PROJECT SCOPE STATEMENT

Jessica Cabrera Zamora


2018

Case Study
PROJECT SCOPE STATEMENT
PETRONAS TWIN TOWER 2

Tabla de contenido
1. INTRODUCTION ............................................................................................................ 2
2. OBJECTIVES .................................................................................................................. 2
3. SCOPE DESCRIPTION ..................................................................................................... 2
4. REQUIREMENTS ............................................................................................................ 3
5. PROJECT BOUNDARIES .................................................................................................. 3
6. DELIVERABLES .............................................................................................................. 4
Project Management ........................................................................................................ 4
Design and Engineering Plans ............................................................................................ 4
Construction .................................................................................................................... 4
7. ACCEPTANCE CRITERIA .................................................................................................. 5
8. CONSTRAINTS ............................................................................................................... 6
Time ................................................................................................................................ 6
Budget ............................................................................................................................. 6
Design.............................................................................................................................. 6
Geographical .................................................................................................................... 6
Climate ............................................................................................................................ 6
Structural ......................................................................................................................... 6
9. ASSUMPTIONS .............................................................................................................. 7
10. WORK BREAKDOWN STRUCTURE .............................................................................. 7
11. WBS DICTIONARY ...................................................................................................... 8

pág. 1
PROJECT SCOPE STATEMENT
PETRONAS TWIN TOWER 2

1. INTRODUCTION
The Project Scope Statement is a main document that serve for defining the
scope of the Petronas Twin Towers Project, in this project also must include the
deliverables work, this is necessary to ensure a common understanding of the
project.

Any change to the scope statement must be vetted in the original and approved
project, all the changes must be check before the implementation.

2. OBJECTIVES
Create a structure that would represent the growing success of his country, also
attract the tourists and the local people feel proud of their city.

3. SCOPE DESCRIPTION
The Petronas Twin Towers, is a project that has a development design of twin
skyscrapers, located in Malaysia (Kuala Lumpur), built with a Postmodern
Architectural style that will be used as Commercial offices and tourist attraction;
the towers are connected by a bridge between them. The towers reach a height
of 451, 9 meters and a total 88 floors, and they will be the tallest buildings in the
world.

Project Name: The Petronas Towers


Project Sponsor: Petronas Oil Company
KLCC Holdings Sdn Bhd
Stakeholders: Tun Dr. Mahathir Mohamad, KLCCB, Bovis Land
Design Project manager: Architect Cesar Pelli; (Pelli&Co)
Project manager: Bob Pratt (Tower 1)
Jon Dunsford (Tower 2)

pág. 2
PROJECT SCOPE STATEMENT
PETRONAS TWIN TOWER 2

Charlie Thornton (chief engineer)


Constructors: Hazama Corporation (Tower 1)
Samsung C&T and Kukdong Engineering &
Construction (Tower 2)
Time frame: 6 years

4. REQUIREMENTS
The main requirements in the Petronas Towers are:

 The design of the buildings should follow the same patterns of


construction.
 The towers are joined by an air bridge at the 41st floor that should has
58.4 meters long, and give solution in case of fire.
 Each tower has 88 flats.
 Each tower is 451, 9 meters high. (Pinnacle -73.6).
 Each tower has 5 subterranean levels to parking places
 The skybridge has a rotational pin directly over the arch crown to
permit the crown rise and fall as towers move due to the heavy-winds.
 Seventy-six elevators need to be located in the towers.
 29 of the elevators will be double deck
 the elevators will ascend and descend at a speed of 23 feet per second
 The spires or pinnacles found on the top of both towers are also a
notable feature of Islamic buildings.

5. PROJECT BOUNDARIES
The Petronas Towers project includes all planning, designing and building
associated work.

The Petronas Towers is project that embrace all type engineering and
planification, reports, meeting of work, lab, foundation, build, sky bridge, testing

pág. 3
PROJECT SCOPE STATEMENT
PETRONAS TWIN TOWER 2

material, manual and also a great human team, however into the project have
delimited thing as the height, the pinnacles, glasses and time restrains.

