Dec-15 04-Dec-15, 14234-3.Con
14234-3.Construction.2.14 Erection of Gas/Gas Exchanger (E-300A/B) Skid
14234-3.C 7 09-Dec-15 17-Dec-15 17-Dec-15, 14234-3.Co
14234-3.Construction.2.15 Erection of Gas Liquid Exchanger (E-302(A/B Skid
14234-3.C 7 27-Nov-15 04-Dec-15 04-Dec-15, 14234-3.Con
14234-3.Construction.2.16 Erection of Regeneration Gas Cooler (E-303) Skid
14234-3.C 7 10-Dec-15 17-Dec-15 17-Dec-15, 14234-3.Co
14234-3.Construction.2.17 Erection of Lighting Poles
14234-3.C 7 14-Nov-15 23-Nov-15 23-Nov-15, 14234-3.Cons
14234-3.Construction.2.18 Cable Pulling - Instrument Cables
14234-3.C 21 07-Nov-15 28-Nov-15 28-Nov-15, 14234-3.Cons
14234-3.Construction.2.19 Cable Pulling - Electrical Cables
14234-3.C 21 07-Nov-15 28-Nov-15 28-Nov-15, 14234-3.Cons
14234-3.Construction.2.20 Electrical Cables Termination in MCC
14234-3.C 14 19-Jan-16 02-Feb-16 02-Feb-16, 14234
14234-3.Construction.2.21 Erection of ESD/FGS Panel
14234-3.C 7 27-Nov-15 04-Dec-15 04-Dec-15, 14234-3.Con
14234-3.Construction.2.22 Instruments Cable Termination in DCS Panel
14234-3.C 14 04-Dec-15 19-Dec-15 19-Dec-15, 14234-3.Co
14234-3.Construction.2.23 Instruments Cable Termination in ESD/FGS Panel
14234-3.C 14 07-Nov-15 21-Nov-15 21-Nov-15, 14234-3.Const
14234-3.Construction.2.24 Interconnecting Cables - DCS to ESD/FGS Panel
14234-3.C 14 19-Dec-15 02-Jan-16 02-Jan-16, 14234-3.C
14234-3.Construction.2.25 Interconnecting Piping Works
14234-3.C 64 19-Dec-15 24-Feb-16 24-Feb-16, 142
14234-3.Construction.1 Site Modification Works
14234-3.C 103 04-Sep-15 19-Dec-15 19-Dec-15, 14234-3.Co

Actual Level of Effort Remaining Work Page 4 of 7 TASK filter: All Activities
Actual Work Critical Remaini... © Oracle Corporation
Egbaoma Gas Processing Plant - New Level IV Schedule-latest 16-Jul-15 15:25
Activity ID Activity Name Original Start Finish 2014 2015 2016
Duration Q3
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
A21520 Site Modification Works Completion 0 19-Dec-15 Site Modification Works
14234-3.C
14234-3.Construction.1.1 Three Phase Separator Package 18 27-Nov-15 16-Dec-15 16-Dec-15, 14234-3.Co
14234-3.Construction.1.14 Heat Medium Expansion Tank/Pumps Skid
14234-3.C 26 27-Oct-15 23-Nov-15 23-Nov-15, 14234-3.Cons
14234-3.Construction.1.19 LPG Bullets Control Station Skid
14234-3.C 26 27-Oct-15 23-Nov-15 23-Nov-15, 14234-3.Cons
14234-3.Construction.1.26 LPG Loading Arm Skid
14234-3.C 18 27-Nov-15 16-Dec-15 16-Dec-15, 14234-3.Co
14234-3.Construction.1.27 Distributed Control System (DCS)
14234-3.C 35 27-Oct-15 02-Dec-15 02-Dec-15, 14234-3.Cons
14234-3.Construction.1.28 Power Generators
