Sunteți pe pagina 1din 30

- 36 -

FORMWORK AND SUPPORTS


- 37 -

FORMWORK AND SUPPORTS


C-12 FOOTINGS OF COLUMN at plinth level using STEEL shutter
Assuming 8'-0" x 8'-0" Base (D= 21", d=15")
Shuttering Area: 40.63 sft.
(i) 1.5" x 1.5" x 3/16" M.S. angle for frame:
2 x 2 x 8'-0= 32.00 rft.
2 x 2 x 8'-3"= 33 rft.
2 x 4 x 1'-3"= 10.00 rft.
75.00 rft.
Add 5% wastage= 3.75 rft.
78.75 rft.
@ 1.79 Ibs per rft = 140.96 Ibs. @ Tk. 33.00
(ii) 1" x 3/16" F.I. bar for stiffner (9" c/c) in frame :
4 x 5 x 1'-3"= 25.00 rft.
Add 5% wastage= 1.25 rft.
26.25 rft.
@ 0.64 Ibs per rft.= 16.8 Ibs. @ Tk. 30.00
(iii) 16 BWG steel sheet to cover frame:
2 x 8'-0"x 1'-3"= 20.00 sft.
2 x 8'-3" x 1'-3"= 20.625 sft.
40.63 sft.
Add 5% wastage= 2.03 sft.
42.66 sft.
@ 2.44 Ibs per sft = 104.0904 Ibs. @ Tk. 41.00
(iv) Fabrication cost for steel shutter: 40.63 sft. @ Tk. 80.00
(v) Cost of nuts, bolts, J-hook etc. 1 kg. @ Tk. 120.00

Considering 16 times use


(vi) Labour cost for fitting fixing steel shutter
and props in position and removing
after concreting etc. 40.63 sft. @ Tk. 20.00
(vii) Hessian for water-tight for 40.63 sft. @ Tk. 2.00
(viii) Cost for support against sides:
(ix) Curing for 28 days for surface area 104.63 sft. @ Tk. 3.00
Grand total

C-13 RAFT or MAT using STEEL shutter


Assuming raft/mat: 30'-0" x 30'-0" x 4'-0"
Considering panel 6'-0" x 2'-0" = 12 sft.
(i) 1.5 " x 1.5" x 3/16" angle for frame:
2 x 6'-0"= 12.00 rft.
2 x 2'-0"= 4.00 rft.
16.00 rft.
Add 5% wastage= 0.80 rft.
16.80 rft.
@ 1.79Ibs per rft. = 30.072 Ibs @ Tk. 33.00
(ii) 1" x 3/16" F.I. bar
1 x 6'-0"= 6.00 rft.
3 x 2'-0"= 6.00 rft.
12.00 rft.
Add 5% wastage= 0.60 rft.
12.60 rft.
@ 0.64 Ibs per rft. = 8.06 Ibs. @ Tk. 30.00
(iii) 16 BWG steel sheet
1 x 6'-0" x 2'-0"= 12.00 sft.
Add 5% wastage= 0.6 sft.
- 38 -

12.60 sft.
@ 2.44 Ibs per sft.= 30.74 Ibs. @ Tk. 41.00
(iv) Fabrication cost of steel shutter: 12.00 sft. @ Tk. 80.00
- 39 -

(v) Cost of nuts, bolts, J-hooks etc. 1.00 kg. @ Tk. 120.00

Considering 16 times use


(vi) Labour for fitting fixing steel shutter and props
in position and removing after concreting etc.
1 x 6'-0" x 2'-0"= 12.00 sft. @ Tk. 20.00
(vii) Support against sides:
1.5" dia M.S. pipe: 2 x 5'-0"= 10.00 rft. @ Tk. 120.00
1.5" x 1.5" x 3/16" angle: @ 1.79 Ibs per rft.
2 x 3'-0"= 6.00 rft.
= 10.74 Ib @ Tk. 33.00

Considering 30 times use


(viii) Hessian for water-tight for 12.00 sft. @ Tk. 2.00
Grand total
Shuttering cost per sft
Shuttering cost for 4 x 30'-0" x 4'-0" = 480 sft
(ix) Curing for 28 days for surface area 1380.00 sft. @ Tk. 3.00

