Documente Academic
Documente Profesional
Documente Cultură
Operations
Manual
Revision : 2.0
Version : 0.0
Contents
1. INTRODUCTION
2. STATUTORY REGULATIONS
13. ADMINISTRATION
14. TRAINING
15. ANNEXURES
1
INTRODUCTION
LPG OPERATIONS MANUAL
1.1 BACKGROUND
1.1.1 In earlier years when LPG was introduced in India in the kitchens for the
purpose of cooking, the average consumer was very much hesitant to
accept LPG as a cooking fuel. Presently, LPG has become an essential
commodity in everybody's life. LPG has proved to be safe, environment
friendly, economical and easily available fuel in the kitchens. Now LPG is
going to be closer to our day – to – day life by its use in automobiles also.
Refineries
Fractionators
Imports of commercial propane and butane ( blended on
shore to LPG specifications) to bridge the gap between supply
and Demand.
The list of above LPG sources in India and production levels is given at
Annexure No. 1A. Import port locations are given at Annexure – 1B
1.2.1 LPG was first marketed in India in the mid-fifties by the multi-national oil
companies, which were having marketing operations in India. The
bottling operations were, then, mainly confined to Refinery plants and
marketing operations limited to nearby areas.
1.2.2 Though IOC, under Public Sector, started functioning in the year 1959, it
actually started marketing of LPG in the year 1965 with the brand name of
"Indane" through its only bottling plant at Barauni Refinery, which had very
limited bottling capacity.
1.2.3 LPG marketing in India had no noticeable growth till 1980-81. However,
during mid-eighties, there was a tremendous spurt in the marketing of LPG
due to increase in the refining capacity in various refineries and also
availability through Bombay High and Assam Gas fields.
1.2.4 In the early eighties, the total number of customers in the country was
around 30 lacs and the LPG sales was around 4 lacs MT per annum. After
two decades, there is a multifold increase both in numbers of customers
LPG OPERATIONS MANUAL
and in LPG sales. As on 1st April 2001, there were 286 lacs of customers
belonging to IOC (MD) and 579 lacs of customers on Oil Industry basis.
LPG sales on account of IOC stood at 3,237 TMT per annum as on 31st
march 2001 and 6,609 TMT for entire Oil Industry.
As on 1st April 2013, there are 6467 distributors including 944 RGGLV( Rajiv
Gandhi Gamin LPG Vitrak) distributors enrolled with IOC (MD) catering to
7.34 Crore customers as compared to 12610 distributors including 2055
RGGLV distributors on Oil Industry basis catering to 15.04 Crore Customers
1.2.5 During 2012-13 about 1.32 crore of customers were enrolled by the Oil
Industry.
1.2.6 As per the Oil Industry figures, IOC’s share was 47.3 percent as on
31.03.2013 . The number of LPG bottling plants being operated by IOC’s
Marketing Division has increased to 88 Nos. as on 31.03.2013. with
aggregate annual bottling capacity of 6793 TMT including 143 TMT from
two bottling Plants operated by M/s CPCL and M/s OIL, Duliajan but
marketed by IOCL..
The list showing the bottling capacity and tankage of IOC’s bottling
plants as on 31.12.2013 is given in Annexure No. 2
1.2.7 In the initial stages, it was customary to fill LPG cylinders only at LPG
bottling plants within the Refineries. On account of economic and
logistic considerations, it became necessary to set up more number of
LPG bottling plants at different locations which could receive LPG in bulk
from the refinery points and bulk LPG storage installations of GAIL and
ONGC
and bottle the same for distribution in the surrounding areas. This type of
arrangement was primarily made with a view to reduce the marketing
costs by minimizing the cost of transportation and reducing the customer
/ cylinder ratio.
1.4 OBJECTIVES
1.4.1 In view of the rapid expansion of LPG bottling operations being planned in
the coming years as detailed in Section 1.2 above, it is all the more
necessary to issue this Manual to provide field personnel adequate
knowledge of correct operating and safety practices.
1.4.2 The manual is intended to enable the field personnel to carry out their day
to day operational activities more effectively, efficiently and safely by
applying correct operating practices and procedures.
1.5 CLARIFICATIONS
1.5.1 Any additions or alterations to the texts of the manual will be issued only
by LPG Operations Department, Head Office. The same must be filed
serially in the manual folder itself. Instructions of transient nature will,
however, be issued through circulars.
1.5.2 This manual does not replace or supersede in any way the data /
instructions contained in the followings :
(e) Statutory Rules in force (e.g. The Gas Cylinder Rules, 2004; the
Static and Mobile Pressure Vessels (unfired) Rules, 1981
(amended in 1998); relevant Indian Standards/ Codes; Factory
Rules etc).
1.6 SCOPE
1.6.1 This manual covers the guidelines for correct operating procedures and
related activities within LPG bottling plants to ensure safe and efficient
working. The areas covered are :
(d) Other related topics like safety, fire prevention and control,
statutory testing of cylinders, quality control, administration, training
etc.
1.6.2 The manual is intended to cover only operational aspects at the plants
and is not intended to serve as a code or a guideline for standard facilities
or equipment required at the plants. In certain cases, brief description of
the design aspect is covered only with a view to explain its relevance to
the operations.
1.6.4 The manual is primarily intended for use at IOC's bottling plants operated
by the Marketing Division and personnel connected with their activities.
1.7.3 Throughout the manual, the term “LPG” is used to indicate both the
phases; i.e., liquid and vapour. Liquid phase is expressed as liquid LPG
and vapour phase as LPG vapour.
1.7.4 Unless otherwise specified, the term "IOC’s plants" is used in the text of the
manual to cover only the plants owned and operated by IOC Marketing
1.7.5 It should be understood that every rule in the manual has been
included with a specific purpose and must not be ignored no matter,
howsoever, it may appear to be as unnecessary under certain
circumstances.
1.7.6 If any topic is not understood or if there is some doubt, reference should
be made to the concerned State Office / Regional Office / Head Office.
1.7.7 Key points have been printed in bold letters to lay emphasis. Repetition of
certain points in various chapters may appear unnecessary but has been
deliberately done to lay emphasis.
LPG OPERATIONS MANUAL
STATUTORY REGULATIONS
LPG OPERATIONS MANUAL
2.1 GENERAL
2.1.1 LPG plant operation must be carried out in accordance with all statutory
regulations in force. Presently, LPG plant operation in India is mainly
governed by the following regulations :
(g) The Motor Vehicles Act 1988 with latest amendments. & Central
Motor Vehicles Rules, 1989
(h) Contract Labour ( Regulation & Abolition) Act, 1970 and Contract
Labour ( Regulation & Abolition) Central Rules 1971
iii. ( Sudha Joshi committee for better services to LPG users 1987 (
Ministry of Petroleum & Natural Gas).
2.3.1 The List of various topics relevant to LPG operations covered in the
publications is listed under Clause No. 2.1.1.
2.4.2 Copies of all licenses and abstract of Statutory Regulations / Acts must be
displayed in the office premises duly secured.
2.4.3 The licenses must be renewed on time and any queries raised on the
renewal application by the concerned authority must be replied to within
stipulated time to ensure speedy renewals..
LPG OPERATIONS MANUAL
3.2.2 LPG widely marketed in India falls under the category (c), i.e., A Mixture
of Commercial Butane and Commercial Propane, each of which can be
either a mixture of saturated and unsaturated hydrocarbons. Their
compositions are not rigidly specified and they vary from one refinery to
another, depending upon the type of crude oil, refining process, etc.
(b) Since the density of water is 1 gm/cm3 or 1000 kg/m3, and the
density of liquid LPG is about 0.55 gm/cm3, the latter is about ½ as
heavy as water. The density of the liquid is approximately half that of
water and ranges from 0.510 to 0.580 gm/cm3 @ 15 oC.
(c) The liquid density of LPG is important to determine the safe level to
which the containers can be filled i.e., to calculate the maximum
permissible filling capacity.
(d) The density range of liquid LPG for various temperatures is as under:
Density ( gm/cm3)
Temperature ( C)
Propane Butane
0 0.522 to 0.531 0.587 to 0.596
(+)10 0.508 to 0.517 0.576 to 0.585
(+)15 0.500 to 0.510 0.570 to 0.580
(+)20 0.492 to 0.502 0.564 to 0.574
(+)30 0.476 to 0.487 0.552 to 0.562
(+)40 0.458 to 0.470 0.539 to 0.550
(+)50 0.440 to 0.454 0.526 to 0.537
(b) Relative density is used to indicate the density of the gas in relation
to that of air at the same temperature and pressure. If the relative
density is greater than unity, the gas is heavier than air. LPG vapour
is about 1 ½ to 2 times as heavy as air. As a result of this property,
any leakage of LPG tends to settle down at the floor level
particularly in depressions, pits, drains, etc. Floor level ventilation to
disperse the gas and thereby prevent accumulation are, therefore,
most important.
At Atmospheric Pressure
(c) The above fact has to be taken into account in arriving at maximum
filling density pertaining to liquid storage vessels. Filling density is the
ratio of maximum liquid LPG content to water capacity of vessel at
150 C. LPG container must only be filled to a certain volume in order
to leave sufficient space for LPG expansion in case of rise in
temperature.
LPG can exist as a liquid over a wide range of temperatures. The lowest
temperature in the range at which liquid assumes the solid state is known
as the melting point. The value for propane and butane (the main
constituents of LPG) are –187 0C and – 137 0C respectively. It is such a low
temperature that it can not encountered in normal operations/handling
and, therefore, does not have any practical significance.
LPG OPERATIONS MANUAL
(b) Below the critical temperature, the substance can exist either as a
gas or as a liquid. When the substance exists as a gas and liquid
simultaneously it is stated that it is in a state of equilibrium between
gas and liquid. At any given temperature under these conditions
there will be a definite pressure.
Molecular weight 44 58
Boiling Point, 1 atm o C -45 -7
Critical temp o C 95 150
Critical Pressure, Atm 40 35
iii. Vapour pressure has no relation to the quantity of liquid present. If the
temperature of liquid LPG inside a container remains constant, the
pressure inside the container when full or when almost empty will
practically be the same
LPG OPERATIONS MANUAL
-20 0 C 96 96
00C 90 92
+20 0 C 82 87
(a) Specific heat is defined as the quantity of heat required to raise unit
mass of a substance through a unit temperature interval. Specific
heat may also be expressed, as the amount of heat required to
warm a substance in the solid, liquid or gaseous state. Unit of
Specific Heat is Kcal/kg/o C
Propane Butane
0.60 0.57
3.5.2 ODOUR
3.5.3 TASTE
LPG vapours are tasteless and non-toxic. Therefore, the presence of LPG
vapours in the atmosphere cannot be sensed by taste. However,
continued and heavy exposure to environment of LPG may cause mild
dizziness.
(b) There are two basic methods of vaporizing LPG. The most common
method is carried out within the LPG container, the product being
withdrawn directly from the container in gaseous form. In this
method the heat is drawn primarily from the surroundings of the LPG
container although some of the heat comes from the LPG
liquid and from the container’s body. The amount of gas which can
be generated by direct vapourisation is limited by :-
(b) One volume of liquid LPG will produce about 250 volumes of LPG
vapour and combined with 12250 volumes of air would form 12500
volumes of inflammable mixture which would cause combustion on
application of a temperature in the range of 410 0 C to 580 0 C or
more.
The range of flammability for LPG is considerably narrower than for other
common gaseous fuels, but the lower limit of LPG is reached quickly in
case of leakage. Upper and lower limits of flammability for common
gaseous fuels are as under :
LPG OPERATIONS MANUAL
3.7.5 VISCOSITY
Viscosity is defined as the fluid internal resistance to flow. LPG has low
Absolute or Dynamic viscosity approx. 0.15 cP at 15o C ( Centipoise)
which is much less than that of water which is unity. 1 Cp= .001 Pa-s. It is
also expressed in terms of Kg/m-s.
3.8.2 LPG vapour can also be liquefied by refrigeration. The lower the
temperature, the lower the pressure and vice-versa. This helps in storage
of liquid LPG at near atmospheric pressure by refrigeration.
3.8.3 When pressure is released and liquid LPG changes to vapour, the change
of state requires heat. This comes from the product itself and from the
surrounding areas causing drop in temperature of both. The evaporating
product; especially in liquid form; can become cold enough to cause
frost burns on bare flesh, and to condense water vapour from the air,
forming a visible cloud.
3.8.4 LPG is stored and transported as liquid, either under pressure at the
ambient temperature (the normal method followed in marketing) or at
low temperature (refrigerated condition ).
3.8.5 The expansion of liquid LPG, when its temperature rises, is about 15/20
times greater than that of water and exceeds that of most other general
petroleum products. Sufficient ullage space for expansion of the liquid
must, therefore, be left in all storage/transport containers. Filling of
storage vessels up to 85% of its volume has been the accepted norm
among the oil industry.
3.8.6 One volume of liquid LPG will expand to approximately 250 volumes of
vapour in air. Liquid LPG, if leaks, it can create more hazards compared
to vapour leaks (Refer Diagram No. 2).
3.8.7 Liquid LPG has a low viscosity and can leak in situations in which
water/gasoline may not. It is also a poor lubricant and leaks are,
therefore, likely to occur through seals (of pumps, compressors etc.),
glands etc.
LPG OPERATIONS MANUAL
(a) If water in the product is in sufficient quantity it may cause rust and
corrosion to the vessel which might not otherwise be affected by
the product in any way.
(a) With LPG vapour in the system, air can form combustible mixtures
creating a fire hazard.
3.9.2 As more LPG is added into a container, the liquid level rises and the
vapour space becomes smaller. This compresses the vapour, condensing
some of it to the liquid state. This condensation produces heat which
warms the remaining vapour resulting into an increased pressure. Thus,
the addition of liquid has disturbed the temperature and consequently
the pressure equilibrium. It is, however, only temporary. When filling
ceases, the production of heat ceases and the system soon returns to its
equilibrium temperature and consequently to its equilibrium pressure.
Now the vessel has more liquid in it than before but there has been no
increase in pressure.
3.9.3 The reverse of the above will occur when liquid or vapour is withdrawn
from the container. There is first reduction in pressure and more vapour is
formed by vaporization of the liquid to replace the vapour drawn off. This
LPG OPERATIONS MANUAL
3.9.4 Should the container be completely filled with liquid LPG leaving no
vapour space, even a slight rise in temperature will cause the liquid to
expand and exert an excessive pressure on the container; because
liquids are practically non-compressible. Under these circumstances a
relief valve on the container opens to discharge liquid and relieve the
excessive pressure. However, if there is no pressure relief device, as in the
case of a cylinder, or if it fails to operate, the vessel itself may be distorted
or ruptured. If liquid LPG escapes, either from the relief device or from a
ruptured container, a fire or explosion may result, if a source of ignition is
present.
A spring actuated safety valve would re-set itself when the pressure is
reduced below the valve setting and thus prevent further escape of
product to the atmosphere.
3.9.5 From the above details, it could be summarized that vapour pressure
has no relation to the quantity of liquid present. If the temperature of
liquid LPG inside a container remains constant, the pressure inside the
container when full or when empty would be practically the same.
(a) Commercial LPG has no harmful effect upon steel or the majority of
metals in common use.
(b) Aluminium may be affected by traces of caustic remaining in the
LPG after the refining processes.
(c) Odourants added to LPG are non-corrosive
LPG OPERATIONS MANUAL
(c) BURNS BY FREEZING : LPG in liquid form should not come in contact
with the surface of the body. It is particularly important that
contact with the liquid propane or a product with relatively high
vapour pressure be avoided. In the event that LPG in liquid form
comes in contact with the skin, the product immediately vaporizes.
During this vaporization process, heat will be absorbed directly from
the skin and flesh causing a freezing effect. The ultimate result of
freezing is usually referred to as a burn. The results may be serious.
Therefore, if the possibility of exposure to liquid LPG exists, suitable
safety gloves, safety goggles and protective clothing should be
used.
(d) BURNS BY FIRE : Burns may result from the exposure to LPG flames or
by exposure of clothing directly to appliance flames or by
mishandling of portable devices such as torches and burners. In the
type of exposure in which the LPG Flame acts as an igniter, the
severity of the burns may be dependent upon the time required to
extinguish the burning clothing. In the event of exposure of an
individual to a flash fire or explosion of LPG vapours accidentally
discharged, the burns may be direct result of LPG flames
compounded by clothing if they are highly flammable such as those
made from synthetic fibre. In general, clothing which is not highly
flammable may provide a degree of protection when exposed to a
flash fire. For example, shirt of cotton or woolen material may
provide protection against the possibility of freezing burn and
likewise may provide a type of barrier against the flame of flash fire.
(d) COMBUSTION
drains, and will sink to the low level of the surroundings. Unless efforts
are quickly made to disperse the accumulation of vapour it may
under normal conditions remain there for a long time, with the
possibility of fire through a source of ignition at some distance away
from the source of leakage.
(b) A very small proportion of vapour in the air will give rise to a
flammable mixture, which can cause fire, if source of ignition is
present.
(c) Thermal Expansion of LPG can lead to very serious hazards. LPG
streams under pressure in pipelines and equipment expand rapidly
as a result of only moderate increase in the temperature. For
example, the sun shining on a blocked line full of LPG, not provided
with a relief valve to protect against thermal expansion, can lead to
excessive pressures being built up within the line with eventual
rupture of the pipe.
(f) When pyrophoric substances come in contact with air, they react
with the oxygen generating heat. If the heat is not dissipated, the
temperature would rise high enough to ignite a flammable mixture.
In Oil and Gas industry, major source of pyrophoric substance is iron
sulphide. Pyrophoric iron sulphide is a corrosive product that may
form on the wall of the vessels, pipes, flare headers, etc. which
contain or handle hydrocarbons containing sulphur compounds
(e.g. hydrogen sulphide, mercaptan etc.)
LPG OPERATIONS MANUAL
DIAGRAM-1
LPG OPERATIONS MANUAL
DIAGRAM-2
Produces
Combines 12500 Vol.
with of
Produce
12250 Explosive
250 Vol. Vol. of Air Mixture
1 VOL of LPG
of LPG Vapours
Liquid
4
LPG OPERATIONS MANUAL
4.1 GENERAL
4.1.1 Because of the nature of the product handled, every activity at LPG
plant is closely connected with safety. With the increased public
awareness of safety and various statutory rules and regulations becoming
more stringent, currently safety plays a dominant role in the plant life
from the concept of commissioning and subsequent operation and
maintenance. It is, therefore, essential that all the personnel working in
the plant, including contractors’ work force and transport contractors’
crew are fully aware of the possible hazards in the plant. if the
characteristics of LPG are known, it by itself provides the guidelines as to
how it can be safety handled. The following factors contribute to the safe
operation of an LPG Plant :
4.1.2 All personnel working in the plant, should have sound knowledge not only
of properties and behavioral characteristics of LPG but also of the correct
operation and maintenance of the facilities provided therein.
4.1.3 All supervisory personnel working in the plant should be well conversant
and ensure compliance of the safety and statutory procedures at all
times.
4.1.4 There should be a system for managing safety comprising of the following
basic elements :
Establish and maintain good standards for safety of the people, the
processes and the assets.
Remain trained, equipped and ready for effective and prompt response
to accidents and emergencies.
.
LPG OPERATIONS MANUAL
We shall :
1. Maintain good housekeeping & comply with all applicable Health, Safety
& Environment laws.
7. Remain trained, equipped and ready for effective and prompt response
to accidents and emergencies.
f) All such work is carried out under constant and proper supervision.
i) Modified sections of the plant are tested to ensure that they are
free from leaks, clean and purged before re-commissioning.
4.3 MAINTENANCE
4.3.1 The serviceability and safety of LPG plant and equipment, especially in
the long term, are affected by the standard of preventive maintenance
undertaken so as to ensure that the maintenance is carried out safely
and the benefits of effective preventive maintenance are obtained. The
details are covered in Chapter No. 10.
4.3.3 Whenever any work is being done, permit systems (e.g. hot-work, cold
work, working at height, Electrical permits etc.) and other safety
precautions that may be necessary, MUST be followed. The work MUST
be constantly supervised by a competent person from the Plant. Repairs
/maintenance of pressurized systems and hot-work should be entrusted
to the competent agencies -and having sufficient knowledge,
background and facilities to undertake such work, wherever required, as
per statutory regulations.
4.3.4 Whenever any work is being done, permit systems (e.g. hot-work, cold
work, working at height, Electrical permits etc.) and other safety
precautions that may be necessary, MUST be followed. The work MUST
be constantly supervised by a competent person from the plan
All non-routine jobs should be carried out in line with OISD–STD-105. List of
non-routine jobs should be prepared and procedures defined to carry
out them. Roles and responsibilities for work authorization, issue / receipt
of permits, handing over/taking over should be documented and
implemented. In case of any change in the procedures and practices,
system of proper authorization should be instituted.
For further details on work permit system, OISD –STD-105 /137/192 may be
referred.
4.5.2 Various other safe operating practices are summarized and given in the
list of DOs and DONTs at Annexure No. 8
4.6.3 Certain sulphates reducing bacteria can live in the water that may be
present under the oil in the bottom of storage tanks and this bacteria is
capable of reducing sulphates dissolved in the water to form hydrogen
sulphide, which then forms iron sulphide. Iron sulphide formed without
any air contact inside a storage vessel is very active chemically and
when exposed to air, it rapidly oxidizes becoming so hot that it glows
visibly and reaches a temperature sufficient to ignite a mixture of
hydrocarbon with air. It is appropriately described as “PYROPHORIC”.
4.6.4 From the above, it may be noted that chances of pyrophoric material
are more in the equipment (pipelines, vessels, flare headers, columns,
pumps and strainers etc.) handling hydrocarbons in closed condition.
During cleaning of LPG strainers, statutory testing of LPG Storage
vessels/pipelines, probability of release of pyrophoric iron sulphide into
atmosphere is high and thus due care in handling should be taken as
detailed here under.
` Purging with inert gas or steam may not always be feasible in marketing
locations. Hence, in addition to the precaution to keep the pyrophoric
material wet in the vessel till it becomes hydrocarbon free, following
additional precautions for handling pyrophoric material must be taken :
(a) Pyrophoric material should be kept wet till it is buried in the pit and
pit is covered with earth.
(c) Pit for disposal of this sludge should be located sufficiently away
from hydrocarbon area so that the plant / equipment is not in
danger at any time.
The basis for preparing an Emergency Plan should be derived from the
hazard analysis and the consequences of identified maximum credible
accident scenarios .The objective of the Emergency Plan is to provide
measures to contain and minimise the effects of such incidents.
(a) Design : In accordance with , SMPV Rules 1981, Motor Vehicle Act
1989 .
(e) The skill and art of defensive driving should be inculcated with the
drivers by :
System neutral.
Current and potential transformer secondary neutral.
LPG OPERATIONS MANUAL
4.9.5 Earth rods and conductors shall be designed to cope with the
conditions imposed. The earth conductors shall be adequately sized
LPG OPERATIONS MANUAL
All the electrical equipment operating above 250 volts shall have
two separate and distinct connections to earth grid.
4.9.6 The main earthing network shall be used for earthing of the
equipment to protect it against static electricity.
4.9.9 All battery banks shall be routinely checked for healthy cell voltage,
specific gravity of cells, electrolyte level etc. Insulation resistance of all
electrical equipment, such as, all switchboards, motors, transformers,
cables etc. shall be routinely measured and logged to ensure
healthiness of equipment.
4.9.10 Dielectric strength of the transformer, insulating oil, oil circuit breakers
etc. (if any) shall be measured and oil filtration carried out wherever
necessary.
4.9.11 All cable terminals, bus-bar joints, etc. shall be tightened, more so for
equipment subjected to vibrations, to ensure that there are no hot
spots which could lead to fire / equipment failure. Settings of
protective relays shall be checked yearly to ensure that they
are set and operating as per the recommended settings. If
replacement components such as cable glands, conduits or
conduit accessories, are available only with thread forms which
differ from those provided on the apparatus, suitable adaptors
having necessary certification and approval shall be employed.
4.9.12 Equipment enclosures and fittings shall be examined to see that all
stopping plugs and bolts are in position and properly tightened.
Locking and sealing devices shall be checked to ensure that they are
secured in prescribed manner. Replacement towards fasteners, nuts,
studs and bolts shall be of type specified by the manufacturers
for the particular apparatus. No attempt shall be made to
replace or repair a glass in a flameproof enclosure e.g. in a luminary
Fire
Explosion
Spillage of LPG from storage or during handling / transportation.
d. While following the above procedures, two basic points must be kept
in mind :
(b) Who should investigate : The immediate and first level investigation
should be performed by the immediate supervisor of the affected
area. The immediate supervisor who is closest to the scene, knows
the nature of the work, the employees, who do the work and the
nature of the hazards associated with the work.
All efforts should be made to establish the reasons for the accident.
(b) Pending the visit of CCOE or his representative, or until instructions are
received from CCOE that he does not wish to make any further
investigation or enquiry, all wreckage and debris should be left
untouched except in so far as removal may be necessary for the
rescue of the persons injured.
(a) Hands Gloves : These are required for use for protection against
liquid LPG burns by the Workmen handling filled cylinders. They are
also required to be used by Maintenance staff to prevent cuts,
scratches, bruises and burns on fingers, palms and hands. There are
variety of hand gloves available and selection of the right type is
essential.
(d) Safety Belts / Harnesses : Safety belts and harnesses with life lines
attached should be worn by those who work at high levels or
enclosed places where air supply may not be adequate
LPG OPERATIONS MANUAL
(particularly when they are wearing Gas Mask). These are also
required to be used by the personnel manning the hose line during
the course of fire fighting. With the help of this equipment, a person
wearing it can be pulled out in an emergent situation.
For further details on other PPEs, the HSE Manual and OISD-STD-151
&152 may be referred.
4.13.3 The training should also include / reflect current operating practice,
changes that result from the changes in equipment and the changes in
facilities and safe work practices to provide for the control of hazards
during the operation such as confined space entry and opening process
of equipment and piping for maintenance.
(d) Contractor must ensure that each of their personnel has received
and understood their roles in safe working practices by preparing a
record and should verify the efficacy of dissemination of the safety
information. He should also ensure the use of PPEs at work place.
(e) Contractor should ensure that each member of their crew follows
safety rules of the plant facility including safe work practices.
(f) Contractor should keep Plant Manager informed about any unique
hazard presented by their personnel’s at work.
While due care is taken at the time of initial installation to ensure that the
equipment, or the facility provided is safe as required under the relevant
codes/ rules, periodic checking of these facilities is a MUST to ensure
that they remain in the same and safe condition as designed and
installed. For example a flame-proof electrical installation could be
rendered unsafe during the course of maintenance / repair, if the cover
is not properly tightened or glands are removed. Likewise, to ensure that
all recommended safe operating practices are allowed at the plant, a
periodic safety audit of the plant, to cover both facilities and operation;
LPG OPERATIONS MANUAL
is a MUST. The following basic forms have been designed for this
purpose:
BACK
5
LPG OPERATIONS MANUAL
5.1 GENERAL
5.1.1 The Characteristics of LPG necessitates the use of fire fighting and control
techniques different from those applicable to general petroleum
products. However, as it may be necessary to protect LPG plant and
facilities from fires in the adjacent plant and property, personnel
engaged in LPG operations should know how to deal with all types of
fires, not necessarily those involving LPG.
5.1.3 Fire in an LPG plant could result in a catastrophe. Besides huge financial
losses as a result of property loss and loss of production, it involves
considerable risk to human lives and Corporation image. Efforts should,
therefore, be concentrated on ‘prevention’ aspect of fire, while at the
same time remaining fully equipped and alert to face all possible
emergency situations is essential.
5.2.2 Most LPG fires can be prevented. The most effective way of achieving
this is by using only equipment suitable for LPG service and by strict
observance of safe operating procedures which must be taught to all
personnel engaged in LPG Operations. Ignorance of basic characteristics
of LPG and also of proper handling procedures is often the root cause of
LPG accidents.
LPG OPERATIONS MANUAL
5.2.3 Most LPG fires result from the ignition of the product which used to
escape from its containing system. Escape of LPG is sometimes due to
equipment failure but is more often a result of human error i.e. following
incorrect procedures.
5.2.4 Proper training of all personnel working in the plant; including those
engaged by the contractors and transporters; is very significant factor in
preventing LPG leaks/fires.
Persons entering the plant premises shall deposit match boxes, lighters
etc with the Security Department at the main entrance gate of the plant.
The same can be collected by them on their return.
Ordinary torches will not be allowed to use within the plant premises.
Flameproof torches/lamps of only approved manufacturers shall be used.
All vehicles must have spark/flame arrestors duly welded to exhaust pipe
& these should be duly approved by the Chief Controller of Explosives.
Truck number should also be painted on the body of the Spark arrester.
(b) Personnel working in the plant should be vigilant for the abnormal
presence of hydrocarbons in operating environment.
(d) Draining water from LPG vessels should be done under strict
supervision.
(e) Loose wiring, temporary and non-standard fittings are not permitted
inside the plant premises
(g) Light hydrocarbons viz. Petrol etc., should not be used for washing
the hands, area, equipment or personal belongings.
(l) Use only approved type of tools. This will prevent spark due to
hammering, cutting, rubbing actions.
5.3.2 Chemical Foam is an unsatisfactory agent for dealing with either a jet of
vapour or violently boiling liquid LPG. Therefore, CO2 or Dry Chemical
Powder, which provides a smothering cloud and excludes air from the
flame, must be used in case of a small fire.
5.3.4 If the flames touch directly on LPG containers (irrespective of size) the
container wall will get overheated and rupture on account of the high
pressure developed within the vessel. As rupture of the vessel can create
a catastrophe, immediate putting off the fire should be considered in
such cases.
LPG OPERATIONS MANUAL
5.3.6 LPG fires, that are being allowed to burn out, should be prevented from
involving other facilities and property and should be controlled in size and
intensity. This can be achieved by limiting the rate of leakage. For this
purpose, the pressure of the supply source (e.g. vessel on fire) should be
reduced by reducing the temperature of the supply source through
cooling by water spray.
5.3.7 To protect LPG containers / equipment against any failure (refer Clause
5.3.4 above) and to control the intensity of the fire, all such items exposed
to or involved in the fire must be cooled by sprinklers, fixed monitors, hose
stream, etc.
5.3.8 The top portion of LPG vessel, which is in contact with vapour and not
liquid, is more vulnerable to failure when vessel is exposed to fire. Cooling
water must, therefore, be sprayed to the top of the vessels and to their
supports to prevent collapse.
LPG vessels are provided with Pressure Relief Valves (PRVs), designed to
relieve excessive pressure developed (e.g. as a result of fire exposure).
When hose streams containing water are sprayed on vessels, operation of
Pressure Relief Valves should not be interfered with. The discharge
from Pressure Relief Valves should not be deflected, unless it is
endangering other facilities and the jet of the escaping vapour should
not be extinguished if it has been already ignited.
a. Take immediate steps to stop LPG leakage / fire and the fire alarm
should be sounded immediately by the person locating the fire.
Emergency trip button shall be operated to trip the power and to
operate the siren. The information about fire should be reported
LPG OPERATIONS MANUAL
quickly to the control room and the Plant Manager, indicating the
location nature and gravity of the fire. At the same time, with the
help of available persons, following actions should be initiated in
quick succession or simultaneously if possible.
m. If a valve near to fire can be closed for stopping the leakage, the
same should be tried after wearing Fire Proximity Suit., The attempt
should be directed by the trained persons only. The person
attempting the closure of the valve should be continuously
protected by means of water spraying (through fog nozzles), or any
other approved equipment. The person must be equipped with a
safety harness and manned lifeline. Under no circumstance, should
a person try to enter fire or go closer than the permitted range of
Fire Proximity suit.
n. In the case of any emergency situation, it is of paramount
importance to avoid endangering human life in the event of fire
involving or seriously exposing LPG equipment or serious leakage of
LPG without fire.