14234-3.C 19 06-Nov-15 25-Nov-15 25-Nov-15, 14234-3.Cons
14234-3.Construction.1.29 LV Switchgear & MCC
14234-3.C 15 27-Nov-15 12-Dec-15 12-Dec-15, 14234-3.Con
14234-3.Construction.1.23 Heat Medium Heater Skid 12Mmbtu
14234-3.C 26 27-Oct-15 23-Nov-15 23-Nov-15, 14234-3.Cons
14234-3.Construction.1.24 Flare KO Drum Skid
14234-3.C 26 27-Oct-15 23-Nov-15 23-Nov-15, 14234-3.Cons
14234-3.Construction.1.25 Propane Loading Arm Skid
14234-3.C 18 27-Nov-15 16-Dec-15 16-Dec-15, 14234-3.Co
14234-3.Construction.1.15 Fuel Gas Conditioning Skid
14234-3.C 25 27-Oct-15 21-Nov-15 21-Nov-15, 14234-3.Const
14234-3.Construction.1.16 Instrument Air Package
14234-3.C 26 27-Oct-15 23-Nov-15 23-Nov-15, 14234-3.Cons
14234-3.Construction.1.17 Depropanizer Reboiler Skid
14234-3.C 26 27-Oct-15 23-Nov-15 23-Nov-15, 14234-3.Cons
14234-3.Construction.1.18 Debutanizer Reboiler Skid
14234-3.C 26 27-Oct-15 23-Nov-15 23-Nov-15, 14234-3.Cons
14234-3.Construction.1.30 Synchronization Panel
14234-3.C 15 07-Nov-15 23-Nov-15 23-Nov-15, 14234-3.Cons
14234-3.Construction.1.13 Deethanizer Reboiler Skid
14234-3.C 26 27-Oct-15 23-Nov-15 23-Nov-15, 14234-3.Cons
14234-3.Construction.1.3 Inlet Compressor Package - A
14234-3.C 26 06-Nov-15 03-Dec-15 03-Dec-15, 14234-3.Cons
14234-3.Construction.1.5 Inlet Compressor Package - C
14234-3.C 26 06-Nov-15 03-Dec-15 03-Dec-15, 14234-3.Cons
14234-3.Construction.1.7 Regeneration Heater Skid
14234-3.C 26 27-Oct-15 23-Nov-15 23-Nov-15, 14234-3.Cons
14234-3.Construction.1.8 Deethanizer Reflux Accumulator Skid
14234-3.C 26 27-Oct-15 23-Nov-15 23-Nov-15, 14234-3.Cons
14234-3.Construction.1.9 Depropanizer Reflux Accumulator Skid
14234-3.C 26 27-Oct-15 23-Nov-15 23-Nov-15, 14234-3.Cons
14234-3.Construction.1.10 Debutanizer Reflux Accumulator Skid
14234-3.C 26 27-Oct-15 23-Nov-15 23-Nov-15, 14234-3.Cons
14234-3.Construction.1.11 Condensate Flash Tank Skid
14234-3.C 26 27-Oct-15 23-Nov-15 23-Nov-15, 14234-3.Cons
14234-3.Construction.1.12 Cold & LP Separator Skid
14234-3.C 26 27-Oct-15 23-Nov-15 23-Nov-15, 14234-3.Cons
14234-3.Construction.1.20 Propane Bullets Control Staion Skid
14234-3.C 26 27-Oct-15 23-Nov-15 23-Nov-15, 14234-3.Cons
14234-3.Construction.1.21 LPG Loading Pumps Skid
14234-3.C 18 27-Nov-15 16-Dec-15 16-Dec-15, 14234-3.Co
14234-3.Construction.1.22 Heat Medium Heater Skid 6Mmbtu
14234-3.C 26 27-Oct-15 23-Nov-15 23-Nov-15, 14234-3.Cons
14234-3.Construction.1.4 Inlet Compressor Package - B
14234-3.C 26 06-Nov-15 03-Dec-15 03-Dec-15, 14234-3.Cons
14234-3.Construction.1.6 Molecular Sieve Filters Package
