“Fitness for Purpose”

Obligations in
Construction Contracts
The Supreme Court decision in MT Højgaard v E.ON

By Paul Buckingham

In a rare decision concerning a construction contract, the


Supreme Court held that a “fitness for purpose” obligation
contained within a schedule to a construction contract was to be
given its natural meaning and effect, and that the warranty of
fitness was not inconsistent with the other terms of the contract.

The ruling sets aside the decision of and the monopiled foundations. One of the and notified MTH of a defect under the
the Court of Appeal and restores an inherent characteristics of the code was contract. The parties subsequently reached
earlier judgment of the Technology and that it provided for a probabilistic design, agreement on the cost of remedial works
Construction Court, which had held that which did not guarantee performance. in the sum of €26.25 million, leaving it for
the fitness for purpose obligation required In other words, there was always an inherent the court to decide which of them should
the contractor to achieve a result, namely risk that the foundation might fail if, for bear the cost.
that the foundations would last for example, the 100 year wave came in the
20 years. The case affirms the position first operational year of the windfarm.
that the courts are inclined to give full This meant that there was always a risk Procedural History
effect to the terms of a contract and to of failure, albeit a very low risk (being in
a requirement that a product complies the range 10-4 to 10-5), which had to be In the Technology and Construction Court,
with the contractual specification. allocated contractually between the parties. Mr Justice Edwards-Stuart held that MTH
had not been negligent in the design of
However, in 2009, slippage of the transition the grouted connection but that it was
Background pieces at the Egmond aan Zee windfarm led nonetheless responsible for the cost of
to the discovery of a fundamental problem the necessary rectification work by reason
The matter arose out of the construction within the code: the calculation of the axial of a breach of the ”fitness for purpose”
of the Robin Rigg offshore wind farm, strength for plain pipe grouted connections obligation within the contract
located in the Solway Firth on the North was overestimated by a factor of about ten, with E.ON. MTH appealed.
West coast of Britain. MT Højgaard (“MTH”) with the result that connections designed
was engaged as the design and build to the code were bound to fail (although The Court of Appeal allowed MTH’s appeal,
contractor for the foundations by the this problem did not affect two UK offshore deciding that there was no ‘fitness for
operator, E.ON Climate and Renewables (“E. windfarms which had been designed using purpose’ obligation within the contract.
ON”). The windfarm was to be built to the shear keys within the grouted connection). It noted that the industry expected
offshore code DNV-OS-J101, which included compliance with the well known J101
guidelines for the design of the grouted In 2010, E.ON inspected the Robin Rigg standard, but that it was also generally
connection between the transition pieces windfarm, noted that slippage had occurred known that compliance with J101 did not

-6-
guarantee that the foundation would have (x) so that each item of Plant and the Technical Requirements involved MTH
an operational life of 20 years. It said that, Works as a whole shall be free from warranting either that the foundations
whilst two paragraphs of the Technical defective workmanship and materials would have a lifetime of 20 years or agreeing
Requirements at first sight constituted a and fit for its purpose as determined that the design of the foundations would be
20 year warranty, all the other provisions of in accordance with the Specification such as to give them a lifetime of 20 years.
the contract pointed the other way, referring using Good Industry Practice…” In those circumstances, he considered that
to a ‘design life’ and the requirement to there were only two arguments realistically
exercise reasonable skill and care in the Within the Technical Requirements open to MTH as to why the paragraphs
design of the foundations. The Court of (which the parties agreed was the should not be given their natural meaning,
Appeal considered that the paragraphs intended reference to the Specification both of which were mutually reinforcing.
within the Technical Requirements were in clause 8.1(x)), it stated that:
“too slender a thread” upon which to hang a “… where different or inconsistent
finding that MTH had warrantied a 20 year “3.2.2.2 Detailed Design Stage standards were imposed, the correct
lifetime for the foundations. E.ON appealed The detailed design of the foundation analysis was that the more rigorous or
to the Supreme Court. structures shall be according to the demanding of the two requirements
method of design by direct simulation of must prevail…”
“The primary question which the court the combined load effect of simultaneous
had to answer was whether the clause … load processes (ref: DNV-OS-J101)…. The first argument was that the warranty
meant that MT Højgaard had warrantied would be inconsistent with the obligation
a 20 year lifetime for the foundations, The design of the foundations shall to comply with J101. Lord Neuberger
or that MT Højgaard only had to design ensure a lifetime of 20 years in every reviewed the approach of the English (and
with reasonable care and diligence.” aspect without planned replacement. Canadian) courts and concluded that they
The choice of structure, materials, were generally inclined to give full effect
corrosion protection system operation to a requirement that an item produced
“Fitness for Purpose” Obligation and inspection programme shall be complied with the prescribed criteria on
made accordingly.” the basis that, even if the employer had
MTH’s general obligations were set out in specified or approved the design, it is the
the Conditions of Contract as follows: The primary question which the court had contractor who would be expected to take
to answer was whether the clause 8.1(x), the risk:
“8.1 General Obligations when read with clause 3.2.2.2 of the
The Contractor shall, in accordance with Technical Requirements, meant that MTH “…even if the customer or employer
this Agreement, design, manufacture, had warrantied a 20 year lifetime for the has specified or approved the design,
test, deliver and install and complete foundations, or that MTH only had to design it is the contractor who can be expected
the Works: with reasonable care to take the risk if he agreed to work to
and diligence following the design a design which would render the item
(i) with due care and diligence expected methodology in J101. incapable of meeting the criteria to
of appropriately qualified and which he has agreed.”
experienced designers, engineers and In giving the judgment of the court, Lord
constructors (as the case may require); Neuberger was of the view that the natural
... meaning of paragraph 3.2.2.2 of the

