Sunteți pe pagina 1din 10

Available online at www.sciencedirect.

com

International Journal of Project Management 26 (2008) 665–674


www.elsevier.com/locate/ijproman

Delays in construction projects: The case of Jordan


a,*
G. Sweis , R. Sweis b, A. Abu Hammad c, A. Shboul d

a
Department of Civil Engineering, University of Jordan, Jordan
b
Department of Business Administration, Amman – Ahlyah University, Jordan
c
Department of Civil Engineering, Applied Science University, Jordan
d
Department of Architecture Engineering, University of Jordan, Jordan

Received 29 April 2007; received in revised form 22 August 2007; accepted 25 September 2007

Abstract

The construction industry is a major player in the economy, generating both, employment and wealth. However many projects expe-
rience extensive delays and thereby exceed initial time and cost estimates. A host of causes of construction delays in residential projects
were identified and classified according to Drewin’s Open Conversion System. The most common causes were evaluated by using both,
the data collected in a survey conducted to residential projects consultant engineers, contractors, and owners, and interviews with senior
professionals in the field. Most correspondents agreed that, financial difficulties faced by the contractor and too many change orders by
the owner are the leading causes of construction delay. Severe weather conditions and changes in government regulations and laws
ranked among the least important causes.
Ó 2008 Elsevier Ltd and IPMA. All rights reserved.

Keywords: Construction delays; Residential construction projects; Jordanian construction industry

1. Introduction on. In addition, delays are often interconnected, making


the situation even more complex [2].
Stumpf [1] defined delay as an act or event that extends Recent events in the Middle East region coupled with
the time required to perform the tasks under a contract. It restructuring of economies, emergence of the World Trade
usually shows up as additional days of work or as a delayed Organization and the rising price of oil are expected to
start of an activity. He showed, in his article, that delay yield an unprecedented growth in construction activities,
does matter, and that different methods for analyzing sche- especially in the tourism and the residential sectors. Conse-
dule delay lead to different results for the owner and quently, a huge number of large-scale projects are currently
contractor. under construction or in the planning and contract-award-
Construction delays became an integral part of the pro- ing phase. Recently, the Jordanian construction industry
ject’s construction life. Even with today’s advanced tech- has been undergoing a boom. One major question of con-
nology, and management understanding of project cern however arises: what are the major causes of delays in
management techniques, construction projects continue the Jordanian construction industry and their relative
to suffer delays and project completion dates still get importance?
pushed back [1].
There are many reasons why delays occur. They may be 2. Problem statement and study objectives
due to strikes, rework, poor organization, material short-
age, equipment failure, change orders, act of God and so Delays in construction projects are common in the Jor-
danian construction industry. Construction delays are
*
Corresponding author. Tel.: +962 6 535 5000; fax: +962 6 535 5580. often responsible for turning profitable projects into loos-
E-mail address: gsweis@ju.edu.jo (G. Sweis). ing ventures. These delays can be avoided or reduced

0263-7863/$30.00 Ó 2008 Elsevier Ltd and IPMA. All rights reserved.


doi:10.1016/j.ijproman.2007.09.009
666 G. Sweis et al. / International Journal of Project Management 26 (2008) 665–674

provided the major causes of such delays can be identified [20], Semple et al. [21], Ogunlana et al. [22], Lo et al.
and dealt with in a timely fashion. Therefore the study [23], Chan and Kumaraswamy [24], and Aibinu and Odey-
objectives are (a) to identify the major causes of delay in inka [9] cited many significant causes of delays as: inclem-
the Jordanian residential construction sector; and (b) to ent weather, shortages of resources, financial difficulties
asses the relative importance of these causes from the point faced by public agencies and contractors, poor contract
of view of residential projects consultant engineers, con- management, shortages of materials, and inadequate
tractor, and owners. resources. Their overall ranking of delay causes indicated
areas of construction industry practices that require
3. Literature review improvement. However, they still differed in their percep-
tions as to what should be emphasized most among the dif-
Delays happen in most construction projects, whether ferent construction delay causes.
simple or complex. Construction delay could be defined Few studies have been conducted in Jordan as well as
as the time overrun either beyond the contract date or the Middle East region on the subject of construction
beyond the date that the parties agreed upon for delivery delays. Such studies are found in different countries like
of a project [11]. Saudi Arabia [5,11,3], Lebanon [4], and Kuwait [6]. Table
Odeh and Battaineh [8], Kaming et al. [13] and 1 shows a summary of previous studies on construction
Alaghbari et al. [14] stressed the importance of early delays in the Middle East.
identification of construction delays and suggested major There is no consensus in the literature on the identifica-
delay-reducing remedies. tion of factors which affect construction times of buildings.
Analyses of delays are characterized as complex and dif- One reason for this is that researchers have largely viewed
ficult due to the large number of activities that have to be the subject from diverse perspectives. Even most recent
dealt with in any construction project [25]. Researchers research in construction delay is characterized by diversi-
have studied the numerous causes of delay in construction fied views on what should constitute a major delay cause
projects; Baldwin et al. [16], Arditi et al.[17], Okpala and in construction projects [27–34]. This study seeks to build
Aniekwu [18], Dlakwa and Culpin [19], Mansfield et al. on prior research by ranking each individual cause of con-

