The copyright of this document is vested in Bara Gas Company. All rights reserved. Neither the whole nor any part of this document
may be reproduced, stored in any retrieval system or transmitted in any form or by any means (electronic, mechanical, reprographic,
recording or otherwise) without the prior written consent of the copyright owner. The contents of this controlled document shall not
be altered without formal approval of the document Custodian.
Document Control Procedure Rev: 02A
Revision History
Date of
Rev # Status Description Originator Checker Approver
Issue
0000-BGC-G000-GE00-G00000-JA-6017-00002 Page 2 of 14
Document Control Procedure Rev: 02A
TABLE OF CONTENTS
1. PURPOSE ........................................................................................................................................................ 4
2. DISTRIBUTION .............................................................................................................................................. 4
3. DEFINITIONS ................................................................................................................................................. 4
4. GENERAL ....................................................................................................................................................... 4
5. REFERENCES ................................................................................................................................................. 5
6. RISK ................................................................................................................................................................. 5
7. DOCUMENT NUMBERING .......................................................................................................................... 5
7.1 Number String .........................................................................................................................................................................5
7.2 Discipline – Document Types ................................................................................................................................................5
7.3 Sequential Number..................................................................................................................................................................6
7.4 Sheet Number (for drawings only) .........................................................................................................................................6
7.5 Revision ....................................................................................................................................................................................6
7.6 Status and Issue Codes............................................................................................................................................................7
7.7 Security Classification .............................................................................................................................................................8
7.8 ECCN: Export Control Classification Number ....................................................................................................................9
8. ASSAI (EDMS) PHILOSOPHY...................................................................................................................... 9
9. DOCUMENT FORMATS FOR SUBMISSION ............................................................................................. 9
9.1 Electronic Files Requirements ...............................................................................................................................................9
9.2 Scanned Images .......................................................................................................................................................................9
9.3 Hardcopy Documents .............................................................................................................................................................9
9.4 Language ................................................................................................................................................................................ 10
10. DOCUMENT CONTROL Process ................................................................................................................ 10
10.1 Project Documents ........................................................................................................................................................... 11
11. ISSUE AND Review process ......................................................................................................................... 11
12. Company Document CODES ........................................................................................................................ 11
12.1 Approval Codes................................................................................................................................................................. 11
12.2 Internal Company Produced Project Documentation – Approval Coding .................................................................. 11
13. CONTRACTOR DOCUMENT ..................................................................................................................... 12
13.1 Extranet Submission and Receipt of Data ..................................................................................................................... 12
13.2 External Contractor documentation – Approval Coding .............................................................................................. 12
14. REGISTERS .................................................................................................................................................. 13
15. APPENDICES................................................................................................................................................ 14
Appendix 1 – Assaiweb Work Instruction ............................................................................ 14
Appendix 2 – BGC Document Template .............................................................................. 14
0000-BGC-G000-GE00-G00000-JA-6017-00002 Page 3 of 14
Document Control Procedure Rev: 02A
1. PURPOSE
The purpose of this procedure is to define the documentation format and Control Process, to be
applied by BGC.
This procedure Shall be applied to all BGC generated Corporate & Engineering related
documentation. The requirements highlighted in this procedure are intended to cover
documentation generated both by internal BGC offices and to documentation produced by
Consultants on Behalf of BGC.
Section 13 shows the Requirement for Technical Authority Input to Contractors Documents.
2. DISTRIBUTION
Unless otherwise authorised by BGC, the distribution of this document is confined to BGC and its
nominated Consultants.
3. DEFINITIONS
The Process Owner of this procedure shall be the Information Management Lead for the BGC
Company.
For the purposes of this procedure the term COMPANY shall be BGC. In the event of any
changes to the COMPANY name, this definition will be updated
The term TECHNICAL DOCUMENTATION refers to all revision controlled documentation
produced by the COMPANY.
The term CONSULTANT refers to External companies providing services on behalf of BGC.,
The word shall indicates a requirement. The word should indicates a recommendation.
4. GENERAL
This procedure and its appendices define the requirements surrounding the creation and
management of Documentation.
It should be noted that Documentation generated, either internally by the COMPANY or externally
by CONSULTANTS, which fails to comply with the requirements laid out in this procedure shall be
rejected back to the originator for re-formatting.