C-14 FOUNDATION BEAM using STEEL shutter


Assuming size of beam: 20'-0" x 3'-0" x 1'-6"
Shuttering Area: 120 sft.
(i) 1.5 " x 1.5" x3/16" angle for frame:
2 x 2 x 20'-0"= 80.00 rft.
2 x 3 x 2 x 3'-0"= 36.00 rft.
116.00 rft.
Add 5% wastage= 5.80 rft.
121.80 rft.
@ 1.79 Ibs per rft. = 218.022 Ibs @ Tk. 33.00
(ii) 1" x 3/16" F.I. bar for stiffner
and tie between side shutter.
2 x 20'-0"= 40.00 rft.
2 x 3 x 6 x 3'-0"= 108.00 rft.
1 x 5 x 1'-10"= 9.20 rft.
157.20 rft.
Add 5% wastage= 7.86 rft.
165.06 rft.
@ 0.64Ibs per rft. = 105.64 Ibs. @ Tk. 30.00
(iii) 16 BWG steel sheet for covering steel frame:
2 x 20'-0" x 3'-0"= 120.00 sft.
Add 5% wastage= 6 sft.
126.00 sft.
@ 2.44 Ibs per sft.= 307.44 Ibs. @ Tk. 41.00
(iv) Fabrication cost of steel shutter: 120.00 sft. @ Tk. 80.00
(v) Cost of nuts, bolts, J-hooks etc. 4.00 kg. @ Tk. 120.00

Considering 16 times use


(vi) 1.5" dia M.S. pipe for inclined support
2 x 3 x 6'-0" = 36 rft. @ Tk. 120.00
Considering 30 times use
(vii) Labour cost for fitting fixing steel shutter and props
in position and removing after concreting etc.
2 x 20'-0" x 3'-0"= 120.00 sft. @ Tk. 20.00
(viii) Hessian for making
shutter water-tight 120.00 sft. @ Tk. 2.00
- 40 -

(ix) Cost for support against sides


- 41 -

(x) Curing for 28 days for surface area 150.00 sft. @ Tk. 3.00
Grand total

C-15 PADESTALS, COLUMN CAPITALS, LIFT WALLS and WALLS using STEEL shutter
Assuming 10'-0" x 12" x 12" Column
Shuttering Area: 40 sft.
(i) 1.5" x 1.5" x 3/16" angle for frame
4 x 2 x 10'-0"= 80.00 rft.
2 x 3 x 1'-4"= 7.98 rft.
2 x 3 x 1'-0"= 6.00 rft.
93.98 rft.
Add 5% wastage = 4.699 rft.
= 98.68 rft.
1.79 Ibs per rft = 176.64 Ibs. @ Tk. 33.00
(ii) 1" x3/16" F.I. bar for stiffner
2 x 8 x 1'-4"= 21.28 rft.
2 x 8 x 1'-0"= 16.00 rft.
= 37.28 rft.
Add 5% wastage= 1.86 rft.
39.14 rft.
@ 0.64Ib. per rft= 25.05 Ibs. @ Tk. 30.00
(iii) 16 BWG steel sheet for covering frame
2 x 10'-0" x 1'-4"= 26.60 sft.
2 x 10'-0" x 1'-0"= 20.00 sft.
46.60 sft.
Add 5% wastage= 2.33 sft.
48.93 sft.
@ 2.44 Ibs per sft.= 119.389 Ibs. @ Tk. 41.00
(iv) Fabrication of steel shutter:
2 x 10'-0" x 1'-4"= 26.67 sft.
2 x 10'-0" x 1'-0"= 20.00 sft.
46.67 sft. @ Tk. 80.00
(v) Nuts, bolts, J-hooks etc. 1.5 kg @ Tk. 120.00

Considering 16 times use


(vi) 1.5" dia M.S. pipe for propping
4 x 8'-0"= 32.00 rft. @ Tk. 120.00
(vii) Turn-buckle in/c tie-rod 2.00 Nos. @ Tk. 550.00