Table 1
Summary of previous studies of the causes of delay in construction projects (middle east region)
Country Researchers Major causes of delay
Saudi Arabia Assaf et al. [3]  Slow preparation and approval of shop drawings
 Delays in payments to contractors
 Changes in design/design error
 Shortages of labor supply
 Poor workmanship
Lebanon Mezher et al. [4]  Owner had more concerns with regard to financial issues
 Contractors regarded contractual relationships the most important
 Consultants considered project management issues to be the most
important causes of delay
Saudi Arabia Al-Khal and Al-Ghafly [5]  Cash flow problems/financial difficulties
 Difficulties in obtaining permits
 ‘‘Lowest bid wins’’ system
Jordan Al-Moumani [7]  Poor design
 Changes in orders/design
 Weather
 Unforeseen site conditions
 Late deliveries
Kuwait Koushki et al. [6]  Changing orders
 Owners’ financial constraints
 Owners’ lack of experience in the construction business
United Arab Emirates (UAE) Faridi and El-Sayegh [15]  Slow preparation and approval of drawings
 Inadequate early planning of the project
 Slowness of owner’s decision making
 Shortage of manpower
 Poor site management and supervision
 Low productivity of manpower
Saudi Arabia Assaf and Al-Hejji [13]  Change in orders by the owner during construction
 Delay in progress payment
 Ineffective planning and scheduling
 Shortage of labor
 Difficulties in financing on the part of the contractor
G. Sweis et al. / International Journal of Project Management 26 (2008) 665–674 667

Feed Back Feed Back

Input Factors Internal Environment, Output Factors


Organizational Structure,
Supervision, Management, Span
Labor of Control, Work Rules, etc.

Capital Rework

Input Conversion Output Products


Mechanism Technology Mechanism
Energy and
Projects

Material

Disturbance Disturbance
Equipment

Exogeneous Factors such as:


Disturbance Weather, Economic Conditions, Disturbance
Unions, Government Regulations,
Public, etc.

Fig. 1. Drewin’s open conversion system.

struction delay from the viewpoints of the consultant engi- struction delay causes and measure differences in collective
neer, the residential contractor, and the owner in the con- perspectives and any possible popular misconceptions or
text of Drewin’s Open Conversion System. prejudices.
Next, the questionnaire was distributed to a random
4. Research design and survey methodology sample of consultants, contractors,1 and owners, in the
field of residential building projects in Jordan. Responses
The design of the questionnaire has been based on the to the questionnaire were then collected and analyzed.
Open Conversion System proposed by Drewin [10]. The analysis of the questionnaire included ranking of
According to Drewin, the conversion process associated the different responses according to their frequency for
with construction is complex, influenced by technology consultants, contractors, and owners (Appendix A). Fur-
and by many externalities such as government regulations, thermore, a one-way ANOVA was carried out among the
weather, unions, economic conditions, etc., and by various means of responses of the three groups for each individual
internal environment components (Fig. 1). This research, delay cause to measure for any significant differences
hence synthesizes potential delay causes identified in previ- among the respondents’ perceptions. Discussion of the
ous research [5] and the factors presented in the Drewin’s results was based on personal interviews that were con-
Open Conversion System to arrive at a clearly structured ducted to clarify responses. Interviewees were experts from
questionnaire. Finally, 40 potential delay causes were sum- the Association of Construction Contractors and the Min-
marized into three major categories: istry of Housing and Public Works.
The scope of this research includes residential buildings
Input Factors (IF) in Jordan. Sampling in this research was necessary because
Labor (L) it would be practically impossible to conduct a census to
Materials (M) rank delay causes by all elements of the population. The
Equipment (E) population consists of all the consultants, contractors,
Internal Environment (IE) and owners in the Municipality of Amman who are actively
Contractor involved in residential buildings at the time the study was
Owner conducted. The researchers chose to follow a simple ran-
Consultant dom sampling to assure that each element in the popula-
Exogenous Factors (EF) tion has an equal chance of being included in the sample.
Weather This technique was deemed most appropriate given the rel-
Government Regulations atively large size of the population of consultants, contrac-
tors, and owners. The sample size was selected based on the
Due to the dearth of real data relating to delays in res- judgment of the researchers taking into consideration the
idential construction, the researchers developed a survey
questionnaire to assess the perceptions of the consultants,
1
contractors, and owners of the relative importance of con- Contractors hired by the owner.
668 G. Sweis et al. / International Journal of Project Management 26 (2008) 665–674

