Sunteți pe pagina 1din 7

ENERGIZATION PROGRAM FOR 11/0.

415 kV DISTRIBUTION STATIONS


RING-1: SB 0054 & SB 0052
UNDER SCHEME NO. ND/11/16/34.

AL AIN DISTRIBUTION COMPANY (AADC)

POWER PROJECTS DELIVERY DEPARTMENT

Document No: AADC/PRJD/ENER/2017/……

Document Date: 02 FEBRUARY, 2017 (Revision 0)

ENERGIZATION PROGRAM FOR 11/0.415 kV DISTRIBUTION STATIONS


RING-1: SB 0054 & SB 0052 UNDER SCHEME NO. ND/11/16/34.

Scheme No: ND/11/16/34

Commissioning Engineer: Amjad Saeed (AADC Projects)

Revision Index
Revision Issue date Issue description Pages Origin
0 Feb. 2017 For approval

Scheme No. ND/11/16/34 - 11/0.415 KV Distribution SB 0052,SB 0053,SB 0054,SB 0055&SB 0056
Scheme No. ND/11/16/34 Page No: 1 of 7.
Rev. 0
ENERGIZATION PROGRAM FOR 11/0.415 kV DISTRIBUTION STATIONS
RING-1: SB 0054 & SB 0052
UNDER SCHEME NO. ND/11/16/34.

TABLE OF CONTENTS

A. Scope…………………………………………………………………………………………………...

B. Energization Prerequisites……………………………………………………………………….......

C. Switching Program…………………………………………………………………………………….
Anexure-1: Name and contact number of Engineers executing the programs……………

A. Scope:

1.0 Step-01: Energization of 11 kV cable from SHB-A-PU1/K08 to SB 0054/K04 & Energization of SB 0054.
2.0 Step-02: Energization of 11/0.415 kV Transformer-1&2 at SB 0054 and respective LVAC.
3.0 Step-03: Energization of 11 kV cable from SB 0054/K01 to SB 0052/K01 & Energization of SB 0052.
4.0 Step-04: Energization of 11/0.415 kV Transformer-1&2 at SB 0052 and respective LVAC.
5.0 Step-05: Energization of 11 kV cable from SHB-A-PU2/K07 to SB 0052/K04.

Notes:
HSE rules will be strictly followed during execution of complete program.

Scheme No. ND/11/16/34 - 11/0.415 KV Distribution SB 0052,SB 0053,SB 0054,SB 0055&SB 0056
Scheme No. ND/11/16/34 Page No: 2 of 7.
Rev. 0
ENERGIZATION PROGRAM FOR 11/0.415 kV DISTRIBUTION STATIONS
RING-1: SB 0054 & SB 0052
UNDER SCHEME NO. ND/11/16/34.

B. Energization Prerequisite.
S. No. Action By Checked
1.1 Copy of SLD delivered to AMD, C.E, DMS and T&P Contractor/Consultant
1.2 Pre-commissioning test results delivered to T&P. Contractor/Consultant
1.3 Clearance to energize certificate for SB 0054 and SB
0052 is issued by Contractor and signed by all Contractor/Consultant
concerned.
1.4 Confirm that no earthing applied in the circuit to be
Contractor/Consultant
energized.
1.5 Energization program approved. Contractor/Consultant /AADC
1.6 All Power Cables are tested and connected. Contractor/Consultant
1.7 All protections are in service, healthy and approved
Contractor/Consultant /AADC
setting has been adapted and tested.
1.8 All permits are returned Contractor/Consultant /AADC
1.9 All engineers executing the programs are available
Contractor/Consultant /AADC
and ready to start.
1.10 Confirm all LVAC panels incoming Isolator and O/G
Fuses are open. No power supply connected and no
Contractor/Consultant
earthing applied to LVAC related to SB 0054 and
SB 0052
1.11 All earthing removed for the circuit/equipment to
Contractor/Consultant /AADC
be energized at SB 0054 and SB 0052

Scheme No. ND/11/16/34 - 11/0.415 KV Distribution SB 0052,SB 0053,SB 0054,SB 0055&SB 0056
Scheme No. ND/11/16/34 Page No: 3 of 7.
Rev. 0
ENERGIZATION PROGRAM FOR 11/0.415 kV DISTRIBUTION STATIONS
RING-1: SB 0054 & SB 0052
UNDER SCHEME NO. ND/11/16/34.
C. SWITCHING PROGRAMS.

Step-1: Energization of 11 kV cable from SHB-A-PU1/K08 to SB 0054/K04 & Energization of SB 0054.


A. Pre-Energization conditions.
S. No. Action By Checked
1.1 a. Confirm no alarm persisting at K08 of SHB-A-PU1 and
SB 0054.
b. Confirm E/Sw. Q5 and CB Q0 for K08 at SHB-A-PU1 are
open and all line isolator Q1 and CB Q0 at SB 0054 are
open.
Contractor/Consultant
c. Protection settings adapted and trip test has been
/AADC
done.
d. All 11kV cables tested and connected at SB 0054/K04
& SHB-A-PU1/K08.
e. Reduce TMS to minimum for O/C & E/F protection of
K08 of SHB-A-PU1.

B. Energization of 11 kV cable from K08 of SHB-A-PU1 to SB 0054.


S. No. Action By Checked
1.2 a. Confirm no personnel available rather than operator
in 11 kV switch gear at SHB-A-PU1 and SB 0054.
b. Close CB Q0 of K08 at SHB-A-PU1. The 11kV cable
from K08 at SHB-A-PU1 to SB 0054/K04 is now Contractor/Consultant
/AADC
energized.
c. Confirm that 11 kV cable is normal.