14234-3.C 26 20-Oct-15 16-Nov-15 16-Nov-15, 14234-3.Constr
14234-3.Construction.1.2 Booster Compressor Package
14234-3.C 42 06-Nov-15 19-Dec-15 19-Dec-15, 14234-3.Co
14234-3.Construction.1.31 UPS System
14234-3.C 67 04-Sep-15 12-Nov-15 12-Nov-15, 14234-3.Constr
14234-3.Commissioning Precommissioning & Commissioning Wo
14234-3.Co 105 12-Nov-15 29-Feb-16 29-Feb-16, 142

A21480 Precommissioning & Commissioning Completion 0 29-Feb-16 Precommission


14234-3.Commissioning.1 Pre-Commissioning Works
14234-3.C 57 12-Nov-15 09-Jan-16 09-Jan-16, 14234-3.C
A21500 Pre-Commissioning Completion 0 09-Jan-16 Pre-Commissioning C
14234-3.C
14234-3.Commissioning.1.1 Three Phase Separator Package 7 11-Dec-15 18-Dec-15 18-Dec-15, 14234-3.Co
14234-3.Commissioning.1.2 Booster Compressor Package
14234-3.C 7 19-Dec-15 26-Dec-15 26-Dec-15, 14234-3.C
14234-3.Commissioning.1.3 Inlet Compressor Package - A
14234-3.C 7 03-Dec-15 10-Dec-15 10-Dec-15, 14234-3.Com
14234-3.Commissioning.1.4 Inlet Compressor Package - B
14234-3.C 7 03-Dec-15 10-Dec-15 10-Dec-15, 14234-3.Com
14234-3.Commissioning.1.5 Inlet Compressor Package - C
14234-3.C 7 03-Dec-15 10-Dec-15 10-Dec-15, 14234-3.Com
14234-3.Commissioning.1.6 Molecular Sieve Filters Package
14234-3.C 7 19-Dec-15 26-Dec-15 26-Dec-15, 14234-3.C
14234-3.Commissioning.1.7 Regeneration Heater Skid
14234-3.C 7 02-Jan-16 09-Jan-16 09-Jan-16, 14234-3.C
14234-3.Commissioning.1.8 Deethanizer Reflux Accumulator Skid
14234-3.C 7 02-Jan-16 09-Jan-16 09-Jan-16, 14234-3.C
14234-3.Commissioning.1.9 Depropanizer Reflux Accumulator Skid
14234-3.C 7 02-Jan-16 09-Jan-16 09-Jan-16, 14234-3.C
14234-3.Commissioning.1.10 Debutanizer Reflux Accumulator Skid
14234-3.C 7 02-Jan-16 09-Jan-16 09-Jan-16, 14234-3.C
14234-3.Commissioning.1.11 Condensate Flash Tank Skid
14234-3.C 7 02-Jan-16 09-Jan-16 09-Jan-16, 14234-3.C

Actual Level of Effort Remaining Work Page 5 of 7 TASK filter: All Activities
Actual Work Critical Remaini... © Oracle Corporation
Egbaoma Gas Processing Plant - New Level IV Schedule-latest 16-Jul-15 15:25
Activity ID Activity Name Original Start Finish 2014 2015 2016
Duration Q3
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
14234-3.C
14234-3.Commissioning.1.12 Cold & LP Separator Skid 7 02-Jan-16 09-Jan-16 09-Jan-16, 14234-3.C
14234-3.Commissioning.1.13
14234-3.C Deethanizer Reboiler Skid 7 02-Jan-16 09-Jan-16 09-Jan-16, 14234-3.C
14234-3.Commissioning.1.14
14234-3.C Heat Medium Expansion Tank/Pumps Skid 7 02-Jan-16 09-Jan-16 09-Jan-16, 14234-3.C
14234-3.Commissioning.1.15
14234-3.C Fuel Gas Conditioning Skid 7 02-Jan-16 09-Jan-16 09-Jan-16, 14234-3.C