Document shall not be sent as attachments to email. This practice spreads original documents to
many locations, and it becomes unclear which document is the latest revision. Email is not a secure
medium and does not comply with IM Security of Information.
Under no circumstances should documents classified as Confidential be sent as Email
attachments.
0000-BGC-G000-GE00-G00000-JA-6017-00002 Page 4 of 14
Document Control Procedure Rev: 02A
5. REFERENCES
Key references to be used along with this procedure are as follows:
6. RISK
Two main risks are identified which will occur if the correct procedure is not followed:
1. Correct information is not readily available and in one common place-this could result in
decisions being made without the latest available information. This can have a Cost and
schedule impact.
2. Information Security is compromised resulting in Exposure and Liability of BGC if some
information is seen by a non authorised party.
7. DOCUMENT NUMBERING
Example of Numbering
0000-BGC-G000-GE00-G00000-JA-6017-00002 Page 5 of 14
Document Control Procedure Rev: 02A
FF-GGGG Discipline and Document Type Codes are prescribed in the DEP 82.00.10.30-
Gen, Engineering Information Specification (EIS)
7.3 Sequential Number
Five Digit sequence number increasing incrementally from 00001 upwards dependant on the other
elements in the numbering string.
This is a numeric starting from sheet 001 up to 999. Each sheet should be treated as a separate
electronic file. Multiple pages within a single file (such as a line list) should be denoted as pages not
sheets. A line list for example, is a single document, single file, single sheet that contains multiple
pages.
7.5 Revision
The revision methodology to be adopted for all documentation will be as follows. The revision
number will consist of a two digit numeric number running sequentially from 01 to 99 followed by a
suffix Alpha character as outlined below.
Revision Suffix
Code Description
I Information
R Review
A Design / Tender / Purchase /Approval
H Construction with Holds
C Construction
Z As Built
X Cancelled
The alpha suffix will change dependant upon the stage in the Project lifecycle the document has
attained. (See Example table below)
Revision Examples
At any time the document may be cancelled by up Revving to the next revision sequence number
and adding the suffix X .e.g. 08X Cancelled
0000-BGC-G000-GE00-G00000-JA-6017-00002 Page 6 of 14
Document Control Procedure Rev: 02A
The full status code with requisite description shall be displayed on all submitted drawings and
documents.
Issue Codes will be displayed on any transmittals
Note the code AFU – Approved for Use is to be applied to Approved internal COMPANY
governance documentation only (Including Documents created by Consultants on behalf of
the Company) The term governance document covers internal project procedures, such as
cost procedures, HR procedures, internal IM procedures etc. Documentation that does not
form part of the Design process so does not reach the status AFD or AFC, but is merely
reviewed and then approved for use on the Project.
0000-BGC-G000-GE00-G00000-JA-6017-00002 Page 7 of 14
Document Control Procedure Rev: 02A
For reasons of security and ownership a security classification code shall be applied to all
documentation issued by the Company.
It is the Originator’s responsibility to classify a document in accordance with Codes listed above.
0000-BGC-G000-GE00-G00000-JA-6017-00002 Page 8 of 14
Document Control Procedure Rev: 02A
Assai is set up to manage the document metadata. It controls the creation, registration and
movement of documents both within the company and also externally.
All Issuing and commenting on documents shall be via Assai. This allows for a quality audit trail to
be maintained including transmittals, dates, recipients etc.
Livelink is the repository for image files and is automatically linked to Assai.
Where the submission of scanned documents is unavoidable, the submitted scanned images shall
comply with DEP 82.00.10.30-Gen.Sec 3.4.5
0000-BGC-G000-GE00-G00000-JA-6017-00002 Page 9 of 14
Document Control Procedure Rev: 02A
In the event of hard copy submission particular attention should be paid to the following:
• The density and quality of lines and printing are extremely important in obtaining
satisfactory images.
• Care must be taken on minute details, such as decimal points, symbols for degrees,
etc. They must be perfectly clear or even slightly exaggerated.
• The minimum character height shall be 2.5 mm. It is stressed that these are
minimum sizes and larger ones are preferred. When lower case letters are used, they
should be proportioned so that the body height is approximately 0.6 times the capital
letter height.