(c) LPG vessels and other facilities exposed to fire must be thoroughly
cooled by means of sprinkler system, fixed monitors and hose
streams. The top of LPG vessel shells, which are in contact with
vapour and their supports are the most vulnerable areas.
(f) Fire fighters and other personnel dealing with vapour clouds must
be protected continuously by water sprays. Continuity of water
supply for this purpose must be ensured by means of two hoses
connected to different supply points. Care should be exercised to
ensure that static charge is not generated in LPG vapour cloud. For
this purpose, solid jets of water must be avoided, instead, fog nozzles
should be used.
(h) Water protection for fire fighters should never be shut-off, even
though flames appear to have been extinguished, until all
personnel are safely out of the danger area.
LPG OPERATIONS MANUAL
(j) LPG storage vessels exposed to fire will be protected against over-
pressure by Pressure Relief Valves (PRVs) to a certain extent.
However, in some situations, PRVs may not provide total protection
to the spheres and attention should be always paid to the pressure
(b) If the escaping LPG is not on fire, the valve should be closed to
stop the flow. Automatic gas detectors are provided at the Plants.
Wherever these are provided, they would give “Gas Leakage
Alarm” and give a signal on control panel also. This will help to
identify easily and timely the location of the trouble spot for
quick remedial action.
(e) In some case of leakage from a pressure vessel without a fire (such
as leak from tank truck bullet on over-turning ) it may be desirable
to move the vessel to some remote area, such as block of isolated
LPG OPERATIONS MANUAL
(f) If the flow of LPG feeding a fire cannot be stopped quickly the
first fire-fighting effort must be directed towards cooling the
container so as to prevent spreading of fire to adjacent vessels and
property.
(g) Water protection for fire fighters should never be shut-off until all
are safely out of the vapour cloud /danger area.
(h) Attempts should be made to deflect leaking LPG liquid from flowing
towards work areas, equipment etc, by means of low earth walls,
sand bags, etc. Such barriers can hold vapour and therefore,
should be treated as hazard, until all vapour is dispersed following
their removal.
(b) to the top valve assembly and to the top of the vessel so that
water flowing from the top will cover the shell. Cooling streams
should be continued even after extinguishing the flames until all
danger of re-ignition from the hot steel is eliminated. Cooling of
other adjacent vessels/spheres should also continue by applying
water sprays in an adequate manner.
(b) Apply cooling water streams to the top of the vessel so that the run-
off water covers the shell. Also apply water to the supporting
LPG OPERATIONS MANUAL
(d) Pump water to the vessel to float the flammable material above the
leak. This will extinguish the flames if the water pumping rate
exceeds the rate of leakage.
(e) Should a shell failure occur below the liquid level of the tank and
result in leakage, which exceeds the capacity of water pumping
facilities, spray several solid streams of water on the shell surrounding
the leak. Try to form a curtain of water spray and maintain it until all
the flammable material i.e. LPG is consumed and the vessel
becomes gas free by natural ventilation or by the introduction of
steam (if available to the vapour space of the tank).
5.6.5.1 Case – 1
5.6.5.2 Case - 2
Fire on Storage Vessels : The main defence against the accidental fires
are the inherent safety of vessels constructed to an authoritative pressure
vessel design code, correct operational procedures, the provision
made to prevent overfilling and uncontrolled liquid escape, and
the exclusion of sources of ignition from the storage area. If a pressure
vessel is exposed to radiant heat from external fire, it should be kept
cool by water sprays to prevent excessive pressure rise in the vessel.
The most serious condition arises, when there is direct flame impingement
on the part of the vessel surface which is in contact with the vapour and
not with liquid. Cooling water sprays must be applied without delay to
heat the affected area. For this purpose, fixed water sprinklers, which are
capable of covering the vessel surface area at the desired rate and
which can be put into operation quickly either automatically or by one
man, are of great value. If fixed sprinklers are not fitted, equivalent
coverage of water spray through fixed monitors or other equipment
should be brought into action as soon as possible. Correctly sized
pressure relieving devices protect the vessel from overpressure due to
heating of the liquid contents. Cooling of the vessel with water sprays
reduces the heat input to the vessel and thereby reduces the pressure,
thus, reducing the rate of discharge from relief valves.
5.6.5.3 Case – 3
Tank Truck Fires : In case LPG tank truck is involved in a collision which
results in leakage of LPG, not followed by fire, immediate action should
be taken to stop the leakage. All possible ignition sources should be
extinguished and escaping vapour is dispersed by water spray, if
LPG OPERATIONS MANUAL
available, which should be directed to divert the vapour away from the
nearby occupancies. If the flow of liquid or Vapour cannot be stopped
within short time, the area within at least 100 Ms. (300ft) radius of the
Tank truck should be evacuated and attempts should be made to
disperse the vapour. In case the leakage cannot be stopped until the
bullet is empty, consideration should not be given to deliberate Ignition
of the escaping gas in order to prevent further spread of gas. The
wisdom of such a decision is doubtful because it may result in direct
flame impingement on the bullet shell or a severe explosion may cause
further damage and accentuate the leakage. If, on the other hand, the
escaping gas is ignited by chance, then it should not be extinguished,
but every effort should be made to stop the flow of fuel feeding the
fire, and at the same time, the bullet should be kept cool with copious
application of water spray, particularly on areas where there is direct
flame impingement. Water spray is also useful in giving protection to
persons when approaching valves in an attempt to close them and
thereby stop the flow.
It is likely that in a short time after the bullet is directly involved in fire, the
safety valve will start discharge. Water jets or spray should be continuously
applied to the bullet to reduce the heat input, but if there is a shortage of
water and there is a marked increase in the noise of escaping gas or in
the size of the flame at the safety valve, the rupture of the tank may be
imminent and the surrounding area should be evacuated
5.6.5.4 Case – 4
5.6.5.5 Case – 5
Allow the fire at the relief valves to continue; meanwhile cool the
vessel and tackle the adjacent fire.
When the vessel is cooled sufficiently, the pressure inside the vessel
drops and the PRVs close automatically extinguishing the fire at the
PRV.
5.6.5.6 Case - 6
Fire of LPG vapour escaping from a damaged vessel fitting- flame not
playing on vessel :
5.6.5.7 Case – 7
Fire from overturned bulk LPG lorry - lorry on it’s side with fire enveloping
pressure vessel :
Fire fighters must not position themselves in line with the dished ends
of the bullets.
5.6.5.8 Case - 8
Start water spray only on those LPG vessels exposed to fire / heat.
Isolate affected vessels and run out fire water hoses in case hose
stream cooling becomes necessary.
If PRVs fitted to the LPG vessels have started blowing vapour, take
no further action (apart from cooling), unless the pressure inside the
vessel continues to rise.
Do not try to empty LPG vessels exposed to fire : They become more
vulnerable to overheating as their liquid content decreases.
(c) All LPG storage Vessels, Cylinder Storage/ Filling/ Repair Sheds, LPG
Pump Houses, Bulk Lorry and Tank Wagon Gantries shall be fully
covered by medium velocity water spray system.
(d) Fire Protection Facilities shall have fire fighting access, means of
escape in case of fire and also segregation of facilities so that the
adjacent facilities are not endangered during the fire. The layout
shall permit access from at least two directions.
periphery of the LPG vessel), water density for cooling shall be considered
at the rate of 10.2 LPM/Sq.m surface area.
Tank Lorry Gantry : In case of Tank Lorry Gantry, automatic heat detection
for automatic actuation of MV sprinkler system having remote/local
operated Deluge valve with spray density 10.2 LPM/Sq.m of surface area
shall be provided. A maximum of 8 bays shall be considered as single risk
area.
Fire Water Flow Rate : Typical examples for calculation of fire water
flow rate for various sections in the bottling plant are given in Appendix
No. I
Water for the hydrant service shall be stored in any easily accessible
surface of underground concrete reservoir or above ground tank of steel
or concrete. However, above ground tanks shall be preferred in view of
the availability of flooded suction condition for easy start of the fire water
engines. The effective storage capacity shall be not less than 4 hrs.
aggregate working capacity of fire water pumps.
LPG OPERATIONS MANUAL
5.7.1.5.1 Centrifugal type water pumps for fire service shall be installed to meet the
designed rate of discharge and total head. These pumps preferably
should have a flooded suction
5.7.1.5.2 There shall be a jockey pump of capacity not less than 10 Cu.m/hr. per
100 Hydrant Points. ( one Monitor is equivalent to 4 Hydrant Points). The
system pressure has to be maintained at 7 kg/cm2 (g) with the help of
Jockey Pump operating automatically. The Jockey Pump shall be quick
auto start-stop type with the help of pressure switches. A standby jockey
pump shall be provided if the number of hydrant points are more than
100.
5.7.1.5.3 The fire water pump(s) including the stand by pump(s) shall be of diesel
engine driven type. The pump shall be capable of discharging 150% of its
rated discharge at a minimum of 65% of the rated head. Each engine
shall have an independent fuel tank of suitable size for 6 hrs. continuously
running.
5.7.1.5.5 Fire water pump house / fire water tanks or reservoir shall be located
at least 60 M. (minimum) away from LPG facilities.
5.7.1.5.6 Fire water pumps shall be exclusively used for fire-fighting purpose only.
LPG OPERATIONS MANUAL
Fire hydrant ring main should be normally laid above ground. Following
precautions should be taken for laying fire water ring main above ground
:
a. Pipe line shall be laid at a height of 300 mm to 400mm above the
finished ground level.
b. The mains shall be supported at regular intervals not exceeding 6
meters.
c. The system for above ground portion shall be analyzed for
flexibility against thermal expansion and necessary expansion loops,
wherever required, shall be provided.
(h) Hydrants / monitors shall be located bearing in mind that the fire
hazards at different sections of the premises are to be anticipated
and to give most effective service.
(i) Hydrant / monitors shall be provided for every 30 meters in case of
hazardous areas and may be spaced 45 meters in other areas.
(j) Connections for fire water monitors shall be provided with
independent isolation valves.
(k) Hose boxes with 2 nos. of hoses and a nozzle shall be provided at
each hydrant points.
(l) Considering radiation levels in the event of a fire, hydrants /
Monitors / Control valves shall be located at a safe distance
(minimum distance of 15 meters) and from hazardous equipment /
buildings.
(m) The Deluge valves shall be located out side the kerb wall at a safe
distance in case of LPG spheres / bullets and 15 meters away from
the limits of LPG cylinder sheds. A fire wall shall be provided for the
protection of Deluge valve and for operating personnel.
(n) The above ground fire water main and the fire hydrant stand post
shall be painted with corrosion resistant "Fire Red" paint.
(o) Water monitor and hose box shall be painted with "Luminous Yellow”
paint.
(I) An audio visual alarm at the local / main control panel and
fire water station, indicating the vessel on fire.
LPG OPERATIONS MANUAL
Requirement of First Aid Fire Fighting equipment shall be OISD 144/169 for
LPG Bottling Plants
d. 100% spare CO2 cartridges and 50% (Min) spare DCP bags (as per
Fire Extinguisher Capacities) shall be stored in each plant.
5.8.2.2 Public Address System : Public address system should be connected to all
control rooms, administration building (all floors), all departmental heads,
security etc. Telephone exchange should control and take care of this
system.
5.8.2.3 Fire Sirens : The Fire siren(s) should be located suitably to cover the whole
area with the operational control in the Fire station control room. These
should be tested at least once in a week to keep them in working
condition. Fire siren code should be as follows :
(a) Fire situation: A wailing siren for two minutes. Sirens will be sounded
three times for thirty seconds with an interval of fifteen seconds in
between.
(b) Disaster: Same type of siren as in the case of fire but the same will
be sounded for three times at an interval of one minutes.
(c) All clear (for fire): Straight run siren for two minutes.
5.8.2.4 Walkie-Talkie / Wireless :All the Fire Tenders shall be provided with a
walkie-talkie/ wireless system which will help in communicating with the
people, in case other systems fail. Besides, key personnel coordinating
emergency operations should also be provided with walkie-talkie.
5.8.2.5 Fire Alarm System : Fire alarm points shall be provided at suitable
locations like access point, approach roads, walkways etc. to cover the
critical areas with a control panel in the Fire station control room. The
location should be conspicuously marked for proper identification.
5.9.2 The vapour space portion of the shell gets overheated and fails even at
the operating pressure. As such, it is important that the metal
temperature in the vapour space is protected from overheating by some
measures. A passive measure like fire proofing/ insulation or fire retardant
coating will provide protection in the initial period of fire which is very
crucial. This will give some breathing time for activating other fire fighting
measures like starting of pumps, organizing people, opening of valves
etc. This will also take care of automation failure wherever it is provided.
5.9.3 The fireproofing of LPG storage vessel should be decided based on the
risk analysis keeping in view the local considerations, availability of water
and societal risk.
5.9.6 Fire water line to each sphere should be so routed that it is not exposed
to direct fire. This is to protect it from the failure in the initial period, when
water flow has not commenced. It is recommended that the riser should
be located away from the bottom ROV. The horizontal run of the Fire
Water line may be buried if fire engulfment cannot be avoided
otherwise. Fire-proofing shall include connected LPG lines and pipe
supports within 15 m. of the storage vessel or in the drainage paths.
others, and all have their own limitations. The following points should be
remembered:
(a) For any equipment, the field of effectiveness and capacity are
the two important characteristics.
(e) Combination type spray nozzles, which provide a high velocity jet
for reach and hitting power, are specially useful. They can be
used both for ‘know down’ fires under pressure and to provide
water screen protection for personnel, important equipment and
pressure vessels.
The minimum detectors facility wise are as given below as per OISD 144
& OISD 150. Any Changes in the same shall become applicable:
LPG OPERATIONS MANUAL
Storage vessels (above ground) – 1, No. top and 1 No. near bottom
ROV. LPG pump house 1 No. in pump house and 1 No. in manifold. Filled
cylinder shed - 2 Nos. Valve change shed – 1 No. Empty-cum-filling shed –
2 Nos. near carousel, 1 No. near evacuation unit tank, 1 No. weight
correction unit, 1 no. at degassing shed ( if separate shed is there), 1 no.
at 47.5 Kg Filling machine if provided. TLD – one at each manifold and at
ends. Tank wagon gantry – 1 no. for every two bays or 30 m whichever is
less at bottom. Additionally, some detectors at selected locations shall be
provided at the top of platform. The number and location of the
detectors required over and above the minimum requirements specified
above shall be as per the specific requirements identified in the risk
analysis / HAZOP study report.
All the key points in the fire fighting system should be checked daily and
corrective action should be taken wherever required. The following
points are to be checked :
5.13.1 A plan of action for use in the event of a major LPG product leakage with
a fire or risk of fire is essential. Such plan should be carefully prepared by
the Plant Manager. It must be fully understood by all the plant supervisory
personnel and other personnel responsible for taking action as per plan. It
can be based on the following
(b) If leakage and / or fire occurs, it is the duty of all personnel to use
the equipment provided, and to carry out their allotted tasks as
detailed in the “Fire Fighting Organization Plan’.
(c) All personnel must know how to identify fire control equipment
suitable for use with LPG also its location and how to use it.
(f) The “Fire Fighting Organization Plan” together with layout of fire
fighting and safety devices must be displayed at prominent places
after explanation to all personnel. It should include the following
functions, expanded to suit the local facilities / requirement :
LPG OPERATIONS MANUAL
The local fire brigade should be made familiar with the plant layout
showing in addition to the operating facilities, the position of all fire
control equipment, water sprinkler system, mains and hydrants, and
the position of all important equipment including the emergency / safety
valves. They should also be well informed regarding the extent of the
operation carried out, e.g. volume of product normally held in bulk,
cylinders, vehicles, etc.
Close co-operation with the local fire authorities is essential and should
take the following form :
(a) The Fire Brigade should be made familiar with the location of
important facilities, all the fire control equipment / facilities
provided, and their method of use. The holding of fire drills /
exercises jointly by the plant personnel and local fire-brigades
should be considered.
LPG OPERATIONS MANUAL
(b) Fire Fighting equipment at the plant should be compatible with the
fire brigade equipment. Otherwise, adaptors should be kept ready
for hoses, hydrants, etc.
(d) In the event of an emergency / fire, the Plant Manager and /or his
representative must advise the Fire Officer about the particular or
potential hazards that may be present, e.g. stocks of filled cylinders
at that particular point of time.
(e) Liaison should also be maintained with other nearby oil Companies
/ Industrial plants to provide mutual assistance in case of an
emergency.
(a) Mock Drills for all plant personnel, making use of the “Fire fighting
Organization Plan” and practicing the specialised techniques
required for fighting LPG fires or dispersing / diluting LPG vapour
clouds, should be held minimum once in 30days.
(b) (The drills should cover various types of incidents , e.g. major
spillage of LPG, bulk tank truck fire, cylinder fire, etc.
(d) Fire alarms should be tested for proper sound (neighbouring plants /
factories and the Fire Brigade should be warned in advance of this
test.)
a. The Plant Manager should ensure that records of all LPG emergency
(fire) drills held are maintained in the ‘Fire Drill Record‘ book.
Every pump should be test run for at least half an hour minimum two
times a week. Once in a month, each pump should be checked and
tested and the shut off pressure observed and logged. Once in six
months each pump should be checked for performance. This may be
done by opening the required number of hydrants/monitors depending
on the capacity of the pump and by verifying that the discharge
pressure, flow and motor load are in conformity with the design
parameters. For the flow measurement suitable device, like ultrasonic
instrument may be considered.
LPG OPERATIONS MANUAL
The ring main should be checked once in a year for the leaks etc. by
operating one or more pumps with the hydrant points kept closed as
required to get the maximum operating pressure. The ring main, hydrants,
monitors, valves should be visually inspected every month for any
pilferage, defects and damage. All fire main valves should be checked
for operation and lubricated once in a month. Flushing of fire water
header ring main shall be flushed weekly section/loop-wise through a
return line provided for the purpose from the header to fire water tanks as
per HO guidelines. Pipeline sections having dead ends shall be flushed
through blow down drain at the dead end.
5.15.2 A mock fire drill should be conducted once in a month to rehearse the
fire emergency procedures and to keep the fire fighting team trained
and alert and facilities in top order.
APPENDIX No. I
TYPICAL EXAMPLE FOR CALCULATION OF FIRE WATER FLOW RATE
1. DESIGN BASIS
The fire water system in the plant shall be designed to meet the
highest fire water flow requirement of a single largest risk of any of
the facilities at a time plus 288 Cu.m/Hr. for operating 2 Nos. Fire
water Monitors/ Supplementary Hose requirements. The Fire Water
pressure system shall be designed for a minimum residual pressure
of 7.0 kg/ cm2 g at the remotest place of application in the plant.
The calculations given below are illustrative. OISD standards and
guidelines from HO LPG latest as applicable to be referred for
details.
(a) Data:
No. of spheres in one area = 3
Diameter of each sphere = 17 meters.
Note: Manifold area & any other connected facility with vessel
covered by sprinklers, to the sphere area to arrive at actual flow
requirement )
BACK
6
LPG OPERATIONS MANUAL
6.1 GENERAL
6.1.1 This chapter covers the description of various facilities and equipment
provided at LPG bottling plants for storage and handling of bulk LPG.
6.1.3 Bulk storage facilities at LPG plants are installed in accordance with “The
Static & Mobile Pressure Vessels (Unfired) Rules, 1981” (SMPV Rules). The
conditions of the relevant licenses required as per the rules must,
therefore, be complied with. This should be ensured before
commissioning of any facility / equipment and thereafter during
operation of the vessels.
6.1.4 For further detailed information on bulk storage and handling facilities
OISD STD-144 may be referred.
6.2.1.1 The mechanical design of storage vessel are based on the following
considerations:
(a) Design Code : ASME SEC. VIII or IS-2825 or PD 5500 ( formerly BS 5500
) or equivalent duly approved by CCOE.
Design shall take into account “Static and Mobile Pressure Vessels
(Unfired) Rules 1981” and subsequent amendment revisions , if any .
A single code shall be adopted for the design, fabrication,
inspection and testing, i.e. ASME and BS shall not be combined.
(c) Marketable LPG conforming to IS: 4576 & IS: 14861 is having a
maximum vapour pressure of 16.87 Kg/cm2. (g) at 650 C
temperature
(d) Presently, the pressure vessels are being designed for a design
temperature of -270 C to 550 C with a design pressure of 15 Kg/cm2
at the top of the vessel at 55o C
This type of storage is useful in rocky terrain for huge quantities and is
cost effective. For identification of most favorable site, assistance of
expert geologists is required for determining the rock conditions and
water level by drilling number of bores at suitable depth. There are
3 types of such storage systems :
These storage systems are isolated from external hazards like fire,
war, sabotage, explosions and natural calamities. This type of
storage requires less area of land. In some countries (especially in
U.S.A.), large quantities of LPG are stored underground. One cavern
storage of 60000 MT LPG storage capacity was commissioned in
2008 at Visakhapatnam.
(c) Mounded Storage : Mounded type storage vessels are sited above
ground, horizontally placed cylindrical vessels and completely
covered by a mound of earth or similar inert, non combustible, non-
corrosive material except for nozzles, manhole covers and
inspection covers fitted on the vessels. The mounded storage of
LPG has proved to be safer compared to above ground storage
vessels since it provides intrinsically passive and safe environment
and eliminates the possibility of Boiling Liquid Expanding Vapour
Explosion (BLEVE). The cover of the mound protects the vessel from
fire engulfment, radiation from a fire in close proximity and acts of
sabotage or vandalism. The area of land required to locate a
mounded system is minimal compared to conventional storage.
Mounded vessels with storage capacity of 100 -2100MT, have
been provided at IOC plants.
The Pressurised vessels used for storage of LPG must have following
details affixed on them :
(a) All fittings and accessories of the storage vessel shall be conforming
to” Static & Mobile Pressure Vessels (Unfired) Rules, 1981".
(b) Each storage vessel shall be provided with fittings as shown in the
following table:
LPG OPERATIONS MANUAL
(c) Spheres and bullets shall have a single nozzle at the bottom for the
inlet and the outlet. The nozzle shall be of seamless pipe fully
welded to the bottom of the vessel, stress relieved along with the
vessel and shall extend minimum 3 (three) metres from the shadow
of the sphere / bullet. A fire safe Remote Operated Valve (ROV)
shall be provided on this bottom nozzle at a distance of at least 3
(three) meters from the shadow of sphere / bullet. The nozzle pipe
shall have a slope of 1.5 degrees.
(d) There shall not be any other flanges, valves, manhole and
instrument tapping on this nozzle up to the ROV or at the bottom of
sphere / bullet. In order to avoid stress on the nozzle due to relative
settling of supports and sphere, support legs from the vessel
supporting the bottom nozzle should be provided. The top vapour
zone of the vessel shall be provided with nozzles for vapour inlet /
outlet, which shall also be provided with fire-safe ROV.
(e) All the fittings shall be suitable for use at not less than the design
pressure of sphere / bullet and for the temperature appropriate to
the worst operating conditions. The remote operated valves on the
lines connected to the sphere / bullet shall be fire-safe type. The
flange joints of these valves shall have spiral wound metallic
gaskets. Plain asbestos sheet gaskets should not be used. All flange
joints shall be fitted with SS Spiral wound metallic gaskets with
LPG OPERATIONS MANUAL
properly sized standard studs and nuts suitable for the rating of the
flanges.
(a) Pressure Relief Valve is a device to protect the vessel against the
damages as a result of excessive build-up of pressure beyond the
prescribed safe limits. It is also known as ‘Safety Relief Valve’ (SRV).
Basically, there are two types of pressure relief valves:
Single Port (Refer Drawing No. 6)
Multi Port (Refer Drawing No. 7)
(b) Multi Port relief valves have more than one port and are used on
large containers such as horton spheres and storage bullets. For
small containers such as tank wagon bullets and tank truck bullets,
single port pressure relief valves are used. In the case of multi port
pressure relief valves, each of the ports can be isolated from the
container by the operation of the built-in isolating valve, thus
facilitating removal of that port for inspection and maintenance.
(c) While the valve retains vapour at normal working pressure, it opens
to relieve excess pressure in case of any build-up of pressure beyond
safe limits. The situations which may cause abnormal rise in pressure
are due to :
Fire
over-filling
(d) Minimum two pressure relief valves with 100 % relief load each are
provided on a pressure vessel as per statutory rules. The pressure
relief valves provided MUST be spring loaded. Weight loaded relief
valves are not permitted.
Manufacturer’s name.
Date of Manufacture and Batch/Serial Number
Test date of the SRV
(f) A positive shut-off valve MUST be provided between the vessel and
relief valve. The valve must have direct communication with the
vapour space of the vessel. For storage vessels, valve must be fitted
with extended vent(s), adequately supported and having outlet at
least three metres above the top of the vessel. The vent pipes must
be fitted with rain caps (loosely fitted). Isolation valve shall be kept
locked in open condition or wheel removed in open condition.
(h) The valve is set and sealed at the factory to function at a specific
“Start-to discharge” pressure. The two SRVs on LPG storage vessel
shall be set at two different set pressures in line with OISD 144. If the
container pressure reaches the set value , the valve will open
slightly. Despite this, if the pressure in the container rises, the valve
will suddenly pop wide open. This action is accompanied by a
sharp noise of escaping vapour.
(ii) Pipelines
Tank wagon loading / unloading points.
Tank truck loading / unloading points.
(b) In the normal condition, the excess flow check valve is kept in open
condition by a means of a spring, i.e. when the rate of LPG flow
is below the rated capacity. When the flow rate increases more
than the setting, the valve seat closes, thereby stops the flow of LPG.
(c) Following type of Excess Flow Check Valves are being used:
Fixed Maximum Liquid Level Gauge indicates the liquid level at which the
container is filled to its maximum permitted filling capacity i.e. 85%.
This device is installed and set to the maximum level to which the vessel
can be safely filled. It is a tube with bleeder valve at the top. The length
of the tube inside the tank is pre-determined with the result that when the
liquid level reaches the bottom of the tube, the liquid comes out as a
spray through the bleeder valve when opened. Since this gauge has the
limitation of indicating only one particular level, it is installed only as an
auxiliary gauge from the safety point of view. This type of gauge is
installed on storage vessels as well as tank trucks / tank wagons. ( Refer
Drawing No.10 )
This type of gauge indicates the liquid level in a vessel through a range of
levels. Following gauges fall into this category :
LPG OPERATIONS MANUAL
The gauge has two SS floats, which move up down with rise or fall of the
liquid level of the Vessel. Each float has inside a special annular ring
magnet. The floats travel along a 40 mm NB SS tube called "Guide Tube".
This "Guide Tube" is sealed at the bottom. Inside the guide tube, a
calibrated gauging rod fitted with magnet at its lower end travels.
Assuming that the bullet is empty and filling is about to start, both the
floats as well as the gauge rods would be in the lowermost position. The
gauge cover at the top is unscrewed so that the gauge rod can move
out. When the filling starts, the float slowly starts moving upwards along
the guide tube. The magnet inside the float causes the gauging rod to
move up. The calibrated gauging rod carries the level markings, which
can be read easily. (Refer Drawing No. 11)
It is a gauge constructed with a float inside the vessel resting on the liquid
surface, which transmits its position through a suitable leverage to a
pointer and a dial outside the container indicating the liquid level. The
motion is transmitted magnetically through a non-magnetic plate so that
no LPG is released to the atmosphere. This type of gauge is normally
provided on the storage bullets / evacuation vessels (Refer Drawing No.
12 and 13). With the addition of accessories like explosion proof
transmitter and remote display, the reading of the level of Liquid LPG can
also be transmitted to the pump house and control room. This gauge can
be used only in the LPG bullets / mounded storage vessels up to
diameter of 6metres.
Simple buoyancy and magnetic field are the underlying principles of this
instrument. This instrument has a float (called displacer), which is
suspended across a spring. When the vessel is filled with liquid, the
displacer is submerged below the surface of the liquid. When this
happens, the buoyancy causes the spring to contract. This longitudinal
movement displaces a drive magnet, which then attracts a follower
magnet, provided on the outside of the lead pipe. This actuates a micro
switch, which gives an output signal. This output signal is fed to an audio-
visual alarm located at any convenient place. This output signal is also
used to close the ROV on the liquid line of the vessel. This shall be
checked once a month by competent person and record maintained.
(Refer Drawing No. 16).
It is normally provided with a shut off valve of 50mm (2-inch) dia. nominal
size. This shut-off valve is provided with a length of pipe terminating
with a second shut off valve of 50 mm (2 inch) diameter nominal size.
The first valve nearer to the water drain point shall be of quick shut off
type and the second upstream valve near vessel shall be of throttle type
(globe valve). Between these two valves, EFCV of suitable rating is
provided. The length of pipe between the valves is such that the risk of
simultaneous obstruction of both the valves is minimised. A sufficient
length of piping is provided downstream of the throttle valve to ensure
that the discharge will not take place beneath the vessel / pipeline
LPG OPERATIONS MANUAL
manifold. The second valve and the connected pipeline are adequately
supported and secured to prevent breakage by jet forces. The throttle
valve shall be locked in closed condition and shall be opened by
operator only for the draining purpose. End flange with blind shall be
provided at the drain mouth. The blind flange shall be removed only
during water draining purpose and shall be re-fixed after completion of
water draining
In the case of first category, the Railways own the under-frame as well as
the bullet. In the case of joint ownership tank wagon, the under-frame is
provided by the Railways whereas the barrel (Bullet along with fittings) is
provided by a marketing company.
Design Criteria : All tank wagons used for transportation of LPG shall be
as per the approved design of RDSO. RDSO of Indian Railways issues the
design parameters for the tank wagons used for transportation by rail. The
design parameters of the LPG wagons are as follows:
LPG OPERATIONS MANUAL
6.4.1.3 Filling Considerations : The maximum quantity of LPG filled in any tank
wagon shall be limited to the filling density of the LPG and shall be such
that the tank wagon shall not be liquid full due to expansion of the
contents with rise in the temperature to 55 degree C. or limited to
specified gross weight on the wagon, whichever is less.
LPG OPERATIONS MANUAL
6.4.2.1 Types : There are basically two types of LPG tank trucks :
6.4.2.3 Design :
6.4.2.4 Applicable rules : LPG tank trucks fall under the purview of the ‘Static
and Mobile Pressure Vessels (Unfired) Rules,1981’ . All applicable rules
pertaining to the tank truck, which would include driving unit with chassis,
as well as the bullet, must be followed.
6.4.2.5 Fittings : The following fittings are provided in LPG tank trucks :
(a) Safety Relief Valve (SRV) : There shall be minimum two Safety Relief
Valves with each one sized in such a way to suit the full relieving
capacity of the vessel. SRV shall be so installed that it does not
project out of the top surface of the vessel. If necessary, recessed
cup formation on the vessel shall be made to house the SRV. Safety
relief valves shall have the following marking punched :
(c) Internal Valve with Excess Flow Check Valve : Internal valves with
EFCV of appropriate ratings shall be installed on LPG liquid and
vapour lines. This valve shall have an in-built internal excess flow
check valve(Refer Drawing No17). All tank trucks used for Auto LPG
supply to ALDS(Auto LPG Dispensing Station) shall be provided with
Internal EFCVs on LPG liquid and vapour lines.
(d) Liquid Level Gauging Device - Roto Gauge : The vessel is equipped
with a liquid level gauging device for determination of the liquid
level in the vessel at any time. The liquid level gauging device is to
be operated manually for determination of liquid level at any point
of time. When the level has to be measured, the lever outside the
gauge is rotated slowly till a vapour cloud becomes visible thru a
LPG OPERATIONS MANUAL
tiny opening on the nut of the lever. Hence, a very small leakage
of the product to the atmosphere takes place.
This liquid level gauging device is located on the shell near the
midpoint / top upper half of the vessel in a recessed cup formation.