14234-3.Commissioning.1.16
14234-3.C Instrument Air Package 7 02-Jan-16 09-Jan-16 09-Jan-16, 14234-3.C
14234-3.Commissioning.1.17
14234-3.C Depropanizer Reboiler Skid 7 02-Jan-16 09-Jan-16 09-Jan-16, 14234-3.C
14234-3.Commissioning.1.18
14234-3.C Debutanizer Reboiler Skid 7 02-Jan-16 09-Jan-16 09-Jan-16, 14234-3.C
14234-3.Commissioning.1.19
14234-3.C LPG Bullets Control Station Skid 7 02-Jan-16 09-Jan-16 09-Jan-16, 14234-3.C
14234-3.Commissioning.1.20
14234-3.C Propane Bullets Control Staion Skid 7 02-Jan-16 09-Jan-16 09-Jan-16, 14234-3.C
14234-3.Commissioning.1.21
14234-3.C LPG Loading Pumps Skid 7 02-Jan-16 09-Jan-16 09-Jan-16, 14234-3.C
14234-3.Commissioning.1.22
14234-3.C Heat Medium Heater Skid 6Mmbtu 7 02-Jan-16 09-Jan-16 09-Jan-16, 14234-3.C
14234-3.Commissioning.1.23
14234-3.C Heat Medium Heater Skid 12Mmbtu 7 02-Jan-16 09-Jan-16 09-Jan-16, 14234-3.C
14234-3.Commissioning.1.24
14234-3.C Flare KO Drum Skid 7 02-Jan-16 09-Jan-16 09-Jan-16, 14234-3.C
14234-3.Commissioning.1.25
14234-3.C Propane Loading Arm Skid 7 02-Jan-16 09-Jan-16 09-Jan-16, 14234-3.C
14234-3.Commissioning.1.26
14234-3.C LPG Loading Arm Skid 7 02-Jan-16 09-Jan-16 09-Jan-16, 14234-3.C
14234-3.Commissioning.1.27
14234-3.C Gas Metering Skid 7 02-Jan-16 09-Jan-16 09-Jan-16, 14234-3.C
14234-3.Commissioning.1.28
14234-3.C Water Degassing Boot & CPI Separator Skid 7 02-Jan-16 09-Jan-16 09-Jan-16, 14234-3.C
14234-3.Commissioning.1.29
14234-3.C Condensate Stabilization Skid 7 02-Jan-16 09-Jan-16 09-Jan-16, 14234-3.C
14234-3.Commissioning.1.30
14234-3.C Condensate Transfer Pump Skid 7 02-Jan-16 09-Jan-16 09-Jan-16, 14234-3.C
14234-3.Commissioning.1.31
14234-3.C Gas/Gas Exchanger (E-300A/B) Skid 7 02-Jan-16 09-Jan-16 09-Jan-16, 14234-3.C
14234-3.Commissioning.1.36
14234-3.C Distributed Control System (DCS) 7 19-Dec-15 26-Dec-15 26-Dec-15, 14234-3.C
14234-3.Commissioning.1.37
14234-3.C Synchronization Panel 7 23-Nov-15 30-Nov-15 30-Nov-15, 14234-3.Com
14234-3.Commissioning.1.32
14234-3.C Gas Liquid Exchanger (E-302(A/B Skid 7 02-Jan-16 09-Jan-16 09-Jan-16, 14234-3.C
14234-3.Commissioning.1.33
14234-3.C Regeneration Gas Cooler (E-303) Skid 7 02-Jan-16 09-Jan-16 09-Jan-16, 14234-3.C
14234-3.Commissioning.1.34
14234-3.C F&G System 7 02-Jan-16 09-Jan-16 09-Jan-16, 14234-3.C
14234-3.Commissioning.1.35
14234-3.C ESD/FGS System 7 02-Jan-16 09-Jan-16 09-Jan-16, 14234-3.C
14234-3.Commissioning.1.38
14234-3.C LV Switchgear & MCC 7 12-Dec-15 21-Dec-15 21-Dec-15, 14234-3.Co
14234-3.Commissioning.1.39
14234-3.C UPS System 7 12-Nov-15 19-Nov-15 19-Nov-15, 14234-3.Comm
