Up to 25m depth boring performed at the site. Natural moisture content, Unit
Weight of soil, Grain Size Analysis of soil by sieve and hydrometer analysis &
Specific gravity test, Plasticity Index were performed in the laboratory and
prepared soil test report. The shallow foundation designed by using the laboratory
test data.
Performed 50m-70m depth boring at the site. Disturbed and Undisturbed samples
collected from the holes. Grain size distribution and Hydrometer Analysis,
Atterberg Limit, Moisture Content, Specific Gravity, Unit Weight, Direct Shear
Test, Unconfined Compression Test, Consolidation Test, Other Physical &
Mechanical Properties were performed in the laboratory, prepared soil profile in
AutoCAD and soil test report.
Up to 55m depth boring performed at the site. Natural moisture content, Unit
Weight of soil, Grain Size Analysis of soil by sieve and hydrometer analysis &
Specific gravity test, Plasticity Index, Unconfined compression test for cohesive,
Consolidation test for cohesive soil, Specific gravity, Direct Shear test
(Consolidated drain test), (i) Chemical Analysis (test to be conducted) (i) PH,
(ii)Chlorides, (iii) Sulphates.
Up to 15m depth boring performed at the site. Natural moisture content, Unit
Weight of soil, Grain Size Analysis of soil by sieve and hydrometer analysis &
Specific gravity test, Plasticity Index were performed in the laboratory and
prepared soil test report. The shallow foundation designed by using the laboratory
test data.
Up to 18m depth boring performed at the site. Natural moisture content, Unit
Weight of soil, Grain Size Analysis of soil by sieve and hydrometer analysis &
Specific gravity test, Plasticity Index were performed in the laboratory and
prepared soil test report. The shallow foundation designed by using the laboratory
test data.
Performed 50m depth boring in the river Bakhkhali and in the river bank. Disturbed
samples collected from the holes
the consultancy of NKDM Association
Up to 53m depth boring performed at site. Disturbed and undisturbed samples
collected from the holes.
Date: 30-04-18
[Signature] Day/Month/Year
Page 1 of
Asaduzzaman Chowdhury
Page 1 of
Routine/ Legal
Sl Non- Evaluation of After existing
Activity Hazards Consequences / Risk Require Existing Control Measures Additional Control Responsibility
No Routine / Hazard control measure
ments
Emergency
Situation Proba Seve Risk Proba Sever Risk
(R/NR/E) bility rity Level bility ity Level
H=Fx
A B C D E F G I J K L=JxK M
G
• Minor Injury to person
• First Aid Injury 1.Follow Kinetic method of lifting
• Improper posture
• Low Back ache, Neck, a) Proper posture while lifting Area Incharge,
during material handling,
R shoulder and body pain, • Yes 3 4 12 b) Training of personnel is required for manual material handling. 2 4 8 Site Engineer/
loading and unloading.
fatigue 2. Use of Safety Helmet, Safety steel toe Shoes, Cotton /leather hand Supervisor
gloves etc. while handling material manually.
1. Tripod shear legs should keep on hard consolidated and level base.
2. All workmen should aware about risk & mitigation measures of rotary
• Loose Soil/ Uncompact parts & linear movement of wire ropes.
• Injury 1. Ensure soil strength &
soil 3. Use base plate/ Shear legs shoes below the legs of tripod. Section Incharge,
• First Aid shear leg's base plate with
• Topple of tripod rig R/NR No 4 4 16 4. Shear legs shoes should be pinned to prevent toppling over of shear 3 4 12 Site Engineer/
• LTA anchoring pins are locked
• Subside of tripod legs legs. Supervisor
• Fatal with soil.
• Fall of material 5. Wire rope should be tied properly at the chisel / bailer end.
5. Use always safety helmet in working area.
6. Unauthorized operation/entry should be strictly restricted.
Routine/ Legal
Sl Non- Evaluation of After existing
Activity Hazards Consequences / Risk Require Existing Control Measures Additional Control Responsibility
No Routine / Hazard control measure
ments
Emergency
Situation Proba Seve Risk Proba Sever Risk
(R/NR/E) bility rity Level bility ity Level
Boring, Sampling,
3 H=Fx
Testing
A B C D E F G I J K L=JxK M
G
1. Bore casing should be atleast 30cm above the ground. bore hole
should be protected against fall of person inside.