C. Energization of 11kV SB 0054


S. No. Action By Checked

1.3 a. Confirm CB at SB 0054 to Transformer-1, 2 & K01 is


open.
Contractor/Consultant
b. Close respective line isolator Q1 and CB Q0 at SB
/AADC
0054/K04.
c. Confirm SB 0054 is energized.

Scheme No. ND/11/16/34 - 11/0.415 KV Distribution SB 0052,SB 0053,SB 0054,SB 0055&SB 0056
Scheme No. ND/11/16/34 Page No: 4 of 7.
Rev. 0
ENERGIZATION PROGRAM FOR 11/0.415 kV DISTRIBUTION STATIONS
RING-1: SB 0054 & SB 0052
UNDER SCHEME NO. ND/11/16/34.
Step-02: Energization of 11/0.415 kV Transformer-1&2 at SB 0054 and respective LVAC.

S. No. Action By Checked


2.1 a. Confirm no personnel available rather than operator
in the SB 0054.
b. All Isolator and O/G Fuses are open, no earthing and
power supply connected to LVAC.
c. Close line isolator Q1 and CB Q0 of TR-1 & 2 at SB
0054.(K02&K03) Contractor/Consultant
d. TR-1 & 2 is energized. /AADC
e. Energize respective LVAC by closing incoming Isolator
of incomer-1 & 2 one by one; Isolator of B/S shall be
open.
f. Confirm phase sequences and measure voltage.
g. Close all O/G Fuses if necessary to feed the load.

Step-03: Energization of 11 kV cable from SB 0054/K01 to SB 0052/K01 and Energization of SB 0052.

S. No. Action By Checked


a. Check both end of the cable from SB 0054 to SB 0052
3.1 are terminated and no earth applied in the cable
anywhere.
b. Confirm isolator Q1 & CB Q0 at SB 0052 / K01, K02,
K03 & K04 are open.
Contractor/Consultant
c. Close corresponding isolator Q1 and CB Q0 at SB
/AADC
0054/K01. The cable from SB 0054/K01 to SB
0052/K01 is energized.
d. Close corresponding isolator Q1 and CB Q0 at SB
0052/K01.
e. Confirm SB 0052 is energized

Step-04: Energization of 11/0.415 kV Transformer-1&2 at SB 0052 and respective LVAC.


Scheme No. ND/11/16/34 - 11/0.415 KV Distribution SB 0052,SB 0053,SB 0054,SB 0055&SB 0056
Scheme No. ND/11/16/34 Page No: 5 of 7.
Rev. 0
ENERGIZATION PROGRAM FOR 11/0.415 kV DISTRIBUTION STATIONS
RING-1: SB 0054 & SB 0052
UNDER SCHEME NO. ND/11/16/34.
S. No. Action By Checked
4.1 a. Confirm no personnel available rather than operator h.
in the SB 0052.
b. All Isolator and O/G Fuses are open, no earthing and
power supply connected to LVAC.
c. Close line isolator Q1 and CB Q0 of TR-1 & 2 at SB
0052. (K02&K03) Contractor/Consultant
d. TR-1 & 2 is energized. /AADC
e. Energize respective LVAC by closing incoming Isolator
of incomer-1 & 2 one by one; Isolator of B/S shall be
open.
f. Confirm phase sequences and measure voltage.
g. Close all O/G Fuses if necessary to feed the load.
Step-05: Energization of 11 kV cable from SHB-A-PU2/K07 to SB 0052/K04.
S. No. Action By Checked
a. Confirm no alarm persisting at SHB-A-PU2/K07
5.1 b. Confirm E/Sw. Q5 and CB Q0 are open at SHB-A-
PU2/K07 and Isolator Q1 and CB Q0 are open at SB
0052/K04.
c. Protection settings adapted and trip test has been
done for SHB-A-PU2/K07.
d. 11kV cable tested and connected at both ends at SHB-
A-PU2/K07 and SB 0052/K04.
e. Reduce TMS to minimum for O/C & E/F protection of Contractor/Consultant
SHB-A-PU2/K07. /AADC
f. Check no personnel available in 11 kV switch gear at
SHB-A-PU2/K07and SB 0052.
g. Close CB Q0 of SHB-A-PU2/K07. The 11kV cable from
SHB-A-PU2/K07 to SB 0052/K04 is now energized.
h. Confirm that 11 kV cable is normal.
i. NOTE: NOP at SB 0052/K04.
Normalize all protection settings.

Scheme No. ND/11/16/34 - 11/0.415 KV Distribution SB 0052,SB 0053,SB 0054,SB 0055&SB 0056
Scheme No. ND/11/16/34 Page No: 6 of 7.
Rev. 0
ENERGIZATION PROGRAM FOR 11/0.415 kV DISTRIBUTION STATIONS
RING-1: SB 0054 & SB 0052
UNDER SCHEME NO. ND/11/16/34.

Anexure-1: Name and contact number of the engineers executing the program.

Name Position Contact No. Company


Mr. Kamarul Hassan Project Engineer AADC
Mr. Amjad Saeed Malik Commissioning Engineer AADC
Mr. Commissioning Engineer AADC
Mr. Commissioning Engineer AADC
Mr. Protection Engineer AADC
Mr. O& M Engineer AADC
Mr. DMS Engineer AADC
Mr. Syed Khader Basha Project Manager 0551017176 Contractor.

Scheme No. ND/11/16/34 - 11/0.415 KV Distribution SB 0052,SB 0053,SB 0054,SB 0055&SB 0056
Scheme No. ND/11/16/34 Page No: 7 of 7.
Rev. 0

S-ar putea să vă placă și