6. DELIVERABLES

Project Management
 Project Management documentation.
 Proposal
 Weekly work meetings
 Manuals
 Engineering report including updates on progress, schedule and
Budget
 Certifications
 Completed safety plan including both fire safety plan and Terrorism
safety plan.
Design and Engineering Plans
 Design drawings
 Design documents
 Structural:

Resist lateral wind forces up to 250 km/h.

(16) Cylindrical high-strenght concrete columns connected by a ring


beam at each level.

Concrete should be consistent between the perimeter columns and


range from 80 MPa at the base to 40 MPa at the top.

Support building in limestone site flooring and resist 300,000.00


metric tons weight.

Core structure in order to house the elevators.

Construction
 The tower should be complete the internal structure and finishes:

pág. 4
PROJECT SCOPE STATEMENT
PETRONAS TWIN TOWER 2

The final architecture must follow the design approved.


The final architecture interior and exterior should be delivered with
high light finishes.
The interior architecture as door, furniture, bathrooms etc., should
be high quality and luxurious.

 Utilities:

Working hot/cold water system for supply and movement of water.

Cool-down mechanical system composed by 12 feet diameter


wheels meant to rotate slowly to supply and exhaust air streams
and drop humidity of air supply from 90% to 70% and reduce fresh
air cooling by more than 50%.

The installation of electrical systems should meet international


safety standards and architectural plans.

The elevators should be high speed ones in order to make 58 lifts


to transport 10000 people.

7. ACCEPTANCE CRITERIA
 All services have passing the running test and are stable in its functions
and certificates are available and signed by competent and qualified
bodies.
 The construction of the Petronas Towers is made according to the
country and city legislation and regulations.
 Customer can to receive part of the works if that part is accord with the
plant and specification.
 Quality dossiers are handed over to customer at the time the Provisional.
 The towers once completed should match with the defined and signed off
Requirements.

pág. 5
PROJECT SCOPE STATEMENT
PETRONAS TWIN TOWER 2

 Cumplir con todos los entregables dentro del tiempo y el presupuesto


programados.

8. CONSTRAINTS

Time
The time frame is limited to 6 years, when a similar project would need
up to 8 years.

Working hours will need to be unlimited 24 hours a day, 7 days per week.
Due to the heavy rains, there is an impact in team schedule and time.

Excavation and foundation time frame: 1 year.

4 days of construction per floor.

Budget
The full Project is limited by USD $ 1.6 billion

Design
The exterior design of tower should represent the Islamic culture and be
unique.

Tallest buildings in the world

Geographical
Malaysia is located in the heart of the monsoon Lack of light steels,
tender concrete

Climate
Heavy rain, aggressive weather, strong wind

Structural
Unstable bedrock

pág. 6
PROJECT SCOPE STATEMENT
PETRONAS TWIN TOWER 2

9. ASSUMPTIONS
 During the rainy season, cheap labor will be available.
 All-important stakeholders will come to the next meeting.
 The Petronas Towers Project has full support from Malaysia Prime
Minister and government.
 Builders working 24 hours/ 7 days a week is adequate to complete the
project in 6 years since its beginning.
 Materials cost will not increase more than a 10 % in the following 2
years.

10. WORK BREAKDOWN STRUCTURE

PETRONAS TOWER
CONSTRUCTION

1.5 Interior and


1.1 Project 1.2 Integral Desing 1.4 Main Structural
1.3 Foundations Exterior Structure and 1.6 Closing
Management and Engineering Plans System
components

1.1.1 Project 1.1.2 Management 1.3.1 construction


1.2.1 Foundations 1.2.3 Technical 1.5.1 Wall int. and
Management and Control Reports 1.2.2 Plans firm selection 1 and 2 1.4.1 Concrete System 1.6.1 final Report
requirement Memories ext.
Planning and Documents towers

1.1.1.1 Stimated 1.2.1.1Test in lab 1.2.3.1 Materials 1.3.2 Construction 1.6.2 Financial
1.2.2.1Architectural 1.2.3.2 Schedule 1.4.2 Colums 1.5.2 Glass Structure
Budget /validation specification equipment Reports