To avoid damage to this liquid level gauging device, a suitable
hinged cover is provided.
(e) Pressure Gauge : 1 no. dial type (100 mm) glycerin filled pressure
gauge with EFCV shall be provided on the rear dished end in the
vapour space. This shall be protected by 10 mm thick U-type shield
metal plate. The range of the pressure gauge shall be from 0 to 21
kg/sq. cm (g).
(h) Manhole : 1 no. manhole of size as per IS 2825 or code followed for
the design and fabrication of vessel shall be provided on the rear
dished end.
1. Vessel Manufacturer
2. Vessel Manufacturer’s Serial No.
3. Design code
4. Radiography
5. PWHT
6. Design Pressure
LPG OPERATIONS MANUAL
7. Design Temperature
8. Hydrostatic test pressure
9. First test date and subsequent test dates
10. Water capacity in litres
11. Licensed Product capacity in MT and symbol or chemical
name.
12. Name of the Inspection Agency with its stamp.
13. Certificate number of Inspecting Agency.
14. Shell thickness & Dish End Thickness
15. This vessel shall not contain any product having vapour
pressure in excess of 120 RVP at 55 deg. C.
16. Next hydro test date of the vessel shall be painted on the body
of the vessel.
III. The maximum width and height of the vessel and its service
equipment shall be such that these do not project beyond
the overall width and height of the rest of the vehicle. The
maximum height of the vehicle shall be in accordance
with Motor Vehicles Act, 1989.
6.5.1.1 The word ‘transfer’ is used to indicate the movement of bulk LPG within
the plant area. It could be between any two points as follows :
6.5.2 The various facilities / equipment used for the purpose are described
below :
(b) There are two categories of LPG pipelines at the plant; one carrying
LPG in the liquid form and other in vapour form. The lines should be
properly color coded to differentiate liquid lines ( Yellow) and
vapour lines ( Green).
“Case History”
Double Mechanical seal for sealing the shafts of all rotary pumps
designed specifically for these liquids with seal failure alarms shall
be provided.
LPG Pumps shall be provided with suction and discharge pressure
gauges, a high point vent to safe height or flare, and a suction
strainer.
6.5.3.2 Types of Pumps : There are two types of pumps used for LPG service :
6.5.4 COMPRESSORS
6.5.4.2 The compressor method of product transfer is based on the principle that
the compressor creates a differential pressure between the receiving and
discharging vessels by withdrawing the vapour from the receiving vessel
and forcing it at high pressure into the discharging vessel, thereby
establishing smooth product flow. The procedure is explained in detail in
Chapter No. 7.
6.5.5.1 Positive displacement type liquid flow meters and Mass Flow Meters are
used for LPG service. A suitable strainer, vapour eliminator and
differential valves are provided as integral parts of the metering system.
6.5.6 HOSES
6.5.6.1 There are 3 different types of hoses. Type-1, 2 and 3. In general, LPG hoses
are made utilising three basic components as follows :
(a) Carcass : The strength member or body of the hoses is the tube of
woven fabric cords or woven wires, which make up the inner body of the
hose and provides both form and strength. The number of plies or layers
may vary depending upon the diameter or working pressure of the unit.
This structural form is secured in place by vulcanisation of an elastomer
about the individual plies.
(b) Tube : With the carcass there is a cylindrical tube, which is vulcanized
directly to the inner surface. The purpose of the tube is to provide seal
LPG OPERATIONS MANUAL
6.5.6.2 Flexible connectors are normally made for LPG hoses. Suitable end
connections are attached so that the connectors fit into the connections
at loading / unloading points and also on liquid / vapour connections on
tank wagons and tank trucks. (Refer EN-1762 ( Earlier BS : 4089 )-
Specification for Rubber hose and Hose assembly)
6.5.6.3 BIS has also standardised the specification for LPG Hoses vide IS:9573.
Basic details are as under:
(a) Following details are marked on each length of hose, at least once
every 3metres :
(b) Hoses are manufactured with varying bore diameter ranging from
8mm to 75mm. Length of a hose can be specifically ordered on the
manufacturer.
(d) The hoses are suitable for use of LPG in vapour phase as well as
liquid phase.
6.5.6.4 Basically hoses subjected to vessel pressure are designed for a bursting
pressure of not less than five times the design pressure of the vessel and a
test pressure of not less than twice the design pressure of the vessel. The
LPG OPERATIONS MANUAL
hoses are tested at 25 Kg/sq.cm. and the pressure must be maintained for 5
minutes. Subsequently the hoses shall be tested pneumatically for 3.5
Kg/sq.cm. and the pressure shall be maintained for 10 minutes.
6.5.6.5 Hoses should be mechanically and electrically continuous. The hose should
have electrical continuity from one end to the other; with the resistance
of not more than 0.75 ohm/m.
6.5.6.6 Hoses conforming to IS: 9573 or meeting with higher standards should only
be used for LPG service.
6.5.6.7 LPG Hoses shall be inspected and hydrostatically tested at an interval of not
exceeding 4 months in line with OISD std 135.
6.5.7.1 The unloading / loading arms are made of steel pipes with swivel joints and
get rotational freedom connected with special couplers. They are provided
for making quick connection / disconnection of LPG tank truck outlet
nozzles to the plant pipe lines. These are provided as a replacement to the
conventional rubber hoses for unloading / loading of LPG tank trucks. The
advantages are :
6.5.7.2 Loading arms are also provided at LPG Railway tank wagon gantry
without ‘Quick Connect Dry Break Couplers’, wherever the volume of
handling of LPG tank wagons is very high. Such locations could be LPG
Import Facilities or TOPs.
6.5.7.3 Functions :
time lost in making the connections using hoses and reducing the efforts
of handling.
(ii) LPG Unloading / Loading arms with Quick Connect Dry Break
Coupler
(iii) LPG Unloading / Loading arms with Quick Connect Dry Break
Coupler and Emergency Break Away Coupler
This type of unloading / loading arm is very similar to the above (i)
except that it has emergency break-away coupler. The emergency
break-away coupler is provided to enable the unloading / loading
arm to get separated from the tank truck under the emergency
situation when the tank truck drives out of the unloading / loading
bays even without disconnection. The breakaway coupler operates
on the mechanism that on experiencing a pulling shear force due to
the tank truck being driven out of the bay causes the two halves of
the break-away coupler joints by shear pin or spring loaded clamps
to get separated and consequently closes the spring loaded valves
to stop the leakage of LPG from both the halves of the couplers.
After the emergency is over, the break away coupler can be re-
assembled and fixed with a new shear pin or sprng clamps as per
the design.
For the tank truck LPG unloading / loading facilities at bottling plants, LPG
TOPs and Import Facilities, the arm size of 50 mm dia. end connection is
considered to be adequate. For Railway tank wagons, the piping size of
75 mm dia. is considered to be adequate with end nozzle/ coupler of 50
mm dia. For LPG unloading application, two arms per bay are
required, one for liquid and the other for vapour. At loading locations no.
of arms is decided depending on the process. In case vapour balancing
line is provided, two arms are not required and only one liquid arm will
be sufficient. However, for weight correction / sick tank truck
decantation, the bay should have both liquid & vapour arms.
LPG tank truck, when it reports to near the TLD bay before the earlier
a batch is about to be released, has to be fixed with the spare male
adapters provided in the plant. In some older versions, along with
adapters, spool pieces may have to be attached. All flanged
connections are to be made using 8 nos. studs of proper size (
around 2-4 threads shall be visible after full tightening on both sides )
and metallic gasket of standard rating ( Class 300 ). No fibre/CAF
gaskets are to be used .
LPG OPERATIONS MANUAL
(i) LPG tank wagon after positioning at the gantry, will require
threaded spool piece to be screwed into the top Liquid outlet valve.
The threaded spool piece has flanged end on the other side.
(ii) The unloading / loading arm parking lock is opened and the end
flange of the arm is aligned with the spool piece flange and fixed
with a gasket and studs / bolts.
(iii) The unloading / loading arm valve is opened and the flow of liquid
for transfer is commenced.
(iv) While closing down, the reverse operation is to done.
6.5.7.9 Maintenance :
The general tips for maintenance are given below but however, for
comprehensive maintenance plan, it is suggested to follow the
manufacturer’s recommendations.
LPG OPERATIONS MANUAL
Sight flow indicators are provided on the pipe lines near the tank truck /
tank wagon loading / unloading points and also near the pump house
to find out the flow of liquid through the line. It consists of a flanged unit
fixed on the pipeline with transparent glasses on two sides. The flow in
the pipeline can be visually seen through the glass.
(ii) This is an essential feature for every LPG plant, since it is the
basic means to check the quantity loaded into or unloaded
from the bulk Tank Trucks in terms of weight. Despite having
loading through Mass Flow Meters at some of the plants, Weigh
bridge is used for final measurement for invoice preparation.
(iii) Weigh bridges are also used for loading tank wagons.
LPG OPERATIONS MANUAL
DRAWING-1
LPG OPERATIONS MANUAL
DRAWING NO.2
LPG OPERATIONS MANUAL
DRAWING NO.3
DRAWING NO.4
LPG OPERATIONS MANUAL
DRAWING NO.5
DRAWING NO.6
LPG OPERATIONS MANUAL
DRAWING-9B
LPG OPERATIONS MANUAL
DRAWING NO.10
LPG OPERATIONS MANUAL
DRAWING NO. 11
DRAWING NO.12
LPG OPERATIONS MANUAL
DRAWING NO.13
DRAWING NO.14 .
DRAWING NO.15
TYPICAL INSTALLATION OF RADAR LEVEL GAUGES ON
MOUNDED LPG BULLETS
LPG OPERATIONS MANUAL
DRAWING NO.16
LPG OPERATIONS MANUAL
DRAWING NO.17
DRAWING NO.17
7
LPG OPERATIONS MANUAL
7.1 GENERAL
7.1.1 This chapter covers the details of operations at LPG Bottling Plant
pertaining to handling of bulk LPG.
7.1.2 Bulk LPG operations at the plant are governed by the ‘Static & Mobile
Pressure Vessels (Unfired) Rules,1981’ . Therefore, all related rules and
conditions for the licenses granted under the “Static & Mobile Pressure
Vessels’ (unfired) Rules, 1981” must be complied with. However, These
Rules undergo revisions/amendment and same shall be applicable once
they comes into force
7.2.1 The total storage of bulk LPG shall be restricted to the licensed capacity
approved by CCOE and the capacity of the individual storage vessel
should be restricted to 85 % of the level of the approved water capacity
of the storage vessel. This reading must be painted prominently near the
storage vessel and in LPG pump house.
7.2.2 Where LPG is transferred from one vessel to another or is moved through
a pipeline system, hazards like over filling, very high pressure leading to
failure of hoses / pipelines, leakages etc may develop unless all relevant
safety precautions are observed. The transfer of LPG in or out of mobile
vessels (e.g. tank truck or tank wagon) requires special attention as
accidental movement of these mobile vessels may cause rupture in the
transfer equipment. The precautions applicable to most of the transfer
operation in mobile/static vessels are as follows :
(b) Fire extinguishers shall be placed near the advantage points as per
the guidelines of OISD standards during the transfer operations.
(c) Gas detection system shall be provided in line with OISD-STD-144 and
150 (for Mounded Storage) .
LPG OPERATIONS MANUAL
(g) Do not place any part of the heavy material over any gauging
device, or over the discharge end of a pressure relief valve.
(h) Do not expose hands, face, or clothing to liquid LPG. Always wear
protective gloves to avoid skin burns, while connecting /
disconnecting the connections, which may discharge liquid LPG.
(i) Venting and purging of LPG during the transfer operation normally
should not be carried out in open atmosphere. In case the same is
warranted for operation, then it should be piped to a suitable flare
system. Where such facility does not exist, vent pipes shall be
provided to carry the vented product to a safe distance and
released at a height not less than 1.5 meters above the eve of the
shed . The vent pipe shall be properly earthed and its exhaust be
covered with copper non corrosive material double wire mesh(Size
:11 linear) between the end flanges provided for the purpose.
LPG OPERATIONS MANUAL
(j) Any vessel (tank trucks, storage vessels etc) having a pressure of less
than (one) 1 Kg/ sq.cm.(g) should be investigated for such low
pressure before unloading/loading.
(m) Ensure that log book is maintained properly for all transfer operation
and readings of the vessels under operation should be recorded in
the log book on hourly basis.
(n) Once the liquid line ROV closes on actuation of HLA of storage
vessel , the ROV is to be manually opened locally ( manual mode )
or through pneumatic override for taking the product out for
filling/TT loading, inter vessel transfer etc. and immediately put back
into Auto mode once the HLA is deactivated. Any ROV that is put
into manual/local mode is to be logged in the log book by the
concerned Operator/supervisor with reason for the manual mode
and against such entry , date and time for putting back into manual
mode is to be logged.
LPG OPERATIONS MANUAL
7.3.3 A positive bonding must be provided between any mobile vessel (i.e.
tank wagon or tank truck) and the receiving or discharging vessel or
system. The bonding should be completed before any operation related
to the transfer procedure is commenced. The bonding should remain
effective throughout the operation. Locations where Automated Loading
Facilities are available, earthing of TT is checked through earthing relay.
Any discontinuity in earthing leads to stoppage of flow and alarm at
control station. The bonding should be disconnected only after the
transfer operation has been completed and the system is secured with all
openings plugged, capped or flanged.
7.4.1 GENERAL
The high volatility of LPG calls for transfer techniques different from the
conventional pumping system used for the less volatile petroleum liquids.
LPG may be transferred by gravity or pumping or pressure differential
between the ullage space of the vessel being discharged and the ullage
space of the receiving vessel or by a combination of these methods.
7.4.3.1 If LPG is pumped from vessel ‘A’ to vessel ‘B’ along a single line system
[Refer Drawing No. 19(a) ], the pressure in the ullage space of vessel ‘A’
gradually falls and may reach the atmospheric pressure. When this
happens, the liquefied gas in the vessel ‘A’ commences to boil and this
boiling will continue as long as pumping continues. The latent heat of
vaporisation absorbed from the liquid and the vessel surroundings cools
the liquid and in consequence, the vapour pressure of the liquid falls. If
the vapour pressure inside the vessel falls below the vapour pressure of
LPG, vapour lock may take place in the pumps resulting in stoppage of
LPG transfer.
7.4.3.2 Pumping difficulties at times encountered with single line system may be
overcome by equalising the ullage space pressure through the
LPG OPERATIONS MANUAL
7.4.3.3 By-pass valve {Refer Drawing No. 15(c)} on the discharge side of the LPG
pump helps to relieve the pressure in the event of development of
pressure above the pre-determined limit due to accidental closure of
discharge valve. The by-pass valve discharges into the pump suction or
back to the supplying vessel. While either manually controlled or
automatic by-pass valve set to operate at a pre-determined differential
pressure can be used with centrifugal pumps, it is necessary to provide
automatic by-pass valve set at pre-determined differential pressure with
positive displacement type pumps.
7.4.4.1 This method involves withdrawing vapour from the receiving vessel,
compressing the vapour and discharging the compressed vapour into
the ullage space of the delivering vessel. The method of pressure
differential is well suited for unloading operations.
7.4.4.3 Differential vapour pressure of 1.5 to 2.0 kg/cm2 is usual for most of the
unloading operations.
7.4.5.2 Before LPG is transferred from a vessel to any other vessel, whether it is a
storage vessel, tank truck or tank wagon, the following precautions are
to be followed :
LPG OPERATIONS MANUAL
7.4.5.3 During LPG transfers from tank trucks / wagons or one vessel to another,
regular monitoring is to be done by the competent person to ensure that
the receiving vessel is not being over filled. On completion of the
operation also, the receiving vessel should be checked to ensure that it is
not filled above its safe filling level. To ensure safe operation, the ROVs of
all LPG vessels shall be interlocked for closure with HLA (High Level Alarm).
7.4.5.4 In the case of tank truck / tank wagon operations, the procedures given
below should also be followed, in addition to the precautions listed
above :
7.4.6.2 Any drain valve, bleeder valve, etc. in the LPG system which
communicates directly to the atmosphere should not be left open
without a competent person in attendance unless positive measures are
taken to prevent escape of the product.
7.4.6.4 The person in charge of operation should ensure that transfer operation is
stopped and all valves are closed in case of the following
occurrences :
7.4.7.1 No operation should be carried out during the hours of darkness unless
adequate lighting as per SMPV rules is available. Permission for carrying
out transfer operation after sunset must be available with the plant for
carrying out any operation after sunset.. Generally, endorsement for
carrying out the operation after sunset is given by CCOE for the LPG
Plants on applying for the same.
LPG OPERATIONS MANUAL
7.5.1.1 All relevant precautions listed in Clauses Nos. 7.4.5 to 7.4.8 and their sub-
clauses should be observed for the operation.
7.5.1.2 The unloading area must be free and clear of any material that might
cause a potential fire hazard. The surface of the ground together with
stairs, ladders, and platforms, if any, must be in such a condition that the
operator can perform his duty without any hazard. Wherever overhead
gantry is provided, gantry platforms (swing type) and hoses / unloading
arms are to be raised and secured in position after completing the final
inspection and before the entry of the tank wagon rake.
7.5.1.3 All tools, hoses, unloading arms and pipe fittings must be clean and free
of oil dirt or grit so that the pipe connections can be made conveniently
and safely.
7.5.1.4 Ensure that necessary operational / safety equipment and tools required
for the operation are kept ready.
7.5.2.1 Determine the tank wagon number and verify the particulars with the
shipping advice or challan or any other relevant document.
7.5.2.2 Check for the correct placement of the tank wagons in relation to the
hoses / arms connections at the unloading point.
7.5.2.3 Set the brakes of the tank wagons, in coordination with the Railways.
Place the appropriate caution signs such as “STOP-TANK WAGONS
CONNECTED” on the open end or ends of the siding. The signs should be
placed at least one tank wagon length away from the last tank wagon at
the open end. These signs must remain in place until all the tank wagons
LPG OPERATIONS MANUAL
7.5.2.4 Whenever separate gate is available for the Railway siding, the same
should be closed and locked after the placement has been made.
7.5.2.6 Before unloading, the wagons shall be visually examined. Check for
physical damage to the barrel and for leakages for dome fittings.
7.5.2.7 Check that wagon surface is free from rust and deep pitting and the
painting is in good condition.
7.5.2.8 Before opening the lid of the dome, ensure that the seals and locks, if
any, are intact. Break the seal, remove the dome cover pin and carefully
lift the dome cover.
7.5.2.9 The operating personnel should not position their faces over the relief
valve.
7.5.3 SAMPLING
(a) Operating personnel should not lean over or position their head or
body directly over the tank wagon gauging device, while releasing
the hold-down latch.
(b) Remove the cover that protects the magnetic gauge. This must be
done slowly and carefully since the slip tube gauging device may
have become unlocked and be pressed against the cover. High
pressure may force the gauge tube to come out rapidly and
therefore, should be prepared to prevent it from popping up when
the cover is freed. If the gauge has not come up by itself pull out
the same, but do not bring it to the extreme lower end.
(c) Slowly pull out the magnetic level gauge till a resistance is felt due
to magnetic pull by the opposite pole floating magnet on the liquid
around the magnetic gauge pipe. The gauge shall be held at this
position by itself. Read the gauge mark on the side of the slip tube
corresponding to the top surface of the gauge pipe mouth and
record the reading. This reading is indicative of the liquid level in the
tank wagon.
(d) As soon as the gauge is read, bring the magnetic gauge down to
the lowest position and lock it in its place. Secure the gauge cover
back over the slip tube.
(e) Record the gauge tube readings. The difference in the dip reading
of the loading location and the unloading location is to be noted.
This is to be correlated with the loading and unloading temperatures
to ascertain whether it is due to temperature difference. The
difference in dip reading is to be within logical limit. If the variation is
consistently on the negative side, the matter is to be taken-up with
respective source with complete facts and figures to try to ascertain
the reason & the issue to be highlighted. This data is to be analyzed
source wise. The data to be randomly cross-verified for correctness.
Each unloading location must maintain two dip rods separately for
BTPG and TG of standard specifications and company e.g. Midland
USA, or ARIECKAL Industries, Panvel, Mumbai etc. In case of wagons,
where dip rods are not functioning, the average of remaining
wagons to be taken for reference. However, the actual stock
accounting would be made through Servo gauges taking LEV into
account. Railways to be intimated about these defects along with
all loading locations.
LPG OPERATIONS MANUAL
7.5.5.1 Based on the observed liquid level, liquid volume can be determined
through the relevant tank wagon calibration chart.
7.5.5.3 In the event of weighbridge(s) available in the rail system, the weight
should be determined by weighing the tank wagons before and after
unloading operation. The difference would give the quantity of LPG
unloaded from the tank wagons.
7.5.5.4 Compare the quantity worked out as above with the shipped quantity.
Investigate for abnormal variation, if any.
7.5.6.1 Ascertain that the liquid discharge valve and the vapour valve within the
tank wagon cover are in the closed position.
7.5.6.2 Open the port covers in the side of the dome shell, if exists. Unscrew the
plugs in the outlets of the vapour valve and the liquid valves using a box
wrench. This must be done slowly.
7.5.6.5 With the plugs removed, screw pipe nipples into the outlets of the valves
after first having applied a modest quantity of sealant to the male
threads, keeping the sealant away from the end of the thread. Tighten
nipples with a pipe wrench.
LPG OPERATIONS MANUAL
7.5.6.6 Connect the two liquid transfer unloading swing arms or hoses to the
nipples attached to the liquid discharge valves. Connect the vapour or
equalizing swing arm or hose to the nipple attached to the vapour valve.
In most of the cases, these connections will be made by means of either
a ground joint union or a hose coupling.
7.5.6.7 In the event, a ground joint union is used, no gasket will be required. If a
hose coupling is employed, ensure that the appropriate gasket is in
place. Make sure that they are secured tightly by appropriate means.
7.5.6.8 Recheck the lines and connections to make sure they are properly
connected.
7.5.6.9 After the vapour and liquid hoses have been connected and before any
valve is opened, the valves on the tank wagon are slightly opened in
order to apply pressure to the hoses / arms as a test for any leak.
7.5.6.10 If any leak appears, the valve should be immediately closed and
corrective measures be taken.
7.5.6.11 After the liquid and vapour lines are secured and tested, both liquid
eduction valves should be opened slowly and completely. Then, open all
other valves in the liquid line from the tank wagon to the storage tank.
7.5.6.12 Open the storage tank filling valve slowly and take extra care not to open
this valve too far if the tank wagon pressure is in excess of the storage
tank pressure. Otherwise the tank wagon excess flow check valve may
get closed.
7.5.6.13 If the tank wagon pressure is higher than that in the storage tank, do not
open the valves of vapour line or operate the compressor. When the rate
of liquid flow drops to an unsatisfactory level, open the vapour valves
between the tank wagon and the storage tank.
7.5.6.14 At this point, make sure that the control valves of the compressor are in a
position that allows the compressor to draw vapour from the storage tank
and force it into the tank wagon. If so, start the compressor.
7.5.6.15 For proper unloading, the tank wagon pressure should be maintained
between 2.0 to 2.5 Kg/sq. cm. above the storage tank pressure. If the
LPG OPERATIONS MANUAL
differential pressure is too low, the flow of LPG liquid will be slow and may
stop and if it is more, the excess flow valves of the headers and wagon
may get closed.
7.5.6.16 Flow of gas instead of liquid through the sight-flow glass in the unloading
line indicates that the wagon is empty of liquid. Recheck this by opening
the sample valve in the tank wagon dome.
7.5.6.17 When the tank wagon is emptied of all liquid, stop the compressor and
close the liquid valves beginning at the storage tank and progressing to
the tank wagon.
7.5.6.18 To remove concentrated vapour from the tank wagon, the valves in the
manifolds should be manipulated suitably to reverse the flow so that the
compressor will draw the vapour from the tank wagon, and force it into
the storage vessel. The sequence of piping line-up during unloading liquid
LPG and vapour LPG is shown in Drawing No. 18
7.5.6.19 Restart the compressor and continue to draw vapour from the tank
wagon till pressure inside the wagon reduces to about 1.5 Kg/cm2. Once
the pressure reaches about 1.5 Kg / cm2, stop the compressor and close
all the valves in the vapour line.
7.5.6.20 After bleeding off the pressure in the hoses through cold flaring line,
disconnect both the liquid and vapour lines. Replace all the plugs in the
tank wagon valves and the unloading fittings.
7.5.6.21 Recheck sample valve and gauging device to determine that they are
returned to their original condition and are closed tightly. Lower the
dome cover carefully and lock it in place with the locking pin or secure
by appropriate means.
7.5.6.25 Any defect observed in the tank wagon should be recorded in the
appropriate forms and routed in accordance with acceptable
procedures.
7.5.6.26 Notify the Railways in writing about the release of wagon and ensure that
it is removed from the siding promptly. Gauge the storage tanks, within
the plant, which have received the LPG to determine that the liquid level
is appropriate.
7.5.6.27 In the event of LPG received on weight basis, the tank wagon may
require weighing after the completion of the unloading operation.
7.5.7.1 The tank wagon can also be unloaded with the help of liquid pump, but it
is impossible to remove residual vapour from the tank wagon if this system
of unloading is followed. The compressor is a more desirable means of
unloading. The basic procedure for unloading through pump is the same
as that of unloading using a compressor except that the liquid line from
the tank wagon is connected to the pump suction and the pump
delivery is connected to inlet line of the storage vessel. However, there is
practical difficulty of using pumps at lower levels of LPG as vapour shall
enter the pumps when any of the wagon becomes empty which causes
pumping to stop due to vapour lock
7.5.7.2 In case of LPG tank wagons, the liquid inlet is at the top of the tank with
eduction pipes extending to the bottom so that the effect of the
‘flooded suction’ does not normally occur initially. The liquid from the
tank wagon, which enters the eduction pipe at the bottom of the tank
wagon, rises in the pipe and passes through the pipeline or hose on the
unloading point and drops to the pump suction. This flow pattern is an
effective siphon so long as the pressure differential remains appropriate
and vapour does not enter or form within the eduction pipe or the line
to the pump suction.
(a) The ullage should be calculated based on the gauge reading of the
vessels, before taking the tank trucks for unloading. On the basis of
available ullage, vessel should be identified for receiving the
product.
(b) Only the required number of tank trucks for unloading should be
allowed inside the plant based on the ullage. The TTs to be checked
for the shipment advice and also details in challan before
permitting inside for unloading.
7.6.1.2 Inspection
(b) All the required equipment, tools and tackles should be inspected to
determine that they are in good working condition and kept ready
for use.
(a) Before allowing the entry of tank truck inside the licensed area for
unloading, the following checks are required to be made :
(I) TT is carrying a challan for the plant, where it has reported for
unloading.
(II) Time taken between dispatch from loading location and
reporting at receiving location is normal. In case of abnormal
delay, matter shall be investigated for finding the reasons.
(III) Seals on the TT carry the same no. as mentioned in the challan
and are intact.
LPG OPERATIONS MANUAL
(b) The truck should be weighed on the Weigh Bridge and the
reading(Gross Wt.) should be recorded on the challan or any
relevant document and Drivers’ signature to be obtained on
weighment slip. Recorded Gross Wt. should be tallied with the Gross
Wt. mentioned on the loading invoice. In case of abnormal
variation , matter should be brought to be the knowledge of Plant
Manager and Transporter before start of decantation of such TT.
(c) No repairs shall be carried out on the truck while it is in the unloading
/ loading area. The crew should remain present throughout the
operation.
(g) Ignition keys of the Tank truck shall be handed over to the
competent person supervising unloading operations. The vehicle’s
hand brake system should be applied and chock-blocks fixed at the
front and rear wheels and vehicle kept in neutral mode.
(h) The fire extinguishers should be kept ready near the tank truck for
use in case of emergency.
(j) Before caps / plugs / blind flanges are removed from either liquid or
vapour connections on the tank truck, manually controlled valves
should be checked to determine that they are closed.
(l) Check the roto gauge , pressure gauge and temperature gauge
and record the readings .
(m) Liquid line and vapour line of the tank truck should be connected to
the respective hoses / unloading arms fixed to the unloading point,
taking due care for the correct connections. All flange connections
are to be made using only SS spiral wound metallic gaskets and
eight nos. properly sized studs. Bonding across the TT flange and
loading coupler/hoses to be ensured.
LPG OPERATIONS MANUAL
(n) After the vapour and liquid hoses / arms have been connected, the
first valves on the TLD manifold should be crack opened to check
for any leakage. If any leak appears, the valve should be
immediately closed and corrective measures should be taken.
(r) Care should be taken to see that the pressure, within the delivery
vessel does not reach or exceed the set pressure of the relief valve.
(s) In order to ascertain that the liquid contents of the tank truck are
fully discharged, the roto- gauge can be placed at ‘zero’ reading
and the bleeder valve opened. The vapour discharge in this
position is indicative of the complete discharge of the liquid.
Alternatively, it can also be checked from sight flow indicator at
unloading bay. Record the observation on the challan or relevant
document. When the transfer of the liquid is completed, the
compressor or pump should be shut-off, followed by immediately
closure of all liquid and vapour valves progressing from the tank
truck to receiving storage vessel.
(u) When the tank truck pressure is reduced to 1.5 to 2.0 kg/cm2 , stop
the compressor and close all the valves. Under no circumstances
LPG OPERATIONS MANUAL
(w) Before disconnecting the hoses / unloading arms, the valves of the
tank truck should be checked for closure and the valves at the
receiving risers should likewise be re-checked.
(x) As soon as it has been determined that the shut-off valves at each
end of the hoses / arms are closed and the trapped LPG in the
hoses / unloading arms is vented out, the hoses / arms are to be
disconnected and placed at designated place.
(y) Caps and plugs must then be immediately fitted to the valves /
fittings on the tank truck and on free end of the hoses/arms.
(z) Before starting the tank truck engine for the removal from the bay,
the tank truck should be inspected by the competent person
supervising of the operation to check that the hoses / arms have
been disconnected, tank truck valves closed and plugged, bonding
cable wires disconnected and there is no concentration of vapour
around the vehicle.
(aa) With this operation completed, the choke blocks are removed and
the vehicle engine may be started for moving out the tank truck.
The empty tank truck should be weighed(Tare Wt.) and the reading
should be recorded on the challan or in the relevant document and
the net weight(Gross Wt.- Tare Wt.) should be calculated from this.
(b) Fuel tank is protected by means of stout guard and fuel tank cap is
locked.
e) Valid yearly certificate for SRV along with purging certificate and
Half Yearly Certificate for visual examination are available.
k) Excess flow check valves are functioning. (The Excess flow checks
valves of tank trucks on liquid as well as on vapour service must be
checked by suddenly opening of the liquid / vapour valve after
connecting the hoses to the tank truck. EFCVs will close with ‘tick’
sound and on closing the tank truck’s Liquid / vapour valve
suddenly the EFCV will open and ‘tick’ sound will again be heard.
LPG OPERATIONS MANUAL
n) Liquid / vapour pipe lines are in single piece from excess flow
check valve to the discharge valves.
Note: Whenever a truck is taken for the first time for unloading in the
plant, the trucks should be subjected to all the checks mentioned at
Clauses Nos.7.6.2.1(a), 7.6.2.2 and 7.6.2.3. After full satisfaction that the
tank truck is complying with all the above points, then only loading
advice should be issued.
7.6.3.1 The contents of the tank truck should be verified by actual weighment.
The tank truck should be weighed prior to the unloading operation and
again after the completion of the unloading operation. The difference
represents the quantity unloaded. Proper records of the same should be
maintained. The quantity decanted shall be tallied with challan quantity
and incase of shortage beyond permissible limit, action as per transport
contract shall be taken.
7.6.4 UNLOADING THE TANK TRUCK USING PTO (Power Take-off) UNIT
7.6.4.1 This type of system is under use in Rural Marketing Vehicle (RMV) and in
Emergency Rescue Vehicle provided in some of the plants and in the
Auto LPG Bulk delivery vehicle (Bob Tail).
