ASSESSMENT REPORT
SANGLI, MAHARASTRA
PREPARED BY
OBJECTIVES
TO CARRY OUT THE ASSESSMENT OF PROJECT & WORK OUT THE PLAN TO COMPLETE & COMMISSION
THE PLANT
INDEX
1. SYNOPSIS
5. CONTRACTOR STATUS
9. TENTATIVE SCHEDULE
01. SYNOPSIS
AFTER DEPLOYMENT
i. Our engineers will work out the list drawings / documents status in 2-3 weeks (will the
prioritized) for immediate actions.
ii. Will prepare area wise plug list in 2-3 weeks time (will the prioritized) for immediate actions.
iii. Will submit the list of equipments for water treatment plant in 3-4 days
iv. Will submit list of tools / tackles etc in 3-4 days.
v. Actions for integration of Fuel Handling system shall be taken up (Separate design agency
needed to be engaged for designing the system)
BUDGETARY COST : For working out the budgetary cost we will be requiring design inputs / authentic
list of balance materials.
Disadvantages
i. Capex is high
ii. Power consumption is high
iii. In case of failure of the system the Power Plant operation will be disrupted
SUGGESTED : In place of centralized AC we should install 10x 2 Tonnes (of Refrigration) split air
conditioners.
Advantages
i. Capex is very low just 20 – 30% of the Centralised AC
ii. Power consumption is lower , because during nights & summers only few ACs need to be
operated.
iii. In case of failure of 1or 2 units , Power Plant operation is not hampered.
NUTRALISING PIT
i. The present neutralizing pit is too big in size & the quality of job done is too bad (gunny
bags are left at RCC joints) this will cause leakage.
ii. The water proofing & further lining with Acid proof bricks will be requiring good investment.
Solution
We need to construct another neutralizing pit & size will be approximately 1/4th of the existing one
, this will be requiring lesser investment in construction as well as acid proof tiling.
START UP POWER
Present plan :
Initially to start with 11 KV later on switch over to 132 KV
Our suggestion :
i. Planning for 11 KV will be requiring power feeding arrangement this will attract
capex.
ii. We should straight way apply for 132KV start up Power & the evacuation system can
be used for drawing the strat up power.
Emergency Power
DG Set to be decided immediately – lead time 3 approx. months + integration with the
system 45 days.
WATER
PROOFING TO BE
DONE + SUMP
D CEP PIT COMPLETED SINEWAVE / CVPL PIT TO BE MADE
E 3.5 MTR FLOOR MAX WORK COMPLETED
OPTION KOTA
STONE / RCC RCC WITH IRON
WITH IRON TOPPING WILL BE
F 8.0 MTRS FLOORING SINEWAVE / CVPL TOPPING ECONOMICAL
FALSE ROOFING -
CLEARANCE
GIVEN FOR
SEMIFINSHED STARING THE
G CONTROL ROOM CONDITION SINEWAVE / CVPL WORK
TO BE STARTED
H FALSE FLOOING PENDING SINEWAVE / CVPL IMMEDIATELY
ARCHITECTURAL DRAWING TO BE NO DRAWINGS WERE
I DRAWING WORK JUST STARTED SINEWAVE / CVPL REVIEWED AVAILABLE AT SITE
CIVIL - FOUNDATIONS
WORK TO BE
1 ASH HANDLING PENDING DRAWINGS AVAILABLE STARTED
DM PLANT
2 CIVIL WORKS FLOORING PENDING SINEWAVE / CVPL
ACID TILING SINEWAVE / CVPL
DARIN ACID PROOF
TILING SINEWAVE / CVPL
INCOMPLETE - SIZE TOO IT CAN BE USED
BIG , NOT TO BE USED FOR SOME