14234-3.Commissioning.1.40
14234-3.C Power Generators 7 26-Nov-15 03-Dec-15 03-Dec-15, 14234-3.Com
14234-3.Commissioning.2 Commissioning Works
14234-3.C 48 09-Jan-16 29-Feb-16 29-Feb-16, 142
A21490 Commissioning Completion 0 29-Feb-16 Commissioning
14234-3.C
14234-3.Commissioning.2.1 Three Phase Separator Package 5 24-Feb-16 29-Feb-16 29-Feb-16, 142
14234-3.Commissioning.2.2 Booster Compressor Package
14234-3.C 5 24-Feb-16 29-Feb-16 29-Feb-16, 142
14234-3.Commissioning.2.3 Inlet Compressor Package - A
14234-3.C 5 24-Feb-16 29-Feb-16 29-Feb-16, 142
14234-3.Commissioning.2.4 Inlet Compressor Package - B
14234-3.C 5 24-Feb-16 29-Feb-16 29-Feb-16, 142
14234-3.Commissioning.2.5 Inlet Compressor Package - C
14234-3.C 5 24-Feb-16 29-Feb-16 29-Feb-16, 142
14234-3.Commissioning.2.6 Molecular Sieve Filters Package
14234-3.C 5 24-Feb-16 29-Feb-16 29-Feb-16, 142
14234-3.Commissioning.2.7 Regeneration Heater Skid
14234-3.C 5 24-Feb-16 29-Feb-16 29-Feb-16, 142
14234-3.Commissioning.2.8 Deethanizer Reflux Accumulator Skid
14234-3.C 5 24-Feb-16 29-Feb-16 29-Feb-16, 142
14234-3.Commissioning.2.9 Depropanizer Reflux Accumulator Skid
14234-3.C 5 24-Feb-16 29-Feb-16 29-Feb-16, 142
14234-3.Commissioning.2.10 Debutanizer Reflux Accumulator Skid
14234-3.C 5 24-Feb-16 29-Feb-16 29-Feb-16, 142
14234-3.Commissioning.2.11 Condensate Flash Tank Skid
14234-3.C 5 24-Feb-16 29-Feb-16 29-Feb-16, 142
14234-3.Commissioning.2.12 Cold & LP Separator Skid
14234-3.C 5 09-Jan-16 15-Jan-16 15-Jan-16, 14234-3
14234-3.Commissioning.2.13 Deethanizer Reboiler Skid
14234-3.C 5 24-Feb-16 29-Feb-16 29-Feb-16, 142
14234-3.Commissioning.2.14 Heat Medium Expansion Tank/Pumps Skid
14234-3.C 5 24-Feb-16 29-Feb-16 29-Feb-16, 142
14234-3.Commissioning.2.15 Fuel Gas Conditioning Skid
14234-3.C 5 24-Feb-16 29-Feb-16 29-Feb-16, 142
14234-3.Commissioning.2.16 Instrument Air Package
14234-3.C 5 24-Feb-16 29-Feb-16 29-Feb-16, 142
14234-3.Commissioning.2.17 Depropanizer Reboiler Skid
14234-3.C 5 24-Feb-16 29-Feb-16 29-Feb-16, 142

Actual Level of Effort Remaining Work Page 6 of 7 TASK filter: All Activities
Actual Work Critical Remaini... © Oracle Corporation
Egbaoma Gas Processing Plant - New Level IV Schedule-latest 16-Jul-15 15:25
Activity ID Activity Name Original Start Finish 2014 2015 2016
Duration Q3
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
14234-3.C
14234-3.Commissioning.2.18 Debutanizer Reboiler Skid 5 24-Feb-16 29-Feb-16 29-Feb-16, 142
14234-3.Commissioning.2.19
14234-3.C LPG Bullets Control Station Skid 5 24-Feb-16 29-Feb-16 29-Feb-16, 142
14234-3.Commissioning.2.20