• In cases where Paper or Hardcopy submission is required e.g. legally binding
agreements or certificates carrying original signatures or marks that authenticate a
document. Such hardcopy shall be deemed to be the original Wet signed / stamped
document.
• All prints and photocopies shall be supplied in A4 / A3 size on clean, white paper,
and minimum weight of 80g/m2. Any reduction from the original size shall be
agreed with COMPANY prior to submission.
• Photocopies shall be legible, and made from the original document.
9.4 Language
Unless stated otherwise in the specific purchase order instructions, all documentation shall be
provided in English. Some documents may need to be translated at a later date.
• Requestor must send email c/w First page and Summary page to ISG-DCC@Shell.com
• A number will be assigned to the document.
Once a document is complete, it shall be submitted to DCC and details of the action and
recipients will be set as per the Relevant Document Matrix or as advised by the document owner
Access to Assai users the individuals GID logon name. Therefore any comments added into
Assai can only be made by the individual who has logged in. This also allows for formal
Approval to be given electronically and physical signatures on documents is not required.
• DCC will register and transmit the documents via the COMPANY system ( Assai).
• The document will be issued using a transmittal with appropriate recipients added
0000-BGC-G000-GE00-G00000-JA-6017-00002 Page 10 of 14
Document Control Procedure Rev: 02A
Recipient commenting will be carried out using Assai and comments close-out by Responsible
Engineer will also take place using Assai.
Document submissions from the CONTRACTOR will be loaded into Assai to allow for access
for BGC staff to have access to any relevant project documents.
Once a document is in Assai/Livelink and is to be issued for Review or Approval the recipient will
receive an email notification. The recipient will add their comments and close out their own receipt.
The responsible engineer will collate all comments. They will then update the document and the re-
issue for final approval through Assai.
For the purpose of review and comment COMPANY Project engineers will be expected to apply an
approval code to all documentation sent for review or approval. The approval code shall be used to
reflect the nature of comments being made. Approval codes will be applied electronically utilizing
ASSAI.
0000-BGC-G000-GE00-G00000-JA-6017-00002 Page 11 of 14
Document Control Procedure Rev: 02A
The COMPANY shall establish an Extranet Site to which the CONTRACTOR shall submit
electronic files of documentation being sent for review, approval or information.
For the ISG Project DCC please e-mail – ISG-DCC@SHELL.COM
Documentation placed into the Project Extranet for COMPANY Review, Approval or Information,
shall be accompanied by an e-mail notification to the relevant COMPANY DCC e-mail address. The
email should contain a Transmittal as notification of documentation placement.
The email must be sent to the relevant Project Document Control Centre (DCC):ISG-
DCC@SHELL.COM
Note: E-mail submission of documentation (To the above addresses) will only be
acceptable where extranet access has not yet been provided or is not possible for technical
reasons
Comments made on CONTRACTOR originated documentation will be returned by DCC via the
dedicated Project extranet site. All comments will be accompanied by an external transmittal
generated by the COMPANY DCC.
The COMPANY DCC will send a notification of comments being returned, via the extranet (Under
Cover of an External Transmittal) to the CONTRACTOR DCC via e-Mail.
Upon completion of the review of received CONTRACTOR documentation the COMPANY
assigned Responsible Engineer will apply an Approval code to reflect the nature of comments being
made. The approval code will appear on the external transmittal accompanying COMPANY
documentation comment return. All COMPANY comments shall be returned via the extranet with
an e-mail confirmation to the relevant CONTRACTOR DCC Department.
The COMPANY shall apply the following Approval codes (Below) to marked-up or commented
documentation returned to the CONTRACTOR following formal review / approval. The applied
approval codes shall be used to reflect the nature of the comments being made. The codes to be
used by the COMPANY in returning commented documentation to the CONTRACTOR are as
follows:
0000-BGC-G000-GE00-G00000-JA-6017-00002 Page 12 of 14
Document Control Procedure Rev: 02A
14. REGISTERS
A suite of Registers is available within livelink which show both the cumulative and weekly issue of
Company documents.
0000-BGC-G000-GE00-G00000-JA-6017-00002 Page 13 of 14
Document Control Procedure Rev: 02A
15. APPENDICES
Appendix 1 – Assaiweb Work Instruction
0000-BGC-G000-GE00-G00000-JA-6017-00002 Page 14 of 14