LPG OPERATIONS MANUAL
7.6.4.2 Some tank trucks may be equipped with pumps or compressors that may
be utilised to discharge / recover the contents of the tank trucks. This type
of arrangement may facilitate delivery of the product to the locations
(e.g. Industrial Customer, LPG retail outlet), which are not equipped with
the product transfer equipment.
7.6.4.3 Similar safety and operational precautions mentioned for unloading and
loading of tank trucks must be ensured in this operation also. Hence,
specific details are not being mentioned here. This may be read in
conjunction with unloading of tank trucks mentioned in Clauses Nos.7.6.2,
7.6.3 & 7.6.4.
7.6.4.4 The pump or compressor and tank truck engine should not be operated,
when the vapour is released in the vicinity of the tank truck. When the
tank truck is moved into position for unloading, the engine must be shut-
off and not re-activated until complete unloading operation takes place.
7.6.4.6 When the tank truck is empty, the pump or compressor should be
disengaged before the hoses are disconnected.
7.6.4.7 After the hoses are disconnected, time should be allowed for the
dissipation of the product, which may have escaped, before the
engine is re-started.
7.6.5.1 The tank truck can be unloaded with the help of liquid pump, but it is
impossible to remove residual vapour from the tank truck if this system of
unloading is followed. Whether the pump performing the unloading
operation is permanently installed within the plant or is a part of the tank
truck unit, the generalized procedures described below should be
followed :
LPG OPERATIONS MANUAL
(a) Connect suction-side of the pump to tank truck liquid line and
delivery side of the pump to the liquid inlet line of the receiving
vessel.
(b) If pressure in the tank truck bullet is lower than the pressure in the
receiving storage vessel, equalise through the vapour connection .
If the tank truck pressure is higher than the pressure in the receiving
storage vessel equalise with the liquid stream.
(e) Check through the tank truck roto gauge (by setting it to 0%
reading ) to ensure that the tank truck is empty.
(f) If the tank truck is not empty, determine cause for loss of suction on
unloading pump. Determine that excessive container pressure
does not exist. Allow sufficient time for ‘excess-flow-check--valve’
equalization, if the closure occurs. Determine that the bypass line is
operating as intended. If the suction can be re-established, open
the valves and continue unloading. If the tank truck cannot be
emptied, discontinue pumping, close the valves and investigate
causes for taking corrective measures. However, at lower liquid
levels in the tank trucks, some TTs can become empty before other
trucks and vapour may enter the pump causing “vapour lock”
thereby stopping the pumping
(g) LPG compressor is required for recovery of vapour from the tank
truck. In view of the inherent disadvantage of tank truck unloading
by pump, when compared to unloading by compressor, the above
method should not generally be followed , unless specific
circumstances necessitate it.
7.6.6.1 Whether the compressor is installed as part of the storage plant facilities
or is installed on the tank truck, the following generalised procedure
could be followed :
-
LPG OPERATIONS MANUAL
a. Connect the suction side of the compressor to the vapour outlet of the
receiving vessel and the delivery side of the compressor to the
vapour line of the tank truck. Connect the liquid inlet line of receiving
vessel to the liquid line of the tank truck.
c. Start the compressor. The vapour will be sucked from the receiving
vessel and will be discharged into the vapour space of the tank truck
bullet creating a differential pressure, thereby pushing the liquid from
the tank truck to the receiving vessel.
d. Care must be exercised to see that the pressure created within the
tank truck does not approach or exceed the set pressure of relief
valve.
e. After all the liquid LPG has been decanted from the tank truck
bullet, the vapour remaining in the bullet may be recovered by
connecting the suction of the compressor to the vapour
connection of the tank truck bullet [the vapour valve is provided at
the bottom side of the bullet and the connecting pipe extends inside
the bullet up to the vapour space at the top) and discharge of the
compressor may be connected to the vapour inlet of receiving
storage vessel.
f. When the tank truck bullet pressure has been reduced to 1.5 to 2.0
kg/cm2, stop the compressor and close all valves.
h. After ensuring that the shut-off valves are closed tightly and the
trapped LPG in hoses is vented out, disconnect the liquid and vapor
hoses/arms
LPG OPERATIONS MANUAL
7.7.2 With the scope of loading procedures, two types of basic vehicles are
considered viz., tank wagon and tank truck. In each case, the vessel
being filled is capable of movement with the result the hose
connections used for transfer can be snapped if the vehicle moves
accidentally. It is, therefore, absolutely essential that during a transfer
operation these vehicles remain fixed.
7.7.3 The same basic safety requirements enumerated in Clause No. 7.4 and
Clauses Nos.7.4.5, 7.4.6, 7.4.7 and 7.4.8 should be observed, whenever
loading operations are undertaken .
7.8.1.1 Within the loading area there must not be any source of ignition (e.g.
smoking, naked flames, match box, cigarette lighter etc.).
7.8.1.2 At the sign of any leak the operation must be stopped immediately. Leaks
must be repaired promptly. If the leakage cannot be stopped, the
matter should be reported immediately to the Plant Manager for taking
corrective action / precautionary measures.
7.8.1.3 Before the start of loading operation, the tank wagons shall be visually
examined for the following :
(c) The surface is free from rust and deep pitting and the paint on the
barrel are not peeled off .
(d) It must be ensured that the liquid and vapour eduction valves,
sampling valve and magnetic gauging device are complete in all
respects and are in perfect working order and that there is no
evidence of leakage.
(f) When defective Wagons (Dip tube well, EFCV, leakages, etc), are
identified during loading operations or with prior intimation from
unloading locations, the details of all such wagons to be forwarded
to Railways with a request for joint inspection. Such wagons to be
loaded after clearance from Railways.
7.8.1.4 The tank wagons to be loaded shall not be located under or near any
electrical wire and wagons shall be suitably earthed before
commencement of loading.
7.8.1.5 Tank wagons found to be in any way defective shall not be loaded until
repairs are carried out by the Railways. Repairs involving hazards, should
not be allowed to be carried out in the plant premises.
7.8.1.6 Caution signs must be exhibited at a suitable distance away from tank
wagons on the approach end or both ends as applicable.
7.8.1.7 Jumping from the loading gantry to tank wagon or from one tank wagon
to other is extremely un-safe and should be prohibited. Rough handling
of tank wagons, whether loaded or empty within the plant should not
be permitted.
7.8.1.8 During placement on the siding, tank wagons should be aligned as close
as possible to the specific point for most convenient loading whether it
may be on an elevated loading gantry or ground-level loading
connection.
LPG OPERATIONS MANUAL
7.8.1.9 The use of open lights is prohibited. If the torches are required to be used,
they must be of flameproof type
7.8.1.11 Loading shall be done through the liquid eduction valve, which has pipe
leading to the bottom of the tank. The vapour eduction valve is
connected to the storage system of LPG plant. Good operating condition
of these valves should be ensured before commencement of loading
operation.
7.8.1.14 Tank wagons should be inspected thoroughly for the leaks before
issuing release memo.
7.8.1.15 Raise and secure gantry platforms (swing type) after completing the final
inspection wherever over-head gantry is provided .
7.8.1.16 Loaded tank wagons should be sealed and properly labeled giving
despatch particulars.
7.8.1.17 New tank wagon bullet or the bullets received after repairs / pneumatic
test must be purged before loading duly following purging procedures
(Annexure 10).
7.8.1.18 The Tare weight of the new tank wagon must be verified on a
weigh bridge and got corrected through local Railways, in case of any
variance with the marked tare weight.
c. Tank wagon brakes should be set and caution sign boards are
i. to be placed at the tank wagon gantry.
(d) Liquid outlet line from the supplying vessel is to be connected to the
liquid line of tank wagon. It should be ensured that the vpour line of
tank wagon bullet is connected to vapour inlet line of the supplying
vessel (i.e. vapour return line or equalizing line).
(f) If a compressor is used, vapours from any other storage vessel in the
plant would be drawn and discharged into the supplying vessel.
In this case vapours from the tank wagon must be returned to the
storage system and in no case should be vented freely to the
atmosphere. The compressors may be started at this point.
(i) After the last tank wagon is loaded, shut down the loading
pump (or compressor).
(j) Check final readings (liquid level) and then lower magnetic level
gauge to lock the position and secure
(k) Disconnect the loading hoses and plug or cap all connections
taking all possible measures to minimise venting of vapour to
atmosphere.
(l) Make sure that all valves in tank wagon bullet and unloading points
are shut tightly and all plugs are in place and gauging device is
locked. Inspect for leakage. Before shutting off the valve, it must be
ensured that thermal expansion arrangement by way of pop action
valve is provided and is operative on the section of pipelines
blocked with valves at both ends.
(n) Remove the bonding cable. Note that the bonding cable is fixed
before the operation starts and is disconnected after all the
operations on the tank wagon are over
(p) Do not remove caution signs on the siding until all the tank wagons
on the siding are loaded, disconnected and ready for release
operation also. The following shall also be ensured before taking the truck
for loading :
a. The tank truck has a valid License and drawing duly approved by the
Chief Controller of Explosives. Apparent condition of the tank truck
before undertaking the loading operation should also be checked.
If there is any deviation, regarding the condition of the tank truck or its
safety fittings, the truck should not be taken for loading.
b. After truck has been moved to loading position, the engine must be
stopped and ignition and lights are switched off. Battery Cut-off switch
must be in “off” condition.
c. Crew must leave the truck cabin and handover the ignition keys to the
competent person supervising the operation. Crew should not re-enter
the cabin unless authorized by the competent person.
f. Only couplings suitable for LPG service shall be used for attaching
loading lines to the truck.
h. When hoses/arms are not actually attached to the unit being loaded,
they should be properly secured to the hooks provided for the
purpose to prevent accidental run-over by a vehicle.
i. Trucks or other vehicles shall not be driven in the loading area when
there is heavy concentration of vapour in the atmosphere.
Explosimeter check should be made in such cases.
j. New tank truck or those received after repairs/ pneumatic test, must
be purged before loading, duly following purging procedures.
(Annexure 10).
LPG OPERATIONS MANUAL
(I) With the help of ‘Roto Gauge’ : Filling through Roto gauge is
the basic method of Filling wherein exact quantity
determination (by weight) is not possible during the process of
filling. The maximum Roto gauge reading up to which TT can
be filled is different for different TTs. When tank truck is to be
filled using a ‘roto gauge’, percentage volume to be filled
should not be straight away set for the filling level determined,
but should be set around 50% level initially and thereafter 10%
higher i.e. 60%, 70% and 80% till final level is reached.. When
the level of LPG filled by volume reaches 5% below the pre-
determined level very close supervision is to be maintained to
ensure that no over filling takes place. Filling through this system
requires more control and close supervision as this system does
not have automatic control over the quantity to be filled. This
system also has the drawback that the TT filled may require
frequent corrections for under/over filling by weight.
(I) With the help of Weigh Bridge: In this system, every bay is
provided with a weighing bridge. Weight of LPG loaded is
available at any point of time during the loading. This ensures
accurate filling as far as net weight is concerned.
(II) With the use of Mass Flow Meter(MFM): Mass Flow Meter
directly measures the weight of the product flowing through it.
It measures the weight with greater accuracy with the help of
“Corriolis Principle”. Since MFMs can work accurately when a
single phase flow is maintained , it is recommended to provide
“Vapor Eliminator” before MFM. Loading through MFM is
possible by manually punching the quantity to be loaded
locally or through automated loading system with batch
controller and other facilities. This remote loading facility is
installed at places where no. of TTs loaded is quite high. In an
automated loading system, following features are available:
Flow rate etc. The system also shows the loading pump
being used, and status of ROVs etc.
h. Earthing to TT is controlled by means of earthing relay, which
does not allow loading to take place if it is not connected
and alarm is generated in control room.
This system provides a better control over the loading process and
requires minimal corrections.
While all the above methods are different and uses different equipment
to keep a control on the LPG to be loaded in the tanker, final invoice is
prepared on the basis on net weight loaded in the tanker, which is
determined by weighing the tanker before and after loading. All the
measuring equipment including the weigh bridge shall be regularly
calibrated and verified by local legal metrology department. Irrespective
of any method used for loading, following steps should be necessarily
followed while loading of tanker.
(b) After accepting the TT for loading, record tare weight of the TT after
proper placement of TT on the weigh bridge platform. The
positioning of the TT should be within the box painted on the weigh
bridge since positioning of TT at the edges increases probability of
error in weighment.
(d) Position the vehicle in the loading area in the designated painted
box to facilitate proper connection of loading arms.
LPG OPERATIONS MANUAL
(e) Apply Hand brakes of the TT. Switch off the TT and apply Master cut
off Switch. The tank truck engine, lights, radio and all other electrical
equipments must also be switched off.
(f) Remove Fire extinguishers from the TT and position one on the front
and other on the rear side of TT.
(h) Connect Earthing / Bonding cable on two points (one on tank shell
and other on chassis)
(i) Ignition keys shall be handed over to the person supervising the
loading operations for safe keeping in the box designated for this
purpose.
(l) As the filling operation progresses, the pressure within the tank truck
should be observed to ensure that it does not approach the ‘Start-
to-discharge pressure’ of pressure relief valve. The pressure relief
valve should not get actuated as a result of the filling operation.
(m) In case the tank truck pressure becomes excessive, the loading
operation should be stopped. Causes for excessive pressure build up
should then be investigated. Check the equalizing line, which may
have been blocked as a result of the closure of an ‘excess flow
check valve’ (on the tank truck vapour line). If this be the case,
valve on the vapour line of the tank truck must be closed to allow
the equalization of pressure across the excess flow check valve.
When re-establishing the transfer operation, care should be
LPG OPERATIONS MANUAL
(o) As soon as the maximum filling level is reached, the valves on the
tank truck should be closed. Also, the valves on the loading point of
the bay closed. With the valves attached to hose ends closed, the
couplings on the liquid and vapour connections should be loosened
slightly, to gain assurance that the tank shut- off valves are tightly
closed. In case of automated systems, the cut off is automatic
through digital control valve (DCV) which in turn is controlled by two
nos. of solenoid valves and the control system.
(p) After tightness tests as above have been completed, the couplings
may be removed and the plugs and caps immediately replaced on
the tank truck bullet valves. Recheck tightness for any leakages.
(q) Using roto gauge, check reading on both (left and right) sides to
determine that the identical readings are obtained. In case the
readings are not identical, the mean value should be recorded.
However, it must be ensured that any of the readings does not
individually exceed the maximum safe filling volume.
(t) Remove the chock blocks and authorize the driver to remove the
vehicle from the loading area to weigh bridge.
LPG OPERATIONS MANUAL
(u) Tanker should be weighed (gross wt.) and it shall be ensured that it
has not exceeded the Registered Laden weight of the vehicle. New
weight(Gross Wt. – Tare Wt) shall be calculated and cross checked
against the licensed capacity of the vessel. In no case, net weight
shall be more than the licensed capacity.
After all the tank trucks are loaded, the pump should be stopped and all
valves should be close.
7.10.1.2 The techniques and procedures, which may be necessary for the transfer
of LPG may vary widely since in one case the transfer line may be
extremely short merely passing through the fence from Refinery to the
bulk storage plant located immediately adjacent to the Refineries. In
some cases, the line may transverse many kilometers between Refineries
and Marketing plants conveniently located for the distribution purpose.
7.10.1.5 Dispatching location shall got all the requisite test done before supply of
the product. LPG passing all laboratory test shall only be pumped. Test
certificates of all batches shall be sent to receiving location at regular
intervals.
7.10.2.1 In order to ensure that there is sufficient capacity within the plant to
receive the pipeline shipment, receiving storage vessels should be
gauged by positive methods to ensure that sufficient capacity is
available for receiving the parcel and that maximum safe level should
not be exceeded.
7.10.2.3 In most of the cases, the rate of transfer into the plant will be known and
the volume to be received will be pre-determined. Hence, a schedule
can be developed covering the entire transfer operation. Manifold
manipulation can be pre-determined to ensure that the storage
vessels, which are being filled, are monitored at appropriate intervals
and switching over from one storage vessel to another can be made
without any difficulty.
7.10.2.5 Ensure that no other activity except vapor balancing is being carried out
or planned from the same vessel during the receipt operation and
constant monitoring of gauges / reading is carried out by the competent
person.
7.10.2.8 The quantity being received should be matched with the dispatching
location at a regular intervals of time. In case of any major deviation is
observed, dispatching point / location should be immediately informed
to stop the operation till corrective action is taken.
7.10.3.2 Due to the nature of a pipeline transfer, even though regulating means
are provided to ensure that the excessive pressures are not induced by
the incoming product, it is essential that the receiving storage vessels
are observed periodically to ensure that the pressures do not develop
which approach the ‘Start-to-discharge’ pressure setting of the pressure
relief valves of the receiving vessels.
LPG OPERATIONS MANUAL
7.10.4.1 At the completion of the transfer operation, the incoming control valves
should be closed. Charts, meter readings and other information that
may have been developed during the process should be noted or
secured. Inspection of the storage vessels where the product has been
received should be immediately completed. This should include
gauging of the contents, recording pressure, observing the product
temperature and making volumetric calculations to ensure that all the
vessels, which have been filled, are at appropriate level in relation to
maximum permissible level. Since, the working pressure during pipeline
transfer is generally higher than in case of decantation through TTs / TWs,
adequate time should be allowed for water draining and gauging of the
tank level.
7.11.1 COMMUNICATION
(a) The names and roles of terminal and ship personnel who will be
responsible for cargo transfer operation may be noted.
(c) Similarly, the officers of the tankers shall satisfy themselves that the
relevant Terminal equipment and inspection checks are carried out
satisfactorily.
7.11.3.1 The basic safety precautions mentioned in Clause No. 7.2 should be
followed fully for the transfer of LPG from tanker to vessels.
7.11.3.2 Before the arrival of the ship, the port clearance should be obtained and
other statutory formalities like customs should be completed.
7.11.3.3 On berthing of the ship and getting clearance from the customs, the
boarding officer should board the ship along with the surveyor for taking
joint ullage of the tanker and tallying with the quantity on board. In case
of shortage, protest is to be lodged with the Master of the ship.
7.11.3.4 Terminal tank levels are gauged and the quantity of the product arrived
at are recorded jointly with the independent surveyors.
LPG OPERATIONS MANUAL
7.11.3.5 Jetty lines cooling shall be done before transferring the product. During
line cooling and subsequent tanker discharge, communication with Jetty
control room and the boarding officer is maintained respectively.
7.11.3.7 The marine unloading arms are connected to the tanker manifold.
7.11.3.8 Samples are taken from the ship tanks and sent to the lab. for analysis
before commencement of discharge.
7.11.3.10 The pumping rate and the number of pumps to be operated at any time
at the tanker end shall be controlled, based on the feed back from the
terminal on the pressures in the refrigerated tanks.
7.11.3.13 Logging of all the events should be done in a log book and all
parameters should be recorded on hourly basis.
7.11.3.14 On completion of discharge the ship tanks should be gauged and the
quantity of product discharged should be arrived.
Trim correction - to make allowance for the liquid level indicating devices
not centrally located.
7.12.2 All relevant safety precautions listed in Clause No. 7.2 should be
followed. Particular care must be exercised to ensure that the pressure
in the receiving vessel does not exceed the safe limits and that the
liquid level in the receiving vessel after completion of the transfer is not
above safe maximum level.
7.13.1 It is not uncommon to find the presence of water in LPG vessels. The
water, in free form, being heavier than LPG will always settle at the
bottom of the vessels.
LPG OPERATIONS MANUAL
The presence of water in LPG tank truck can be detected by rotating the
roto-gauge to 0% reading & subsequently opening the bleed valve on
the on the roto-gauge before opening the unloading valve of the TT. If
water comes, the roto-gauge should be slowly rotated to higher reading
keeping the bleeder valve open till LPG start to come. At first sign of LPG,
the bleeder valve should be closed. The % water content should be
noted and recorded to take up further with the transporter/ Supply
location. Driver’s signature should be obtained on the declaration of
water quantity detected through the above process. However, as a
safety measure no attempt should be made to drain water from the
tank truck within the plant, but the same should be transferred to the
storage vessel along with liquid LPG.
As a routine, check for the presence of water in the storage vessel should
be made daily morning by opening the drain valve. However, if there
is no fresh receipt of the parcel into the vessel after the last draining,
subsequent checking and draining should be avoided till fresh receipt
of the parcel. This is done to minimise hazards that are associated with
water draining operation.
LPG OPERATIONS MANUAL
7.13.3.1 While draining water from the storage vessels, it must be ensured that
two valves are provided on the drain connection with a suitable distance
between them and an EFCV after the 1st valve (upstream valve).
7.13.3.3 The lock on the 1st valve nearer the vessel should be opened. The first
valve ( nearer to the vessel ) should be opened first and then closed.
After closing the first valve fully, the second valve (nearer to the drain
point) should be opened after opening the end blind flange. The
contents collected between the valve shall be drained and the second
valve shall be closed. The procedure shall be repeated in cycles till the
water is completely drained.
7.13.3.4 It should be ensured that the drain outlet is at a safe distance from the
vessel so that accidental ignition of any escaping vapour will not expose
the vessel to flame impingement.
7.13.3.7 When not in use, both the drain valves should be kept in locked condition
and end of the pipe should be blinded or plugged.
7.13.3.8 Draining operation should be performed during the daylight hours only.
Draining shall be not be carried out in the event of lightening/thunder
storm.
7.13.3.9 Brief instructions for draining operation along with schematic diagram
should be displayed on a board near the storage area. The instructions
should be written in vernacular in addition to Hindi and English.
7.13.3.10 The records of water draining and quantity of water drained must be
entered in the gauge book.
7.14 ODOURISATION
7.14.1 LPG is an odourless gas, heavier than air. Any leakage developed from a
source of LPG can go undetected, thereby creating a grave safety
hazard. Therefore, if LPG is to be distributed as a utility gas to the
consumers, it shall be odourised by addition of a warning agent of such
characteristics that it is detectable by a distinct odour down to a
concentration in air of not over one fifth of the lower limit of flammability.
7.14.2 Ethyl mercaptan is commonly used as the odorant for LPG because of its
distinctive smell. The assessment of odour level and the amount of ethyl
mercaptan to be dosed are determined as per the guidelines given in
IS :1448 - 1968 (P : 75). Dosing of ethyl mercaptan to LPG to be carried out
at production source or import terminal before further dispatch. Normally
around 20 ppm of ethyl mercaptan is added
7.14.4 Vapour pressure of ethyl mercaptan increases rather rapidly with the
temperature. It is, therefore, recommended that the drums containing
ethyl mercaptan be kept cool and away from direct exposure to
heat/sunlight before they are opened.
LPG OPERATIONS MANUAL
7.14.5 An useful device for transfer of ethyl mercaptan from a drum consists of a
dip pipe assembly equipped with tight bung or fittings. The dip pipe
should reach the bottom of the drum, if the drum is not kept tilted. An
inert gas is used to apply pressure inside the drum to force out mercaptan
through the dip pipe. The system shall have a suitable relief valve to avoid
accidental rupture of the drum due to high pressure built up. Alternately,
a suitable pump may be used for transferring ethyl mercaptan from a
drum into a dosing vessel.
7.14.6 Because of the odour of mecaptan, only hermetically sealed pumps shall
be used.
(I) Valid Storage license of Bulk LPG from CCOE and endorsement of
the same from the local concerned CCOE office.
(II) Permission for commissioning of new plant from Director(Marketing)
routed through concerned Regional Office and State Office.
(III) Availability of original test certificates from the third party inspection
agencies regarding radiography / stress relieving / hydrotesting etc
pertaining to storage vessels.
(IV) Availability of approved procedures containing the names of
officers and staff against each and every activity throughout the
period of commissioning by the Competent Authority / State LPG
Head.
c. Equipment checks.
d. (Tightness test.
e. Removal of air.
LPG OPERATIONS MANUAL
7.15.2 CHECKLIST
(a) (a) Inspect the vessel to check that all foreign matters are
removed and that the interior of the vessel is cleaned.
(b) Check that all fittings, valves, ROVs including pressure relief valves,
duly tested, are installed.
(c) The drain line is provided with two valves with EFCV in between.
(d) Check that all the valves are working by opening and closing
them. Also check all the instruments / fittings on the vessels for
proper functioning.
(h) (Ensure that all the electrical installations / equipment are of flame
proof. No loose wire connection is in this area.
(i) (Risk analysis and Hazop study are conducted and the
recommendations are implemented. Check for Fire proofing
recommendations).
(m) Fire fighting equipment is deployed as per the OISD 144 norms.
a. Close all the valves on all lines connected with the vessel.
c. Close the isolating valve provided below each of the ‘Pressure Relief
Valves”.
d. Vent the air from the nozzles available on the top of the vessel and
subsequently from the vapour line valve at ground level.
e. Open all the valves on the line connecting the hydrant to the
liquid inlet of the storage tank.
f. Start filling water from fire hydrant line by opening the hydrant
valve and gradually bring this valve to full open position.
h. Keep a constant check on the water level in the vessel. When the
water starts overflowing through the bleeder valve of ‘fixed-tube-
level-gauge’ provided on the vessel top, displacer of the “SerVo
Gauge” should be brought to the top position and valve beneath it
shall be closed to avoid ingress of water in the gauge. Subsequently,
when water start coming through the vapour valve at the ground
level, shut-off the water flow to the vessel. After a time interval of
about 5/10 minutes, again pump water and allow to overflow.
Continue this process for few more minutes till the air pockets are
removed.
i. Close the vapour valve at the ground level and bleeder valve on
the ‘fixed-liquid-level -gauge’.
(b) Connect the vapour inlet of the vessel to the outlet of the LPG
compressor.
(c) Connect the vapour outlet of any LPG tank truck (or tank wagon
or nearby storage vessel) containing the LPG to the inlet of the
compressor.
(d) For new locations the vapour inlet of the vessel can be
connected directly to the vapour out let of the tank truck at TLD to
displace the water in the pipeline and in the vessel.
(e) Connect the drain valve of the vessel to any convenient line for
taking water from the vessel back to the drainage system of the
Plant through the sump.
(f) Ensure isolating valves for pressure relief valves on the receiving
vessel are open, secured with seals and locked in open position.
(g) Open valves on the vapour outlet of the tank truck (or tank
wagon or another Storage vessel) and vapour inlet of the
storage vessel and start the LPG compressor
(j) Continue draining of water till LPG vapour just starts coming out of
the water draining line. After the traces of vapour are observed
form the drain line, close the drain valve and carry out the
water draining as per the water draining procedure mentioned
in Clause No. 7.13.3
(k) Close the water outlet drain valve immediately. At this stage
there will be some quantity of water left at the bottom of the
vessel.
(l) Receive some more vapour for raising the pressure in the
storage vessel to about 2 kg/cm2
(n) The vessel is now not full of vapour but with small quantity of water
at the bottom.
a. Check the vessel for any leak and rectify before receiving liquid
LPG.
b. Start receiving liquid LPG in the vessel gradually increasing the level.
Depending upon the temperature, pressure of 3 to 9 kg/cm2 (g) will
be attained.
f. Ensure that safety relief valves / thermal safety valve / pop action
valves are provided on the pipeline sections which remain blocked
with valves at both ends.
LPG OPERATIONS MANUAL
(c) Liquid lines should be first filled with vapour, which should
thereafter be displaced with liquid LPG displacing the vapour
back into the vessel.
(b) Displacing the complete LPG vapour safely by over flowing the
vessel with water.
the period of shut down to ensure that all steps are carried out in the
correct sequence.
7.16.3 When an LPG storage vessel is opened, pyrophoric iron may be present in
the residues in the vessel. In the presence of the air, the pyrophoric iron
may get ignited if it becomes dry. Therefore, it must be kept wet until it is
removed and disposed off properly. If it catches fire inside the vessel,
considerable damage may occur to the steel shell of the vessel.
7.16.4 The procedures described below is for Horton Sphere. The shutdown
procedures for LPG storage bullet is the same in principle as for LPG
Horton Sphere.
(b) Pump away as much liquid LPG as possible. (The high volatility of
liquid LPG makes it difficult to pump out when the liquid level
becomes very low). It should be ensured that during emptying out,
positive pressure is maintained within the sphere until pumping out
operation of Liquid LPG is completed.
(c) The float (wherever provided) will be at the bottom of the vessel,
having come down with the reducing level of liquid.
(e) Start filling of sphere with water (using the bottom flooded
connection). As the sphere is getting filled, residual liquid LPG will
float on the rising level of water. (The float if provided will come
upwards with the increasing level of water). At the same time
LPG OPERATIONS MANUAL
vapour from the vessel will get displaced into the vessel connected
for the purpose.
(f) Continue to fill the sphere completely with water, but slow down the
rate of entry of water nearer the topping up level.
(g) It is important to slow down the rate of entry of water at this stage to
ensure that the flow rate does not exceed the capacity of the
connecting line to the adjacent sphere. If the capacity of this line
for displacing the liquid is exceeded, the liquid LPG (floating on the
water) will be compressed at the top of the sphere under the
pressure relief valve, possibly resulting into the valve being blown off
with the associated hazard of liquid LPG being leaking to
atmosphere.
(h) Continue the flow of water into the sphere until a sample taken of
from the top of the sphere (e.g. drain point of Pressure gauge) gives
only water. This will confirm that all the LPG vapour is displaced
through the vapor line into the adjacent sphere.
(j) Close the valve on the vapour line to the adjacent sphere.
(k) Disconnect all the pipelines attached to the vessel and blank off the
connections while these are full of water.
(l) Start draining of water after having opened the vent at the top of
the sphere with a view to allow the volume of water being drained
of. This prevents creation of vacuum in the sphere. As a precaution,
vacuum gauge should be temporarily fitted at the top of the
spheres for the operation.
(n) Remove the manhole cover to ventilate the sphere before man-
entry.
LPG OPERATIONS MANUAL
(o) Precautions should be taken to keep the interior of the sphere wet,
as pyrophoric iron may be present. These deposits, in the presence
of air, may ignite when they become dry.
(p) Man-entry for the work in the vessel should be allowed only after the
vessel has been checked and certified as ‘Gas Free’ by a
competent person and hot work permit is made for vessel entry.
(b) Details of LPG tank wagons and LPG tank trucks are covered in
Chapter No. 6. Details of operations / precautions within the plant
are covered in earlier sections in this Chapter. This section deals
broadly with the transportation aspects outside the plant premises.
(b) As per OISD guidelines not more than 600 MTs of LPG should be
unloaded / handled on a railway siding at the plant, at any given
time.
(c) Once the tank wagons are released from the plant and till such time
they are placed at the receiving end they are in the custody of
Railways and plant personnel have no direct role to play during
actual rail transportation.
LPG OPERATIONS MANUAL
7.17.3.1 General
(b) Tank trucks used for LPG transportation must have a valid
transportation license issued by CCOE and must also comply with
the license conditions. The vehicle must also comply with RTO rules
and regulations.
(d) Drivers for the tank trucks shall have their licensed endorsed for
carrying “Hazardous Goods” and shall be given training for safe
handling of the equipment and the compressed gas carried in the
vehicle before allowing them inside the plant for LPG transportation.
Tank Trucks carrying Auto LPG for unloading at Retail Outlets shall be
advised not to decant between hours of sunset and sunrise until and
unless permission for same is available from CCOE(PESO).
(a) No, fire, artificial light, or article capable of causing fire or explosion
shall be taken or carried on any vehicle. This would also mean that
NO SMOKING is allowed within or around the tank truck.
(d) In an emergency, the driver may seek the co-operation of the local
police authorities in finding a suitable parking place for the vehicle.
(e) Whenever road or weather conditions are such that there is any
doubt with regard to the safe completion of the trip, the vehicle
may be parked safely or alternate safer route may be followed.
