Please answer each of the following 10 multiple choice questions by selecting the best
answer, from among other possible “good” answers, by CIRCLING the letter next to it.
1. Personality conflicts during project phase-out are often caused by __________.
c) pressure to complete the project and anxiety about leaving the project
Ans: c Section Reference: 4.2 Conflict and the Project Life Cycle
2. Identify the category of conflict that is NOT included in the categories used by
Thamhain and Wilemon in their study of project conflict.
c) interpersonal problems
d) discipline/problem-orientation differences
Ans: d Section Reference: 4.2 Conflict and the Project Life Cycle
1
MGO 634 F20 Quiz 5 of 10 Fall 2015
4. When dealing with conflict between parties, it is recommended that one __________ in
order to avoid the conflict becoming interpersonal.
d) focus on interests
5. There are probably more opportunities for __________ in handling conflicts and
negotiations than in any other aspect of project management.
a) errors in judgment
b) ethical missteps
6. The authors mention three situations where the highest level of negotiating skill is
required by the project manager. Which of the following is NOT one of them?
b) using sub-contractors
d) using input from multiple functional units in developing the project mission
7. Which of the following is NOT included in the authors’ four part agreement for
partnering?
2
MGO 634 F20 Quiz 5 of 10 Fall 2015
8. According to the authors; which of the entities below is NOT a party to the chartering
process?
b) the customer
c) senior management
d) functional managers
9. There are several words that are synonyms for negotiate. Which of the following is
NOT quoted by the authors?
a) arbitrate
b) bicker
c) conciliate
d) haggle
10. Which of the following is NOT one of the four points of principled negotiation?
Please answer ONLY 10 of the following 12 multiple choice questions by selecting the best answer,
from among other possible “good” answers, by CIRCLING the letter next to it.
1. Identify the statement that is NOT a major advantage of placing a project within a
functional element of the parent organization.
c) The functional division tends to be oriented towards activities particular to its function.
3
MGO 634 F20 Quiz 5 of 10 Fall 2015
2. Identify the statement that is NOT a major disadvantage of placing a project within a
functional element of the parent organization.
b) The project’s client is not the primary focus of activity in the function.
d) The functional division contains the normal path of advancement for individuals whose
expertise is in the functional area.
3. Identify the statement that is NOT a major advantage of placing a project within the
pure project organization.
a) The functional manager retains full line authority over project team members.
4. Identify the statement that is NOT a major disadvantage of placing a project within the
pure project organization.
a) The project manager has full line authority over the project.
b) Projects duplicate effort because resources are not shared across projects.
d) Policies and procedures of the organization are inconsistently used and enforced.
4
MGO 634 F20 Quiz 5 of 10 Fall 2015
5. If the project manager controls when and what people do while the functional
managers control who will be assigned to the project and what technology will be
used, the __________ organizational form is probably being used.
a) projectized
b) pure project
c) matrix
d) weak project
d) product warranties
7. Identify the statement that is NOT a major advantage of placing a project in the
matrix approach.
a) A single individual, the project manager, takes responsibility for managing the project.
b) The project will have access to representatives from the administrative units of the parent
firm.
c) The division of authority between the project manager and the functional managers is
complex.
d) There may be less anxiety among team members about what will happen to them when
the project is completed.
8. Identify the statement that is NOT a major disadvantage of placing the project in the
matrix approach.
5
MGO 634 F20 Quiz 5 of 10 Fall 2015
9. When a project requires the integration of inputs from several functional areas and
involves reasonably sophisticated technology, but does not require all the technical
specialists to work for the project on a full-time basis, the __________ organizational
form should be used.
a) functional
b) matrix
c) pure project
d) mixed
10. The process of dealing with uncertainties in projects that may affect the project
for better or for worse has come to be known as __________.
a) scope management
b) risk management
c) quality management
d) procurement management
6