Documente Academic
Documente Profesional
Documente Cultură
Industrial Boilers
GP 07-02-01
Scope
1) [I] This Global Practice (GP) covers the design, fabrication, and inspection of gas and oil fired water
tube (membrane or tangent tube) industrial boilers (other than gas turbine exhaust boilers) having
steam outlet conditions not exceeding 1700 psig (117221 kPa-g) and 960°F (515°C).
2) [I] An asterisk (*) indicates that a decision by Purchaser is required or that additional information is
specified by Purchaser.
Refining/Chemicals, Downstream
For ExxonMobil Use Only Version 2.0.0
Imperial Oil
Table of Contents
4. Documentation ...................................................................................................... 9
4.1. Proposal information .................................................................................... 9
4.2. Post Award Review .................................................................................... 10
4.3. Final Records ............................................................................................. 11
5. Materials............................................................................................................... 11
5.1. Drums and Headers ................................................................................... 11
6. Design .................................................................................................................. 12
6.1. General....................................................................................................... 12
6.2. Drums and Headers ................................................................................... 12
6.3. Superheater................................................................................................ 13
6.4. Convection Surface Cleaning ..................................................................... 14
6.5. Structure and Casing .................................................................................. 14
6.6. Observation and Access Doors .................................................................. 15
6.7. Platforms and Stairs ................................................................................... 15
6.8. Stack .......................................................................................................... 15
6.9. Burners ....................................................................................................... 16
6.10. Ducting and Windbox ................................................................................. 16
8. Testing ................................................................................................................. 28
9. Guarantee ............................................................................................................ 29
Table of Tables
1. Required References
[I] This Section lists the Practices, codes, standards, and specifications which shall be used with this
Practice.
2. Additional Requirements
1) * [I] This Section lists the Practices, code, and standards which shall be used with this Practice as
specified by Purchaser.
2) * [I] Proposals to use codes other than listed in Section 1 shall be submitted to Purchaser for approval
by Purchaser. To be considered for acceptance, the code must be acceptable to the inspecting
authority of the country in which the boiler will be installed.
ASME SEC VIII D1 Mandatory Appendix 6 Methods for Magnetic Particle Examination
MA APP 6 (MT)
ASME SEC VIII D1 Mandatory Appendix 12 Ultrasonic Examination of Welds (UT)
MA APP 12
3. Definitions
Term [I] Description
Effective projected radiant [I] In the furnace, this shall be calculated as the flat projected
surface area of exposed tubes and exposed extended surface integral
with tubes. Refractory covered surfaces shall not be included.
Calculation of furnace heat absorption is to be based on this
definition.
Radiant heating surface [I] In the furnace, this is defined as the flat projected area of
all surfaces enclosing the furnace volume exclusive of
superheater cavity opening. Calculation of furnace heat
release is to be based on this definition.
BMS - Supervised Automatic [I] This is an ExxonMobil term used to describe a burner
management system by which a boiler is purged and a burner
is started (ignited) automatically, as defined by NFPA 85, but
with specific hold points added for operator verification and
confirmation.
SIS - Safety Instrumented [I] Protective system designed per requirements of GP 15-07-
System 02. For boilers, the Burner Management System (BMS)
usually handles all protective functions and is the SIS.
Pilot [I] Burner main flame ignition device.
Igniter [I] Device to ignite pilot
4. Documentation
4.1. Proposal information
[I] A technical description, including the following information for the boiler and auxiliaries, shall be
supplied:
1) An itemized descriptive list of valves, instruments, controls, piping, and other boiler accessories
included in the scope of supply.
2) The system resistance curve, overplotted on the fan characteristic curve for all FD and ID fans, for
each operating combination.
3) Guaranteed ramp rates (load change) through entire range for:
a) Cold startup
b) Upward load charge
c) Downward load charge
4) A functional logic diagram showing the light-off and shutdown sequence for the burners.
5) Heat transfer surface in the furnace and boiler bank reported according to the definitions given in this
Practice.