14234-3.C Propane Bullets Control Staion Skid 5 24-Feb-16 29-Feb-16 29-Feb-16, 142
14234-3.Commissioning.2.21
14234-3.C LPG Loading Pumps Skid 5 24-Feb-16 29-Feb-16 29-Feb-16, 142
14234-3.Commissioning.2.22
14234-3.C Heat Medium Heater Skid 6Mmbtu 5 24-Feb-16 29-Feb-16 29-Feb-16, 142
14234-3.Commissioning.2.23
14234-3.C Heat Medium Heater Skid 12Mmbtu 5 24-Feb-16 29-Feb-16 29-Feb-16, 142
14234-3.Commissioning.2.24
14234-3.C Flare KO Drum Skid 5 24-Feb-16 29-Feb-16 29-Feb-16, 142
14234-3.Commissioning.2.25
14234-3.C Propane Loading Arm Skid 5 24-Feb-16 29-Feb-16 29-Feb-16, 142
14234-3.Commissioning.2.26
14234-3.C LPG Loading Arm Skid 5 24-Feb-16 29-Feb-16 29-Feb-16, 142
14234-3.Commissioning.2.27
14234-3.C Gas Metering Skid 5 24-Feb-16 29-Feb-16 29-Feb-16, 142
14234-3.Commissioning.2.28
14234-3.C Water Degassing Boot & CPI Separator Skid 5 24-Feb-16 29-Feb-16 29-Feb-16, 142
14234-3.Commissioning.2.29
14234-3.C Condensate Stabilization Skid 5 24-Feb-16 29-Feb-16 29-Feb-16, 142
14234-3.Commissioning.2.30
14234-3.C Condensate Transfer Pump Skid 5 24-Feb-16 29-Feb-16 29-Feb-16, 142
14234-3.Commissioning.2.31
14234-3.C Gas/Gas Exchanger (E-300A/B) Skid 5 24-Feb-16 29-Feb-16 29-Feb-16, 142
14234-3.Commissioning.2.32
14234-3.C Gas Liquid Exchanger (E-302(A/B Skid 5 24-Feb-16 29-Feb-16 29-Feb-16, 142
14234-3.Commissioning.2.33
14234-3.C Regeneration Gas Cooler (E-303) Skid 5 24-Feb-16 29-Feb-16 29-Feb-16, 142
14234-3.Commissioning.2.34
14234-3.C F&G System 5 24-Feb-16 29-Feb-16 29-Feb-16, 142
14234-3.Commissioning.2.35
14234-3.C ESD/FGS System 5 24-Feb-16 29-Feb-16 29-Feb-16, 142
14234-3.Commissioning.2.36
14234-3.C Distributed Control System (DCS) 5 24-Feb-16 29-Feb-16 29-Feb-16, 142
14234-3.Commissioning.2.37
14234-3.C Synchronization Panel 5 24-Feb-16 29-Feb-16 29-Feb-16, 142
14234-3.Commissioning.2.38
14234-3.C LV Switchgear & MCC 5 24-Feb-16 29-Feb-16 29-Feb-16, 142
14234-3.Commissioning.2.39
14234-3.C Power Generators 5 24-Feb-16 29-Feb-16 29-Feb-16, 142
14234-3.Commissioning.2.40
14234-3.C UPS System 5 24-Feb-16 29-Feb-16 29-Feb-16, 142
14234-3.Perf & Rel Test Performance and Reliability Test
14234-3.Pe 33 29-Feb-16 04-Apr-16 04-Apr-16,

14234-3.Perf & Rel Test.Perf Test Performance Test


14234-3.Pe 3 29-Feb-16 03-Mar-16 03-Mar-16, 142
A24210 Performance Test 3 29-Feb-16 03-Mar-16 Performance T
14234-3.Perf & Rel Test.Rel. Test Reliability Test
14234-3.Pe 30 03-Mar-16 04-Apr-16 04-Apr-16,
A24220 Reliability Test 30 03-Mar-16 04-Apr-16 Reliability T

Actual Level of Effort Remaining Work Page 7 of 7 TASK filter: All Activities