Considering 30 times use


(viii) Labour for fitting fixing steel shutter and props
in position and removing after concreting etc.
4 x 10'-0" x 1'-0"= 40.00 sft. @ Tk. 20.00
(ix) Hessian for water-tight for 40.00 sft. @ Tk. 2.00
(x) Curing for 28 days for surface area 41.00 sft. @ Tk. 3.00
Grand total

C-16 TIE-BEAM, LINTEL using STEEL shutter


Assuming 10'-0" x 10" x 9" lintels or tie beams
Shuttering Area: 18.75
(i) 1.5" x 1.5" x 3/16 angle for frame
2 x 2 x 10'-0"= 40.00 rft.
25% x 2 x 10'-0"= 5.00 rft.
2 x 2 x 2 x 10"= 6.67 rft.
51.67 rft.
- 42 -

Add 5% wastage 2.58 rft.


54.25 rft.
@ 1.79 Ibs per rft.= 97.11 Ibs. @ Tk. 33.00
(ii) 1.5" x 3/16" F.I. bar for stiffner
2 x 6 x 10"= 10.00 rft.
1 x 2 x 1'-1"= 2.17 rft.
Tie: 1 x 3 x 1-1"= 3.25 rft.
15.42 rft.
Add 5% wastage= 0.771 rft.
16.19 rft.
@ 0.956 Ibs per rft.= 15.48 Ibs. @ Tk. 30.00
(iii) 16 BWG steel sheet (@ 2.44 Ibs per sft.)
2 x 10'-0" x 10"= 16.67 sft.
25% x 10'-0" x 1'-1"= 2.7 sft.
19.37 sft.
Add wastage 5%= 0.97 sft.
20.34 sft.
= 49.63 Ibs. @ Tk. 41.00
(iv) Nuts, bolts, J-hooks etc. 1.00 kg. @ Tk. 120.00
(v) Fabrication of steel shutter 19.37 sft. @ Tk. 80.00

Considering 16 times use


(vi) 1.5" dia M.S. pipe for propping:
2 x 7'-0"= 14 rft. @ Tk. 120.00
Considering 30 times use
(vii) Labour for fitting fixing steel shutter and props
in position and removing after concreting etc.
2 x 10'-0" x 10"= 16.67 sft.
25% x 10'-0" x 10"= 2.083 sft.
18.75 sft. @ Tk. 20.00
(viii) Hessian for water-tight for 18.75 sft. @ Tk. 2.00
(ix) Curing for 28 days for surface area 27.57 sft. @ Tk. 3.00
Grand total

C-17 T-BEAM, EL-BEAM, RECTANGULAR BEAM using STEEL shutter


Assuming 20'-0" x 1'-6" x 1'-0" beams
Shuttering Area: 80 sft.
(i) 1.5" x 1.5" x 3/16" M.S. angle for frame
2 x 3 x 20'-0" = 120 rft.
2 x 3 x 2 x 1'-6"= 18 rft.
1 x 3 x 2 x 1'-4"= 7.98 rft.
145.98 rft.
Add 5% wastage= 7.30 rft.
= 153.28 rft.
@ 1.79Ibs per rft.= 274.37 Ibs. @ Tk. 33.00
(ii) 1.5" x 3/16" F.I. bar for stiffner and tie:
1 x 2 x 20'-0"= 40.00 rft.
2 x 3 x 4 x 1'-6"= 36.00 rft.
1 x 3 x 6 x 1'-4"= 23.94 rft.
6 x 1'-4"= 7.98 rft.
107.92 rft.
Add 5% wastage= 5.40 rft.
= 113.32 rft.
@ 0.96Ibs per rft.= 108.79 Ibs. @ Tk. 30.00
(iii) 16 BWG steel sheet for covering frame
2 x 20'-0" x 1'-6"= 60.00 sft.
- 43 -

1 x 20'-0" x 1'-4"= 26.60 sft.


