Quiz 3
Name: ___________________ __________________ Grade:_____/ 10
(PRINT): *Last* First
Please answer only 10 of the following 15 Multiple Choice questions by selecting the best answer, from
among other possible “good” answers, by CIRCLING the letter next to it.
Ans: a
Section Reference: 3.1 Project Management and the Project Manager
Level: easy
Bloom’s: Comprehension
2. According to the authors, the analytic method, when applied to systems, focuses on
__________.
a) assembling the components of a system into an integrated package
b) building an array of individually designed and manufactured components
c) calculating the cost and schedule requirements
d) dividing the components of a system into smaller and smaller elements
Ans: d
Section Reference: 3.1 Project Management and the Project Manager
Level: intermediate
Bloom’s: Comprehension
1
MGO 634 F10/PM1 Project Management Fall 2018
Quiz 3
Ans: b
Section Reference: 3.1 Project Management and the Project Manager
Level: easy
Bloom’s: Comprehension
4. According to the authors, three major questions face the project manager with respect to
synthesizing the requirements of a project. Identify the item that is NOT listed as one of the
three major questions.
a) What needs to be done?
b) Who will actually do the work of the project?
c) When must it be done?
d) How will the required resources be obtained?
Ans: b
Section Reference: 3.1 Project Management and the Project Manager
Level: intermediate
Bloom’s: Comprehension
2
MGO 634 F10/PM1 Project Management Fall 2018
Quiz 3
5. When managing a project, the project manager is responsible for __________.
a) auditing the project
b) executing the project
c) budgeting the project
d) designing the project
Ans: c
Section Reference: 3.1 Project Management and the Project Manager
Level: intermediate
Bloom’s: Comprehension
6. The project manager's responsibilities are broad and fall primarily into three separate areas.
Responsibilities to _____________ is NOT one of these.
a) the parent organization
b) the project and the client
c) the members of the project team
d) special-interest groups
Ans: d
Section Reference: 3.1 Project Management and the Project Manager
Level: easy
Bloom’s: Comprehension
7. The project manager must make trade-offs between project progress and process.
Conceptually, this involves trade-offs between the __________ functions.
a) technical and managerial
b) schedule and cost
3
MGO 634 F10/PM1 Project Management Fall 2018
Quiz 3
c) performance and schedule
d) cost and performance
Ans: a
Section Reference: 3.2 Special Demands on the Project Manager
Level: intermediate
Bloom’s: Comprehension
8. During the __________ stage of the project lifecycle, there is no significant difference in
the importance that project managers place on the three goals of cost, time, and scope.
a) main
b) formation
c) buildup
d) phaseout
Ans: b
Section Reference: 3.2 Special Demands on the Project Manager
Level: easy
Bloom’s: Application
9. According to the authors the project manager should be more skilled at __________.
a) general management
b) technology
c) synthesis
d) analysis
4
MGO 634 F10/PM1 Project Management Fall 2018
Quiz 3
Ans: c
Section Reference: 3.1 Project Management and the Project Manager
Level: easy
Bloom’s: Comprehension
10. According to the authors, of all the characteristics desirable in a project manager,
__________ is the most important.
a) availability
b) a strong technical background
c) ability to keep the project team happy
d) drive to complete the task
Ans: d
Section Reference: 3.3 Attributes of Effective Project Managers
Level: easy
Bloom’s: Comprehension
Ans: c
Section Reference: 3.3 Attributes of Effective Project Managers
Level: easy
5
MGO 634 F10/PM1 Project Management Fall 2018
Quiz 3
Bloom’s: Comprehension
12. Projects are conducted in four important environments. They are __________.
a) economic, political, legal, and sociotechnical
b) internal, external, transitional, and multicultural
c) routine, unique, fast-paced, and complex
d) profit, not for profit, government, and industry
Ans: a
Section Reference: 3.4 Problems of Cultural Differences
Level: easy
Bloom’s: Comprehension
13. According to the authors, the key to coping with uncertainty at the end of a project (a
common obstacle for project managers) is __________.
a) discipline
b) communication
c) planning
d) supervision
Ans: b
Section Reference: 3.2 Special Demands on the Project Manager
Level: intermediate
Bloom’s: Knowledge
6
MGO 634 F10/PM1 Project Management Fall 2018
Quiz 3
14. During the buildup phase, the project goals, in order of importance, are __________.
a) schedule, scope, cost
b) cost, schedule, scope
c) schedule, cost, scope
d) cost, scope, schedule
Ans: a
Section Reference: 3.2 Special Demands on the Project Manager
Level: Intermediate
Bloom’s: Comprehension
15. Project managers must have __________, which refers to possessing enough technical
abilities to direct the project.
a) technical credibility
b) managerial credibility
c) negotiation skill
d) drive to complete the task
Ans: a
Section Reference: 3.3 Attributes of Effective Project Managers
Level: intermediate
Bloom’s: Knowledge