Documente Academic
Documente Profesional
Documente Cultură
MUMBAI-400 001
TENDER DOCUMENT
FOR
CONSTRUCTION OF
AT
Page 1 of 1
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
INDEX
Sr. DESCRIPTION PAGES
No.
FROM TO
INDEX
2 1 3
4 UNPRICED BID 1 5
5 TIME SCHEDULE 1 2
Page 1 of 3
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
Page 2 of 3
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
Page 3 of 3
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
PROJECT DESCRIPTION,
SCOPE OF WORK&
SCHEDULE OF QUANTITIES
Page 1 of 34
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
The bidder is advised to visit and examine the site of works and their surrounding and
obtain for himself and on his own responsibility all information that may be necessary for
preparing of the bid and entering into the contract. The cost of visiting the sites shall be at
bidder’s own expenses. No extra claim on account of non-familiarity of site conditions shall
be entertained during execution of works.
The prospective bidders are requested to thoroughly read and comprehend the various
sections of this tender document and visit the sites before quoting for the tender and offer
their most competitive rates for the job.
Paradeep Terminal
Paradeep- 754145
Orissa
Page 2 of 34
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
SCOPE OF WORK
IMPORTANT NOTES
1. Entire Cement concrete job need to be carried out thru Ready mix concrete only. The scope of
mix design is included in the scope of bidder and the same to be vetted by reputed
engineering institute like IIT, Kharagpur or any other reputed Engineering Institutes/
Consultant duly approved by HPCL. Party has to submit vetted design calculations to EIC and
obtain approval of the same before commencement of the job. RMC plants shall be of repute
like ACC, L&T etc. Alternatively, party can also set up a batching plant at the site and make
design mix as per provision including vetting by the reputed engineering institute like IIT,
Kharagpur or any other reputed Engineering Institutes/ Consultant duly approved by HPCL.
Party has to submit vetted design calculations to EIC and obtain approval of the HPCL before
commencement of the job.The batching plant need to be certified by third party for
robustness of performance and equipments associated with it.
2. Design of storage tank is also in the scope of the bidder. Tank design along with all
components shall be vetted by IIT, Kharagpur or any reputed institute/consultant as approved
by HPCL. However, the design data sheet is to be approved by HPCL prior to commencement
of design process and subsequent vetting by IIT Kharagpur or any reputed institute/
consultant. Party has to submit vetted design calculations to EIC and obtain approval of the
HPCL before commencement of the job.Rate to include the same in respective items and No
separate payment shall be made to the party on this account.
3. Scope also includes shifting of all types of materials including scrap materials, if any lying at
the constructional area to the designated place inside the depot premises at no extra cost. Job
also includes site clearing from any debris, vegetation, bushes and trees, etc and make the site
free for construction at no extra cost.
4. Any cables / piping encountered during excavation and other construction activities, the same
shall be separated using Sand Bed and Tiles or to be re-routed, if necessary as directed by the
Engineer in charge at no extra cost to HPCL.
6. If any deviation is found during execution between the specification and the drawings, it is to be
explicitly noted that the specification will hold good and supersede the drawings.
7. The bidder is required to peruse carefully all parts of tender documents and drawings and if any
difference / inconsistency is noticed, he shall bring it to attention of HPCL before submission of
Page 3 of 34
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
tender and shall get the clarification(s) required. Failure to do so will not entitle the successful
bidder for any extra claims on account of such discrepancies/inconsistencies.
8. All jobs shall be executed as per technical specifications, relevant codal provisions, sound
engineering practices and as directed by EIC.
1. Preparation of all detailed and working drawing for storage tanks and obtaining approval of
HPCL/ TPI/ Consultant.
2. Submission of 4 copies of all the above drawings (As built) shall be submitted along with CD
containing soft copy in AutoCAD latest version after job completion.
The prospective bidders are requested to thoroughly read and comprehend the various sections of this
tender document and visit the sites before quoting for the tender.
SITE INFORMATION
The job needs to be carried out in the working Terminal premises. Works to be commenced only after
having obtained necessary work permit on a daily basis & all safety precautions to be taken by the
party for carrying out the above jobs as directed by Engineer In Charge/ Terminal Manager.The party
will also have to arrange for all necessary safety and fire fightingequipments like fire extinguishers,
foam trolley, localised fire screen etc at no extra cost. The party will have to abide by all instructions
and directions by Engineer In Charge/ Terminal Manager while working inside the premises.
All conditions of work permit to be followed religiously by the party. The explosive meter readings and
check for presence of flammable vapour shall be checked by contractor’s supervisor along with HPCL’s
representative before undertaking hot work. Full time supervisor to be provided at work spot and job
shall be carried out only after complying with all safety norms of the depot. A full Time Qualified
Engineer who is technically competent and having sufficient Site experience to be available at site for
supervising and carrying out all the Jobs as per the Scope.
All the safety precautions including supplying & providing localised fire screens etc shall be arranged by
the Contractors as per the directions of Engineer in charge at no extra cost to HPCL. The contractor has
to take necessary precaution for the safe transportation of the material. Before quoting for the said job
the contractor is required to visit the site and make himself acquainted with the scope of the job and
quote accordingly.
The tenderers are required to go through the tender document thoroughly and carefully and offer their
most competitive rates for the job. All sets of this tender document are to be read in conjunction with
each other and accordingly quote in the priced bid.
In case of any clarifications contractor may contact Shri B. S. GOPALA KRISHNA, Senior Manager-E&P,
Engg& Projects Dept., Gresham Assurance House, 2ND Floor, A-1595 (3), 1-A, Sir P M Road, 132, Shahid B
Singh Road, Fort, Mumbai- 400 001 on 022-22608507 regarding any queries. Party may also contact
ShriR. C. Panna, Senior Manager on 06722-229225 or 09437573955regarding any queries.
Page 4 of 34
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
SITE VISIT
1. The bidder is advised to visit and examine the site of works at all locations and their surrounding
and obtain for himself on his own responsibility all information that may be necessary for preparing
of the bid and entering into the contract. The cost of visiting the sites shall be at bidder’s own
expenses. No extra claim on account of non-familiarity of site conditions shall be entertained during
execution of works.
2.The bidder and any of his personnel or agents will be granted permission by the Owner to enter
upon his premises and lands for the purpose of such inspection, but only upon the explicit condition
that the bidder, his personnel or agents will release and indemnify the Owner and his personnel and
agents from and against all liability in respect thereof and will be responsible for personnel injury
(whether fatal or otherwise), loss of or damage and expenses incurred as a result hereof.
The prospective bidders are requested to thoroughly read and comprehend the various sections of this
tender document and visit the sites before quoting for the tender.
Page 5 of 34
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
SCHEDULE
OF
QUANTITIES
Page 6 of 34
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
1. These notes to be read in conjunction with the schedule of quantities and is integral part
of the same.
2. Scope of Work , Supply of Material, Technical Specifications, QAP, ITP( Inspection Test
Plan) Requirement of relevant Codes , SCC( Special Conditions to Contract), GTC (General
Terms & Conditions) , Schedule of Rates ,Statutory Rules & Guide Lines as applicable,
Minimum Equipment / Machineries Deployment and any other requirement to complete
the Job / Work as per this Tender Document shall be deemed to be included in SOR items.
3. For all Items preparation of Design and Construction Drawing as per relevant code &
Tech. Specifications of this Tender & vetting after review by HPCL through Third Party
approved by HPCL, Quality Control , Inspection & Job procedure, Project Scheduling &
Monitoring Document as per SCC , Submission of all these documents to HPCL for
approval deemed to be included in quoted rates.
4. Design of storage tank is also in the scope of the bidder. Tank design along with all
components shall be vetted by IIT, Kharagpur or any reputed institute/consultant as
approved by HPCL. However, the design data sheet is to be approved by HPCL prior to
commencement of design process and subsequent vetting by IIT Kharagpur or any reputed
institute/ consultant. Party has to submit vetted design calculations to EIC and obtain
approval of the HPCL before commencement of the job. Rate to include the same in
respective items and No separate payment shall be made to the party on this account.
5. The Water and Electrical power required for constructional activity shall be in the Scope of
Contractor & shall be deemed to be included in SOR Items.
6. All the Testing and Third Party Charges for Items as per tender documents elicited in
various sections shall be borne by contractor and deemed to be included in quoted rates.
7. All Tools & Tackles, Equipments, and items brought to site by contractor will be permitted
to be taken out only after completion of work & fulfillment of necessary formalities.
8. Rate for all items to include deployment of qualified Quality Control & Safety Engineer at
site from the date of LOI till completion of job as per PO. QC Engineer & Safety Engineer
deployed as per above will report to HPCL site-in-charge on daily basis for complying all
the QC/safety jobs mentioned in the PO.
9. The Drawings/QAP/ITP /Job procedures attached along with tender document are for
guidance/ tender purpose only. The successful bidder to submit the above for HPCL
approval as per the job requirements during the execution of the job.
Page 7 of 34
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
Staking out, marking the outline for excavation, excavation in any type of soil
including soft rock (except hard rock) for general site grading and tank pad
foundations/Ring beams/Foundations of underground tank etc. either by
machinery or manually up to 2.0m below NGL including removal of stumps and
roots to full extent, removal of all vegetation including bushes and grass,
dewatering, taking spot levels @ 5 m C/C in grid pattern, leveling, dressing and
rolling the excavated surface, loading, transportation of surplus earth to an
unobjectionable place inside the site premises, spreading, leveling, compaction
etc as per instructions of the engineer in charge. The job to be executed as per
attached technical specifications, job procedures etc complete and as directed by
EIC.
Page 8 of 34
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
Providing and laying 230mm thick or specified thickness dry trap rubble stone
(granite/basalt)soling at all depths including hand packing, filling the interstices
with chips, spalls and binding with grit and selected murrum, watering,
compaction by hand ramming & rolling with 1 MT hand roller etc complete as per
attached job procedures, technical specification and as per direction of EIC.
Providing and laying Plain Cement Concrete of nominal volumetric mix 1:2:4(1
Cement; 2 Sand: 4Crushed stone aggregates) with 40mm and down size graded
aggregates for bed block for foundations& any other work as per HPCL
requirement including any required shuttering, machine mixing, tamping,
ramming, curing, etc all complete as per Specifications,Drawings, job procedures
etc and instructions of HPCL Engineer-in-Charge.
Designing of mix, Providing, mixing and placing in position M20 mix concrete with
20 mm and down size well graded crushed aggregate including fixing form work,
compacting and curing etc complete as per specifications but excluding the cost
of supply and placing in position steel reinforcement which will be paid under
separateitem. Mobile weigh batcher or Ready Mix Concrete shall be adopted.
Mix Design shall be for Normal exposure. .Concrete ingredients shall conform to
IS 456- 2000. Rate also to include necessary Polythene sheets of approved quality
to be placed before laying the concrete. The job to be executed as per attached
technical specifications, job procedures etc complete and as directed by EIC.
Page 9 of 34
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
Ready Mix Concrete shall be adopted. Mix Design shall be for Normal exposure.
NOTE: Rate also to include necessary brickwork in CM 1:5 required for shuttering
on the inside face of the plinth beam to match the slope and thickness of the tank
apron. The job to be executed as per attached technical specifications, job
procedures etc complete and as directed by EIC.
(1) HSD TANKS - 30.0MDia x 10.0 M Ht- Self-supporting Fixed cone roof – 2 No.
(2) MS TANKS - 28.0 M Dia x 10.0 MHt – External Floating Roof – 2 No.
Plate work for above scheduled Tanks(For Annular bottom and sketch, shell
and roof/deck plates): Taking over and Transportation of Free issue Plates
Page 10 of 34
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
10.0 Shell strakes of thickness varying from 6 mm to 22 mm including extension Metric 400
plates. Ton
11.0 Roof plates including foam dam plates including design of floating roof. Metric 250
ton
Page 11 of 34
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
Important Note:- If the Gamma ray source needs to be kept inside the
location on a continuous basis, all precautions as stipulated by BARC needs
to be strictly followed and approval shall be obtained from them before
keeping the source inside the location.
STRUCTURAL STEEL WORK USING STRUCTURAL STEEL SUPPLIED BY
CONTRACTOR.REFERENCE SHALL BE MADE TO THE SPECIAL TERMS AND
CONDITIONS FOR SCOPE OF SUPPLY AND OTHER DETAILED SPECIFICATIONS
OF MATERIAL.
(For item nos. 12 to 20)
Page 12 of 34
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
STRUCTURAL/PLATE WORK
Structural/ Plate work: Supply, fabrication, erection, inspection and testing of
steel structures as per approved drawings and designs such as rolled
sections, gratings and flats for curb angles, spiral stairways, landings, top
platform, earthing connections cleats, wind girder supports & pad plates,
stiffeners/ gussets for wind girder, deflector plate for wind girders, stiffeners/
catwalks for interconnecting tanks, supply of all materials, consumables,
labour, equipments/ machinery, tools & tackles required to complete the
work as per drawings, Scope of work, technical specifications, job
procedures, QAP/ITP complete and instructions of HPCL Engineer-in-Charge.
Rate to include supply, fabrication, erection & welding, straightening, cutting
to required length supply and fixing all nuts and bolts washers wherever
required for following items. Separate measurements will not be taken for
nuts, bolts, washers etc for payment purpose.
All structural designs shall be vetted by IIT, Kharagpur or any reputed
institute/consultant as approved by HPCL.However, the design data sheet is
to be approved by HPCL prior to commencement of design process and
subsequent vetting by the bidder.
12.0 Supply, fabrication, welding and erection of all floating roof structural, rim Metric 30
and frame angles, pontoon stiffening rafters, curb angles, cleats, support Ton
structural for sprinkler system and foam system, and all angles, gusset
plates, wind girders etc complete as per specifications.
13.0 Supply, fabrication, welding and erection of all self-supporting fixed cone roof Metric 40
structural trusses, rafters, cleats, gussets etc complete as per attached Ton
technical specifications, drawings, job procedures, QAP/ITP and as directed
by EIC.
Job also to include copper slag blasting of the structural members followed
by one coat of 65 micron inorganic zinc silicate primer. The primer shall be
followed with one coat of 100 micron HBMIO followed by two coats of
each of 40 micron polyurethane paint of approved make and shade.
14.0 Structural steel for the hand rail of the stringer type spiral stairway, landing Metric 6
Page 13 of 34
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
platforms and roof top railing like angles, flats and connecting cleat angles. Ton
Note:- Hand rails will be pipe hand rails and will be paid though separate
item.
The stairway step gratings, landing platform gratings, MS square rods will be
paid through a separate item.
15.0 Structural steel for ladder, track, rollers, axle and connecting flat of the self- Metric 6
leveling steps made out of MS gratings only Rate to include supply and Ton
bracing of brass strip over wheels of rolling ladder in floating roof tanks.
Note: Hand rails will be pipe hand rails and will be paid though separate
item. The stairway step gratings will be paid through a separate item.
16.0 Supply, fabrication, welding and erection of pipe hand rails for the staircase Metric 3
made out of 40 mm diaSch 80 seamless pipe conforming to ASTM A106. Ton
17.0 MS square bars of 20 mm size for stairway and ladder as per attached Metric 2
drawings and technical specifications and as directed by EIC. Ton
MS GRATINGS
Supply, fabrication, welding and erection of the following size MS gratings
with MS flat in honey comb pattern as shown in the drawing. The Gratings
shall be fabricated out of 25x6 MS flats(Outer frame, Straight flats) and 25x 3
MS Bent flats. Rate includes grit blasting thoroughly to S.A 2.5 of Swedish
Ivonsk Standard SIS 055900-Latest edition and applying one coat (DFT 65
microns) of inorganic zinc silicate (Zinc anode 304) primer of Berger or
approved equivalent. (For items 56 to 58) followed by 100 micron HBMIO.
18.0 800 x 250 mm size gratings for all stairways with honeycomb pattern. Square 65
meter
19.0 800 x 1000 mm size grating for the top and mid landing platforms with honey Square 55
comb pattern. meter
20.0 800 x 200 mm size gratings for all rolling ladder stairways with honeycomb Square 25
pattern. meter
TANK APPURTENANCES
REFERENCE SHALL BE MADE TO THE SPECIAL TERMS AND CONDITIONS FOR
SCOPE OF SUPPLY AND OTHER DETAILED SPECIFICATIONS OF MATERIAL.
Page 14 of 34
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
23.0 250mm DIA using seamless pipes conforming to ASTM A 106 Grade XS Each 4
Page 15 of 34
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
Foam pourer nozzles of 150 mm dia with reinforcement pad plate, seamless
pipe, ASA class 150 slip on flanges with holes as per ANSI-B 16.5, foam
deflector, gasket, nuts, bolts, washers, flanges including fixing of foam maker
&foam pourer for floating roof and fixed cone roof as per design/tech
specifications/standards/codes complete. Job also includes supplying and
fixing of approved foam maker & pourers as per technical specs attached at
required elevation with gasket, stud bolts, etc complete. All the
Testing/Design/Third party inspection/vetting requirements as per attached
technical specifications/job procedures shall be included in the quoted rate.
No separate payment will be made for the same. The job to be executed as
per attached technical specifications, job procedures etc complete and as
directed by EIC.
Page 16 of 34
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
29.0 GAUGEWELL SLEEVE FOR AUTOLEVEL GAUGE AND MANUAL GAUGE PIPE. EACH 4
Page 17 of 34
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
500 mm nominal diameter manholes with cover plates and handles. Suitable
Neoprene rubber beading / lining of 5/6 mm shall be provided on the neck of
pontoon manhole with proper fixing arrangement to prevent any sparking.
Manhole cover shall be provided with proper locking/venting arrangement.
The job to be executed as per attached technical specifications, job
procedures, drawings etc complete and as directed by EIC
Supply, fabrication, erection of 150 mm nominal dia rim vent, including fixing
of vendor supplied Aluminium pressure vacuum (PV) vent as per attached
specs and approved makes. Rate to include supply, fabrication, erection of
pipe, flanges and PV vent.
Page 18 of 34
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
Complete layout of Primary Roof Drain shall be provided by the supplier and
installed by the Contractor. Contractor shall supply all required materials.
35.0 100 mm NB (actual length to be as per site conditions) seamless pipes of Meters 100
schedule 40 thickness for sleeves of legs.
36.0 80 mm NB( actual length to be as per site conditions)seamless pipes of Meters 180
schedule 80 thickness for leg supports with holes drilled as specified in the
drawing for two operating levels one at 1.8 mt and the other at 1.2 mt
respectively and MS rod and cotter pin of specified size.
2. The 80 mm dia leg support shall have 36mm dia sleeve at locations where
holes are drilled.
3. Bearing plate under each pipe supports (legs) shall be welded around.
4. 100 mm Sleeve shall be brass brazed at the top and bottom for length. of
50 mm measured along the pipe.
6. The rates to include supply and fixing of neoprene between sleeve and leg
Page 19 of 34
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
Supply, fabrication, erection and welding of the 400 mm NB gauge well using
seamless pipes conforming to ASTM A 106 Gr B of schedule 40 thickness with
holes drilled as per drawing. Rate to include supply, fabrication and welding
of the neck rings, seamless pipes, bolting flanges, supplying and fixing of all
gaskets ,stud bolts and fabrication and connecting the well pipes with party
supplied Al gauge hatches complete along with welding of 600 x 600 x 8 mm
datum plate as per specifications. Rate also to include providing and fixing
guide pole cover/housing of approved design and make to minimize
evaporation of MS/HSD and other volatile organic compound (VOC).
Necessary structural supports shall be paid vide item no 12. Job to be
executed as per attached technical specifications, job procedures, drawings
etc complete and as directed by EIC
Note: One no. 200 mm NB & one no. 80mm NB pipes shall be placed inside
400mm NB pipes erected against this item. However, the same shall be paid
separately against item nos. 39&40 respectively. Party shall quote only for
400 mm NB Combined still well pipes.
Supply, fabrication, erection and welding of the 300 mm NB gauge well using
seamless pipes conforming to ASTM A 106 Gr B of schedule 40 thickness with
holes drilled as per drawing. Rate to include supply, fabrication and welding
of the neck rings, seamless pipes, bolting flanges, supplying and fixing of all
gaskets ,stud bolts and fabrication and connecting the well pipes with party
supplied Al gauge hatches complete along with welding of 600 x 600 x 8 mm
datum plate as per specifications. Rate also to include providing and fixing
guide pole cover/housing of approved design and make to minimize
evaporation of MS/HSD and other volatile organic compound (VOC).
Necessary structural supports shall be paid vide item no 13.0. Job to be
executed as per attached technical specifications, job procedures, drawings
etc complete and as directed by EIC.
Supply, fabrication, erection and welding of the 200 mm NB gauge well using
Page 20 of 34
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
Note: The above 80mm NB pipes shall be placed inside 400mm NB pipes
erected against this item for floating roof tank.
Page 21 of 34
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
all drawings and obtaining HPCL approval. Supply of all materials and
installation of primary mechanical shoe seal using SS metallic shoe of dept
1.2mm (for sliding contact along with primary seal fabric) and rim mounted
Secondary Seal along with all fixtures, inspection and testing of all materials
and sealing device namely Pusher Mechanism of SS 304 grade, Hanger, dip
curtain of PTFE, SS shunt, shoe, Secondary seal. Providing Two Year
performance Guarantee for the Primary and Secondary seals from the date of
commissioning all complete as per specifications, standards and instructions
of HPCL Engineer-in-Charge. Contractor shall furnish the name of the supplier
and Model quoted in the tender along with relevant catalogues in Unpriced
Bid.
600 mm nominal dia roof manhole with neck ring, manhole cover plate with
handle, bolting flange, MS reinforcement pad plate and suitable dia stud
bolts etc complete.
45.0 ROOF NOZZLES (VENT) with PRV – Fixed Cone Roof Each 4
Page 22 of 34
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
Supply and fixing of 200 mm dia. Roof nozzles With PRV as per attached
specifications with reinforcement pad plate, MS ERW pipe of suitable
thickness,180 degree forged steel bend of sch 40, ASA class 150 slip on
flanges with holes drilled as per ANSI-B-16.5, stud bolts, washers etc
complete. Rate to include fixing of vendor supplied Aluminium pressure
relief valve.
Supply, fabrication, erection and welding of the 200 mm NB gauge well using
seamless pipes conforming to ASTM A 106 Gr B of schedule 40 thickness
with holes drilled as per drawing. Rate to include supply, fabrication and
welding of the neck rings, seamless pipes, bolting flanges, supplying and
fixing of all gaskets ,stud bolts and fabrication and connecting the well
pipes with party supplied Al gauge hatches complete along with welding
of 600 x 600 x 8 mm datum plate as per specifications. Necessary
structural supports shall be paid vide item no 13.0.Job to be executed as
per attached technical specifications, job procedures, drawings etc
complete and as directed by EIC
Page 23 of 34
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
48.0 30.0 M Dia x 10.0 M HtSelf-supporting Fixed cone roof Tank EACH 2
50.0 30.0 M Dia x 10.0 M Ht Self-supporting Fixed cone roof Tank EACH 2
NOTE: In case of any leaks observed during any of the above tests contractor
shall decant the water up to 300 mm below the leak, repair the leak and
again test the tank by filling the water to the satisfaction of the Engineer-in-
charge. Contractor shall repeat the process till all the leaks are rectified.
Page 24 of 34
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
TANK CALIBRATION
CALIBRATION OF TANK BOTTOM(Note: For Item Nos 54 & 55)
Physical calibration of the following dia tank bottom by calibrated flow meter
up to the datum plate. Rate to include arrangement of equipment necessary
pumping water, taking readings as per technical specifications, job
procedures etc complete and as directed by EICand presenting the same etc.
complete including certification by proper statutory authorities.
54.0 30.0 M Dia x 10.0 M Ht Self-supporting Fixed cone roof Tank EACH 2
56.0 30.0 M Dia x 10.0 M Ht Self-supporting Fixed cone roof Tank EACH 2
Page 25 of 34
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
the visit of representatives from W&M. All statutory fees and any other
expenses in this regard shall be borne by the contractor. Rate quoted in the
above 4 items shall include certification by W&M. Certificates to be handed
over to HPCL.
Supply ,fixing of thermal safety valve for a differential pressure of range 6.5-
7.5 kg/cm2 as per attached technical specifications, drawings and as directed
by EIC complete. The TSV shall be designed for back pressure of max 1.5
2
kg/cm . The Make of the TSV shall be “Tyco” or equivalent as approved by
HPCL. The design calculations for selection for a particular tanks regarding set
pressure shall be submitted by the vendor and the same shall be approved by
HPCL before procurement.
Page 26 of 34
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
TANK EARTHING
EARTHING PITS
Supply and fixing of 25 sq. mm braided copper cables between rolling ladder
and track & rolling ladder and platform at the top. Rate to include supply and
fixing of Copper lugs, bolts etc. complete. Job to be executed as per technical
specifications, drawings, job procedures etc complete and as directed by EIC
Page 27 of 34
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
Design, supply, fabrication, erection and testing of following size pipes for
sprinkler system conforming to IS 1239/3589 as per attached specs in the
specified curvature and installing with necessary GI ‘U’ clamps supplied by
the party on the periphery of floating roof tanks on angle support welded on
the shell of the tanks. Job includes supply, fabrication, welding of necessary
half couplings to MS pipe for fixing m sprinkler nozzles, fabrication and
welding of angle supports (shall be paid separately under the item no. 20).
The curved pipe to have flange joints every 6 m for ease of removal and
replacement at a later date. Supplying and fixing necessary flanges, gaskets,
stud bolts as per HPCL specs attached to this tender are in the scope of the
vendor. Rate to include all the Testing/Design/Third party
inspection/vetting requirements as per attached technical
specifications/job procedures shall be included in the quoted rate. No
separate payment will be made for the same.Job to be executed as per
technical specifications, drawings, job procedures etc complete and as
directed by EIC.
Design, supply, fabrication, erection and testing of following size pipes for
sprinkler/foam system conforming to IS 1239/3589 as per attached specs for
the vertical tap-off / connection for sprinkler lines / foam makers including
installing necessary ‘U’ clamps/ stopper rods on the periphery of floating roof
tanks and on support angles (shall be paid separately under the item no. 55)
welded on the shell of the tanks. Battery limit flange also to be supplied and
welded by the party. (Note: For items 68 & 69)
Note:- For the items 66 to 70, party to submit the design from a reputed fire
fighting equipment manufacturer/ consultant for sprinkler / foam line
sizing and selection of numbers & K value of the sprinkler nozzles provided
Page 28 of 34
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
at each level, based on tender specs ,TPI vetted, for HPCL approval before
proceeding with the procurement activities.
EXTERNAL PAINTING OF TANKS
Page 29 of 34
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
Page 30 of 34
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
INTERNAL PAINTING
Page 31 of 34
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
Note: - Payment for this item will be made on actual surface area of tank
shell and roof measured only once.
EACH
77.0 30.0 M Dia x 10.0 M Ht Self-supporting Fixed cone roof Tank 2
PU PAINTING( STAIRWAY) :
79.0 30.0 M Dia x 10.0 M Ht Self-supporting Fixed cone roof Tank EACH 2
80.0 28.0 M Dia x 10.0 M Ht External Floating roof/open roof Tank EACH 2
Page 32 of 34
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
Supply and painting the logo sign of the 2.4 M x 3.0 M size for the above
ground tanks on the top or penultimate shell or as directed by Engineer-In-
Charge. Rate to include for supply of required shade of enamel paints of
approved make, supply and erection of pipe scaffolding and painting the logo
Page 33 of 34
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
85.0 COPPER SLAG BLASTING AND PRIMER COAT INSIDE PONTOONS EACH 56
Page 34 of 34
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
UNPRICED BID
Page 1 of 5
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
SR.
DESCRIPTION UNIT QUANTITY
NO
Excavation up to 2.0 meter Cubic Meters 250
1
Murrum Filling Cubic Meters 2000
2
Rubble Soling Cubic meters 75
3
Plain Cement Concrete 1:2:4 Cubic Meters 50
4
RCC M 20 Tank Apron Cubic Meters 135
5
RCC M 20 Ring Beam Cubic Meters 75
6
REINFORCEMENT STEEL Metric ton 12.5
7
ANTI CORROSIVE LAYER Square meters 3000
8
F & L BOTTOM PLATES Underside painting
Metric Ton 310
9 incl.
Page 2 of 5
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
Page 3 of 5
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
CR TANK
Page 4 of 5
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
HEADINGS Each 4
82
LETTERING Each 4
83
LOGO Each 4
84
Page 5 of 5
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
TIME SCHEDULE
Page 1 of 2
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
TIME SCHEDULE
DESCRIPTION OF WORK:
PARADEEP
ORISSA
NOTE:
1) Time for completion shall be reckoned from the date of issue of Fax/ Letter of
Intent/Purchase Order by HPCL.
2) Time for completion shall include the time required for mobilization, design,
QAP, fabrication, erection, Testing, calibration, handing over, demobilization,
carrying out the works as per requirements of Contract Document and
instructions of HPCL Engineer-in-Charge.
Page 2 of 2
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
SPECIAL CONDITIONS
OF
CONTRACT
Page 1 of 24
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
1.0 GENERAL
1.1 Special Conditions of Contract (SCC) shall be read in conjunction with the
General Conditions of Contract (GCC) also referred to as General Terms &
Conditions of Works Contract, Schedule of Quantities, specifications of
work, drawings and any other document forming part of this Contract
wherever the context so requires.
1.3 Where any portion of the GCC is repugnant to or at variance with any
provisions of the Special Conditions of Contract, then unless a different
intention appears, the provision(s) of the Special Conditions of Contract
shall be deemed to override the provision(s) of GCC only to the extent
that such repugnancy or variations in the Special Conditions of Contract
are not possible of being reconciled with the provisions of GCC.
1.4 Wherever it is stated in this Bidding Document that such and such a
supply is to be affected or such and such a work is to be carried out, it
shall be understood that the same shall be affected and /or carried out by
the Contractor at his own cost, unless a different intention is specifically
and expressly stated herein or otherwise explicit from the context.
Contract Price shall be deemed to have included such cost.
1.5 The materials, design & workmanship shall satisfy the applicable relevant
Indian Standards, the job specifications contained herein & codes referred
to. Where the job specifications stipulate requirements in addition to those
contained in the standard codes and specifications, these additional
requirements shall also be satisfied. In the absence of any Standard /
Specifications / Codes of practice for detailed specifications covering any
part of the work covered in this bidding document, the instructions /
directions of Engineer-in-Charge will be binding upon the Contractor.
Page 2 of 24
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
1.7.1 Contractor shall provide adequate number of standard lengths of IS Stamped Fire
hoses, IS Stamped DCP Fire extinguishers, fire buckets with sand and nozzles.
These items can be taken back by the Contractor after completion of work. Sand
shall also be maintained dry by the Contractor with fresh supply, whenever
required. Work permit may not be issued by HPCL in the absence of above items.
1.7.2 Safety Helmets shall be provided to all the employees of Contractor including
that of his labour contractors.
1.7.3 Safety Belts and Harnesses shall be provided by the Contractor in adequate
number for the workers working at heights.
1.7.4 Proper earthing shall be provided for all equipments and generators.
2.1.1 The scope of work and Scope of Supply covered in this Contract
will be as described in Scope of work provided in the Instructions
Page 3 of 24
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
The Completion period for Construction of Petroleum Oil storage tanks on existing
pile foundation shall be 6(SIX) Months from the date of handing over the site.
2.2.1 Time is the essence of this Contract. The period of completion given includes
the time required for mobilization as well as testing, rectifications, if any,
retesting, demobilization and completion in all respects to the satisfaction
of the Engineer-in-Charge.
2.2.4 Contractor shall give every day category-wise labour and equipment
deployment report along with the progress of work done on previous day
in the proforma prescribed by the Engineer-in-Charge.
2.4.1 Payment will be released within 15 days of submission of duly certified Running
Account Bills at Disbursement section at Mumbai after deduction of
Page 4 of 24
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
2.5.1 All temporary works, enabling works, including dewatering of surface and
subsoil water, preparation and maintenance of temporary drains at the
work site, preparation and maintenance of approaches to working areas,
adequate lighting, wherever required, for execution of the work, shall be
the responsibility of the Contractor and all costs towards the same shall be
deemed to have been included in the quoted prices.
Page 5 of 24
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
2.7 Leads
2.7.1 For the various works, in case of contradiction, leads mentioned in the
Schedule of Quantities shall prevail over those indicated in the Technical
specifications.
3.1 Royalty
3.1.1 All royalties etc., as may be required for any Borrow Areas, including right
of way etc., to be arranged by Contractor shall be deemed to have been
included in the quoted prices.
3.1.2 Contractor’s quoted rates should include the royalty on different applicable
items as per the prevailing State Government rates. In case, Owner is able
to obtain the exemption of royalty from the State Government the
Contractor shall pass on the same to Owner for all the items involving
royalty. Any increase in prevailing rate of royalty shall be borne by the
Contractor at no extra cost to the Owner.
3.2.1 Income Tax at the prevailing rate as applicable from time to time shall be deducted
from Contractor’s Bills as per Income Tax Act and quoted rates shall be inclusive
of this. Owner will issue the TDS (Tax Deduction at Source) Certificate.
3.3 Firm Prices
3.3.1 The contract price shall remain firm and fixed till the completion of work in
all respects and no escalation in prices on any account shall be admissible
to the Contractor except for statutory variations as per General Terms and
Conditions (GTC).
Page 6 of 24
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
4.1.1 The Contractor shall strictly comply with the provisions of Employees
Provident Fund Act and register himself with Regional Provident Fund
Commissioner (RPFC) before commencing work. The Contractor shall deposit
Employees and Employers contributions to the RPFC every month. The
Contractor shall furnish along with each Running bill, the challan / receipt
for the payment made to the RPFC for the preceding month. The
Contractor shall furnish the code number allotted by the RPFC Authority to
the Engineer-in-Charge before commencing the work.
4.1.2 In case the RPFC challan / receipt, as above, is not furnished, Owner shall
deduct 16% (sixteen percent) of the payable amount from Contractor’s
running bill and retain the same as a deposit. Such retained amounts shall
be refunded to Contractor on production of RPFC Challan / receipt for the
period covered by the related running bill.
4.2.1 Before starting of work, Contractor shall obtain a license from concerned
authorities under the Contract Labour (Abolition and Regulation) Act 1970,
and furnish copy of the same to Owner.
4.3.2 The Contractor shall at all times take all reasonable precautions to prevent
any unlawful, riotous or disorderly conduct by or amongst his staff and
labour and to preserve peace and protection of persons and property in
the neighbourhoods of the Works against such conduct.
Page 7 of 24
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
4.4.1 The Contractor shall ensure that local labour skilled and / or unskilled, to
the extent available shall be employed in this work. In case of non –
availability of suitable labour in any category out of the above persons,
labour from outside may be employed.
4.4.2 The Contractor shall not recruit personnel of any category from among
those who are already employed by other agencies working at site but
shall make maximum use of local labour available.
4.5.1 The Contractor shall clean and keep clean the work site from time to time
to the satisfaction of the Engineer-in-Charge for easy access to work site
and to ensure safe passage, movement and working.
4.5.2 The Contractor shall dispose off the unserviceable materials, debris etc., to
the earmarked area within the premises or any other location outside the
premises as decided by the Engineer-in-Charge. No extra payment shall be paid
on this account.
4.5.3.1 HPCL/consultant will normally require and utilize a maximum time frame of seven
(07) working days from the date of Receipt for Review/Approval of Drawings,
Design and other documents submitted by Contractor. Upon Review of the
submitted documents, HPCL may give their comments and ask for redesign/
resubmission after necessary rectifications/ modifications and the time frame of
7 working days will be applicable for same.
4.6.1 Contractor shall obtain all clearance (work permit) from the Owner, as may
be required from time to time, prior to start of work. Work without
permit shall not be carried out within the existing premises.
Page 8 of 24
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
4.6.2 Contractor shall obtain plans and full details of all existing and planned
facilities/services/utilities from the Owner and shall follow these plans
closely at all times during the performance of work. Contractor shall be
responsible for location and protection of all facilities/utilities and
structures at his own cost.
4.6.3 Despite all precautions, should any damage to any structure / utility etc. occur,
the Contractor shall contact the Owner / authority concerned and
Contractor shall forthwith carry out repair at his expenses under the
direction and to the satisfaction of Engineer-in-Charge and the
Owner/concerned authority.
4.6.4 Contractor shall take all precautions to ensure that no damage is caused
to the existing facilities etc., during construction. Existing
structures/facilities/utilities damaged / disturbed during construction shall be
repaired and restored to their original condition by Contractor after
completion of construction to the complete satisfaction of Owner.
4.7.1 The work involved under this Contract may include such works as
have to be taken up and completed after other agencies have completed
their jobs. The Contractor will be required and bound to take up as and
when the fronts are available for the same and no claim of any sort
whatsoever shall be admissible to the Contractor on this account. Only
extension of time limit shall be admissible, if the availabilities of work
fronts to the Contractor are delayed due to any reason not attributable to
the Contractor and the same is clearly recorded.
4.8.1 The Contractor shall arrange for the following facilities at site, for workmen
deployed/engaged by him / his sub-contractor, at his own cost:
Page 9 of 24
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
4.9.1 Owner shall provide land only for contractor’s site office and stores and
fabrication yard, if any at site. However, same shall be dismantled prior to
submission of Final Bill.
4.9.2 The Contractor shall remove all temporary buildings / facilities etc., before
leaving the site after completion of works in all respect.
4.10.2 Water required for the works shall be arranged by the Contractor. The
contractor has to make all necessary arrangement for drawing water
including making temporary storage, pumping etc.
4.10.3 CEMENT:
Cement required for execution of the job under the entire scope of work (other
than for Ready Mix Concrete where the cement is from the RMC manufacturer
scope) contained in this tender shall be supplied at provided at site by the
contractor at his own cost. Contractor to include the cost of cement required
for execution of various items included in this tender in their quoted rates.
Cement shall be of 43 / 53 Grade OPC as specified in the technical specifications
of Ultra Tech Cement/ Gujarat Ambuja / ACC / Birla / Lafarge Makes only and
shall conform to IS relevent standards of latest edition. Contractor to produce
Invoice Copy of every batch of cement procured at site to EIC. However, HPCL’s
decision with regard to the specific brand of cement to be procured for the
execution of the work shall be final and binding on the contractor.
Page 10 of 24
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
The contractor will be required to maintain a stock register for receipt, issuance
and daily consumption of cement at site. Cement shall be regulated on the basis
of 1st receipt to go as 1st issue. Cement not consumed within 3 months after
bringing to site shall not be used and shall be removed from site with prior
written permission of EIC.