Table 2 and by the consensus justification as provided by the


Frequency weighting scale in the research survey experts during post-results interviews.
Frequency Scale
Continual Frequent Occasional Rare Never  Financial difficulties faced by the contractorFinancial
5 4 3 2 1 difficulties faced by the contractor were considered to
be the first and most frequent causes of delay in build-
ing projects in Jordan from the viewpoint of the con-
low variance or homogeneity of the different elements of tractor and second most important according to both
the population [26]. Finally a sample of 30 consultants, the owner and the consultant.Most expert interviewees
50 contractors, and 30 owners were drawn that was pro- claim that financial difficulties faced by the contractor
portional to the relative population size [12]. are a natural result of the competitive nature of the
Returned questionnaires consisted of 29 consultants, 36 industry. Furthermore, most Jordanian residential con-
contractors, and 26 clients. The respondents were asked to tractors are independent, small in size, and often resorts
express their perception, in terms of frequency of the delay to underbidding rivals to win contracts. Also contrac-
causes stated in the questionnaire. The questionnaire was tors in Jordan have little access to credit facilities.
constructed based on the compiled list of causes. The The causes mentioned above provide for a certain rec-
respondents were asked to give their opinion on the fre- ipe for cash flow problems later.It is obvious that both
quency of each delay cause based on a five-point Likert the owner and the consultant support the contractor’s
scale. The scale and the weight given to each response are claim with respect to the contractor’s financial difficul-
shown in Table 2. ties by ranking it second most important cause. More-
over, the contractor indirectly blames his/her financial
5. Data analysis and results difficulties on the owner by ranking ‘‘delay in progress
payments by the owner’’ 5th most important cause of
The ranking of delay causes was determined by taking delay.
the respective average score of the reported data for all  Too many change orders by the ownerHaving to deal
the respondents. The resulting averages and corresponding with too many change orders ranked as the second
ranks are presented in Appendix A. most important delay cause from the viewpoint of the
All average values above 3 are considered ‘‘accepted contractor and third most important according to the
results’’, which basically indicated that the corresponding consultant. In fact, many experts agree that excessive
delay result is a critical cause of delay to the group in ques- change orders have a tremendous effect on the financial
tion. The values are ranked according to their averages in a performance of a construction project. Change orders
descending order according to the highest average in the can make or break a job. The average cost of change
group response. orders on construction, as a percentage of the original
project budget, is 5–10%, according to many expert
– The consultants’ responses classified the following three interviewees.It is clear that the contractors support
delay causes as the most critical: their opinion regarding change orders as a major delay
1. Poor planning and scheduling of the project by the cause by ranking ‘‘Interference in the construction
contractor operation’’ as eighth highest among the delay causes.
2. Financial difficulties faced by the contractor Furthermore, the contractor partially blames the con-
3. Too many change orders from owner sultant for the extensive change orders. This is mani-
– The contractor accepted the following as critical top fested by the relatively high rank (9th) given to the
three delay causing factors: delay cause ‘‘Ambiguities, mistakes, and inconsistencies
1. Financial difficulties faced by the contractor in specifications and drawings’’. On the other hand, we
2. Too many change orders from owner notice that the views of both consultant and owner are
3. Shortage of manpower (skilled, semi-skilled, leaning toward blaming excessive change order partially
unskilled labor) on the contractor’s shortage of technical professionals
– The owners viewed the following three delay causes as in the contractor’s organization ranking it 4th and
most critical: 5th respectively.
1. Poor planning and scheduling of the project by the  Poor planning and scheduling of the project by the
contractor contractorBoth the owner and the consultant ranked
2. Financial difficulties faced by the contractor this major delay cause as most important. The critical
3. Incompetent technical staff assigned to the project importance of this cause can be seen clearly by notic-
ing the relatively high ranks given by both the consul-
6. Discussion of the results tant and the owner for the following delay causes
relating both directly and indirectly to ‘‘poor planning
The following discussion will emphasize on the most and scheduling of the project by the contractor’’
important causes of delay by each of the three parties (Table 3).
G. Sweis et al. / International Journal of Project Management 26 (2008) 665–674 669