6) The applicable performance data shown in Table 5 for the maximum continuous rating and other
specified operating points.
7) Dimensional drawing or drawings showing drum internals, drum and header material, outside
diameter, plate thickness; water and steam circuit arrangement, furnace configuration, burner
locations, flue and duct arrangements, and dimensions and material of expansion joints, size location
of observation, access and inspection doors, and sizes and locations of vents and drains.
8) Materials of construction.
9) Extent of platforming, ladders, and stairways to be supplied.
10) A list of exceptions to this Practice or, if there are no exceptions, a statement to this effect in the
proposal.
11) Maximum boiler turndown with all burners in operation and minimum recommended excess air for
the specified design fuel and fuel pressure.
12) The maximum capacity of liquid fuel guns—these shall be stated in lb/hr (kg/h).
13) The minimum load obtainable with combination firing.
14) A curve showing the variation of superheater outlet temperature with boiler load over the range of
operation of the boiler.
15) Method of tube replacement/plugging for each coil.
16) Complete description of all field work required—Drawings shall show all break points and weights of
individual shop assembled items.
17) A curve showing circulation rate versus steam production over the range of boiler operation.
5. Materials
5.1. Drums and Headers
1) * [S] Material with a maximum tensile strength in excess of 112,500 psi (775 MPa) is not acceptable.
Proposals to use proprietary alloy material shall be submitted for approval by the Owner's Engineer.
2) [R] A corrosion allowance of 1/ 16 in. shall be used for drums, headers, and crossover piping.
6. Design
6.1. General
1) * [R] Boiler design and fuel combination shall be commercially demonstrated in a similar service,
and operating range, including fuel transitions, to the satisfaction of the Owner's Engineer.
2) * [O], [R] Based on design fuel higher heating value, the maximum heat release at Maximum
Continuous Rating (MCR) in the furnace shall not exceed the limits shown in Table 1.
3) [O] Boiler and auxiliary equipment, with the exception of the forced draft fans and drivers, shall be
designed for at least 10 percent excess air for firing gas fuel and 15 percent excess air for firing oil
fuel or combination gas and oil fuel.
4) [O] All circuits and coils shall be drainable. For superheater exception, see Section 6.3, Item (1).
4) [O], [R] For boilers operating over 500 psig (3450 kPa), steam drum internals shall include
centrifugal type primary separators and secondary separators. Separators shall be sealed below water
level.
5) * Proposals to use other types of primary separators shall be submitted to the Owner's Engineer for
approval. To be considered for approval, Vendor must substantiate with test data from a commercial
unit that the solids content of steam entering the superheater will not exceed job specification
requirement when operating with water at high level and with specified boiler water concentration.
6) [R] Drums with wall thickness greater than 2 in. (50 mm) shall have welded connections as follows:
a) Connections greater than NPS 4 (100 mm) shall be according to Figures PW-16.1 (q-1), (q-2), (q-
3), or (q-4) of ASME SEC I.
b) Connections NPS 4 and less shall be as above or according to Figures PW-16.1 (a), (b), (c), (g),
(h). Figures PW-16.1 (y) or (z) may also be used for tube connections NPS 4 and less when the
tube wall thickness is less than 1/ 2 in. (13 mm).
7) [S], [R] Drums and headers, where both the wrapper plate and tubesheet exceed 2 in. (50 mm) in
thickness, shall be designed according to GP 05-01-02.
8) [R] The interior of the upper and lower drums shall be cleaned to SSPC SP 7 prior to tube installation.
9) [S], [R] Design of feedwater and chemical feed entry through steam drum shell shall be approved by
the Owner's Engineer. Use of a thermal sleeve is required when differential temperature between
fluids exceeds 100°F (38°C).