(f) It should be ensured that all the valves fixed on to the bullet
(whether full or empty); controlling liquid and vapour are closed and
properly secured to prevent tampering.
(c) The vehicle should be parked off the street in uncongested areas at
least 50 feet away from any building.
(b) The tank truck should be parked minimum 15 metres away from the
buildings, storage - facilities and filling operations.
(d) One security guard should be positioned round the clock in TTPA for
supervision/control of movement of TTs.
(e) Nobody should be allowed to sleep in the TTPA except Drivers’ rest
room.
(g) The tank truck bullet’s liquid & vapour connections should be in
closed condition. In addition, liquid and vapour outlets should be
capped or plugged to provide a gas-tight seal and locked to
prevent tampering.
(a) Vehicles should not be parked or garaged in any building unless the
building is specifically approved for such use.
(a) Repair work shall not be performed on the bullet or primary shut-off
valves while the vehicle is in a garage unless the bullet is empty,
checked and certified ‘gas-free’ by a competent person.
LPG OPERATIONS MANUAL
(b) All repairs involving LPG systems attached to the tank trucks should
be performed preferably in the open area, well away from the
buildings and possible sources of ignition.
(i) Park the vehicle off the road, if possible. If on an incline, turn the
wheels towards a curb or bank and apply hand brake.
(ii) Shut-off engine and set the chock blocks on the real
i. wheels.
(iii) Place the fire extinguisher in easy-to-use position. Extinguish any
open flame in the area. Check the vehicle for damages. If there is a
leakage of LPG, stop all traffic and keep people away.
(iv) Enlist police help for this purpose, if readily available.
(v) Notify Police Authorities and the Plant Manager.
(a) Wherever possible, close the valve or cap fixed to the valve outlet
to stop gas flow. If this is not possible, possibility of moving the
vehicle to a safe place should be explored, provided this does not
expose the bullet, pipeline, or fittings to further damage and does
not endanger the public or property.
(b) Use all available means to disperse LPG vapours if the vehicle
cannot be removed. Evacuate the area and remove all sources of
ignition.
(c) In all cases where gas leakage cannot be stopped, seek the help of
Fire Brigade
(a) Spray large quantities of water by jet or sprinklers over the bullet to
keep it cool. This will allow controlled burning of the gas without fear
of bullet rupture. However, every effort should be made to remove
the source of flame impingement by cutting off the gas supply.
LPG OPERATIONS MANUAL
(a) Where the tank truck does not give rise to hazard (i.e. where
leakage is not experienced, or is of minor character, or can be
controlled), immediate action under the supervision and
specialist guidance of a competent person should be taken to
evacuate the contents and hoist the vehicle into an upright
position. Lifting gear should be positioned to avoid damage to
bullet fittings and over-stressing of any part of the bullet structure.
(b) (b) Where fire occurs from a small leakage not likely to cause
further hazards, the fire should be allowed to burn until
arrangements are ready to evacuate the bullet and place the
vehicle in an a up-right position.
(c) Where severe fire exists, its intensity or effect may be controlled by
copious volumes of water.
.
LPG OPERATIONS MANUAL
DRAWING 18
DRAWING 19
8
LPG OPERATIONS MANUAL
8.1 GENERAL
8.1.1 In this chapter the details of LPG Equipment like LPG cylinders, its fittings, SC
Valve, LOT Valve, Domestic Pressure Regulator and consumables like O
ring, PVC Seal and Safety Caps and other related operations are covered.
The description covers in brief the design / construction, utility and
operation of each unit.
8.1.2 Details of Statutory Testing (5/10 years testing) of cylinders as per IS16054
are covered in Chapter No. 9
In the initial few years , Oil Marketing Companies which include IOC, HPC
and BPC were sourcing equipments from manufacturers, who were almost
their ancillaries. As the popularity with acceptance of LPG as a fuel
zoomed, the requirement of equipment also grew geometrically.
OITC is a body consisting of 3 members, one each from IOC, HPC and
BPC. OITC has been primarily constituted to deal with all technical matters
related to LPG equipment. BPC is the convenor of OITC.
a) Advisory body on all technical matters with a view to ensure over all
quality and conformity to all the specifications in manufacturing of
LPG Equipment.
b) Technical assistance for procurement of LPG Equipment.
c) Liaise with BIS, CCOE etc from time to time on technical matters
related to LPG Equipment.
d) Monitor and upgrade the quality standard followed in manufacturing
of LPG Equipment.
e) Develop and enlistment of vendors for manufacturing of LPG
Equipment and consumables.
f) Technical development activities related to LPG Industry and liaison
with LERC.
Oil Industry Technical Audit Team ( OITAT) consisting of members from IOC,
HPC and BPC carries out technical audit of manufacturers of LPG
equipment ( i.e. Cylinder, Valve and Regulator) minimum once a year and
consumables ( e.g. Safety caps, PVC Seals and O rings) twice a year to
ascertain the quality of equipment/consumables being manufactured
and advise manufacturers to take corrective actions as required.
Inspection is carried out mainly in line with relevant BIS codes and Oil
company tender documents. The reports of inspection shared within Oil
Companies.
All expenses towards LERC are shared among the Industry members i.e.
IOC/HPC/BPC in the ratio of 2:1:1 and also officers are deputed in the ratio
of 2:1:1.
8.4.1 FEATURES
The standard IS 3196 (Part 3) describes methods of test for welded low
carbon steel cylinders. This standard lays down various tests carried out in
the LPG Cylinder manufacturing unit and laboratory and details of
carrying out these tests.
Design of LPG cylinders for domestic and NDNE use have been
standardised on Oil Industry basis. They are designed for maximum
working pressure of 1.66 MPa (16.87 kg/ cm2), which is the maximum
permissible vapor pressure for Propane-Butane mixture as per BIS
specification No. IS 4576 :1990 at the assessed temperature of 65C (149F).
8.4.5 DRAWINGS :
LPG Cylinders are manufactured from Low carbon steel Hot rolled steel
plate sheet conforming to IS 6240 : 2008. The coil thickness and minimum
finished wall thickness of cylinders as per design calculation are as given
below :
Also LPG Cylinders are manufactured from newly introduced High Tensile
Strength Steel conforming to IS 15914 . The Steel Plate has thickness of
LPG OPERATIONS MANUAL
2.1± 0.1 mm, which will reduce the tare weight of cylinder by 20 to 25% as
compared to LPG Cylinders made of HR Steel conforming to IS 6240
The LPG Cylinders are manufactured by the party who has BIS license and
PESO approval for manufacturing of LPG Cylinders of specific water
capacity.
12. Hydrostatic Test of cylinder at 25 kgf/cm² for a period not less than 30
seconds.
13. Removal of water and internal cleaning by vacuum pump
14. Grit blasting for surface preparation for metalizing
15. Metalising i.e. zinc coating of 40 µ (microns)
16. Primer painting by zinc chromate primer conforming to IS 2074
17. Final painting by Synthetic enamel paint conforming to IS 2932 of
Signal Red color (Shade No. 537 of IS 5). Both the layers of the Primer
and Finish paint shall have total thickness of minimum 30 microns.
18. Tapping of bung threads and checking by L1 and L9 gauges.
19. Internal Cleaning of cylinders by vacuum pump, drying, checking by
low voltage bulb and magnet.
20. Tare weighting of cylinder with SC Valve and Safety cap.
21. Punching of test date and tare weight on the cylinder on bung and
one of the Stay Plates. Also punching of Gross Weight on one of the
Stay Plates.
22. Screen printing of safety slogans and statutory warning on the
cylinder.
23. SC Valve fixing at torque of 145±15 lb-ft
24. Pneumatic test at 12 kgf/cm² by immersing cylinder with safety cap
fitted on SC Valve in water tank for a period not less than 60 seconds
for ensuring that no leakage from the body of the cylinder and bung
joint (valve pad).
25. Out of batch of 403 cylinders, one cylinder is taken for Acceptance
Test and two cylinders for burst Test as per IS 3196 (Part 3). Basis of
passing of samples, BIS issues Test Certificate for entire batch.
26. Record keeping for test reports of raw materials, stage wise
inspections during manufacturing, calibration of testing equipment
etc.
27. Packing and Despatch of new cylinders duly de-pressurized to LPG
Bottling Plant.
8.4.9 FITTINGS :
Only fitting which is directly mounted on LPG cylinder and forms an integral
part of the cylinder is the cylinder valve of Self-Closing (SC) type. Details of
a Self Closing type Valve is described in detail in Clause No. 8.5.
Oil Industry has standardized the design of the domestic LPG cylinder. The
details of the markings standardized on Oil Industry basis pertain to the LPG
cylinder is given below
Foot ring is embossed with ‘INDANE’ mark on one side and with ‘IOC’ mark
on the other side. BIS allocates exclusive number to each manufacturer as
Marking License number, BIS Marking License No. in seven digits as CM/L-
xxxxxxx ( For example CM/L 1234567), which is embossed on the foot ring
with letters of 6 mm height. Also circumferential weld machine
identification number is punched on Foot ring. For details please refer
Sheet 1 of 4 of above drawing of LPG Cylinder
e.g. T for TISCO, S for SAIL, E for Essar, L for Lloyds, P for Ispat, SL
for Salem Steel, J for Jindal , B for Bhushan Steel etc.
c Tare Weight of the cylinder in kg.
d Maximum Gross Weight of the cylinder in kg.
2 Second vertical Stay Plate must have following markings :
a IS 3196 PART 1, LPG, BIS Logo and “SR” or “N” below BIS Logo.
(Letter “SR” or “N” , if the cylinder is stress relieved or normalized)
b Water capacity (WC) in litres.
c Maximum Working Pressure (WP) : 1.66 MPa.
d Test Pressure (TP) : 2.45 MPa.
3 Third vertical stay must have the following markings :
a Batch No.
b Test Date (Month and year of Hydrostatic Test ) i.e. for Jan 2013 as
01-13)
On the inner portion of the vertical stays, following details must be screen
printed :
Quarter [ i.e. A for 1st Quarter ( Jan to Mar) , B for 2nd Quarter ( Apr to Jun)
, C for 3rd Quarter ( Jul to Sept) & D for 4th Quarter ( Oct to Dec)] and
year of next due date ( in two digits) of statutory testing of cylinder will be
screen printed on inner side of the vertical Stay Plate having Batch No. &
Test Date.
( For example “A 23” for Statutory Testing is due in 1st Quarter of Year 2023)
Tare weight ( e.g. “15.5” ) will be screen printed on the inner side of the
other two vertical Stay Plates
On the top of the cylinder bung, details of (a) Cylinder Serial Number (in 6
digits), (b) Source of Steel, (c) Month & Year of Hydrostatic Test , (e) Tare
Weight of cylinder in kg and (f) Identification Mark of manufacturer are
stamped/punched.
The following details are screen printed on the body of the cylinders both
in Hindi and English.
For Domestic Cylinder : (a) Indane, (b) Check seal and weight on delivery,
(c) Switch off regulator when not in use & (d) Statutory warning : This
cylinder is for domestic use only, Non domestic use is strictly prohibited and
punishable.
For NDNE Cylinder : (a) Indane, (b) Check seal and weight on delivery
and (c) Switch off regulator when not in use.
8.4.11.1 The position of 3 vertical stay plates are fixed on the cylinder. The screen
printing on LPG Cylinder for safety instructions and other details is carried
out as per the standard drawing at earmarked locations on the cylinder
as shown in the drawing w.r.t. vertical stay plate for Batch Number & Test
Dates ( SP 1) so that all cylinders are look-alike irrespective of
manufacturer.
8.4.11.2 The thickness of the paint on the cylinder should be measured with the
help of digital type Elcometer in the same plain and without putting any
excess pressure on the Elcometer. In case reading is not taken in the same
plain or excess pressure is exerted on the Elcometer, the meter may not
give correct reading of the paint thickness. Therefore, necessary
precaution should be taken for proper measurement of the paint coat
thickness.
LPG OPERATIONS MANUAL
8.4.11.4 Five gauge readings for each spot shall be taken moving the probe a short
distance for each new gauge reading within an approximate area of 2
cm x 2 cm. Discard any unusually high or low gauge reading that cannot
be repeated consistently. Take the average of the five guage readings as
a spot measurement.
8.4.11.5 Make five such spot measurements approximately evenly spaced over the
surface of the cylinder.
8.4.11.6 Each spot measurement shall not be below 80 percent of the specified
minimum thickness and average of the five spot measurements shall not
be below the specified thickness
8.4.12.1 PESO has approved revised schedule of periodic inspection and testing of
L
Background
P ISI Spec for Lettering Year of Year of
G color Shade color manufacturing retesting
White 127 Black 2012 2022
Sea
c Green 217 Black 2013 2023
Dove
y Gray 694 Black 2014 2024
Air
l Craft Blue 108 White 2015 2025
Salmon
i Pink 443 Black 2016 2026
India
n Brown 415 White 2017 2027
d Blue
Satin 177 Black 2018 2028
e Green
Bus 299 White 2019 2029
r
Black 521 White 2020 2030
s
Yellow 355 Black 2021 2031
8.4.12.2 To facilitate segregation of the cylinders at the plant for statutory testing, a
uniform procedure is evolved by the Oil Industry. According to the
procedure, colour coding / marking is done on inside face of the vertical
Stay Plate (having Batch no. & Test Date at outer face ) of the valve
protection ring by screen printing the Quarter and Year of next due date
of Statutory Testing.
Since all the cylinders, which are in use by the Oil Industry are standardized
to the same specification, the Oil Industry has adopted the following
convention to facilitate identification of the ownership of the cylinders
a. IOC Cylinders : painted fully with Signal Red (Shade No. 537 of IS 5).
The foot ring is having 6 horizontal oval holes for air vent and 8 nos. 5
mm diameter holes at the bottom for draining of water.
b. BPC Cylinders : painted fully with Signal Red (Shade No. 537 of IS 5)
with Golden Yellow ( Shade No. 356 of IS 5) on shroud. The foot ring is
having 6 round holes for air vent and 8 nos. 5 mm dia holes at the
bottom for draining of water.
c. HPC Cylinders : painted fully with Signal Red (Shade No. 537 of IS 5)
with French Blue ( Shade No. 166 of IS 5) on shroud. The foot ring is
having 6 vertical oval holes for air vent and 8 nos. 5 mm dia holes at
the bottom for draining of water.
LPG OPERATIONS MANUAL
a. IOC Cylinders : Painted fully with Oxford Blue ( Shade No. 105 of IS 5)
with Signal Red (Shade No. 537 of IS 5) on shroud . The foot-ring is
having 6 horizontal oval holes for air vent and 8 nos. 5 mm dia holes
at the bottom for draining of water for 5 kg cylinder and no drain
holes in case of 19 kg and 47.5 kg cylinders.
b. BPC Cylinders : Painted fully with Oxford Blue ( Shade No. 105 of IS 5)
with Golden Yellow ( Shade No. 356 of IS 5) on shroud. The foot ring is
having 6 round holes for air vent and 8 nos. 5 mm dia holes at the
bottom for draining of water for 5 kg cylinder and no drain holes in
case of 19 kg , 35 kg and 47.5 kg cylinders.
c. HPC Cylinders : Painted fully with Oxford Blue ( Shade No. 105 of IS 5 )
with French Blue ( Shade No. 166 of IS 5) on shroud. The foot ring is
having 6 vertical oval holes for air vent and 8 nos. 5 mm dia holes at
the bottom for draining of water for 5 kg and 19 kg cylinder and no
drain holes in case of 35 kg and 47.5 kg cylinders.
8.4.14.1 On receipt of the new cylinders from the manufacturer, LPG Plant shall
carryout random quality check ( RQC ) of the cylinders as under :
LPG OPERATIONS MANUAL
Apart from above there some other aspects of LPG cylinder quality which
are listed below. In case any discrepancy is observed, same shall be
reported to HO LPG Materials and LPG- Equipment Development, HO.
LPG OPERATIONS MANUAL
10. Water To check the actual water Water capacity to be checked by weight
capacity capacity of the cylinder method. Please note that for this the tare
wt. of the cylinder should be taken after
removing the valve. For 14.2 kg cylinder
water capacity = 33.3ltrs + 3% / - 0%
Two cylinders of same batch of only one manufacturer per bottling plant
in one quarter ensuring that all the manufactures supplying cylinders to a
particular plant are covered in one complete year.
8.4.16 REPORT OF FIRST FILL LEAK / SUBSEQUENT FILL LEAK OF LPG CYLINDER :
During first filling of new cylinders, if any body leak cylinder is found, the
same shall be reported to HO (LPG-ED) so that suitable action is taken
against the manufacturer. The matter of first fill leak should be reported
within 24 hours.
8.4.16.1 PROCEDURE FOR REPORTING FIRST FILL (FF) LEAK OR SUBSEQUENT FILL LEAK
OF LPG CYLINDER :
In case of first fill leak of new cylinder or subsequent leak ( market return
cylinder during warrantee period), the following details duly signed by
Plant Manager shall be Intimated to HO LPG-ED :
LPG OPERATIONS MANUAL
The LPG from leaking cylinder shall be evacuated, the area from where
leak detected shall be marked with circle by permanent ink pen /painted
and cylinder is kept in safe custody under lock and key so that no body
tampers, steals and replaces with duplicate cylinder. The photographs of
the FF leak cylinder are taken including the leak portion, stay plate
marking etc.
The BIS officials will carry out joint inspection with manufacturer including
hydrostatic test and pneumatic test. After joint inspection , manufacturer
sends the FF Leak cylinder to LERC, Bangaluru for failure analysis and LERC
submits report to the HO (LPG-ED) and LPG Plant.
Basis of joint inspection with BIS officials, manufacturer identifies the root
cause of the defect and takes corrective measures to prevent re-
occurrence of the defect. Thereafter, BIS inspects the trial batch of the
cylinders and corrective measures taken by the manufacturer. On
satisfactory manufacturing and passing of the trial batch, BIS issues
resumption of stoppage of marking.
After fire accident at the LPG bottling plant, Shakurbasti, in the year 1983,
Government of India appointed Vasudevan Committee for detailed
investigation and submission of recommendations. Vasudevan
Committee’s recommendations are :
8.5.2 Government decided to adopt Kosan Technova design for valves and
both Kosan Technova (Denmark) and Sierra (Italy) designs for Pressure
Regulators (PRs) on 29.12.1983.
The technology for LPG valves was imported by IOC on behalf of the Oil
Industry from Kosan Technova, Denmark. The technology is for 25.6 mm
LPG OPERATIONS MANUAL
collar diameter and valve is called as Self Closing type valves (SC Valves).
Technology for SC valves was adopted by the Oil Industry in 1985 after its
implementation as per the requirement of Indian condition. SC Valves are
being used by the Oil Industry in India since then. Presently, there is only
one type of cylinder valves in circulation for the use on IOC cylinders as
well as cylinders of Other Marketing Companies (OMC).
8.5.5.1 The function of the valve is to provide gas-tight seal in closed position and
to prevent the contents leaking from the cylinders and in open position to
allow operation such as filling, discharge, evacuation, venting, etc. in a
controlled manner
8.5.5.2 The term ‘Self Closing’ is derived from its design as it remains closed unless
a pressure regulator (PR) or other suitable device is used for opening it. In
the case of accidental removal of the PR or the Filling Gun or any other
device, the valve automatically gets closed, thereby preventing any likely
LPG OPERATIONS MANUAL
accident that may otherwise take place due to large scale leakage of
LPG from the cylinder. This aspect makes this valve safer when compared
to other types of valves.
8.5.6 IS STANDARD :
Bureau of Indian Standards formulated Standards for the “Valve fittings for
use with Liquefied Petroleum Gas (LPG) cylinders of more than 5 litres
water capacity as per IS 8737:1995
Basically, the valve should withstand the working pressure of the cylinder to
which it is fitted. SC Valves are designed for a working pressure of 1.66
MPa ( 16.87 kgf/cm2) at 65 °C.
This valve is standardised on Oil Industry basis and all cylinders are
provided with these type of valves.
The body of SC Valve is made of brass . Valve body is forged from wrought
or extruded sections. The valve inlet have a taper of 1 in 16 on diameter
and thread size ¾” – NGT of ANSI/CGA V-1-1987 “Compressed gas cylinder
valve outlet and inlet connection, ANSI”.
The valve with threaded outlet connection have parallel left hand
external threads conforming to SI threads with a pitch of 1.814 mm and
thread angle of 60°.
LPG OPERATIONS MANUAL
1. Body 6. Spring
2. O ring 7. Spindle Guide
3. Upper Spindle 8. Adjusting Screw
4. Gasket 9. Safety Cap
5. Lower Spindle 10. Thread Cap
8.5.10 DRAWING :
8.5.11.1 The metallic valve housing is forged from the wrought or extruded sections
of brass alloy mainly of copper and zinc to meet the requirement of
physical properties as appended below
8.5.11.2 The materials of construction of the component parts of the valves are
selected so as to ensure that they are unaffected by the chemical,
thermal and cyclic stress influences that will be encountered in normal use.
The SC Valve is made out of brass rod meeting the IS 8737 specification.
The following is the sequence of manufacturing process :
f. Stamping on 6 hexagonal sides for IS no. & BIS Logo, Batch, Qtr &
year of manufacture, BIS License no., Manufacturer’s monogram, Oil
Co’s name, WP.
g. Outlet Operation on PMT Index machine or CNC m/c or Multi Spindle
m/c.
h. Inlet Operation on PMT Index machine or CNC m/c or Multi Spindle
m/c.
i. Threading on inlet dia by Special Wagener die head drilling m/c.
j. Ultrasonic cleaning of valve body
k. Sub-assembly fitting ( Spindle with gaskets, spindle guide, spring,
adjustment screw)
l. Air cleaning of assembled SC Valve.
The following tests are carried out by the manufacturer as per IS 8737 and
“Scheme of Testing and Inspection for Certification of Valve fittings for use
with Liquefied Petroleum Gas (LPG) Cylinders of more than 5 litre water
capacity according to IS 8737” :
iii. Cycle Test of one sample out of 20000 valves of same type is
being carried out. The valve shall perform satisfactorily at not less
than 5000 cycles of opening and closing operations with valve
inlet connected to an air supply of not less than 7 kgf/cm². After
the cycle test , the valve shall be subjected to the Pneumatic Test.
LPG OPERATIONS MANUAL
SC Valve fitted to the LPG cylinder MUST have the following markings on
the six hexagonal sides :
Sr Description Samples
a Check marking on hexagonal of 0.1% of consignment subject to
Valves w.r.t. approved drawing minimum 10 Nos.
The leakage in the case of this type of valve can occur as under :
(a) With the valve in closed position and valve outlet open :
As described earlier, the valve seat in this type of valve remains closed
unless external pressure is applied. Therefore, to keep the valve seat open
there will be a need for special type of adaptor called as ‘Dummy
pressure regulator’ (Dummy PR). In this case the leakage can occur
through the connection between the valve outlet and the special adaptor
(Dummy PR) indicating that the sealing ‘O’ ring is absent or defective. This
will necessitate replacement of the ‘O’ ring.
Valve bodies are made of brass alloy and can get damaged, if it is hit
against any object. This may develop leak of LPG creating serious
hazards. To prevent this, protection for the valve is provided by means of
valve protection (VP) ring assembly on the top of the cylinder.
Each and every valve housing after machining are being cleaned by the
valve manufacturers with Ultrasonic Cleaning Equipment to remove any
oil, grease, chips from the valve housing before assembly. The solution
used in Ultrasonic Cleaning Equipment is Trichloroethylene. In this system,
there are three chambers. The first chamber contains liquid
trichloroethylene which vibrates at ultrasonic frequency. The second
chamber is of liquid trichloroethylene without any frequency and the third
chamber is a vapour chamber.
8.5.21 DEFECTS OBSERVED IN VALVES DUE TO HANDLING :
In an LPG Cylinder, LPG exists in dual phase under equilibrium i.e. Vapour
phase and Liquid phase. The Liquid Off Take (LOT) Valve is to facilitate the
off take of liquid LPG from the Commercial cylinders of higher capacity to
meet the heavy BTU loads found in industrial uses and enable the user to
withdraw the full quantity of LPG from the cylinde
The LOT Valve can be either of following make approved by PESO and
tested by third party inspection agency like M/s Bureau Veritas (BV) , M/s
Lloyds Register of shipping , M/s Det Norske Veritas (DNV) etc :
8.6.4 DRAWING :
The LOT valve body is made of brass , have external threading to match
with the existing internal bung thread on cylinder i.e. ¾” 14 NGT. The valve
body is forged from wrought or extruded sections.
a. The hand wheel is provided to regulate the flow rate of liquid LPG.
b. A Pressure Relief Valve is provided near the outlet & integral part of
LOT Valve
c. Excess Flow Check Valve (EFCV) is provided at bottom inlet side of
the valve at the top of liquid withdrawal tube. The EFCV will close
automatically if the flow exceeds the pre set flow rating.
d. The LOT valve is provided with a tube which, on screwing of valve
on cylinder, shall go up to the bottom of the cylinder. This will
facilitate direct removal of liquid from cylinder.
e. LOT Cap with Nylon string.
LOT Valve fitted to the LPG cylinder MUST have the following markings :
c. SRV Test for pop up & reset at 19 kg/cm² whenever cylinder pressure
drops, rest and relieving (declared) capacity
d. EFCV closing flow ( 7.5 lpm LPG max) and residual leak ( 500 cc/min
max)
e. Closing /Opening Torque
f. Filling Rate 20 litres /minute at 12 to 15 kg/cm²
The following visual inspection of LOT Valves shall be carried out by the
Plant on receipt from the manufacturer :
Sr Description Samples
a Check marking as per approved 0.1% of consignment subject to
drawing minimum 10 Nos.
LOT Valve & Its components are guaranteed by vendor against defective
material, design and workmanship as per warrantee period from date of
delivery for Indian vendors and from date of boarding for foreign vendors.
In case any defects develop within warrantee period the same shall be
replaced or the goods shall be replaced free of charge. All expenses
incurred including those on transportation shall be borne by the
manufacturer.
LPG OPERATIONS MANUAL
The valve shall be fixed on the cylinder with applying specified torque of
176 to 200 Nm max, with fixture & torque wrenches only. It is
recommended to install a filter/strainer at the filling site (before the filling
adopter) to prevent any dirt from entering the cylinder. An approximate
10 mm cutting of the tube is recommended so the tube will not be bent on
the bottom and the gas will not get blocked.
8.7.1 GENERAL :
8.7.1.1 Prior to 1991-92, IOC and HPC were procuring Pressure Regulators (PRs) as
per the technology imported by IOC from Kosan Technova, Denmark
whereas BPC finalised technology from Sierra, Italy and had been
procuring PRs of Sierra design right from the beginning. As per Kosan
Technova design the PR is having three position knob i.e. on / off /
detach.
8.7.1.2 Subsequently IOC and HPC decided to switch over to Sierra Design for
procurement of PRs during 1991-92 due to obvious advantage of two
position knob i.e. on / off. The locking of Sierra design PR is independent of
on / off position of the knob. In this PR the engagement of inlet of PR with
outlet of SC valve is done by five steel balls held by a circular ring called a
bush. After engaging the regulator to the valve outlet, the regulator gets
LPG OPERATIONS MANUAL
8.7.1.3 Procurement of Sierra design PRs for IOC and HPC actually started from
the third quarter of 1994 after reviewing various dimensions, tolerances
and other design aspects of Sierra design PRs by the Oil Industry.
It has a vertical inlet without any threads. It sits on the outlet of SC valve
and is mechanically locked to the valve with the help of a circular ring
called ‘bush’. The valve is opened / closed by a lever mechanism
operated by a 2 position knob. After placing the PR on the outlet of the
valve, the bush is lifted upwards and locking of the PR with the valve is
ensured by pushing the bush downwards. By turning the PR knob or
spindle, it presses down the valve pin keeping the valve seat in open
position. The design of the PR is such that the valve seat will not be opened
unless the regulator is properly kept in locked position on the valve outlet.
The gas tightness of the connection, joining the valve and the PR, is
achieved with the help of secondary sealing ring made of synthetic rubber
(Base polymer NBR, CAN content or FKM ) provided on the inlet of PR and
is called tight joint of PR.
At the time of making PR connections, it must be ensured that the ‘O’ ring
is present at the outlet of the valve for primary sealing between SC Valve
outlet and PR inlet.
For disconnection, PR knob should be in off position. Then only the bush
can be pushed upwards to disengage the PR from the valve.
8.7.2.2 FUNCTION :
The pressure in a LPG cylinder will depend on the composition of LPG and
will vary with the temperature within the cylinder. Usually it is considerably
higher than that required for the consuming appliances. To enable to
reduce the pressure within the cylinder to the operating pressure of the
consuming appliances, a Pressure Regulator is required.
The PR consists of a gas tight casing with inlet and outlet passages and
divided into two chambers by a flexible diaphragm. The diaphragm is
connected to jet in the vapour inlet connection, by means of a lever
mechanism which closes the jet whenever the diaphragm is lifted. An
adjustable compression spring is mounted above the diaphragm and
applies a downward pressure which tends to open the jet. A vent hole in
the upper casing connects the chamber above the diaphragm to the
atmosphere. The vapour from the cylinder flows into the lower chamber
of the PR and it tends to lift the diaphragm against the spring pressure and
LPG OPERATIONS MANUAL
thus closes the set. When the vapour in lower chamber is used, the
pressure under the diaphragm tends to fall, thereby opening the jet. In
practice, the diaphragm constantly fluctuates for regulating the
flow/pressure , thus state of balance exists and delivery pressure is held
within narrow limits.
8.7.2.4 IS STANDARD :
8.7.2.6 DRAWING :
Sr Component Sr Component
1 Plastic Cap for Bush 16 Filter
2 Spacing Collar 17 Lever
3 Bush 18 Lever Pin
4 Clamping Balls – 5 nos. 19 Rubber Disc ( Lever Pad)
5 Tight Joint 20 Diaphragm Plate
LPG OPERATIONS MANUAL
Sr Component Sr Component
6 Spring for Bush 21 Diaphragm
7 Washer 22 Connecting Fork
8 Operating Tap with Spindle 23 Load Spring
9/10 O - rings 2 nos. for Operating 24 Regulating Knob
Tap Spindle
11 Retaining Pin 25 Marking Plate
12 Working Rod 26 Plastic Cap for outlet nozzle
13 O - ring for working rod 27 Bottom Cover ( Body)
14 Spring for Working Rod 28 Upper Cover
15 Bush for Working Rod
1. Die Casting : Zinc Alloy (Zamac 5) is used for making body and cover
by die casting method by use of hot chamber die casting machine
and dies of body and cover.
2. Trimming : Extra flashes in body and cover castings are removed.
3. 5 hole drilling and reaming
4. Stub hole drilling
5. Retaining pin hole drilling
6. 6 hole( rivet ) hole drilling
7. Orifice hole drilling
8. Final filling and visual checking
9. O ring seat reaming
10. Passivation/degreasing and vibrating fro burr removing : 7 tank
process.
11. Preheating at 60 to 80° C for moisture removing in electrical oven
12. Powder coating and Baking at 180 to 190° C in electrical oven
13. Visual Checking
14. Orifice reaming
15. Lever sub-assembly and Lever fitting by 2 Ton hydro-pneumatic Press
16. Filter fitting
17. Cover fitting and riveting by 15 Ton hydro-pneumatic Press
18. Load spring and nut fitting
19. First soundness testing at 1500 mm WC
20. Operating Tap Spindle (OTS) sub-assembly and OTS fitting
21. Bush fitting
LPG OPERATIONS MANUAL
Tests on DPR are being carried out as per IS specification and Technology
Implementation report :
The following visual inspection of DPR shall be carried out by the Plant on
receipt from the manufacturer :
LPG OPERATIONS MANUAL
Sr Description Samples
a Check marking as per approved 0.2% of consignment subject to
drawing minimum 10 Nos.