86.60 sft.
Add 5% wastage= 4.33 sft.
90.93 sft.
@ 2.44 Ibs per sft. 221.87 Ibs @ Tk. 41.00
- 44 -

(iv) Fabrication for steel shutter: 86.60 sft. @ Tk. 80.00


(v) Nuts, bolts, J-hooks etc. 4 kg. @ Tk. 120.00

Considering 16 times use


(vi) Props: (10 Nos.)
2" dia M.S. pipe: 1 x 7'-0"= 7.00 rft. Tk. 150.00
1.5" dia M.S. pipe: 1 x 7'-0"= 7.00 rft. @ Tk. 120.00
Adjustable mechanism in/c
top and bottom plates: 1.00 No. @ Tk. 650.00

Cost for 10 Nos. prop


Sub-total
Considering 30 times use
(vii) Labour cost for fitting fixing steel shutter and props
in position and removing after concreting etc.:
2 x 20'-0" x 1'-6"= 60.00 sft.
1 x 20'-0" x 1'-0"= 20.00 sft.
= 80.00 sft. @ Tk. 20.00
(viii) Hessian for water-tight for 80.00 sft. @ Tk. 2.00
(ix) Curing for 28 days for surface area 80.00 sft. @ Tk. 3.00
Grand total

C-18 FLOOR AND ROOF slab using STEEL shutter


Assuming 20'-0 x 16'-0" x 6" Slabs
Shuttering Area: 350 sft.
4" x 2" Steel box channel with 12 BWG steel plate:
Break-up for 20 rft. steel box channel:
(1) 12 BWG steel sheet:
20'-0" x 2 (4"+2")= 20.00 sft.
Add 5% wastage= 1.00 sft.
= 21.00 sft.
@ 4.27 Ibs per sft.= 89.67 Ibs. @ Tk. 45.00
(2) Cutting and bending: 20.00 rft. @ Tk. 10.00
(3) Welding and grinding: 20.00 rft. @ Tk. 30.00

Cost of per rft. of box channel.


Say, Tk. 242
(a) 16 BWG steel sheet: (2.44 Ibs per sft.)
1 x 20'-0" x 16'-0"= 320.00 sft.
Add 5% wastage= 16.00 sft.
336.00 sft.
= 819.84 Ibs. @ Tk. 41.00
Considering 16 times use
(b) 4" x 2" steel box under steel sheet: 1" c/c in
long direction and below 2'-0" c/c in short direction
18 x 21'-0" = 378.00 cft.
11 x 17'-0" = 187.00 cft.
565.00 rft. @ Tk. 242.00
Considering 30 times use
(c) Steel shutter around roof slab:
(i) 1" x 1" x 1/8" angle for frame
2 x 20'-2"= 40.33 rft.
2 x 16'-0"= 32.00 rft.
4 x 2 x 5"= 3.33 rft.
75.66 rft.
Add 5% wastage= 3.78 rft.
- 45 -

79.44 rft.
@ 0.8 Ibs per rft.= 63.55 Ibs. @ Tk. 33.00
- 46 -

(ii) 1 x 1/8" F.I. bar for stiffner


2 x 11'-0"= 22.00 sft.
2 x 12'-0"= 24.00 sft.
46.00 sft.
Add 5% wastage= 2.30 rft.
48.30 rft.
@ 0.425 Ibs per rft.= 20.53 Ibs. @ Tk. 30.00
(iii) 16 BWG steel sheet to cover frame
2 x 20'-2" x 5" = 16.81 sft.
2 x 16'-0" x 5" = 13.33 sft.
30.14 sft.
Add 5% wastage= 1.51 sft.
31.65 sft.
@ 2.44 Ibs per sft.= 77.23 Ibs. @ Tk. 41.00
(iv) Fabrication steel shutter
for around slab: 30.14 sft. @ Tk. 20.00
(v) Cost of nuts, bolts, J- hooks etc. 12.00 kg. @ Tk. 120.00