3 NEUTRALISING PIT FOR NP SINEWAVE / CVPL OTHER PURPOSE
SUMP
WATERPROOFIN
G TO BE DONE &
RETURN SUMP
WATER
PROOFING TO BE
TAKEN UP
4 COOLING TOWER ALMOST COMPLETED SINEWAVE / CVPL IMMEDIATELY
AREAS NEAR COOLING
5 TOWER FLOORING PENDING SINEWAVE / CVPL TO BE TAKEN UP
EXCEPT CRUSHER
HOUSE + CHIPPER TO
6 FUEL HANDLING SYSTEM CIVIL COMPLETED SINEWAVE / CVPL BE ADDED
THIS WILL BE
REQUIRED FOR
TO BE STARTED QUICK & SAFE
7 PLANT ROAD NO ACTION SINEWAVE IMMEDIATELY COMMISSIONING &
OPERATION OF THE
PLANT
TURBINE
BEARINGS & EXCITOR
ARE IN OPEN
CONDITION THIS
MAY LEAD TO
DAMAGE OF
1 TG PLACED ON FOUDATION SINEWAVE / CVPL BERAINGS / EXCITOR
OIL PIPE WAS IN
PROGRESS NOW
2 TG OIL PIPING STOPPED SINEWAVE / CVPL
BOTTOM FLANGES
ARE CUT BY GAS ,
THIS IS A BAD
3 CONDENSER PLACED ON FOUDATION SINEWAVE / CVPL PRACTICE
SOLE PLATE TO BE
CONDENSER INSTALLED SINEWAVE / CVPL
BELLOW TO BE
CONDENSER CONNECTED SINEWAVE / CVPL
CONDENSER GROUTING TO BE DONE SINEWAVE / CVPL
4 CONDESATE PIPING TO BE STARTED SINEWAVE / CVPL
SWPL
INFORMED THAT
ALL PIPES DRAWINGS WERE
TURBINE AUX STEAM APPROVED BY NOT AVAILABLE AT
5 PIPING TO BE STARTED SINEWAVE / CVPL IBR SITE
SWPL
INFORMED THAT
ALL PIPES DRAWINGS WERE
OTHER STEAM & IBR APPROVED BY NOT AVAILABLE AT
6 PIPING IN PROGRESS SINEWAVE / CVPL IBR SITE
CVPL TO SUBMIT THE
DOCUMENTS – ENGG
QA FOR STEAM & IBR CONSULATANT TO
7 PIPING NOT KNOWN REVIEW & APPROVE TO BE CHECKED
BOP
MISC
HOPPER GATES BOILER
1 & ESP NOT ERECTED SINEWAVE / CVPL
2 PIPE SUPPORTS NOT ERECTED SINEWAVE / CVPL
ASH HANDLING
ERECTED MINOR JOBS SINEWAVE / CVPL or
1 SILO PENDING CVPL’S SUB VENDOR
SINEWAVE / CVPL’S SUB
2 ASH VESSELS NOT RECD VENDOR
SINEWAVE / CVPL’S SUB
3 CONVEYING PIPING NOT RECD VENDOR
SINEWAVE / CVPL’S SUB
4 DOME VALVES NOT RECD VENDOR
5 COMPRESSOR STATUS NOT KNOWN SINEWAVE / CVPL
FUEL HANDING
FINAL PLUG LIST
TO BE PREPARED
AFTER
DEPUTING
1 CONVEYOR GALLERY ALMOST COMPLETED SINEWAVE / CVPL ENGRS
SPECS TO BE FROZEN
IMMEDIATELY &
PROCUREMENT
ACTION TO BE
2 CUTTERS NO ACTION TAKEN SINEWAVE / CVPL INITIATED
DRAWINGS TO BE
FROZEN
NO ACTION TAKEN - IMMEDIATELY &
LIST IS AVAILABLE – PROCUREMENT
DRAWINGS ARE NOT ACTION TO BE
3 PULLEYS AVAILABLE SINEWAVE / CVPL INITIATED
DRAWINGS TO BE
FROZEN
NO ACTION TAKEN - IMMEDIATELY &
LIST IS AVAILABLE – PROCUREMENT
PULLEY DRAWINGS ARE NOT ACTION TO BE
4 FRAMES/CARRIERS AVAILABLE SINEWAVE / CVPL INITIATED
DRAWINGS TO BE
FROZEN
IMMEDIATELY &
PROCUREMENT
ACTION TO BE
5 WEIGHYERS NO ACTION TAKEN SINEWAVE / CVPL INITIATED
8 TRANSFORMERS
PLACED ON
a AUX TRANSFORMER FOUNDATION
b GT READY FOR DISPATCH
SWITCH YARD
TOTAL TIME TO
OUT OF 4 THREE ARE COMPLETE
1 TOWERS CLEAR FOR ERECTION 2MONTHS GOOD PROGRESS
2 FOUNDATIONS DONE
TOWER ASSEMBLY TO
BE STARTED
3 SWITCH YARD
a TOWERS ERECTED
INSPECTION BY MSDCL
b INSULATORS COMPLETD
c CT / PT etc AVAILABLE AT SITE
EASILY AVAILABEL WILL
d ENERGY METER BE PROCURED LATER
EASILY AVAILABEL WILL
e BARE CONDUCTORS BE PROCURED LATER
2.5 MONTHS ,
TIME REQUIRED TO INCLUDING CEIG
f COMPLETE THE JOB APPROVAL
INFRASTRUCTURE
REQUIRED
AS THE AREA IS
PRONED TO
FLOODING , STORM