10) [S], [O] The steam drum shall:
a) Contain adequate volume to withstand the "shrink" and/or "swell" resulting from maximum
guaranteed ramp rates to and from MCR without reaching the high or low level alarm. For
calculation purposes, assume all steam bubbles collapse during a "shrink" occasion.
b) For boilers up to 600 psig provide minimum holdup of three minutes at MCR from low level
alarm to low level trip point, which is set just above the point where damage can occur (one inch
above level at which tubes are uncovered), unless specified otherwise.
c) * For boilers operating at over 600 psig provide minimum holdup of one minute at MCR from
low level alarm to low level trip point, which is set just above the point where damage can occur
(one inch above level at which tubes are uncovered), unless specified otherwise.
d) In calculating holdup time, Vendor shall consider only that water which can actually enter the
tubes within the stated time. Water cutoff from the tube by internal baffles or partitions must not
be considered.
11) [S] The steam drum shall be equipped with two man-ways, one at each end of the drum, with
minimum dimensions of 15 in. x 18 in.
12) If supplied, chevron drains to be piped below LWCO.
6.3. Superheater
1) [R] The superheater shall be arranged such that the inlet tubes are not located in the region of highest
flue gas temperature.
2) [R] * Boiler Vendor shall indicate whether the superheater is drainable or non-drainable. Vendor
shall have demonstrated experience with the proposed design and shall outline the proposed method
for internal cleaning of superheater coils.
RFCH, DIOL For ExxonMobil Use Only Version 2.0.0
2) [R] Membranes on membrane wall construction shall be welded to the adjoining tubes on the front
and back face of the membrane.
3) [O] Drains shall be furnished at the low point of the boiler furnace and bank areas to permit removal
of the flue gas deposits by water washing. Minimum opening shall be 3 in. (75 mm) diameter. Drain
openings shall be effectively sealed against flue gas bypassing and casing overheating.
4) [R] Metallic jacket covering boiler insulation shall have a minimum thickness of 0.05 in. (1.3 mm)
and shall be galvanized carbon steel sheet or corrugated aluminum sheet. Jacket shall also be
adequately reinforced to prevent buckling and vibration.
5) [S] Waterwall (flue gas path) design pressure shall be the maximum (shutoff) F.D. fan discharge
pressure if the boiler outlet flue gas path can be blocked—e.g., equipped with a flue gas damper.
6.8. Stack
[S] Top of stack shall be a minimum of 10 ft (3000 mm) above any equipment which is located within 50
ft (15 m) horizontally of the stack. The stack shall also be at least 10 ft (3000 mm) higher than any
working platform that is regularly used by operating or maintenance personnel (with a frequency of once
a day or greater), and is within a horizontal distance of 100 ft (30 m).
6.9. Burners
1) [R] Burners shall meet one of the following:
a) A burner which has been commercially proven in comparable service (service conditions, fuel,
orientations, turndown excess air, and heat release, fuel transitions, and individual fuel trips for a
multi-fuel burner).
b) A demonstration (of the burner being provided) under simulated field conditions to the
satisfaction of the Owner's Engineer.
2) [O] For liquid fuel only burners, there shall be a minimum of two fuel guns per boiler to facilitate
burner changes without loss of combustion. Operating procedures with recommended fuel conditions
shall be provided and demonstrated for such fuel gun transitions.
3) [O] Dual fuel burners shall be:
a) Capable of firing the gas and liquid fuels specified, both separately and simultaneously.
b) Dual rated—i.e., must be capable of meeting design requirements on each fuel, fired separately, if
specified.
c) [R] A boiler firing two primary fuels shall be designed to continue to operate when either primary
fuel trips. This shall be true over the entire operating window. Burner stability, during a switch
from two fuels to one fuel while at high excess air, shall be demonstrated at initial startup.
4) [S] A device shall be provided to prevent pressurized furnace gases from blowing out through burner
gun openings when guns are removed.
5) [S] Oil gun heads for liquid fuel shall be designed so that no fuel or steam will escape if head is
removed without first blocking fuel and steam lines.
6) [S], [M] All burners shall have interrupted spark ignited gas pilots (NFPA 85 Class 3). All pilots and
ignition sources shall be removable with burner in operation. * In special cases when gaseous fuel is
not available, NFPA 85 Class 3 direct electrical pilots may be used if approval is given by Owner.