Considering 16 times use


(d) Props: (88 Nos.)
(i) 2" dia M.S. pipe: 1 x 7'-0"= 7.00 rft. Tk. 150.00
(ii) 1.5" dia M.S. pipe: 1 x 7'-0"= 7.00 rft. @ Tk. 120.00
(iii) Adjustable mechanism in/c top and bottom plates
and locking arrangements etc.: 1.00 No. @ Tk. 650.00
Total for 1 set Prop.
Cost for 88 Nos. prop
(e) 2" dia M.S. pipe for cross bracing:
9 x 18'-0"= 162.00 rft. @ Tk. 150.00
Sub-total
Considering 30 times use
(f) Labour cost for fitting fixing steel shutter and props
in position and removing etc.:
20'-0" x 16'-0"= 320.00 sft.
2 x (20'-0" + 16'-0") x 5"= 30.00 sft.
= 350.00 sft. @ Tk. 20.00
(g) Hessian tap for making shutter
water-tight 350.00 sft. @ Tk. 2.00
(i) Curing for 28 days for surface area 350.00 sft. @ Tk. 3.00
Grand total

C-19 CORNICE, DROP-WALLS, RAILING, LOUVER AND FINS etc.


using STEEL shutter
Assuming 10'-0" x 3'-0"= 30 sft. drop walls
Shuttering Area: 62.50 sft.
(i) 1" x 1" x 1/8" M.S. angle for frame
2 x 3 x 10'-3"= 61.50 rft.
2 x 2 x 3'-1.5"= 12.50 rft.
2 x 0'-5" = 0.83 rft.
74.83 rft.
Add 5% wastage= 3.74 rft.
= 78.57 rft.
@ 0.80 Ibs per rft= 62.86 Ibs. @ Tk. 33.00

(ii) 1" x 1/8" F.I. bar for frame & stiffner


2 x 14 x 3'-0" = 84.00 rft
2 x 4 x 10'-0" = 80.00 rft
1 x 14 x 0'-5" = 5.83 rft
- 47 -

4 x 0'-5" = 1.67 rft


171.50 rft
- 48 -

Add 5% wastage = 8.58 rft


180.08 rft
@0.43.00 Ibs per rft = 77.43 Ibs. @ Tk. 30.00
(iii) 18 BWG M.S sheet
2 x 10'-0" x 3'-0"= 60.00 sft.
1 x 10' - 0" x 0'-5" = 4.17 sft.
64.17 sft.
Add 5% wastage= 3.21 sft.
67.38 sft.
@ 2.04Ibs per sft.= 137.46 Ibs. @ Tk. 45.00
(iv) Fabrication steel shutter: 64.17 sft. @ Tk. 80.00
(v) Nuts, bolts, J- hooks etc. 5.00 kg @ Tk. 120.00

Considering 16 times use


(vi) Wooden batten under steel shutter & inclined support
4 x 3'-6" x 3" x 2" = 0.58 cft.
2 x 4 x 3' - 4" x 2" x 2 ' = 0.74 cft.
1.32 cft.
Add 5% wastage= 0.07 cft.
1.39 cft. @ Tk. 500.00
Considering 6 times use

(vii) 2"/1.5" dia M.S. props in/c adjustable mechanism


with top and bottom plate etc. 4 Nos. @ Tk. 2,540.00
Considering 30 times use
(viii) Labour for fitting and fixing steel shutter &
props in position:
2 x 10'-0" x 3'-0"= 60.00 sft.
10' - 0" x 3"= 2.50 sft.
62.50 sft. @ Tk. 20.00
(ix) Hessian tape for making
shutter water-tight 62.50 sft. @ Tk. 2.00
(x) Curing for 28 days for surface area 62.50 sft. @ Tk. 3.00

C-20 SUNSHADE using STEEL shutter


Assuming 10'-0" x 3'-0"= 30 sft. sun-shade
Shuttering Area: 34 sft.
(i) 1.5" x 1.5" x 3/16" M.S. angle for frame
2 x 10'-3"= 20.50 rft.
2 x 2 x 3'-1.5"= 12.50 rft.
33.00 rft.
Add 5% wastage= 1.65 rft.
= 34.65 rft.
@ 1.79 Ibs per rft= 62.02 Ibs. @ Tk. 33.00
(ii) 1" x 3/16" F.I. bar for stiffner:
2 x 10'-3"= 20.50 rft.
2 x 3 x 0'-3"= 1.50 rft.
= 22.00 rft.
Add 5% wastage= 1.10 rft.
= 23.10 rft.
@ 0.64 Ibs per rft.= 14.78 Ibs. @ Tk. 30.00
(iii) 16 BWG steel sheet
1 x 10'-0" x 3'-0"= 30.00 sft.
Add 5% wastage= 1.50 sft.
31.50 sft.
@ 2.44 Ibs per sft.= 76.86 Ibs. @ Tk. 45.00
- 49 -