Three PRs of same batch of only one manufacturer per bottling plant in
one quarter ensuring that all manufactures supplying PRs to particular
plant are covered in one complete year.
PRs may become frozen if water is present in LPG. Water may enter into
the system due to hydrostatic testing of vessels, cylinders, pipelines etc. or
due to breathing-in of empty cylinders if valves are left open.
LPG, both in the liquid and the vapour phase, absorbs moisture readily until
saturation point is reached. Any water present in the LPG cylinder is likely
LPG OPERATIONS MANUAL
8.7.9.1 GENERAL :
The Multi Function Regulator have four additional features in built in the
design, over & above the basic features in normal DPR.
MFR is provided with inbuilt mechanism to shut off the flow of LPG, in case
of failure of tube connecting MFR outlet to the Gas stove. The mechanism
meet following working requirements:
b) Under normal usage and gas flow condition, the excess flow
shut off feature does not activate.
c) The excess flow mechanism is not be for one time use. Once
the mechanism is operated, it is possible to reset the
mechanism after taking corrective action & ensuring safety by
the operator. The resetting process is simple and easy to
operate without requiring any tools or tackles.
MFR is provided with an analogues display which helps the user to monitor
the level of the LPG in the cylinder. The display have indication for various
situations like ‘LOW GAS’ & ‘REFILL’ by the way of different colours zones.
This will help the user to decide for the refill of cylinder well in advance. The
display can be also electronic which gives alarm in case the Gas is Low.
It is possible to use this low level indicator to check for the minor leakages
in the gas tube/hose and from the joints.
8.7.9.3 IS SPECIFICATION :
PESO has accorded approval for introducing MFR duly approved by third
party inspection agency like TUV on pilot basis.
Valve outlet is fitted with Safety Cap to avoid damage to internals of the
LPG valve and also to arrest the entry of dust particles and dirt inside the
valve assembly. Safety cap should be put on to the valve at all times
except for filling of the cylinder at the Plant and usage of the cylinder at
the customer’s premises.
If the safety cap is not fitted on to the valve by means of SS spring, valve
may get damaged due to entry of dust particles or dirt into the valve
spindle joint packing and may cause leakage of LPG through the valve.
Hence, the safety cap is also considered as a protection for the leakage
of the valve. This is an important component for valve protection as well
as stopping leakage in case of emergency.
8.8.2 DRAWING :
8.8.3 SPECIFICATION :
Safety cap shall be milkfish white in colour. Average weight of cap with
spring and nylon/PPMF string shall be 9.18 + 0.5 grams. Average weight of
cap without spring and nylon/PPMF string shall be minimum 7.5 grams. It is
tested for pneumatic pressure of 17 kgf/ cm².
The Plant shall check all critical dimensions of safety caps by gauges etc .
Plant shall keep weighing scale with proper least count duly calibrated
for checking the quality of safety cap on receipt. Immediately on receipt
of Safety Cap, Plant shall weigh 25 nos of safety cap for every lot of
25000 nos. of safety caps received and shall maintain record of the same.
LPG OPERATIONS MANUAL
Also check fitment of safety cap on the SC Valves for easy fixing and
removal.
If in the physical test, it is found that the samples are not meeting the
requirements viz. average weights, fitment on the SC Valves, critical
dimensions etc. the supplier shall be informed for joint inspection and
once it is established that the caps are not meeting the requirement for
average weights, fitment on the SC Valves, critical dimensions etc. then
the entire supplies/ lot should be rejected.
Marking for the following on Safety Caps shall be as given in the drawing
The Safety Caps are to be procured from the OITC (Oil Industry Technical
Committee) enlisted manufacturers only.
8.8.7 NORMS FOR SENDING SAMPLES OF SAFETY CAPS TO LERC FOR TESTING :
8.9.1 FUNCTION
The O - ring is provided on the outlet of SC Valve for primary sealing of DPR
inlet with SC Valve outlet. Thus there will not be any leakage from the
regulator when regulator is kept in “ON” position. If any leakage is
observed from the O - ring, then O - ring shall be replaced with new O ring.
8.9.2 DRAWING :
8.9.3 SPECIFICATION :
Marking for the following on the inner side of O ring shall be as given in the
drawing :
a. Cavity/Pin number
b. Manufacturers identification mark
c. Half year and Year of manufacture.
LPG OPERATIONS MANUAL
LERC shall test the samples and submit the test report within 15 days from
the date of receipt of samples by LERC. Plant on receipt of report shall
decide about utilization of O rings. If the O rings are rejected, Plant shall
deform the O ring and hand over to the supplier.
PVC Heat Shrinkable seal is being used for sealing of safety cap provided
on filled LPG Cylinder to prevent any theft of LPG from the cylinder by
unscrupulous person or delivery boys. The PVC Seal is placed on the safety
cap and with steam, the PVC seal shrinks and is tight fitted on the safety
caps, thus it is difficult to remove the PVC seal without breakage due to its
shrinkable properties.
8.10.2 DRAWING :
The thickness of PVC Seal shall be 0.08± 0.010 mm. Height shall be 42 mm
with 9 mm collar. The color of PVC Seal shall be metallic white with
markings as shown in the drawing.
Plant shall keep weighing scale with proper least count duly calibrated
for checking the quantity of PVC Seal on receipt. 1000 pieces of PVC Seal
weigh 700 grams (min) Immediately on receipt of PVC Seal, Plant shall
carryout dimensional checks and average thickness of PVC Seal and
average thickness of PVC Seal should not be less than 0.08 mm.
Perforations of 4 mm size with gap of 1.5 mm between consecutive
perforations shall be checked.
If in the physical test, it is found that the samples are not meeting the
requirements viz. average weights, dimensions etc the manufacturer shall
be informed for joint inspection and once it is established that the PVC
Seals are not meeting the requirement for average weights, dimensions
etc. then the entire supplies/ lot should be rejected.
Marking for the following on PVC Seal shall be as given in the drawing :
The PVC Seals are to be procured from the OITC (Oil Industry Technical
Committee) enlisted manufacturers only.
LPG OPERATIONS MANUAL
8.10.7 NORMS FOR SENDING SAMPLES OF PVC SEALS TO LERC FOR TESTING :
LERC shall test the samples and submit the test report within 15 days from
the date of receipt of samples by LERC. Plant on receipt of report shall
decide about utilization of PVC Seals. If the PVC Seals are rejected, Plant
shall deform the PVC Seals and hand over to the manufacturer.
8.11.1 GENERAL
7 3 X 24 pt 1/2 90/180
8 4 X 24 pt 1/2 120/240
Bottling plants having a bulk inventory not exceeding 100 MT of LPG with
minimum two storage vessels and also bottling a total quantity not
exceeding 20 MT of LPG per shift of 8 hrs are falling under OISD 169. The
addendum provided vide Section 5 as approved in the 26th Safety
Council Meeting held on 25th July,2008 of OISD 169 lays down the
additional minimum safety requirements on design, layout, storage,
loading / unloading, operation at LPG installations having Bulk Storage (a)
exceeding 100 MT but limited to 300 MT for aboveground storage and also
for (b) 450 MT in mounded or in combination of aboveground and
mounded storage of LPG with total bottling quantity not exceeding 35 MT
per shift. of 8 hrs.
For all the plants where either storage or bottling capacity is higher than
the above limits, OISD Std.144 shall be applicable.
8.11.1.3 From the safety point of view, separate covered sheds, with a minimum
distance of 15 metres between the sheds are planned for the following
activities :
However the facilities are combined to Two / Three sheds as per the latest
design, but cold repair shed is always segregated 15 metres away from the
main filling operation. Valve changing unit without evacuation can be
provided in filling shed itself. For OISD-169 bottling plants all the activities
are covered under single shed only.
8.11.1.4 In the area within the plant, where cylinder handling is done, mastic
covering is provided on the columns (up to 1.5 metres height) and the
entire shed flooring. It minimizes the cylinder damage and also prevents
sparking, in the case of accidental fall of cylinders.
LPG OPERATIONS MANUAL
8.11.1.5 The movement of cylinders within the plant should, as far as practicable,
be handled through conveyor system. For manual handling of cylinders,
wherever unavoidable, cylinder trolleys should be used for the safe
handling of the cylinders.
8.11.2.1 Function
(b) The chain can run at different velocities on different sections when
provided with suitable drive units, giving considerable flexibility to
adopt to different working requirements.
These are intended to convey LPG cylinders from chain conveyor to stake
trucks and vice-versa. It consists of a stationary and a movable section. The
movable section can be extended for 6 metre and is supported by the
steel rollers in the stationary section. It comprised of chain conveyors with 2
parallel chains, which are common for both the stationary and the
movable sections. Two drive units with necessary gears and transmission
elements are built into the stationary section, one for the conveyor chains
and the other for the extension and retraction of the movable section. Two
actuators are placed on the movable section of the telescopic conveyor,
one for start and stop and reversing of the chain conveyor; and the other
for extension and retraction of the movable section. For safety reasons, the
movable section of the telescopic conveyor is provided with automatic
stop-device as well as a safety stop-device, which at the slightest touch,
instantaneously stops both the conveyor chains and the movable section.
LPG OPERATIONS MANUAL
(a) The chain conveyors are driven by the drive units. Drive unit consists
of worm reduction gear box coupled to flame proof electric motors.
Transmission of power is made by the transmission chain from the
sprocket of the gear box (or directly through the sprocket assembly
of planetary gear box) to the sprocket of conveyer drive section.
(b) The number and specific dimensions of the driving units are adopted
based on the anticipated load and the desired velocity of
conveyance. The driving units are provided with tensioning device for
the conveyor chain. Soap water trays are provided at suitable
locations on the system, where the chain gets cleaned and
efficiently lubricated during its continuous passage through the
solution.
8.11.3.1 The following facilities are provided prior to the filling of cylinders :
(a) Purging unit : The unit consists of Vacuum pump with gauge and a
manifold with sets of adopters for removal of air from the new
empty cylinders and filling of LPG vapor .into these cylinders. The
unit is installed and operated on line and designed for automatic &
semiautomatic operations. To ensure removal of air up to 0.35
kg/cm2 (absolute )/ (-)494 mm of Hg (g)/(-)0.65 kg/cm2 (g), pressure
based purging cut-off has been provided.
(b) Cylinder washing / Drying unit : This unit is installed on line for the
cylinder washing and subsequent drying of empty Cylinders prior to
filling. The unit consists of continuous water rinsing section with rinsing
nozzles and water tank with filter, centrifugal pump & air blower.
(c) On line check facilities for market return cylinders. The facilities
consist of check weighing scale along to check the weight of
defectives returned by the distributors.
(b) Weighing machine forms a primary part of filling machine along with
mechanism for filling liquid LPG.
For the safety of filling operation, filling machine (carousel / unit filling
machine) should be electrically interlocked with the vapor extractor system
i.e. without operating the vapor extraction system , filling operation cannot
be commenced.
Gross weight system is adopted for filling operation in all plants. In this
case, the machine is provided with individual adjustments for ‘Tare-Weight’
and ‘Net-Weight’. Once the weight of the product to be filled is pre-set as
‘Net-weight” which remains constant, the only adjustment required is that
of ‘Tare-Weight’. Once the set ‘Gross-Weight’ (arithmetical sum of pre-set
‘Net-Weight’ and the ‘Tare-Weight’ set) is reached, the product flow is cut-
off automatically. So the accuracy of the filling relates to the accuracy of
‘Tare-Weight Marking’ on the cylinders and the tare weight set on the
LPG OPERATIONS MANUAL
From the central column, gas and air are distributed through
distributing pipes to circular pipes behind the filling machines and
through gas-stop valves and anti-static hoses. A filling machine can
thus be shut-off for repairs without affecting the operation on the
other machines. The LPG liquid line from the pump house is provided
with a by-pass arrangement with DP (Differential Pressure) Valve
near the carousal. The DP valve is a spring loaded valve, which
automatically allows the flow of LPG through a by-pass line,
whenever LPG pressure in the pipeline exceeds the set limit..
The filling pressure shall not exceed max. working pressure of the
cylinder i.e. 16.9 Kgf/sq cm at 65 Degree centigrade.
b) Types of Carousels
The tare weight of the cylinder from the individual filling machine is
automatically transferred to check scale for verification. The data
from carousal and check scale is used for generation of on-line MIS
by means of a PC installed in the control room. Also the fault
LPG OPERATIONS MANUAL
The check scale consists of electronic weighing scale with load cell
and digital display and the net weight (14.2 Kg, 19 Kg etc) is tared or fixed
and the check scale shows only the variation in weight of the cylinder and
cylinders with weight variation higher than the preset values are
automatically rejected into a different loop.
LPG OPERATIONS MANUAL
In some of the Plants, stand alone check scales are still available. In this
type of check scale, tare weight of the cylinder is punched by an operator
as it approaches the check scale. Check scale after comparison
automatically accepts or rejects the cylinder as the case may be.
The scales of capacity 1200cyls/hr, 1400 cylinders/hr, 1600 cylinders /hr are
available and are provided with anti jam sensors to stop the operation in
case of accumulation of cylinders down the stream or on the rejection
conveyor.
Over filled / under filled cylinders rejected from the check scale are
manually corrected at this unit. The unit consists of weighing scale and one
filling head (common for filling and evacuation) with a stopper, lifting
mechanism, tilting mechanism for evacuating excess quantity of over filled
cylinders. The under filled cylinders are corrected by topping up with the
required quantity and the overfilled cylinders are evacuated to the net
quantity by tilting the cylinder on the frame of the machine. The system
operates on the same gross weight method similar to the filling, where the
operation cuts off once the total weight of cylinder reaches the gross
weight of cylinder.
LPG OPERATIONS MANUAL
The cylinders after correction are checked again in the check scale for the
correct net weight.
At many of the plant, since the rejection from electronic carousal is very
low, Automatic Weight Reduction Unit has been provided in place of
Integrated Weight Correction Unit. The cylinders rejected from check scale
are fed to this machine, wherein 3 to 4 Kg of gas is removed (by
evacuating the gas for a fixed time from all the cylinders. These cylinders
are then sent back to the carousal for refilling.
The CVT is used for checking the ‘O’ ring condition and the valve leak. CVT
is designed to detect the leakage of 0.5 gm per hour and above. It
consists of a detecting head with a central air capillary connected to the
top chamber filled with kerosene. When the head is connected to the
cylinder valve, it clamps the valve and probe air is supplied around valve
‘O’ ring . For any damage in the ‘O’ ring, the air passes through the ‘O’ ring
to the top chamber through air capillary. Bubbles in the kerosene chamber
shall indicate the damaged “O” ring or the valve leak. If the bubble
continues to persist, when the probe air is cut off, it indicates the valve leak
and if not, defective ‘O’ ring. The working of CVT should be verified by
using CVT verifier. Now a days, CVT is being used only at RQC loop at most
of the Plants.
The unit consists of testing head with auto centering and cylinder
clamping/lifting facility. When the cylinder enters the unit, the cylinder is
clamped and lifted simultaneously .The testing head lowers and is
clamped to the cylinder valve, probe air is supplied around Valve “O” ring
. For any damage in the “O” ring, the air passes through the central
capillary and taken to the pressure transmitter. The pressure transmitter
produces an electrical signal (4-20 milliamps) proportionate to the
quantum of air leak. As per the preset values set in the PLC panel, the
cylinder will be sorted out according to the magnitude of the electrical
signal. The cylinder valve with defective ‘O’ ring shall be rejected
automatically by a pusher to the rejection conveyer. The on line MIS is also
generated as the unit is integrated to the PC.
LPG OPERATIONS MANUAL
The detector has the capacity to check 1200 to 2200 cylinders /hr with
single/ double head. The unit is totally automated and does not require
manning.
The unit consists of single / multi sensing head with auto centering &lifting
facility. The equipment is also provided with a gas analyzer and a control
panel. When the cylinder enters the unit, the cylinder is lifted and centered
automatically. The sensing head is automatically lowered covering and
sealing the valve and bung portion of the cylinder. Clean air is supplied to
the sealed cavity of the sensor head. In case of a leaky cylinder, mixture of
air and LPG is formed within the sealed cavity of sensor head. This mixture
of air and LPG from the sensor head cavity is transferred through a tube to
the gas analyzer, which intern actuates the control panel to give a signal
for auto rejection of the cylinder.
The unit is totally automated one and does not require manning. The
cylinders segregated from this unit are either valve leak or bung leak. These
segregated cylinders are sent for valve change after evacuation. OK
valves fitted on Bung leak cylinders can later be retrieved through valve
retrieval machine/system.
Operation : The cylinder enters into the unit on the conveyor and is
automatically positioned under the testing head. The testing head lowers
on to the cylinder valve and test starts as soon as head is engaged to the
cylinder valve fully. Incase there is no leakage the head lifts off after pre-set
time and cylinder is released for further operation. Incase of leak either
LPG OPERATIONS MANUAL
from the valve seat or damaged valve ‘O’ ring the head lifts up. For any
leakage, the air/LPG vapor passes through the central capillary and taken
to the pressure transmitter. The pressure transmitter produces an electrical
signal (4-20 milliamps) proportionate to the quantum of leak. As per the
preset values set in the PLC panel, the cylinder will be sorted out according
to the magnitude of the electrical signal and pusher of the unit ejects the
cylinder to the rejection conveyer loop for further identification of the type
of leakage and necessary operation there of.
This unit consists of pneumatically operated PVC head and it taps on the
top of the safety cap placed on the valve. This unit is installed before the in
line bath to ensure that capping of the cylinder is done before entering
into water bath.
The filled cylinders are passed through the in-line water bath, dipped up to
the bung level to determine the leakage from the bung and the body. The
facility consists of a water bath made of sheet metal having chain
conveyer for the movement of cylinders inside the bath.
Periodical painting of the interior surface of the water bath with white paint
or cleaning of the white tiles, provision of sufficient lighting arrangement
and periodical changing of water are required to ensure that it is kept
clean for easy detection of the leaks.
The cylinder sealing is done by means of PVC seal using hot air. The PVC
seals are placed on the safety caps over which hot air or steam jet is
forced on. The PVC seals shrink and effectively cover the safety cap as a
seal. Portable hot air sealing unit may be provided at plants, in addition to
fixed hot air sealing unit to ensure 100% sealing of sound filled cylinders
before dispatch.
LPG OPERATIONS MANUAL
The unit consists of on-line check scale and a CVT, installed after the
sealing unit .Filled cylinders ready for dispatch (Minimum 0.5% of saleable
cylinders filled in a shift production ) are checked at random in intervals of
one hour during the shift production. The cylinders after having subjected
to all pre-filling and post filling quality checks, carried out earlier during the
filing operation, including sealing of safety caps are drawn from the
conveyor for the RQC check. The quality of cylinders shall be analyzed for
further corrective action. In any case, the rejection should not exceed
2.25% of the total cylinders checked during RQC.
The unit is used for emptying of contents from the LPG cylinders. The
contents are emptied out when cylinder is found leaky, defective or over
filled.
(i) On line cylinder holding rack with evacuation adapters and anti-
static LPG hoses, having pneumatically operated inverting
mechanism for evacuating the cylinders in inverted position. The
evacuation adopters in the racks are in turn connected to the
evacuation vessels through pipe line manifold. A special adapter is
required for evacuating pin defective cylinders
(v) High level alarm switch shall be provided in evacuation vessel and to
be set at 85% with audio-visual alarm and arrangement for change
over of vessels.
The cylinders enter into the rack of the unit in batches depending on
the number of heads on the rack are clamped with evacuation
adopters to the pipe line system either automatically or manually.
The rack gets / is inverted by pneumatic arrangement for
evacuating cylinders. By means of vapor transfer and compression
by the compressor low pressure is created in one vessel & higher
pressure in the other. The vessel at the lower pressure gets
connected to the cylinders at the evacuation rack through the four
way valve and thereby LPG flows to the vessel from the connected
cylinders under evacuation. The vessel at higher pressure gets
connected to storage vessel through the four way valve and there
by product from evacuation vessel is transferred to the storage
vessel due to pressure difference.
A sight flow indicator is fitted on to the outlet LPG pipeline from the
rack to observe the flow of LPG and ensure emptying of LPG liquid
from the cylinders before de-pressurization.
(a) Function
After ensuring fitness of the bung thread of the cylinder, valves are
fixed on to the bung with suitable thread sealant. Teflon tapes are
generally used as the thread sealant. Valve should be fitted on
cylinder by using minimum 2 rounds of un-sintered polytetra fluro
LPG OPERATIONS MANUAL
This unit changes the defective valve with a new valve without evacuation
of LPG liquid from the cylinder. The unit consists of a welded frame with
centering device, a head covering valve and bung, internal shaft (driven
by hydraulic jack to go up and down) to screw and unscrew driven by a
hydraulic motor, hydraulic power station with explosion proof motor and
pneumatic control cabinet.
(d) The defective returns from the distributors may be classified in two
categories as under :
(b) Rejection criteria guidelines for physical and material defects on the
cylinder are given in Table 1 to Table 3 as per IS 15966:2013.
LPG OPERATIONS MANUAL
(e) (Extra care should be exercised to check for spurious cylinders and
efforts be made to identify the source of receipt. Spurious cylinders
must be segregated for scrapping.
(g) Cylinders due for statutory testing / hot repairs MUST not be taken up
for filling but sent to testing plant.
(i) Cylinders of OMCs, unless specifically sent for filling, should not be
taken up for filling but segregated for exchange with the concerned
marketing company.
1 Depressed bung Damage to the bung which alters Rejection in all cases
the profile of the cylinder
Arc or torch Burning of the cylinder base metal , Rejection in all cases
burns a hardened heat affected zone ,
the addition of extraneous weld
metal, or removal of metal by
scarfing or catering
Fire damage Excessive general or localised Rejection in all cases
heating of the cylinder usually
indicated by: a)
Charring or burning of paint1)
b) Fire damage of the metal
c) Distortion of the cylinder
d) Melting of metallic valve parts
-
e) Melting of safety cap
1) In case of superficial charring of paint cylinder may be accepted.
BIS code “IS 15966:2013 – Refillable Welded steel Cylinder for LPG-
Procedure for checking before, during and after filling” shall also be
referred.
(a) The cylinders are passed through online washing and drying unit for
washing.
(b) Safety cap of the cylinder is removed only after the cylinder passes
through the washing and drying unit as the entry of the water inside
may damage the internals of the valve. It must be ensured that
cylinder is introduced to the filling machine only after removal of
safety cap.
(a) Wherever the tare weight stenciling is not legible on the cylinder
shoulder, tare weight is marked with a chalk on the cylinder shoulder
LPG OPERATIONS MANUAL
(a) All filled cylinders coming out of the carousel are weighed for
ensuring 100% check weighing.
(f) Filling machines on the carousal in the plant are serially numbered.
Accuracy of each electronic filling machine should be checked at
the check scale at the beginning of each shift and subsequently
every four hours during the shift operation and recorded..
Alternatively, print out of filling machine accuracy to be taken from
control room PC for review and corrective action, However, if data
logging is not provided/working the format has to be maintained
manually for corrective action. This process helps to detect any
filling machine giving incorrect quantity and necessary corrective
action is taken from time to time to adjust the machine for giving
correct quantity.
(g) A daily record should be maintained for under filled and over filled
cylinders generated in each operating shift.
8.12.1.7 SEGREGATION – I
8.12.1.8 SEGREGATION- II
a. ‘O’ ring damage is identified at AVTS / “O” Ring leak detector .For
the defective ‘O’rings identified, “O” rings are replaced with new
ones by “O” ring fixing tool and further subjected to test by AVTS.
The sound filled cylinders, passed through all quality control checks, are
then sealed at the sealing unit. As per Packaged Commodity Rules 1977,
Retail Selling Price (RSP) and Month & Year of Packaging to be mentioned
on all Non - Domestic cylinder. At this stage the cylinders are ready for
dispatch.
8.12.2.1 PURGING
Purging of cylinders is undertaken to purge air from the cylinders. If the air is
not removed from the cylinders, LPG being heavier will settle down at the
bottom of the cylinder and the air will remain at the top. During the initial
operation of the pressure regulator, only air will be released from the
cylinder and the burner will not get ignited. There is every possibility that the
consumer under the false impression may keep the regulator and burner in
open position, thereby allowing LPG to spread in the surrounding area
which may result into fire accident when get ignited.
The air is sucked from the cylinder by means of a vacuum pump and the
pressure inside the cylinder comes down below the atmospheric pressure
0.35 kg /cm2 absolute= (-)0.65 kg/cm2(g)) . The cylinder then immediately
filled with LPG vapour to bring it back to at least atmospheric pressure (i.e.
a pressure of 1.035 kg / cm2). In this process, the entire cylinder space is
occupied with LPG vapour.
8.12.2.2 STATUATORY TESTING / HOT REPAIR : (For details refer Chapter No. 9)
Cylinders segregated for statutory testing and hot repairs should be sent to
the testing plant. Record of cylinders sent to the testing plant should be
maintained.
(b) Leaky spot should be circled using paint for easier Identification
subsequently
(c) In case of a body leak during the first filling of new cylinders, it should
be segregated and the matter be referred to HO LPG Department
(Materials) for further action. Such cylinders should be scrapped only
after the investigation is over.
(f) All the leaky cylinders must be evacuated before the close of
working hours.
8.12.2.5 REJECTION
Serial No.
Date rejected.
Manufacturer’s Code / Name.
Date of Manufacture.
Reasons for Rejection.
8.12.2.6 EVACUATION :
The valve leak and bung leak cylinders are repaired as under :
The torque limit (20 Kg-M. +/- 2Kg-M.) set on screw / unscrew machine
should be verified by using a torque wrench at the beginning of the shift
and every two hours thereafter.
LPG OPERATIONS MANUAL
b. Cold Repair of Bung leak cylinder : For bung leak cylinders, the cylinder
is to be fitted with a new valve with suitable jointing compound (Teflon
tape). If the repaired cylinder, is found leaking from the bung in the
same cycle, cylinder should be scrapped after evacuation and
degassing.
Any cylinder which fails to pass periodic examination or test or which loses
in its tare weight by over 5 per cent or which for any other defect is found
to be unsafe for use , shall not be filled with any compressed gas and shall
be destroyed by flattening it as a whole or after being cut into pieces in
such a manner that the pieces cannot again be joined together by
welding or otherwise to form a cylinder, under intimation to the owner of
the cylinder, as specified in IS:8198. History sheets or records of such
cylinders shall be closed and records maintained. Reports of the details of
such closed history cards or records shall be sent to the Chief Controller, in
writing, on the 1st of January, April, July and October every year.
8.12.3.1 HANDLING
Owner’s record:-The owner of a cylinder shall keep for the life of each
cylinder, a record containing the following information regarding each
cylinder, namely:-
b) Under the statutory rules referred to above, separate license for the
plant is required for filling and storage of LPG cylinders.
d) Improper handling of cylinders not only reduces the life of the cylinders
but also creates safety hazards.
e. The safety cap should not be removed from the cylinder valve until the
cylinder is taken up for filling or any other operation. The same should
be refitted as soon as the operation is over. Safety cap should be fitted
while the cylinders are passed through the washing unit.
f. Tests for suspected leaks must never be made with naked flame.
LPG OPERATIONS MANUAL
g. For all practical purposes, empty cylinders must receive same care and
attention as given to filled cylinders while handling.
a. General
iii. The operations can be carried out after sun set hours also with
adequate Illumination and with the approval from CCOE.
not exceed the RLW fixed by R.T.O. and other local road restrictions
en route.
v. Cylinders must not be subjected to rough handling.
c) The storage area should be cool, dry, well ventilated, covered and
away from any potential source of heat. The area should also be
easily accessible
i. Filled cylinders :
Serviceable cylinders.
Segregated for statutory testing.
Segregated for hot repairs
Defective empty cylinders awaiting cold repairs.
Defective/spurious cylinders for scrapping.
New cylinders.
ST repaired / HR returned cylinders
f) All the filled cylinders MUST be stacked vertically with the exception
of body leak cylinders which may be temporarily laid horizontally.
However, this should not be done in the case of cylinders having
leakage through bungs or valves. These cylinders are to kept
vertically since the escape of LPG will be of vapour and not the
liquid as leakage of liquid LPG is more hazardous compared to
vapour leakage as explained earlier. Such cylinders, however, must
be evacuated on priority.
i) In case removal of valve is essential for longer periods, the bung hole
must be covered with a suitable plug taking all precautions to ensure
that the internal threads of the bung are not damaged ,due to
corrosion.
LPG OPERATIONS MANUAL
The filled cylinders should be stored at the plant in filled cylinder storage
shed in lots only in two highs as mentioned earlier.
a. Leaky cylinders
i. Cylinders with body leak, bung leak and valve leak fall into this
category. Cylinders should be properly identified with a marker
indicating the type of leak.
ii. Contents from all leaky cylinders should be evacuated at the earliest
giving preference to those which are leaking profusely.
iv. No leaky cylinder should be left in leaky condition at the end of the
working hours.
LPG OPERATIONS MANUAL
ii. Such cylinders should be stacked in the same manner as filled sound
cylinders described above, with the exception that the stack should
be limited to a single tier.
iii. The contents from the cylinder should be evacuated at the earliest.
ii. The new cylinders may be stored in open in a stack of 200 cylinders of
5 high (horizontally), If specified area (concrete yard) is provided in
the layout for the purpose. If no yard is available, suitable drainage
should be provided on the bottom row, to avoid stagnation of rain
water and corrosion to the cylinders. However it is advised not to
store the new cylinders in open area for a longer period and the
cylinders should be consumed on ‘FIRST IN FIRST OUT’ basis.
iii. Passage between each stack, whether stored in the covered shed or
in the open, should be left as per the standard stack arrangement,
already mentioned above.
LPG OPERATIONS MANUAL
(b) The cylinders due for hot repairs should be stacked in demarcated
area as per standard stack arrangement and sign board should be
displayed.
(a) The valve should be removed from the cylinders identified as scrap
and the cylinders should be made gas-free immediately thereafter
and before stacking.
(b) Once the cylinders are made gas free, they can be stored in open
in horizontal stacks as in the case of new empty cylinders as
described above.
LPG OPERATIONS MANUAL
8.12.4.1 GENERAL
The stake truck deployed for transportation of LPG cylinders, whether filled
or empty, should meet with the following requirements :
d. Exhaust pipe should be re-routed towards the front driver side and
should be welded with a spark arrestor of CCOE approved quality
make and design.
LPG OPERATIONS MANUAL
g. Floor of the truck body should not contain protruded nails or any other
objects which can cause a spark or damage to the cylinders
h. Every truck should carry minimum two numbers of 10 kg DCP type fire
extinguishers of BIS approved quality.
i. Master cut off switch should be provided in the cabin of the truck in a
easily accessible position.
n. The LPG cylinders shall always be transported and kept in the up-right
position and shall be so placed that these cannot be knocked over
(c) The truck MUST be parked minimum 15 metre away from the filled or
empty cylinder shed within the plant.
(d) After the truck is properly positioned, the engine should be put off
and ignition key is removed. The lights and electrical switches should
LPG OPERATIONS MANUAL
be switched off by isolating the power through master cut off switch.
The truck should be positioned in gear & hand brakes should be
applied
(e) Fire extinguishers should be positioned on the ground near the truck
for ready access of operation in case of emergency. Driver should be
available all along the loading operations.
(i) The cylinders, whether filled or empty, should not project above or
beyond the sides or ends of cage of the truck.
(j) After loading is over, check should be made for the leakage of the
gas with the help of Explosimeter and the truck should be released
after endorsing on the challan as ‘NIL leakage observed’. In case of
any suspected leakage, the leaky cylinders should be segregated
and replaced with sound cylinders.
(a) No person, other than the driver and the helper, should travel in the
truck.
(b) ‘SMOKING’, and ‘COOKING’ of food etc, MUST NOT be done in and
around the truck. No person should ride over the cylinders.