Table 3 7. Difference in perception among the three groups


Highly ranked factors relevant to poor planning and scheduling
Delay cause Rank by Rank by A one-way analysis of variance was conducted among
consultant owner the means of responses from the three groups to check
Shortage of technical professionals in the 4th 5th for any significant differences among the groups’ percep-
contractor’s organization tions regarding the importance of the various delay causes.
Insufficient coordination among the parties 5th 10th
by the contractor
The mean values under the three groups, F statistics, and
Ineffective quality control by the contractor 7th 9th the P values at which hypothesis of equality of mean values
across different groups could be rejected were calculated
(Appendix B). From the analysis, it was found that there
 Shortage of manpower (skilled, semi-skilled, unskilled were statistically non-significant differences among the
labor)Manpower shortage was ranked third most impor- respondent groups over the following causes:
tant delay cause from the viewpoint of the contractor.
Manpower shortage, skilled, semi-skilled, and unskilled, 1. Changes in Government regulations and laws.
has been a serious delay cause for residential construc- 2. Financial difficulties faced by the contractor.
tion projects in Jordan. Recently, the Middle East region 3. Severe weather conditions on the job site.
has been experiencing a boom in construction due to
wars as well as the high prices of oil resulting in access The results of the ANOVA analysis (Figs. 2–4) show
liquidity and thus a higher demand for investment that the means of the different groups are not significantly
opportunities. The Jordanian residential construction different from one another (measured F’s = 0.17, 0.73,
boom has been accompanied by shortages in foreign 0.07) while the tabular critical F value at the 0.05 level
manpower leading to higher wages and thus adding to for 2° and 87° of freedom is approximately (3.10), indicat-
the financial burden on the contractor. This explains ing a strong agreement among the three groups. Conse-
the contractor’s reliance on cheap, unskilled labor. Addi- quently, there is no need to carry out the analysis any
tionally, this fact is very revealing in that it ties with the further by using Duncan Multiple Range Test or Scheffe’s
high ranks given by the consultant and the owner to Test to detect where exactly the mean differences lie since
‘‘Poor planning and scheduling of the project by the con- differences are negligible.
tractor’’ and ‘‘Incompetent technical staff assigned to the Combining the above result with the highest-ranking
project’’ respectively. causes according to the mean of the averages of the three

Source DF SS MS F P
Type 2 0.189 0.095 0.17 0.840
Error 87 47.100 0.541
Total 89 47.289

S = 0.7358 R-Sq = 0.40% R-Sq(adj) = 0.00%

Individual 95% CIs For Mean Based on


Pooled StDev
Level N Mean StDev ---+---------+---------+---------+------
Consultant 28 4.3214 0.6696 (-------------*-------------)
Contractor 37 4.3514 0.7156 (-----------*-----------)
Owner 25 4.2400 0.8307 (--------------*--------------)
---+---------+---------+---------+------
4.00 4.20 4.40 4.60

Pooled StDev = 0.7358

Fig. 2. One-way ANOVA for ‘‘Financial difficulties faced by the contractor’’.


670 G. Sweis et al. / International Journal of Project Management 26 (2008) 665–674

Source DF SS MS F P
Type 2 0.811 0.406 0.73 0.485
Error 87 48.311 0.555
Total 89 49.122

S = 0.7452 R-Sq = 1.65% R-Sq(adj) = 0.00%

Individual 95% CIs For Mean Based on Pooled StDev


Level N Mean StDev --------+---------+---------+---------+-
Consultant 28 1.7143 0.6587 (-------------*-------------)
Contractor 37 1.9189 0.7951 (-----------*-----------)
Owner 25 1.9200 0.7594 (--------------*--------------)
--------+---------+---------+---------+-
1.60 1.80 2.00 2.20

Pooled StDev = 0.7452

Fig. 3. One-way ANOVA for ‘‘Severe weather conditions on the job site’’.