(iv) Fabrication steel shutter: 30.00 sft. @ Tk. 80.00


- 50 -

(v) Cost of nuts, bolts, J- hooks etc. 0.50 kg @ Tk. 120.00

Considering 16 times use


(vi) Wooden side shutter:
1 x 10'-0" x 3" x 1.5"= 0.31 cft.
2 x 3'-1.5" x 3" x 1.5"= 0.20 cft.
= 0.51 cft.
Add 5% wastage= 0.03 cft.
0.54 cft. @ Tk. 500.00
Considering 6 times use
(vii) 4" x 2" box channel under steel shutter
4 x 4'-0"= 16 rft. @ Tk. 300.00
Considering 30 times use
(viii) 2"/1.5" dia M.S. props in/c adjustable mechanism
with top and bottom plate etc. 4 Nos. @ Tk. 2,540.00
Considering 30 times use
(ix) Labour for fitting and fixing steel shutter &
props in position as required.:
1 x 10'-0" x 3'-0" = 30.00 sft.
(3'-0" + 10'-0" + 3'-0") x 3" = 4.00 sft.
34.00 sft. @ Tk. 20.00
(x) Hessian tap for making
shutter water-tight 34.00 sft. @ Tk. 2.00
(xi) Curing for 28 days for surface area 34.00 sft. @ Tk. 3.00

C-21 STAIR CASE SLAB AND STEPS using STEEL shutter


Assuming 8'-9" long & 4'-0" wide stair
Shuttering Area:70.50 sft.
8'- 9" x 4'-0" x 0'-6" = 17.50 cft.
1/2 x 9 x 4'-0" x 0'-10" x 0'-6" = 7.56 cft.
= 25.06 cft.
(i) 1.5" x 1.5" x 1/4" M.S. angle for frame for slab and sides:
1 x 8 x 8'-9"= 70.00 rft.
1 x 5 x 4'-4"= 21.65 rft.
2 x 2 x 1'-0"= 4.00 rft.
= 95.65 rft.
Add 5% wastage= 4.78 rft.
= 100.43 rft.
@ 2.34 Ibs per rft.= 235.01 Ibs. @ Tk. 33.00
(ii) 1" x 1" x 1/8" M.S. angle for steps:
9 x 2 x 4'-0"= 72.00 rft.
9 x 2 x 6"= 9.00 rft.
2 x 9 x 1'-0" = 18.00 rft.
= 99.00 rft.
Add 5% wastage= 4.95 rft.
= 103.95 rft.
@ 0.8 Ibs per rft = 83.16 Ibs. @ Tk. 33.00
(iii) 1.5" x 1/4" thick F.I. bar for stiffner and tie for frame for slab and side:
Stiffner: 5 x 8'-9"= 43.75 rft.
7 x 4'-4"= 30.31 rft.
2 x 7 x 1'-0" = 14.00 rft.
Tie between two sides: 2 x 4'-4" = 8.67 rft.
96.73 rft.
- 51 -

Add 5% wastage= 4.84 rft.


101.57 rft.
@ 1.28 Ibs per rft.'= 130.01 Ibs. @ Tk. 30.00
(iv) 1" x 1/8" F.I. bar for stiffner for frame for steps:
9 x 1 x 6"= 4.5 rft.
Add 5% wastage= 0.23 rft.
= 4.73 rft.
(@ 0.425 Ibs per rft.)= 2.01 Ibs. @ Tk. 30.00
(v) 16 BWG steel sheet for covering frame:
1 x 8'-9" x 4'-4"= 37.89 sft.
2 x 8'-9" x 1'-0"= 17.50 sft.
9 x 4'-0" x 6"= 18.00 sft.
= 73.39 sft.
Add 5% wastage= 3.6695 sft.
= 77.06 sft.
@ 2.44 Ibs per sft.= 188.03 Ibs. @ Tk. 45.00
(vi) Nut, bolts, J-hooks etc. 2.5 kg @ Tk. 120.00
(vii) Fabrication of steel shutter: 73.39 sft. @ Tk. 80.00