All RA bills including the final bills will be accompanied by Cement Consumption
Statements giving the detailed working of cement used.
HPCL will not entertain any claims by the Contractor for theft, loss or damages to
cement. Contractor shall not remove from the site any cement bags at any time.
Entire quantity of reinforcement / structural steel required for the project shall
be supplied and provided at site by the contractor at his own cost. Contractor
to include the cost of steel reinforcement / structural steel required to be used
against various items of this scope of work in their quoted rates. HPCL shall not
supply any reinforcement / structural steel. The contractor shall make necessary
Page 11 of 24
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
arrangement at his own cost for unloading, storage of steel in the open duly
fenced under locking arrangement. The reinforcement steel shall be procured
from Tata/SAIL/Vizag Steel/Jindal and will produce invoice for the same to EIC
for every batch of procurement alongwith Manufacturer’s Test Certificate.
For the purpose of dealing and accounting, only linear measurements will be
taken and any difference in weight based on linear measurement and actual
weight shall be to contractor’s account. Quoted rate shall be deemed to include
the above and the wastage mentioned below. No claim whatsoever shall be
entertained on account of wastage and difference in weight as referred to
above.
All binding wires required for tying the reinforcement in position etc. will be
supplied by the contractor. Cost of this binding wire and labour will be included
in the item for binding and placing reinforcement in position.
It will be necessary that the contractor get the steel tested at his own cost at a
Govt. approved laboratory as per the testing schedule or as per the EIC’s advise,
for strength and other properties specified in IS – 1786 latest editioin before
using it in the work.
The permissible wastage (wastage defined as bars having less than 3 mt. Length)
shall be of 3% of theoretical consumption. Recovery for less consumption as per
theoretical consumption will be recovered at Rs.50,000/- per MT. All scrap
(scrap defined as pieces of steel bars measuring less than 3 mt. in length) shall be
Page 12 of 24
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
the property of the contractor. The wastage quantity shall not be considered to
be included within the theoretical quantity and no extra shall be payable on
account of wastage.
4.11 Construction
5.0 Procedures
5.2 Security
5.2.1 As the premises will be protected area, entry into the area shall be
restricted and may be governed by issue of photo gate passes. The
Contractor shall arrange to obtain through the Engineer-in-Charge, well in
advance, all necessary entry permits/gate passes for his staffs and labourers
and entry and exit of his men and materials shall be subject to vigorous
checking by the security staff. The Contractor shall not be eligible for any
claim or extension of time whatsoever on this account.
Page 13 of 24
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
enable the bidder to make an offer in line with the requirements of the
owner.
5.3.2 The contractor as per ‘scope of work’ shall carry out preparation of detailed
and working drawings. Detailed construction layout drawings as needed
shall be prepared by contractor and got reviewed/approved by Engineer-in-
Charge/Architect before taking up the work.
5.4.1 All payments to and recoveries from the Contractor shall be rounded off to
the nearest rupee. Wherever the amount to be paid / recovered consists of
a fraction of a rupee (paise), the amount shall be rounded off to the next
higher rupee if the fraction consists of 50 (fifty) paise or more and if the
faction of a rupee is less than 50 (fifty) paise, the same shall be ignored.
5.5.1 HPCL will provide an approved format for Measurement sheets, Bill Summary and
Bill Abstract. Contractor has to ensure that these data are updated for each
subsequent RA and Final Bill.
5.5.1 HPCL will utilize these data for processing and verification of the
Contractor’s bill.
5.6.2 The Contractor shall provide all necessary superintendence during the
execution of the Works and as long thereafter as the Engineer-in-Charge
may consider necessary for the proper fulfilling of the Contractor’s
obligations under the Contract Such superintendence shall be given by
Page 14 of 24
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
Owner reserves the right to execute any additional works / extra works,
during the execution of work, either by themselves or by appointing any other
agency, even though such works are incidental to and necessary for the
completion of works awarded to the Contractor.
5.8.1 It shall be the responsibility of the contractor to obtain the approval for
any revision and/or modifications decided by the contractor from the
Owner / Engineer-in-Charge before implementation. Also such revisions and /
or modifications if accepted / approved by the Owner / Engineer-in-Charge
shall be carried out at no extra cost to the owner. Any change required
during functional requirements or for efficient running of system, keeping
the basic parameters unchanged and which has not been indicated by the
contractor in the data / drawings furnished along with the offer shall be
carried out by the contractor at no extra cost to the owner.
5.8.4 Preparing approaches and working area for the movement of his men and
machinery.
Page 15 of 24
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
5.8.5 The procurement and supply in sequences and at the appropriate time of
all materials, and consumables shall be entirely the contractor’s
responsibility and his rates for execution of work will be inclusive of
supply of all these items.
5.9.1 Contractor shall be responsible for proper coordination with other agencies
operating at the site of work so that work may be carried out
concurrently, without any hindrance to others. The Engineer – in – Charge
shall resolve disputes, if any, in this regard, and his decision shall be final
and binding on the Contractor.
5.10.1 The Contractor will familiarize himself with and obtain information and
details from the Owner in respect of all existing structures, and utilities
existing at the job site before commencing work. The Contractor shall
execute the work in such a manner that the said structures, utilities, etc.
are not disturbed or damaged, and shall indemnify and keep indemnified the
Owner from and against any destruction thereof or damages thereto.
5.11.2 The Contractor shall furnish a No-Claim/No-Due declaration indicating that there
are no balance dues to his sub-vendor/sub-contractors/labour contractors along
with the Final Bill.
Page 16 of 24
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
6.1.1 The Contractor shall carry out the various tests as enumerated in the
technical specifications of this Bidding Document and technical documents
that will be furnished to him during the performance of the work at no
extra cost to the Owner.
6.1.2 All the tests either on the field or at outside laboratories concerning the
execution of the work and supply of materials by the Contractor shall be
carried out by Contractor at his cost.
6.1.4 Compressed air for carrying out works ,if required shall be arranged by the
Contractor at his own cost.
6.1.5 For material supplied by Owner, Contractor shall carry out the tests, if
required by the Engineer-in-Charge, and the cost of such tests shall be
reimbursed by the Owner at actual to the Contractor on production of
documentary evidence.
6.1.6 All results of inspection and tests will be recorded in the inspection
reports, proforma of which will be approved by the Engineer-in-Charge.
These reports shall form part of the completion documents. Any work not
conforming to execution drawings, specifications or codes shall be rejected
and the Contractor shall carry out the rectifications at his own cost.
Page 17 of 24
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
6.2Final Inspection
After completion of all tests as per specification the whole work w ill be subject to a
final inspection to ensure that job has been completed as per requirement.
If any defect is noticed, the Contractor will be notified by the Engineer-in-
Charge and he shall make good the defects with utmost speed. If
however, the Contractor fails to attend to these defects within a
reasonable time (time period shall be fixed by the Engineer-in-Charge) then
Engineer-in-Charge may have defects rectified at Contractor’s cost.
6.3.1 All inspection and tests on bought out items shall be made as required by
specifications forming part of this contract. Various stages of inspection
and testing shall be identified after receipt of Quality Assurance
Programme from the contractor / manufacturer.
6.3.3 The contractor shall ensure full and free access to the inspection
engineer of Owner at the contractor’s or their sub-contractor’s premises at
any time during contract period to facilitate him to carry out inspection
and testing assignments.
6.3.4 The contractor / sub – contractor shall provide all instruments, tools,
necessary testing and other inspection facilities to inspection engineer of
Owner free of cost for carrying out inspection.
6.3.5 Where facilities for testing do not exist in the contractor’s / sub-
contractor’s laboratories, samples and test pieces shall be drawn by the
contractor / sub-contractor in presence of Inspection Engineer of Owner and
duly sealed by the later and sent for tests in Government approved test
Page 18 of 24
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
6.3.6 The contractor shall comply with the instructions of the Inspection
Engineer fully and with promptitude.
6.3.8 The contractor shall not offer equipment for inspection in painted
conditions unless otherwise agreed in writing with the Owner .
6.3.9 The contractor shall ensure that the parts once rejected by the
inspection engineer are not used in the manufacture of the plant and
equipment. Where parts rejected by the inspection engineer have been
rectified or altered, such parts shall be segregated for separate inspection
and approval, before being used in the work.
6.4 Documentation
Page 19 of 24
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
7.0 OTHERS
7.1.1 In the event of any disputes or differences between the Contractor and the
Owner, if the Contractor is a Government department, a Government
company or an undertaking in the public sector, then such disputes or
differences shall be resolved amicably by mutual consultation or through
the good offices or empowered agencies of the Government. If such
resolution is not possible, then the unresolved disputes or differences shall
be referred to arbitration of an arbitrator to be nominated by the
Secretary. Department of legal affairs (Law Secretary) in terms of the
Office Memorandum No. 55 / 1 / 75 – CF dated 19th December 1975 issued
by the Cabinet Secretariat (Dept. of Cabinet Affairs) as modified from time
to time. The Arbitration Conciliation Act 1996 shall not be applicable to
the arbitrator under this clause. The award of the arbitrator shall be
binding upon parties to the dispute, provided, however any party aggrieved
by such award may make a further reference for setting aside or revision
Page 20 of 24
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
of the award to Law Secretary whose decision shall bind the parties finally
and conclusively.
7.2.4.1 The CONTRACTOR shall present the programme and status at various review
meetings as required.
Venue : Site
Page 21 of 24
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
Daily report in duplicate as out lined in 2.2.4 of SCC and any other additional
information/data/guideline/job procedure sought by Engineer-in-Charge shall be
submitted without fail to HPCL at site by contractor.
The contractor has to ensure efficient use of natural resources like water,
fuel oil and lubricants. The contractor should ensure proper awareness to
workers to maintain a green and clean environment inside / outside the
building premises. The contractor must collect and dispose of all the waste
and scrap materials at the designated place only as directed by Engineer – in
– Charge.
Page 22 of 24
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
APPENDIX -1 TO SCC
TERMS OF PAYMENTS
1.1 The basis and terms of payment without prejudice to any other mode of
recovery available to Owner, shall be as given below :
1.2 The Contractor shall be paid monthly running account bills at stages of
completion of individual item / work, based on the joint measurement, in
the following manner after deductions of necessary dues payable by
Contractor to the Owner such as Retention money, Taxes, Duties etc. in
accordance with various provisions made elsewhere in this document.
Following payment shall be made to the contractor against the running bills
subject to the rate awarded to him and the clause regarding retention money as
per general terms and conditions.
30 % after Fabrication
25 % after erection & welding,
10% after radiography
30 % after hydro-testing
5% after Completion and acceptance by HPCL as pr SOR
Page 23 of 24
CONSTRUCTION OF PETROLEUM OIL STORAGE TANKS AT PARADEEP
NOTES :
1.For Each stage, necessary testing shall be completed prior to claiming the
percentage break-up as given above
2. Partial bill will be processed only after submission of duly certified copy of
proof of payment towards royalty.
3. Final bill will be processed only after submission of “No objection certificate”
from relevant statutory authorities towards payment of royalty.
Page 24 of 24
GENERAL
SCOPE OF WORK
FOR
TANKS
Page 1 of 27
1.0 SCOPE OF WORK
The scope of work for Contractor shall include the following but not limited to the
same. The scope of work shall also include other items / works required to
complete the work in all respects as per specifications, standards, drawings, IS
codes/API Standards & instructions of HPCL whether specifically mentioned or
not in the tender document :
ii) Preparation of all detailed and working drawings including plate cutting
diagrams for various components of storage tanks & getting the same
reviewed and approved by HPCL prior to commencement of work. No work
will commence without HPCL’s approval on drawing by Engineer in Charge.
iii) Preparation, Submission for Review and obtaining approval from HPCL for
Detailed Quality Assurance System plans/ procedures developed by
contractor basis Std. Inspection & Test Plan furnished in this tender/ Scope
of work/SOR/GTCC/SCC & other relevant codes. The same shall be
reviewed / approved by HPCL prior to commencement of work. The required
competent man power, machinery, tools, tackles, equipments, etc required
to execute the work as per the Approved Quality assurance plan (QAP) shall
be the responsibility of contractor. Due records will be maintained by
contractor through out the work period as per instructions of Engineer-in-
Charge.
Vii) Time is the essence of this contract. Monthly/weekly Execution Plans will be
developed by Contractor in consultation with Engineer- in- Charge &
execution of work as per these plans will be the sole responsibility of
contractor. Scheduling & Monitoring of awarded work is the SOLE
RESPONSIBILITY of contractor, in this regards rates quoted shall include
following:
1. Kick off Meeting shall be planned by contractor within SEVEN DAYS
from date of LOI.
2. Contractor shall submit DETAILED BAR CHART/RESOUCE
PLAN/MICRO SCHEDULING ACTIVITY WISE giving earliest & latest
date with back up calculation of Man –Power, Machinery,
Consumables,, etc for HPCL’s approval for Tankage Work All the
queries on matter suggested by HPCL will be complied on mutual
discussion basis & Final Detailed Bar Chart will be made implemented
within Fifteen days from date of LOI.
Page 2 of 27
3. Contractor will provide his authorized nominee at site to take
participation in weekly meeting & to sign the Records of Meeting.
4. Contractor will submit on daily basis Progress Report to be generated
at site in E Form through E- Mail @ the address provided by HPCL
giving all the details including valid reasons for delay if any vis-à-vis to
commitment i.e. weekly plan /monthly plan /approved bar chart in
prescribed format approved by HPCL.
5. Contractor to submit procurement plans for various item falling under
their scope to supply under this tender along with Bar Chart vide point
Vii 2.
iv) (A) Submission of Design calculations of TANK AS PER RESPECTIVE
standards in detail for review by EIL or IIT, Kharagpur or equivalent as
approved by HPCL and thereafter, approval by HPCL. The document shall
be first submitted to HPCL and same shall be forwarded by HPCL to EIL or
IIT or any other approved institution by HPCL. The charges for vetting of
design by EIL or IIT, Kharagpur shall be borne by the Contractor. It shall be
the sole responsibility of the Contractor to prove these design calculations
details while conducting the Test to HPCL Engineer in toto. Contractor shall
also carry out design calculations as per API 650 & other relevant codes for
Shell, Bottom plates incl. annular sketch plate, wind girder, stability against
wind & seismic movement, Brackets for Top Wind Girder /Plate form,
Brackets for Sprinkler & Foam Pipe etc
1. Welding Procedure Specifications for all the Weld Joints to be made in field for
Bottom, Shell & Roof along with all other type of joints shall be prepared by
contractor as per QW-482 Suggested Format for WPS in ASME Sect.IX.
(Sample Joint design QW 402 for various joint is attached in Tender Document).
The same will be vetted/certified by HPCL approved Third Party like IRS, BV,
TUV etc. The weld joints will be made in accordance to respective approved
WPS only.
Page 3 of 27
3. QW 484 ASME Sect.IX Welding Operator Performance Qualification will be
conducted in presence of HPCL Engineer and HPCL approved Third Party like
IRS, BV, TUV etc.. at site. After due testing of Test Piece like radiography etc
WOPQ duly certified by Third party will be submitted to HPCL for all proposed
deployed welding operators.
4. Contractor shall submit proposed number of radiographs shots as per API 650
along with procedures for undertaking shots on the drawing i.e. operating with
required due safety /Health/Environment precautions and Film review norms in
accordance to API 650, ASME IX & respective other standards duly vetted by
HPCL approved Third Party to enable HPCL to direct for Shots.
5. FILMS will be reviewed & vetted by HPCL approved Third Party. HPCL will
witness the process randomly.
6. All the third party charges shall be borne by the contractor. No separate
payment will be made on this account.
xi) Supply, Fabrication and erection of Inlet and outlet troughs for Inlet and
Outlet nozzles.
xii) Design, Fabrication, Erection and testing of External single deck floating roof
(EFR)and its components with foam dam and its accessories including pipe
supports & appurtenances including welding on underside.
xiii) Design, Fabrication, Erection and testing of Fixed Cone roof tanks with self
supporting(FR) truss and its components with necessary sprinkler/foam
appurtenances etc and its accessories.
xiv) Design, Fabrication, Erection and testing of Open roof tanks appurtenances
etc and its accessories.
Page 4 of 27
xvi) Conducting Floatation test for the roof (EFR & IFR)
xviii) Design and its vetting/ Review and approval by HPCL, procurement, supply,
fabrication, erection, testing, & commissioning of Sprinkler/Foam system
complete in all respects, structural supports for Foam cooling system risers,
etc.
xix) Design and its vetting/ review and Approval, procurement, Third party
Inspection, supply & installation of Primary shoe seal and Secondary seals
floating roof tanks s with all components and accessories etc as per
manufacturer’s instructions.
xx) Supply & fabrication of stairways, handrails, landing platforms, curb angle,
bracing for foam dam, structural supports for primary wind girders.
xxi) Supply, fabrication, installation and testing of various roof appurtenances for
Single and Double Deck Pontoon Type for both External and internal
floating roof & Fixed Cone Roof Self supported.
xxii) Supply, fabrication & erection of Gauge hatch with still well, still wells for
level transmitters, level switch & temperature instruments etc and Gauge
socks.
xxiii) Supply, fabrication & erection of earth connection as per respective IS code.
Xxvi) Radiography / DP / Diesel chalk/ Vacuum box test/ any other test on various
components of tanks as per Specifications of this Tender document,
requirements of API standard & instructions from Engineer-in-Charge.
Additionally, all Horizontal and vertical Shell joints including extensions
above the Maximum Design Liquid Level shall be Dye Penetrant Tested after
Root Run and necessary repairs carried out as per HPCL’s instructions. All
radiography Films shall be reviewed by a HPCL approved Third Party
Inspection Agency.
xxvii) Calibration of tanks and getting approval from Weights & Measure
department using contractor’s own tape,tools ,tackles etc.
Page 5 of 27
xxviii) Carrying out hydrostatic / water fill up test in accordance to OISD 129/
Standard Specifications of this Tender & keeping the records for same,
pneumatic , vacuum & other test as specified in code/ specifications & as per
requirements of Engineer-in-Charge using contractor’s own equipment.
Fixed cone Roof leak proof test as per code/specifications.
xxix) Pontoon Leak proof test by air @ 20mm water column as directed by HPCL
& deck weld joints with Vaccum Box Methods. Floating Roof Joints like
joining of Pantoon & deck which can not be tested by Vaccum Box Method
shall undergo DP test for Root Run . Puncture Test or Satisfying design
condition by filling the quantity of water on deck / & pantoon shall be carried
out successfully to establish the design.
xxx) Accomplishment of any other item of work required to make the storage
tanks ready for commissioning and as per instruction of Engineer-in- Charge.
xxxii) Supply of all equipment, machineries, tools, tackles etc, labour and
supervision of all works at site.
xxxiii) Clean-up job at site for all surplus material, debris, scrap, construction
equipment etc as per direction of Engineer-in – charge.
xxxiii) Reconciliation of free issue steel / material and returning excess plates, off
cuts and scrap as per direction of Engineer-in – charge.
xxxiv) Supply of Power required for the job shall be the responsibility of the
Contractor & will be in his scope. HPCL will not give any connection from
their existing electrical system.
xxxv) Complying & meeting all the safety rules & regulations as per standards &
instructions of Engineer- in – Charge will be the sole responsibility of
contractor.
xxxvi) Supply of all required materials, supplying and providing /Double scaffolding
wherever required, Carrying out Grit blasting and surface preparation, primer
and finish painting.
xxxvii) Quoted rates for work to include deployment of Qualified Quality Control
Engineer/Safety Engineers at site right from starting date whose
responsibility is to prepare all the Quality control/Safety records as sought in
PO, relevant to work, relevant codes, and other requirements to ensure full
Page 6 of 27
compliance on quality/Safety during execution as guided by HPCL. The
suggested formats for QC re cords for Civil Foundation & Tankage work
attached with this section i.e scope of work.
xxxviii) The work will be performed as outlined in Standard Inspection Test Plan for
Tank Fabrication(ITP) in the tender document/ developed by contractor basis
this Tender document duly approved by HPCL. This ITP can undergo
revision at the sole discretion of HPCL Engineer- in – Charge to meet the on-
going practical scenario at site while execution and to improve the quality of
work. Job Methodology will be prepared by contractor for items as sought by
HPCL for proper execution & quality of Work.
xxxix) Material handling arrangement i.e MS Plate, Sand, Sand asphalt mix
movement etc at site has to be properly & effectively designed by contractor .
The same shall be got approved from HPCL prior to work commencement.
The rates quoted shall be inclusive of this. HPCL will not allow to change/
amend/break any other existing facilities construced/under construction.
xl) Supply of Gauge Hatch & Leg Support Sacks, Liquid mounted Mech Shoe
Seal as per attach specifications.
xli) Contractor will have to make all necessary arrangement for water requirement
for the entire job. After Hydro test & First Test water shall be disposed off by
Contractor in an un-objectionable manner to HPCL , Statutory Authorities like
PCB etc & it’s neighbors in unobjectionable manner at his cost & efforts. The
tank shall be washed with sweet water by contractor at no extra cost to HPCL
before commissioning.
SCOPE OF SUPPLY
2.1.1 Subject to the provisions mentioned elsewhere in the tender document, HPCL
will issue the following materials free of charge from Stores at Site for the Steel
plates IS2062 of regular width & Length required only for the following
components of the tanks:
- Bottom: Annular Ring & Sketch plates
- Shell
- Internal and External Floating Roof: Pontoon Bottom & Top, Deck plates,
Outer & Inner Rim , Doubler plates, Bulk Head & foam dam and
Page 7 of 27
appurtenances.
- RF Pads & bearing plates for floating roof pipe support, pontoon manhole
neck & cover plate.
-Top wind girder including extensions for stairways and plate stiffeners as
applicable.
-Secondary wind girder as per design requirements of the tank s including
plate gussets/ plate stiffeners.
-Tertiary wind girders as per design requirements of the tanks including plate
gussets/ plate stiffeners
A Tabulated statement showing the size wise plates issued and Total
consumption will be prepared as per HPCL instructions. Based on the Total
consumption in MT as a sum of individual sizewise consumption for a
particular site, generation of maximum 2.7% Returnable accountable scrap is
allowed. The Returnable Accountable scrap includes Offcuts and plates
smaller than 2400mm perimeter. Offcut plates shall be of minimum perimeter
2400 mm generated as per approved cutting Schedules. Plates smaller than
2400mm in perimeter are also classified under Returnable Accountable Scrap.
On an overall basis, the generation of accountable scrap shall be limited to
2.7% of total net consumption taken as a sum of net consumption for various
sizes. However, the Contractor shall make an all out effort at the time of
preparation of Drawings/ BOQ to limit the generation of Returnable
Accountable Scrap to a minimum preferably less than 2.7%.It will be the
responsibility of the Contractor to load, transport the accountable scrap, weigh
at weighbridge including payment of weighbridge charges, return to HPCL
Premises, Unloading and handing over to HPCL at their Storeyard/ scrap yard
as per instructions of HPCL Engineer-in-Charge. Apart from Accountable
Scrap, the Contractor shall be allowed a maximum of 0.30% of Burnout
Losses.
Page 8 of 27
schedule to control his scrap generation within above limits.
A) All steel plates required for the components other than those listed in
Cl.2.1.1.
C) All structural steel sections wherever required for curb angles, Top wind
girders Supports/stiffeners/ extensions for stairways, Top wind girder
bracings, Secondary wind girders, supports for Fire water Cooling Spray
Headers/ risers, supports for Foam system risers, spiral stairways, landings ,
platforms, handrails, bracing for foam dam, Inlet and Outlet Nozzle Troughs,
Gratings(which may be fabricated by the Contractor at a workshop/ factory
outside HPCL premises), stiffeners for Shell extension and supports for top
platform, trusses for Roof ,INSULATION STUBS & RING ANGLES ETC.
F) All seamless pipes for nozzle necks 200mm NB and below, internal pipes,
Nozzle necks for openings more than 200mm,Materials for Inlet/ Outlet
Nozzle troughs, floating roof supports, bleeder vents, emergency drain,
extension piping for roof drain, etc.
G) All pipe fittings, valves, flanges, matching flanges and blind covers
wherever specified for all nozzles, stainless steel wire mesh for emergency
drain, brass items and brazing for Auto bleeder vents/legs
H)Repeatable lay pattern Flexible Hose Pipe type primary roof drain after Third
Party Inspection with associated rigid piping sections, if any adequately
supported on Bottom/ from deck underside, necessary shoes/ guards, etc as per
Manufacturer’s instructions including brass non return valve, gate valve,
extension piping. The Flexible roof drain shall be manufactured by ( A) Coflexip
(Flexi France) / ( B) Well stream Holding Plc U.K / (C) NKT Flexible Denmark.
Page 9 of 27
I) Bolts, nuts and gaskets for roof & shell manholes, nozzles with blind cover/
matching flange, bolts & nuts for roof structure and other structural works.
J) Seals (Primary & Secondary) and weather protector, wherever applicable of
approved make, guide rollers, roof stoppers, earthing cable, shunts etc.
Seals shall be supplied after Third Party Inspection only.
M) Pipes, fittings, flanges and bolts and nuts and spray Nozzles and orifice
plates and structural supports for Piping for Fixed water Cooling spray
system.
N) Pipes, fittings, flanges, orifice plates, Foam makers/ Pourers and deflectors
on point of spray on shell and structural supports for Piping for Foam system
T) Any Blind flanges, valves, nipples, plugs, bolts, nuts, gaskets, etc required for
conducting hydrostatic testing and any other test required by HPCL.
U) All primer materials and painting materials, scaffolding, Ferrous Grit and
related equipment for Painting.
Note:
While every effort has been made to list all the supply items, it
shall be the sole responsibility of the Contractor to review the list and
seek clarifications, if any at the time of Unpriced Bid itself. HPCL
undertakes to provide only Free Issue Steel plates for Fabrication and all
the other items shall be supplied by the Contractor only. No claims/
disputes by the Bidder/ Contractor shall be entertained by HPCL at a later
date.
Page 10 of 27
following sequence:
1. Drawing Index
4. Shell plate layout showing location of nozzles & their distances from weld
seams.
8. Plate layout of Pontoon top & Bottom, Roof Deck, inner &outer rim , bulk
heads for floating roof, floating roof support details, details of appurtenances
on floating roof , detail along with design calculation.
12. Details of tank internals like still wells, roof stoppers etc.
13. Details of Foam & Cooling System along with supporting calculations.
14. Details of Roof Drains (Primary & Emergency) along with design
calculations.
15. Plate cutting diagram for Free Issue Plates along with indicating anticipated
the oritical scrap i.e. Burn oil losses & Accountable losses.
Page 11 of 27
19. Final Inspection certificate and Hydrostatic test report.
Page 12 of 27
!
" # $ %
&'
( '!
& ) $ ( '! $
* )
Page 13 of 27
++ , * -
./ 5!6 % -+ 7 * 6 6 5 84 .9
.0 5!6 % -+ 7 * 6 6 5 84 .9
.1 5-, '6 + *6 6 5 /9 .9
.2 5-, '6 + *6 6 5 /9 .9
.3 6 + *6 6 5 84 ..
.4 6 + *6 6 5 84 ..
Page 14 of 27
+6%
$ : >$ $
/ 5 ;
0 % * :$ ( '! '
- '
1 ? 6 *@ ( !! A 6+ 6 + !B * %( ( '! *6 #
* ? -+ 7 $ -7 +
2 : $ 89
: > ( '!
3 " =
C :
Page 15 of 27
D $
> ; C !-@ ( ! % ; 7 !6 # ; 5 %B
(6 ; @ 56 * * 6+ 6 -+ 7 ' ! 7 A! % -+ 7
.9 5 : ! "#$ % & :
* C
? @ !B * 6 7 * * 6 *% #- E # - A *'( *% + ? @ !B
*6 7 * + ? @ !B 6
6 + % ( !B * 6 7 * + 6 + % ( !B * 6 7 * * 6 *% #-
E # - A * '( *%
6 -+ % + 6 : -!
.. : .99 *
C F G
: ( '! : > 6
'( 5 /H
D3H :
') *
. I C =
> "
8 I C =
> "
Page 16 of 27
SPECIFICATIONS
FOR
MATERIALS
IN
CONTRACTOR’S SCOPE
OF
SUPPLY
Page 17 of 27
SPECIFICATIONS FOR MATERIALS IN CONTRACTOR’S SCOPE OF
SUPPLY
1.0 SCOPE:
2.0 VENDORS:
In cases where ISI / API/ASTM mark may not be available on the materials,
Contractor shall obtain HPCL approval for the subject vendor on a case-to-case
basis. For rolled structural sections, materials must be sourced from SAIL,
RINL, VIZAG Steel or TISCO. LSAW/ Seamless pipes must be sourced from
Surya Roshni, SAWPIPES, Welspun, Maharashtra Seamless, Jindal, SAIL,
Indian seamless or Man Industries or any other reputed foreign vendor
approved by HPCL.
3.0 TESTING:
Page 18 of 27
4.0 LIST OF ITEMS IN CONTRACTOR’S SCOPE OF SUPPLY WITH
SPECIFICATIONS:
SL.NO. ITEM DESCRIPTION MATERIAL SPECIFICATIONS
1 COMBINED Pipes
STILL WELL 406.4 MM/ 12.7 API 5L GR. A, B OR X 42
MM WT/123.3 (LSAW)
KG/M
&
TEMP. ELEMENT 88.9 MM/7.6 SEAMLESS ASTM A-106
MMWT/15.24 GR.B
KG/M
&
LEVEL 300 MM/SCH.40 SEAMLESS ASTM A 106
TRANSMITTER GR.B
2 PLATE PLATES IS: 2062 GR. A OR B
FABRICATION
3 STRUCTURALS SECTIONS IS: 2062 GR.A
incldg. GRATINGS
4 NOZZLE NECKS 300 NB AND SEAMLESS ASTM A-106
BELOW- GR.B
XS SCHEDULE
5 NOZZLE NECKS ABOVE 300MM IS: 2062 GR.A
NB 14MM THK
Page 19 of 27
12 GASKETS(CAF) SHEET CHAMPION OIL & WATER
SW:ASTM A 105
CAPS BW: ASTM A 234 GR. WPB
4.0 For items not listed above such as bushes, split pins, neoprene bushes, etc, for
which Manufacturer Test certificates may not be available, HPCL may approve
for incorporation in works based on visual inspection.
5.0 Shoe seal /SS leg pins to be included
Page 20 of 27
ANNEXURES
Page 21 of 27
Page 22 of 27
Page 23 of 27
Page 24 of 27
Page 25 of 27
Page 26 of 27
Page 27 of 27
TECHNICALSPECIFICATIONS
FOR
Page 1 of 32
CONTENTS
1.0 SCOPE
2.0 REFERENCE
6.0 APPURTENANCES
8.0 CALIBRATION
9.0 PAINTING
10.0 TOLERANCES
12.0 GUARANTEE
Page 2 of 32
STANDARD SPECIFICATIONS FOR FABRICATION,
ERECTION AND TESTING OF ABOVE GROUND STORAGE
FLOATING ROOF TANKS
1.0 SCOPE
2.0 REFERENCE
Page 3 of 32
IS : 875 (Part 3) : Code of practice for design loads,
wind loads(other than earthquake)
For building and structures.
Page 4 of 32
2.2 Materials Codes
2.3 Regulations
3.3 Plate material used for ring flanges shall have a minimum
UTS of 4200 Kg./cm2 . For Flange thickness over 38 mm,
plate material shall be boiler quality, fine-grained, killed, and
normalised and impact tested as per the requirements of
API Standard 650.
3.5 Gaskets for manholes fitted with blind flanges shall conform
to IS: 2712. 3.0 mm thickness. All the nozzles shall be fitted
with spiral wound gasket with CS outer ring & SS inner ring
(API 601) up to24” dia.
3.6 Bolts and nuts for all nozzles fitted with blind flanges shall
conform to IS: 1367, ASTM A-307 Gr. B, A-193 Gr. B-7, or
Page 5 of 32
A-194 Gr. 2H. Bolts and nuts for all structures shall conform
to IS: 1363.
Page 6 of 32
accordance to API 650 with product density 0.86 for shell,
Bottom & FR and fabrication drawings based on the
drawings/ written instructions issued on award of
contract/purchase order and shall include the following:
Page 7 of 32
10. Details of rolling ladder and track and Earthing
connections with Bill of Material for floating roof tanks.
16. Details of primary roof drain and Drain sump for F.R.
tanks including Bill of Material.
Page 8 of 32
22. Details of Roof opening for Automation level/
temperature gauge.
5.1 Plates
Page 9 of 32
the concave side with numbers as shown on erection
drawings.
5.3 Bottom
Page 10 of 32
drain Nozzle/ shell.
h] Annular plates shall be assembled by butt welding with
backing strips and the sketch plates shall be lap welded
to the Annular plates.
i] Three plates lap joints shall be suitably joggled to a
length of 150 mm minimum to facilitate welding.
Joggling shall be to the satisfaction of Engineer-in-
Charge.
Page 11 of 32
5.4 Shell
Page 12 of 32
hang of 25mm from the top of the shell. The thickness of
curb angle shall in no case shall be less than 8mm.
Page 13 of 32
l) The shell to bottom joints are performed as fillet welds
for the annular plate thickness less than 12mm. The
bottom edge preparation for the first shell plate more than
12mm thick annular plate shall be a Double”V” as per
clause no: 5.1.5.7/fig: 5-3.c of API 650 11th edition
5.5.1 Overview
Page 14 of 32
pontoon type construction with or with out buoys.
Page 15 of 32
- The submergence of outer rim when 254
mm rain water is accumulated on the roof with
primary Roof Drain inoperative.
Page 16 of 32
- The submergence of inner and outer rim
near the punctured compartments when deck
and two adjacent pontoon compartments are
punctured with No water or live load.
Page 17 of 32
5.5.5 Floating Roof Supports
a) Support shall be adjustable to two position
Page 18 of 32
5.5.6 Rolling ladder and track shall be provided as per HPCL
Standard Drawings enclosed in this Document.
Page 19 of 32
Sch. 40.
5.5.8 Vents
Page 20 of 32
6.0 APPURTENANCES
Page 21 of 32
Shell settlement measurement shall be made after tank
erection, prior to hydro testing and during water filling.
Page 22 of 32
d) All the inspection shall be carried out in
accordance with the relevant codes and
requirements of drawings and specifications.
Page 23 of 32
under the supervision of third party.
d) The Welder performance qualification record
(WPQR) QW-484 ASME Section-IX: WPQR will
be performed under the supervision of HPCL
approved third party and approval vetting will be
granted by TPI for successful welders I
prescribed format recommended by ASME
Section-IX. During this process TPI will also vet
the various accessories like Welding rectifier,
regulator, holder; cable etc and the record will be
maintained for the same. The records shall be
used as benchmarking for QC.
c) No welding shall be undertaken without approval
of the welding procedure and welder qualification
test by the Engineer-in-charge.
Note: as a sample WPS/WPQR/PQR used at other HPCL
sites are attached.
Page 24 of 32
d) Radiographs shall be taken as soon as welding of
the Joint is completed. If repairs are required,
these shall be carried out before starting other
welds. New radiography examination of such
repairs shall also be carried out by the Contractor
at his own cost. The no. and location of
radiograph along with welder identification shall
be properly maintained by the contractor as per
figure 8.1 of API 650 of Clause 8.1 ,11th edition.
d) Radiograph film length shall be 250 mm min.
except if the weld is less than 250 mm long. In
such cases, film length shall be full length of weld.
f) Radiographic film shall be of approved quality
KODAK/approved make by HPCL/TPI.
g) Welds examined by radiography shall be judged
acceptable or unacceptable by standards of
paragraph UW-51(b) in section VIII of the ASME
code (attached)
h) The radiography films and reports shall be
reviewed and approved by a HPCL approved
Third Party Agency. The quoted rates are
deemed to include same. The evaluator (TPI
person) shall have a Level-II/III of certification of
ASNT-SNT-TC-IA. The film shall have a proper
identification marks vide point no:d above along
with TPI certification.
7.1.4 Liquid penetrant examination:
Wherever specified in drawing/code, liquid penetrant
examination shall be carried out as per specifications and
codes. Additionally, all Horizontal and vertical Shell joints
including extensions above the Maximum Design Liquid
Page 25 of 32
Level shall be Dye Penetrant Tested after Root Run and
necessary repairs carried out.
It is to be noted that the entire weld joints which are non
accessible to any type of regular tests like vacuum box,
Hydro test, Pneumatic test shall undergo DP test for root
run mandatorily.
The bottom to shell joint root run shall undergo Kerosene-
chalk test prior to DP test from both inside to outside and
vice versa mandatorily.
7.2 Testing
All equipment required for testing shall be supplied by the
contractor.
Opening other than those used for hydrostatic test or any
other test shall be closed by plugs and blind flanges
supplied by the contractors.
Page 26 of 32
c) The weld joints under the shell periphery shall be
Vacuum box tested (i.e. annular butt joint) as
above(7.2.b) before erection and welding of first
shell course.
Page 27 of 32
purpose shall be carefully removed from inside
and outside surface of the tank to the satisfaction
of the Engineer-in-Charge.
Page 28 of 32
Filling shall be in 4 stages- 25%, 50%, 75%
and 100%. After each stage a load stabilization
period shall be observed:
- 24 hrs between each stage for tanks with a
capacity equal or more than 10,000 cu.m.
- 12 hrs between each stage for tanks with a
capacity under 10,000 cu.m.
Filling rate shall not exceed 5 metres per day.
g) When the tank is full all the weld joints shall be
hammered by the Contractor in the presence of
Engineer-in-Charge. In case of any defect it shall
be repaired and retested by the Contractor as per
instructions of Engineer-in-charge.
h) Tank shall be emptied at a maximum water level
variation rate of 5 metres per day or as per
instructions of Engineer-in-Charge.
i) All weld repairs shall be done with water level
minimum 300 mm below the joint being repaired.
Page 29 of 32
on the deck and in the stabilized state
submergence of outer rim shall not exceed 65%
of its height at any point.
ii) For annular pontoon type external as well as
internal floating roofs the condition of deck and
two adjacent pontoon compartments punctured
shall be simulated and the submergence of inner
rim and outer rim at the punctured pontoon shall
be compared with the calculated value.
iii) Failing to meet the above requirements contractor
shall rectify the floating roof and test at his cost till
the above requirements are satisfied.