Source DF SS MS F P
Type 2 0.085 0.043 0.07 0.929
Error 87 50.315 0.578
Total 89 50.400

S = 0.7605 R-Sq = 0.17% R-Sq(adj) = 0.00%

Individual 95% CIs For Mean Based on Pooled StDev


Level N Mean StDev ---+---------+---------+---------+------
Consultant 28 1.8214 0.6696 (-------------*-------------)
Contractor 37 1.8919 0.8091 (------------*-----------)
Owner 25 1.8800 0.7810 (--------------*--------------)
---+---------+---------+---------+------
1.60 1.80 2.00 2.20

Pooled StDev = 0.7605

Fig. 4. One-way ANOVA for ‘‘Changes in government regulations and laws’’.

groups (Appendix A), namely, ‘‘Financial difficulties faced the contractor’’ is by consensus of all respondents the lead-
by the contractor’’, ‘‘Too many change orders from owner’’, ing cause of construction delay in the Jordanian residential
and ‘‘Poor planning and scheduling of the project by the con- construction sector (Fig. 2). In addition, we notice a strong
tractor’’, it becomes clear that ‘‘financial difficulties faced by agreement among the respondents on the two lowest scoring
G. Sweis et al. / International Journal of Project Management 26 (2008) 665–674 671

causes namely, severe weather conditions on the job site owner, and poor planning and scheduling of the project
(Fig. 3) and changes in government regulations and laws by the contractor continue to be the major sources of res-
(Fig. 4). idential project delays in Jordan. Using the terminology
of the Drewin’s Open Conversion System, it can be
8. Conclusion clearly argued that major delay causes are related to the
internal environment of the system especially that of the
The findings of this research are discussed below empha- contractor, and the Input factors relating to labor, while
sizing the most important delay causes according to Dre- the exogenous factors have very little or negligible effect
win’s Open Conversion System. In addition, the on project delay.
discussion will emphasize the relation between the research
findings and other comparable research in the field. 9. How does the outcome of this research compare with
outcomes of previous research conducted in the Middle East?
 Internal environmentWithin the contractor’s internal
environment, ‘‘financial difficulties’’ is the first most In this study, the contractors, consultants, and owners
important delay cause. Moreover, all three groups of were shown to agree statistically on the relative impor-
respondents agree on the severity of this cause thereby tance ranking of the causes of delay. Among the most
making it one of the most critical delay causes in the important causes found are financial difficulties faced
Jordanian residential construction sector. Both the by the contractor and too many change orders. These
owner and the consultant ranked ‘‘poor planning and results are in agreement with outcomes of research con-
scheduling’’ of the project by the contractor as most ducted in Saudi Arabia by Assaf et al. [3], Al-Khalil
important delay cause. Additionally it was ranked and Al-Ghafly [5], and Assaf and Al-Hejji [11], Jordan,
third most important according to the mean of the Al-Momani [7] and Kuwait, Koushki et al. [6]. However,
overall averages of the three groups of respon- there is a clear disagreement with regard to the signifi-
dents.Within the owner’s internal environment, ‘‘too cance of certain delay causes i.e., exogenous factors (gov-
many change orders’’ is viewed as the second most ernment and the weather) were very insignificant in this
important delay cause from the perspective of the con- research while Al-Momani [7] ranked the weather as a
tractor and third most important from the perspective major delay-causing factor in the Jordanian construction
of the consultant. Also this delay cause ranked as sec- industry.
ond most important according to the mean of the
average ranking of all three groups of respondents. 10. Implications and future research and developments
However, there are no significant delay factors accord-
ing to the mean of the overall averages of the three This study assessed the factors contributing to delays in
groups of respondents concerning the consultant’s the Jordanian residential sector by grouping the various
internal environment. factors according to Drewin’s Open Conversion System.
 Exogenous factorsThe least ranked causes, according to The results have clear implications for the residential con-
the perception of all three parties, were severe weather struction sector in Jordan and the construction industry at
conditions on the job site and changes in government large. By ranking the various delay causes from the per-
regulations and laws. There are no significant differences spectives of consultants, contractors, and owners, the
among all respondents’ perceptions regarding these study provides a fresh perspective on an old chronic prob-
delay causes.Generally speaking, there is a shared sense lem in the construction sector. This study has provided
among the respondents that weather and the govern- evidence on the most significant delay causes in the Jorda-
ment are not major contributors to residential construc- nian residential construction as well as those least signifi-
tion delays in Jordan. The consensus is that, in Jordan, cant causes.
contact with the government is basically to obtain cer- Finally, although this study is specific to the country of
tain permits and this is usually done at both early and Jordan, its results can be applicable to other developing
late stages of the project and consequently not having countries facing similar problems in their residential con-
any major impact as a delay cause. struction sectors. This research could be used as an avenue
 Input factorsAmong the Input factors, labor appears to for other researchers to conduct additional studies on con-
be most significant. Shortage of manpower (skilled, struction delay. Several aspects of this research could be
semi-skilled, unskilled labor was ranked 3rd highest by improved, including the following:
the contractor and 15th highest from the perspective
of the consultant while the owner’s rank of this cause  Expanding the research to other types of projects such
came very low. Whereas equipment and material were as public projects.
ranked very low according to all respondents.  Applying the methodology used in this research to other
developing countries, thereby increasing the data avail-
The result of this study indicated that financial difficul- ability for future comparison among different delay
ties faced by the contractor, too many change orders from causes.
672 G. Sweis et al. / International Journal of Project Management 26 (2008) 665–674