7) [S] The burner vendor shall state the minimum to maximum level of excess combustion air where
burner stability is guaranteed.
a) These limits shall be confirmed in the field through rigorous testing for all specified fuels,
operating conditions and transitional fuel switches.
b) Air/fuel controls must be configured and tuned to keep the boiler within guaranteed burner
stability limits for all specified fuels, operating conditions and transitional fuel switches.
8) [S] All burner piping designs supplying fuel to more than two burners shall be analyzed for equal
distribution to each burner.
a) [S] If a zirconia type analyzer is used, then it shall be equipped with a flame arrestor to prevent
flame propagation in the event of ignition by the heated sensor.
b) [S] The power to the zirconia type analyzer shall also be removed automatically in the event of a
boiler trip. The analyzer power reset shall be performed automatically by the BMS. The
following alternatives to power shutoff are acceptable with Owner's Engineer approval:
i) For extractive systems, block the flue gas sample flow and replace with ambient or
instrument air.
ii) Flood the analyzer probe with calibration air.
In all cases, reset of the analyzer following a boiler trip shall not occur until after completion of
the subsequent firebox purge.
3) [R] Feedwater control shall be of the three-element type.
4) [S] Fail-Action direction for the following valves/dampers shall be:
a) Fuel-close
b) Fuel gas vent–open
c) Combustion air–remain stationary (tend to open on air bleed down)
d) Feedwater (steam drum level control)–remain stationary (tend to close on air bleed down)
e) Blowdown-close
f) Desuperheater water (steam temperature control) - remain stationary (tend to close on air bleed
down)
g) Atomizing medium remain stationary (tend to open on air bleed down)
h) FGR damper - remain stationary (tend to close on air bleed down)
5) [S] Combustion air flowrate measurement shall be by a venturi type meter. Where a venturi is not
possible because of construction reasons, pitot arrays may be used subject to Owner's approval. Pitot
array should allow for on-line removal of the array element to facilitate cleaning in case of nozzle
fouling.
a) Either type shall be sized to generate a pressure differential of not less than 6 in. (150 mm) H2O at
normal firing rate and excess air. This provides adequate turndown capability.
b) A single primary measuring element is acceptable for both control and protective system
requirements provided each input has a separate transmitter with its own root valves and there are
no intermediate valves which could isolate more than a single transmitter.
6) [S] Measurement method for loss of forced draft fan shall be low fan speed (measured by fan shaft or
wheel RPM).
7) [R] Firebox pressure taps shall be 2" minimum to prevent potential restriction/plugging.
8) [S] Where flow measurement requires two or more inputs (e.g., fuel, steam), a single orifice plate or
wedge meter is acceptable; however, separate taps shall be used for each transmitter.
9) [R] The use of bridle assemblies to reduce the number of vessel connections is permitted per GP 15-
05-01 Section 7.1. Owner shall approve the final configuration.
a) All pairs of taps for level transmitters shall span the same range of drum level.
b) The level control transmitter can share a bridle with the gauge glass. Each shall have separate
root valves so they can be maintained independently.
e) Flame detectors shall detect their burner's flame at all loads and during all load changes without
picking up radiation from other burner flames on multiple burner units.
f) Continuous pilots may not be used in place of flame detection except when specified by
Purchaser.
g) The time interval between loss of flame and stopping the fuel flow to the burner(s) shall be not
more than five seconds.
h) For high FGR applications (greater than 10%), flame scanner purge air source should be fresh air
only.
5) [S] The flame safeguard systems for front or opposed fired boilers shall be designed according to
NFPA 85 with the following additional requirements:
a) Dual flame detection shall be provided for each burner.
b) To trip the associated individual burner fuel shutdown valves (or main shutdown valves for single
burner units), 2-out-of-2 voting of the flame detectors is required for boiler reliability purposes.
i) A single detector flameout signal shall alarm in the main control room and on the local panel.