DRAINS & ARTERIAL
DRAINS ARE
REQUIRED TO BE
COMPLETED BEFORE
1 STROM WATER DRAINS RAINS
2 PLANT DRAINS AS ABOVE
REQUIRED FOR
SMOOTH & SAFE
PHERIPHERAL PLANT OPERATION OF THE
3 ROAD PLANT
ADVISE FOR
IMPROVEMENT
THIS WILL SAVE THE
10X 2TONNES SPLIT AIR CAPEX BY 90% +
CONTROL ROOM AIR CONDITIONERS IN PLACE PART OPERATION
1 CONDITIONING OF SPLIT AC WILL SAVE ENERGY
WATER PROOFING TO
BE DONE + DRAIN PIT
2 CEP PIT FOR PUMPING OUT
THE PRESENT NP
SIZE IS TOO BIG , SHALL WILL BE USED FOR
BE USED FOR SOME SOME BETTER
3 NEUTRALISING PIT OTHER PURPOSE PURPOSE
THE SCHEME WAS NOT
AVAILABLE TO BE
REVIEWED & IF REQD THIS SCHEME IS VERY
WATER TREATMENT SCHEME CHANGES WILL IMPORTANT TO BE
4 SCHEME BE DONE REVIEWED
SUGGESTED TO GO
FOR 132KV ONLY , AS
THIS IS RELIABLE &
OPTIONS 11 KV & 132 THE SAME CIRCIUT
6 START UP POWER KV CAN BACK FEED
ASSESSORIES FOR
SYNCHRONISING WITH
9 TG & EMERGENCY DG IN SCOPE OF CVPL
C MOHAMMAD
DEMOLISED , TOOLS & UNDER CONTROL OF PLUG LIST JOBS
3 BOILER TACKLES ARE AT SITE CVPL TO ATTENEDED
NEEDED TO BE
MOBILSED
IMMEDIATELY
CONTRCATOR UNDER CONTROL OF FOR STARTING
4 COOLING TOWER DEMOBILISED CVPL THE JOB
BAD QUALITY OF
WORK , PROPER PIPE
SUPPORTING NO
DONE, MISMATCH
BETWEEN THE PIPE &
SOBHAN ENGG. – UNDER CONTROL OF PUMP FLANGE
5 PIPING ACW & MCW MOBILISED CVPL ELEVATION
NEEDED TO BE
MOBILSED
IMMEDIATELY
BD ENTERPISES – FOR STARTING BAD QULAITY OF
6 DM PLANT DEMOBILISED THE JOB WORK
NEEDED TO BE
RK & RKUMAR MOBILSED
DEMOBILSED , WILL IMMEDIATELY
REACH SITE ONCE WE FOR STARTING
7 ELECTRICALS & INSTT GIVE CLEARNCE THE JOB
CONTRACTOR
NEEDED TO
FINALISED IMPORTANT
IMMEDIATELY ACITIVITY TO BE
FOR STARTING COMPLETED BEFORE
8 INSULATION TO BE TAKEN UP THE JOB TRAILS START
CONTRACTOR IMPORTANT
9 ILLUMINATION TO BE TAKEN UP NEEDED TO BE BECAUSE
FINALISED ILLUMINATION IS
MUST FOR STARTING
THE TRAILS
LOCAL SMALL
TIME TO BE
ENGAGED TO
CARRY OUT THE UNIT RATE CAN BE
PETTY JOBS LEFT DECIDED & OPEN
PETTY MECH BY OTHER CONTRACT CAN BE
10 CONTRACTOR PARTIES AWARDED
TARGET TIME TO
THE PRESENT COMPLETE THE JOB
CONTRACTOR IS WITH CEIG
SWITCH YARD & COMPLETING THE JOB APPROVALS – 2.5 TO
11 TRANSMISSION LINE EFFICIENTLY 3.0 MONTHS
We will plan parallel activities based on the site movement & will try to squeeze the time for putting the
plant into operation.
Subjective Conditions :
i. Availability of documents / drawings / design inputs
ii. Material flow as per requirement
iii. Contractor engagement as per requirement
iv. Manpower deputation as per requirement
GENERAL
APPLICATION TO SPCB FOR CFO (CONSENT TO OPERATE)
BOILER
IBR APPROVALS (THIS CAN BE INITIATED ONLY AFTER COMPLETION OF ALL IBR JOBS)
ELECTRICAL
CEIG APPROVALS FOR
1. COMPLETE HT SYSTEM
2. COMPLETE LT SYSTEM
3. SWITCH YARD
4. TRANSMISSION LINE
5. ISSUANCE OF SAFETY CERTIFICATE
Line – tie permission for synchronizing the plant with grid as well as power drawl from grid for starting
the plant.
AVIATION :
Since the site is not near any airport (as per the information sought from site people) , aviation
clearance is not mandatory , but fixing of aviation lamps on Chimney is mandatory.