Page 30 of 32
8.0 CALIBRATION
9.0 PAINTING
10.0 TOLERANCE
10.1 Shell
For tanks to have acceptable appearance and to permit
proper functioning of floating roof, they shall have
tolerances strictly as specified in applicable codes/tender
document whichever is stringent.
10.2 Floating Roof Tolerance
Tolerance allowed on the annular clearance between shell
and floating Roof shall be compatible with the requirement
specified by seal manufacturer. This shall be maximum 50
mm radially.
Page 31 of 32
11.2 Packing and Transportation
a. All plates shall be transported in tractor or trailer and shall
not be dragged.
b. All rolled shell plates shall be packed properly to retain the
shape and shall be handled carefully to avoid damage
during transit.
c. Contractor shall be responsible for transportation of material
fabricated in his workshop or worksite.
12.0 GUARANTEE
Guarantee, if not covered by the General Conditions of
contract, shall be as following:
12.1 The entire Work shall be guaranteed in accordance with
conditions given in the “General terms and Conditions of
Contract” and “Special Conditions of Contract”.
12.2 Any part of tank found detective within 12 months from the
date of Completion of work as per Completion Certificate
and not having been subjected to faulty operations or
incorrect service conditions shall be promptly
replaced/repaired and reassembled by the contractor at his
own cost, failing which owner has the right to get the same
replaced/repaired by others and charge the cost incurred
to the contractor.
Page 32 of 32
TECHNICAL SPECIFICATIONS
FOR
SELF SUPPORTED
Page 1 of 22
CONTENTS
1.0 SCOPE
2.0 REFERENCE
6.0 APPURTENANCES
8.0 CALIBRATION
9.0 PAINTING
10.0 TOLERANCES
12.0 GUARANTEE
Page 2 of 22
STANDARD SPECIFICATIONS FOR FABRICATION,
ERECTION AND TESTING OF ABOVE GROUND STORAGE
SELF SUPPORTING CONE ROOF TANKS WITH CONE
DOWN BOTTOM & SUMP
1.0 SCOPE
1.4 The tanks shall be designed as per API 650 strictly. The
design calculation in the scope of contract includes
Bottom Plate(Annular/Sketch), Shell, Wind girders if any,
Top Kerb Angle, Roof Plates, Self Supporting
Trusses(Main Beam) and Rafters ,Check for overturning of
tank under wind load, seismic design etc for HPCL’s
approval prior to drawing preparation .
Page 3 of 22
2.0 REFERENCE
Page 4 of 22
OISD-118 : Layouts for Oil & Gas installations.
2.3 Regulations
3.3 Plate material used for ring flanges shall have a minimum
UTS of 4200 Kg./cm2 . For Flange thickness over 38 mm,
plate material shall be boiler quality, fine-grained, killed,
normalised and impact tested as per the requirements of
API Standard 650.
Page 5 of 22
3.6 Bolts and nuts for all nozzles fitted with blind flanges shall
conform to IS: 1367, ASTM A-307 Gr. B, A-193 Gr. B-7, or
A-194 Gr. 2H. Bolts and nuts for all structurals shall
conform to IS: 1363.
Page 6 of 22
4.2 Contractor shall prepare all design calculations and
fabrication drawings based on the drawings issued on
award of contract/purchase order and shall include the
following:
Page 7 of 22
8. Details of spiral stairway and extension stairway to
Top platform, landings and handrails with bill of
materials.
Page 8 of 22
20. Details of all datum plates.
5.1 Plates
Page 9 of 22
b] A pre-assembly of a sufficient part of roof structure
may be called for by the Engineer-in-Charge to assess
the correct workmanship.
5.3 Bottom
a] Bottom slope shall be as indicated in the respective
tank drawings. The Bottom shall be Cone Down type with
a central sump of approx. 200 litres capacity.
Page 10 of 22
h] Bearing plates & Datum plates shall be fabricated as
per standard drawings and positioned as per AFC
Drawings.
5.4 Shell
Page 11 of 22
welds or reinforcement pad welds as per code and
applicable appendices.
Page 12 of 22
5.6 Vents
6.0 APPURTENANCES
Page 13 of 22
relieved prior to installation, wherever required
as per code and applicable appendices.
Page 14 of 22
b) HPCL’S representatives shall have free access
to the entire contractor’s shops as well as to
worksite.
7.1.2Welding Procedure
a) Welding procedure qualification shall be carried
out as per Exhibits enclosed in tender and as
per details in Scope of Work.
Page 15 of 22
b) All long seams of fabricated nozzles shall be
fully radiographed.
Page 16 of 22
Openings other than those used for hydrostatic test or any
other test shall be closed by plugs and blind flanges
supplied by the contractors.
7.2.2Shell Test
a) Bottom to shell joints shall be tested as follows:
Page 17 of 22
ii) Examination for inner fillet to detect cracks shall
be performed using either the liquid penetrant
method or Magnetic particle method.
Page 19 of 22
above, design check for vacuum shall be
made before proceeding with the test.
7.2.4Nozzle Reinforcing Plates
a) Nozzle reinforcing plates shall be pneumatically tested
at 1.05 kg/cm2g with soap solution. This test shall be
carried out before filling the tank for hydrostatic testing. All
the weld joints in roof shall be checked with soap suds for
detection of leaks.
b) Observations will be made for leakages during
Hydrostatic testing.
8.0 CALIBRATION
Strapping and Calibration of all tanks shall be done in
accordance with IS:2007 & 2008 (Latest editions).
9.0 PAINTING
For details of primer and painting, Painting specification
shall be referred to.
10.0 TOLERANCE
10.1 Shell
For tanks to have acceptable appearance and to permit
proper functioning, they shall have tolerances strictly as
specified in applicable codes.
Page 20 of 22
11.0 IDENTIFICATION, PACKING AND TRANSPORTATION
11.1 Identification
Each plate and structural member shall be clearly marked
with the specification number, drawing number and
assembly number.
12.0 GUARANTEE
Guarantee, if not covered by the General Conditions of
contract, shall be as following:
12.1 The entire Work shall be guaranteed in accordance with
conditions given in the “ General terms and Conditions
of Contract” and “Special Conditions of Contract”.
12.2 Any part of tank found detective within 12 months from the
date of Completion of work as per Completion Certificate
and not having been subjected to faulty operations or
incorrect service conditions shall be promptly
replaced/repaired and reassembled by the contractor at
his own cost, failing which owner has the right to get the
same replaced/repaired by others and charge the cost
incurred to the contractor.
Page 21 of 22
13. STRUCTURAL STEEL
Page 22 of 22
STANDARD
SPECIFICATION
FOR SHOP
AND
FIELD PAINTING
Page 1 of 10
STANDARD SPECIFICATION FOR SHOP AND FIELD PAINTING
1.0 GENERAL
1.1 These technical specifications shall be applicable for the work covered by the
Contract. It is understood that Contractor shall complete the work in all respects
with best quality materials and workmanship, best engineering practice,
Manufacturer recommendations, ITP and instructions of HPCL.
1.2 All the items covered in this specification are required to be supplied by the
Contractor only.
2.0 SCOPE
Scope of work covered in this specification shall include but not limited to the
following:
1. Surface preparation for all components of A/G product storage tanks covered in
this Contract.
Page 2 of 10
4.0 EQUIPMENT
All tools, brushes, rollers, spray guns, abrasive materials, sand, hand/ power tools
for cleaning, scaffolding materials, air compressors, instrument for measuring
humidity, profilemeter etc required for the works shall be supplied by the
Contractor.
5.1 GENERAL
5.1.1 In order to achieve the maximum durability, copper slag cleaning shall be
followed.
5.1.2 Mill scale, rust, rust scale, etc. shall be fully removed by copper slag blast cleaning
to SA 2 ½ or equivalent as per
SWEDISH STANDARD: IS-05-5900-1967/ISO-8501-1-1988.
5.1.3 Copper slag Blast cleaning shall not be performed where dust can contaminate
surfaces undergoing such cleaning or in conditions where the humidity exceeds
85%.
5.1.4 The first coat of primer must be applied on dry surface immediately and in any
case within 4 hrs of cleaning of surface.
5.1.5 Blasting and painting shall in general be avoided during unfavorable weather
conditions.
1. The surface shall be cleaned of all dust and heavier layers of rust by copper slag
blasting the entire internal surface to photographic standard SIS: 055900-1967.
2. The consumption rate of copper slag is 1.6 Kg/Sqm of the blasted area. This has
to be ensured strictly.
3. All tools, equipments, base material, hand and power tools for cleaning, including
scaffolding material, copper slag blasting equipment, air compressor etc. shall be
arranged by the contractor at site in sufficient quantity.
Page 3 of 10
at a pressure of 7 kg/sq.cm.
5. The abrasive used shall be of the physical properties as mentioned below and
shall be free from oil, loan and mud etc.
6. The blast cleaned surface shall be blasted with dry compressed air before
applying primer. This should be done even if the surface appears very clean and
white in colour. The white colour may be due to deposition of silicon and reflection of
light on the surface.
7. Proper earthing and bonding arrangements shall be made to prevent any damage
by sparks produced by static electricity. Bonding shall be done between tank and
blast nozzles and hopper and air compressor also. The bonding conductor should
not be less than 16 SWG single strand copper cable.
8. The time gap between blast cleaning and application of primer shall not be more
than THREE hours. Blast cleaning work shall, commence from top to bottom.
9. The blast cleaning operation shall be carried out keeping the nozzle at an angle of
30 degree to the vertical in order to prevent rebounding abrasive from showing down
the abrasives emerging from nozzle and from under cutting the material to be
removed.
A blast cleaning, the percentage of bare metal obtained shall be between 95% to 100%
of each of sq.cm. of the blasted area corresponding to photographic visual standards
of SA 2 ½ of the Swedish standard referred above.
10. Arrangements for inspection of various stages of the job shall be made available
by the Contractor so that the entire copper slag blasted area is available for
inspection. Any defective work noticed shall be immediately rectified and even
reblasting shall be done if necessary.
Colour : Black.
Grain shape : Granulated, Angular multifaceted.
Hardness : 5 to 7 Moh’s scale.
Sp. Gravity : 3.2 to 3.7
Bulk Density : 1.87 Kg/ltr.
Moisture Content : less than 1 %
Page 4 of 10
-2.36 to + 1 40 to 55
-1 to + 0.5 15 to 30
-0.5 to + 0.212 6 to 12
-0.212 below 0.2 to 1.0
5.3.1 Copper Slag blasted surface upon inspection and clearance by HPCL shall be
coated with one complete application of primer as soon as practicable and in no
case later than 4 hrs on the same day. Applied paint shall have the required Dry
Film Thickness (DFT) after drying which shall be measured and recorded by the
contractor and should be submitted to HPCL.
5.3.2 Each coat shall be in a proper state of cure or dryness before the application of
succeeding coat. Manufacturer’s instructions shall be followed for intercoat
interval.
5.3.3 The type of application may be Airspray or Airless spray or Brush application as
per manufacturer recommendation and HPCL instructions for getting satisfactory
results.
5.3.4 For each coat, the painter should know the WFT corresponding to the specified
DFT and standardize the paint application technique accordingly. This has to be
ensured in a qualification trial by Contractor.
5.4 SCAFFOLDING
Double pipe scaffolding shall be used and all the painters shall be provided with
Safety belts for ensuring accident free working.
5.5 DOCUMENTATION
1. A written quality Plan with procedure for qualification trials and for actual work.
2. Daily progress Report with details of humidity, surface preparation, surface profile,
Dry film thickness particulars of applications, number of coats applied, type of
materials used, methodology-Air or Airless or Brush, progress of work vs
programme.
Page 5 of 10
4. Type of testing equipments and their calibration.
5. Elcometer and Profilemeter readings for the various components jointly recorded
with HPCL.
8.1 All painting materials including primers and thinners brought to site by the
Contractor for application shall be directly procured from Approved manufacturers
as per specifications and shall be accompanied by Manufacturer Test Certificates.
8.2 HPCL may call for tests for the primers and paints including verification of
batchwise tests for physical and chemical analysis. The Contractor shall carry out
the same at his own cost and provide the results to HPCL.
8.3 The painting work shall be subjected to inspection by HPCL at all times. Stages of
inspection are as follows:
1) Surface preparation
2) Primer application
3) Each coat of paint
All records of inspection shall be maintained in Registers and jointly signed by
HPCL and Contractor.
Page 6 of 10
Any defect noticed during the various stages of inspection shall be rectified by the
Contractor to the satisfaction of HPCL before proceeding further. Irrespective of
the inspection, repair and approval at intermediate stages of work, Contractor
shall be fully responsible for making good any defects found during Final
inspection or during the Defect Liability period. DFT shall be checked and
wherever shot same shall be made up with additional coats.
8.4 The shades of successive coats should be slightly different in colour in order to
ensure application of individual coats in consultation with manufacturer.
8.5 Calibrated Digital Elcometers, surface profile gauges (calibrated Profilemeter) and
any other inspection instrument required by HPCL shall be provided by the
contractor at site.
8.6 The contractor shall arrange expert technical support at site by paint Manufacturer
who will cross verify independently regarding surface preparation and DFT and
quality and provide a report to HPCL.
PRIMERS
P-6 : EPOXY ZINC PHOSPHATE PRIMER
Page 7 of 10
1 FIRE SA 2 1/2 1 COAT OF F-9 @ 65- 1 COAT OF F- P-6 AS
WATER 75 MICRONS DFT/ 6 @ 100 STRIPE
COAT + MICRONS COAT
1 COAT OF P-6 @ 40 DFT/COAT+ 1 (RED
MICRONS DFT/ COAT OF F-2 SHADE);
COAT @ 40 F-6
(65+40=105) MICRONS (GREY)
DFT/COAT AND F-2
(100+40 (FIRE
=140) RED;
IS:536)
2 FOAM SA 2 1/2 1 COAT OF F-9 @ 65- 1 COAT OF F- P-6 AS
75 MICRONS DFT/ 6 @ 100 STRIPE
COAT + MICRONS COAT
1 COAT OF P-6 @ 40 DFT/COAT+ 1 (RED
MICRONS DFT/ COAT OF F-2 SHADE);
COAT @ 40 F-6
(65+40=105) MICRONS (GREY)
DFT/COAT AND F-2
(100+40 (GOLDEN
=140) YELLOW;
IS:356)
ALL WELD JOINTS SHALL BE BUFFED AND COATED WITH STRIPE COAT OF
EPOXY ZINC PHOSPHATE PRIMER PRIOR TO TAKING UP F-6
Page 8 of 10
DFT/ COAT cured) @ 80 Total=225
MICRONS microns
DFT/COAT
(80x2=160)
ALL WELD JOINTS SHALL BE BUFFED AND COATED WITH STRIPE COAT OF
EPOXY ZINC PHOSPHATE PRIMER PRIOR TO TAKING UP F-6.
4 All still well pipes SA 2 1/2 1 COAT OF F-9 1 COAT OF F-6(AMIDE F-6(Grey)
above max. liquid @ 65-75 CURED)@ 100
MICRONS DFT/ MICRONS DFT/COAT
Total=285microns)
level
COAT + 1 COAT + 2 COATS OF F-2 @
OF P-6(RED) @ 40MICRONS
40 MICRONS DFT/COAT
DFT/COAT (100+2 X40=180)
(65+40=105)
ALL WELD JOINTS SHALL BE BUFFED AND COATED WITH STRIPE COAT OF EPOXY ZINC
PHOSPHATE PRIMER PRIOR TO TAKING UP F-6.
Page 9 of 10
PAINTING FOR FIXED CONE ROOF OF INTERNAL FLOATING ROOF TANKS:
EXTERNAL
ALL WELD JOINTS SHALL BE BUFFED AND COATED WITH STRIPE COAT OF EPOXY ZINC
PHOSPHATE PRIMER PRIOR TO TAKING UP F-6.
Page 10 of 10
Page 1 of 7
! " #" " " " $ " " "
% "" ! # "
! "#" " # "
! & ' " "
"#" "
( )
% * % " +
" " ,!" " " -# "" " %
! "$" "
"#" - " % " " ! " #
%
.* ." " +
"#" " ,!" " "$ % "#" "
* #" / ! "
0* 0! # " " % +
1 " "$ "$ # " # " " -
" #" "" ,!" 0! # " "#" "
" ! ! "2" " 2 " " $2 #" ,! "
! " 3 2
Page 2 of 7
4444444444444444444444444444444444444444444444444444444444444444444444
! " " . %
"$ " "#
5 ! " "$ " "# . %
( "$1 "
6 7 / 0! .
6 / ! 2" ! "$ 2 "$ . %
@ 5. :! "" " . .
5 "" " 3 # . %
5 "" " 3 # "" .
Page 3 of 7
?
8 ! 2 # " ! . 0
< 0 ,! "$ # . 0-
A ? "$ . 0
C 6 "$ . 0
D F" ! "$ . .
G ) - ) 7 %H ! !
! = " 5 . %
F !! ' ! "$ . 0
F !! ' "$ . %
( " $2 ! # ! 2 "$ . .
Page 4 of 7
! "$ " " !
9 " 6! - "$ . .
.% 2 9 2 EE 2
= " 5 . .
< ) EE
= " 5 . .
@ 9 ! " . %
A 0 " 6! . %
A 0 7 -0 " $ #" ! . .
D "$
5 "$ " " . %
5 "$ . %
$" $2 "$ # .
Page 5 of 7
8 ! 2 # 2 " 6! "$ .
@ ?! - " " . 0
A F !! "$ 6 . %
C " # ! . 0
D "$ " # ! . 0
G 9 "'" $ "$ ?! . .
"" 6 " . .
0! 9"'" $ !$ # . 0
( 0 "$ ! # " $. 0
8 " ?! - . %
< "$ . 0
A 0 . %
C " . %
D 0 "'" $ . %
Page 6 of 7
( 1 " - " . %
8 "$ 3 . .
< 0 "$ !$ ) ! # . %
@ % . %
A " ! . %
C F !! . %
#" " ! .
Page 7 of 7
Page 1 of 15
! " # $% & % ' !%
! (!% ) !! % *
!
" # $
Page 2 of 15
+ +
Page 3 of 15
+ + +
%
# & "& ' &
& # # " # !
" # # $
# ( " # $% & %
% # !% ! (!% ) !! % *
"" ' $ ' #
) * +,* +, *+ *
) * -. , *
• - * ( / 0+ 1 - ,
• - - , +, 2+0 - 2 * 34 + &- + , 4
5 4 * - - ,
8 6 9 +,* - - : 2- ,
8 . , +0
! $ " # $ ""
# "' ' " "" ! #;
Page 4 of 15
" # & $ & " & # &
" & " # & " & " &' "
"" " $ # "
! #
• # #
8% * + 6 -, . +,* * 2 ,
! # #
! $ # " ! # # "
'" $ " !
! " "" ' ! #
" ' 7 0 " ' " ! # " #!
" " & # # ! # 7 0 ! "
! ' ' 7 0 "
* " # " " ! # " "" "
# "" ' ' ' '" 7 0 !
"" # & " " & ! # '
' ' "
! # " "
! # "" ' ' ! "" ' !
' 7 0 * # !& 7 0 ##
# ""
"" ' ' !
7 0
B * -. , + , * , 2 - ,
B 0-, . 6 + 4
Page 5 of 15
B " #! # $ "" "
"" " # #
"! $ "" - *( /
'" # ! # $
$ "" #
B 5 * "
B 8 * -. , + + 0-, . 6 + 4
% ( ! !, - (!$ ! ) &! ! ! % * % *
% * (!% ) ! $%
& !! % * )
$ ! % % #( 3 "! ! # @ #
, ! ) D
# #
! #
% #( 5 $ - @ #
/ D "
" # ! #
Page 6 of 15
! # ! #
# "" ' "
' "!
! #
% $ ! ) #( 3 "! ! # @ #
) , ! %8D
# #
! #
% #( 5 $ - @ #
%8D "
" # ! #
! # ! #
# "" ' "
' "!
! #
) #( + ( # @ #
8 D $ -
" " # ! #
! ! #
# & #
"" ' " ' "!
!
#
B B "
Page 7 of 15
B / & " # # "" '
'" #
#
B C -, . + , * - - , -, .
B% + 4
B% "" $ $ ""
$ "" ' ! "
"" ' ! " "" "
$ "" ' " ""
" $ "" '" " " "" '
$ "" " # " " #
$ ""
/ - ,
' # "" ' "
! # " ! #
Page 8 of 15
C -, . + , * - - , -, .
E + -, -, .
+ " # "" #& "" '
! # #
& " # # "" '
'" # # #
#
Page 9 of 15
Page 10 of 15
!
""
# $ %
. ' ,
5) $ 67,
$8 )
(* "" & ( !
.
!
1* %
* "" +
) ""
0 0
40
& 40
&0
&0 40
&0
0
'* 9 ""
!
! 0 % : 2 % :
Page 11 of 15
* "" 3 !
#* , "" , +00-
5* 8 . () ,1 2
;* ) "" <
""
,
* ) ""
=
* > "" ! -
% : 2% :
?* 9
"" ,
@* ( "" %
- 8( $,
(@ # ) $7 ,)
! "" +
1 ! + ! 3,
, ,+ . /
' + 1 ,+ -
0 "" ! %
' ,5) $ 67,
$8 )
Page 12 of 15
+ +
Page 13 of 15
+ +
" ! # " # #
"& # ' & # $
" # $
% 2 04
% * # & ' & " $ & ""
" & &' # ""
! $& ! # " # ! ' " &
! # $ # $ $ "" '
" '
) * -. ,
) " # # - ; 5 E CE
! <)(BD ! > "" ' "
$ ' "" # $ + #
" "" ' $
# # "!
5 + -+ 0 + , * , 2 - ,
5 $ ' & " "" - ; %)E
# 6 " " ' "
Page 14 of 15
58 + "" " &' & & $ #
" '" "" - ;5)
8 -, .
+ "" & " "" ' " "" "
C $# ? " '" "" ' #
# " # "" ' '
+ "" # " "" '
' 7 0
B 6 9 + , 7 - & -, - 7 + , * + -, -, .
+ "" '" "" ' ! # ! $ + ""
' # "" ' ""
+ "" "" ' ! %
'" ?
'" #
/ + 9 -, .
$ "" ' " " " $ ! "" ! #;
• F $
• 4
• F
• "
• + ?- -
Page 15 of 15
STANDARD
INSPECTION
TEST PLAN
FOR
PIPELINE JOBS
Page 1 of 4
1.0 GENERAL
The enclosed ITPs shall be followed for the works to be performed by the Contractor
under this Tender. The provisions indicated for stagewise inspection by HPCL are a
minimum and the contractor shall develop a detailed ITP and obtain approval for the
same prior to commencement of work. Contractor to carry out 100% examination of all
activities.
2.0 LEGEND
W: Witness Point;
An activity which requires witnessing by HPCL when the activity is performed.
______________________________________________________________________
Page 2 of 4
S.NO. ACTIVITY CONTRACTOR HPCL
________________________________________________________________________
A. PRIOR TO FABRICATION
3. Incoming Material
- Owner’s Supply WC Rw
- Contractor’s supply, including check testing WC HP
Note : Party to establish WPS/PQR within 15 days from the date of LOI
4. Sequence of welding WC S
5. Baking of electrodes WC S
6. Inter-pass cleaning WC S
Page 3 of 4
8. DPT/RADIOGRAPHY of the joints WC HP
9. Erection of valves WC W
11. Hydrotesting WC HP
Page 4 of 4
TECHNICAL
SPECIFICATIONS
FOR
CONCRETE AND
REINFORCEMENT
WORKS
Page 1 of 15
1. CONCRETE AND STEEL REINFORCEMENT
1.1 GENERAL:
This section describes and specifies work required for plain and reinforced cement
concrete including reinforcement and form work. Unless otherwise specified or agreed
in writing by the EIC, all materials and methods used in the production, testing and
handling of concrete shall comply with the latest editions or amendments of the relevant
Indian Standards.
1.2 MATERIALS:
All materials shall be obtained from sources approved by the EIC. The agreed source or
quality of any material shall not be changed during the course of the contract except
with the approval of the EIC.
Whenever requested by the EIC, the Contractor shall provide a certificate from the
manufacturer, for each and every delivery of material, showing the source, quantity
delivered and confirming that the material has been tested and conforms to the required
Indian Standard.
1.4 CEMENT :
The cement used throughout the work shall be to the approval of the EIC. A certificate
shall be obtained from the manufacturers and produced to EIC for each delivery of
cement and it shall comply with the requirements of as mentioned in the “Technical
Specification – Materials” . The Contractor shall store the cement in storage sheds to be
provided by him for this purpose at site. The cement shall be delivered to the site in
bags sealed with the manufacturer's seal and different types of cement shall be stored
separately. The storage sheds with watertight walls and roof, shall be maintained in a
perfectly dry and wall ventilated condition, 12" above ground level and the cement shall
be stored a per instructions issued by EIC. It shall be turned over from the bottom as
and when required by the EIC. Any cement which has been deteriorated caked or which
has been damaged due to any reason whatsoever shall not be used. No cement shall
be used for the works that has been stored at site for more than three months. Test
samples of cement may be drawn from each consignment as delivered and tested by
the EIC. Should the results of such test show that any samples does not comply with
the specified requirement, the whole consignment from which the sample was taken,
shall be rejected and forthwith removed entirely from the site and replaced with cement
of satisfactory quality.
Page 2 of 15
1.5 SAND :
Sand to be used for concrete shall be well graded mixture from coarse to fine grains,
complying with the requirements of IS 383 Latest edition. It shall be clean, hard and free
from salt, earth, clay and other impurities. Fine sand confirming to Zone – iv shall not be
used. It will comply with sieve analysis in accordance with IS 2386 Part I & II.
Unless initially clean, all sand shall be thoroughly and carefully cleaned by screening
and washing in fresh and clean water. The screened and washed sand shall not contain
more than 8% by volume of clay, dust and silt immediately after allowing it to settle for 3
hours in water.
Field tests shall be carried out regularly to ensure the suitability of sand.
Sample loads shall be available at site for inspection of the EIC and if approved by him
all sand in the work shall be of quality at least equal thereto.
In case of sand containing moisture the proportions of concrete materials shall be
adjusted to give the correct mixture.
The coarse aggregate where absorption of water after 24 hours immersion is more than
5% by weight shall not be used.
When required by the EIC the tests indicated in I.S. 383 or IS-2386 ( all parts ) shall be
got carried out by the Contractor at his cost to show the acceptability of the materials.
Stowage piles of aggregate shall have good drainage, preclude inclusion of foreign
matter and preserve the gradation.
1.7 WATER :
Water used for all purpose in this contract shall be free from oil, acid, vegetable matter,
salts or dirt of any kind which will have adverse effect on cement or steel in the case of
reinforced concrete. Whenever called for, the Contractor shall produce test results for
water being used on work. The water quality shall confirm to IS-456-2000.
1.8 ADMIXTURES:
Page 3 of 15
Admixtures or Cement containing additives (such as accelerators, retarders, water
proofing agents etc.) shall not be used unless specified or otherwise directed or
approved by the EICs). The Admixtures shall confirm to IS-9103 latest edition.
The form work shall be designed and constructed in such a manner that all concrete
work shall be true to line, level and size, and free from honeycombing, pinholes, surface
irregularities and every other defect whatsoever.
All form work shall be adequately propped, braced and framed to prevent deformation
under weight and pressure of wet concrete, constructional loads, wind, vibrations and
other forces. All joints in shuttering shall be close fitting to prevent the loss of cement
paste or mortar from the concrete.
All form work shall be carefully cleaned and coated with an approved proprietary mould
oil before use, care being taken to keep all reinforcement away from contact with such
oil. All moulds shall be free from sawdust, shavings, dirt, mud or other debris by hosing
with water or oil free compressed air.
The shuttering for beams and slabs shall be erected so that the shuttering on the sides
of the beams and of the soffits of the slabs can be removed without disturbing the beam
bottoms. For beams having spans greater than 6 meters and for cantilevers, the form
work shall be given adequate upward camber as directed by the EIC.
Details of all temporary work (timbering, staging etc.) are to be submitted for the
approval of the EIC and the form work shall be inspected and approved by the EIC
before concrete is placed within it. Notwithstanding such approval, any damage or
consequences arising there from shall be the Contractor's entire responsibility.
The contractor shall design concrete mixes (by Ready Mix Concrete Plants ) to produce
concrete of the required strengths. The contractor must submit full designs done from
RMC plants of the mixes for approval of EIC and trial mixes will be prepared by the
contractor in the presence of the EIC, having workability, strength, minimum cement
content and surface finish as criteria. Notwithstanding the acceptance by the EIC of any
mix design and series of trial mixes, variations may be made to the proportions when
considered necessary by the EIC. Such variations may be made also to normal mixes if
used, but variations of this nature will not be allowed to affect the unit price of concrete.
For both Nominal as well as Design mix concrete, the quantity of cement shall be
determined by weight. Where standard bags of cement are used, their weight shall be
checked at frequent intervals and any loss in weight due to leakage etc. shall be made
good.
In the case of Nominal Mix concrete, aggregates shall be measured by volume, cement
by weight and mixing water in graduated cans. In the case of controlled concrete all
Page 4 of 15
aggregates and cement shall be measured by weight in approved weigh batching
equipment. Mixing water shall be measured in graduated cans.
While calculating the amount of mixing water, the moisture content of the aggregates
shall be taken into account.
The grades of concrete shall be in accordance with Table below the cement content of
the mixes specified shall not exceed the minimum content specified in Table by more
than 20%.
The provision in this section shall apply to all concrete grades and is to be considered
as a supplementary to general provisions for Plain Cement Concrete & Reinforced
Cement Concrete works.
• Ready mix concrete (RMC) may be manufactured in a central automatic weigh batching
plant and transported to the job by agitating Transit mixers. The RMC is to be sourced
from reputed & approved batching plants as mentioned in the approved list of
manufacturers or suppliers only. The design mix has to be submitted to HPCL before
concreting and the same has to be approved by HPCL before concreting is done.
• Note : No puzzolonic material such as Fly ash, Metakaoline & rice husk ash etc shall be
used for the work.
• The standard deviation for concrete mix design will be considered as per Table 8 of IS-
456-2000.
The following specifications, standards and codes are made a part of this specification. All
standards, tentative specifications, codes of practice referred to herein shall be the latest
editions including all applicable official amendments and revisions.
In case of discrepancy between this specification and those referred to herein, this
specification shall govern.
IS 383:- Specification for coarse and find aggregates from natural source for concrete.
IS 3025:- Methods of sampling and test (Physical and chemical) water used in industry.
IS 432:- Specification for mild steel and medium tensile steel (parts I & II) bars and hard drawn
steel wire for concrete reinforcement.
IS 1139:- Specification for hot rolled mild steel and medium tensile steel deformed bars for
concrete reinforcement.
IS 1566:- Specification for plain hard drawn steel wire fabric (Part I) for concrete
reinforcement.
IS 1786:- Specification for cold twisted steel bars for concrete reinforcement.
IS 3370:- Code of practice for concrete structures for storage of liquids (Part I to IV)
IS 2502:- Code of practice for bending and fixing of bars for concrete reinforcement.
IS 3596:- Safety code for scaffolds and ladders. (Part I & II)
Page 6 of 15
In the event that state, city or other Government bodies have requirements, more stringent
than those set forth in this specification, such requirements shall be considered part of this
specification and shall supersede this specification where applicable.The quality of materials ,
method and control of manufacture and transportation of all concrete works irrespective of the
mix , whether reinforced or otherwise, shall conform to the applicable portion of this
specification.Engineer shall have the right to inspect the source/s of material/s , the layout of
operations of procurement and storage of materials, the concrete batching and mixing
equipment and quality control system. Such an inspection shall be arranged and approval of
Engineer-In-Charge shall be obtained prior to starting of concrete work. Concrete shall be
mixed by mechanical mixer only and no hand mixing shall be allowed for RCC works.
GENERAL:
The quality of materials and method and control of manufacture and transportation of all
concrete work irrespective of mix, whether reinforced or otherwise, shall conform to the
applicable portions of this specification.Engineer shall have the right to inspect the source/s of
material/s, the layout and operation of procurement and storage of materials, the concrete
batching and mixing equipment, and the quality control system. Such an inspection shall be
arranged and Engineer’s approval obtained, prior to starting of concrete work.
The ingredients to be used in the manufacture of standard concrete shall consist solely of a
standard type portland cement, clean sand, natural coarse aggregate, clean water and
admixtures, if specially called for on drawings or specifications.
CONSISTENCY:
The consistency of the concrete shall be such that it flows sluggish during pumping of concrete
into the forms and around the reinforcement without any segregation coarse aggregate from
mortar. The slump tests are mandatory and shall be carried out at regular intervals so that the
consistency concrete can be monitored.
PLACING OF CONCRETE:
Concreting shall commence only after inspection and written approval by EIC.
Shuttering shall be clean and free from deposits of foreign materials and proper deshuttering
agent shall be applied to the surface.
Proper arrangements shall be provided for conveying the concrete the place of deposition
without disturbing the reinforcement.
COMPACTION:
Page 7 of 15
Immediately on removal of forms, the RCC works shall be examined by the Engg. -in-Charge /
Architects before any defects are made good.
The work that has sagged or contains honey combing to an extent detrimental to the structural
safety or architectural concept shall be rejected.
Surface defects on a minor nature may be accepted and the same shall be rectified as follows
:
a) Bulges due to movement of forms, ridges at forms, ridges at form joints shall be carefully
chipped and then rubbed with a grinding stone.
b) Honeycombed and other defective areas must be chipped out, the edges being out as
straight as possible and perpendicular to the surface. Shallow patches are first treated with
a coat of thin grout (1 cement : 1 sand) and then filled with mortar similar to that used in
concrete. Large and deep patches shall be filled up with concrete held in place by forms
and shall be reinforced.
c) Holes left by bolts shall be filled carefully with mortar. Holes extending right through the
concrete shall be filled with mortar with a pressure gun.
d) The same amount of care to cure the material in patches should be taken as with the whole
structure.
The surface which has to receive plaster or where it has to be joined with brick masonry walls
shall be properly roughened immediately after the shuttering is removed.
MEASUREMENT
All measurements shall be as per IS 1200
Mixing of concrete shall continue until there is a uniform distribution of material and the
concrete is uniform in colour and consistency and for at least two minutes.
Page 8 of 15
Mixes and weigh batches shall be maintained in first class condition throughout the
contract and any mixer or plant which is faulty shall not be used. The drums on all
mixers shall revolve at the speed recommended by the maker. A mixer of any type
which has been out of use for more than 20 minutes shall be thoroughly cleaned out
before any fresh concrete is mixed. All equipment shall be maintained in a clean
serviceable condition and their accuracy periodically checked.
The Contractor shall keep at the site of the works for the EIC’s use or his representative
a standard slump test mould and shall provide facilities throughout the construction for
tests to be made as and when the EIC may require.
The Contractor shall keep on site minimum 12 no.s standard 15 cm test cube moulds
and ancillary equipment for preparing test cubes. Before the Contractor commences
any concrete construction he shall make six cubes of mix concrete with the cement
sand, aggregate and water which he proposes using on the contract and shall have
them tested at a Laboratory approved by the EIC/EIC. Three cubes shall be tested at 7
days and three cubes at 28 days after casting and curing. In all cases the cubes shall
give the minimum compressive strength. No concrete construction shall be commenced
until Preliminary Tests on the six cubes referred above have been completed and
results show the concrete to have the minimum compressive strength. As construction
proceeds samples from fresh concrete shall be taken as per IS 1199 - 1959 and cubes
shall be made, cured and tested in accordance with IS 516 1959.
Three test specimens shall be made from each sample for testing at 28 days. Additional
cubes may be required for various purposes as to determine the strength of concrete at
7 days or at the time of striking form work, or to determine the duration of curing, or to
check the testing error.
The test strength of the sample shall be the average of the strength of three specimens.
The individual variation should not be more than 15 percent of the average.
Any part of the work from which the cubes fail to give the required minimum
compressive strength shall be dealt with by the Contractor as directed by the EIC and at
the expenses of the Contractor.
The concrete is also liable to be rejected or repaired as per the instructions of the
EIC/EIC if it is porous or honeycombed, its placing has been interrupted without
providing a construction joint or the reinforcement has been disproportionately
displaced. The rejected concrete has to be demolished and redone to the satisfaction of
the EIC free of cost.
Page 9 of 15
The Contractor shall keep a daily record (Concrete Pour Card ) showing the date when
each portion of concrete is poured in slab, beam, column etc., curing, removal of form
work and test cube results at 7 days and 28 days period. They shall be sent
immediately to the EIC/EIC.
The concrete should be thoroughly compacted and fully worked around the
reinforcement, around embedded fixtures and into the corner of the form work without
formation of honeycombing, pinholes or surface irregularities and any other defects
whatsoever.
The use of mechanical vibrators having capacity of producing vibrations at a rate not
less than 5000 cycles per minute is recommended. Over vibration or vibration of very
wet concrete is harmful. In addition to mechanical vibration, sufficient hand tools must
be used to assure full consolidation around reinforcement and at edges and corners.
No unset concrete shall be brought into contact with unset concrete containing cement
of different type. Special permission and instructions shall be obtained when concrete
has to be deposited under water.
Newly placed concrete shall be protected by approved means from rain, sun and drying
winds. Concrete placed below the ground shall be protected from falling earth during
and after placing. Approved means shall be taken to protect immature concrete from
damage by debris, excessive loading, vibration, abrasion, deleterious ground-water,
Page 10 of 15
mixing with earth or other materials that may impair the strength and durability of
concrete.
Before construction commences the Contractor shall submit to the EIC, for his
approval, sketches showing proposed positions of construction joints.
If the concrete has been allowed to harden excessively, the surface shall be chipped
over its whole surface to a depth of at least 3/8"and thereafter thoroughly washed. If the
concrete has not fully hardened, all laitance shall be removed by scrubbing the wet
surface with wire brushes to avoid dislodgement of particles of aggregate. Before fresh
concrete is added to the other site of a construction joint the surface of the old concrete
will be thoroughly wetted and then covered with a thin layer of cement mortar of the
same quality as that in the concrete.
Water stoppers shall be provided to the construction joints of terrace slabs, kitchen and
bathroom slabs, and water retaining structures where water leakage poses serious
problems.
Expansion joints or other permanent structural joints shall be provided in the positions
and of the form described in the drawings or elsewhere. In no case shall the
reinforcement, corner protecting angles or other fixed metal items, embedded or
bonded into concrete run continuously through as expansion joint. The placing of
concrete on either side of the expansion joint shall be done separately after an interval
of atleast 7 days.
