Case Study
PROJECT SCOPE STATEMENT
PETRONAS TWIN TOWER 2
Tabla de contenido
1. INTRODUCTION ............................................................................................................ 2
2. OBJECTIVES .................................................................................................................. 2
3. SCOPE DESCRIPTION ..................................................................................................... 2
4. REQUIREMENTS ............................................................................................................ 3
5. PROJECT BOUNDARIES .................................................................................................. 3
6. DELIVERABLES .............................................................................................................. 4
Project Management ........................................................................................................ 4
Design and Engineering Plans ............................................................................................ 4
Construction .................................................................................................................... 4
7. ACCEPTANCE CRITERIA .................................................................................................. 5
8. CONSTRAINTS ............................................................................................................... 6
Time ................................................................................................................................ 6
Budget ............................................................................................................................. 6
Design.............................................................................................................................. 6
Geographical .................................................................................................................... 6
Climate ............................................................................................................................ 6
Structural ......................................................................................................................... 6
9. ASSUMPTIONS .............................................................................................................. 7
10. WORK BREAKDOWN STRUCTURE .............................................................................. 7
11. WBS DICTIONARY ...................................................................................................... 8
pág. 1
PROJECT SCOPE STATEMENT
PETRONAS TWIN TOWER 2
1. INTRODUCTION
The Project Scope Statement is a main document that serve for defining the
scope of the Petronas Twin Towers Project, in this project also must include the
deliverables work, this is necessary to ensure a common understanding of the
project.
Any change to the scope statement must be vetted in the original and approved
project, all the changes must be check before the implementation.
2. OBJECTIVES
Create a structure that would represent the growing success of his country, also
attract the tourists and the local people feel proud of their city.
3. SCOPE DESCRIPTION
The Petronas Twin Towers, is a project that has a development design of twin
skyscrapers, located in Malaysia (Kuala Lumpur), built with a Postmodern
Architectural style that will be used as Commercial offices and tourist attraction;
the towers are connected by a bridge between them. The towers reach a height
of 451, 9 meters and a total 88 floors, and they will be the tallest buildings in the
world.
pág. 2
PROJECT SCOPE STATEMENT
PETRONAS TWIN TOWER 2
4. REQUIREMENTS
The main requirements in the Petronas Towers are:
5. PROJECT BOUNDARIES
The Petronas Towers project includes all planning, designing and building
associated work.
The Petronas Towers is project that embrace all type engineering and
planification, reports, meeting of work, lab, foundation, build, sky bridge, testing
pág. 3
PROJECT SCOPE STATEMENT
PETRONAS TWIN TOWER 2
material, manual and also a great human team, however into the project have
delimited thing as the height, the pinnacles, glasses and time restrains.
6. DELIVERABLES
Project Management
Project Management documentation.
Proposal
Weekly work meetings
Manuals
Engineering report including updates on progress, schedule and
Budget
Certifications
Completed safety plan including both fire safety plan and Terrorism
safety plan.
Design and Engineering Plans
Design drawings
Design documents
Structural:
Construction
The tower should be complete the internal structure and finishes:
pág. 4
PROJECT SCOPE STATEMENT
PETRONAS TWIN TOWER 2
Utilities:
7. ACCEPTANCE CRITERIA
All services have passing the running test and are stable in its functions
and certificates are available and signed by competent and qualified
bodies.
The construction of the Petronas Towers is made according to the
country and city legislation and regulations.
Customer can to receive part of the works if that part is accord with the
plant and specification.
Quality dossiers are handed over to customer at the time the Provisional.
The towers once completed should match with the defined and signed off
Requirements.
pág. 5
PROJECT SCOPE STATEMENT
PETRONAS TWIN TOWER 2
8. CONSTRAINTS
Time
The time frame is limited to 6 years, when a similar project would need
up to 8 years.
Working hours will need to be unlimited 24 hours a day, 7 days per week.
Due to the heavy rains, there is an impact in team schedule and time.
Budget
The full Project is limited by USD $ 1.6 billion
Design
The exterior design of tower should represent the Islamic culture and be
unique.
Geographical
Malaysia is located in the heart of the monsoon Lack of light steels,
tender concrete
Climate
Heavy rain, aggressive weather, strong wind
Structural
Unstable bedrock
pág. 6
PROJECT SCOPE STATEMENT
PETRONAS TWIN TOWER 2
9. ASSUMPTIONS
During the rainy season, cheap labor will be available.
All-important stakeholders will come to the next meeting.
The Petronas Towers Project has full support from Malaysia Prime
Minister and government.
Builders working 24 hours/ 7 days a week is adequate to complete the
project in 6 years since its beginning.
Materials cost will not increase more than a 10 % in the following 2
years.
PETRONAS TOWER
CONSTRUCTION
1.1.1.1 Stimated 1.2.1.1Test in lab 1.2.3.1 Materials 1.3.2 Construction 1.6.2 Financial
1.2.2.1Architectural 1.2.3.2 Schedule 1.4.2 Colums 1.5.2 Glass Structure
Budget /validation specification equipment Reports
1.3.4 Structure
1.2.2.3 Electrical 1.4.4 Sky Bridge 1.5.4 facilities/Utilities
foundations
1.2.2.5 Mechanical
pág. 7
PROJECT SCOPE STATEMENT
PETRONAS TWIN TOWER 2
pág. 8
PROJECT SCOPE STATEMENT
PETRONAS TWIN TOWER 2
1.3.2 Construction
equipment esquema de empresas que incluye proveedores y
ejecución en el sitio
1.3.3 Ground 21m depth foundation excavation
excavation
1.3.4 Structure Concrete, once began he construction of the building,
foundations needs to be tested in order to grant its quality and
ressistance
1.4 Main Structural System
1.4.1 Concrete
System
1.4.2 Colums construction of the columns eleaboracion of iron sheets
1.4.3 Slabs/beam elaboration of sheet iron, supervision and control
1.4.4 Sky Bridge Achieve the solution that best fits the scenario. Brige
required for evacuation in case of fire.
1.4.5 Central Core Installation of the local elevators (those covering the
for elevators upper floors).
1.5 Interior and Exterior Structure and components
1.5.1 Wall int. and Cladding of walls and roofing of the 88 floors
ext.
1.5.2 Glass Incorporation of the windows in each of the 88 floors.
Structure
1.5.3 finishes Build up of the 88 floors in each tower
(floor, roof, External and internal painting
paint)
1.5.4 facilities/Utili activities designed to ensure that the
ties development and maintenance process is
adequate to ensure the whole building meet its
objectives.
1.6 Closing
1.6.1 final Report Final reporting to the management team upon
the development of the project.
1.6.2 Financial this financial report covers the entire construction and
financially details all aspects of the work
Reports
1.6.3 Technical is a document that is delivered at the end of the
Reports work in which covers infomorms, workbooks,
plans as built
pág. 9