2. All opening of bore should be covered by using bore caps or grating.
3. Working area should be barricaded & waring/ Danger sign boards to
• Bore opening be displayed.
• Fall of material 4. Strictly avoid other vehicle movements near the working zone.
• Fall of person in bored 5. All material/ equipment's should be stacked away from the bored pile. 1. Strictly ensure hard Section Incharge,
Material handling • LTA
pit R No 4 4 16 6. Hard barricade with Blinking light should be installed for identification 3 4 12 barricading of bore Site Engineer/
1 manually/ • Fatal
• Mud/ Slush/ water of hazard in night & provide adequate illumination for night work. opening area. Supervisor
Mechanically • Major accident
logging area 7. Use gumboots working near muddy/ slush area.
• Slip /Trip/ Fall 8. Dewatering should be done at working area if water logged area
exists.
9. Regular inspection of work area & tripod rig should be done by
concern engineer/ supervisor
10. Maintain good housekeeping near the working area.
Routine/ Legal
Sl Non- Evaluation of After existing
Activity Hazards Consequences / Risk Require Existing Control Measures Additional Control Responsibility
No Routine / Hazard control measure
ments
Emergency
Situation Proba Seve Risk Proba Sever Risk
(R/NR/E) bility rity Level bility ity Level
H=Fx
A B C D E F G I J K L=JxK M
G
1. Use only approved equipment and deploy competent operator.
2. Adhere to permit to work system
3. Inspect machine (Excavator) before starting the job.
4. If excavation is manually - all tool should be insulated & Make sure
absence of underground utilities.
5. Don't stack material at the edges of excavated pit. (atleast 2 m away
• Fall of person into pit
from the edge or depth of excavation whichever is more)
• Fall of heavy objects
6. Provide hard barricade with sign boards surrounding to the excavated
Material handling stone, boulder, soil etc. 1. For finding out
• Injury to person pit.
1 manually/ into pit underground utilities to
• Property Damage 7. As per soil type should be make benching & sloping.(Maintain angle of
Mechanically • Cave-in/ side wall be used earth penetrating Section Incharge,
• LTA repose as per classification of soil)
collapse R/NR Yes 3 4 12 2 4 8 radar (If exists) Site Engineer/
• Electric shock 8. Ensure safe access/ egress while working in pits & also ensure
• Working near 2. Ensure all tools shall be Supervisor
5 Trial Pit/ Excavation • Overhead powerlines • Electrocution emergency exit.
well insulated to prevent
• Drowning 9. Ensuring Vehicle/ Equipment are stopped far away from the edge of
• Defective Machinery electrical shock.
excavated area at least 2m or equal distance of depth of excavation
• Water accumulation in
whichever is more.
pit
10. Maintained safe clearance distance from live cables (As per
electricity rule)
11. Body earthing is providing for equipment for avoid induction.
12. Dewatering pump should be arranged for accumulated water
removal.
13. Pep-talk & training to be conducted to workmen on Excavation safety.
1. To be make an arrangement for water sprinkling against dust.
• Health related illness
• Dust 2. Ear plug/ ear muff are using.
R (Lungs Cancer) Yes 2 4 8 1 4 4 Site Engineer/
• Noise 3. Nose mask to be provided to workmen.
• NIHL Supervisor
1. Work area should be baricaded.
2. Use standard tools & use right tool for right job.
3. If vehicle movement is present, divert the trafic/ vehicle movement.
4. Be certain the circuit is deenergized and discharged before connecting
• Nearby Vehicle
resistant tester.
movement • Injury 1. Ensure standard tools
5. Do not apply power to a circuit while measuring resistance.
Electrical Resistivity • Bare conductor • LTA Section Incharge,
6 NR No 2 5 10 6. When you are finished using an measuring apparatus, switch it to the 1 5 5 & equipements are using
Test • Faulty apparatus • Electrocution Site Engineer/
OFF position. while conducting test.
• Loose connection • Electric shock Supervisor
7. Don't touch any lead/terminal of appratus when the testing starts.
• Damaged cables/wires
8. Trained & skilled person should have deployed for work.
9. Unauthorised entry to be restricted in work area.
10. Use all necessary PPE (Safety Helmet, Safety Shoes, Reflective
jackets, Rated electrical rubber hand gloves etc.)
_________________ _________________
PM / CM / Section Head EHSO
E=Elimination
S=Substitution AC=Administrative controls
EC=Engineering controls PPE=Personal Protective Equipment