No concrete shall be cut into, nor shall it be interfered with in any way, without the prior
approval in writing of the EIC. Necessary holes shall be provided as required for
plumbing work and for electrical pipes etc. at the time of execution.
Exposed surfaces of concrete shall be kept continuously in a damp or wet condition for
at least seven days from the date of placing of concrete.
Page 11 of 15
Approved curing compounds may be used in lieu of moist curing with the permission of
the EIC. Such compounds shall be applied to all exposed surfaces of the concrete as
soon as possible after the concrete has set.
1.20 SUPERVISION:
Constant and strict supervision of all the items of the construction is necessary during
the progress of the work, including the proportioning and mixing of the concrete.
Supervision is also of extreme importance to check the reinforcement and its placing
before being covered.
Before any important operation, such as concreting or striking off the form work is
started, adequate notice shall be given to the EIC.
The rates of contractor for providing and laying cement concrete in various grades or
proportions in the Schedule of Quantities shall, apart from any other factors specified
elsewhere in the tender documents, include for the following:
(a) For all factors and method of work described in these specifications.
(b) For all materials, labour, tools and plants, scaffolding, etc. mixing, conveying and
placing concrete in position, ramming, vibrating, trawling, curing, providing necessary
scaffolding and removing the same after the work is complete.
(c) Unless otherwise specified in the Schedule of Quantities the cost for concrete items
shall include for providing and fixing form work as described inclusive of erecting,
propping to required heights, bracing, providing stays, struts, bolts, nuts and everything
necessary to keep the forms rigid, smoothening the surface to receive concrete as per
detailed drawing, striking and stripping form work after the concrete is cured, hacking
the concrete surface required to receive plaster etc.
(d) The reinforcement in case of Reinforced Concrete work will be paid for separately
unless otherwise stated in the particular items, but rate shall include for pouring
concrete and packing around reinforcement.
(e) The measurement of concrete will be as per detailed drawings, shapes and size based
on net structural sizes as per drawings i.e. exclusive of plaster.
(f) Rates for concrete items shall cover for any shape of structural members like columns,
beams, facias, fins, louvers etc. and for cantilevered beams slabs etc.
(g) Formation and treatment of contraction and expansion joints (where water bars like
copper strips or joint fillers like 'Shalitex' are specified, such materials shall be paid for
separately.
Page 12 of 15
(h) Design of mixes where so required by specification in an approved Laboratory and on
tests of materials and work required in the opinion of the EIC and described in these
specifications.
(i) Fixing all inserts like pipes, plugs, forming holes etc. as described.
(k) For taking out dowel bars, fan hooks etc. through shuttering.
(l) In case where at the junctions of beams, columns, slabs, the composition of concrete
mix or specified strength be different for columns, beams and slabs, then in such cases
only the richer concrete among those specified for in all these members shall be used at
the junctions and rate quoted for columns, beams and slabs or any member entering
such junctions shall allow for the same. Rate shall also cover for spill over of richer
concrete in beams to natural angle of repose of wet concrete required from practical
considerations, while concreting the junctions.
(m) For forming drip moulds in Chajjas, sills, etc. and where shown in the drawings or as
directed.
2 STEEL REINFORCEMENT :
Page 13 of 15
correct specified cover. Contractor shall be responsible for all costs for rectification
required in case the bars are displaced out of their correct position.
2.6 WELDING :
Welding of bars shall not be carried out unless specially authorised in writing by
Structural EIC.
In case of mild steel reinforcement bars of larger sizes, where cold bending is not
possible, they may be bent by heating with written permission of the Project Engineer.
Bars when bent hot shall not be heated beyond cherry red colour and after bending,
shall be allowed to cool slowly without quenching. The bars damaged or weakened in
any way in bending shall not be used on the work. High strength deformed bars shall in
no case be heated to facilitate bending or cranking.
A notice of at least 24 hours shall be given to the Project Engineer by the Contractor for
inspection of reinforcement.
If in the opinion of the Project Engineer any material is not in accordance with the
specification or the reinforcement is incorrectly spaced, bent or otherwise defective, the
contractor shall immediately remove such materials from the site and replace the same
and rectify any other defects in accordance with the instruction of the Project Engineer
to his entire satisfaction.
Page 14 of 15
2.10 RATES QUOTED FOR REINFORCEMENT SHALL IN ADDITION TO ANY FACTORS
MENTIONED ELSEWHERE SHALL ALSO INCLUDE FOR :
(a) All cutting to lengths, labour in bending and cranking, forming hooked ends, handling,
hoisting and everything necessary to fix reinforcement in work as per drawings.
(c) Cost of PVC blocks to maintain cover and holding reinforcement in position.
(d) For fabricating and fixing reinforcement in any structural member irrespective of its
location, dimensions and level.
(e) Removal of rust and every other undesirable substances, using wire brush etc. as
described.
Page 15 of 15
SPECIFICATION OF MECHANICAL SHOE SEAL (LIQUID MOUNTED
MECHANICAL SEAL)
The Channel hanger type assembly should successfully maintain a constant seal
elevation even with a wide rim space.
Stainless steel shoes shall have a minimum nominal thickness of 1.2 mm (18
gauges). Stainless steel shall conform to the requirements of ASTM A 240/A
240M (austenitic type only).
Vendor should inspect the seals once in six months during guarantee / warrantee
period & Vapour loss calculations meeting CPCB standards to the relevant
clause using Tank 4.0 (latest version) software, incorporating local weather
conditions shall be provided along with the inspection report.
GUARANTEE: 24 months from the date of installation & 30 months from the date of
supply which ever is earlier.
Page 2 of 5
Specifications of Secondary Seal
Secondary seal system shall be tight fitted, rim mounted, with a wiper Tip made
of a polymer compatible to the stored product.
Seal shall have very low coefficient of friction, shall not damage or score the tank
shell. Metallic seal components shall have adequate corrosion protection for long
life. All material used in the seal manufacturing shall be tested and certified for
extended use in hydrocarbon products.
INSPECTION CRITERIA :
Maximum seal gap area will be 20 cm2/m of tank diameter.
Vendor should inspect the seals once in six months during guarantee / warrantee
period & Vapor loss calculations meeting CPCB standards to the relevant clause
using Tank 4.0 (latest version) software, incorporating local weather conditions
shall be provided along with the inspection report.
GUARANTEE : 24 months from the date of installation & 30 months from the date of
supply which ever is earlier.
Page 4 of 5
Page 5 of 5
Specification for Gauge Pole Sleeve / Landing Leg Sleeve
The Gauge Pole Sleeve shall consist of a flexible enclosure to be installed over existing
slotted gauge pole along the height of the pole and can adjust its height depending
upon the height of the deck in an external floating roof tank. The Landing Leg Sleeve is
a flexible enclosure to be installed over existing telescopic landing legs along the height
of the pipe. This flexible enclosing device should completely enclose the slotted gauge
pole and the landing leg while eliminating VOC emission pathway from inside the tank
through the gauge pole slots and the landing legs. It should also seal any opening
between well cover and any other openings in the gauge pole well & landing leg area.
Gauge pole sleeve / Landing leg sleeve shall be self adjusting type and can be easily
retrofitted on existing gauge poles & landing legs. The Gauge Pole Sleeve / Landing leg
sleeve shall be provided to minimize emissions through the gauge pole slots and
landing leg area.
INSPECTION CRITERIA:
Vendor should inspect the Sleeve once in six months during guarantee / warrantee
period & Vapor loss calculations using Tank 4.0 (latest version) software, incorporating
local weather conditions shall be provided along with the inspection report.
Page 1 of 2
Tests of other components to be carried out at a reputed laboratory and the results
shall be furnished for review / approval.
GUARANTEE : 36 months from the date of installation & 42 months from the date of supply
which ever is earlier.
Page 2 of 2
SPECIFICATION FOR
FOR
OF
Page 1 of 3
1.0 SCOPE
2.1 Flexible pipe shall consist of two layers, each layer unbonded to each other as
follows:
Flexible pipe must provide Repetitive Lay Pattern (RLP) without any
external support or accessories like tethered assemblies, ballasting etc.,
during its full operational life.
Flexible pipe shall have Built-in end fittings with ASME B 165, 150# CS
RF swivel flange.
Page 2 of 3
Full length of pipe shall be in single continuous length without any
intermediate joints in between the two end flanges. Vulcanization is not
acceptable.
The unbounded flexible hose should be designed in such way that the
inner SS type 304 carcass is held in tension to keep the hose in same
position as it was when installed. No kinking of flexible pipe shall take
place during movement (upward/downward) of the roof.
Flexible pipe shall not induce lateral forces on the floating roof.
2.2 Vendor shall guarantee the product for minimum 3 years after installation.
2.3 Vendor /Manufacturer of the flexible pipe must have a minimum of 3 years of
field proven reference in India for similar application in floating roof tanks.
Relevant document from the customers shall be furnished along with bid.
2.5 The manufacturer shall provide hydro test certificates for the flexible pipe duly
certified by Third Party Independent Inspection agency.
2.6 Bidder shall specify the make offered in their unpriced bid along with all
necessary literature, catalogues, etc. for above.
Page 3 of 3
1. The vendor’s scope covers design, manufacture, supply, testing, installation, hydro test,
supervision of commissioning & guarantee of stainless steel armored hose as per API-650
(latest edition) including connecting flange for floating roof tank.
2. Stainless steel armored hose as per API 650 in contact with liquid stored in the tank must
be 100 % resistant to aromatics.
3. Stainless steel armored hose as per API 650 must provide REPETITIVE LAY PATTERN
(RLP) without any external support or accessories like tethered assemblies, ballasting,
chain etc, during its full operational life.
5. Flexible tube shall have built in end-fittings with ASME B 16.5 #150, A105 Flange.
6. The designed working pressure rating for the flexible drain tube should be 30 PSI and the
test pressure should be 60 PSI.
7. Full length of tube shall be in single continuous length without any intermediate joints
in between the two end flanges
8. The stainless steel armored hose should be designed in a way that the hose shall be kept
in the same position as it was when installed. No kinking of stainless steel armored hose
as per API 650 shall take place during movement (upward/downward) of the roof.
9. No chemical attack, gas penetration or ballasting and mechanical wear shall take place
with flexible tube
10. Stainless steel armored hose shall not induce lateral force on the floating roof.
11. Stainless steel armored hose shall be inspected by third party inspection agency
LLOYDS/DNV/CEIL/BV or any other third party inspection agency approved by HPCL.
12. Relevant certificate / documents (along with each flexible line) shall be furnished along
with supply
13. Third party inspection includes pressurizing the flexible hose to the test pressure (60 psi),
allow it to stabilize and maintain pressure for 4 hours & carry out a visual inspection for
leaks
14. The manufacturer shall provide hydro test certificate for the flexible hose duly certified
by third party inspection agency.
15.Vendor shall confirm the adequacy of the design of stainless steel armored hose as per
API 650(its size & length) for 100% evacuation when the roof is in its lowest position
during maximum rainfall intensity period
TECHNICAL
SPECIFICATIONS
FOR
PIPES
Page 1 of 4
TECHNICAL NOTES FOR PIPES
1.0] GENERAL
1] All pipe and their dimensions, tolerance, chemical composition and physical properties. Heat
treatment hydro test and other testing and marking shall conform to the codes and standards
specified herein. In case of any deviations the same should to be highlighted.
2] Test report shall be supplied for al mandatory test as per the applicable material specifications
Test report shall also be furnished for any supplementary test specified herein.
3] Material test certificates (physical properties chemical composition and Heat treatment report)
shall also be furnished for the pipes supplied.
4] Steel made by acid Bessemer process shall not be acceptable.
5] All longitudinally welded pipes other than IS: 3589 should employ automatic welding only.
Vendor shall specify the type of welding technique which will be employed.
6] Pipe shall be supplied in single random length OF 4 – 7 Mtrs.
7] Seamless and LSAW pipes shall not have any circumferential seam joint in a random length.
8] Pipes with Bevel ends shall be in accordance with ANSI B-16.25 weld contours shall be as
follows.
9] Specified heat treatment for CS shall be carried out after weld repairs, number of weld repairs at
same spot shall be restricted to max two by approved repair procedure.
1] All pipe shall be marked in accordance with the applicable codes, standards and specifications.
In addition the PO No and item digit code will also be marked.
2] Point or ink marking shall not carry any harmful metal or metallic salts such as lead. Zinc or
copper which causes corrosive attack on heating.
3] Pipe shall be dry, clean and free from moisture, dirt and loss foreign material of any kind.
4] Pipe shall be protected from rust, corrosion and mechanical damage during transportation,
shipment and storage.
5] Rust preventive used on machined surfaces to be welded shall be easily removable with a
petroleum solvent or shall not be harmful to welding.
6] Both ends of the pipe shall be protected with the following material:
PE Plastic Cap
BE Wood, Metal or Plastic cover.
End protectors to be used on BE shall be securely and tightly attached with belt or wire.
Page 2 of 4
4.0] Quality and data/ documentation requirements
1] QA plan
Vendor during bidding stage shall confirm compliance to his Quality Assurance plan consisting
of relevant procedures covering various activities like design and engineering material
procurement, manufacture, inspection and testing documentation dispatch to site erection and
commissioning wherever applicable and maintenance of quality records in the post order stage.
The vendor shall confirm the validity of their QA plans and submit only deviation/revisions if
any to these plans to Sr. Manager –E&P HPCL 1 floor Hindustan Bhavan for approval within
two weeks from the date of receipt of FOI/PO whichever is earlier.
2] ITP
Vendor shall submit inspection and test plan for approval within 2 weeks of FOI/PO and before
commencement of manufacture to Sr. Manager –E&P and should cover bought out items from
sub vendors.
3] Drawing Schedule
Vendor shall submit a total index of drawings and documents required for review/records along
with the scheduled date of submission of each drawing/document within 2 weeks from date of
issue of FOI PO whichever is earlier where ever required.
7] Calibration Records
Vendor shall use only calibrated measuring and test instruments and maintain calibration
records. Vendor shall furnish records of calibration of measuring and test instruments including
recalibration records to Third party inspection Agency on demand.
Page 3 of 4
9] Quality records
Vendor shall maintain quality records as per his procedures inspection reports & test records
copies shall be furnished to HPCL/Third Party Inspection Agency.
General
11.1] Vendor shall ensure that each drawing shall contain the following information:
PO No name of equipment, tag no., name of project, Client, Drawing/Document title,
Drawing No., Revision and date.
The drawing document shall be checked approved and duly signed stamped by the vendor
Revisions and date.
Code 1 Approved
Code 2 Proceed with manufacture / fabrication as per commented
Document revised document required.
Code 3 re submit for review as marked.
Page 4 of 4
!
"
!
"
#
e) Cold straightening of section and plates, whenever they are bent and
kinked.
! $ #
! & #
) *
#
+! , - #
.
%! #
"
! -
"
) / #
0
1- 1
2 + 343 45 + 6 7
463
! 8
9 ! :
# 9 / !
! + %
9 !
! " /
! + . #
! ( "
! )
! & .
# 8
.
! : %
# . #
.
%!
' $(
! - " #
4;4; 46 #
6
! < 9
+ 6 46=!
! <
- #
> >
7 $
/
8 # #
= ? ; @
# 9
# !
;
3 @
2.2.6 A # #
#
5 $ B
6 2 %
# due to
fatigue. Welding across tension flange of crane girders is not permitted.
4 $
+ 6 46= + 6 3 434
# .
2
#
7 ! ""!
7
- / C+ # + ?BD
7 2 #
#
>- >
7 7 - . +%
# . 8
%
E # 1- 1
7 = ) + 6; 46;
7 ; B
+
#
! , ,
! &
,! A
7 3 A +
7 464
7 $! % &' %
7 ? / + 737 44
7 /
+ 73= 44
#
77 !" $'"%
77 &
+ 6 = 44 <
+ 5 6 45= # <+,
= &
+
; , #
97 ; !
; , +
#
#
#
;7 9F "& ! # #
# #
;=
;; + .
4 G, G, ,
(
3 ) )
3 2 =
+ 6 46=
3 2
37 '
( #
3= #
# * +
5 ,
5 $ 6 46=
#
5 $ .
57 -
5= $
5 ; 45=H +
#
5; -
53 - % /
#
55 ,
8 :
56 #
/
54 + #
9; ; !
"
5 + . # *
5 + / % . #
# ' #
%
# 8
5 %
5 7 9 !
5 = A
#
5 ; %
5 3 # -I I <JK )< ++
5 5 # 9 !
+ 5 ; 45=
-
6 , #
L A 9 !
#L 9
% !
C! .
#!
# ! .
# ! A
/! K % /
J! #
J! +
/ ! 2 . %
6 A
> . + 57 6 9 +!
45=
67 - + 4;4; 46=
6=
+ =7;7 435
6; < 77
.
63 < <
65 : ' /
; G7 G, #
66 $ /
+ 73 7 45= .
64 A (
0 B
+
6 A
#
6 $ /
#
6 $ #
2
#
6 7 - -
#
6 = $
6 ; +
H - .
6 3 A
#
6 5 & #
6 6 #
<
#
6 4 # %
* +
4 /
4 ' ,: # , >
, >
#
#
4 -
"
, > ( # '
,
47 ,
"
" # ,
4= &
"+ &
*
"+
# + # "
%
,
4;
4; "< # *
! % 1
0
! %
" /
+ 8 #
4; + % "+ ,
"+
8
, %
( , ,
4;= # #
. #
"+ # ,
"
,
"
#
,
4;; I "+
# %
"
4;3 - % #
,
"+
/ .
C </ - @ #
! C
! K
#! + 8
#! </ #
#!
?
2 92 +!
#
2 - I
- & ? 3;
7 K
K # 8
! ,
! :
#! (
K - I
-I +"-A 2 43 , 3 $
?
&
# $
/
= ) $ ?
9J ( ) </ ! @
@
/
H
! (
!
! :
#! :
#! ,
) -
I -I +"-A 2 43 <
- #
7
5; /
%
: -
! C 0 2 M
# 2
;4 0 3 - I
-I ++-A 2 43
#
! K
3 7 0 3 7
#
- I -I ++-A 43 , 3 ,
#
! )
) 3 0 3
- I -I ++-A 2 43 , 3 ,
#
! -
! K
#
! A
/ #
# 2 # #
,
%
7 )
7 #
9 H !
# 7 0 77
7 & / # "
/ ;
77 A 5;@
H9 ,
/
(
= )
= <
9
!
= - >
" 9)
7 0 7 7!
=7 ,
# $
#
#
== ,
; B ,
! , >- 1
! & >
! , "
; + ,
"+
3 + # .
#
#
!
! " "
!
!
.
! - "
! ) #
! )
/ 8
7 < 2
7 # #
77 <
77 <
77 $ . # + 5 ; 45=
+ 5434 45; # +
777 < /
77= .
-
. # #
.
77; $ #
77; # . #
. <
%
.
# 8
77; <
77;7 - # /
# #
77;= I %
77;; $
77;5 -
#
77;6 #
.
.
.
77;4 , # .
0
7= -
7= 9
!
7= A
%
7= 7 A
/ %
#
#
7= = # #
"
7= ; -
# I
7= - /
. A #
#
; %
7= - .
7=7 - ' $( + = 44
7=7 .
# . # .
7=77 )
7=7= . .
#
7=7;
7=73 -
#
7; +
7; - <, +BI
73
73 ? #
# #
#
73 ? " #
#
#
75
75 9 <, +BI ;! !
# %
3.7.2
76
& / #
* +6
74
74 -
74 #
! -
! #
! 2 # /
#
! 2
! ,
9 !
! 2
7 , 1- ? 1
#
= = =
=7 & + 3 444
=77 ( 8 7 /;
: = #
# # $
#
#
% #
# "
# A
=7= +
' # "
=7;
/
$
-
# #
& 2$
; B$ 5;
?BD
=73 $
. 2
=75 #
=76 #
; K )$-,< )< - )- +BI $B) -+I +I (
; ( <I <)-:
# #
-
. ;7 B
.
; 9 !& "
& " 7
+ + ;;4
! ( ;
#
> $
#
- #
;
! ( 7 #
-
#
7
; 9 ! , ?
! #
+ ;;4 435
! 3N ".
#
7! - .
.
.
=! 8 ;3 5
, "& 5 N ". .
88
; .
5 ".
;! #
3!
# #
5! #
?
88
3 A (
6!
' )<< ?
4! 88 7
# # #
# 88 #
!- 4;@ @
. #
- O # 9
!
!- # % #
, # -
# #
! ,
!, ?
!( ( -
!' ; 5& P
! ( # 7 75
(
!? 2 65 "
!& , @
7! # - ,
0":" 0;" <1 1 = &5"
= Q7 =
7 Q 73 7
73 Q = ;;
Q ; ; 7
; Q 3
,
#
#
# / # #
> " , 3. - @
#
B
H= ++ /
#
- : H5;H&
• All painting materials including primers and thinners brought to site by the Contractor
for application shall be directly procured from Approved manufacturers as per
specifications and shall be accompanied by Manufacturer Test Certificates.
• HPCL may call for tests for the primers and paints including verification of batch wise
tests for physical and chemical analysis. The Contractor shall carry out the same at his
own cost and provide the results to HPCL.
• The painting work shall be subjected to inspection by HPCL at all times. Stages of
inspection are as follows:
• Surface Preparation
• Primer application
• Each coat of paint
• All records of inspection shall be maintained in Registers and jointly signed by HPCL
and Contractor.
• Any defect noticed during the various stages of inspection shall be rectified by the
Contractor to the satisfaction of HPCL before proceeding further. Irrespective of the
inspection, repair and approval at intermediate stages of work, Contractor shall be fully
responsible for making good any defects found during Final inspection or during the
Defect Liability period. DFT shall be checked and wherever shot same shall be made up
with additional coats.
• The shades of successive coats should be slightly different in colour in order to ensure
application of individual coats in consultation with manufacturer.
• Calibrated Digital Elcometers, surface profile gauges and any other inspection
instrument required by HPCL shall be provided by the contractor at site.
• The contractor shall arrange expert technical support at site by paint Manufacturer who
will cross verify independently regarding surface preparation and DFT and quality and
provide a report to HPCL.
5.1.4 DOCUMENTATION:
1.A written quality Plan with procedure for qualification trials and for actual work.
2.Daily progress Report with details of humidity, surface preparation, surface profile,
Dry film thickness particulars of applications, number of coats applied, type of
materials used, methodology-Air or Airless or Brush, progress of work vs programme.
5.Elcometer readings for the various components jointly recorded with HPCL.
; $ >
#
; (
-
; 7 ?
1, - 1 B
; = +
R .
: . >9 ! C 9 !
R 9 ! "
9 #! 9 ! 9#!
0 9# !
/
; ; A . 9
!
; 3 #
; 5 -
; 6 A #
#
#
; 4 + ; @ .
-
9 %
/ +
! .
.
; - + =65
46; ; @ #
;G, #
6;@ P -
2
# #
;
9B$ !
#
<:,B& < <) B$
; - #
# # 2$ ! $
7
; 7 # .
#
; = < # % #
# .
; ; &
; 3
# #
I
; 5 S # / #
#
+
/
/
; 6 . #
# + 4;6 45; . # +
;7 ,
# .
#
9 ! # .
3 -:+<I B+I
3 >
3 #
,
/
$ # ,
/ % I /
3 2
3 7 & 9 !
9 !
#
. .
3 = -
.
.
3 ; , IB , $
#
#
3 2
37
37 - # #
#
#
#
#
37 #
. #
#
377 -
.
"
%
37=
.
37; + .
. #
3=
3= ,
3= ? ,
"
?
# B
$ ,
>- # > 1- # 1 I - # 1
- # ,
/ # $
3=7 2 # , #
3==
,
#
3=; I
# #
B
3=3 T
3==
U- ? 1
3=5
, >
,
3=6
#
3=4 "
+ R ", "' ,:
, "' ,:
3;
3; ,
8 / .
8 & 8
#
# # .
3; + . ,
" "
/
( #
- H2
/
3;7 A . /
" ".
# ,
/ ,
!
#! "
.
3 = ,
3 = # -
. .
. /
3 ;
3 ; ! ""!
+ 9 6! 447 ; 9 4! 457 %
#
! .
# 6 6 464 " -+:
&- 56 ;
.
# #
' # #
- #
#
! + # : H
!
# # .
+
# #
!
/
#
. ,
!
/
3 3 2
3 5 ,
3 5 - ,
# %
% % #
# , - #
+
% " > #
,
, =
3 6
3 6 ?
, #
1- ?K +: 1 9:
)
3==0 3=3
(
3 6 ,
9) 3 5 !
# #
$ "
# "
- #
* +
" 1 0%%02!" '":0 0$&% 0& ?0 @ &' 5 5" $A @$!"% A$ 2$! % $A &$ 1 ! 3 <@05@
% "&5 @ 2 !!% 0& ! '"'
"% 0? 0$& ) $!" '0 <1 1 = " 1 0%%02!" '":0 0$& " ": 0& 5 $ ?
$4 !% !
01" "
2 : !0 3 ? $ ( B $ !01 0
2$:" ( B
$&" 1 1 / 7%
$& @$!"%
? $ 1
-
" 2$:" 1 ? $ .D
$A C0% $A 7 $A &0
.
* +
2 2 # 9Q! <
, : &
K ; ; ; ; ; B# ;
7 = ; 3 5 6
! 2 #
$
: 0
! &
, 7 7; = =; ;
&
!
; 7 7; =
!
; ; 7 7;
! & (
, ; 7 7; =
! :
A
< ; ; 7
B <
&
7 = ; 3 5 6
++
! 2
,
! 2
; 7 7; =
! 2
; ; 7
! 2
! 2
! 2
;
7 = ; 3 5 6
+++
2 #
2
-
2 #
+ /
! - 7 ; 5 6 4
?
! 7 ; 6 = ;
! 8 9 0 !
; ; 7 7; =
- !
0 / 7 ; 5 6 4
!
; ; 7 7; =
#
* +
6 , E
(
* +6
2 # /
: # /
+ Q" ;
+ : Q" ;
2 # #
, # Q" ;
7 B /
C /
$ .
<#
-
$
B .
<#
; 2 % Q" ;
? "
3 2 # # Q" ;
A #
IB < ! 79 ! 79 ! % = ;
! U' V #
.
7 )K <
- Q ";
) Q ; #
B ?
# Q ";
Q #
7 :
C Q
= : Q;
; 2 # # :" #
9: W !
IB <
#
+
" .
# # #
+ 43
#
ANNEXURE-V
O + ;;4
$ , 9 ! B 3; 2$ +
9+ ! B ' ? & +B
7 $ , 9$ ! - F =
& 2 $ ",
=; &
* +6
! - ( - "?
+ 3 44
! % ( ?
; 3 44
+ 54 466
7 ; 3 454 9( X
= !
7 ! ,
7 & - - & - 733 - ;4;
; . 8
9;;@ - =7@ 8 ;@ !
- & - 54 - 745 ? 3
36
# = - +I S
5 6 445 # /
# # ;
! ,
7 & - - & - 733 -
;4; ; ". 8
9;;@ - =7@ 8 ;@ !
- & - 54 - 745 ? =;
;
# = - +I S
5 6 445 # /
# # ;
9$) !
+ 633 4649$) !
; ( , + 3 Y
44
3 , + 7==7 Y 46
5 ( 8 3 + 7;=6 466
6 - / 737 46=
+ 73= 467 9 / ! A
+ =6 46
, # + 6 = 44 ,
! <) = >,>/ ( - ( ?
3 44
! & ( ? ; 3 44
9 # . !
! $ -+: & - 7; ' X-+' X?
! A 9, ! ; 3 44 /
= $
1, 1 #
#
6
(
LIST OF APPROVED MAKE
SPECIFICATION FOR
FABRICATION
AND
ERECTION OF PIPING
! "
#$ %& ' ( (#) * (+ ( , &-&-.
$ (& #( / 01 -&-. , 2
&-&-.
# / (%#(0'#0( /* (+
) ' .#( '# ( %) // 8(-' # // &-& * (+ -. ' . (1 -#; * -#) #) ( 50-( 1 .#% & (#-. .#
. ( / (( . 1 .# $( * -. .$ %& '- -' #- . 4 ) ( %& '- -' $ # -/% 8(-' #- . ( . #
-.$-' # $ . #) $( * -. % ( . # %& '- - $ ) ( -. 8(-' #- . .$ ( '#- . %) // 8 $ . -.
'' ($ .' * -#) #) ' $ (& #( / 01 ( -. (; &-&-. / # %# $-#- .
' &
%#-. .$ /0%)-.
8(-' #- . .$ ( '#- . %0&& (#-. / 1 .#% - %) %9 0-$ %9 %# & .') (%9 '/-&%9 '( $/ %
#' -.'/0$-. &&/;-. . ' # ( $ <-$ >-.' ')( 1 # &(-1 (
8(-' #- . .$ ( '#- . %0&& (#-. -<#0( % - 8( '+ #%9 ' .#-/ : ( %#(0#% #' -.'/0$-.
&&/-' #- . . ' # ( $ <-$ >-.' ')( 1 # &(-1 (
&&/-' 8/ $ % ? # .$ ($%
/- .1 .#
#) ( /- .1 .#' .%-$ ( #- .%
// / . '-. %) //8 #(0 .$ & (& .$-'0/ ( # #) <-% #) &-& # * )-') #) ; ( ## ') $
/ . 8 /#) / % %) //%#( $$/ #) . (1 /' .#(
-& @ -.#%
) ( / : .# &-&-. '/ %% ## ') $ # ') /-. %& '- - % #) #;& &-& @ -.#% # 8 $ &# $ -.
' .%#(0'#- . -. // &-&-. %;%# 1 % . . ( /9 @ -.-. ( /-. % A .$ 8 : -. 0#-/-#; &-&-.
%;%# 1 %) //8 '' 1 &/-%) $ 8; 80##* /$-. ' .. '#- .% -& /-. % E A .$ 8 / * %) //) :
% '+ # * /$ $ , 80## * /$ $ , %'( * $ @ -.#% % %& '- - $ -. #) &-&-. 1 # (- /% %& '- -' #- .%
0##* /$ $ @ -.#% %) //8 % & (%# .$ ($
! / .-. &-&-.
. ' 1 &/ #- . 8(-' #- .9 //&-& % .$ -##-. % %) //8 '/ . $ -.%-$ .$ 0#%-$ 8; %0-# 8/
1 .% C" ') .-' / '/ .-. # /9 * -( 8(0%)9 #' D 8 ( ( '#- . # .%0( #) # %% 1 8/; -%
( ( 1 /// % ( - . 1 # (- /%0') % %' / 9% .$9* /$9%& ## (& (#-'/ %9'0##-. ')-&%9 #'
/ .-. ( 50-( 1 .#% ( %& '- / % (:-' %9 - .;9 %) // 8 % %& '- - $ -. #) &-&-. 1 # (- /
%& '- -' #- .%
D 4 )-/ -##-. 0& 1 #-. / . %9' ( %) //8 < ('-% $ # &( & (/; /- . #) &-& % .$ # ') '+
#) / . % (#(0 . %%9% #) # ' % #) / . % ' . 8 &0// $ 0& # #) (* -#) 0#-.$0'-.
.; %#( %% % ##) &-& % .$ 50-&1 .# . >>/ % ) 8 /# ) / % / . % -. #) : (#-' /&/ .
%) // %#( $$/ #) : (#-' /' .#( /-. #) &-& -. #) ( '# $ & %-#- . .$ ( / . % -. #)
) (-> .# /&/ . 9#) 8 /#) / % %) //%#( $$/ ) (-> .# /&/ . 0./ %% #) (* -% -.$-' # $ . #)
$( * -. %
/ & % %& '- - $ (: (- 0% /-. % -. #) $( * -. % %) //8 1 -.# -. $ 8; #) ' .#( '# ( . ' % #)
' .#( '# (% 0. 8/ # 1 -.# -. #) -.$-' # $ %/ & ) %) //') '+ #) % -. #) &-& * -#)
&( '-%- . %&-(-# / : / F .#% .$ $( -.% ( %) * . -. #) -% 1 #(-' ') /-. .$ #) % (
-.# .$ $9 $0(-. );$( %# #-' # %#9 ( ( / %-. #) #( && $ -( .$ $( -.-. 0# #) # %# /0-$
# ( # %#-. F /: : .#% .$ $( -.% ( /% %) * . * ) ( : ( ( 50-( $ ) ' .#( '# ( %) //
&( :-$ : .#% .$ $( -.% ' .. '#- .% : . * ) . #) % ( . # %) * . -. #) $( * -. % .$ (
0.$ . ' %% (; 8; #) . -. ( -. ') ( ( &( ' %% /-. % ) $ # -/% ( #) #;&
' .. '#- .% # 8 $ &# $ %) //8 -: . # #) ' .#( '# ( ##) #-1 * (+
# ( #) &-&-. -% ( '# $ -. -. / & %-#- .9 -# %) // 8 '/ . $9 # %# $ ( #- )#. %% .$ + &# $(;
* ) ( : (-.%#(0'# $9 % $ %'(-8 $ -. #)-% %& '- -' #- .
F /: %
0&& (#%
) ' .#( '# ( %) //$- #) &-& /-. #( .') % * ) ( . ' %% (; '' ($-. # #) $( * -. 9#(0 #
#) /-. .$ ( $- .# % & (%& '- -' #- .% .$ % $-( '# $ 8; #) . -. ( -. ') (
) ' .#( '# ( %) //8 ( %& .%-8/ ( ' (( '# / ; 0# .$ ( $- .# #) /-. (( (%9- .;9%) //
8 ( '#- - $ 8; #) .#( '# ( #)-% * . ' %#
) #( .') %) //8 '0##(0 # #) /-. / : / $ * -#) #) ) /& %- )#( -/% &( :-$ $ # : (; 2 " #
') . $-( '#- .9 ( $- .# .$ # .; %0-# 8/ $-%# .' % $-( '# $ 8; . -. (-. ') (
2 * (-. .$ / ;-.
; " ')-.
; B .$
.$ ( : 0( 8/ # 1 & ( #0( 9' .$-#- .% .$ 0%-. 1 #) $% * )-') * -//. # $ 1 ' #-. 9#)
&-& 1 ; 8 / * ( $ -.# #) #( .')
//%+-$ 1 (+% .$ #) (&/ ' % $ 1 %) //8 #) ( 0 )/; < 1 -. $ # .%0( &( & (& #')-.
* ) ( . ' %% (;98 ( #) &-& -% -. //; / * ( $ -.# #) #( .')
# $ &-& %) //. #8 ) .$/ $ (1 : $ 8; 1 .% ' 8/ (') -.% (8; &( ;-. * -#) %+-$% (
8 (%9-#%) //8 #- )# . $ .$ / * ( $ 8; 0%-. / * (-. -. 8 /#% %# .$ ($ * -$#) .$ $ %- .
(#) %-> &-& 8 -. ) .$/ $
( '' %% %) //8 &( :-$ $ ( #) * /$-. #) '-('01 ( .#- /@ -.#% 8; -.'( %-. #) * -$#)
.$ $ &#) #) #( .') ##) % & -.#% ) ( %) 0/$ 8 . ' .%#(0'#- . # #) * /$ ( ( 1 .;
%-$ % #) # $ * /$ $ @ -.#-% 8# -. $
2 '+ -//-.
# ( # %#-. .$ -.%& '#- . #) &-& /-. # #) .#-( % #-% '#- . #) . -. ( -. ') ( 9#)
#( .') %) // 8 8 '+ -// $ * -#) #) <' : # $ 1 # (- / #( .') %) // 8 8 '+ -// $ * -#) 0#
#) &&( : / #) . -. ( -. ') ( '+ -//-. * -#) #) <' : # $ 1 # (- /%) //8 $ . -.
/ ; (% 22 1 1 * //* # ( $ .$ ( 1 1 $ # : -$ .; % ##/-. # (* ($%
) ' .#( '# (%) //&/ ' % -/ : (#) #( .') # %0') ) - )# % * // % -. &-.- . #) . -. (
-. ') ( 9# &( :-$ $ 50 # /; ( 0#0( % ##/ 1 .# #) #( .') 8 '+ -//
$0 # <- .'- % #) * (+9% 1 & (#- . #) &-& /-. -% 8 '+ -// $ * -#) 0# &&( : / #)
. -. ( -. ') ( 9 #) . -. ( -. ') ( %) //) : #) (- )# # ($ ( 0.' : (-. #) &-&
( < 1 -. #- . .$ #) ' %# %0') 0.' : (-. %) //8 8 (. 8; #) .#( '# (
0(&/0% <' : # $ % -/ ( (088-%) 1 # (- /%) //8 ( 1 : $ 8; #) .#( '# ( #)-% * . ' %##
&/ ' $ %- . # $ 8; #) . -. (-. ') (
4 ) . #) #( .') ) % 8 . $0 #)( 0 ) ( $%9 //8 '+ -//%) //8 #) ( 0 )/; ' 1 & '# $ . ' (# -.
' % %9%& '- /' 1 & '#- . 1 #) $% 1 ; 8 ( 50-( $ 8; #) . -. ( ') ( )-% %) //8 $ .
8; #) ' .#( '# ( #. <#( ' %## #) * . (
4 ) . #) #( .') ) % 8 . $0 #)( 0 ) 0./-. $ $-#') % #) 8 '+ -//%) //8 #) ( 0 )/; ' 1 & '# $
-. 2 1 1 / ; (% ( $-%# .' 2 1 8 ; .$ #) 0#%-$ 8 .+% #) $-#') . -#) ( %-$
) 8 .+% #) $-#') %) // /% 8 ' 1 & '# $ -. 2 1 1 / ; (% #. <#( ' %## #) * . (
# ( #) ( $% ) : 8 . /( $; ( $ $ .$ - #) ; ( #( .') $ ( #) (* -% $-%#0(8 $ 8; #)
.#( '# ( $0(-. / ;-. #) &-& /-. %9 #) ' .#( '# ( %) // ( %# ( #) ( $ # -#% (- -. /
/ : / .$ ' .$-#- . . #) : .#9 #) ' .#( '# ( -% ( 50-( $ # &/ ' <#( -//9 ( : /9 ( #) (
%& '- /1 # (- /% -#%) //8 $ . 8; )-1 * -#) 0# .; <#( ' %## #) * . (
) (#) . 8 #) %-$ % #) &-& /-. #( .') * )-') ) % 8 . $-%#0(8 $ $0(-. #) ' .%#(0'#- .