Appendix A
Average Average Average Overall
(consultant) (contractor) (owner) average
Labor (L)
1 Shortage of manpower (skilled, semi-skilled, unskilled 3.50 4.16 2.52 3.39
labor)
2 Presence of unskilled labor 3.96 3.19 4.08 3.74

Material (M)
3 Shortage of materials 3.11 2.97 2.88 2.99
4 Delay in materials delivery 2.71 3.08 2.96 2.92
5 Materials price fluctuations 2.82 2.65 2.16 2.54
6 Modifications in materials specifications 2.04 2.59 2.24 2.29

Equipment (E)
7 Shortage of equipments 3.04 2.89 3.32 3.08
8 Failure of equipments 2.93 2.62 2.76 2.77
9 Insufficient equipments 2.50 2.46 3.12 2.69

Internal Environment (IE)


Contractor
10 Lack of contractor’s administrative personnel 3.39 2.49 3.36 3.08
11 Shortage of technical professionals in the contractor’s 4.18 2.92 4.04 3.71
organization
12 Insufficient coordination among the parties by the 4.07 2.59 3.8 3.49
contractor
13 Delay in mobilization 2.64 2.49 2.32 2.48
14 Safety rules and regulations are not followed within the 3.93 2.19 3.96 3.36
contractor’s organization
15 Incompetent technical staff assigned to the project 3.82 2.86 4.12 3.60
16 Improper technical study by the contractor during the 3.89 2.81 3.88 3.53
bidding stage
17 Poor planning and scheduling of the project by the 4.39 2.95 4.32 3.89
contractor
18 Improper handling of the project progress by the 2.86 2.32 2.76 2.65
contractor
19 Ineffective quality control by the contractor 3.96 2.76 3.84 3.52
20 Use of unacceptable construction techniques by the 2.75 2.11 2.84 2.57
contractor
21 Financial difficulties faced by the contractor 4.32 4.35 4.24 4.30
22 Delays in contractor’s payments to subcontractors 3.75 2.73 3.92 3.47
Owner
23 Delays in site preparation 1.96 2.57 2.24 2.26
24 Delay in contractor’s claims settlements 2.54 3.81 2.72 3.02
25 Work suspension by the owner 1.89 2.30 2.48 2.22
26 Too many change orders from owner 4.21 4.24 3.64 4.03
27 Slow decision making from owner 3.86 3.81 2.88 3.52
28 Inference by the owner in the construction operations 3.68 3.76 2.28 3.24
29 Delay in progress payments by the owner 3.43 4.03 2.84 3.43
30 Financial constraints faced by the owner 3.54 2.89 3.32 3.25
31 Insufficient coordination among the parties by 3.07 2.70 3.24 3.00
the Owner
G. Sweis et al. / International Journal of Project Management 26 (2008) 665–674 673

Appendix A (continued)
Average Average Average Overall
(consultant) (contractor) (owner) average
Consultant
32 Ambiguities and mistakes in specifications and drawings 2.43 3.46 2.76 2.88
33 Poor qualification of consultant engineer’s staff assigned 2.89 3.11 2.88 2.96
to the project
34 Delay in the approval of contractor submissions by the 2.68 4.11 3.08 3.29
engineer
35 Poor coordination by the consultant engineer with the 2.46 2.92 2.72 2.70
parties involved
36 Slow response by the consultant engineer regarding 2.61 3.05 2.76 2.81
testing and inspection
37 Slow response by the consultant engineer to contractor 2.79 3.30 3.04 3.04
inquiries
Exogeneous factors (EF)
Weather
38 Severe weather conditions on the job site 1.71 1.92 1.92 1.85
Government regulations
39 Difficulties in obtaining work permits 2.11 2.00 2.44 2.18
40 Changes in Government regulations and laws 1.82 1.89 1.88 1.86

