Documente Academic
Documente Profesional
Documente Cultură
Document
GETABEC
A.I CUSTOMER
Reference Document/Drawings/ Standard Production QA/QC
Item Area of activity Quality control activity Acceptance Criteria
Code
Point
Point
Point
Point
Signature Date Signature Date Signature Date Signature Date
1.1 Design data/calculations Review design data and calculations Technical requirement
D H H H H
Design code and standard ASME VIII & Project spec.
1.2 Drawing for approval Review drawing for approval Design Calculation,code and standard ASME VIII & Project spec. D H H H H
1.3 Drawing for construction Review drawing for construction Design calculations
D H H H H
Approved drawing ASME VIII & Project spec.
2 Material
2.1 Raw material for pressure part Verify material certificates and mfg. stencil marks Material certificates
D H H R
Material receiving reports Material specification
22
2.2 Raw material for non-presure pt.
pt Visual and dimensional inspection Drawing for construction
D H H
Purchase order Material specification
3 Welding
3.1 Welding Procedure Specification Review WPS Drawing for construction ASME IX D H H R H
(WPS)
3.2 Procedure Qualification Record Review test records (existing) WPS ASME IX D H H R H
(PQR) Witness PQR test (new) and review test records. Test records D H H R H
3.3 Welder Qualifiaction Test (WQT) Review welder certificates (existing) Welder certificates,WPS ASME IX D H H R R
Witness welder test (new) and review test records. Drawing for construction D H H R R
3.4 Weld map/Welding NDE scedule Weld map and Weld&NDE schedule preparation Drawing for construction & WPS ASME IX,WPS D H H R R
4 Pre- fabrication
4.1 1) Material Material identification check Material identification record UG-77,UG-94Sec VIII Div.1 H H R
4.1.1 Head
3) Forming (press) Process check Drawing for con.,Fabrication Standard UG-79 Sec VIII Div.1 R R
4) Spinning a) Dimension and thickness check Dimension report UG-79,81,96, Sec VIII Div.1 D H H R
b) Ground smooth & flush for all temporary weld Drawing for con.,Fabrication
con Fabrication Standard UG 95 Sec VIII Div.1
UG-95, Div 1 R R
5) Cutting & beveling Edge preparation check Drawing for con., WPS UG-76,UW31,Sec viii Div.1 H H
4.1.2 Shell
1) Material Material identification check Material identification record UG-77,UG-94Sec VIII Div.1 H H R
3) Cutting & beveling a) Dimension check Drawing for con., WPS Weld map,drawing H H
(alignment,gap,cleanliness inspection)
5) Forming (rolling) Out of roundness Drawing for con. UG-79,UG-96, Sec VIII Div.1 H H
d) Review RT Film & Reports RT Film & Reports UW-51,Sec VIII Div.1 D - R R
4.2 Nozzle
3) Cutting & grinding Edge preparation check Drawing for con., WPS UW-31,UW-32,UW-33, R R
4) Fit-up
Fit up flange to neck & weld a) Dimension check Drawing for con
con., WPS Weld map
map,drawing
drawing H H
5 Assembly
(alignment,fit-up,cleanliness inspection)
5.1.2 Circumferential weld a)WPS,welder,visual Inspection Drawing for con., WPS UW-31,UW-32,UW-33, H H
d) Review RT Film & Reports RT Film & Reports UW-51,Sec VIII Div.1 D - R R
(alignment,fit-up,cleanliness inspection)
5.2.2 Circumferential weld a)WPS,welder,visual Inspection Drawing for con., WPS UW-31,UW-32,UW-33, H H
d) Review RT Film & Reports RT Film & Reports UW-51,Sec VIII Div.1 D - R R
(alignment,fit-up,cleanliness inspection)
5.3.2 Circumferential weld a)WPS,welder,visual Inspection Drawing for con., WPS UW-31,UW-32,UW-33, H H
2 of 2
Document
GETABEC
A.I CUSTOMER
Reference Document/Drawings/ Standard Production QA/QC
Item Area of activity Quality control activity Acceptance Criteria
Code
Point
Point
Point
Point
Signature Date Signature Date Signature Date Signature Date
d) Review RT Film & Reports RT Film & Reports UW-51,Sec VIII Div.1 D - R R
d) Review RT Film & Reports RT Film & Reports UW-51,Sec VIII Div.1 D - R R
1) Opening on Head wall Orientation & elevation check Drawing for con., As drawing H H
(alignment,fit-up,cleanliness inspection)
(alignment,fit-up,cleanliness inspection)
6 1) Finishing (for internals & externals) a) PT all temporary weld Fabrication standard Sec VIII Div.1 H H
b) Final visual & dimension check Drawing for con., WPS As drawing H H W H
c) Final weld inspection Drawing for con., WPS No defect & clean H H W H
2) Inside Inspection Inside Cleanliness,Visual Inspection Project Spec,Fabrication Standard No defect & clean H H W
7 Hydrostatic Test a) Pressure Gauge calibration Calibration records Sec VIII Div.1 D H H R R
d) Holding time (1 Hr. , Held) Drawing for con., Design & Pressure test reports UG-102,vSec.VIII Div.1 H H H H
e) Leakage test Drawing for con., Design & Pressure test reports UG-102,vSec.VIII Div.1 D H H H H
10 Name plate Visual & Dimension Check Section VIII,Div.1 Section VIII,Div.1 H H H H
----------- End of Ammonia Storage Tank Fabrication Process and Ready for Transport to site------------------