#) &-& /-. %) //8 %1 #) . $ .$ / #-. ' .$-#- . % #-% '# (; # #) . -. (-. ') (
!2
. (/
* . (-% .#-#/ $ # % .$ )-% * . -.%& '# (9# - /$ (%) &% * ) ( &( 8(-' #- . .$ ( '#- .
&-& /-. % ( 8 -. $ . 9* -#) #) // * -. 0.'#- .% 80#. #/-1 -# $ # 3
-:D ') '+ * ) #) ( * /$-. -% ' . (1 -. # ( / : .# %& '- -' #- . .$ #) &( '#-'
' .%#(0'#- . &( '#-'
.#( '# ( %) // . #- ; %0 -'- .#/; -. $: .' #) ' 1 1 .' 1 .# 50 /- -' #- . # %#%9 * /$-.
* (+ .$ '' &# .' # %#%9# . 8/ #) * . (=% .%& '# (# %0& (:-% #) % 1
.#( '# (%) //&( :-$ #) * . (=% .%& '# (* -#) // '-/-#- % . ' %% (; (' ((;-. 0#)-% * (+
#. <#( ' ## #) * . (
&&( : / ( 1 #) * . (=% .%& '# ( %) // . # ( /- : #) ' .#( '# ( & (#- //; ( 0//; )-%
( %& .%-8-/-#- % .$ 0 ( .# % 0.$ (#)-% ' .#( '#
.%& '#- . // * /$% %) // 8 ' ((- $ 0# % & ( -.-%) $ * /$% %) // 8 :-%0 //;
-.%& '# $ ( & ( // / .$ <- / 1 -% /- .1 .# #) * (+9 '( '+%9 -. $ 50 # & . #( #- .9 0.
( & -( $ 80(. #)( 0 )9 $-1 .%- .%9 .$ #) ( %0( ' $ '#%9 .$ -# %) // &( % .# . #
* (+1 . /-+ && ( .' .$ ( '0##-. $@ ' .# # #) -. /8 $ . #) 0#%-$ #) &-&
%) //. # <' $ 2 ! 1 1 -. $ &#) EI #) &-& * //#)-'+. %%9* )-') : ( -% %1 // ( .$
#) '01 0/ #-: / . #) %) //. #8 1 ( #) . 2 1 1 -. .; ' .#-.0 0% 22 1 1 / . #) * /$
'#% * )-') ( . # * -#)-. #) '' &# 8/ /-1 -#% %) //8 ( 1 : $ ( 1 #) @ -.# ' 1 &/ # /; 8;
')-&&-. ( (-.$-.
( & -(%) //8 ' ((- $ 0#* -#) 0#&(- ( 0#) (-> #- . #) . -. (-. ') (
H2
. (/
) - /$ # %#&( %%0( %) //. #8 / %% #) . #) ( # %# #) // * -. 3
01 #) 1 <-1 01 %0%# -. $ & ( #-. &( %%0( ( #) 1 <-1 01 &-& /-. %# #-' &( %%0( .$
#) 1 <-1 01 ' /'0/ # $ %0( &( %%0(
%#1 $-01
/ .-.
1 & ( (; /-.$%
F .#-. 3
( %%0(->-.
) # %# &( %%0( -% # 8 1 -.# -. $ ( %0 -'- .# #-1 # & (1 -# ' 1 &/ # -.%& '#- . #)
%;%# 1 0.$ ( # %# 80# -. . ' % %) // #) #-1 8 / %% #) . # . 1 -.0# % %# %) // 8
' .%-$ ( $ ' 1 &/ # ./; * ) . &&( : /-% -: . 8; #) . -. (-. ') (
%# 0 %3
.#( '# (=% * . # %# 0 %) //8 -.%# // $ % '/ % % & %%-8/ # #) / * %#& -.#-. #) %;%# 1
8 -. # %# $ (- ( # -.%# // #- .9 #) # %# 0 %) //8 ') '+ $ -.%# %# .$ ($ 0 (
' /-8( # $ * -#) #) -$ $ $ * - )# # %# ( /-8( #- . # %# 0 % %) // 8 #)
( %& .%-8-/-#; #) ' .#( '# (
( -.-.
22
2 %# ' (#- -' # % ' .# -.-. $ # ( # %#9 -$ .#- -' #- . #) &-&-. %;%# 1 9 # %# /0-$ 0% $9 # %#
&( %%0( .$ &&( : / * . (=% -.%& '# (
(#- -' # % ( /0%)-. ' .# -.-. /0%)-. 1 $-01 0% $9 -$ .#- -' #- . #) &-&-. %;%# 1 9 $ #
/0%)-. .$ &&( : /8; * . (=% -.%& '# (
"
;1 .# (&-&-. %) //8 8 % $ . /-. (1 %0( 1 .#% ' /'0/ # $ . #) 8 %-% #) < '0#- .
$( * -. % ) / . #) %) // 8 1 %0( $ / . #) ' .#( /-. % &-& %9 ' .#( /-. % 8 .$%
.$ /8 * %9 # %9 ( $0' (9 4 9 / . $ @ -.#% // #;& % : /: % %) // 8 <'/0$ $ ( 1 #)-%
1 %0( 1 .# ( .') ' .. '#- .% %) //8 1 %0( $ ( 1 #) 0# (%0( ' #) ) $ (
// &-&-. ## ')1 .#%9 %0') % ' 0&/-. 9 .-&&/ %9 #) (1 * //% #' %) // 8 -.%# // $ 8; #)
.#( '# ( % & ( #) &-&-. * (+ .$ . % & ( # & ;1 .# %) // 8 1 $ ( %0') * (+
B * : (9 <# .%- . . %0') ## ')1 .#% %0') % : .#% .$ $( -.% * -//8 1 %0( $ .$ & -$ %
&&/-' 8/ (#) ( %& '#-: %-> .$ ' # (; &-&-. , : /: %
8(-' #- . 1 -#( 8 .$9 ' .' .#(-' .$ '' .#(-' ( $0' (% 8(-' # $ ( 1 &-& % %0&&/- $ 8;
* . (9 .$ 8(-' #- . / . % ( 1 &/ # % %0&&/- $ 8; * . (9* -//8 & -$ # ( %& '#-: 0.-#
( # % B * : (9 ( '#- . #) % -# 1 % * -//8 / . * -#) &-&-. #) ( %& '#-: %-> .$ .
% & ( # & ;1 .#* -//8 1 $ ( ( '#- . ) ( $0' (% * -//8 1 %0( $ .$ & -$ / . * -#)
#) &-&-. / ( $- 1 # (
% & ( # & ;1 .# * -// 8 1 $ ( 1 +-. &-& # &-& 8( .') ' .. '#- . '( %% % * -#) (
* -#) 0#( -. ('-. & $% .$ #) 0.-#( # % (&-&-. ( $ 1 $ # -.'/0$ //%0') * (+
8(-' #- .9 -.%# // #- . .$ ( 1 : / # 1 & ( (; %& /&- ' % #' # -$ ' .#( '# (=% * (+ %0')
% 8(-' #- .9 ( '#- .9 /0%)-. # %#-. 9 .$ #' * -//. -#) ( 8 1 %0( $ . ( & -$ % & ( # /;
) % 1 -% $ 1 $ # 8 -.'/0$ $ -. #) 0.-#( # % (&-&-.
4 B
C 8 : ( 0.$ (#- .D
)-% %& '- -' #- . %) //. #8 &&/-' 8/ ( * /$-. &-& /-. % ( #( .%& (# #- . /-50-$
& #( / 01 .$ #) (%-1 -/ (&( $0'#%
? 3
//* /$-. * (+9 50-&1 .#% (* /$-. 9) ##( #1 .#9 #) ( 0<-/- (; 0.'#- .% .$ #)
* /$-. & (% .. / %) // 1 # #) ( 50-( 1 .#% #) / # %# $-#- .% #) // * -.
<& '# $ %# .$ ($% .$ &( ' $0( % 0./ %% #) (* -% %& '- - $ -. #) 4 /$-. %& '- -' #- .
') (# .$ #) # ').-' / . # % ## ') $ . #) ' % ' . /-'#-. ( 50-( 1 .#%9 #)
( 50-( 1 .#% 1 .#- . $ -. * /$-. %& '- -' #- . ') (# , ').-' / # % %) // 8
&&/-' 8/
D ) 1 -' / / .# .$ #( / 01 -. (; -&-. 3
8D ) .$- . -/ ( 0/ #- .%
" 3
4 "
) ' .#( '# ( %) // &( :-$ 9 # )-% * . <& .% 9 // #) * /$-. ' .%01 8/ % . ' %% (;
( #) < '0#- . #) @ 8 %0') % / '#( $ %9 -// ( * -( %9 <; .9 ' #;/ . 9 ( . #'9
.$ #) % %) 0/$ 8 (#) &&( : / #) . -. ( -. ') (
) * /$-. / '#( $ % .$ -// ( * -( % %0&&/- $ 8; #) .#( '# ( %) // ' . (1 # #)
'/ %% %& '- - $ -. #) * /$-. %& '- -' #- .% ') (# ) 1 # (- /% %) // 8 #) 1 +
&&( : $ 8; #) . -. ( -. ') (
/ '#( $ 50 /- -' #- . # %#( ' ($% %) 0/$ 8 %081 -## $ % & (#) <)-8-#6 C ## ') $D -.
( %& '# #) / '#( $ % # %# $ 8; #) .#( '# (9 ( 8# -.-. #) &&( : / #)
. -. ( -. ') (
) ' .#( '# ( %) // %081 -# 8 #') # %# ' (#- -' # %9 ( 1 #) / '#( $ 1 .0 '#0( (%9
-:-. $ # -/% &);%-' / .$ ') 1 -' / # %#% ' ((- $ 0# 8; #) 1 9 ( ') 8 #')
/ '#( $ # 8 0% $
// / '#( $ % %) // 8 &0(') % $ -. % / $ ' .# -. (% .$ %# ( % &( & (/; # &( : .#
$ # (- ( #- . ) / '#( $ % ( 1 : $ ( 1 #) ' .# -. (% %) //8 + &# -. ) /$-. : .%
# # 1 & ( #0( % ( ' 1 1 .$ $ 8; #) / '#( $ 1 .0 '#0( ( K 0# #) : . #-1 K .
/ '#( $ %9 8 ( #) ; ( ' .%01 $ %) // . # <' $ #) /-1 -#% ( ' 1 1 .$ $ 8; #)
/ '#( $ 1 .0 '#0( ( ) / '#( $ % %) //8 ) .$/ $ * -#) ' ( # : -$ .; $ 1 #
#) /0< ' : (-.
// / * );$( . #0& / '#( $ % %) //8 ( 8 (+ $ # 22 ( ) 0( 1 -.-1 01 .$
2
%# ( $ -. : .% + &# # !2 22 8 ( 0% ' 1 1 .$ #- .% #) / '#( $
1 .0 '#0( (%) //8 // * $ - : -/ 8/
) / '#( $ %9 -// (* -( % .$ /0< 0% $ %) //8 ( ( 1 (0%#9 -/9 ( % 9 (#) .$ #) (
( - . 1 ## (* )-') '##) 50 /-#; * /$-.
! 0. %# . / '#( $ % 0% $ %) //' . (1 # %& '- -' #- .
B ? 3
4 3
! / .-.
) .$% # 8 * /$ $ %) //8 &( & (/; '/ . $ # ( 1 : & -.#9 -/9 ( % 9(0%#9 <-$ %9
% .$9 (#) .$ #) ( ( - . 1 ## ( ) .$% %) //8 ' 1 &/ # $(; 8 ( #) * /$-.
' 1 1 .' %
8 . ' 1 &/ #- . ') (0.9 '( # (%9 * /$-. -(( 0/ (-#- %9 %/ #' 9 %) //8 ( 1 : $ 8;
(-.$-. .$ ')-% /-. 4 -( 8(0%) % 0% $ ( '/ .-. %# -./ %% %# / @ -.#% %) // ) :
%# -./ %% %# / * -( % .$ #) (-.$-. * ) /% 0% $ ( (-.$-. %# -./ %% %# / %) // 8
%0-# 8/ #;& & ( # (-.$-. * ) /% .$ * -( 8(0%) % %) 0/$ 8 0% $ (' (8 . %# /%
.$ %# -./ %% %# /
H " ? 3
2 4 B 3
2 ) & (#% 8 -. * /$ $ .$ #) * /$-. & (% .. /%) 0/$ 8 $ 50 # /; &( # '# $ ( 1
( -. .$ %#( . * -. % . #) 8% .' %0') &( # '#- . . * /$-. %) // 8 ' ((- $
0#
2 0(-. - /$ * /$-. 0%-. 4 &( ' %%9 & (#-'0/ ( ' ( %) // 8 < ('-% $ # &( : .#
.; -('0(( .# '#-. #) * /$-. &( ' %%
4 B L 3
# %%
D # & %% %) // 8 1 $ * -#) / '#( $ %, -// ( * -( % ( ' 1 1 .$ $ -. #) * /$-.
%& '- -' #- . ') (# ( -// # * /$-. ( # * /$-. %) // 8 $ . * -#) ' .%01 8/ %
( ' 1 1 .$ $ ( -// ( & %% % ) &( ( 8/ %-> #) / '#( $ % -% 11
$- 1 # (C 4 D80#-. .; ' % . # ( # (#) . 11 C 2 4 D
8D &* ($ # ').-50 %) //8 $ &# $ (* /$-. &-& ) /$ -< $ * -#) -#% <-% ) (-> .# /
'D ) ( # & %% 80## @ -.#% %) 0/$ 8 < '0# $ % % # ')- : 0// & . #( #- . * -#)
' 1 &/ # 0%- . #) ( # $ % 4 /$ &( @ '#- . -.%-$ #) &-& %) //. # <' $
1 1 9* ) ( : (9NNN %& '- - $ 8; #) &&/-' 8/ ' $
$D .; $ :- #- . $ %-( $ ( 1 #) ( ' 1 1 .$ $ * /$-. # ').-50 .$ / '#( $ %
-.$-' # $ -. #) * /$-. %& '- -' #- . ') (# %) 0/$ 8 $ &# $ ./; # ( 8# -.-.
<&( %% &&( : / #) . -. ( -. ') (
D 4 /$-. %) //8 0.-.# ((0&# $
D 4 )-/ #) * /$-. -% -. &( ( %% ' ( %) 0/$ 8 # + . # : -$ .; +/-.$ 1 : 1 .#
#) ' 1 & . .#%9%) '+%9:-8( #- .% .$ %#( %% % # &( : .# ''0(( .' * /$ '( '+%
D .-. %) //. #8 0% $
J -.# 1 &/ #- .
D J -.# %) // 8 ' 1 &/ # $ 0%-. #) '/ %% / '#( $ %9 ( ' 1 1 .$ $ -. #) 4 /$-.
& '- -' #- . ) (# -> #) / '#( $ %) // . # <' $ 1 1 -. $- 1 # ( ( %# -./ %%
%# / .$ // ; %# /% 0% $ (/ * # 1 & ( #0( &&/-' #- .%
8D * * /$% 8 $% %) //. #8 %# (# $ ##) % 1 & -.#-.
'D 0## @ -.#% %) //8 ' 1 &/ # $ * -#) ' : ( / ; ( #) # * 0/$ '# $ 0%- . # #) @ -.#
$ % .$ ( $0 /. #') ( %0( '
$D ') * /$ @ -.#%) 0/$ ) : * (+1 . /-+ -.-%)
D 4 /$ -$ .#- -' #- . * (+ %) // 8 %# 1 & $ '/ (/; # ') @ -.# @0%# $@ ' .# # #) * /$
" # /%# 1 &-. %) //. #8 0% $ % %# .$ ($ 0-# 8/ & -.#%) //8 0% $ . #)-. * //&-& %
(-$ .#- -' #- .
D & -.#-. %) //8 $ . 0.#-/#) * /$ @ -.#) % 8 . &&( : $
-%%-1 -/ (* /$%
4 ) ( * /$% ( # 8 &( $0' $ 8 #* . ' (8 . %# /% .$ // ; %# /%9&( ) # .$ & %#* /$
B # ( #1 .# ( 50-( 1 .# %) // 8 #) % %& '- - $ ( ' (( %& .$-. // ; %# /% .$
/ '#( $ % %) //' (( %& .$ # 4 2 , 2 ! #;& (* /$% 8 #* . #* $-%%-1 -/ ( ( "
/ * // ; %# /%9 &( ) # .$ & %# * /$ ) # #( #1 .# %) //8 #) % %& '- - $ ( )- ) ( // ;
%# / .$ / '#( $ % 0% $ %) // ' (( %& .$ # #) % %& '- - $ ( %# / / * ( // ; ' .# .#
( ' (8 . %# / ( // ; %# / # %# -./ %% * /$%9 0% / '#( $ % 2H , 2, - (
%) // 8 1 $ ) * /$-. &( ' $0( 9 / '#( $ %, -// ( * -( % # 8 0% $9 &&( : $ 8; #)
. -. ( -. ') (
B " 3
( ) #-.
D * /$-. %) //8 & ( (1 $ * -#) 0#&( ) #-. #) @ -.## 2O C 2O D* ) . #) 1 8- .#
# 1 & ( #0( -% 2O .$ 8 / *
8D ( ) #-. ( 50-( 1 .#% ( #) : (- 0% 1 # (- /% %) //8 % & ( #) * /$-. %& '- -' #- .
') (# ## ') %
'D ( ) #-. %) // 8 & ( (1 $ 0%-. ( %-%# .' ( -.$0'#- . ) #-. 1 #) $% ( ) #-.
8; % 80(. (%90#-/->-. <; ' #;/ . ( <; &( & . % 1 -<#0( %9* -#) . 0#( / / 1 1 ;
/% 8 ' ((- $ * ) . & (1 -## $ 8; #) . -. ( -. ') (
$D ( ) #-. %) // <# .$ 0.0.- (1 /; # # / %# #)( #-1 % #) #)-'+. %% #) @ -.#9 80#
. #/ %% #) . 2 1 1 9 . 8 #) %-$ % #) * /$
D ( ) #-. # 1 & ( #0( %) // 8 1 -.# -. $ : ( #) * ) / / . #) #) @ -.# $0(-.
* /$-. 1 & ( #0( -.$-' #-. ' (; .% #) ( # 1 & ( #0( -.$-' #-. $ :-' % %) //8
&( :-$ $ 8; #) ' .#( '# (# ') '+ #) # 1 & ( #0(
%#B #-.
.'% // ; %# / 1 # (- /% %0') % ( "' %# /%9 - #) %# 4 B # 1 & ( #0( -% . #
& ( (1 $ -1 1 $- # /; # ( * /$-. 9 #) * /$ @ -.# .$ $@ ' .# &-& 9 # / %# 21 1 .
-#) ( %-$ * /$9 %) //8 0.- (1 /; ) # $ # 22O )-% # 1 & ( #0( %) //8 1 -.# -. $
( ) 0(% 1 -.-1 01 9#) . * ( && $ -. %8 %# % ( -.%0/ #-. 8 ( // * -. -## ' /# ( 1
# 1 & ( #0( 9 & %#* /$ B # ( #1 .# % %& '- - $ -. #) 4 /$-. & '- -' #- . ) (# %) //8
' ((- $ 0#/ # ( .
%#* /$ B # ( #1 .#
D %# * /$ B # ( #1 .#9* ) ( : ( ( 50-( $ ( @ -.#% 8 #* . &-& %9 &-& % .$ -##-. %9
&-& 8 $; .$ %0&& (#% %) // 8 ' ((- $ 0# % & ( #) * /$-. %& '- -' #- . ') (#9
&&/-' 8/ ' $ % %# .$ ($% .$ #) -.%#(0'#- .% #) . -. ( -. ') (
8D ) ' .#( '# (%) //%081 -# (#) &&( : / #) . -. ( -. ') ( 9* //8 ( ' ((;-.
0# '#0 /B # ( #1 .#9 #) $ # -/% #) & %# * /$ B # ( #1 .# &( ' $0( % & (
<)-8 ## ') $9 #) # ) &( & % % # $ &# ( ') #) 1 # (- / %% 1 8/;, & (#
-.: /: $
'D %# * /$ B # ( #1 .# %) //8 $ . -. 0(. ' ( 8; 0%-. .$ / '#(-' ( %-%# .' (
-.$0'#- . ) #-. 50-&1 .#9 % $ '-$ $ 8; #) . -. ( -. ') (
$D 4 )-/ ' ((;-. 0# / ' /& %# * /$ B # ( #1 .#9 # ').-50 &&/-' #- . ) # 1 0%#
.%0( 0.- (1 # 1 & ( #0( ## -.1 .# # // & -.#% #) & (#- . 8 -. ) # #( # $
( %) // 8 # + . # .%0( #) # * -$#) ) # $ 8 .$ : ( * )-') %& '- - $ & %# * /$
B # ( #1 .# # 1 & ( #0( ## -. $ -% # / %# #) # %& '- - $ -. #) ( / : .# &&/-' 8/
%# .$ ($%,' $ %
D )( 0 ) 0# #) ';'/ ) # #( #1 .#9 #) & (#- . 0#%-$ #) ) # $ 8 .$ %) // 8
%0-# 8/; * ( && $ 0.$ ( -.%0/ #- . % % # : -$ .; ) (1 0/# 1 & ( #0( ( $- .# # #)
<& % $ %0( ' &-& ( #)-% &0(& % # 1 & ( #0( # #) <& % $ %0( ' &-&
%) 0/$ . #8 // * $ # <' $ 22O
D ) # 1 & ( #0( ## -. $ 8; #) & (#- . 0.$ () ##( #1 .#%) //8 ( ' ($ $ 8; 1 .%
#) (1 ' 0&/ &;( 1 # (% $ 50 # .01 8 ( #) (1 ' 0&/ % %) 0/$ 8 ## ') $ #
#) &-& $-( '#/; # 50 //; %& ' $ / ' #- .% / . #) & (-&) (; #) &-& @ -.# )
1 -.-1 01 .01 8 ( #) (1 ' 0&/ % ## ') $ & ( @ -.# %) // 8 0&# KK$- 9 0&# 2KK
$- .$ ( KK $- .$ 8 : B * : (9 #) . -. ( -. ') ( ' . -.'( % #)
( 50-( $ 1 -.-1 01 .01 8 ( #) (1 ' 0&/ % # 8 ## ') $ - 0.$ . ' %% (;
D 0# 1 #-' # 1 & ( #0( ( ' ($ (% * )-') ) : 8 . %0-# 8/; ' /-8( # $ %) 0/$ 8
1 &/ ; $ ) ' /-8( #- . ') (# ') ( ' ($ %) 0/$ 8 %081 -## $ # #) . -. ( -.
') ( &(- ( # %# (#-. #) B # ( #1 .# & ( #- .% .$ )-% &&( : / %) 0/$ 8
8# -. $
)D 1 1 $- # /; . ' 1 &/ #- . #) B # ( #1 .#9 #) & %# * /$ B # ( #1 .#
') (#%,( ' ($% / . * -#) #) ) ($. %% # %#( %0/# $ . #) * /$ @ -.#%9* ) ( : ( ( 50-( $
% & ( #) 4 /$-. & '- -' #- . ') (#9 %) // 8 %081 -## $ # . -. ( -. ') ( ( )-%
&&( : /
-D ') @ -.# %) // 8 ( . -$ .#- -' #- . .01 8 ( * )-') %) // 8 1 -.# -. $ -. #) &-&-.
%+ #') # 8 &( & ( $ 8; #) .#( '# ( ) @ -.#-$ .#- -' #- . .01 8 (%) 0/$ && ( .
#) ' (( %& .$-. & %# * /$ B # ( #1 .# ') (#% ) ') (# ' .# -.-. #)
-$ .#- -' #- . .01 8 (% .$ &-&-. %+ #') %) // 8 %081 -## $ # #) . -. ( -. ') ( -.
%0-# 8/ /$ (%
B 4 J
//* /$ @ -.#% %) //8 ( ( 1 $) ( .#* /$ %& ## (% %/ 9%* ( 9$-(# ( ( - . 1 ## ( )-% ' .
8 ')- : $ 8; 8(0%)-. ( %# -./ %% %# /9 8(0%) % * -#) ./; %# -./ %% %# / 8(-%#/ % %) 0/$ 8
0% $
. (/
'D .#( '# (%) //-.#-1 # %0 -'- .#/; -. $: .' #) ' 1 1 .' 1 .# 50 /- -' #- .
# %#%9 * /$-. * (+% .$ '' &# .' # %#% # . 8/ #) * . (K% -.%& '# ( # 8
&( % .## %0& (:-% #) 1
.$ %) //( / % #) &( ' $0( ( 50 /- -' #- . # %#% ) &( ' $0( 50 /- -' #- . # %#
%) //8 ' ((- $ 0#8; #) .#( '# ( #)-% * . <& .% ' 1 &/ # % # # %#( %0/#%
-. (1 # % & ( <)-8-#- . ## ') $ %) //8 %081 -## $ # #) * . (K% -.%& '# (
4 /$ (K% L 0 /- -' # .
$- ( &)-' < 1 -. #- .
D ) $- ( &)-' < 1 -. #- . &( ' $0( # 8 $ &# $ %) // 8 %081 -## $ 8; #)
.#( '# ( % & ( <)-8-# .$ %) //8 # &&( : $ 8; #) * . (K% .%& '# (&(- (
# 1 &/ ;1 .# ) ( $- ( &)-' # ').-50 .$ &( ' $0( $ &# $ %) // ' . (1
# #) ( 50-( 1 .#% 1 .#- . $ -. (#-'/ 9 % * // (#-'/ C H 9 D "
' F ) L % .%-#-:-#; 8# -. $ %) //8 50 /# ( 8 ## ( #) . #) ( 50-( 1 .#%
1 .#- . $ -. # 8/ .$ # 8/ (#-'/ " ' F (%-. / * // .$
$ 08/ * // ( $- ( &); ( %& '#-: /; 0(' %-$ &( ' $0( ,# ').-50 )
'' &# 8/ /-1 -#% $ '#% .$ ( 1 : / $ '#% %) //8 % & (#) ( / : .#' $ %
8(-' #- . ) ' .#( '# ( %) // 8 ( %& .%-8/ ( ' ((;-. 0# $- ( &);9
( '#- -' #- . $ '#% .$ ( ( $- ( &); * /$% ( & -( $,( '#- - $
8D ) <# .# $- ( &); %) // 8 % & ( %& '- -' #- .% # 8 %0&&/- $ # #)
.#( '# ( ( * /$% 8 #* . $-%%-1 -/ ( 1 # (- /%9 #) <# .# $- ( &)-'
< 1 -. #- . (#) 1 # (- /% 8 -. * /$ $ 4 ) ( : (( .$ 1 $- ( &); -% ' // $
( -. & (#-'0/ ( &-&-. '/ %%9 #) $-%%-1 -/ ( 1 # (- /% * /$ @ -.# %) // %% .#- //; 8
-.'/0$ $
'D $- ( &)-' < 1 -. #- . %) //8 ' ((- $ 0#0%-. 7 $- #- .9 1 1 ( ; % 0(' %
1 ; 8 0% $ -. &/ ' 7 ( ; * -#) #) &&( : / #) * . (K% -.%& '# (
$D ) ' .#( '# ( %) // 0/-// // #) %# #0# (; % #; ( 50-( 1 .# * )-/ ) .$/-. 7 ( ;
.$ 1 1 ( ; 50-&1 .#%
D ) @ -.#% ( $- ( &); %) // 8 % / '# $ 8; #) * . (K% .%& '# ( .$ #)
$- ( &); %) //8 & ( (1 $ -. )-% &( % .' ) ' .#( '# ( %) // 0(.-%) //#)
( $- ( &)% # #) * . (K% .%& '# ( -1 1 $- # /; # ( &( ' %%-. ) $ # -/%
#) ( $- ( &)% / . * -#) #) @ -.# -$ .#- -' #- . .01 8 ( %) //8 $0/; .# ( $ -.
( -%# ( .$ %- . $ 8; #) .#( '# ( .$ %) // 8 %081 -## $ # #) * . (K%
.%& '# ( ( &&( : /
D ) ' .#( '# ( %) //&( :-$ #) .%& '# ( //#) . ' %% (; '-/-#- % #%-# %0') %
$ (+ ( 1 * -#) ' .#( // $ # 1 & ( #0( 9 -/1 :- * ( #' # . 8/ )-1 #
< 1 -. #) ( $- ( &)%
D 4 ) ( ( .$ 1 ( $- ( &); -% %& '- - $9 #) -(%# * /$ ') * /$ ( %) // 8
' 1 &/ # /; ( $- ( &) $ . #) ' % &-& %-> % KK .$ 8 / * 9 #) -(%# #*
* /$% %) // 8 ' 1 &/ # /; ( $- ( &) $
)D ( ') * /$ & ( (1 $ 8; * /$ (9 0.$ 0. '' &# 8/ #* $$-#- . / ') '+%
%) 0/$ 8 ' ((- $ 0# . * /$% & ( (1 $ 8; #) % 1 * /$ ( )-% & ( #- . -%
-# ( #-: .$ #) &( ' $0( ( $- ( &)-. #* $$-#- . / * /$% ( ') * /$
$ 1 $ 0.% #-% '# (; %) // 8 ' .#-.0 $ #-// %0') #-1 #) # #) #* ' .% '0#-:
* /$% % #-% '# (; ( 0.$ ( : (; $ '#-: * /$
B ($. %% %#
B ($. %% ( 50-( $ ( * /$% %) // 8 % & ( #) * /$-. %& '- -' #- . ') (# C ## ') $D
B ($. %% # %#-. %) //8 ' ((- $ 0#8; F-'+ (% B ($. %% %# ($0(-. * /$-. &( ' $0(
50 /- -' #- . . // #) (' % % ) ($. %% # %#-. 1 ; 8 ' ((- $ 0#8; F-'+ (%9 (-.. /9 (
/$; ) ($. %% # %# ( % ( $ 8; #) * . (K% .%& '# (
! ( %#%
B ;$( %# #-' .$ &. 01 #-' # %#% %) //8 & ( (1 $ % & ( #) ( 50-( 1 .# / -$ $ * . 8;
( %& '#-: /0%)-. .$ %#-. %& '- -' #- ., &&/-' 8/ ' $ % # $ 1 .%#( # #)
% 0.$. %% #) * /$% ) # %#% %) // 8 ' .$0'# $ # ( 0/-//-. #) ( 50-( 1 .#
:-%0 / < 1 -. #- .% ( $- ( &); #' 9 .$ # ( #) .#-( * (+ ) % 8 . ' (#- - $ 8; #)
* . (K% -.%& '# (# 8 -# (8 -. %08@ '# $ # %0') # %#%
2 4
D '#% %' (# -. $9#)( 0 ) #) -.%& '#- . 1 #) $%9* )-') ( 8 ; .$ '' &# 8/ /-1 -#% %) //
8 ( 1 : $ # (#) @ -.#-% ' 1 &/ # /; ( $- ( &) $ 8; #) &( ' %% ')-&&-. .$ (-.$-.
8D 4 ) . #) .#-( @ -.# -% @0$ $ 0. '' &# 8/ 9 #) * /$-. %) // 8 ' 1 &/ # /; '0# .$ #)
$ % 8 %0-# 8/; &( & ( $ % & ( ( 50-( $ /- .1 .# # / ( .' % ) ( * /$ $ @ -.# %) //
-. 8 < 1 -. $ // * -. %# .$ ($ &( '#-' %
'D ( & -(%) //8 ' ((- $ 0#* -#) 0#&(- (& (1 -%%- . #) * . (K% -.%& '# (
$D & -(% .$ , ( * (+ $ '#-: * /$% %) //8 $ . -. #-1 # : -$ $- -'0/#- % -. 1 #-.
#) ' .%#(0'#- . %') $0/ %
2 " " C BD
SPECIFICATION
FOR
WELDING
!
" #
& #
'
()* *+ ,)), -) . , / 0* ) 12 .2 *( + 3 12). 0, 04 . *- 1+)+). *5*- 6
)11 -3 12* 097.,-) . *1)+ . 1 . *;47-- .2 * ,< -3 12 )--). *80 ). 0,). + 2*8 -,
., * .5 / 0) -) . 4 -3 . -( +0 /)*) .* -( , 2 * .2 -( *+ ,)), -) .* )/ . 4 1 3 -( 1 - 0
*( 11+0 / )1
12). +0 , 270 @7 1)), -) .* 0 11+)+). A, +--( * 7.2 0-( +70/) 3 # 8*( 114 * + 0-(
1 - *- 2)-) . - .2 02 0 3 12). +)+ 1). * .2 0 1 - 2 ,)1)-) *8 * ,-) . B ( , .-0 ,- 0
*( 11*746 )--( 3 12). +0 , 270 - 00 , )+- 3 0< 02 0 3 . 0).*+ ,- 0*( 110 /) 3 8,( ,< .2
++0 / 3 12). +0 , 270 - 0, .27,-). *7,( - *-* * 0 . , ** 05 -*( 114 -( 0 *+ .*)4)1)-5
, .-0 ,- 0- 00 . .2 , 005 7-*7,( - *-* -()* 3 . , *-*
3 12 0*( 114 + 06 )-- 2 - 3 0< 3 )-( 7--( + ** **) . )2 .-)), -) . , 02 3 12 0)* 7.2
- + 0 06 -5+ 3 12). 0 ). + *)-) . 0 . 6 - 0) 1 0 3 (),( ( )* . - @7 1)) 28 ( *( 114
2 4 00 2 0 6 2 ). 70-( 0 3 0< 11*7,( 3 12* *( 114 ,7- .2 0 2 . 45 -( , .-0 ,- 0 -()* 3 .
, *-
" #
. . 0 1-()* *+ ,)), -) . *( 114 7* 2 ). 3 12). -( , 04 . *- 16 - 0) 1* ( /). *+ ,)) 2 - .*)1
*-0 . -( &8&&& +*) 01 **
1 ,-0 2 *:
( , .-0 ,- 0*( 11*746 )-6 .7 ,-70 0* , 0-)), - * 0 ,( 4 -,( 1 ,-0 2 * *7++1) 2 45 ()6
& #
.2 0 + 0 -) .
1 .).
( .2* - 4 3 12 2 *( 114 +0 + 015 ,1 . 2 11+ ).-8 )18 0 * 807*- .2 A)2 ). . 0 1*( 114
0 6 / 28 * 3 11 * 11 0-(8 * .2 0 .5 -( 0 6 - 0) 13 (),( , 712 4 ( 06 71- -( 3 12). .2*
*( 114 - - 115 205 3 ( . 3 12 2
2)0- 0 2 40)* 3 )114 + 06 )-- 2 ). -( +)+ 1). 0) 0 - 1) .6 .-8 -( ).*)2 ,( 9 ).- *( 114
2 @7 - 15 *3 44 28 )-( 0 45 7* 1 -( 0 , ./ * 4 1- 2)*, +0 + 0 2) 6 - 0 0 -( 0 )6 +0 / 2
6 -( 2
1) .6 .- .2 + ,).
0#7--' ).-*:
0 )11 -3 12*
'
1 2 3 4 5 Contractor HPCL
TANK NO.
JOB NO. 1
DESIGNED BY
Calibration Chart
Location
Tank No. :9
Product : MS
Calibrated On : 02.02.2007.
Notes :
The level of Datum plate of the tank immediately below the Gaugewell pipe should be
taken as zero depth in the calibration chart.
This calibration chart is valid upto 01.02.2012 or even earlier to the date of making
any addition or alteration in the tank or change its position.
Calibration chart table is set out to show litres at the intervals of 5.0 cms .Use fraction
part table for immediate dips to get accurate results.
Certified that calibration upto cone top for Bottom plate was physically done by filling water
through water meter.
Page 1/12
Calibration Chart Tank No.
Ownres Name : Hindustan Petroleum Corporation Limited.
Dip In Volume In Dip In Volume In Dip In Volume In Fractions
Cms. Litres Cms. Litres Cms. Litres Cms. Litres
0 6233 250 945026 500 1894985 0.1 380
5 16033 255 964027 505 1913983 0.2 760
10 33610 260 983027 510 1932981 0.3 1140
15 52190 265 1002027 515 1951979 0.4 1520
20 71191 270 1021028 520 1970977 0.5 1900
25 90191 275 1040028 525 1989975 0.6 2280
30 109187 280 1059029 530 2008973 0.7 2660
35 128190 285 1078029 535 2027972 0.8 3040
40 147198 290 1097029 540 2046971 0.9 3420
45 166208 295 1116030 545 2065970 1.0 3800
1 2 3 4 5 6 7 8 9
Avg.Ext.Circum. 3.1428 69.2200 69.2180 69.2010 69.1900 69.1860 69.1770 69.1620 69.1630 69.1580
Thickness 14.0 14.0 12.0 10.0 8.0 8.0 6.0 6.0 6.0
Thick 2 py t 0.087998 0.087998 0.075427 0.062856 0.050285 0.050285 0.037714 0.037714 0.000000
V.Jts. 0.012 0.012 0.012 0.012 0.012 0.012 0.012 0.012 0.012
Total Dedudction 0.099998 0.099998 0.087427 0.074856 0.062285 0.062285 0.049714 0.049714 0.012000
Avg.Int.Circum. 69.1200 69.1180 69.1136 69.1151 69.1237 69.1147 69.1123 69.1133 69.1460
Radius 6.2856 10.99656 10.99625 10.99554 10.99579 10.99715 10.99572 10.99534 10.9955 11.0007
Lit./5 Cms. 21.993 19002.06 19000.96 18998.53 18999.39 19004.10 18999.16 18997.82 18998.37 19016.36
CDW 0.576 19001.49 19000.39 18997.95 18998.82 19003.53 18998.58 18997.24 18997.79 19015.78
Lit / Cms. Avg. 3800.257 3800.297 3800.077 3799.590 3799.763 3800.706 3799.716 3799.449 3799.559 3803.157
Shell Height 201 200 150 150 152 151 150 151 150
C. Height 25.5 175.500 175.5 375.5 525.5 675.5 827.5 978.5 1128.5 1279.5 1429.5
Cap.Of shell 666952 760015 569939 569964 577707 573757 569917 573733 570474
Page 4/12
Addition , Deduction Tank No.