1.3.3 Ground 1.5.3 finishes (floor, 1.6.3 Technical


1.2.2.2 Engineering 1.2.3.3 Final Budget 1.4.3 Slabs/beam
excavation roof, paint) Reports

1.3.4 Structure
1.2.2.3 Electrical 1.4.4 Sky Bridge 1.5.4 facilities/Utilities
foundations

1.4.5 Central Core for


1.2.2.4 Plumping
elevators

1.2.2.5 Mechanical

1.2.2.6 Details Plans

pág. 7
PROJECT SCOPE STATEMENT
PETRONAS TWIN TOWER 2

11. WBS DICTIONARY

CA: Package: Name: Description:


1.1 Project Management
1.1.1 Project Set of procedures for creating and maintaining the
Management attributes of engineering drawings.
Planning
1.1.1.1 Stimated initial budget
Budget
1.1.2 Management Petronas towers document and progress reports issue
and Control for all stakeholders
Reports and
Documents
1.2 Integral Desing and Engineering Plans
1.2.1 Foundations The concrete receipe created in the laboratory needs
requirement to be tested in order to grant the resistance needed.
1.2.1.1 Test in lab Concrete, once began he construction of the building,
/validation needs to be tested in order to grant its quality and
ressistance.
1.2.2 Plans elaboration of plans and approval by the client
1.2.2.1 Architectural Petronas Towers detailed design documentation in
regard of dimensions, quantities, façade, partitions,
features and services.
1.2.2.2 Engineering Petronas Towers detailed design documentation in
regard of facilities, equipment, systems and
technology
1.2.2.3 Electrical Electrical installation and conditioning.
1.2.2.4 Plumping Plumbing installation and conditioning.
1.2.2.5 Mechanical Petronas Towers engineering design and
documentation for sky bridge.
1.2.2.6 Details Plans Petronas Towers detailed design documentation in
regard of gardens, outside furniture, signaling and
urbanization.
1.2.3 Technical Elaboration of manuals and technical memories
Memories
1.2.3.1 Materials Petronas Towers construction material supply
specification scheme including on-shore and off-shore
1.2.3.2 Schedule Petronas Towers Time Schedule documents
1.2.3.3 Final Budget final budget report
1.3 Foundations
1.3.1 construction Petronas Towers engineering design and
firm selection documentation for building foundation works,
1 and 2 including all ground works, footings, piles and slabs
towers

pág. 8
PROJECT SCOPE STATEMENT
PETRONAS TWIN TOWER 2

1.3.2 Construction
equipment esquema de empresas que incluye proveedores y
ejecución en el sitio
1.3.3 Ground 21m depth foundation excavation
excavation
1.3.4 Structure Concrete, once began he construction of the building,
foundations needs to be tested in order to grant its quality and
ressistance
1.4 Main Structural System
1.4.1 Concrete
System
1.4.2 Colums construction of the columns eleaboracion of iron sheets
1.4.3 Slabs/beam elaboration of sheet iron, supervision and control
1.4.4 Sky Bridge Achieve the solution that best fits the scenario. Brige
required for evacuation in case of fire.
1.4.5 Central Core Installation of the local elevators (those covering the
for elevators upper floors).
1.5 Interior and Exterior Structure and components
1.5.1 Wall int. and Cladding of walls and roofing of the 88 floors
ext.
1.5.2 Glass Incorporation of the windows in each of the 88 floors.
Structure
1.5.3 finishes Build up of the 88 floors in each tower
(floor, roof, External and internal painting
paint)
1.5.4 facilities/Utili activities designed to ensure that the
ties development and maintenance process is
adequate to ensure the whole building meet its
objectives.
1.6 Closing
1.6.1 final Report Final reporting to the management team upon
the development of the project.
1.6.2 Financial this financial report covers the entire construction and
financially details all aspects of the work
Reports
1.6.3 Technical is a document that is delivered at the end of the
Reports work in which covers infomorms, workbooks,
plans as built