The local panel shall indicate which detector had the flameout signal.
ii) If the BMS is implemented using relays, flame detector relays shall operate individual burner
fuel shutdown valves without intermediate relays except additional relays necessary to
provide the required number of contacts.
iii) [S] For one burner units, two outputs from each detector shall be independently wired to the
BMS with 1oo2 trip voting logic for each scanner's dual inputs.
c) Single flame detectors for each burner are acceptable for multiple burner units with 8 or more
burners, with Owner's Engineer approval, and provided the following conditions are met:
i) The type of flame detector selected is capable of reliable detection over the entire operating
window, including the range of fuels, excess air levels and boiler loads.
ii) The burner vendor has confirmed that MCR steam production is feasible with any two
detectors out of service and the associated burners off-line.
6) [S] Tangentially fired boilers shall meet the requirements in Item (4) above, with the exception or
addition of the following:
a) The flame detectors must be designed/positioned such that an individual burner flame can be
detected without picking up radiation from other burners at firing rates up to the initiation of
"fireball" conditions. (e.g., 30% MCR)
Once the boiler is in "fireball" conditions individual burner light-offs shall be allowed to proceed
even if flame is sensed.
b) At firing rates below "fireball" conditions, individual burners shall be tripped based on the
individual flame scanner(s).
c) At firing rates above initiation of "fireball" conditions, a flame scanner voting scheme shall be
used to initiate a master fuel trip. The voting scheme shall be determined by the burner vendor
and approved by the Owner's Engineer.
d) Steam flow shall be used to determine when the boiler reaches "fireball" load conditions.
Three transmitters shall be used for this input to the BMS for 2oo3 voting logic.
e) [R] Single flame scanners are acceptable for single gun burners as long as there are a sufficient
number of burners such that loss of signal from any two detectors will not result in a boiler
shutdown.
RFCH, DIOL For ExxonMobil Use Only Version 2.0.0
7) [S] Input to the BMS for the steam drum low level boiler trip shall consist of three level transmitters
for 2oo3 voting logic.
c) For boilers with flue gas recirculation (FGR), the FGR damper closed position switch shall be a
purge permissive.
The open position switch shall be utilized to prove the FGR duct has been purged at the end of
the firebox purge cycle.
4) [S] A light-off checklist shall be permanently mounted on local panels.
5) [S], [O] All inputs tied into burner light-off permissive logic, including limit switches, shall be
provided with individual visual indication at the local panel to display the status.
e) Fuel shutdown and vent trip valves shall not be equipped with manual reset solenoids. These
solenoids shall be reset after a boiler trip and before initiating a boiler light-off sequence by a
Master Reset pushbutton on the local panel.
f) [R] Main fuel shutdown valves shall also be equipped with open limit switches, with a
discrepancy alarm only, for additional error detection and advance warning of drifting closed for
reliability.
8) [S] For boiler liquid fuel systems equipped with recycle downstream of the main shutdown valve
(e.g., high viscosity, heated fuels), a separate shutdown valve shall be provided on the recycle line. A
check valve alone is not considered adequate for this service.
9) [S] Main, individual and pilot burner fuel shutdown valves shall be located to achieve the minimum
practical piping volume between the valve and the burner.
10) [S] The fuel gas and pilot gas vent trip valve shall be provided for all types of fuel gas.
The NFPA 85 exception for heavier-than-air gases shall not apply.
11) [S] Fuel shutdown bypass valves shall be provided when the required boiler run length exceeds the
required protective system test interval as per GP 15-07-02.
a) On multiple burner boilers, bypass valves shall not be provided for individual burner fuel
shutdown valves, as individual burners can be shutdown for testing.
b) Bypass valves provided around the main fuel shutdown valves shall be CSC and provided with
limit switches initiating an alarm when the bypass valves are not fully closed. The fully closed
position of the bypass valves shall be included as a purge/lightoff permissive. In addition, these
valves shall also be provided with a warning sign as per GP 15-07-02, Section 4.3, stating
"CAUTION - THIS VALVE TO BE USED ONLY FOR CHECKING PROTECTIVE
SYSTEMS."
c) For dual shutdown valve installations, each shutdown valve shall be equipped with a separate
bypass valve to allow testing one shutdown valve at a time. This prevents loss of complete
protection during testing.
d) The entire BMS must be designed/programmed to provide for on-line testing, one shutdown valve
at a time, in this case.