0 0-5 5.-10 10.-15 15.-20 20.-25 25-30 30-35 35-40 40-45 45-50
6233 9800 17577 16680 19001.487 19001.487 19001.487 19001.487 19001.487 19001.487 19001.487
1900 -0.236 -0.788 -0.788 4.700 1.270 3.820
-1.329 1.630 3.270 -0.788 5.220 4.240
1.650 3.300 3.270 -0.788 5.220
0.388 3.880 3.300 3.270 -0.788
-4.429 -4.429 3.880 3.300 3.270
-3.250 -3.610 -4.429 3.880 3.300
-3.610 -4.429 3.880
-3.610 -4.429
-3.610
6233 9800 17577 18580 19001.487 18999.922 18996.688 19003.110 19007.810 19009.600 19016.390
50-55 55-60 60-65 65-70 70-75 75-80 80-85 85-90 90-95 95-100 100-105
19001.487 19001.487 19001.487 19001.487 19001.487 19001.487 19001.487 19001.487 19001.487 19001.487 19001.487
4.240 4.240 4.240 4.240 4.240 4.240 4.240 4.240 4.240 4.240 4.240
4.240 4.240 4.240 4.240 4.240 4.240 4.240 4.240 4.240 4.240 2.970
5.220 5.220 5.220 5.220 5.220 5.220 3.133 -11.400 -20.360 -20.360 -20.360
-0.788 -0.788 -0.788 -0.788 -0.788 -0.788 -0.236 -0.970 -0.970 -0.970 -0.970
3.270 2.940 3.880 1.940 -4.429 -0.490 -0.970 -4.429 -4.429 -4.429 -4.429
3.300 0.990 -4.429 -4.429 -3.610 -4.429 -4.429 -3.610 -3.580 -6.400 -6.400
3.880 3.880 -3.610 -3.610 -3.610 -3.610 -3.610 -3.610 -3.610
-4.429 -4.429
-3.610 -3.610
19016.810 19014.170 19010.240 19008.300 19006.360 19005.870 19003.855 18989.558 18977.018 18974.198 18972.928
105-110 110-115 115-120 120-125 125-130 130-135 135-140 140-175 19001.4870 680-825 19003.5286
19001.487 19001.487 19001.487 19001.487 19001.487 19001.487 19001.487 175-180 19000.4950 825-830 19001.0550
0.424 -20.360 -20.360 -20.360 -20.360 -20.360 -8.960 180-375 19000.3870 830-975 18998.5800
-20.360 -0.490 -4.429 -4.429 -4.429 -4.429 -1.950 375-380 18998.1935 975-980 18998.1795
-0.970 -4.429 -6.400 -6.400 -6.400 -6.400 -2.820 380-525 18997.9521 980-1125 18997.2449
-4.429 -6.400 525-530 18998.7285 1125-1130 18997.4100
-6.400 530-675 18998.8160 1130-1275 18997.7947
-2.890 675-680 19003.0585
Page 5/12
Hindustan Petroleum Corporation Limited. Tank No.
Discription
Dip Pipe 29.21 cms dia 0.27 Litres / 5 cms Comman dead wood
0.54 for 2 nos.
Temp. Sensor Pipe 2" 0.036 Litres / 5 cms comman dead wood
Central Roof drain pipe 0.7229 3.61 Ltr / 5 cm - 25.5 to 109 cms.
36.66 legth
Pipe inlet nozzle 47.5x28 1.04458 5.22 Ltr / 5 cm + 35.5 to 83.0 cms.
Pipe inlet nozzle 29*29 0.6605 3.3 Ltr / 5 cm + 27.5 to 56.5 cms.
Pipe inlet nozzle 32*26 0.6534 3.27 Ltr / 5 cm + 27.5 to 59.5 cms.
Pipe inlet nozzle 38*26 0.7759 3.88 Ltr / 5 cm + 29.5 to 67.5 cms.
Leg support
43 nos 4" sleeve 0.03 6.4 Ltr / 5 cm - 23.5 to 137.2 cms.
Pg 6/12
Hindustan Petroleum Corporation Limited Tank No.
Mathematical Computation
we will deduct 2 nos. gauge well pipe and 1 no temp sencor pipe throuout shell ht by 0.576 lit / 5 cms.
18999.922 Lit / 5 cm
18996.688 Lit / 5 cm
19003.110 Lit / 5 cm
Pg 7/12
Hindustan Petroleum Corporation Limited Tank No.
From 40 to 45 cms 19001.487 Lit / 5 cm
Addition for manholes 1.270 Lit / 1.5 cm
Pipe inlet 18" 5.220 Lit / 5 cm
Trough 2nos. -0.788 Lit / 5 cm
Pipe 12" 3.270 Lit / 5 cm
Pipe 12" 3.300 Lit / 5 cm
Pipe 3.880 Lit / 5 cm
Deduction for legs support pipe -4.429 Lit / 5 cm
Deduction for roof drain pipe -3.610 Lit / 5 cm
19009.600 Lit / 5 cm
19010.240 Lit / 5 cm
Pg 8/12
Hindustan Petroleum Corporation Limited Tank No.
19008.300 Lit / 5 cm
19006.360 Lit / 5 cm
19005.870 Lit / 5 cm
19003.855 Lit / 5 cm
18989.558 Lit / 5 cm
Pg 9/12
Hindustan Petroleum Corporation Limited Tank No.
18977.018 Lit / 5 cm
18974.198 Lit / 5 cm
18972.928 Lit / 5 cm
18966.862 Lit / 5 cm
18969.808 Lit / 5 cm
Pg 10/12
Hindustan Petroleum Corporation Limited Tank No.
18970.298 Lit / 5 cm
18987.757 Lit / 5 cm
Pg 11/12
Hindustan Petroleum Corporation Limited.
2 No deduction for roof weight is to be made when the liquid is not touching the floating roof.
(a) when the roof is on LOW LEGS , the off float position is 137.2 cms. depth.
(b) when the roof is on HIGH LEGS, the off float position is 197.2 cms. depth.
3 (a) The fully floating position of the roof depends upon the gravity of the tank contents.
The following is the method for finding the fully floating positions of the roof.
Fully flaoting position of the roof = off float position in cms+Roof weight displacement in cms.
Roof weight in Kilograms 1
Roof weight displacement in cms. = --------------------------------------------- X----------------------------------------
Density of stock at tank temp. in Kgs./ Ltrs. Liters / cms. for the tank.
4 The roof is to be considered as partly submerged where the level is in between off float position and full float position
proportionate capacity due to roof weight is to be deducted when the roof is partly submerged.
DATA Gauge readings = 145.0 cms.Tank Temperature = 32 C Density of stock = 0.73 Kgs/ Ltrs.
69863
Now Approximate disp. = X (145-137.2) =
-------------------- 29648 Litres
18.38
Net volume for 145 cms at tank temperature = 546011-29648 516363 541015
Ltrs Ltrs.
5 Volume obtained when roof is partly submerged as in (4) above are not accurate . The roof should, therefore, be always kept
either fully floating or completely - Off float by pushing water at the bottom.
6 The roof should always be maintained on Low legs while the tank is in service.
Pg 12/12
Contractor
FABRICATION REPORT
SL. DIMENTION
DRG NO ITEM NO DESCRIPTION SIZE QTY Contractor HPCL REMARKS
NO. CHECKED
' ( (
(
! $
& # )& #
$ *
! " # $ ! " # $
" # %& " # %&
Page 1 of 2
TANK NO: P.O. NO:
DATE:
UNDULATION SIGNATURE
SL TYPE OF
JOINT NO THICKNESS OF ANNULAR DATE REMARKS
NO JOINT Contractor HPCL
JOINT
INTERNAL MATERIAL INSPECTION REPORT (IMIR)
JOB :
PO NO. :
PARTY:
Qty Area of
Date of Qty Recd Cumu Qty Date of Cumul Contractor HPCL
RGP No Batch No. Mfg Dt. Consumed Painting Location Painting in Balance
Receipt in Ltrs Recd Consmptn Consmptn Sign Sign
in Ltr Sqm
Contractor
POST WELDING INSPECTION READINGS FOR SHELL
PLUMB READING
Plumb Area 0 / 360º 45º 90º 135º 180º 225º 270º 315º
Top
Middle
Bottom
RADIUS READING in mm
Radial Area 0 / 360º 45º 90º 135º 180º 225º 270º 315º
Top
Middle
Bottom
DIA READING in mm
Top
Middle
Bottom
CIRCUMFERENCE READING in mm
PLUMB READING
Plumb Area 0 / 360º 45º 90º 135º 180º 225º 270º 315º
Top
Middle
Bottom
RADIUS READING in mm
Radial Area 0 / 360º 45º 90º 135º 180º 225º 270º 315º
Top
Middle
Bottom
DIA READING in mm
Top
Middle
Bottom
CIRCUMFERENCE READING in mm
Joint No 1 2 3 4 5 6 7 8
Top
Middle
Bottom
Date: P.O:
Tank No: Party:
Activity: - Job:
Date: P.O:
Tank No: Party:
Activity: - Job:
Date: P.O:
Tank No: Party:
Activity: - Job:
Date: P.O:
Tank No: Party:
Activity: - Job:
Date: P.O:
Tank No: Party:
Activity: - Job:
Date: P.O:
Tank No: Party:
Activity: - Cu slag Blasting and primer Job:
Plate Use Location:
Surface Preparation:
Sr. No. Plate Heat L*B*T Surface DFT Reading – primer Signature Remark
No. No. preparation name @ micron
on as per
standard
S/A 2 1/2
1 2 3 4 5 Contractor HPCL
Date: P.O:
Tank No: Party:
Activity: - Finish Paint Job:
Plate Use Location:
Surface Preparation:
Sr. Plate L*B*T DFT Reading – High Build Epoxy Signature Remark
No. No. MM Finish Coating @ 100 micron
1 2 3 4 5 Contractor HPCL
Date: P.O:
Tank No: Party:
Activity: - Job:
Plate Use Location:
Surface Preparation:
Sr. Plate Heat L*B*T Surface DFT Reading – Inorganic Zinc Signature Remark
No. No. No. MM preparatio Silicate Coating @ 65-70
n on as micron
per
standard
S/A 2 1/2
Contra HPCL
1 2 3 4 5
ctor
DATE:
PAGE :
TITLE
RECORDS REQD.TO
ACTION /EXTENT OF CHECK BY BE SUBMITTED /
SL.NO. ACTIVITY/ DESCRIPTION CHARACTERISTICS TO BE CHECKED TYPE / METHOD OF CHECK TYPE AND EXTEND OF CHECK BY JACOBS TYPE OF RECORD/BASIS
CONTRACTOR MAINTAINED BY
CONTRACTOR
A CIVIL WORK
1 Accuracy Measurement Detail Check 100 % Review records Yes Lab Reports/ Site Test
Calibration of Test / Measuring Instruments
2.a Construction Materials
Sand Physical properties Physical Tests Detail Check 100 % Review records Yes Lab Test/ Site Test
Soil Usability Visual Detail Check 100 % Review records Yes Site Report
Ready Mix Concrete Physical properties Physical Tests Detail Check 100 % Review records Yes Lab Test/ Site Test
Physical & Chemical Properties
Cement Review Records Detail Check 100 % Review records Yes Mfrs Test Certificate
Aggregrates Physical properties Physical Tests Detail Check 100 % Review records Yes Lab Test/ Site Test
Bitumen Physical Properties Review Records Detail Check 100 % Review records Yes Mfrs Test Certificate
Reinforcement Physical & Chemical Properties Review Records Detail Check 100 % Review records Yes Mfrs Test Certificate
Coating Thickness Review Records Detail Check 100 % Review records Yes Mfrs Test Certificate
b Construction Equipments
Excavator Workability Visual Detail Check 100 % Review records Yes Site Report
RTO Permission(If reqd.) Review Records Detail Check 100 % Review records Yes RTO Permits
Concrete Mixer Workability Visual Detail Check 100 % Review records Yes Site Report
Vibrators Workability Visual Detail Check 100 % Review records Yes Site Report
Trucks / Dumper Workability Visual Detail Check 100 % Review records Yes Site Report
RTO Permission(If reqd.) Review Records Detail Check 100 % Review records Yes RTO Permits
c Consumables
Water Chemical Properties Chemical Tests Detail Check 100 % Review records Yes Lab Test
DOC.NO.
DATE:
PAGE :
TITLE
3 Survey and Layout Dimensions Measurement Detail Check 100 % Check/witness Yes Joint Record
Hard Strata Visual Detail Check 100 % Check/witness at random Yes Site Report & Records
Check/witness at random
Sand filling Dimension Measurement Detail Check 100 % Yes Site Report & Records
Check/witness at random
Consolidation Phy.test Detail Check 100 % Yes Site Report
Check/witness
Ring Beam Dimension Detail Check 100 % Yes Site Report
Measurement & Visual
Review records
Pre-concreting Check Check list Detail Check 100 % Yes Site Report
Check/witness
Cube CR Strength Physical Tests Detail Check 100 % Yes Lab Test / Site Test
Check/witness
Bitumen carpet Dimension,Profile Measurement Detail Check 100 % Yes Site Report
Check/witness
Consolidation Visual Detail Check 100 % Yes Site Report
Check/witness at random
Apron work Dimension,Profile Detail Check 100 % Yes Site Report
Measurement & Visual
Check/witness at random
b Road work Dimension,Profile Detail Check 100 % Yes Site Report/Joint Records
Measurement & Visual
Consolidation Visual Detail Check 100 % Check/witness at random Yes Site Report/Joint Records
5 Safety Awarness / Implement & apply as per Review Detail Check 100 % Close Vigliance on Day to day basis Yes
records of periodic checks
norms of tools & tackles,Lifting
Machinery ,Electrical
equipments etc
6 As Built Drawing Dimensions with co-ordinates Review Submit Review records Marks up on Drawings
Drawings
DOC.NO.
DATE:
PAGE :
TITLE
B TANK CONSTRUCTION
1 Calibration of Tests/Measuring Instruments Accuarcy Measurement Detail Check 100 % Review records Yes Lab reports/Site Tests
2a Materials
Plates and Structurals Physical,Chemical Properties Review Records Detail Check 100 % Review records Yes Mfrs Test Certificate
Physical,chemical properties
Pipes for nozzles Review Records Detail Check 100 % Review records Yes Mfrs Test Certificate
Lab Test Certificate
Dimensions and surface quality
Detail Check 100 % Review records Yes Site Report
Measurements and Visual
Physical,chemical properties,
Flanges for nozzles Review Records Detail Check 100 % Review records Yes Mfrs Test Certificate
heat treatment
Lab Test Certificate
Lamination free Visual,UT(If reqd.) Detail Check 100 % Review records Yes Mfrs Test Certificate
Site Report
Pipe fittings Review Records Detail Check 100 % Review records Yes Mfrs Test Certificate
Physical,chemical properties,
heat treatment Lab Test Certificate
DATE:
PAGE :
TITLE
QUALITY ASSURANCE PLAN
RECORDS REQD.TO
ACTION /EXTENT OF CHECK BY BE SUBMITTED /
SL.NO. ACTIVITY/ DESCRIPTION CHARACTERISTICS TO BE CHECKED TYPE / METHOD OF CHECK TYPE AND EXTEND OF CHECK BY JACOBS TYPE OF RECORD/BASIS
CONTRACTOR MAINTAINED BY
CONTRACTOR
b Equipments
DG Set Workability Visual Detail Check 100 % Review records Yes Site Report,Callibration
Report /Fit Certificates
Hydra Workability Visual Detail Check 100 % Review records Yes Site Report,Load test
certificates
RTO Permission(If reqd.) Review Records Detail Check 100 % Review records Yes RTO Permits
Welding Rectifiers Workability Visual Detail Check 100 % Review records Yes Site Report,Calibration
Report
Grinding Machines Workability Visual Detail Check 100 % Review records Yes Site Report
Cutting Sets Workability Visual Detail Check 100 % Review records Yes Site Report
Erection Jacks Workability Lab Test/Visual Detail Check 100 % Review records Yes Site Report,Load test
certificates
Grinding Wheel Workability Visual Detail Check 100 % Review records Yes Site Report / MTC
Gases Workability Visual Detail Check 100 % Review records Yes Site Report
3 Fabrication Drawing Technical Requirements Review of Drawing Detail Check 100 % Review and Approve Yes Approved Drawings ED
318
Annular Plate Alignment,Fitup,Root gap Cleanliness Detail Check 100 % Check/witness at random Yes Site Report /ED316
Measurement / Visual
of joint
Dimension & Shape Detail Check 100 % Check/witness at random Yes Site Report /ED316
Measurement / Visual
Smoothness and reinforcement of Visual Detail Check 100 % Check/witness at random Yes Site Report /ED316
final weld
Internal flow Radiography Detail Check 100 % Review records Yes Site Report /ED328
DOC.NO.
DATE:
PAGE :
TITLE
Weld soundness Detail Check 100 % Check/witness Yes Site Report /ED316
Visual/Vacuum Box Testing
Fitment, dimension Detail Check 100 % Check/witness at random Yes Site Report /ED316
Annular plate to Bottom sketch plate Measurement / Visual
Weld soundness Detail Check 100 % Check/witness Yes Site Report /ED316
Visual/Vacuum Box Testing
Annular plate to shell plate Fitment,dimension Detail Check 100 % Check/witness at random Yes Site Report /ED316
Measurement / Visual
Weld soundness Detail Check 100 % Check/witness Yes Site Report /ED316
Visual/Oil-chalk Testing
Leak tightness LPT Detail Check 100 % Check/witness Yes Site Report /ED327
b Shell plates
Fabrication Dimension,Checking diagonal & Detail Check 100 % Review records Yes Site Report /ED316
Measurement / Visual
squaring
Fitment of weld Joints Detail Check 100 % Check/witness at random Yes Site Report /ED316
Alignment,Fitup,Root gap Measurement / Visual
Plumbness
Cleanliness of joint Visual Detail Check 100 % Check/witness at random Yes Site Report /ED316
Dimension & Shape Detail Check 100 % Check/witness at random Yes Site Report /ED316
Measurement / Visual
Root run after back gauging of Butt weld Free of flow Visual Detail Check 100 % Check/witness at random Yes Site Report /ED316
Joints
Smoathness and reinforcement of
Finished Butt Weld Joints Visual Detail Check 100 % Check/witness at random Yes Site Report /ED316
final weld
Internal Radiography Detail Check 100 % Review records Yes Site Report /ED328
(10% & all Tee joint)
Peaking,Banding, Detail Check 100 % Check/witness Yes Site Report /ED320
Measurement / Plumbness
Verticality,Circularity
DOC.NO.
DATE:
PAGE :
TITLE
Fitment, Dimension Detail Check 100 % Check/witness at random Yes Site Report
Measurement / Visual
Weld soundness Visual Detail Check 100 % Check/witness at random Yes Site Report /ED324
Erection Layout Detail Check 100 % Check/witness at random Yes Site Report /ED390
Measurement / Visual
Fitment,dimension,slope Detail Check 100 % Check/witness at random Yes Site Report /ED390
Measurement / Visual
Weld soundness Visual / Pneumatic Test Detail Check 100 % Check/witness Yes Site Report /ED390
d Roof Plates
Fabrication Dimension, checking diagonal & Detail Check 100 % Review records Yes Site Report /ED316
Measurement / Visual
squaring
Erection Fitment, dimension,Slope Detail Check 100 % Check/witness at random Yes Site Report /ED316
Measurement / Visual
Weld soundness Visual / Air Test Detail Check 100 % Check/witness Yes Site Report /ED316
e Shell appurtenances
Fabrication Dimension Detail Check 100 % Check/witness at random Yes Site Report
Measurement / Visual
Alignment,Fitup,Root Gap Detail Check 100 % Check/witness at random Yes Site Report
Measurement / Visual
Cleanliness of joint
Orientation Dimension Measurement Detail Check 100 % Witness Yes Site Report
Fitment of weld Joints Alignment,Fitup,Root Gap Detail Check 100 % Witness Yes Site Report
Measurement / Visual
Cleanliness of joint
(Nozzle to Shell)
Dimension & Shape Detail Check 100 % Check/witness at random Yes Site Report
Measurement / Visual
Finished Weld joints Smoathness and reinforcement of Visual Detail Check 100 % Check/witness at random Yes Site Report
final weld
RF Pad/ Nozzle to shell Leak tightness DP Test / Air Test Detail Check 100 % Check/witness Yes Site Report
DOC.NO.
DATE:
PAGE :
f Roof appurtenances
Fabrication Dimension Detail Check 100 % Check/witness at random Yes Site Report
Measurement / Visual
Alignment,Fitup,Root Gap Detail Check 100 % Check/witness at random Yes Site Report
Measurement / Visual
Cleanliness of joint
Orientation Dimension Measurement Detail Check 100 % Witness Yes Site Report
Fitment of weld Joints Alignment,Fitup,Root Gap Detail Check 100 % Witness Yes Site Report
Measurement / Visual
Cleanliness of joint
(Nozzle to Roof)
Dimension & Shape Detail Check 100 % Check/witness at random Yes Site Report
Measurement / Visual
Finished Weld Joints Smoothness and reinforcement of Visual Detail Check 100 % Check/witness at random Yes Site Report
final weld
Completeness,Cleanliness,Overall Measurements / Visual
g Detail Check 100 % Witness/ Review of Film Yes Site Report
Inspection prior to release for Hydrotest dimension, Plumbness,Orientation, Verification of Documents
Radiography etc
h Inspection during hydrotest Leak tightness Visual Detail Check 100 % Witness Yes Site Report
vertically Detail Check 100 % Witness Yes Site Report
Measurement / Plumbness
6 As Built Drawing Dimensions with co-ordinates Review Submit Review records Mark up on Drawings
Drawing
DOC.NO.
DATE:
PAGE :
TITLE
a Welding of Test Piece Establishing Correctness of welding Conduct Witness Witness Yes Site Report
variables
b NDT Internal Radiography(100%) Detail Check 100 % Review records Yes Site Report
Destructive Test Physical Test Physical Properties Witness Witness Yes Lab Test Certificate
5 Welder Performance Qualification
Welder Test Ability of Welder to Perform Conduct Witness Witness Yes Site Report
NDT Internal Flow Radiography(100%) Detail Check 100 % Review records Yes Site Report
6 Procedure
a Radiography Correctness Scrutiny Preparation & Submit Review records / Procedures Approval Yes Approved Procedure
ASME Sec V
b Dye Penetrant Correctness Scrutiny Preparation & Submit Review records / Procedures Approval Yes Approved Procedure
ASME Sec V
c Ultrasonic Correctness Scrutiny Preparation & Submit Review records / Procedures Approval Yes Approved Procedure
ASME Sec V
d Diesel Chalk Test Correctness Scrutiny Preparation & Submit Review records / Procedures Approval Yes Approved Procedure
ASME Sec V
e Vacuum Box Correctness Scrutiny Preparation & Submit Review records / Procedures Approval Yes Approved Procedure
API 650 & Sec V
f Air Test Correctness Scrutiny Preparation & Submit Review records / Procedures Approval Yes Approved Procedure
API 650 & Sec V
g Hydro Test Correctness Scrutiny Preparation & Submit Review records / Procedures Approval Yes Approved Procedure
API 650 & Sec V
DOC.NO.
DATE:
PAGE :
TITLE
QUALITY ASSURANCE PLAN
RECORDS REQD.TO
ACTION /EXTENT OF CHECK BY BE SUBMITTED /
SL.NO. ACTIVITY/ DESCRIPTION CHARACTERISTICS TO BE CHECKED TYPE / METHOD OF CHECK TYPE AND EXTEND OF CHECK BY JACOBS TYPE OF RECORD/BASIS
CONTRACTOR MAINTAINED BY
CONTRACTOR
D PAINTING
Lab Reports/Site Test
1 Accuarcy Measurment Detail Check 100 % Review records Yes
Calibration of Test/ Measuring Instruments
2a Material
Paints & Thinner Chemical Properties Review Detail Check 100 % Review records Yes Mfrs Test certificate
b Equipments
Compressor Workability Visual Detail Check 100 % Review records Yes Site Report
Blasting Equipments Workability Visual Detail Check 100 % Review records Yes Site Report
Spray Painting Equipments Workability Visual Detail Check 100 % Review records Yes Site Report
3 Take Over of Tank for painting Completeness Visual Detail Check 100 % Check/witness at random Yes Site Report
4 Surface Visual Detail Check 100 % Witness Yes Site Report
Surface Preparation / Grit Blasting
5 Primer application- DFT Check Thickness Measurement Detail Check 100 % Witness Yes Site Report
6 Final Painting -DFT Check Thickness Measurement Detail Check 100 % Witness Yes Site Report
7 Equipment Identification Numbering Visual Detail Check 100 % Witness Yes Site Report
E MECHANICAL COMPELETION Completeness Visual Detail Check 100 % Check/witness at random Yes Site Report
Measurement / Visual
F FINAL INSPECTION Detail Check 100 % Witness Yes Site Report
Thick of Coupon : 6 mm
Thickness Range : 6 mm
FILLER MATERIAL (QW 404)
Spec. No. (SFA) : 5.1 Filler Size : 3.15 mm
AWS No. (CLASS) : E 6013 Electrode Flux Type : -
A. No.: : 1 Backing / Storage : As per Manuf. Std.
F. No.: : 2 Consumable Insert : None
Make : ESAB/ADVANI/D&H
POSITION (QW 405)
Position of Groove : 3G Position of Fillet : NA
AWS No. (CLASS) : UPHILL
PREHEAT (QW 406) POST WELD HEAT TREATMENT (QW 407)
Preheat Temp. (Min) : NA Temperature : NA
Interpass Temp. (Max) : NA Time : NA
Preheat Maint : NA Other : NA
GAS (QW 408)
Shielding Gas : NA Flowrate : NA
Percentage Comp. : NA Gas Backing : NA
Trailing : NA Purging : NA
ELECTRICAL CHARACTERISTICS (QW 409) TECHNIQUE (QW 410)
Current Mode : DC String or weave Bead : String / Weaving
Volts : 18 to 30 Orifice or Gas Cup Size : NA
Electrical Polarity : STRAIGHT Initial / Interpass Cleaning : Wire Brushing
Amperage : 80 TO 140 Method of back gauging : Grinding
Tungsten Electrode Size & Type : NA Oscillation : NA
Mode of Metal Transfer (GMAW) : NA Contact Tube to work distance : NA
Elect. Wire - Feed,Speed,Range : NA Multiple of Single Pass (/ side) : Multiple
Other : NA Multiple of Single Electrode : Single
Travel Speed Range : SEE TABLE
Peening : NA
WELDING PROCEDURE
Filler Material Current & Voltage Travel Speed Heat Input
Pass No. Welding Process
Class Dia Type & Pol. Amps Range Volts Range mm / min kJ / mm
NAME :
SIGNATURE :
DATE :
WPS NO.:
DATE :
PQR NO.:
CLIENT : Hindustan Petroleum Corporation Limited
LOCATION :
SIGNATURE :
DATE :
WPS NO.:
DATE :
PQR NO.:
CLIENT : Hindustan Petroleum Corporation Limited
LOCATION :
NAME :
SIGNATURE :
DATE :
WPS NO.:
DATE :
PQR NO.:
CLIENT : Hindustan Petroleum Corporation Limited
LOCATION : MAHUL TERMINAL
NAME :
SIGNATURE :
DATE :
WPS NO.:
DATE :
PQR NO.:
CLIENT : Hindustan Petroleum Corporation Limited
LOCATION :
NAME :
SIGNATURE :
DATE :
WPS NO.:
DATE :
PQR NO.:
CLIENT : Hindustan Petroleum Corporation Limited
LOCATION :
NAME :
SIGNATURE :
DATE :
WPS NO.:
DATE :
PQR NO.:
CLIENT : Hindustan Petroleum Corporation Limited
LOCATION :
NAME :
SIGNATURE :
WPS NO.:
DATE :
PQR NO.:
CLIENT : Hindustan Petroleum Corporation Limited
LOCATION :
NAME :
SIGNATURE :
DATE :
WPS NO.:
DATE :
PQR NO.:
CLIENT : Hindustan Petroleum Corporation Limited
LOCATION :
NAME :
SIGNATURE :
DATE :
WPS NO.:
DATE :
PQR NO.:
CLIENT : Hindustan Petroleum Corporation Limited
LOCATION :
NAME :
SIGNATURE :
DATE :
WPS NO.:
DATE :
PQR NO.:
CLIENT : Hindustan Petroleum Corporation Limited
LOCATION :
NAME :
SIGNATURE :
DATE :
WPS NO.:
DATE :
PQR NO.:
CLIENT : Hindustan Petroleum Corporation Limited
LOCATION : MAHUL TERMINAL
NAME :
SIGNATURE :
DATE :
WPS NO.:
DATE :
PQR NO.:
CLIENT : Hindustan Petroleum Corporation Limited
LOCATION :
NAME :
SIGNATURE :
DATE :
WPS NO.:
DATE :
PQR NO.:
CLIENT : Hindustan Petroleum Corporation Limited
LOCATION : MAHUL TERMINAL
NAME :
SIGNATURE :
DATE :
WPS NO.:
DATE :
PQR NO.:
CLIENT : Hindustan Petroleum Corporation Limited
LOCATION :
NAME :
SIGNATURE :
DATE :
WPS NO.:
DATE :
PQR NO.:
CLIENT : Hindustan Petroleum Corporation Limited
LOCATION :
NAME :
SIGNATURE :
DATE :
WPS NO.:
DATE :
PQR NO.:
CLIENT : Hindustan Petroleum Corporation Limited
LOCATION :
NAME :
SIGNATURE :
DATE :
Note : 1) For 5mm to 16mm joint separate WPS has to be made using E7018 Rod
2) Inner joint bulk head shall have doublers plate
WPS NO.:
DATE :
PQR NO.:
CLIENT : Hindustan Petroleum Corporation Limited
LOCATION :
Backing : NO FIG 7
Thick of Coupon : 16 mm
Thickness Range : 5 to 16 mm
FILLER MATERIAL (QW 404)
Spec. No. (SFA) : 5.1 Filler Size : 3.15 / 4 mm
AWS No. (CLASS) : E 7018 Electrode Flux Type : -
A. No.: : 1 Backing / Storage : As per Manuf. Std.
F. No.: : 4 Consumable Insert : None
Make : ESAB/ADVANI/D&H
POSITION (QW 405)
Position of Groove : - Position of Fillet : 2F
AWS No. (CLASS) : -
PREHEAT (QW 406) POST WELD HEAT TREATMENT (QW 407)
Preheat Temp. (Min) : NA Temperature : NA
Interpass Temp. (Max) : NA Time : NA
Preheat Maint : NA Other : NA
GAS (QW 408)
Shielding Gas : NA Flowrate : NA
Percentage Comp. : NA Gas Backing : NA
Trailing : NA Purging : NA
ELECTRICAL CHARACTERISTICS (QW 409) TECHNIQUE (QW 410)
Current Mode : DC String of weave Bead : String
Volts : 20 to 28 Orifice or Gas Cup Size : NA
Electrical Polarity : Electrode-Straight Initial / Interpass Cleaning : Wire Brushing
Amperage : 90 TO 190 Method of back gauging : Grinding
Tungsten Electrode Size & Type : NA Oscillation : NA
Mode of Metal Transfer (GMAW) : NA Contact Tube to work distance : NA
Elect. Wire - Feed,Speed,Range : NA Multiple of Single Pass (/ side) : Multiple
Other : NA Multiple of Single Electrode : Single
Travel Speed Range : SEE TABLE
Peening : NA
WELDING PROCEDURE
Filler Material Current & Voltage Travel Speed Heat Input
Pass No. Welding Process
Class Dia Type & Pol. Amps Range Volts Range mm / min kJ / mm
NAME :
SIGNATURE :
DATE :
WPS NO.:
DATE :
PQR NO.:
CLIENT : Hindustan Petroleum Corporation Limited
LOCATION :
Type : T FILLET
Backing : NO FIG 12
P. No. : 1 To 1
Group No. : 1 To 1
Thick of Coupon : 5 mm
Thickness Range : 5 mm
FILLER MATERIAL (QW 404)
Spec. No. (SFA) : 5.1 Filler Size : 3.15 / 4 mm
AWS No. (CLASS) : E 6013 Electrode Flux Type : -
A. No.: : 1 Backing / Storage : As per Manuf. Std.
F. No.: : 2 Consumable Insert : None
Make : ESAB/ADVANI/D&H
POSITION (QW 405)
Position of Groove : - Position of Fillet : 2F
AWS No. (CLASS) : -
PREHEAT (QW 406) POST WELD HEAT TREATMENT (QW 407)
Preheat Temp. (Min) : NA Temperature : NA
Interpass Temp. (Max) : NA Time : NA
Preheat Maint : NA Other : NA
GAS (QW 408)
Shielding Gas : NA Flowrate : NA
Percentage Comp. : NA Gas Backing : NA
Trailing : NA Purging : NA
ELECTRICAL CHARACTERISTICS (QW 409) TECHNIQUE (QW 410)
Current Mode : DC String of weave Bead : String
Volts : 20 to 28 Orifice or Gas Cup Size : NA
Electrical Polarity : Straight Initial / Interpass Cleaning : Wire Brushing
Amperage : 80 TO 180 Method of back gauging : Grinding
Tungsten Electrode Size & Type : NA Oscillation : NA
Mode of Metal Transfer (GMAW) : NA Contact Tube to work distance : NA
Elect. Wire - Feed,Speed,Range : NA Multiple of Single Pass (/ side) : Multiple
Other : NA Multiple of Single Electrode : Single
Travel Speed Range : SEE TABLE
Peening : NA
WELDING PROCEDURE
Filler Material Current & Voltage Travel Speed Heat Input
Pass No. Welding Process
Class Dia Type & Pol. Amps Range Volts Range mm / min kJ / mm
NAME :
SIGNATURE :
DATE :
WPS NO.:
DATE :
PQR NO.:
CLIENT : Hindustan Petroleum Corporation Limited
LOCATION :
Backing : NO FIG 13
Backing Material Type / Grade : NA
P. No. : 1 To 1
Group No. : 1 To 1
Thick of Coupon : 6 mm
Thickness Range : 6 mm
FILLER MATERIAL (QW 404)
Spec. No. (SFA) : 5.1 Filler Size : 3.15 / 4 mm
AWS No. (CLASS) : E 7018 Electrode Flux Type : -
A. No.: : 1 Backing / Storage : As per Manuf. Std.
F. No.: : 4 Consumable Insert : None
Make : ESAB/ADVANI/D&H
POSITION (QW 405)
Position of Groove : - Position of Fillet : 2F
AWS No. (CLASS) : -
PREHEAT (QW 406) POST WELD HEAT TREATMENT (QW 407)
Preheat Temp. (Min) : NA Temperature : NA
Interpass Temp. (Max) : NA Time : NA
Preheat Maint : NA Other : NA
GAS (QW 408)
Shielding Gas : NA Flowrate : NA
Percentage Comp. : NA Gas Backing : NA
Trailing : NA Purging : NA
ELECTRICAL CHARACTERISTICS (QW 409) TECHNIQUE (QW 410)
Current Mode : DC String of weave Bead : String
Volts : 20 to 28 Orifice or Gas Cup Size : NA
Electrical Polarity : Straight Initial / Interpass Cleaning : Wire Brushing
Amperage : 80 TO 180 Method of back gauging : Grinding
Tungsten Electrode Size & Type : NA Oscillation : NA
Mode of Metal Transfer (GMAW) : NA Contact Tube to work distance : NA
Elect. Wire - Feed,Speed,Range : NA Multiple of Single Pass (/ side) : Multiple
Other : NA Multiple of Single Electrode : Single
Travel Speed Range : SEE TABLE
Peening : NA
WELDING PROCEDURE
Filler Material Current & Voltage Travel Speed Heat Input
Pass No. Welding Process
Class Dia Type & Pol. Amps Range Volts Range mm / min kJ / mm
INSIDE
ROOT (1) SMAW E7018 3.15 REVERSE 100 to 135 20 to 24 80 to 120
SUB. PASS (2) SMAW E7018 4 REVERSE 130 to 190 24 to 28 90 to 150
OUTSIDE
ROOT (1) SMAW E7018 3.15 REVERSE 100 to 135 20 to 24 80 to 120
SUB. PASS (2) SMAW E7018 4 REVERSE 130 to 190 24 to 28 90 to 150
NAME :
SIGNATURE :
DATE :
Note : Joint at the point where Outer rim & Lap of Bottom Deck plate meet shall be like
a) Bottom deck has to be made Sq Butt joint for 100 mm length
WPS Pg (a) should be submitted separately
Hence Joggly not needed
WPS NO.:
DATE :
PQR NO.:
CLIENT : Hindustan Petroleum Corporation Limited
LOCATION :
NAME :
SIGNATURE :
DATE :
WPS NO.:
DATE :
PQR NO.:
CLIENT : Hindustan Petroleum Corporation Limited
LOCATION :
NAME :
SIGNATURE :
DATE :
WPS NO.:
DATE :
PQR NO.:
CLIENT : Hindustan Petroleum Corporation Limited
LOCATION :
Backing : NO FIG 16
P. No. : 1 To 1
Group No. : 1 To 1
Thick of Coupon : 5 mm
Thickness Range : 5 mm
FILLER MATERIAL (QW 404)
Spec. No. (SFA) : 5.1 Filler Size : 3.15 / 4 mm
AWS No. (CLASS) : E 6013 Electrode Flux Type : -
A. No.: : 1 Backing / Storage : As per Manuf. Std.
F. No.: : 2 Consumable Insert : None
Make : ESAB/ADVANI/D&H
POSITION (QW 405)
Position of Groove : - Position of Fillet : 2F
AWS No. (CLASS) : -
PREHEAT (QW 406) POST WELD HEAT TREATMENT (QW 407)
Preheat Temp. (Min) : NA Temperature : NA
Interpass Temp. (Max) : NA Time : NA
Preheat Maint : NA Other : NA
GAS (QW 408)
Shielding Gas : NA Flowrate : NA
Percentage Comp. : NA Gas Backing : NA
Trailing : NA Purging : NA
ELECTRICAL CHARACTERISTICS (QW 409) TECHNIQUE (QW 410)
Current Mode : DC String of weave Bead : String
Volts : 20 to 28 Orifice or Gas Cup Size : NA
Electrical Polarity : Electrode-Straight Initial / Interpass Cleaning : Wire Brushing
Amperage : 80 TO 180 Method of back gauging : Grinding
Tungsten Electrode Size & Type : NA Oscillation : NA
Mode of Metal Transfer (GMAW) : NA Contact Tube to work distance : NA
Elect. Wire - Feed,Speed,Range : NA Multiple of Single Pass (/ side) : Multiple
Other : NA Multiple of Single Electrode : Single
Travel Speed Range : SEE TABLE
Peening : NA
WELDING PROCEDURE
Filler Material Current & Voltage Travel Speed Heat Input
Pass No. Welding Process
Class Dia Type & Pol. Amps Range Volts Range mm / min kJ / mm
NAME :
SIGNATURE :
DATE :
NAME :
SIGNATURE :
DATE :
WPS NO.:
DATE :
PQR NO.:
CLIENT : Hindustan Petroleum Corporation Limited
LOCATION :
NAME :
SIGNATURE :
DATE :
WPS NO.:
DATE :
PQR NO.:
CLIENT : Hindustan Petroleum Corporation Limited
LOCATION :
NAME :
SIGNATURE :
DATE :
WPS NO.:
DATE :
PQR NO.:
CLIENT : Hindustan Petroleum Corporation Limited
LOCATION :
NAME :
SIGNATURE :
DATE :
WPS NO.:
DATE :
PQR NO.:
CLIENT : Hindustan Petroleum Corporation Limited
LOCATION :
NAME :
SIGNATURE :
DATE :
Note : WPS for 10mm to insert plate joint should be submitted separately
WPS NO.:
DATE :
PQR NO.:
CLIENT : Hindustan Petroleum Corporation Limited
LOCATION :
Backing : YES
NAME :
SIGNATURE :
DATE :
WPS NO.:
DATE :
PQR NO.:
CLIENT : Hindustan Petroleum Corporation Limited
LOCATION :
NAME :
SIGNATURE :
DATE :
WPS NO.:
DATE
WPS NO.:
CLIENT : HINDUSTAN PETROLEUM CORPORATION LTD.