Considering 16 times use


(viii) 2"/1.5" dia M.S props in/c adjustable
mechanism with top and bottom plate
and locking arrangement etc.: 8 Nos. @ Tk. 2,540.00
(ix) 1.5" x 1.5" x 1/4" M.S. angle as cross bar:
4 x 5'-0"= 20.00 rft.
Add 5% wastage= 1.00 rft.
21.00 rft.
@ 2.34 Ib per rft = 49.14 Ibs. @ Tk. 33.00

Considering 30 times use


(x) Labour for fitting fixing steel shutter and
props in position and removing etc.:
1 x 8'-9" x 4'-0"= 35.00 sft.
2 x 8'-9" x 1'-0"= 17.50 sft.
9 x 4'-0" x 6"= 18.00 sft.
= 70.50 sft. @ Tk. 20.00
(xi) Hessian for water-tight for 70.50 sft. @ Tk. 2.00
(xii) Curing for 28 days for surface area 70.50 sft. @ Tk. 3.00
Grand total
- 52 -

Per Ib. = Tk. 4,651.68

Per Ib. = Tk. 504.00

Per Ib. = Tk. 4,267.71


Per sft. = Tk. 3,250.40
Per kg. = Tk. 120.00
Total = Tk. 12,793.79
= Tk. 799.61

Per sft. = Tk. 812.60


Per sft. = Tk. 81.26
L.S. = Tk. 100.00
Per sft. = Tk. 313.89
= Tk. 2,107.36
Cost per sft. = Tk. 51.87
Cost per sqm. = Tk. 558.33

Per Ib. = Tk. 992.38

Per Ib. = Tk. 241.80


- 53 -

Per Ibs. = Tk. 1,260.34


Per sft. = Tk. 960.00
- 54 -

Per kg. = Tk. 120.00


Total = Tk. 3,574.52
= Tk. 223.41

Per sft. = Tk. 240.00

Per rft. = Tk. 1,200.00

Per Ib = Tk. 354.42


= Tk. 1,554.42
= Tk. 51.81
Per sft. = Tk. 24.00
Tk. 539.22
= Tk. 44.94
= Tk. 21,571.20
Per sft. = Tk. 4,140.00
Total = Tk. 25,711.20
Cost per sft. = Tk. 53.57
Cost per sqm. = Tk. 576.63

Per Ib. = Tk. 7,194.73

Per Ib. = Tk. 3,169.20

Per Ibs. = Tk. 12,605.04


Per sft. = Tk. 9,600.00
Per kg. = Tk. 480.00
Total = Tk. 33,048.97
= Tk. 2,065.56

Per rft. = Tk. 4,320.00


= Tk. 144.00

Per sft. = Tk. 2,400.00

Per sft. = Tk. 240.00


- 55 -

= Tk. 50.00
- 56 -

Per sft. = Tk. 450.00


= Tk. 5,349.56
Cost per sft. = Tk. 44.58
Cost per sqm. = Tk. 479.86

Per Ib. = Tk. 5,829.12

Per Ib. = Tk. 751.50

Per Ib. = Tk. 4,894.95

Per sft. = Tk. 3,733.60


Per kg. = Tk. 180.00
Total = Tk. 15,389.17
= Tk. 961.82

Per rft. = Tk. 3,840.00


each = Tk. 1,100.00
Total = Tk. 4,940.00
= Tk. 164.67

Per sft. = Tk. 800.00


Per sft. = Tk. 80.00
Per sft. = Tk. 123.00
= Tk. 2,129.49
Cost per sft. = Tk. 53.24
Cost per sqm. = Tk. 573.08
- 57 -

Per Ib. = Tk. 3,204.63

Per Ib. = Tk. 464.40

Per Ib. = Tk. 2,034.83


Per kg. = Tk. 120.00
Per sft. = Tk. 1,549.60
Total = Tk. 7,373.46
= Tk. 460.84

Per rft. = Tk. 1,680.00


= Tk. 56.00

Per sft. = Tk. 375.00


Per sft. = Tk. 37.50
Per sft. = Tk. 82.71
= Tk. 1,012.05
Cost per sft. = Tk. 53.98
Cost per sqm. = Tk. 581.04