12) [S] Facilities shall be provided to allow nitrogen leak testing of fuel trip valves/vent combinations, as
well as fuel trip valve bypasses if equipped, during maintenance downtimes.
Exception: Automated leak testing prior to each light-off, as defined by NFPA 85, is not required,
unless specified by the Owner's Engineer based on leakage experience with a fouling/dirty fuel or as
required by local codes.
SDOP + f (SHOP)
SDSP =
0.95
SHSP
f = − 1
SHOP
Where:
SDSP = Steam Drum Set Pressure
SDOP = Steam Drum Operating Pressure
SHSP = Superheater Set Pressure
SHOP = Superheater Operating Pressure
5) [S] A common steam condensate/disengaging drum, discharging to the sewer and vented to a safe
location, shall be provided for the following vents and drains:
a) Economizer, steam generation and superheater drains
b) Level gauge drains
c) Atomizing steam warm-up vents
d) Soot-blower warm-up vents
e) Any other services expected to discharge hot flashing condensate or steam during boiler start-up,
shutdown or re-start.
f) All vent and drain connections to this closed system shall be provided with a manual bleeder at
the source takeoff point for flow verification purposes.
6) [R] Boiler outlet steam piping shall be considered to be in "process induced vibrating service" for the
purpose of designing small bore piping support per GP 03-18-01. High vibration is likely during
steam blowing activities.
7) [S] All burner piping designs supplying fuel and, if applicable, atomizing media to two or more
burners shall confirm, by calculation, equal distribution to each burner.
3) [R] Magnetic particle inspection of nozzle welds and a random selection of 10 percent of the welds
joining the shell to a tube or tube stub shall be according to the ASME SEC VIII D1 MA APP 6.
Both sides of the completed weld, where accessible, shall be examined after any post weld heat
treatment. If back welding is done, the back side of the root pass shall be examined after it has been
prepared for back welding. The D-C prod method shall be used prior to post weld heat treatment and
the A-C yoke or coil method after final post weld heat treatment.
4) [R] Ultrasonic examination. All piping welds where the wall thickness exceeds 11/ 4 in. (32 mm) shall
be 100 percent ultrasonically inspected. Ultrasonic examination shall be according to ASME SEC
VIII D1 MA APP 12.
5) [R] When the tubesheet of a boiler drum or header exceeds 2 in. (50 mm) in thickness and the
wrapper plate is less than 2 in. in thickness, the tubesheet shall be inspected according to the
following:
a) Ultrasonic examination of plates—Plates (and plate-like forgings such as forged shell rings) shall
be ultrasonically examined according to ASTM A 578/A 578M. Acceptance standard shall be
Level II. In addition, the entire surface area within two plate thicknesses from the location of a
major load bearing attachment weld or corner type joint shall be examined. Acceptance standard
shall be Level 1.
b) Magnetic particle examination of edges prepared for welding and openings—Prior to welding, all
edges prepared for welding and plate openings shall be examined by the magnetic particle method
(D-C prod only). Indications found shall be cleared and back welded to provide a minimum
depth of 1 in. (25 mm) of sound metal.
6) [R] Inspection and testing according to GP 05-01-02 is required for drums and headers when both the
wrapper plate and tubesheet exceed 2 in. (50 mm) in thickness (references ASME Code radiography
shall be according to ASME SEC I instead of ASME SEC VIII D1).
8. Testing
1) [R] Hydrostatic testing of the completed boiler shall be according to ASME SEC I except that the
maximum hydrotest pressure shall be held for 1 hr/in. (1 hr/25 mm) of metal thickness, and in no case
for less than one hour or more than three hours. The minimum permissible test temperature according
to GP 18-10-01 shall be stamped on the boiler nameplate and noted on the Manufacturer's data report.