Appendix B
Labor (L) Overall F-Values P-Values
average
1 Shortage of manpower (skilled, semi-skilled, unskilled labor) 3.39 30.04 0.000
2 Presence of unskilled labor 3.74 10.24 0.000
3 Shortage of materials 2.99 0.44 0.643
4 Delay in materials delivery 2.92 1.36 0.262
5 Materials price fluctuations 2.54 3.65 0.030
6 Modifications in materials specifications 2.29 3.52 0.034
7 Shortage of equipments 3.08 1.71 0.187
8 Failure of equipments 2.77 0.87 0.423
9 Insufficient equipments 2.69 4.36 0.016
10 Lack of contractor’s administrative personnel 3.08 9.00 0.000
11 Shortage of technical professionals in the contractor’s organization 3.71 26.30 0.000
12 Insufficient coordination among the parties by the contractor 3.49 31.12 0.000
13 Delay in mobilization 2.48 0.89 0.413
14 Safety rules and regulations are not followed within the contractor’s 3.36 51.64 0.000
organization
15 Incompetent technical staff assigned to the project 3.60 20.90 0.000
16 Improper technical study by the contractor during the bidding stage 3.53 13.22 0.000
17 Poor planning and scheduling of the project by the contractor 3.89 32.65 0.000
18 Improper handling of the project progress by the contractor 2.65 3.59 0.032
19 Ineffective quality control by the contractor 3.52 22.05 0.000
20 Use of unacceptable construction techniques by the contractor 2.57 8.28 0.001
21 Financial difficulties faced by the contractor 4.30 0.17 0.840
22 Delays in contractor’s payments to subcontractors 3.47 19.28 0.000
23 Delays in site preparation 2.26 3.62 0.031
24 Delay in contractor’s claims settlements 3.02 19.48 0.000
(continued on next page)
674 G. Sweis et al. / International Journal of Project Management 26 (2008) 665–674

Appendix B (continued)
Labor (L) Overall F-Values P-Values
average
25 Work suspension by the owner 2.22 3.41 0.038
26 Too many change orders from owner 4.03 4.63 0.012
27 Slow decision making from owner 3.52 11.16 0.000
28 Inference by the owner in the construction operations 3.24 21.59 0.000
29 Delay in progress payments by the owner 3.43 13.01 0.000
30 Financial constraints faced by the owner 3.25 3.72 0.028
31 Insufficient coordination among the parties by the Owner 3.00 3.13 0.049
32 Ambiguities and mistakes in specifications and drawings 2.88 11.49 0.000
33 Poor qualification of consultant engineer’s staff assigned to the project 2.96 0.68 0.512
34 Delay in the approval of contractor submissions by the engineer 3.29 26.05 0.000
35 Poor coordination by the consultant engineer with the parties involved 2.70 1.87 0.161
36 Slow response by the consultant engineer regarding testing and inspection 2.81 2.00 0.141
37 Slow response by the consultant engineer to contractor inquiries 3.04 2.63 0.078
38 Severe weather conditions on the job site 1.85 0.73 0.485
39 Difficulties in obtaining work permits 2.18 1.83 0.166
40 Changes in Government regulations and laws 1.86 0.07 0.929