Per Ib. = Tk. 9,054.21

Per Ib. = Tk. 3,263.70


- 58 -

Per Ib. = Tk. 9,096.67


- 59 -

Per sft. = Tk. 6,928.00


Per kg. = Tk. 480.00
Total = Tk. 28,822.58
= Tk. 1,801.41

Per rft. = Tk. 1,050.00


Per rft. = Tk. 840.00

each = Tk. 650.00


Total = Tk. 2,540.00
= Tk. 25,400.00
= Tk. 27,940.00
= Tk. 931.33

Per sft. = Tk. 1,600.00


Per sft. = Tk. 160.00
Per sft. = Tk. 240.00
= Tk. 4,732.74
Cost per sft. = Tk. 59.16
Cost per sqm. = Tk. 636.80

Per Ib. = Tk. 4,035.15


Per rft. = Tk. 200.00
Per rft. = Tk. 600.00
Total = Tk. 4,835.15
= Tk. 241.76
.00 per rft.

Per Ib. = Tk. 33,613.44


= Tk. 2,100.84

Per rft. = Tk. 136,730.00


= Tk. 4,557.67
- 60 -

Per Ib. = Tk. 2,097.15


- 61 -

Per Ib. = Tk. 615.90

Per Ib. = Tk. 3,166.43

Per sft. = Tk. 602.80


Per kg. = Tk. 1,440.00
Total = Tk. 7,922.28
= Tk. 495.14

Per rft. = Tk. 1,050.00


Per rft. = Tk. 840.00

each = Tk. 650.00


= Tk. 2,540.00
= Tk. 223,520.00

Per rft. = Tk. 24,300.00


= Tk. 247,820.00
= Tk. 8,260.67

Per sft. = Tk. 7,000.00

Per sft. = Tk. 700.00


Per sft. = Tk. 1,050.00
= Tk. 24,164.32
Cost per sft. = Tk. 69.04
Cost per sqm. = Tk. 743.15

Per Ibs. = Tk. 2,074.38


- 62 -

Per Ibs. = Tk. 2,322.90

Per Ibs. = Tk. 6,185.70


Per sft. = Tk. 5,133.60
Per kg. = Tk. 600.00
Total = Tk. 16,316.58
= Tk. 1,019.79

Per cft.
= Tk. 115.83

each
= Tk. 338.67

Per sft. = Tk. 1,250.00

Per sft. = Tk. 125.00


Per sft. = Tk. 187.50
Total = Tk. 3,036.79
Cost per sft. = Tk. 48.59
Cost per sqm. = Tk. 523.02

Per Ibs. = Tk. 2,046.66

Per Ibs. = Tk. 443.40

Per Ibs. = Tk. 3,458.70


- 63 -

Per sft. = Tk. 2,400.00


- 64 -

Per kg. = Tk. 60.00


Total = Tk. 8,408.76
= Tk. 525.55

Per cft.
= Tk. 45.00

Per rft.
= Tk. 160.00

each
= Tk. 338.67

Per sft. = Tk. 680.00

Per sft. = Tk. 68.00


Per sft. = Tk. 102.00
Total = Tk. 1,919.22
Cost per sft. = Tk. 56.45
Cost per sqm. = Tk. 607.63

Per Ib. = Tk. 7,755.33

Per Ib. = Tk. 2,744.28


- 65 -

Per Ib. = Tk. 3,900.30

Per Ib. = Tk. 60.30

Per Ib. = Tk. 8,461.35


Per kg. = Tk. 300.00
Per sft. = Tk. 5,871.20
Total = Tk. 29,092.76
= Tk. 1,818.30

each = Tk. 20,320.00

Per Ib. = Tk. 1,621.62


Total = Tk. 21,941.62
= Tk. 731.39

Per sft. = Tk. 1,410.00


Per sft. = Tk. 141.00
Per sft. = Tk. 211.50
= Tk. 4,312.19
Cost per sft. = Tk. 61.17
Cost per sqm. = Tk. 658.43