% AVANCE PLANIFICADO % AVANCE REAL

PROGRAMADO EJECUTADO
MES PROGRAMADO MES EJECUTADO
ACUMULADO ACUMULADO
1 78.89% 78.89% 1 78.89% 78.89%
2 17.07% 95.96% 2 17.07% 95.96%
3 3.76% 99.72% 3 3.76% 99.72%
4 0.28% 100.00% 4 0.28% 100.00%
INFORME 2
CONTROL DE PAGO DE VALORIZACIONES

N° Mes Sub Total IGV Total


1 Oct-13 151,733.66 27,312.06 179,045.72
2 Nov-13 43,012.12 7,742.18 50,754.30

CONTROL DE AVANCE DE OBRA EN GENERAL

Avance Avance
Avance Avance
Mes Programado Ejecutado
Programado Ejecutado
Acumulado acumulado

Oct-13 78.89% 78.89% 71.77% 71.77%


Nov-13 17.07% 96.06% 20.34% 92.11%
Dec-13 3.76% 99.82%
Jan-14 0.18% 100.00%

CONTROL DE GARANTÍAS
INFORME 3
CONTROL DE PAGO DE VALORIZACIONES

CONTROL DE AVANCE DE OBRA EN GENERAL

CONTROL DE GARANTÍAS