Test to be witnessed by Inspector.
a) Hydrotest water for testing boilers with non-drainable superheaters shall be treated with an
oxygen scavenger.
2) [R] Pneumatic leak testing shall be performed for the boiler casing before external insulation is
applied. The test pressure shall be one and a half times the maximum furnace operating pressure. If
the boiler is to be equipped with isolating dampers, the test pressure shall be the maximum FD fan
discharge pressure. The duration of the test shall be ten minutes, during which time the furnace
pressure may not decrease by more than 10 percent. All leaks which are detected shall be repaired
and the unit retested.
3) [R] Forced draft fan performance test shall be required if:
a) Manufacturer's prototype has not been tested according to AMCA 210 using the test setup
specified by the code most similar to the actual installation.
b) Non-standard duct work (such as an inlet silencer) is supplied. The test setup requires Purchaser's
approval.
4) [I] Within 12 months after mechanical completion or 6 months after start-up, the Owner shall have
option to performance test the boiler according to ASME PTC 4 as mutually agreed by Owner and
Vendor.
5) [R] A Factory Acceptance Test is required of the BMS hardware and software.
6) [S] The safety interlock and protective devices shall be fully function tested by the Project
Management/Design Followup Team and the Manufacturing or Startup Team. These tests shall be
successfully completed before initial operation.
9. Guarantee
1) [I] The following performance guarantees, at maximum continuous steam flow, shall be included:
a) Maximum continuous steam flow.
b) Efficiency—The conditions at which efficiency is guaranteed shall be specified by Manufacturer.
c) Steam temperature leaving the superheater (± 10°F or ± 5°C)—If steam temperature control
equipment is furnished, this equipment shall be guaranteed for a specified load and temperature
range.
d) Steam purity entering the superheater—The solids content in the steam shall not exceed
requirements with boiler water at high level alarm and concentrations as specified in Table 4 for
the operating pressure:
psig kPa ppm (mg/L) ppm (mg/L) ppm (mg/L) ppm max.
0–300 0–2100 3500 700 15 1.0
> 300–450 > 2100–3100 3000 600 10 1.0
> 450–600 > 3100–4200 2500 500 8 1.0
> 600–750 > 4200–5200 1000 200 3 0.5
> 750–900 > 5200–6200 750 150 2 0.5
> 900–1000 > 6200–6900 625 125 1 0.5
> 1000–1700 > 6900–11700 100 — 1 0.1
2) If an air heater is provided, the temperature of the air leaving the air heater ± 30°F (± 17°C).
3) Water/steam pressure drop, psi from upstream of boiler feedwater valve to downstream of steam
stop/non-return valve.
RFCH, DIOL For ExxonMobil Use Only Version 2.0.0
4) Ramp rates:
a) Cold Startup
b) Upward load change
c) Downward load change
Predicted Performance
Item Value
Steam Flow Rate, lb/hr
Fuel
Quantity fuel, lb/hr
Quantity combustion air, lb/hr
Excess air leaving boiler, %
Efficiency, % (LHV Basis)
Quality of Steam leaving drum, ppm
Drum pressure, psig
Superheater pressure drop, psi
Water temperature leaving economizer, °F
Economizer pressure drop, psi
Economizer inlet pressure, psig
Gas temperature leaving furnace, °F
Gas temperature entering superheater, °F
Gas temperature entering boiler section, °F
Gas temperature entering economizer, °F
Economizer outlet gas temperature, °F
Gas temperature entering air preheater, °F
Gas temperature leaving air preheater, °F
Air temperature leaving air preheater, °F
Forced draft fan discharge press, in. W. G.
Burner wind box inlet pressure in. W. G.
Furnace pressure, in. W. G.
Superheater outlet gas pressure, in. W. G.
Predicted Performance
Item Value
Record of Change
Version 1.0.0 Date: 03/02
Location Action Description
Initial Publish.