(c) The speed limit of vehicles should not exceed 40 kms. per hour. If a
lower limit of speed is enforced by Road Transport Authority or any
other Government body, the same MUST be observed.
(d) The truck should not be parked in congested area during transit.
(e) Other goods should not be carried in the truck along with LPG
cylinders.
(i) Minimum 2 Nos. of 10 kg. BIS approved DCP type fire extinguishers
should be carried in a truck in an easily accessible position (one on
either side).
(j) Fire, artificial light, or any item capable of producing fire or explosion
MUST not be taken or carried in the truck.
(l) Whenever roads or weather conditions are such that there is any
doubt with regard to the safe completion of the trip, the vehicle may
be parked safely or alternate safer route may be followed.
a. The truck MUST be parked minimum 15 meters away from the edge of
filled or empty cylinder shed.
b. After the truck is properly positioned, the engine should be put off
and ignition key removed. The lights and electrical switches should
be switched off by isolating the power through the master switch. The
truck should be positioned in gear and hand brakes should be
applied.
d. In case the filled cylinders are received at the plant from other
locations, visual inspection should be made to ensure that the
cylinders received are apparently in good condition. Wherever safety
caps are to found to be missing, quantity of short receipt of safety
caps should be recorded in the relevant challan.
(a) In case any cylinder develops leak during transit, the vehicle should
be promptly taken to an isolated open place away from the sources
of ignition. Leaky cylinders should be identified and segregated.
LPG OPERATIONS MANUAL
9.1 GENERAL
9.1.1 As described earlier LPG cylinders are manufactured as per IS: 3196 (Part-I)
2006 The new cylinders are inspected and tested by BIS officials and a
certificate of fitness is issued by them. Based on the certificate, approval is
given by the Chief Controller of Explosives, Nagpur or his authorised
representative for the use of the cylinders for LPG. As a part of the test by
BIS officials, hydrostatic tests and pneumatic tests are conducted on each
cylinder and the data of hydrostatic testing is punched on one of the stay
plates. I.e., Month and year of testing called as test dates.
9.1.2 Under the Gas Cylinder Rules 2004, after a new cylinder is initially tested at
the manufacturer’s plant, it is required to be re-tested periodically to
ascertain the fitness for further service. The period of re-test as per latest
norms is 10 years from the date of manufacture of cylinders for the
cylinders manufactured from 2nd quarter 2000 onwards and subsequently
every five years as per the approval given by CCOE vide reference No.
R.4(2) 100/2007 dated 20.08.07
9.1.3 The test for re-qualification primarily include the following as per IS 16054 :
(a) Visual inspection of cylinder body, both internally and externally; for
dents, cuts, corrosion etc.
(b) Hydrostatic test after the inspection of cylinders as per IS: 13258 at a
pressure of 2.45 MPa ( 25 Kgf/cm2) an interval of 30 seconds, after the
desired pressure is attained and the external surface is fully dried.
Observation time is minimum 30 seconds.
(c) Pneumatic test, after refitting the valve, with a pressure of 1.180 MPa
(12 Kgf/cm2 ) for an interval of 60 seconds.
9.1.3.1 For the sake of convenience, other related activities such as re-painting of
the cylinders, attending to cold repairs etc. are also carried out at the
Statutory Testing Plant.
9.1.4 The cylinders found unfit for service during the visual inspection or
hydrostatic test are rejected for scrapping. Such rejected cylinders at ST
tester are to be returned to plant for inspection and certification by
LPG OPERATIONS MANUAL
9.1.5 As segregation of the cylinders for statutory testing is done at the Bottling
plants, the testing plants are also planned in the close proximity to
minimise the expenses on transportation and also to have fast turn-round
of the cylinders.
9.1.6 The Statutory Testing Plant require the Chief Controller of Explosives’
license. The approval from the Chief Controller of Explosives is necessary
for de-gassing of cylinders and running of the plant. Further, the operation
at the plant shall be supervised by a competent person whose bio-data
such as name, qualification and experience should be sent to the Chief
Controller of Explosives for record. Qualifications must be in line with the
provisions of Gas Cylinder Rules, 2004 and future amendments
9.1.7 The Statutory Testing operation at the Plant must be done in accordance
with the Gas Cylinder Rules, 2004 and all requirements mentioned therein
must be complied with. Also New IS code for Statutory Testing of LPG
Cylinders for Periodic Inspection and Testing – Welded Low Carbon Steel
Cylinders exceeding 5 Litre water capacity for Liquefied Petroleum Gas
(LPG) – Code of Practice is under consideration of BIS. Same shall be
referred after its publication
9.1.8 As the cylinders which are stored and handled at the testing plant
contain LPG vapour, all rules pertaining to and all precautions applicable
to the licensed premises must be observed.
9.1.9 One set of Gas Cylinder Rules 2004 , BIS code in the form of Manual for
Testing of LPG cylinders in circulation, and all BIS standards referred to in
these two publications MUST be available in the testing plant.
(a) Although the dates of initial test and subsequent re-test are
punched on the third stay plate of the cylinder, segregation of the
cylinders for statutory testing based on the punched markings is not
only cumbersome but also a time consuming process. A system for
colour coding of the cylinders to indicate the age profile has,
therefore, been developed on Oil Industry basis. The system is
described in detail in Clause No. 9.2.3.
(b) As per Gas Cylinder Rules 2004, the following two conditions are
mandatory :
There is only one category of cylinder in use by the Oil Companies, i.e., one
with protected ring supported by three vertical stays.
LPG OPERATIONS MANUAL
(ii) The year of test would be identified by the last two digits of the
year. For example, figure 09 would represent the year 2009.
(iii) If a cylinder has been tested in the month of July 2009,
the punched marking shall be ‘C-09’ based on the above
guidelines.
(b) In order to indicate the next quarter of the testing, inside surface of
one of the vertical stay plates shall be painted with the appropriate
colour scheme as detailed in Clause No.9.2.4 and the next quarter
and the year of testing due are stenciled with the appropriate
colour scheme on the painted background. For example, if a
cylinder is tested in ‘C-09’, the marking on the inside of the stay will
be ‘C-14’.
However, for cylinders coming for 2nd testing, five year periodicity is
to be maintained and color change has to be done according to
the 10 year color scheme given above.
For example :
For cylinders coming for 2nd retesting in year 2013, the color scheme
for retesting for year 2018 is to be adopted.
(b) The height of the lettering shall be of 25 mm for quarter and year
of next due date.
9.2.5 The above colour coding scheme shall also be followed by the Oil
Industry in respect of cylinders in circulation due for next testing.
9.2.6 It is essential that the periodic visual inspection of marking, painting and
stamping on the cylinders is undertaken at the bottling plants to ensure
that these are legible at all times.
9.2.7 Since the stamping and marking are done at the time of re-testing, the
next due date of hydrostatic test can be easily established.
LPG OPERATIONS MANUAL
9.2.8 Statutory testing plants to stencill the next date for re-testing on the vertical
stays of the cylinders with proper colour coding as above and as such the
next date of re-testing can be easily found out from the colour coding
and marking.
9.3.2 The basic facilities provided in the Statutory Testing Plant are given below :
(a) Covered shed, well ventilated at ground level, for the storage for
cylinders due for testing and for carrying out the testing operation.
(b) Sufficient open area to store the cylinders already tested, cylinders
discarded for scrapping and cylinders already de-shaped for
disposal.
(c) Fire fighting facilities covering the covered shed and the open area.
(d) Water storage facility for hydrostatic test and Pneumatic test
9.3.3 The basic equipment required at the Statutory Testing Plant is given
below, which also incorporates facilities required as per Schedule IV of
Gas Cylinders Rules 2004 :
j. Weighing scale with least count of 5/10 gms. for weighing tare weight
of the cylinders together with the standard test weights stamped by
Weights and Measures Department
p. L1 & L9 gauges as per IS-9121 for bung/ valve pad thread inspection.
t. Painting booth for primer coat and finish coat painting of the cylinder.
(a) Before the cylinders are taken for statutory testing, the last test date
punched on the cylinder stay plates should be verified. The cylinder
should be taken for re-test only when it is due as per statutory
regulations or if the re-test is required for any other specific purpose.
(b) At this stage, the serial number of the cylinders, date of last test
and the name of the cylinder manufacturers should be checked
and recorded.
9.5 SEGGREGATION
9.5.1 All the markings of each cylinder shall be scrutinised to establish that it
complies with the requirements of IS: 3196-Part I revised 2006 and with any
other statutory requirement applying to its use. The cylinders having lost its
identity with respect to its original manufacturers, serial number, date of
manufacture and the relevant code of manufacture shall be branded
and declared unserviceable.
9.5.2 The cylinders found acceptable as per Clause No. 9.9.4 of this chapter
shall be segregated separately for hot repairs.
LPG OPERATIONS MANUAL
9.6 PREPARATION
9.6.1 Removal of Valves
9.6.2 All the cylinders shall be de-pressurised to the atmospheric pressure. The
contents shall be released in a safe manner through a high rise vent that
should be 1.5 m from the eve of the shed
9.6.3 At a time not more than 5 cylinders shall be de-pressurised. The gas shall
be cold flared by using a suitable adopter connected to a header. The
gas so collected in the headers shall be finally vented through a piping
above the roof level.
9.6.4 The adopter used for the purpose should not press the valve spindle
beyond 2.5 mm.
9.6.5 The valves shall be removed carefully after ensuring complete de-
pressurisation. While removing the valves, a suitable adopter and proper
fixture shall be used to ensure that valves, bung threads & cylinders are not
damaged. Preferably the Cylinders shall be kept vertical at the time of
valve removal.
9.7.2 Degassing should be carried out in CCOE approved site. Cylinders shall
be degassed by purging the same by inert gas, steam or by filling water till
it overflows. The water shall be retained in the cylinders for not less than
one hour to ensure that entire vapour or gas remaining in the cylinder
comes out. After emptying out the water, the cylinders shall be kept in
inverted position and be tapped gently by non-metallic hammer to
remove dust, rust or any loose remnants in the cylinders.
Pyrophoric material should be kept wet till buried in the pit and pit is
covered with earth. Pit for disposal of this sludge should be located
sufficiently away from hydrocarbon area so that the plant / Equipment is
not in danger at any time
9.8.2 While cleaning the surface of cylinder by caustic soda solution or water jet
the bung of cylinder should be closed by suitable plastic / rubber cap to
prevent the entry of foreign material, solution into the cylinder.
9.8.3 Any suitable method of surface cleaning other than the methods as
mentioned in Clause Nos. 9.8.1 and 9.8.2 may be used as agreed upon
between the owner of cylinder and testing station.
Cylinders with damaged foot ring, valve protection ring, which cannot be
cold repaired and require/can be hot repaired, to be sent for hot
repairs.,
9.9.1.2 For checking the internal surface of the cylinders, a low voltage lamp of
suitable intensity shall be used.
9.9.1.3 Before carrying out the internal inspection of the cylinders, the inside
portion of the cylinders shall be properly cleaned by using vacuum pump,
compressed / hot air and magnetic bar to remove any foreign particles
and traces of water inside the cylinders.
ii) Dent Depression in the cylinder that a) Depth of dent is greater than 1/10th
has neither penetrated nor of the mean diameter of the dent OR
removed the metal and its b) Mean diameter of the dent is greater
width at any point is greater than one-quarter of the diameter of
than 2 percent of external cylinder OR
cylinder diameter c) Dent on or adjacent to weld
iii) Cut or Sharp impression where metal 75mm or more in length or when the
intersection has been removed or depth of cut is such that the
redistributed undamaged (remaining) wall thickness
is less than the minimum calculated
wall thickness
iv) Intersecting Point of intersection of two or Rejection in all cases
cut more cuts
v) Dent Depression in the cylinder When the size of dent or cut exceeds
containing within which there is cut the dimension for rejection as an
cut individual defect
vi) Crack A split or rift in the cylinder shell Rejection in all cases
x) Footring Clearance of the body bottom a) Less than 8mm for cylinders of water
bottom from the ground. capacity upto 34 litre
clearance b) Less that 15mm for cylinders of water
capacity exceeding 34 litre and upto
50 litre
c) Less than 25mm for cylinders of water
capacity exceeding 50 litre.
LPG OPERATIONS MANUAL
ii) Arc or torch Burning of the cylinder base Rejection in all cases
burns metal , a hardened heat
affected zone , the addition
of extraneous weld metal,
or removal of metal by
scarfing or cratering
iii) Fire damage Excessive general or Rejection in all cases
localised heating of the
cylinder usually indicated
by: a)
Charring or burning of
paint1)
b) Fire damage of the metal
c) Distortion of the cylinder
d) Melting of metallic valve
parts -
e) Melting of safety cap
1) In case of superficial charring of paint cylinder may be accepted by
inspecting officer.
LPG OPERATIONS MANUAL
Cylinder shall be first cleaned from inside by using vacuum pump. After
internal cleaning, magnetic bar shall be used to remove any ferrous
particle sticking at the bottom of the cylinder surface
9.10.2 The cylinders which are having the valve pad threads worn out, not
meeting their respective thread gauges, broken at any point and rough
surface on the threads not meeting the requirements of IS-9121 shall be
rejected.
9.11.2 Any cylinder having loss of weight by more than 5% of original tare weight
shall be branded and declared as unserviceable.
LPG OPERATIONS MANUAL
The external surface of the cylinder shall be clean and completely dry so
that any leak can be detected during the test.
All pipe work, flexible tubing, valves, fittings and other components forming
the pressure system of the test equipment shall be designed to withstand a
pressure of 1.5 times the maximum test pressure of cylinder to be tested.
The design and the installation of the equipment and the cylinders
connected to it shall ensure that no air is trapped in the system.
Dedicated pressure gauges for each cylinder to read the cylinder test
pressure in accordance to relevant Indian standard shall be provided. In
addition to this 2 number of main gauges shall also be provided on the
inlet line of the equipment after the isolation valve.
9.12.3 PROCEDURE
The cylinder shall be tested at the test pressure of 2.45 MPa ( 25 kgf/cm2).
During test the pressure shall be increased gradually till the required test
pressure is reached. Then the cylinder shall be isolated from the pumping
system and the pressure shall be retained for a period of not less than 30
seconds. During the test, the cylinder shall be gently tapped with wooden/
nylon hammer near the weld joints.
The cylinder shall be thoroughly examined externally for any leak. Any
reduction in pressure noticed during this retention period or leakage,
visible bulge of deformation, sweating on cylinder body shall be treated as
a case of failure in the test.
Subsequent to hydraulic proof pressure test, water inside the cylinder shall
be completely removed. The internal surface shall be completely dried by
dry compressed air and vacuum pump. Internal cleaning and drying shall
be checked by low voltage lamp.
9.12.5 The fixtures installed for hydrostatic test shall have covered shed with
adequate illumination.
9.13 PAINTING
9.13.1 PRIMER COATING
(a) After the cylinder(s) are coated with primer, the cylinder(s) shall be left
in the air for drying. The drying time shall be as per paint
manufacturer’s/supplier’s recommendations.
(b) The signal red paint shall be based on super synthetic enamel
conforming to IS: 2932-1991 having the colour category No.23(2) Signal
Red as per IS: 2932-1991 which is also shade no. 537 of IS: 5-1991.
(c) The paint shall be of brushing consistency and suitable for application
by spraying. It is desirable that the paint is certified by BIS for its
conformity with IS: 2932-1991.
(d) Painting of 19.0 kg, 5.0 Kg & 47.5 kg Cylinders is to be carried out as per
latest guideline issued by HO.
9.14.2 While applying the primer coating and final painting, care should be
taken to ensure that the shadow zones such as surfaces under foot ring,
VP ring etc. are properly covered with paint.
LPG OPERATIONS MANUAL
9.14.4 Sufficient drying time should be provided after finish coat of enamel
painting.
9.14.5 For better results, it is desirable that both the primer and the enamel paint
are obtained from the same source.
9.15.2 The weighing scale used shall have a least count of not more than 10 gms.
and the value of tare weight may be rounded off to the nearest 100 gms.
as per IS: 2-1990. The weighing scale shall be of suitable weighing
capacity.
(a) The identification mark of the testing unit as registered with Chief
Controller of Explosives, Nagpur.
(b) The new test date retaining the previous test dates
(c) New tare weight of cylinder according to 9.16 and gross weight in,
kg, shall be punched on the cylinder stay plate while retaining the
old tare weight and gross weight. Details for punching are given in
Appendix-I.
(d) Loss in tare weight, if observed under 9.11. (within 5 percent of
original tare weight ) shall be punched at the footring. For example, if
the loss in tare weight is 200 gram, it shall be punched as LTW 200
LPG OPERATIONS MANUAL
The next periodic inspection date and tare weight shall be stenciled on the
cylinder as per the agreement between the IOC and the re-testing
agency.
9.17 STENCILLING
9.17.1 The cylinders, which are marked, shall be taken for stenciling of tare
weight, net. weight and next due date for testing. The colour coding for
stenciling of the next test date due shall be followed as detailed in
Clause No. 9.2.4
9.17.2 Size and the colour of stenciling and location on the cylinder shall be as
per instructions issued by IOCL.
9.18.2 Before the valve fixing operation, the valve pad (bung) threads shall be
cleaned by using ¾”–14 NGT cleaning tap and wire brush. Subsequently
the same shall be checked as per Clause No. 9.10 of this chapter.
9.18.3 Before fixing the valve, inside of the cylinder shall be dried out by the
compressed air. Foreign particles etc., if any, shall be removed by a bar
magnet and checked by a low voltage lamp. The cylinders after
hydrostatic test, may be internally dried using nitrogen, not at a
temperature exceeding 300 deg c and retaining a positive pressure of 2 to
3 bar, effectively preventing internal corrosion.
LPG OPERATIONS MANUAL
Each cylinder after it has been dried and fitted with valve shall be tested
for leakage by subjecting to air pressure of not less than 1.18 MPa
(12kgf/cm2) for period of not less than 1 minute .
All pipe work, flexible tubing, valves, fittings and other components forming
the pressure system of the test equipment shall be designed to withstand a
pressure of 1.5 times of the pneumatic test pressure. Proper illumination
and draining arrangement of soiled water and filling of clean water in
pneumatic tank shall be provided .
Equipment shall have facility to fully immerse the cylinder in water during
the test by use of suitable pneumatic fixture. Equipment shall facilitate
rotation of cylinder manually during the test.
9.19.3 PROCEDURE
Cylinder shall be filled with dry air up to the pressure of 12 kgf/cm2. After
that the cylinder shall be isolated from the pressure source. The cylinder
shall be immersed in water for a period of not less than 1 minute.
The cylinder shall show no leakage from the body of cylinder and the joint
between valve and bung. The test is to be carried out after fixing the
safety cap on the valve.
LPG OPERATIONS MANUAL
Any cylinder that fails the test shall be inspected for leakage cause. In
case the leakage is due to improper tightening of valve, same shall be
corrected and cylinder shall be rechecked.
After testing, air shall be removed by press opening the valve using suitable
adaptor.
9.20 CALIBRATION :
Calibration of equipment shall be carried out at periods not exceeding
the following :
9.21.2 DE-SHAPING
9.21.3 All the rejected cylinders shall be marked prominently with the paint
showing the reasons of rejection. Following codes shall be used.:
9.22.1.1 Since the cylinders received at the Statutory Testing Plants will be
different serial numbers of different manufacturers, recording and
handling of cylinders should be done with proper care to ensure
systematic and batch-wise movement of cylinders so that there is no mix
up resulting into escape of few operations. Following methods are
suggested for handling and recording of cylinders :
staff shall sign the card with date and forward the same to the next
stage.
(c) The allotment of batch number is linked with the year and month of
testing e.g. 01 A-XX which indicates 01 as the year of testing (2001),
A for the month of January, B for the month of February etc. and XX
is the control number for the month as 01,02,03,…. . This procedure
provides necessary assistance in monitoring the control on the
production as well as for easy access to a particular cylinder, if any
information is required at a later date.
(d) The LPG cylinders, which are accepted, are recorded in a format
as per Appendix No. III. The various reasons for rejection shall be
coded as given in Route Card and marked on the back of
Appendix No. V.
LPG OPERATIONS MANUAL
APPENDIX No. I
Batch No.
Old Test Date
Test Dates
XXX XXYY
APPENDIX No. II
Certificate No.:_______________________
Date:_______________
This is to certify that LPG cylinders having normal water capacity_______ litres
as per Appendix No. III belonging to IOC have been found acceptable in visual
inspection as per IS : 13258 – 2013 and Hydrostatic Test at 2.45 Mpa ( 25.0
Kg/cm2). Pressure as per IS: 3196 (Part I) 2006. These cylinders are fitted with
self closing (SC) type valves as per IS: 8737 – 1995 of type I threads (3/4”- 14
NGT of ANSI/CGA V-I-1987).
.
The cylinders rejected / recommended for hot repairs are furnished in
Appendix No. V
Certifying Authority
LPG OPERATIONS MANUAL
APPENDIX - IV
ROUTE CARD
Name Of Cylinders Testing Station
Owner Of LPG Cylinders – IOC Batch No_______________
Batch Size _________________________Date ________________
Control No. 1 2 ….
Sr.No of Cylinder
Name Manufacturers
Date Manufacturer (i.e. first Test Date )
Previous Test Date
Internal & External Inspection
Internal Inspection (OK/ Rej. )
External Inspection (OK/ Rej.)
External Inspection RT/HR/Rej.
Tare Weight Check OK/Rej.
Hydrostatic Test at 2.45 MPa (25.00kg/cm2
OK/Rej.)
Original Tare weight
New Tare weight
Bung Threads rechecked OK/Rej.
Final Inspection Of Marking ,
Painting Stenciling ,
Any Other defects Accepted /Not Accepted
Remarks if any
Name & Signature of Inspecting official ______________________________
Date of Completion _______________________
Remarks : Allotment of batch no is to be linked with the year and month of testing e.g.O5A-XX
which indicates 05 as the year of testing A for the month January , B for the month of February
etc. and XX is the control number for the month as 1,2,3Remarks : Allotment of batch no is to
be linked with the year and month of testing e.g.O5A-XX which indicates 05 as the year of
testing A for the month January , B for the month of February etc. and XX is the control
number for the month as 1,2,3
Certifying Authority
LPG OPERATIONS MANUAL
APPENDIX -V
Name Of Testing Station :
Hot repair
Certificate No. :
Date :
Certifying Authority
10
LPG OPERATIONS MANUAL
10.1 INTRODUCTION
10.1.2 The serviceability and safety of the LPG plant equipment, especially in
the long term, are affected by the standard of maintenance
undertaken. Complete information, through manufacturer’s operating
and maintenance manuals / service booklets should be available
about each type of machine and equipment in the plant. The
recommendations therein must be incorporated in the plant
maintenance schedules to ensure that the equipment is always in
good working condition and will not give unpleasant surprises when
you least expect of them. Typical schedules are available in OISD 144,
under Chapter no 9 and task list attached ( pl. click attachment of
acrobat reader )
10.1.3 Each plant should work out a similar schedule of maintenance based
on the make and type of equipment installed and also the operating
conditions and specific needs for each plant. e.g. Plant operation in
single shift would need a different schedule than the plant running in
two shifts. Depending upon the plant’s size, one or more officers should
be assigned specific jobs for inspection and maintenance.
10.1.4 To avoid rush indents and chances of plant shutdown for want of
sufficient spare parts, maximum and minimum stock levels for the spares
should be worked out and maintained. The need for adequate
inventory level of spares is all the more important, in case of spares
which are to be imported as the lead time for the procurement of such
items would be higher than that for indigenous spares.
LPG OPERATIONS MANUAL
10.2 OBJECTIVE
10.2.1 The objective of an Inspection and Maintenance Programme for an
LPG plant is to ensure uninterrupted, efficient and safe operation.
10.2.2 All equipment log books must be religiously filled to record all
performance and inspection parameters. Log books must be
maintained in standard format
10.2.3 The shift log / activity should contain a specific column detailing any
abnormal working of the plant equipment and breakdowns, observed
during the shift. The above data shall be analyzed and used for
effective maintenance management.
10.2.5 The elimination of safety hazard is an integral part of the inspection and
maintenance. As such safety is not treated as an isolated subject within
this section.
LPG OPERATIONS MANUAL
Essential Care (EC) includes preventing failure from occurring, with tasks
such as detailed cleaning, lubrication, alignment, balancing, operating
procedures, adjustments, and installation procedures.
LPG Pumps
Air / LPG Compressors
Vapor Extraction Unit
Fire Engines / Jockey Pump
DG Sets
Any other as assessed by the Plant
LPG OPERATIONS MANUAL
When the plant shut down is planned, opportunity must be utilized for
undertaking maximum number of critical maintenance activities
simultaneously. A road map / PERT chart shall to be drawn in advance.
Approval of competent authority shall be taken. Alternate supply plan
would be drawn to feed the markets attached with the Plant
undertaking a shutdown. Before proceeding for actual shutdown, it
shall be ensured that all spares and equipments, tools and tackles,
maintenance/service personnel etc. are in place. Control and
Monitoring of all activities as per the PERT Chart drawn shall be
undertaken at micro level.
10.5.2 Maintenance & inspection work should be carried out only with valid
work permits. Hot work / cold work / Height Permit / Electrical work
permits must be issued by the Plant Manager before commencement
of the job. Work permit system for hot work and cold work shall be in line
with OISD Std.105 and Electrical work permit system shall be as per OISD
Std.137. For Height permit, guidelines as detailed in the permit and OISD
Std 192 shall be complied. The Work Permit must be available at the
work site throughout the course of the job. Closing of the work permits
and proper record keeping must be ensured on completion of the job.
LPG OPERATIONS MANUAL
10.6.1 MANUALS
10.6.3 FACILITIES
Where the facilities / equipment at the plant are of special nature such
maintenance / repair jobs must be assigned to the specialists in the field
and the equipment should be re-installed in service after proper
checking and third party inspection.
10.7 DOCUMENTATION
10.7.4 A print out of the history card shall be taken out quarterly from SAP and
kept under custody of the maintenance In-charge..
10.7.6 Plant facility data base maintained at marketing division intranet shall
be kept updated at all times.
OISD STD 150 Design & Safety requirement for LPG Mounded
Storage Facility
10.9.2 The inspection should perceive any conditions, which might in any way
reduce the safety standard of the operation.
10.9.3 Remote Operated Valves (ROV) should be inspected daily for proper
operation and response time. High Level Alarm (HLA) should be
checked daily for audio-visual alarm through test button & once in six
months for proper functioning by filling up the LPG vessel under
controlled conditions. HLA should be set to actuate at 85% volume
liquid level & interlocked with the liquid ROV of the vessel i.e. in case of
actuation of HLA when liquid level reaches 85% volume, the ROV on the
liquid line of the vessel must close preventing further entry of liquid LPG
into the vessel. While carrying out the above check, fixed tube level
gauge should be continuously checked thereby ensuring that vessel
never gets overfilled even if HLA is not working properly. HLA of storage
vessels should be kept in operating conditions always.
10.9.5 Provision of Filter, Regulator & Lubricator units close to the transmitter
and ensuring proper functioning of the same will aid in smooth
functioning of the Differential Pressure (DP) gauges. Draining of water
from the impulse line of DP gauges, zero setting and comparing the
reading with servo gauge must be done daily to ensure proper
functioning of these gauges.
LPG OPERATIONS MANUAL
During the statutory testing of the vessels, all the gauging devices,
Valves &ROVS installed in the vessels shall be overhauled. Displacer
of servo gauge has to be checked once in six months for any
possible sludge or dust deposit. Measuring wire of servo gauge also
has to be inspected for corrosion, twist or any other damage and
dirt on wire drum at least once in a year.
should be open and clear. Vent stacks and protective rain cap also
should be inspected for any abnormalities.
(e) Excess flow check valves (EFCV) can be tested by closing a shut off
valve immediately down-stream of the excess flow check valve
and then venting a section of pipeline downstream of the shut off
device and connecting the line to the vent. Thereafter, the shut-off
valve can be opened rapidly causing closure of the excess flow
check valve.
(i) Unloading arms used for tank lorry decantation should be inspected
regularly to check for leakages, free rotation of swivel joints & proper
lubrication. Balancing arrangement of the (un)loading arm is to be
checked daily for free movement and it should settle at a height equal
LPG OPERATIONS MANUAL
The above tests are also required to be carried out on all Spool
Pieces which are used for connection with the unloading/loading
arms and TTs and records to be maintained separately for the same.
Each such spool piece are also required to be tagged with
identification mark which should not be changed during its service
life.
Maintaining LPG, air and water pipe lines free of corrosion, erosion,
fouling, cracks, leakages etc. is of utmost importance for healthy
working of the plant. Special attention should be given to the ends
of thread connections and to smaller size of the pipelines since rust
and corrosion in these areas can lead to rapid failure. All the
underground pipelines should be properly coated, wrapped and
protected from the environment. While applying wrapping coating,
it is to be ensured that the wrapping and coating are extended up
to the horizontal portion of the pipelines. At no place the pipelines
without wrapping and coating should touch vegetation, soil or
humid areas. Colour coding used for the purpose of pipeline
LPG OPERATIONS MANUAL
It is to be ensured that the fasteners used for flange joints are studs
of low alloy steel and in no case carbon steel bolts are used.
Fasteners of proper size and specification preferably as per
A193/A194 should be used.
10.10.3 In case complete internal and external inspection with hydrostatic re-
test is required, the vessel must be emptied, the internal pressure
reduced to atmospheric and residual vapor dispersed safely by filling
the vessel with water.
10.10.4 Any fitting that is likely to be damaged by the hydrostatic pressure must
be removed and the opening is properly closed prior to carrying out the
hydrostatic test.
10.10.5 In case the vessel entry is required for the purpose of inspection, special
precautions as applicable must be observed. Statutory regulations,
wherever applicable, for such operation must be strictly adhered to.
Given below is a generalized outline of the procedures :
(b) The vessel must be positively isolated from rest of the plant pipeline
system. This should be accomplished by the removal of valves,
fittings, or pipelines with appropriate plugs blanks fixed to the open
ends. The vessel should then be purged of LPG.
(c) Before entering into the vessel, availability of sufficient oxygen must
be ensured by checking the same with oxygen meter prior to
vessel entry. The concentration of gas must also be measured by
an Explosimeter. The measurements should be made immediately
below the manhole and then at the mid point of the vessel and at
the bottom of the vessel. Only after repeated readings are taken
LPG OPERATIONS MANUAL
(d) From the time the workmen enter into the vessel till they leave the
vessel, a person on watch duty must be posted at the manhole.
The person on watch duty must keep in constant touch with the
men within and be aware of their activities at all times.
(f) When any person is inside the vessel, the person on watch duty
outside the vessel must have means of communication to call
people for assistance, if required. In case the need arises for the
person on watch duty to enter into the vessel in an emergent
situation, he must secure a replacement for his position. The
person on watch duty must at all times have a flameproof torch, a
fresh air breathing apparatus, a lifting belt and a safety line.
Multi-port Pressure Relief Valves are so constructed that the valves may
be selectively removed and replaced, while the vessel is pressurized. It
permits the selective removal, testing and possible reconditioning of
individual valves on the valve assembly by rotation.
10.10.9 Valves attached to or installed within the vessel should be removed for
cleaning, inspection and testing. This includes excess flow check valves
& non-return valves. It is recommended that disassembly of any of these
valves should not be undertaken unless the original manufacturer’s test
and maintenance instructions are available.
10.10.10 Equipment such as pumps, compressors, etc., can be isolated from the
storage facilities and inspection performed independently of vessel
inspection. If inspection by disassembly is to be performed with the
equipment installed on site, precautions must be taken to ensure
LPG OPERATIONS MANUAL
All aboveground pipelines used for LPG should undergo hydrostatic test
for a minimum of once in 6 years. Underground pipelines for LPG should
be hydraulically tested every year. Sections of the pipeline system
should be isolated for convenience of testing. A test pressure of 125% of
maximum allowable working pressure of the pipeline should be applied
for a period of at least 30 minutes without indication of leakage.