-7-
He noted that compliance with J101 of construction of contractual documents “I accept that redundancy is not
was stated in the contract to be one of that the intention of the parties must normally a powerful reason for declining
the “MINIMUM requirements” of E.ON be ascertained from the language that to give a contractual provision its natural
and concluded that, where different or they have used interpreted in the light meaning especially in a diffuse and
inconsistent standards were imposed, the of the relevant factual situation in which multi-authored contract (see In re
correct analysis was that the more rigorous the contract was made”, although he Lehman Bros International (Europe) (in
or demanding of the two requirements added that “the poorer the quality of the administration) (No 4) [2017] 2 WLR 1497,
must prevail (as the less rigorous standard drafting, the less willing any court should para 67). However, it is very different,
could properly be treated as a minimum be to be driven by semantic niceties to and much more difficult, to argue that
requirement): attribute to the parties an improbable a contractual provision should not be
and unbusinesslike intention.” given its natural meaning, and should
“…if there is an inconsistency between instead be given no meaning or a
a design requirement and the required Applying those principles, Lord Neuberger meaning which renders it redundant.”
criteria, it appears to me that the effect considered that paragraph 3.2.2.2 was
of para 3.1(ii) would be to make it clear clear in its terms in imposing a duty E.ON’s appeal was accordingly allowed and
that, although it may have complied with on MTH that the foundations would the order of the TCC restored, holding that
the design requirement, MTH would be have a lifetime of 20 years. He was “not MTH had warrantied that the foundations
liable for the failure to comply with the impressed” with the argument that it would have a 20 year life.
required criteria, as it was MTH’s duty would be surprising that the operative
to identify the need to improve on the obligation was in an essentially technical
design accordingly.” document, rather than being spelled out Conclusions
in the contract itself, nor was he
The second argument was that the persuaded by the argument that the It is typical in construction contracts,
operative paragraphs were “too slender operative obligation should not have both domestically and internationally,
a thread” upon which to hang such been “tucked away” within the Technical for the purpose of the project to be
an important and potentially onerous Requirements. Lord Neuberger thought defined in the technical requirements
obligation. Whilst the contract was long that it was “scarcely surprising” that a of the contract.1 The Supreme Court has
and multi-authored, Lord Neuberger provision in the Technical Requirements confirmed that there is nothing inherently
did not believe that it altered the court’s addressing specific conditions at the wrong with allocating risk in this way,
approach to the proper interpretation of the detailed design stage included a although parties would be well advised
contractual documents: provision of fitness for purpose. to ensure that the operative words are
clear and unambiguous.
“…the court has to do its best to “…parties would be well advised to
interpret the contractual arrangements ensure that the operative words are In addition, the Supreme Court has
by reference to normal principles. As clear and unambiguous.” confirmed that in contracts of double
Lord Bridge of Harwich said, giving the obligation, whereby there is an express
judgment of the Privy Council in Mitsui He also did not see why this could be contractual performance warranty
Construction Co Ltd v Attorney General said to be an improbable or unbusinesslike in addition to a requirement that the
of Hong Kong (1986) 33 BLR 7, 14, interpretation that should be given contractor complies with a particular
“inelegant and clumsy” drafting of “a no meaning: specification put forward by the employer,
badly drafted contract” is not a “reason that the more onerous of the obligations
to depart from the fundamental rule is enforceable, even where the defect is
the result of the employer’s specification.

1 see, for example, the approach in the FIDIC Yellow Book


(1999 Edition) and the IChemE Red Book (2013 edition)

-8-