LOCATION :
QW-482 - WELDING PROCEDURE SPECIFICATION
(REF. SPECIFICATION : ASME SECTION IX)
JOINT DESIGN (QW-402) SKETCH / DETAIL:
Type SQ. BUTT
Backing NO FIG 1 (A)
Backing material Type / Grade NA
WELDINHG PROCESS SWAM TYPE MANUAL
BASE METALS (QW 403)
Material Specification IS 2062 / EQ. To IS 2062 / EQ.
Type / Grade No. GR.B To GR.B
P. No. 1 To 1
Group No. 1 To 1
Thick of Coupon 6 mm
Thickness Range 6 mm
FILLER MATERIAL (QW 404)
Spec. No. (SFA) 5.1 Filler Size : 3.15 / 4 mm
AWS No. (CLASS) E 6013 Electrode Flux Type : -
A. No. : 1 Backing / Storage : As per Manuf. Std.
F. No. : 2 Consumable Insert : Non
Make ESAB/ADVANI/D&H
POSITION (QW 405)
Position of Groove 3G Position of Fillet : NA
Weld Progression UPHILL
PREHEAT (QW 406) POST WELD HEAT TREATMENT (QW 407)
Preheat Temp.(Min) NA Temperature : NA
Interpass Temp.(Max) NA Time : NA
Preheat Maint Others : NA
GAS (QW 408)
Shielding Gas NA Flowrate : NA
Percentage Comp. NA Gas Backing : NA
Trailing NA Purging : NA
ELECTRICAL CHARACTERISTICS (QW 409) TECHNIQUE (QW 410)
Current Mode DC String or weave Bead : String / Weaving
Volts 18 to 30 Orifice or Gas Cup Size : NA
Electrical Polarit STRAIGHT Initial / Interpass Cleaning: Wire Brushing
Amperage 80 TO 140 Method of back gauging : Grinding
Tungsten Electrode Size & Type NA Oscillation : NA
Mode of Metal Transfer (GMAW) NA Contact Tube to work distance
: NA
Elect. Wire - Feed,Speed,Range NA Multiple or Single Pass ( /: Side) Multiple
Other NA Multiple or Single Electrode: Single
Travel Speed Electrode : SEE TABLE
Peening NA
WELDING PROCEDURE
Pass No. Welding Process
Filler Material Heat Input
Class Dia Type & Pol. Amps Range Volts Range mm / min kj / mm
JOB PROCEDURES
FOR
TANKAGE WORKS
!
"
#
$
%
%
&
DATE
PAGE NO
03 OF 16
PROJECT TITLE
PROCEDURE FOR FABRICATION & ERECTION OF
TANKAGES BY JACKING UP METHOD
2. PURPOSE:
The purpose of this document is to follow proper methodology to carry out the
activities in a proper sequence for fabrication, Erection and Testing of the storage
tanks.
3. REFERENCE:
API 650
ASME Sec IX
ASME Sec V
Tender Specification.i.e. 18-3188-99-02-V-02-001-A4; VSS004; 18-3188-00/Z-00-
001; 18-3188-99-00-V.02-005-A4 etc
Approved Drawing / Specification.
4. RESPONSIBILITY:
The responsibility of implementation of this procedure rests with Construction
Manager of M/S Vishal Structurals Pvt. Ltd.
5. METHOD OF CONSTRUCTION:
5.1 IDENTIFICATION OF MATERIALS
Each Piece of Plates, fittings or any other component of tankage system shall be
clearly identified by marking heat no. on the part (e.g.: IS 2062 Gr.B, H.No.-XXX)
using hard punching.
Each weld joint shall be marked with joint Number with Welder Number.
5.2 FABRICATION WORK
All fabrication work involving material identification, marking, cutting, rolling and
welding shall be done in accordance with this job procedure, API 650 (Latest
edition), JE Spec and tender documents. The workmanship shall be good in every
respect meeting all safety, QC & NDT requirements, with the coordination of
Engineer-In-Charge.
Prepared by Concurred by Approved by
Name : Name :
Design: Design:
DATE
PAGE NO
04 OF 16
PROJECT TITLE
PROCEDURE FOR FABRICATION & ERECTION
OF TANKAGES BY JACKING UP METHOD
Lay all the plates, Structural & pipes in such a way prior to fabrication to
facilitate proper checking of dimensions & heat no.
Mark the components as per the drawings.
Name : Name :
Design: Design:
DATE
PAGE NO
05 OF 16
PROJECT TITLE
PROCEDURE FOR FABRICATION & ERECTION
OF TANKAGES BY JACKING UP METHOD
The plate shall be rolled as per drawing details and the radius shall be checked
using Template.
Proper care shall be taken for the smooth curvature.
36’’ Long (5 to 6mm thk.) Template shall be used to check rolling curvature
accurately.
The Template shall be checked and cleared by inspection authority.
The rolled plates shall be inspected and shall be within 03mm. of tolerance
limit.
The rolled plates shall be shift to shot blasting yard to carryout the shot blast
as per JE specification.
Final profile and dimensions check shall be carried out before sent for rection.
Name : Name :
Design: Design:
CONTRACTOR . Hindustan Petroleum Crop. Ltd. Hindustan Petroleum Crop. Ltd
DOC NO
DATE
PAGE NO
06 OF 16
PROJECT TITLE
PROCEDURE FOR FABRICATION & ERECTION OF
TANKAGES BY JACKING UP METHOD
5.2.4 APPURTENANCES
Mark the required items of the Appurtenances as per the drawing. All the
cutting operation as per requirement shall be carried out after getting the
clearance from inspection authority.
All the cutting operation shall be carried out by gas cutting method.
Grind the cut edges smooth to remove burrs & slag.
Flanges face to be covered with a suitable cover to protect from damage
during handling, fabrication and transportation.
The entire shell nozzle, roof appurtenance, i.e. flanges, flanges to pipe
joint and other requirements etc. Shall be fabricated as per approved
drawings.
All the fabrication and welding activities shall be carried out after the stage
wise inspection wherever required.
The N.D.T requirements as per code specification.
5.3 ERECTION:
5.3.1. ANNULAR PLATE LAYING
Check the level of foundation as per specification API 650 clause 8.4.2. Latest
edition.
After getting clearance for annular plate laying, mark the 0o, 90o, 180o, 270o co-
ordinates on the foundation from the reference point.
Lay the annular plate as per approved drawing.
Prepared by Concurred by Approved by
Name : Name :
Design: Design:
CONTRACTOR . Hindustan Petroleum Crop. Ltd. Hindustan Petroleum Crop. Ltd
DOC NO
DATE
PAGE NO
07 OF 16
PROJECT TITLE
PROCEDURE FOR FABRICATION & ERECTION OF
TANKAGES BY JACKING UP METHOD
Out radius of the annular plate shall be in positive side (5 to 10 mm.) in order to
achieve the final required radius after weld shrinkage.
Orientation of the annular plate joint shall be as per approved -drawing.
Fit up of annular plate's joints shall be carried out using proper jigs and fixtures as
shown in drawing.
Care shall be taken while fit-up, such that there should not any gap between
annular plate and backing-strip.
Annular plates joints welding shall be carried out by welding alternative joint at four
quadrants.
Qualified welders shall be engaged for the welding work according to WPS.
If any defect found the defect weld shall be removed by grinding and re-weld and
conduct the LPT check test. Repeat the sequence until the defect cleared.
Complete the welding, clean the final weld surface by wire brushing and grinding.
Remove the jigs and fixtures which were used for fit-up of the annular joint and
grind the tack.
Radiography shall be taken as per API-650 Sec-6.
DATE
PAGE NO
08 OF 16
PROJECT TITLE
PROCEDURE FOR FABRICATION & ERECTION OF
TANKAGES BY JACKING UP METHOD
Minimum laps shall be maintained while the fit-up of long-seam as per approved
drg.
Joggling shall be carried out by hammering wherever it necessary. (Three plate
Joining junction.)
Before starting the welding, channels shall be tacked along the long-seam to avoid
the distortion.
After completion of shot seam welding long seam welding will be carried out
alternatively to avoid distortion.
Qualified welder shall be engaged and welding shall be carry out as per approved
WPS.
After Completion of welding thoroughly clean the weld ‘joint by wire brushing and
grinding.
Sketch to annular plate joint shall be welded only after shell to bottom joint welding.
All the bottom plate' s joints vacuum box test shall be carried out as per approved
procedure and code specification.
If any defect found the defect weld shall be removed by grinding and re-weld and
conduct the vacuum box test. Repeat the sequence until the defect cleared.
DATE
PAGE NO
09 OF 16
PROJECT TITLE
PROCEDURE FOR FABRICATION & ERECTION OF
TANKAGES BY JACKING UP METHOD
Peaking to be checked after the fit-up of the vertical joints. Peaking shall be within
the tolerance as per API - 650. (Tolerance 1/2")
Peaking shall be checked at top, middle and bottom of the vertical joints using a
Sweep board of 36” long.
Plumbness shall be checked for the verticality of the shell course at every 60° and
shall be within the tolerance (tolerance 1/200 of the total shell height)
For perfect verticality, channels shall be provided at the regular interval inside of
the shell course (3 to 5 meters) Providing the channels shall be facilitates the
alignment last shall course.
Tack welds of the fitted vertical joints shall be ground smooth.
Offer for inspection and get clearance from Engineer-in-charge for the vertical
fit-up Complete the first side welding by using qualified welders.
Care shall be taken while the welding to avoid the peaking and the roundness
distortion
After completion of first side welding, back-chip shall be carried out for sound metal
from other side of the weld by grinding.
Back-chipped grooves shall be offered for inspection before starting the welding.
Complete the 2nd side welding using qualified welders.
Joint Nos. & welder No. shall be marked on both side of the weld .joint.
Care shall be taken to avoid the peaking and roundness distortion.
Clean weld joints from both sides by wire brushing and grinding.
After completion of welding from both sides remove all the temporary jigs and
fixtures and flush grind the tacks. (Do the weld fill up wherever required) and the
portion checked by D.P.test.
Check the peaking, plumb ness, circumference and the radius, offer for inspection
to the satisfaction of the Engineer-in-Charge.
Erect last shell course plate on top of the erected shell plate, 3mm thick spacers
shall be kept between first and last but one shell course plates to maintain
horizontal seam gap.
Erection channels shall be fixed between last but one shell course plates and
last shell course plates at regular intervals to align and hold the last shell in
vertical position.
DATE
PAGE NO
10 OF 16
PROJECT TITLE
PROCEDURE FOR FABRICATION & ERECTION OF
TANKAGES BY JACKING UP METHOD
After all the shell plates for last shell course is erected, fit-up the vertical joint using
jig plates which has been fixed during erection and tack weld the joints.
Check peaking at vertical joints of shell using a sweep board of 36" wide,
acceptable tolerance shall the as per API-650 clause 5.5.4 (local deviation shall
not exceed 1/2")
Complete welding of last course vertical seam inside after getting clearance from
the Engineer-in-charge.
Back chip & welding shall be carried out following as same as for other shell
course to the satisfaction of Engineer - in - Charge.
After completion of welding, weld visual, peaking & circumference shall be
checked out and recorded to the satisfaction of Engineer - in-Charge.
Fit up the Horizontal seam between top shell courses and tack welded, remove the
spacers provided during erection, tack weld shall be ground smooth and ensure
that the tacks are sound and there are no defects like cracks and porosity etc.
Check peaking at vertical joints of shell using a sweep board of 36" wide,
acceptable clearance shall be as per API 650 clause 5.5.4 (local deviation shall
not exceed 1/2") Using a vertical sweep board 36" long, check banding at
horizontal joints. Deviation shall not exceed 1/2".
Check Verticality of the last shell course, Verticality (plumb ness) tolerance shall
be as per API - 650 clause 5.5.2 (max. out of plumbness at the top of the shell
relative to the bottom of the shell not to exceed 1/200 of total shell height from top
of last shell to Bottom)
While welding care shall be taken for banding and the roundness.
Back-chip shall be carried out by grinding for the sound metal and to the
satisfaction of Engineer-in-Charge.
Complete the 2nd side welding and clean the joint thoroughly from both sides by
grinding and wire brushing.
Check banding, plumb ness and recorded in the approved format to the
satisfaction of Engineer - In-Charge.
Offer weld visual to the satisfaction of Engineer-In-Charge. .
Mark the RT spots as per the instruction of the Engineer -In-Charge, and complete
the RT as per API - 650 Sec-6 requirements.
DATE
PAGE NO
11 OF 16
PROJECT TITLE
PROCEDURE FOR FABRICATION & ERECTION OF
TANKAGES BY JACKING UP METHOD
Offer the RT film for reviewing to the Engineer-In-Charge, and if any repair occurs
the repair spot shall be repaired by grinding for the sound metal, Re- weld the
repair spot as per code API -650 sec-6 requirements.
Take the repair spot RT and re offer for the inspection to the satisfaction of
Engineer-In- Charge
Spiral staircase Erection shall be carried out as per drawing including brackets.
Remove all the temporary cleats and tacks by grinding.
Install jacks as per requirement and the distance between the jacks shall not be
more than 3.5 meter. Connect the power pack and check the total system is ready
for erection of the shell.
Install the jacking cleats on the bottom shell course (inside) and weld soundly the
cleats to the shell. Roof structure & Roof shall be erected then start jacking.
Start jacking of the assembly of top two shell course along with the wind girder.
Lift till the required space for the lower shell course plate width + Erection chair
height. (400~450 mm)
Erect the lower shell course by using the Hydra crane for shifting and position the
plates.
Alignment and fit up shall be carried out by using jigs and fixture and as per
drawing offer the fit up for inspection.
Followed by welding, weld visual, peaking and plumb ness before and after as
mentioned above for the top two shell courses.
After completion of the welding lower down the jacked up assembly on top of 3rd
shell from top.03 mm thick spacer shall be kept between 3rd and 2nd shell from top
to maintain the Horizontal joint gap.
Fit up the Horizontal joint between 3rd and 2nd shell courses from top using jigs
and fixtures and tack weld, remove the spacers provided during erection. Tack
shall be ground smooth, check the banding and record. Offer fit up and banding to
the satisfaction of Engineer-In-Charge.
Followed by welding, banding & plumb ness before and after welding shall be
carried out as mentioned for the above Horizontal joint.
RT shall be carried out and cleared before the next lifting
Portion of the spiral stairway shall be erected as per drawing
DATE
PAGE NO
12 OF 16
PROJECT TITLE
PROCEDURE FOR FABRICATION & ERECTION OF
TANKAGES BY JACKING UP METHOD
After clearance from inspection, the jacking cleats shall be fitted to 3 rd shell from
top course plates and the total assembly shall be jacked up by required height for
erection of the all the shell courses.
In the same manner erect all the shell courses and spiral stairway.
The 1st shell course plates shall be erected, provide min. 6 mm thick packing plates
at required location in each shell plate to facilitate proper welding of the bottom
most portion of the vertical joint. This packing plate shall not be removed until
commencement of shell to annular fit up. Leave the final shell plate open by
providing angular frame in order for deck plate shifting and working.
After completion of welding of vertical seams of the 1st shell course by following
abovementioned process and the Horizontal joint between the shell courses 1 and
2 shall be aligned by lowering the jacks and the fit up shall be carried out.
Follow the above-mentioned process for the horizontal joint welding and
clearance.
RT shall be carried out as per API-650 Sec.6
Shell to annular plate joint shall be carried out using jigs and fixture.
After getting fit up clearance for welding, root weld shall be carried out from
inside.
After completion of inside welding clean the weld thoroughly by wire brushing,
grinding and buffing.
The shell to bottom joint area from both sides shall be cleaned thoroughly to carry
out the chalk-diesel test.
Apply chalk solution from inside. Apply diesel by a hand spray pump from out side.
Hold it as per instruction of the Engineer-In-Charge and check the root weld for
any defect.
If any defect found the defect shall be repaired by grinding the defect area for the
sound metal plus 150mm from both end of the defect.
Conduct the chalk - diesel test on the repair spot. Carry out the whole process until
the repair cleared to the satisfaction of Engineer - In – Charge.
DATE
PAGE NO
13 OF 16
PROJECT TITLE
PROCEDURE FOR FABRICATION & ERECTION OF
TANKAGES BY JACKING UP METHOD
After completion of shell to bottom out side welding visual inspection will be
carried out to the satisfaction of the Engineer-In-Charge.
On completion of shell to bottom welding / NDT and having completed all erection
and welding work on the tank inside related to the roof and roof structure, all
unwanted materials and scrap shall be removed from inside of the tank.
RT of vertical and horizontal joint shall be completed.
Sketch to annular plate joint fit up shall be carried out and complete the welding.
Vacuum box test the shall be carried out for the bottom plate short seam, long
seam and sketch to annular plate joint.
If any repair occurs the same shall be repaired and re-tested as per the approved
procedure and API-650.
After completion of the Top two shell courses erection, fit up, welding and curb ring
fit up & welding shall be done.
Erect the fabricated Centre Drum, Roof Truss, and cross girders as per drawing.
Complete the welding of Roof structure by approved welders and as per approved
WPS.
Erect and Lay the Roof plates on the structure as per the Drg.
While fit up of the short seams and long seams Lap to be maintained as per Drg
Weld the short seams by welding alternative joint or sequence mentioned in the
Drg.to prevents the distortion.
Provided proper support lengthwise of the long seam and weld the joints as per
Drg. sequence.
Roof Nozzles and top shell nozzles fit-up and welding shall be carryout as per the
approved drawing and subsequently it has to be correlated with the concern piping
drawing.
DATE
PAGE NO
14 OF 16
PROJECT TITLE
PROCEDURE FOR FABRICATION & ERECTION
OF TANKAGES BY JACKING UP METHOD
DATE
PAGE NO
15 OF 16
PROJECT TITLE
PROCEDURE FOR FABRICATION & ERECTION OF
TANKAGES BY JACKING UP METHOD
DATE
PAGE NO
16 OF 16
PROJECT TITLE
PROCEDURE FOR FABRICATION & ERECTION OF
TANKAGES BY JACKING UP METHOD
This shall be followed and maintained with the compliance / adherence to the drawings,
procedure and code specification. Records shall be kept in the relevant check sheet and
formats duly signed by all the concerned departments.
9. SAFETY
Tested & certified Lifting equipments should be used for lifting and shifting
purpose.
Safety Precautions should be followed during fabrication and erection as per JE
specification.
Welding cables and power cables to be laid properly as per IE rules and local state
govt. rules.
Proper house keeping and clean condition shall be maintained in the fabrication
shop and site as per requirement.
10. RECORDS
Foundation hand over report
Material Inspection Records
Electrode, Consumables etc. verification record
Welding Inspection report
NDT reports
Test reports
PAGE NO
03 OF 17
PROJECT TITLE
RADIOGRAPHIC EXAMINATION PROCEDURE.
2. PURPOSE:
The purpose of this procedure is to ensure that the radiographic images produced
are acceptable quality and that all radiographic examinations are performed in a
safety policy, project specifications, quality control plan (SEP-Q1-001) and
applicable codes.
3. REFERENCE:
ASME V Nondestructive Examination-Boiler & pressure vessel Code
ASME B31.3 Process Piping
ASME IX Welding and Bracing Qualification
API 650 Welded Steel tanks for Oil Storage.
SNT-TC-1A Recommended Practice for Nondestructive Testing Personnel
Qualification & Certification.
API 1104 Standard for welding pipelines and related facilities.
4. RADIATION SAFETY
4.1 General
The radiographic technician (radiographer) shall be fully trained / qualified, and
shall be fully aware of the hazards of radiation.
Human body tissue will be severely damages if they are over exposed to
radiation and even small amount of exposure on a daily basis, with insufficient
recovery periods, will eventually produce a serious deterioration in health.
All possible safety precaution shall always be taken to avoid unnecessary
exposure.
Prior to commencing any radiation work on site, emergency procedures shall be
established.
All radiographic discipline personnel who are involved with working with ionizing
Radiation shall
Take all reasonable safety precautions.
Not knowingly expose either themselves or any other person to radiation
greater than is absolutely necessary for the purposes of their work.
Prepared by Concurred by Approved by
Name : Name :
Design: Design:
DATE
PAGE NO
04 OF 17
PROJECT TITLE
RADIOGRAPHIC EXAMINATION PROCEDURE.
Make full and proper use of all personal protection equipment provided.
Report any defects to radiographic equipment to his employer immediately
upon discovery.
4.2 Controlled areas
Radiography shall only be undertaken in designated and clearly identified
”controlled areas”.
These areas shall be identified and sealed by the use of the following as a
minimum
Radiation tape Barriers-which surround and seal off the controlled area in its
entirety.
Radiation Hazard Warning Signs in English.
The sign shall be a minimum size of 450 x 450 mm.
These shall be positioned every 30 meters around the periphery of the
controlled area.
Flashing yellow lights to indicate radiation hazard area, these shall be
positioned adjacent to warning signs.
Under no circumstances shall non radiographic discipline (unclassified)
personnel cross or enter the barriers to a controlled area.
Any infringement of this safety rule / regulations concerning controlled areas will
result in the immediate removal of the individual concerned and expulsion from
the Tankage Project.
4.3 Radioactive isotope
The container in which radioactive isotopes are housed shall be lockable and
sealed. They shall be manufactured from expended uranium or similar
materials, to international safety standards.
These containers shall be re-certified as safe to use every of 26 months
(maximum).The senior radiographic technician on site shall hold the keys at all
times (other than usage).The whereabouts of all radioactive isotopes on site
shall be logged and known at all times.
PAGE NO
05 OF 17
PROJECT TITLE
RADIOGRAPHIC EXAMINATION PROCEDURE.
PAGE NO
06 OF 17
PROJECT TITLE
RADIOGRAPHIC EXAMINATION PROCEDURE.
PAGE NO
07 OF 17
PROJECT TITLE
RADIOGRAPHIC EXAMINATION PROCEDURE.
ASTM Wire
Set Diameter
0.032
0.004
A 0.005
0.006
0.008
0.010
0.013
0.016
B 0.020
0.025
0.032
0.040
C 0.050
0.063
0.080
0.100
0.126
0.160
0.200
D 0.250
0.320
DATE
PAGE NO
08 OF 17
PROJECT TITLE
RADIOGRAPHIC EXAMINATION PROCEDURE.
7.PROCESSING REQUIREMENTS
7.1 Quality of radiographs
All radiographs shall be free from mechanical, chemical or other artifacts to be
extent that they cannot mask or be confused with the image of any discontinuity in
the object being radiographed. Such artifacts include but are not limited to:
[a] Fogging
[b] Processing defects such as water or chemical marks.
[c] Scratches, Finger marks, crimps, static smudges or tears
[d] Loss of details due to poor film Contrast.
[e] False indication due to defective screens.
7.2 Processing Manual (According to SE-94)
7.2.1 Preparation :–
No more film should be processed that can be accommodated with a
Minimum separation of ½ “. Hangers are loaded and solutions stirred before
starting development.
7.2.2 Start of development :-
Start the timer and place the films into the developer tank. Separate
to a minimum distance of ½ “ and agitate in two directions for about 15
seconds.
7.2.3 Development:-
Normal development is 5 to 8 minutes at 68° F (20° C)
7.2.4 Agitation:-
Shake the film horizontally and vertically, ideally for a few seconds each
minute during development. This will help develop evenly.
7.2.5 Rinsing:-
Rinse the films with vigorous agitation in clear water.
7.2.6 Fixing:-
The Films must not touch one another in the fixer. Agitate the hangers
vertically for about 10 seconds and again at the end of the first minute, to
ensure uniform and rapid fixation. Keep them in the fixer until fixation is
complete (i.e. at least twice the clearing time),but not more than 15 minutes
in relatively fresh fixer. Frequent agitation will shorten the time of fixation.
7.2.7 Fixer Neutralizing:-
Use hypo eliminator or fixer neutralizer between fixation and washing.
PAGE NO
09 OF 17
PROJECT TITLE
RADIOGRAPHIC EXAMINATION PROCEDURE.
7.2.8 Washing:-
Washing is very slow below 60° F(16° C).When washing at temperature above
85° F(30° C),care should be exercised not to leave films in the water too long.
The films should be washed in batches without contamination from new film
brought over from the fixer. If pressed for capacity, as more films are put in the
wash, Partially washed film should be moved in the direction of the inlet.
7.2.9 Wetting Agent:-
Dip the film for approx. 30 seconds in a wetting agent added clear water.
7.2.10 Drying:-
Take Precaution to tighten film on hangers, so that it cannot touch in the dryer.
Too hot a Drying temperature at low humidity can result in uneven drying and
should be avoided.
8.EXAMINATION PROCEDURE:-
8.1. Surface Preparation
The weld ripples or weld surface irregularities on both the inside (where
accessible) and outside shall be removed by any suitable process to such a
degree that the resulting radiographic image due to any irregularities cannot mask
or be confused with the image of any discontinuity.
8.2. RT request
Upon completion and visual acceptance of a weld that is subject to radiography,
the controlling engineer shall make a request for radiographic examination.
The request shall be entered into the schedule for radiographic examination and
forwarded to the radiographic technicians for execution.
DATE
PAGE NO
10 OF 17
PROJECT TITLE
RADIOGRAPHIC EXAMINATION PROCEDURE.
The boundaries of this ‘controlled area’ shall be identified with radiation tape
barriers, warning signs (in both English and Hindi) and flashing lights.
PAGE NO
11 OF 17
PROJECT TITLE
RADIOGRAPHIC EXAMINATION PROCEDURE.
[2] As alternative, the weld may be radiographed with the radiation beam
positioned so that the images of both walls are superimposed.
When complete coverage is required, a minimum of three exposures taken
at either 60 deg. To 120 deg. To each other shall be made for each joint.
DATE
PAGE NO
12 OF 17
PROJECT TITLE
RADIOGRAPHIC EXAMINATION PROCEDURE.
Material Ug
Thickness (in.) Maximum (in.)
Under 2 0.020
2 trough 3 0.030
Over 3 trough 4 0.040
Greater than 4 0.070
PAGE NO
13 OF 17
PROJECT TITLE
RADIOGRAPHIC EXAMINATION PROCEDURE.
PAGE NO
14 OF 17
PROJECT TITLE
RADIOGRAPHIC EXAMINATION PROCEDURE.
PAGE NO
15 OF 17
PROJECT TITLE
RADIOGRAPHIC EXAMINATION PROCEDURE.
PAGE NO
16 OF 17
PROJECT TITLE
RADIOGRAPHIC EXAMINATION PROCEDURE.
9. EVALUTION
9.1. Quality of radiographs
All radiographs shall be free of mechanical, chemical, handling related or other
blemishes to the extent that they do not mask and are not confused with the
image of any discontinuity in the area of interest of the object being
radiographed. If any doubt exists as to the true nature of an indication
exhibited by the film, the radiograph shall be rejected and re-shot.
9.2. Viewing facilities for radiographs
Viewing facilities shall provide subdued background lighting of an intensity that
will not cause troublesome reflections, shadows or glare on the radiograph.
Equipment used to view radiographs for interpretation shall provide a variable
light source sufficient for the designated wire to be visible for the specified
density range.
9.3.Radiographic density
9.3.1 Density Limitations
The transmitted film density through the radiographic image of the body of
appropriate hole penetrameter or adjacent to the designated wire of a wire
penetrameter and the area of interest shall be 2.0 minimum and 4.0 maximum.
9.3.2 Density variation
[a] General
If the density of the radiograph anywhere through the area of interest varies by
more than minus 15% or plus30 % from the density through the body of the
hole penetrameter or adjacent to the designated wire of a wire penetrameter
within density limitations, then an additional penetrameter shall be used for
each exceptional area or areas and the radiograph taken.
[b] With Shims
When shims are used the plus 30 % density restriction of [a] above may be
exceeded, provided the required penetrameter sensitivity is displayed and the
density limitation are not exceeded.
9.4. IQI sensitivity
Radiography shall be performed with a technique of sufficient sensitivity to
display the hole penetrameter image and the specified hole, or the designated
wire of a wire penetrameter, which are essential indication of the image quality
of the radiograph. The quality levels required using wire Penetrameters shall
be equivalent to the 2-2T level of method E 142/ or practice E1025, ASME Sec
V Article 22 for hole type penetrameters. The table T-276 Article 2 Sec V
Provides a list of various hole type IQI’s and the diameter of the wires of
corresponding EPS (Equivalent Penetrameter Sensitivity) with the applicable
2T holes in the IQI.
Prepared by Concurred by Approved by
Name : Name :
Design: Design:
DATE
PAGE NO
17 OF 17
PROJECT TITLE
RADIOGRAPHIC EXAMINATION PROCEDURE.
11. RECORDS
The following radiographic records shall be maintained as agreed upon between
the client and Visual
11.1 Sketch
11.2 Weld repair documentation
11.3 Film used
11.4 Thickness of material
11.5 Source to film distance
11.6 Film interpretation record shall contain as the minimum following information
11.6.1. Disposition of each radiograph (acceptable or rejected)
11.6.2. If rejected, cause for rejection (slag, crack, Porosity, LOP,LOF etc)
11.6.3. Surface indication verified by visual examination (grinding marks, weld ripple,
spatter etc.)
11.6.4. Signature of the film interpreter
12. ATTACHMENTS
12.1 Sketch showing location markers and arrow markers
12.2 Radiation warning Sign Board.
12.3 Sample radiographic Report.
DATE
PAGE NO
03 OF 05
PROJECT TITLE
PROCEDURE FOR VACUUM BOX TEST
2. PURPOSE
The purpose of this procedure is provide a guide line to carry out the Vacuum
box test to check soundness of annular joints, bottom( long seam & short seam)
and welding joints for annular plates.
3. REFERENCE CODE
1. API-650 (Latest edition) 7.3.4 & 8.6 Eleventh edition
2. ASME Sec-V
.
4. EQUIPMENT
4.1. The Vacuum box test is performed by using a box with visible window of
fiber glass (i.e.6” Wide by 30” long metallic box with a fiber glass). The
open bottom is sealed against the tank surface by a sponge rubber gasket.
The test scheme shall have suitable connections, necessary valve and
calibrated Vacuum gauge. The gauge shall have a range of 0 psi to 15 psi
or equivalent Pressure limits such as 0 in.Hg to 30 in.Hg.
4.2. The Test scheme shall be demonstrated with sample test block by
application bubble solution at site before conduction the test on the job.
The bubble forming solution shall produce a film that does not break away
from the area to be tested, and the bubbles formed shall not break rapidly
due to air drying or low surface tension, soaps or detergents designed
specifically for cleaning shall not be used for the bubble forming solution.
PAGE NO
PROJECT TITLE
PROCEDURE FOR VACUUM BOX TEST
4.3. A vacuum can be drawn on the box by any convenient method, such as
connection to a gasoline or diesel motor intake manifold or to an air ejector
or special vacuum pump. The gauge shall register a partial vacuum of at
least 2 psi ( 4in.Hg)(15KPa) below atmospheric pressure.
4.4. Bubble forming solution (Brand name / Type will be furnished prior to
execution) to be established vide 4.2 & to be recorded.
5. PERSONAL
The personnel shall be competent and have through knowledge in performing
this method.
6. SURFACE PREPARATION
The surface to be examined and all adjacent areas shall be cleaned thoroughly
and free from all dirt, grease, lint, scale, welding flux, weld spatters, paint, oil
and other extraneous matter that could obstruct surface openings or otherwise
with the examination.
Prior to vacuum testing all joints shall be checked visually.
7. PROCEDURE
The temperature of the surface of the part to be examined shall not be below
400F( 50C) nor above 1250F( 500C)
The weld seam on the test shall be applied with a bubble solution for detecting
leaks prior to placing vacuum box.
The foaming shall be minimized by means of uniform application of bubble
solution.
The gauge shall at least register a partial Vacuum of 21 Kpa or 3 Lbf/in2 for
inspection of the joints
An Overlap of 2” minimum for adjacent placement of the Vacuum box shall be
given for each subsequent examination.
The required partial vacuum shall be maintained for at least for 10 seconds
examination time stop watch to be used after reaching the 21 KPA / Designated
vacuum.
PAGE NO
05 OF 05
PROJECT TITLE
PROCEDURE FOR VACUUM BOX TEST
8. EVALUATION
Bubbles produced by air sucked through the welded seam can detect the
presence of defect.
The tested areas are accepted only when no continuous bubbles formation is
observed.
A minimum light intensity of 1000 lux is required for conducting the
examination.
9. REPAIR/RETEST
Defects in welds shall be repaired by chipping, grinding or melting out the
defects from one side or both sides of the joints, as required and rewelding.
Only the cutting out of defective joints that is necessary to correct the defects
is required.
After repairing retest of Vacuum box test shall be carried out.
10. CLEANING
After test the area shall be thoroughly cleaned for the further activities.
12. SAFETY
Safety shall be followed as per HSE specification during test.
PAGE NO
03 OF 05
PROJECT TITLE
LIQUID PENETRANT EXAMINATION
PROCEDURE.
1. SCOPE:
The scope of this procedure shall apply to all liquid penetrant examinations
carried out during the execution of Tankage Ph II Mahul
2. PURPOSE:
The purpose of this procedure is to ensure that liquid penetrant examinations
are performed in accordance with the project specification, quality control
plan (SEP-QI-001) and applicable codes.
3. REFERENCE:
ASME V Nondestructive Examination - Article 6.
ASME B31.3 Process Piping
API 650 Welded Steel tanks for Oil Storage.
SNT-TC-1A Recommended Practice for Nondestructive Testing Personnel
5. MATERIALS
Penetrant materials used shall belong to the same manufacturer and family
of particular type of Penetrant used batch Certificates for Penetrant materials
shall be maintained.
PAGE NO
04 OF 05
PROJECT TITLE
LIQUID PENETRANT EXAMINATION
PROCEDURE.
6. PROCEDURE
6.1. GENERAL
The liquid penetrant examination method is an effective means for detecting
discontinuities which are open to the surface of nonporous metals and other
materials.
6.2.TEMPERATURE LIMIT
It shall be ensured that the temperature of penetrant materials and the surface
of the materials to be tested shall be between 600 F to 1250 F(160 F to 520 F)
6.3. SURFACE PREPARATION
The surface to be examined and all adjacent areas shall be dry and free of all
dirt, grease, lint, scale, welding flux, weld spatter, paint, oil and other
extraneous matter that could obscure surface openings.
6.4.DRYING AFTER PREPARATION
After cleaning, drying of surfaces to be examined shall be accomplished prior
to application of the penetrant.
6.5. APPLICATION OF PENETRANT
The penetrant is applied on the surfaces to be examined by spraying. A liquid
fluorescent or visible dye Penetrant is applied evenly over the surface being
tested and allowed to enter discontinuities open to surface.
6.6. PENETRATION TIME
Penetrant dwell time shall be minimum 10 min. and maximum 60 min.
Ref. Table T-672 ASME Sec V Article 6.
6.7. REMOVAL OF EXCESS PENETRANT
Excess solvent removable penetrants shall be removed by wiping with a cloth
or absorbent paper, repeating the operation until most traces of penetrant
have been removed.
The remaining traces shall be removed by lightly wiping surface with cloth or
absorbent paper moistened with solvent.
To minimize removal of penetrant from discontinuities, care shall be taken to
avoid the use of excess solvent.
Flushing the surface with solvent, following of the penetrant and prior to
developing, is prohibited
DATE
PAGE NO
05 OF 05
PROJECT TITLE
LIQUID PENETRANT EXAMINATION
PROCEDURE.
7. ACCEPTANCE CRITERIA
All indication shall be evaluated in terms of the following applicable
acceptance criteria.
[a] ASME B 31.3
[b] ASME Sec VIII Div 1,APPENDIX-VIII
[c] API 650
[d] T-676 Article 6 ASME Sec V
8. SAFETY
Penetrant materials are highly volatile, relatively toxic and may cause skin
irritation. Use adequate ventilation at all times and avoid prolonged skin
contact. Penetrant materials aerosol cans should be kept out of direct sunlight
or areas in excess of 1300F.
PAGE NO
01 OF 02
PROJECT TITLE
PROCEDURE FOR OIL-CHALK TEST
2. PURPOSE:
The purpose of this procedure is provide a necessary guide line to carry out oil-
chalk test to check the weld joint of shell to annular plate.
3. SURFACE PREPARATION:
The surface to be examined and the adjacent area within at least 1” shall be
cleaned thoroughly, must be dry and free from dirt, oil, grease, scale, welding
flux, spatters, paint and other foreign matter that could obstruct surface
openings or otherwise interfere with the examination.
4. APPLICABLE CODE:
API 650 Sec (Clause 7.2.4 (d)) / ASME Section V article 6).
5. PROCEDURE:
After completion of root weld from inside of the shell to bottom joint, apply wet
chalk solution by brush on the root weld uniformly.
Allow the weld joint to dry thoroughly and then spray diesel/ kerosene on the
opposite side of the weld (outside) by using the hand spray pump.
PAGE NO
02 OF 02
PROJECT TITLE
PROCEDURE FOR OIL-CHALK TEST
8. INSPECTION REPORT:
Test shall be carried out jointly and to the satisfaction of the Engineer-in-charge.
Test to be recorded in the approved format.