References [19] Dlakwa MM, Culpin MF. Reasons for overrun in public sector
construction projects in Nigeria. Int J Project Manage 1990;8(4):237–41.
[1] Stumpf G. Schedule delay analysis. Cost Eng J 2000;42(7):32–43. [20] Mansfield NR, Ugwu OO, Doran T. Causes of delay and cost
[2] Alkass S, Mazerolle M, Harris F. Construction delay analysis overruns in Nigerian construction projects. Int J Project Manage
techniques. Constr Manage Econ 1996;14(5):375–94. 1994;12(4):254–60.
[3] Assaf SA, Al-Khalil M, Al-Hazmi M. Causes of delay in large [21] Semple C, Hartman FT, Jergeas G. Construction claims and disputes:
building construction projects. J Manage Eng 1995;11(2):45–50. causes and cost/time overruns. J Constr Eng Manage, ASCE
[4] Mezher T, Tawil W. Causes of delays in the construction industry in 1994;120(4):785–95.
Lebanon. Eng Constr Arch Manage J 1998;5(3):252–60. [22] Ogunlana SO, Promkuntong K, Jearkjirm V. Construction delays in a
[5] Al-Khalil M, Al-Ghafly M. Important causes of delay in public utility fast-growing economy: comparing Thailand with other economies.
projects in Saudi Arabia. Constr Manage Econ 1999;17(5):647–55. Int J Project Manage 1996;14(1):37–45.
[6] Koushki PA, Al-Rashid K, Kartam N. Delays and cost increases in [23] Lo TY, Fung IWH, Tung KCF. Construction delays in Hong Kong
construction of private residential projects in Kuwait. Constr Manage civil engineering projects. J Constr Eng Manage, ASCE
Econ 2005;23(3):285–94. 2006;132(6):636–49.
[7] Al-Moumani A. Construction delays: a quantitative analysis. Int J [24] Chan DWM, Kumaraswamy MM. Reasons for delay in civil
Project Manage 2000;18(4):51–9. engineering projects—the case of Hong Kong. Hong Kong Instit
[8] Odeh AM, Battaineh HT. Causes of construction delay: traditional Eng Trans 1996;2(3):1–8.
contracts. Int J Project Manage 2002;20(1):67–73. [25] Shi J, Cheung S, Arditi D. Construction delay computation method. J
[9] Aibinu A, Odeyinka H. Construction delays and their causative Constr Eng Manage, ASCE 2001;127(1):60–5.
factors in Nigeria. J Constr Eng Manage 2006;132(7):667–77. [26] Seymour Sudman. Applied sampling. New York: Academic Press;
[10] Drewin FJ. Construction productivity: measurement and improve- 1976. p. 86–7.
ment through work study. Elsevier; 1985. [27] Hegab MY, Smith JR. Delay time analysis in microtunneling
[11] Assaf SA, Al-Hejji S. Causes of delay in large construction projects. projects. J Constr Eng Manage, ASCE 2007;133(2):191–5.
Int J Project Manage 2006;24(4):349–57. [28] Abdul-Rahman H, Berawi MA, Berawi AR, Mohamed O, Othman
[12] Zikmund W. Business research methods (Thomson-South-Western); M, Yahya IA. Delay mitigation in the Malaysian construction
2003. p. 388–89. industry. J Constr Eng Manage 2006;132(2):125–33.
[13] Kaming P, Olomolaiye P, Holt G, Harris F. Factors influencing [29] Youngjae K, Kyungrai K, Dongwoo S. Delay analysis method using
construction time and cost overruns on high-rise projects in Indone- delay section. J Constr Eng Manage 2005;131(11):1155–64.
sia. Constr Manage Econ 1997;15(1):83–94. [30] Yates JK, Epstein A. Avoiding and minimizing construction delay
[14] Alaghbari W, Razali M, Kadir S, Ernawat G. The significant factors claim disputes in relational contracting. J Profl Issues Eng Educ Pract
causing delay of building construction projects in Malaysia. Eng 2006;132(2):168–79.
Constr Arch Manage 2007;14(2):192–206. [31] Sambasivan M, Wen Soon Y. Causes and effects of delays in Malaysian
[15] Faridi AS, El-Sayegh SM. Significant factors causing delay in the UAE construction industry. Int J Project Manage 2007;25(5):517–26.
construction industry. Constr Manage Econ 2006;24(11):1167–76. [32] Zaneldin EK. Construction claims in United Arab Emirates: types,
[16] Baldwin JR, Mathei JM, Rothbart H, Harris RB. Causes of delay in the causes, and frequency. Int J Project Manage 2006;24(5):453–9.
construction industry. J Constr Division, ASCE 1971;97(2):177–87. [33] Zwikael O, Cohen Y, Sadeh A. Non-delay scheduling as a managerial
[17] Arditi D, Akan GT, Gurdamar S. Reasons for delays in public approach for managing projects. Int J Project Manage
projects in Turkey. Constr Manage Econ 1985;3:171–81. 2006;24(4):330–6.
[18] Okpala DC, Aniekwu AN. Causes of high costs of construction in [34] Arditi D, Pattanakitchamroon T. Selecting a delay analysis method in
Nigeria. J Constr Eng Manage, ASCE 1988;114(2):233–44. resolving construction claims. Int J Constr Manage 2006;24(2):145–55.

S-ar putea să vă placă și