CONTRACTOR
Hindustan Petroleum Crop. Ltd. Hindustan Petroleum Crop. Ltd
DOC NO
DATE
PAGE NO
01 OF 03
PROJECT TITLE
PROCEDURE FOR PNEUMATIC PRESSURE TEST
1. SCOPE
The objective of the pneumatic pressure testing is to locate leaks in the welds
of the reinforcement plates to shell plates and pontoons of floating roof .This
is accomplished by applying a soap solution to a local area of the pressure
boundary surface and creating a differential pressure across that local area of
the boundary causing the formation of bubbles as leakage gas passes through
the solution.
2. PURPOSE
The purpose of this procedure is provide a guide line to carry out the
Pneumatic pressure test to check soundness of welds of the reinforcement
plates to shell plate and the welds of roof seam of cone roof tank.
3. REFERENCE CODE
1. API-650 (Latest edition) (7.3.4) Eleventh Edition
2.TABLE I-1021 of ASME Section V, July 1, 2008 Edition.
4. EQUIPMENT
4.1. The test scheme shall have suitable connections, necessary valve and
calibrated pressure gauge. The gauge shall have a range of 0 psi to 15
psi or equivalent Pressure limits such as 0 in.Hg to 30 in.Hg.
4.3. Gases: The test gas will normally be air; however inert gases may be
used.
5. PERSONAL
The personnel shall be competent and have thorough knowledge in
performing this method.
DATE
PAGE NO
02 OF 03
PROJECT TITLE
LONI REVAMPING PROJECT PROCEDURE FOR PNEUMATIC PRESSURE TEST
6. SURFACE PREPARATION
The surface to be examined and all adjacent areas shall be cleaned
thoroughly and free from all dirt, grease, lint, scale, welding flux, weld spatters,
paint, oil and other extraneous matter that could obstruct surface openings or
otherwise with the examination.
Prior to pneumatic pressure testing, joint shall be checked visually.
7. PROCEDURE
SHELL APPURTENANCES-
REINFORCEMENT PLATES TO SHELL PLATES WELDS
The temperature of the surface of the part to be examined shall not be
below 400F( 50C) nor above 1250F( 500C)
Make 6mm diameter-screw threaded Tell tale hole in the reinforcement
pads before its welding to shell and shell appurtenances.
The reinforcements pads shall be tested by applying up to 2 psi in the
pressure gauge between the tank shell and reinforcement plates on each
opening using tell tale hole
Use soap suds on welds between reinforcement plate to shell,
reinforcement plate to appurtenances to shell plate if any defect noticed.
Repair the defective weld and repeat the test till entire satisfaction.
Close the tell tale with a bolts or screw.
DATE
PAGE NO
03 OF 03
PROJECT TITLE
LONI REVAMPING PROJECT PROCEDURE FOR PNEUMATIC PRESSURE TEST
9. REPAIR/RETEST
Defects in welds shall be repaired by chipping, grinding or melting out the
defects from one side or both sides of the joints, as required and rewelding.
Only the cutting out of defective joints that is necessary to correct the defects
is required.
After repairing retest of Pneumatic pressure test shall be carried out.
10. CLEANING
After test the area shall be thoroughly cleaned for the further activities.
The test shall be carried out in presence of the Engineer In charge /HCPL
Inspector.
Upon satisfactory inspection, a report shall be prepared as per HPCL
approved format.
12. SAFETY
Safety shall be followed as per HSE specification during test.
Vishal Structurals Pvt. Ltd. Hindustan Petroleum Crop. Ltd. Hindustan Petroleum Crop. Ltd
DOC NO
V
DATE
PAGE NO
03 OF 05
PROJECT TITLE
JOB PROCEDURE FOR HYDRO TEST / WATER FILL
UP TEST
2. PURPOSE
The purpose of this procedure is providing the guideline and sequential steps for the
hydro test / water fill up test for the tank.
3. CHECK LIST
After completion of the erection, welding and NDT the following points shall be
checked before testing.
All the mechanical activities completion in respect of the drawing and HPCL
Specification and code requirements.
Radiography completion including repairs.
The entire NDT test like chalk-diesel test, LPT, RF .Pad pneumatic test, vacuum box
test completion.
Finally mechanical clearance from the Engineer-In-Charge shall be taken before
Hydrotest in approved format
4. TEST MEDIA
Test media shall be in iron free water, which is clean and free of silt i.e.; Portable
water
5. PROCEDURE
Proper arrangement shall be carried out for the water filling (pipe connection from
the water resource point and providing valves and NRV wherever required.
markers shall be provided on the shell, 500 mm from the bottom to check tank
settlement. Size shall be 50 X 50 X 6mm angle and 100 mm long. The nos. of
setting marker shall be minimum 8 Nos or as per the approved Drg.
PAGE NO
04 OF 05
PROJECT TITLE
JOB PROCEDURE FOR HYDRO TEST / WATER FILL
UP TEST
Settling markers shall be provided at every 300 outside the tank at a height of 500
mm from the top of annular plate.
Setting marker shall be welded and initial level reading shall be taken with respect
to the permanent benchmark using dumpy level / Total station
Shell settlement measurements shall be made after tank erection, prior to
hydrotesting and during water filling at 1000 mm intervals up to maximum filling
height of tank.
The levels taken before water filling called as initial level of the tank and shall be
record in an approved format.
The water filling height shall be restricted to the max. Liquid Level or up to the
curb angle.
The water filling shall be carried out in four stages (25%, 50%, 75% & 100% of the
max liquid level of the tank)
Any leaks observed in the shell joint during the hydro test shall be noted and
repaired with the water level min. of 300mm below the leak spot.
The repaired shall be carried out as per the procedure and tank test shall be
recommenced.
After each stage of filling, a load stabilization period shall be observed as
minimum 24 hours max between each stage of filling.
During the stabilization period the settlement reading shall be observed and
recorded jointly with HPCL Engineer-In-Charge through dumpy level only.
Filling rate shall be not exceed 5 meters per day.
After completion of the water filling the water load shall be maintained for 24
hours. After 24 hours the final settlement reading shall be recorded jointly with
engineer-In-Charge.
Tank shall be emptied at a maximum water level variation rate of 5 meters per
day. Care shall be taken that top manholes are open during empty operation of
conical roof tanks.
If salt water is used then corrosion inhibitor should be sprayed (mixed) prior to
filling / after hydro test the tank should be thoroughly cleaned with sweat water.
DATE
PAGE NO
05 OF 05
PROJECT TITLE
JOB PROCEDURE FOR HYDRO TEST / WATER FILL
UP TEST
6. CLEANING
After draining the water the tank shall be thoroughly cleaned, free from dirt and
foreign materials and shall be dried by air.
7. RECORDS
Records shall be prepared and submitted to Engineer in-charge for approval.
8. SAFETY
All Safety precaution shall be taken during water fill up test.
9. REFRENCE
(A) API 650
(B) OISD 129
(C) PO Tech Specification
DATE
PAGE NO
01 OF 04
PROJECT TITLE
JOB PROCEDURE FOR SURFACE PREPARATION BY
SHOT BLAST CLEANING AND APPLICATION OF
PAINTS
1. SCOPE
This procedure defines the requirements for surface preparation, selection &
application of paint on external surface of pipes & structural steel, ducts, Tanks
and other items to be installed / constructed at LONI revamping project.
2. PURPOSE
The purpose of this procedure is to carry out the shot blasting & primer painting of
all the tanks structures & pipes, ducts etc. in a systematic way to minimize
available errors and to provide guide lines for best achievement in shot blasting &
primer painting at LONI revamping project.
4. EQUIPMENT
To perform this above work the following Equipment / Materials are required from
our end.
1. All Tools
2. Spray Gun
3. Air Hose
4. Hopper
5. Air Filter Compressor of capacity
DATE
PAGE NO
02 OF 04
PROJECT TITLE
JOB PROCEDURE FOR SURFACE PREPARATION BY
SHOT BLAST CLEANING AND APPLICATION OF
PAINTS
6. EIcometer
7. Abrasive Paper such as good quality surface with an abrasive powder glass,
sand/Flint/emery paper of different rating shall be used
8. Cu Slag
9. Air Compressor of capacity 5.6 m3 - 7 m3
10. Brushes (Good quality Nylon bristles with long & flexible bristles shall be used)
11. Paints
5. SURFACE PREPARATION
All the tack weld should be grinded and welding slag, spatters should be
cleaned. The Surfaces shall be Cu Slag blast cleaned by using Cu slag
blasting. All other contaminants: oil, grease etc. shall be removed by use of
an aromatic solvent. The surface shall be cleaned using copper slag of
approved quality meeting tender specifications, at appropriate distance and
angle depending of nozzle size maintaining constant velocity and pressure.
The blasting nozzle should be venturi style with tungsten carbide or boron
carbide as the materials for liners. Nozzles orifice may vary from 3/16 ” to 3/4
” .On completion of blasting operation, the blasted surface shall be clean and
free from any scale or rust and must show a grey white metallic luster. Primer
or first coat of paint shall be applied within maximum 4 hrs of surface
Preparation. Compressor will be oil less compressor. Air pressure will be 7.00
Kg/Sq. Cm, distance & angle of the nozzle will depend on nozzle size
maintaining constant velocity & pressure. Compressed air shall be free from
moisture & oil. There will be one barricading in between sand blasting &
painting yard. Cu slag blasting work will not be performed when relative
humidity beyond 85 %. After blasting, surface will be inspected by photograph
in SIS-05 5900-1967 Code of SA 2 ½.
DATE
PAGE NO
03 OF 04
PROJECT TITLE
JOB PROCEDURE FOR SURFACE PREPARATION BY
SHOT BLAST CLEANING AND APPLICATION OF
PAINTS
6. SELECTION OF PAINT
Selection of Paint system shall be as per Tender Specification
7. PAINT APPLICATION
7.1 PRIMER PAINTING
Blasted surface will be primed with one complete application of primer within 4
hrs of blasting. Primer paint will be Approved Vendor make as per painting
specification. Application of each coat will be continuous and uniform. Primer
application will be performed by Spray Gun. Primer painting DFT thickness will
be checked as per specification.
9. DOCUMENTATION
9.1. A written QAP with Procedure qualification trials and for the actual work.
9.2. Results of measurements of temperatures, relative humidity, surface Profile,
Film thickness, holiday detection, adhesion tests with signature of
appropriate authority.
9.3. Type of testing equipments and calibration.
9.4. Code & batch numbers of paint material used.
DATE
PAGE NO
04 OF 04
PROJECT TITLE
JOB PROCEDURE FOR SURFACE PREPARATION BY
SHOT BLAST CLEANING AND APPLICATION OF
PAINTS
12. SAFETY
Safety Precaution shall be followed as per HSE manual / specification.
DATE
PAGE NO
03 OF 04
PROJECT TITLE
PROCEDURE FOR BITUMEN CARPETING
1. SCOPE
This work shall consist of construction in Anticorrosive layer, layer of
Premixed Carpet and a layer of Seal Coat over the tank foundation pad.
2. PURPOSE
The purpose of this document is to state the requirement of material,
workmanship and construction procedure to be followed during the execution
of tank pads works.
3. MATERIALS
Bitumen:
Bitumen to be used for bitumen macadam shall conform of 60 / 70 grade as per IS:
73
4. PROCEDURE
Anti – corrosive layer will consist of screened coarse sand mixes with 155/6
bitumen or equivalent (8 to 10 % by volume).
Sand shall be clean, dry coarse, hard, sharp, free from all impurities and shall
conform to IS: 383.
Bitumen shall be heated to a temperature 1750 C to 1900 C with 3% kerosene
if required and sand shall be thoroughly mixed with it in mixing drums to give a
uniform mixture and shall be laid over the pad in line, grade and levels as
shown on drawings.
The anti- corrosive layer shall be then tamped to form hard mass of uniform
50 mm thickness.
For Premix Carpet, Sand shall be as per specification. The stone chipping
shall be of hard black trap. It shall be obtained from approved quarry. The
grading of stone shall be 12 mm and down size.
DATE
PAGE NO
04 OF 04
PROJECT TITLE
PROCEDURE FOR BITUMEN CARPETING
Bitumen required for the work shall be 60/70 grade as per IS: 73 or its
equivalent quality used for premix work.
The anti- corrosive layer on which the premix is to be laid shall be thoroughly
cleaned of all dust and loose materials. A coat of heated bitumen at the rate of
1 Kg / m2 shall be uniformly applied.
A seal coat 12 mm thick shall be laid over Premix Carpet layer using bitumen
60 / 70 @ 100 kg / 100 m2 of surface area & mixing with stone chips of size 6
mm @ 0.92 m3 / 100 m2 of surface area as per correct grade and camber and
compaction of the layers done using plate compactor.
DATE
PAGE NO
02 OF 07
PROJECT TITLE
INSPECTION TEST PLAN FOR TANK FABRICATON
1.0 GENERAL
The enclosed ITPs shall be followed for the works to be performed by the Contractor
under this Tender. The provisions indicated for stagewise inspection by HPCL are a
minim um and the contractor shall develop a detailed ITP and obtain approval for the
same prior to commencement of work. Contractor to carry out 100% examination of all
activities.
2.0 LEGEND
W: Witness Point;
An activity which requires witnessing by HPCL when the activity is performed.
DATE
PAGE NO
03 OF 07
PROJECT TITLE
INSPECTION TEST PLAN FOR TANK FABRICATON
STORAGE TANKS
A. PRIOR OF FABRIATION
1. Acceptance of the tanks foundation WC HP
2. Incoming Material
Owner’s Supply WC Rw WC Rw
Contractor’s supply, including check testing WC HP
a) Procedure:
i) WPS to be written for all the Weld Joints for
for Bottom /Shell/Fl. Roof/A ppertunance etc
b) Testing :
i) Carbon Steel WC HP
c) Approval of Final WPS / PQR WC HP
DATE
PAGE NO
04 OF 07
PROJECT TITLE
INSPECTION TEST PLAN FOR TANK FABRICATON
4. Sequence of welding WC S
6. Banking of electrodes WC S
7. Inter-pass cleaning WC S
SHELL
1. Plate size, marking and cutting WC Rw
DATE
PAGE NO
05 OF 07
PROJECT TITLE
INSPECTION TEST PLAN FOR TANK FABRICATON
15. Shell to bottom I/S welding root run visual/ oil chalk test WC HP
18. Radiography
a) Radiography interpretation WC HP
b) Check shot for Radiography WC HP
FLOATING ROOF
DATE
PAGE NO
06 OF 07
PROJECT TITLE
INSPECTION TEST PLAN FOR TANK FABRICATON
C. TESTING
DATE
PAGE NO
07 OF 07
PROJECT TITLE
INSPECTION TEST PLAN FOR TANK FABRICATON
5. Hammer test WC HP
7. Vacuum test WC HP
1. SCOPE:
3. REFERENCE:
IS 456
4. JOBS PRIOR TO RCC WORKS:
A) MARKING
Marking points and measuring the slope of Apron and beam slope
(it should be towards the drain connection point in 1:100) getting
hold point clearance from HPCL.
B) FORM WORK
Submission of design/plan for shuttering and props.
Approved quality formwork to be provided as per HPCL approved
drawings. The forms shall be butting with each other in straight
lines, the corners of the boards being truly at right angles.
Maximum care shall be taken to make the form work watertight.
The contactor shall be permitted reuse of forms brought new on the
work for exposed concrete work as specified below.
Plywood Forms 6 Reuses (Max.)
Steel Forms 10 Reuses (Max.)
The Engineer – in – Charge may, at his absolute discretion, order
removal of any forms considered unfit for use in the work
irrespective of the number of uses specified above.
Inside dimensions to be marked
C) REINFORCEMENT STEEL.
D) CONCRETING
Mix design
The mix shall be designed to produce the grade of concrete having
the required workability and characteristic strength.
The design mix shall be conforming to the guidelines of IS: 10262
Mix design with supportive laboratory tests shall be submitted to
the Engineer-in-Charge for approval
Batching
Mixing
The mixing of concrete shall be strictly carried out in an approved
type of mechanical concrete mixer.
Mixer shall comply with IS: 1791
The mixing shall be continued until there is a uniform distribution
of the material and the mass is uniform in colour and consistency
Mixing time shall be as indicated in the following table
Capacity of Mixer Minimum Mixing Time
3
2 m or less 1 ½ minutes
3 m3 2 ½ minutes
5 m3 3 minutes
All records and charts for the batching and mixing operation shall
be prepared and maintained by the Contractor as per the
instructions of the Engineer-in-Charge
Hand mixing of concrete shall be permitted with the addition of
10% more cement.
For highly lean concrete, hand mixing may be permitted by the
Engineer-in-Charge as a special case. Ten percent (10%) extra
cement shall have to be added to the normal mix when mix by hand
Compaction
Concrete shall be thoroughly compacted with vibrators of pin
dimensions 3” and 4” and fully worked around the reinforcement,
embedded fixtures and into corners of form work before setting
commences and shall not be subsequently disturbed
The vibrators shall be of immersion type with operational
frequency ranging between 8,000 and 12,000 vibrations per
minute.
All vibrators shall comply with IS: 2505.
Screed board concrete vibrators or concreting vibrating tables or
form vibrators conforming to IS: 2506, 2514 and 4656,
Curing
Concrete shall be cured by keeping it continuously moist wet for
the specified period of time.
Curing shall be started after 8 hrs. of placement of concrete, and in
hot weather after 4hrs.
The water used for curing shall be of the same quality as that used
for making of concrete.
Curing shall be assured by use of an ample water supply under
pressure in pipes with all necessary appliances such as hose,
sprinkles etc.
A layer of sacking, canvas, Hessian, of other approved materials
which will hold moisture for long periods and prevent loss of
moisture of the concrete shall be used as covering
Exposed surfaces of concrete shall be maintained continuously in
damp or wet conditions for at least the 1st 7/10 days after placing of
concrete.
For curing the concrete in pavement floors, flat roofs or other level
surfaces, the ponding method of curing is preferred after the expiry
of first 24hrs during which (i.e. 1st 24 hrs) the concrete shall be
cured by use of wet sacking, canvas Hessian etc.
E) ACCEPTANCE CRITERIA
" # $ %&' (
) * )
+, - , . / (*0
1, - . , 2
'3 - . .. , 2
/ !0 2 4 5 6 2# .. , 2 7 .
/ 8 "
, $ $ $ 9:1 / 9 : ( / 7 2 7 ..
$ 7 ; 4 $ $ 6 ) 0 ! $
7 2 . 2 $
/ !0 #
0 ;2 7 2 $ 2 0 + 8< 8 - * # $$ %
0 7 2 7 .. $ # 7 2 $
7 2 % 7 2 .. $
7 2 =
( # $ 8 7 2 #8
2 $
6 ) 2
36 ) 2 $ . $ . 7
$ $ .
6 0 . % 7 2 ! 0 #
;2 . .
!"
0 $ . 2 7 .
2 # 7 2 2# #
. . 0 # 7 . # $
$ & $. # . .. $ #
. 7 2 '' ) &- &( > . 7 2 & )
( . $ 0 . 7 7 2 . 2 $
2 2 . 2#
6 #$ % !
0 $. =$ % . 7 2 0#. ?<@* #
2 2 7 2 # 7 2
$ # ..
6 & # %$
0 $ . 2 0#. ?<@ 7 7 ' /
$. 0 $ . 2 $ $ .
# 2# $ $ . 2 2# A
# 0 .# $ 7 2 5 # 2
;2 0 $ . 7 # $.
# $ 7 2 $ $ $.
$ $. . $.
2 2 % % . 7 # ; ;
$. 0 . $ . 7
%
6 & # %$ ' ( )
0 0 $ . $. = 2
4 6 = 2 $ .
0 = 2 2 % . $
*
0 $ 4 / !0 # 6 7
! 1 * 8! - *
B. - *
! 0 $. C1 *
! 0$ 1( 4 '$ $ %6 $$ %
1 * 8 $ = . - *
- * 2 2 $
2 7 1 * #
"
( 0 $ . 7 2 . 7 2 . % $. .
B. D 1(
9D . 1 D (
1 D . 'D -(
DOC NO
V
DATE
PAGE NO
03 OF 05
PROJECT TITLE
TANKAGE JOB AT LONI TERMINAL JOB PROCEDURE FOR Puncture TEST / Rain water
FILL UP TEST
2. PURPOSE
The purpose of this procedure is to check the design compatibility w.r.t. fabricated
and erected roof under testing.
3. CHECK LIST
After completion of the erection, welding and NDT, Pneumatic testing, diesel chalk
testing of outer rim, visual checking of welds (100%) and rectification if any the
following points shall be checked before testing.
All the mechanical activities completion in respect of the drawing and HPCL
Specification and code requirements.
NRV in central roof drain to be checked.
The entire NDT test like chalk-diesel test, LPT, RF .Pad pneumatic test, vacuum box
test completion.
Punctures with couplings fitted in the deck and adjacent pontoons to be ensured
before commencing of Hydrotesting.
Puncture test to be carried out when roof is in highest position.
Finally mechanical clearance from the Engineer-In-Charge shall be taken before
Puncture test in approved format.
4. TEST MEDIA
Test media shall be in iron free water, which is clean and free of silt i.e.; Portable
water.
5. PROCEDURE
Initial reading of
a. RIM SPACE (atleast at 08 POINTS) to be taken.
b. Location of rolling ladder (drum) w.r.t. shell to be taken and spirit level on ladder
staircase.
c. Deck immersion and rim position w.r.t. tank shell should be noted.
d. Water fill height to be noted.
Out of two adjacent pontoons one to be punctured and time to be noted along with
the height of water column coming out of hole ( this shall help in evaluating the final
height of water after fillup).
Again after the water settles down and no more significant change seen note the
time taken and check for any leakage in adjacent pontoon, then repeat the points ( a
to d) and puncture next ( adjacent) pontoon.
Again note the readings (repeat as above).
After that puncture the central deck and repeat the procedure and steps a to d.
1. Blind the NRV and fill the central deck till 10” and keep the same for one day without
Puncture test condition and with puncture test condition.
NOTE: NRV to be opened thereafter to see the water flow afterwards from roof drain and
time taken to remove the water.
6. CLEANING
After draining the water the tank shall be thoroughly cleaned, free from dirt and
foreign materials and shall be dried by air.
7. RECORDS
Records shall be prepared and submitted to Engineer in-charge for approval in
approved format.
8. SAFETY
All Safety precaution shall be taken during the test.
9. REFRENCE
(A) API 650
(B) PO Tech Specification
DOC NO
VS
DATE
PAGE NO
04 OF 05
PROJECT TITLE
TANKAGE JOB AT LONI TERMINAL JOB PROCEDURE FOR HYDRO TEST / WATER FILL
UP TEST
ACCEPTANCE CRITERIA:
1. At each stage of water filling the time taken in water settling and Tilting should be in
conformance to the approved floating roof design within the mentioned tolerances of all the
variables like RIM SPACE, TILTING, TIME TAKEN TO WATER FILL.
2. For rain water fill test the water filled should overflow on ED and for the period of 24 hrs the
water should in no case come out of deck outer rim (i.e. immersion should be as per design
for water).
3. The time taken by the roof drain water to come out from central roof drain sump should be in
conformance to the design and code requirements ( Appendix C, API 650).
NOTE:
After the completion of test the punctures should be blinded and DP tested for leakage when
roof at lowest position( after Hydrotesting if welded, else coupling should be seal tighted.
DOC NO
DATE
PAGE NO
05 OF 05
PROJECT TITLE
TANKAGE JOB AT LONI TERMINAL JOB PROCEDURE FOR HYDRO TEST / WATER FILL
UP TEST
Prepared by Concurred by Approved by
Name : Name :
Design: Design:
CONTRACTOR . Hindustan Petroleum Crop. Ltd. Hindustan Petroleum Crop. Ltd
QUALITY
ASSURANCE
PROGRAMME
CONTENTS
______________________________________________________________
CLAUSE DESCRIPTION
1.0 INTRODUCTION
2.0 DEFINITIONS
In case of any conflict between this specification and other provisions of the
contract / purchase order, the same shall be brought to the notice of HPCL,
at the stage of bidding and shall be resolved with HPCL, prior to the
placement of order.
2.0 DEFINITION
2.1 Bidder
For the purpose of this specification, the work “Bidder” means the
person(s), firm, company or organization who is under the process of being
contracted by HPCL/Owner for delivery of some products (including service).
The word is considered synonymous to supplier, contractor or vendor.
2.2 Correction
2.2 Process
Set of inter-related resources and activities which transform inputs into
outputs.
1.1.1 The bidder shall understand scope of work, drawings, specifications and
standards etc., attached to the tender / enquiry document, before he
makes an offer.
1.1.2 The bidder shall submit milestones chart showing the time required for
each milestone activity and linkages between different milestone activities
along with overall time period required to complete the entire scope of
work.
1.1.3 The bidder shall develop and submit manpower and resource deployment
chart.
1.1.4 The bidder shall submit, along with the bid, a manual or equivalent
document describing / indicating / addressing various control / check points for
t he purpose of quality assurance and the responsibilities of various
functions responsible for quality assurance.
2.0
4.2.1 During job execution, the bidder shall fully comply with all quality
documents submitted and finalized / agreed against the requirements of
this specification. Approval of HPCL on all these documents shall be
sought before start of work.
4.2.3 Bidder shall facilitate HPCL/Owner during quality / technical audits at his
works / sites.
5.2 After award of work the bidder may review augmentation of manpower
and resources deployment chart (submitted earlier), detail it out, if so
consented by HPCL/Owner and resubmit the same as “Issued for
implementation”.
5.3 The bidder shall plan the contract scope of work on quality plan format
such that no major variation is expected during delivery of contract
scope of work. These quality plan shall be made on enclosed format
complete in all respect. The quality plan shall be assumed to be
detailing bidder’s understanding and planning for the contract / offered
scope of work. The bidder shall plan the type of resources including
various work methodology which he agrees to utilize for delivery of
contract scope of work.
5.4 The bidder is required to review the contract at all appropriate stages to
evaluate his capabilities with respect to timely and quality completion of
all activities pertaining to contracted scope of work and shall report to
HPCL/Owner of constraints, if any.
5.5 The design activities, if any, performed during delivery of contract scope
of work shall be so controlled that the output is reliable enough. It is
expected that during development of design, the bidder shall take
recourse to detailed checking, inter departmental reviews and documented
verification methods.
5.6 For all documents which the bidder is likely to utilise for delivery of
contract scope of work, a system must exist which assures that latest /
required version(s) of the document(s) is available at all location / point
of use.
5.7 In case the bidder decides to sub – contract any part / full of the contract
scope of work (without prejudice to main contract condition), the bidder
shall
- Evaluate the technical and financial capabilities and past performance of
the sub-contractor(s) and their products and/or services before awarding
them with the sub-contracted scope of work. Selection of a sub-
contractor should meet HPCL approval in documented form.
- Requirement of this specification shall be enforced on sub-contracted
agency also. The bidder shall choose sub-contractor based on their
capability to meet requirements of this specification also.
5.8 Bidder shall establish methodology such that the materials supplied by
the owner / HPCL shall be suitably identified in such a manner that
either through identification or some other means, sufficient traceability is
maintained which permits effective resolution of any problem reported in
the outputs.
5.9 Critical activities shall be identified and the bidder is required to have
documented methodologies which he is going to utilize for carrying out
such activities under the contract scope of work. Wherever it is difficult
to fully inspect or verify the output (special process) bidder shall pre-
qualify, the performers and methodologies.
5.10 All inspections carried out by the bidder’s surveillance inspection staff
shall be in conformity to quality plans and / or inspection and test plans.
All inspection results shall be duly documented on controlled / agreed
forms such that results can be co-related to specific product, that was
inspected / tested.
5.11 All inspection, measuring & test equipments (IMTEs) shall be duly
calibrated as per National / International standards / codes and only,
calibrated and certified IMTEs shall be utilized for delivery of contract
scope of work.
5.12 All outputs / products delivered against contract scope of work shall be
duly marked such that their inspection status is clearly evident during all
stages / period of the contract.
5.15 Bidder shall establish appropriate methodologies for safe and effective
handling, storage, preservation of various materials / inputs encountered
during delivery of contract scope of work.
5.16 Bidder shall prepare sufficient records for various processes carried out
by him for delivery of contract scope of work such that requirements of
this specification are objectively demonstrate. In case HPCL/owner finds
that enough objective evidence / recording is not available for any
particular process, bidder shall be obliged to make additional records so
as to provide sufficient objective evidence. The decision of HPCL/owner
shall be final and binding on such issues.
5.17 The bidder shall arrange internal quality audits at quarterly intervals, to
independently assess the conformance by various performers to the
requirements of this specification. The findings of such assessment shall
be duly recorded and a copy shall be sent to HPCL/owner for review.
For all special processes, bidder shall deploy only qualified performers. Wherever HPCL
observes any deficiency, the bidder shall arrange the adequate training to the
performer(s) before any further delivery of work.
QUALITY ASSURANCE PLAN FOR CONSTRUCTION OF STORAGE TANKS
CUSTOMER : DATE :
CONTRACTOR : QAP NO. :
PROJECT : PAGE :
2 Dimensions and M Meas. & Visual 100% APPD DRGS/ ASTM A 6,A20 IR 2 1
surface quality DATA SHEET
3 Lamination free M Visual, UT/MPT (if All edges API 650 ASME Sec. VII MFTRS TC & 3 1 Not reqd. for
reqd.) Div. I IR structurals.
2. Pipes for nozzle 1 Physical, chemical M Physical & As per APPD DRGS/ A 106GR B/C, MFTRS TC 3 1* 1,2 *If specified in WO
properties, heat Chemical Tests specification DATA SHEET API 5L Gr. B
treatment
3. Flanges for nozzles 1 Physical, chemical M Physical & As per APPD DRGS/ ASTM A 105 & A MILL TC 3 3/1 1,2
properties, heat Chemical Test specification DATA SHEET 181
treatment
2 Dimensions & surface M Meas. & Visual 100% APPD DRGS/ ANSI B 16.5 IR 2 1 1,2
quality DATA SHEET
4 Pipe fittings 1 Physical, chemical M Physical & As per APPD DRGS/ As per WO/ MFTRS TC 3 3/1
properties, heat Chemical Tests specification DATA SHEET ASME SA 234
treatment
2 Dimensions & surface M Meas. & Visual 100% APPD DRGS/ ANSI B 16.9 IR 2 1 1
quality DATA SHEET
5 Bolts, nuts for nozzle flanges & 1 Physical, chemical M Physical & As per APPD DRGS/ ASTM A 193 & MFTRS TC 3/2 2,1
structurals properties, heat Chemical Tests specification DATA SHEET 194/ IS 1367
treatment C. L. 4.4.6
2 Dimensions & surface M Meas. & Visual 100% APPD DRGS/ ANSI B 1.1/B IR 2 1 IOC to witness 10%
quality DATA SHEET 1.2/ B 18.2.2 random meas &
100% visual.
SL. DESCRIPTION OF ITEMS CHARACTERISTICS TO CAT TYPE/METHOD EXTENT OF REFERENCE ACCEPTANCE FORMAT OF AGENCY REMARKS
NO. BE CHECKED OF CHECK CHECK DOCUMENTS STANDARDS RECORDS P W V
IN PROCESS:
6. Welding procedure specification Correctness M Scrutiny 100% WPS WPS-ASME WPS 2 1 To be checked
proposed SEC. IX and approved by
IOC before tests.
7 Welding procedure qualification Desired property of M Physical & 100% WPS ASME – SEC ASME WPS & 2 1,2
test and record welding, establishing Chemical Tests IX PQR Formats
correctness of
welding variables
8 Welders Performance Ability of welders to M Radiography 100% WPQ ASME SEC IX ASME WPQ 2 1,2
Qualification make sound weld format
9 Plate cutting for bottom, shell & Dimensions, M Meas. & Visual 100% Cutting Layout APPD. DRGS. IR 2 2 1
roof checking diagonal & Plan
squaring
10 Rolling of Plates Dimensions & M Meas./ Visual 100% APPD. DRGS. APPD. DRGS. IR 2 2 1
Shape
11 Fittments of weld joints Alignment, Edge CR Visual, Meas, 100% APPD. DRGS. APPD. DRGS. IR 2 2,1 H
preparation, root Plumpness
gap, cleanliness
along seam
12 Root run after back gauging of Free of flaw M Visual 100% API 650 API 650 IR 2 2,1
Butt weld joints
13 Finished Butt weld joints 1 Smoothness and M Visual 100% API 650 API 650 IR 2 2,1
Reinforcement
2 Internal Flaws CR Radiography API 650 & API 650 & WO ASME Sec. VIII IR 2/3 2,1 1 H
WO Div. I, UW-51b
3 Peaking/ Banding/ M Meas/Plump 100% API 650 API 650 IR 2 2,1
Circularity
14 All Lap Joints of Bottom Plates 1 Lay out, Edge Prepn M Visual 100% API 650 API 650 IR 2 2,1
2 Welding M Visual, Vacuum 100% API 650 API 650 IR 2 2,1
Test, Pneumatic
Test
SL. DESCRIPTION OF ITEMS CHARACTERISTICS TO CAT TYPE/METHOD EXTENT OF REFERENCE ACCEPTANCE FORMAT OF AGENCY REMARKS
NO. BE CHECKED OF CHECK CHECK DOCUMENTS STANDARDS RECORDS P W V
15 Bottom plates sand blasting 1 Cleanliness/ Surface M Visual / Meas. 100% WO Painting Spec. IR 2 1,2
underside painting Profile
2 Coating thickness M DFT, Elcometer 100 % WO Painting Spec. IR 2 1,2
16 Nozzle to flange & nozzle to Dimension, M Visual, Plumb, 100% APPD. DRGS/ API 650/ IR 2 1,2
shell Orientation of Meas API 650 APPD. DRGS
nozzle, projection,
elevation, fittment
17 RF Pad/ Nozzle to Shell Leak tightness M Pneumatic soap 100% API 650 API 650 IR 2 1,2
suds
18 Shell to Annular plate 1 Weld soundness M Visual/ Meas. 100 % APPD DRGS API 650 IR 2 1,2
2 Leak tightness M Penetrant/ 100% API 650 API 650 IR 2 1,2
19 Deck plate lap joints 1 Fitment, dimensions M Visual/ Meas. 100% APPD DRGS API 650 IR 2 1,2
Slope
2 Weld Soundness M Visual/ 100% API 650 API 650 IR 2 1,2
Penetrant
20 Rim bulk head compartment 1 Fitment / Dimension M Visual & Meas 100% APPD DRGS API 650 IR 2 1,2
2 Welding M LPT/Pneumatic 100 % API 650 API 650 IR 2 1,2
21 Splice joints of rafters/columns Dimensions & M Visual & Meas. 100% APPD DRGS/ API 650 IR 2 1,2
Welding API 650
22 Appurtenances, leg supports Alignment, M Visual /Meas. 100% APPD DRGS API 650 IR 2 1,2
fabricated appurtenances Dimension, Weld
soundness
23 Central Sump 1 Fitment M Visual / Meas. 100% APPD. DRGS. API 650 IR 2 1,2
2 Weld soundness M DPT/ & Visual 100% API 650 API 650 IR 2 1,2
24 Piping for fire water/foam system 1 Layout & fitment M Visual, Meas. 100% APPD. DRGS. APPD. DRGS. IR 2 1,2
2 Welding quality M Root DPT & 100% APPD. DRGS. APPD. DRGS. IR 1 1,2 1 10% of DPT shall
Final welding be witness by 1
Visual
SL. DESCRIPTION OF ITEMS CHARACTERISTICS TO CAT TYPE/METHOD EXTENT OF REFERENCE ACCEPTANCE FORMAT OF AGENCY REMARKS
NO. BE CHECKED OF CHECK CHECK DOCUMENTS STANDARDS RECORDS
P W V
25 Inspection prior to release for Completeness, CR Visual, Random 100% APPD. DRGS, APPD. DRGS. IR 2 1
hydro-test, Inside/Outside cleanliness, overall Meas., DATA SHEET DATA SHEET,
welding surface, External dimension, Verification of all API 650
Internal attachment plumpness records
orientation,
radiography etc.
26 Final inspection during hydrotest Leak tightness CR Hydrotest 100% APPD. DRGS API 650 IR 2 1,2
verticality M Plump Every 30° APPD. DRGS API 650 IR 2 1,2
27 Final assembly Settlement M Meas. Every 30° APPD. DRGS OISD 129/ BS IR 2 1,2
3659
28 Buoyancy test, Floatation test, Smooth Floatation CR Hydrotest 100% APPD. DRGS API 650 IR 2 1,2
Deck puncture test leak tightness M Submersion 100% API 650 API 650 IR 2 1,2
Measurement
29 Rain water test Deck CR Water filling on 100% API 650 Spec. API 650 Spec. IR 2 1,2
deck
30 Calibration Capacity wrt Filling M Meas. & 100% APPD. DRGS IS 2007/2008 Cali. Chart 3 1,2
height Certification IS 2007/2008
33 QA & QC Documentation Overall quality, Data M Review of all 100% Technical Technical IR 2 1
Keeping TC, IR for Specifiation Specifications
previous stages & applicable
codes
SL. CHARACTERISTICS TO TYPE/METHOD EXTENT OF REFERENCE ACCEPTANCE FORMAT OF AGENCY
DESCRIPTION OF ITEMS CAT Remarks
NO. BE CHECKED OF CHECK CHECK DOCUMENTS STANDARDS RECORDS P W V
STANDARD BOUGHT-OUT
ITEMS
34 Gauge hatch 1 Physical & Chemical M Physical, Random AS PER As per spec. MFTRS TC 3,2 1,2
Properties Chemical Tests SPEC. APPD. DRGS
APPD. DRGS.
2 Dimension M Visual & Meas. 100% APPD. DRGS. APPD. DRGS. MFTRS TC 3,2 1,2
DATA SHEET DATA
SHEETS
35 Sprinkler nozzle/ Foam maker Dimension & M Physical & Random APPD. DRGS APPD. DRGS MFTRS TC 3,2 1,2
Surface Quality Chemical Tests & SPEC. & Spec.
36 Foam seal & Accessories 1 Physical & Chemical M Physical & Random APPD. DRGS APPD. DRGS MFTRSTC 2 1
Properties Chemical Tests & SPEC. & Spec.
2 Dimension M Meas. & Visual 100% APPD. DRGS APPD. DRGS MFTRS TC 3,2 1,2
& SPEC. & Spec.
37 Flame arrestor/ Breather valve 1 Physical & Chemical M Physical & Random APPD. DRGS APPD. DRGS MFTRSTC 2 1
Properties Chemical Tests & SPEC. & Spec.