Thickness survey of pipeline should be undertaken once in three years
and the readings must be compared with last reading and designed
thickness. If during the trend analysis, appreciable thickness loss has
been observed, frequency of survey shall suitably be enhanced.
10.10.11 Pressure testing, water should be drained off from all lines and blown
before being returned to service. Flanges disconnected during the
testing procedures should be refitted with new gaskets and studs.
10.11.1 Mounded vessels are distinct from other above ground pressuyre vessels
in that Pressure Vessels are fully contained within a mound except man-
ways and dome for nozzles on each vessel that protrude from the top of
the mound and in some Plants provided in a nozzle box enclosure and
the vessel is protected from corrosion through Cathodic Protection
system ( CP System )
10.11.2 All the regular testes as per Statutory norms and OISD Std. 128 and as
stated above, the vessels are also required to be tested for the Health
of CP System and settlement of the vessel. Following are the schedules
for inspection of mounded storage vessel including the CP system:
Plants having Mounded Vessel must have Cu-CuSO4 Half Cell (Portable
Reference Cell) for taking Vessel to Soil Potential at 12 O’clock Position
on the vessel mound where-in a PVC sleeve is provided for the same. In
case provision is not made the same is to be provided.
The polarization cells (also called Kirk Cells) through which earthing
connection of the vessels are routed to the earth pit, shall be checked
quarterly for replenishing of the liquid levels (OISD 150 -9.2 a (iv)). It
should not be allowed to go below the low level mark. Add water to
bring the solution to high level. If regular replenishment is required
LPG OPERATIONS MANUAL
One must ensure that the intended protected vessel and fittings is
effectively insulated from the unprotected side through prper
insulation/monolithic joints to prevent any leakage of CP current into
the unprotected portion.
LPG OPERATIONS MANUAL
LPG/OPS/046
LPG BOTTLING PLANT, ___________________
Date : Time :
Mains ON ON OF Reference 1 ON OF
Lowest
F F
Under Protection ON OF Reference 2 ON OF
Lowest
F F
Over Protection ON OF Reference 3 ON OF
Lowest
F F
Over Current ON OF Reference 1 Fail ON OF
F F
Unit in Auto Mode ON OF Reference 2 Fail ON OF
F F
Unit in AVCC Mode ON OF Reference 3 Fail ON OF
F F
All Reference Fail ON OF
F
LPG OPERATIONS MANUAL
LPG/OPS/047
LPG BOTTLING PLANT, _____________________
Date : Time :
1. At Reference Cell JB
Reference Voltage Bullet No : 1 Bullet No : 2 Bullet No : 3
(PSP) ON OFF ON OFF ON OFF
Ref. Electrode No: 1 V V V V V V
Ref. Electrode No: 2 V V V V V V
Ref. Electrode No: 3 V V V V V V
Ref. Electrode No: 4 V V V V V V
Ref. Electrode No: 5 V V V V V V
Ref. Electrode No: 6 V V V V V V
Ref. Electrode No: 7 V V V V V V
Ref. Electrode No: 8 V V V V V V
Ref. Electrode No: 9 V V V V V V
Ref. Electrode No: 10 V V V V V V
2. At Anode JB
Use Portable reference cell inside the mound for Testing Protected side
Use Portable reference cell outside the mound for Testing Un-Protected side
Off Potential to be noted instantaneously after switching off DC output from TR unit
10.13.3 Proper functioning of the alarm & trip devices for cavitation protection (
Pressure switch on discharge pipeline shall trip the pump in case
discharge pressure falls below set pressure during cavitation), low level
of seal coolant, seal failure alarm should be checked for proper
functioning for protection of pump and mechanical seal and prevent
any unsafe condition on account of malfunctioning of these protection
devices.. An annunciation panel with audio-visual indication for the
various alarm/trip conditions should be provided.
10.13.4 When minor repairs are to be carried out, it may be possible at times to
repair the pump installed in the system. In this case it is absolutely
essential that the valves connected to the pump are closed and
preferably locked before starting repairs. The pump must be vented of
any LPG before starting the work. Work permit system must be adhered
to carry out the repairs. After minor repairs are completed, the pump
should be carefully tested after work permit clearance to determine
that it is operating satisfactorily before being returned to normal service.
10.13.5 If the unit is removed from the system before repairs, an alternate pump
should be used and the connecting pipelines should be fitted with the
blind flanges until the pump is returned to the system.
10.13.6 Due to the relatively close fittings involved in the LPG pumps, the parts
of the entire assembly must be kept clean and free of dust, dirt or other
foreign materials when repairs are undertaken.
LPG OPERATIONS MANUAL
(c) Proper functioning of the alarm, alarm indication & trip devices
such as low suction pressure, high discharge pressure &
temperature, low lube oil pressure, high liquid level in the suction
volume bottle should be ensured for safe and efficient operation
of the compressors.. Audiovisual annunciation of the compressor
control panel for indicating the trips should be functional.
(e) Proper flow of cooling water for the compressor cylinder jacket
cooling as well as cooling for stuffing box shall be ensured. Safety
valve provided at the compressor discharge shall be tested and
serviced as per the frequency prescribed. Test date and test
pressure must be dispyed on the SRV. SRV shall be sealed in set
condition.
10.15.2 Wearing parts of the valves that need replacement are resilient seat
disc and sealing elements. Resilient materials used for sealing elements
and seat discs are in most cases compounded specifically to resist the
action of LPG. Therefore, the original equipment manufacturer’s
recommended spare parts towards replacement only should be used.
Such spare parts should be available in the plant prior to taking up the
valves for repairs.
10.15.3 Valve body thickness measurements shall be done for the valves
without dismantling for assessment of their health by using ultrasonic
thickness tester. However, thorough internal examination of the valve
seats & internals can be done only after dismantling the valves, which
may be done during the period of partial / total shut down
maintenance.
10.15.4 For detailed procedures for inspection and testing of valves and
accessories, OISD Std. 130 can be referred.
10.15.5 Other than replacement of seat discs & springs, no other repairs shall be
carried out in the safety relief valves. Safety relief valves shall be
subjected to inspection & testing once in a year.. During the visual
inspection of the safety valves after dismantling, flange condition for
pitting, roughening, decrease in width of seating surface and springs for
evidence of bending, cracking and corrosion shall be checked. For
detailed procedures for inspection and testing of safety valves and
accessories OISD Std. 132 may be referred.
10.15.6 Excess flow check valves should not be repaired but replaced, if found
defective.
10.15.7.2 While repairing or removing any of these items, the pipeline system in
which they are located must be shut off and equipment vented safely
before any repairs are undertaken.
LPG OPERATIONS MANUAL
10.15.7.5 Line valves usually require replacement of stem seals of resilient seats in
case of wear outs. Only those materials that are specifically resistant to
the action of LPG should be used for replacement.
10.15.8 PIPELINES
10.15.8.2 Usage of pipe clamps or compression type couplings for arresting the
leakages from LPG pipelines should be restricted to extreme
emergencies and should be removed and leaky / corroded sections of
the pipelines replaced at the earliest.
10.15.8.3 NDT tests like Dye Penetration Test (DP), wet magnetic particle
inspection test (WMPI), Hydrotest etc. as per code of practice shall be
carried out before re-commissioning., Hydrotest shall be carried out at
125% of the design pressure of the pipeline.
LPG OPERATIONS MANUAL
10.16.4 Within the dome of a tank wagon the following items are provided and
should be Inspected to determine that they are leak-free
(b) The Vapour Valve should be tested for gas tight seal in the shut-off
position. A plug should be available at the outlet connection. The
excess flow check valve attached to the vapour valve may be
tested by connecting the outlet of the vapour valve to the vent
system and then rapidly opening the valve. This action should
LPG OPERATIONS MANUAL
(c) Pressure Relief Valve is inspected to determine that the vent outlet
is free and clear. This operation should be performed without
exposing the inspector’s face to the end of the valve. A mirror may
be used for this purpose.
(d) Magnetic level gauge may be inspected for free movement of the
graduated tube within the opening of the gauge and holding of
the tube at the liquid level due to magnetic coupling.
(e) Sampling Valve should be tested for any leakage while in closed
condition. Rapid opening of the sampling valve, when the outlet is
connected to a vent, should lead to closure of the excess flow
check valve on the sampling-line inside the bullet. The sampling
valve may be further tested, if the liquid level within the tank
wagon is relatively low, by opening the valve slightly. If liquid
appears, the sampling line is intact. If not, it has become
disconnected or broken and would therefore needs replacement.
(f) Thermo well can be leak tested, by removing the sealing cap and
filling the well with a suitable anti-freeze solution. By observing the
surface of the liquid within the tube, it will be evident if a leak
exists. In no case water should be used for such a test.
(h) Pressure Relief valve: Discharge from a pressure relief valve could
either be due to leakage from the valve seat or the valve has
performed its intended function. In case of former, the wagon
should be unloaded after taking due precautions and Railways be
informed through tank wagon release memo. If the valve opens
due to increase in the pressure in the vessel, the reasons for the
same shall be investigated and immediate corrective action be
taken.
(i) Gauges: If the leakage is observed above the cap of the plug
of the thermo well, the connection should be tightened. If the
leakage cannot be stopped, the cap or plug should not be
removed since it is possible that the same will result in liquid
discharge. If the leakage cannot be eliminated, adequate safety
precautions should be observed until the wagon is emptied out
and depressurised for subsequent removal of the tube, by railway
authorities, for repair/replacement
Railways carry out repairs of the tank wagons. However, any defect
noticed by the plant in the tank wagons shall be intimated to railways
for corrective action.
10.17.1.1 It should be ensured that the vehicle complies with RTO and
CCOE’s regulations and has valid permits / certificates such as
load permit, registration, insurance, tax payment, fitness certificate,
etc.
10.17.2.2 The following fittings in the tank truck also need to be inspected :
10.18.1 GENERAL
10.18.1.1 LPG hoses in India are manufactured as per IS 9573. Imported LPG hoses
conform to BS 4089, section 2 of which is superseded by BS EN 1762.
LPG hoses being of flexible nature constitute a weak link in the
pressurised system. Therefore, due importance must be attached to its
proper inspection, maintenance and care while handling.
10.18.2.1 Each hose should be tested minimum once in four months as detailed in
subsequent clauses. Those hoses that are found unsuitable for LPG
service shall be disposed off. A metal tag of non-ferrous material should
be attached to each hose so that the serial number, date of
commissioning and date of testing could be conveniently punched.
10.18.2.2 The date of last test should be checked while using the hose and it
should be sent for testing if a period of four months lapses after the last
test. If a hose fails any of the tests detailed below, an attempt should
not be made to cut away the defective portion and re-use the balance
length, but the entire hose length should be discarded from LPG service.
Due care must be exercised while using, handling or storing LPG hoses
as per guidelines given in subsequent clause.
(c) Small cuts and nicks in the outer cover should not be generally
a cause for hose replacement, unless the rubber involved is
loose or the reinforcement is exposed.
(h) The hoses that pass all the above visual inspection
tests shall then be subjected to hydrostatic, pneumatic
and electrical continuity tests as described below;
hoses failing any of these tests must be discarded for LPG
service
(a) The test should be carried out at minimum once in every four
months. Hydro Test pressure is 25 kg/cm2 for a period of 5 minutes.
(b) Original length of the hose as recorded in the hose history card/data
card should be noted
LPG OPERATIONS MANUAL
(d) The end of the hose should be closed by a blank flange, plug
or cap fitted with a bleed valve. At the other end, the delivery
side of the hydraulic pump should be connected.
(e) Before applying the pressure through the pump, the hose must be
completely filled with water taking precautions to ensure that the air
is completely removed from the hose, using the bleed valve.
(f) With the hose completely filled with water, pressure should be
gradually increased at the rate of 0.1 to 0.7 kg/cm2 (g) per
second using the hydraulic pump. The pressure gauge used for
testing should be calibrated and its range should preferably be
twice that of test pressure.
(h) After releasing pressure and draining water, the straight length of the
hose should once again be measured and recorded from one end
to the other. In case a variation in length is more than 5% when
compared to the original length (without pressure) the hose should
be discarded from LPG service.
(j) After the hydrostatic test is over, water content should be fully
drained and the hose interior thoroughly dried before putting to re-
use.
(k) The interior of the hose should be inspected visually to check that the
liner is intact and there is no foreign material present.
LPG OPERATIONS MANUAL
The hose should be tested with air pressure of 3.5 kg/cm2 (g) with the
hose end plugged and submerged in water. The pressure should be
maintained for a period of minimum 10 minutes. The test should be
carried out minimum once in four months.
(a) The hose should be laid down straight on solid supports when not
in use.
(b) The hoses should be covered to protect them from sun light. Cool,
dark and dry storage space is preferred.
(c) Before returning the hose to storage after use, it should be
completely drained.
(d) The new hoses from the store should be used on ‘First-In-First Out’
basis.
(e) Care should be exercised to ensure that people does not step over
the hoses. Likewise, vehicles should not be allowed to be driven
over the hoses.
(f) Care should be exercised to avoid twisting and kinking while
handling.
(g) Hoses should not be lifted from a single point with the ends
hanging down. While lifting the hose it should be supported
at least by two slings located near the ends.
(h) Hoses should not be allowed to lie in a pool of oil or other
liquid that may affect the rubber compound.
(i) Care should be exercised to ensure that the valves are not
operated with a sudden jerk to avoid sudden increase or
decrease of pressure in the hose. Closing / opening of the valves
should be done in a gradual manner.
(j) Hoses should not be allowed to touch any hot surface.
LPG OPERATIONS MANUAL
10.19.1 GENERAL :
Critical and long lead spares should be available at all times to ensure
maximum utility and efficiency and minimum downtime in case of any
LPG OPERATIONS MANUAL
As all Plants are now provided with Electronic carousel it is very essential
to have proper electrical supply and earthing system. Each carousel
must have dedicated earth pit with no other equipment earthing
connected to the pit. The potential difference between the earth and
neutral should not be greater than 0.5 volts ( 0 Volts would be ideal ).
It is also essential that all critical spares are procured through OEM for
healthy upkeep and efficient performance of the equipment on
sustained basis.
a. The interior of the water bath should be painted white and the
bright finish should be maintained by regular cleaning and
painting.
b. Specified minimum water level must be maintained throughout
the operation. At the same time, filling of water beyond
LPG OPERATIONS MANUAL
10.20.1 Valve leak & O-ring leak is checked by using Compact Valve Tester (CVT),
Automatic Valve Testing System (AVTS) or Electronic Gas Detector. In some
Plants it is called GD-PD ( Gas detector- Pressure detector. Segregation of
Valve Leak & O-ring leak has to be done manually in a CVT. In some Plants
AVTS segregates all leaks irrespective of whether the leak is O-Ring leak or
Valve leak. Secondary stage segregation has to be further carried out
between O-ring & valve leaks and in some Plants, there are two rejection
loop downstream of the AVTS and depending upon the detection of O-
Ring defect (OD) or Valve leak defect (VD), cylinders are rejected into
respective loops for further processing/correction. Yet in some Plants, we
have GD to detect valve defect with a downstream rejection loop and
sound cylinders then proceed to PD for O-Ring defect6 heck with a
rejection loop in the downstream. Electronic valve leak detector employs
Infrared sensor or pressure sensor for detection of valve leaks. Infrared
sensor can also detect bung leak
10.20.2 Preventive maintenance schedule for each plant shall be prepared on the
basis of OISD standards, OEM recommendations and Corporation
guidelines.
Calibrate Electronic Leak detector with the calibrator. Check for valve
leak rejection at 0.5 gm/hr leakage as well as for no rejection at lower
level, say 0.3 gm/hr
10.21.1.1 The transmission sprocket must be properly aligned with the chain
conveyor sprocket.
10.21.1.2 Chain conveyors should be well lubricated with the soap solution. It is
essential to prepare soap solution as per recommended specification.
Proper mixing of soap solution only will ensure proper lubrication and
washing of dust / foreign materials from the chains and channels which
reduce wear and tear and enhance the life of chain and conveyor
channel
10.21.1.4 Telescopic loading and unloading conveyors should be checked for its
free forward and backward movement. The drive rollers should be
checked for wear and tear and if observed entire set must be replaced
instead of individual ones. Wherever tyre is used for traction, tyre
pressure should be checked regularly. Controls for the boom movement
and chain ON-OFF should be checked for proper functioning.
It must be ensured that housekeeping around the drive units are proper
with easy accessibility. Oil and water spillage around the foundation
tend to weaken the foundation and the foundation bolts then loosen up
and vibration in the machine starts leading to misalignment and
premature failure. Oil seal quality of gear box is critical for leak free
operation of the drive unit. It is preferable to purchase the same from
OEM. Coupling guards should be designed such that it can be
conveniently removed to facilitate inspection
LPG OPERATIONS MANUAL
10.21.2.1 Water level in the service water tank should be checked whether the
same is adequate. Water pump shall be checked for the development
of pressure and should be kept well maintained with proper coupling
guards, no gland leakage or corrosion.. Choked nozzles are to be
inspected and cleaned whenever necessary. Water in the water tank is
to be replaced after every shift or earlier depending on the condition of
the water. There should not be any water spillage / splashing outside
the unit and corrective action be taken, if required. Entry and exit
flappers to arrest water splash outside, shall be well maintained and
replaced regularly depending on their wear and tear.
This unit is checked for any abnormal noise and the nozzles are checked
for choking and correct, wherever necessary.
The check scale of this unit should be checked at the beginning of the
shift and then every two hours. The records of the same must be
maintained thereof. The FRL should be checked for pressure regulation
LPG OPERATIONS MANUAL
and oil carryover. The check scale should be checked at various loads
with standard weights. The corrected cylinder should be counter
checked with post filling check scale. The pneumatics and electronic
interlocks should be checked for operation. It is worth mentioning here
that correcting overfilled or underweight cylinders is a repair work and
accurate working of this scale will enhance the productivity of the plant.
At some of the plants Weight Reduction Unit has been installed in place
of weight correction unit. In weight reduction unit, it is to be ensured
that some amount of product is taken out from each of the cylinders.
The proper functioning of pneumatics is to be checked for operation.
However, installation of Weight reduction unit should avoided due to
the fact that introduction of part filled (heavier cylinders) into the
carousel increases the wear and tera of the carousel table and also
reduces productivity when compared to Weight Correction Unit.
The unit should be checked for its proper operation. Centring and
Lubrication of the pneumatic parts should be ensured.
10.21.7.1 In most of the plants, fixed type and portable hot air sealing has been
provided where PVC seals are used. Flame-proofness of such system
should be maintained. Thermostat cut-off should be tested periodically.
Whenever one of the two thermo couple is removed for maintenance,
it must be ensured that the thermo-well is plugged to prevent any
accidental leakage of hot air into the control panel in case of any
puncture of thermo-well. In no case should one tinker with electronics
that would jeopardize the FLP characteristics of the equipment. Thermal
insulation of the heated parts and surfaces should be well maintained
to prevent any hot burn injury. Pnematics and centering should be well
maintained for smooth operations.
10.21.8.2 The sight flow indicator, NRV, excess flow check valve, pneumatically
actuated valves should be checked for operation. It is very essential to
maintain earthing and bonding of evacuation guns and the unit as a
whole. The unit should not be operated at all, if there is any break in
bonding within equipment. All pipes, fittings, flanges, studs and nuts shall
be of standard ratings.
10.21.8.3 At some of the plants, Auto Evacuation Unit has been installed along
with auto changeover system in the evacuation bullets. Proper
functioning of auto changeover system should be ensured as its failure
may lead to abnormal high level of product in evacuation tank. High-
LPG OPERATIONS MANUAL
level alarm installed in Evacuation vessels shall be checked for its proper
working. Hoses of the auto evacuation unit shall also be tested at the
interval given above and records shall be maintained.
The hoses should be thoroughly checked. The guns should be free of any
leakage. The unit should be properly earthed. Vent pipe shall be 1.5 m
above the eve of shed and the mouth shall be effectively earthed
Check gearbox for the correct oil level, if gearbox is filled with
lubricating oil. Centering of the socket should be periodically checked
to avoid any damage to the valves. The pneumatic valves should be
lubricated at all times. The torque cut-off should be checked
periodically (at the beginning of shift and thereafter every two hours)
with a torque wrench and if any variation is observed, the same should
be corrected by adjusting the control unit. Flameproof fittings and the
glands should be checked for their integrity. PM schedule as per task list
should be adhered to.
10.21.11.1 The check scale should be checked with the standard weights at the
beginning of the shift and prior to carrying out RQC. A trained person
should calibrate the scale before it is offered for annual stamping to
Weights and Measures inspector. Pneumatic circuits and lifting table
shall be checked for proper functioning.
10.21.12.1 The unit should be checked for proper operation. The pump and motor
should be checked for abnormal vibrations. The water used for de-
gassing should be changed periodically. The FRL should be checked for
proper functioning. The gear should be greased. The universal joint
should be checked for any leakage. Earthing of the unit should be
checked regularly
10.22.1 The weigh bridge should be checked and stamped once in a year by
Legal Metrology department and shall be internally calibrated on quarterly
basis or earlier case of abnormal variation in the weights is observed.
Calibration records shall be maintained at the Plant. The standard weights
should be kept around the platform and uniformity of reading should be
observed. The weigh bridge should be stamped annually by the Weights &
Measures Inspector. The earthing of the weigh bridge should be inspected
regularly. User interface unit should be checked for proper connections
and functioning of display, keyboard, etc. Printer attached to the unit
should be serviced periodically.
Plant are now being provided with air cooled Screw Air Compressors
with VFD ( Variable frequency drive). As these compressors are
lubricated, care must be taken for regular inspection of oil filters for
leakage, clogging etc. to prevent excessive oil carry over to the Air
driers. OEM recommendation as given in the O&M manual of the
equipment must be followed for preventive maintenance.
10.23.4 Air Leakage should be bare minimum in the pneumatic system. Efforts
should be made to peg down the overall leakage in the system to 10%. The
overall leakage can be calculated by conducting a test during off day
when none of the equipment is running. Compressor shall be run after
keeping all the equipment idle with the supply of air on. The ratio of
loading time of the compressor to total loading and unloading time
represented as a percentage is leakage in the system. If this percentage is
more than 10 %, the individual equipment may be isolated to study the
improvement in leakage. Exact leakage area identified should be taken
for maintenance.
LPG OPERATIONS MANUAL
The fire fighting system in the plant consists of fire water system and fire
extinguishers.
a. The tank should be checked for any rusting, sinking, bulge etc.
b. The roof of the tank must be checked for clear gooseneck and
availability of SS wire mesh at the opening.
c. The gauging device must be free.
d. It should be ensured that the annular plate at the bottom of the
tank is clear of any water, deposits or concrete.
e. Full thickness of annular plate must be exposed with outward slope
of the tank pad from the bottom of annular plate.
f. There should not be any gap between the annular plate and the
pad.
g. The tank must be earthed at two places.
done near the weld joints. OISD Std. 129 shall be referred for inspection
of the fire water storage tanks
The Fire water reservoir / tank (ground level) should be cleaned once in
six months or as and when needed so that there shall not be any foreign
particles / fungus / vegetation in the reservoir. It should be checked for
leakages in the reservoir.
The diesel tank of the fire engines should be kept full at all times .The
capacity of diesel tank shall be for running fire engine minimum 6 hours.
The diesel tanks of Fire Engines and also DG sets shall be away from the
exhaust to avoid possible fire. There should not be any leakage of diesel
or water anywhere. The diesel tank breather should be checked for any
possibility of choking and kept clean at all times.
that there are water leaks in the water system. Alignment of motor with
pump, condition of starter contactors and availability of coupling guards
should be checked regularly.
The operation of the jockey pumps and fire engines are automatic. This
automation is achieved by the pressure switches that sense drop in the
line pressure. The set pressure of each engine and Jockey Pump should
be verified by gradually reducing the line pressure through draining. Set
point of pressure switches should be adjusted, if necessary.
10.28.6 STRAINER
The strainer of the pump inlet and inlet of deluge valves must be
inspected and cleaned once in a quarter.
The belts of the compressors must be checked for proper tension. The
compressor must develop the required pressure recommended for
Deluge Valve system and stop thereafter.
10.28.8.1 The ring main shall be kept pressurised and pressure at the farthest point
should be minimum 7kg/cm2 (g).
The pipeline should be inspected for proper rest on the supports and
should not hang over the supports. The damaged supports, if any,
should be immediately repaired to avoid any stress on the pipeline. The
underground pipeline must be wrapped for corrosion protection. The
water in the pipeline must be flushed at least once in a fortnight to
prevent corrosion due to bacterial action. The thickness test of the
above ground lines must be done once in a year.
10.28.8.3 All the valves on the ring main / hydrants / monitors shall be checked for
leaks / operation and lubricated once in a month. All the valves,
hydrants, monitors, sprinkler nozzles should be numbered for easy
identification and maintenance. The sprinkler nozzles should be
checked for free flow, spread and discharge.
10.28.8.4 All deluge valves and sprinkler system shall be operated and checked
once in a quarter for correct remote operation, performance of each
nozzle and effectiveness of the system in total. The sprinkler system in the
sheds shall be tested for correct remote operation once in a quarter by
closing the outlet of the deluge valves. The strainers provided in the fire
water sprinkler system shall be cleaned once in a quarter and records
maintained.
Fire hoses should be periodically inspected for any leakage and other
damages. 25 % of the total hydrant hoses required should be kept as
spare. Hose boxes should be installed at each hydrant point. Each hose
box should have two numbers of hoses and one branch pipe nozzle. The
hose box should be well maintained and numbered. The hose should be
dried completely after use before it is rolled back for placement in hose
box. The new hoses should be checked periodically for fitness.
10.30.1 The sensors must be free of dust, moisture or cobwebs. The sensors
should be calibrated once in a quarter. Day to day record of sensors
activated should be reviewed and necessary corrective action must be
taken.
10.30.2 Calibration and testing must be carried out in line with OISD Std. 144.
Calibration of sensors must be carried out quarterly through test gas and
monthly for audio visual indication at control panel by activating the
sensors by releasing LPG at the sensors in controlled manner. Records
shall be maintained for calibration and testing.
LPG OPERATIONS MANUAL
Electric siren must be operated once in a month for its proper operation.
The sound should be heard at a distance of one km. from the periphery of
the plant. In case sound is not heard, the siren should be repaired or
replaced.
Manual call points must be tested once in a month for its proper
functioning.
The NRV on the blowers discharge of the two blowers including standby
should be properly checked for its functioning to ensure that during
running of one blower , it should not take atmospheric suction from the
discharge of standby blower, reducing effective suction of the blowers
the floor ducts.
LPG OPERATIONS MANUAL
For more details on Personal Protective equipment, OISD Std. 155 Parts I
& II may be followed.
10.35.2 Detailed procedures and checklists for various electrical equipment are
available in OISD Std. 137 and also covered to some extent in OISD
Std.144 section 9. Plants must also comply with the requirements of IE
LPG OPERATIONS MANUAL
Double pole is the first point where HT line is connected to the plant
electrical system. In some of the plants, the double pole structure is
located outside the plant periphery. Area surrounding the double pole
structure should be maintained free of dry vegetation and easily
accessible. Frequent checks should be carried out to see that the dipole
earthing of the dipole structure and the fence provided is proper. The
Gang Operated switch should also be earthed and Operating handle
must be properly insulated. Drop Out ( DO )fuses should be used instead
of exposed wire. Only authorised entry should be permitted.
HT breaker and panel are generally of minimum oil circuit type (MOCB)
or vacuum circuit type (VCB). General cleanliness, proper weather
protection, dust and vermin-proofness, availability of control supply,
accessibility for maintenance and operation, functioning of meters,
indication lamps and correctness of relay settings, etc., are to be
checked on a regular basis. Tripping circuit of the HT breaker shall be
regularly checked through simulation from the Relays/contacts
connected to the breaker. MOCB should be observed for oil leakages.
10.35.5 TRANSFORMER
Daily checks shall be carried out for oil leakage, oil level, and condition
of silica gel, oil and winding temperatures and general cleanliness of the
transformer. In case the transformer is of the outdoor type its fence
should be earthed. There should not be any vegetation in and around
the fence.
Dielectric strength and acidity of oil samples shall be tested every year
and filtration of oil should be carried out in case the dielectric value is
lesser than the permissible value. Bucoltz relay, oil and winding
temperature alarm and trips should be tested once in a year.
In the panel room as well insulating mats as per IS:15652: 2006 should be
provided.
Inspection for air circuit breaker consists of checking for rack in out
mechanism, operation of safety shutters, protection, control, Interlock
circuits, breaker closing and opening time. Tripping circuit of the HT
breaker shall be regularly checked through simulation from the
Relays/contacts connected to the breaker.
10.35.8 RELAYS
Secondary injection test for protective relays should be carried out once
in a year. It is also suggested to carry out primary injection test for over
load relays of major equipment. After relays are calibrated and put
back in the system, a simulation check for the tripping circuit should be
carried out by manually triggering the relay
Diesel Generating Set should be started daily and the parameters like oil
pressure, coolant temperature, frequency and output voltage be
checked. Daily checks should be carried out for the diesel engines for
ascertaining the coolant level in the radiator, engine oil level, fuel level
in the tank and condition of batteries. Water and sediment should be
drained off daily from the fuel tank. Functioning of protective devices,
such as high coolant temperature and low lube oil pressure trip devices
shall be checked once a week. B checks and C checks should also form
part of Plant Preventive Maintenance Schedule.
The equipment shall be checked for any abnormal noise and increase in
the temperature. Earthing connection shall be checked periodically.
Alignment of the engine to the alternator and insulation resistance shall
be checked half-yearly.
10.35.10 MOTORS
10.35.11 CABLES
All flange joints in the pipelines should be first bonded. The pipeline
system should be earthed at least at two points preferably towards the
ends.
Similarly different sections of the conveyors & rail tracks within the gantry
should be bonded and connected to earth grid at minimum two places.
The area wherein the earth connection is provided should be free of
paint & rust.
General cleanliness, specific gravity & level of electrolyte for the cells,
condition of terminals, blockage of the vent plugs & cracks on the
containers shall be checked in the batteries. Application of petroleum
jelly on terminals helps in avoiding sulphate formation on the terminals.
Record of specific gravity of each cell of all batteries must be kept to
know the health of batteries.
10.36.1 Major areas to be inspected in the buildings are mastic flooring of filling
/ filled cylinder / cold repair sheds, structure columns and flooring of the
other sheds, concreted surfaces around the LPG storage vessels,
compound walls, concreted area around the weigh bridge etc.
Inspection of these facilities can be done by visual checks. In the pump
house, the floor should not have water or oil accumulated on it. The
buildings should not have cobwebs and should have pleasing
appearance. Mastic flooring provided on the shed floors and
fireproofing on the columns should not have cracks etc. Top of the
sheds should not have openings / leakages. Rainwater accumulation at
the open areas in the plant should be prevented by providing proper
drainage. Drains in the plant should be kept free of muck / mud at all
times.
LPG OPERATIONS MANUAL
10.36.2 The open space within the licensed area should not have grass /
vegetation growth which affects the pipelines laid thereon. Presence of
dry grass should be avoided at all times, since the same provides fuel for
fire. Scrap accumulation within the operating areas should be avoided,
since it can affect the operation during emergencies. Facilities that are
redundant must be dismantled and area be cleared.
10.36.5 Roads and other asphalted surfaces should have proper slope to avoid
accumulation of water. Vegetation growth should not be allowed on
both sides of the roads. Potholes should be repaired immediately so as
to avoid further damage. Road should not be used as places for
preparation of materials for concreting.
10.36.6 Structures of the towers should not be allowed to corrode and rust.
Visual inspection checks for verticality of tall structures and thickness of
steel members should be done on a routine basis. Growth of grass and
vegetation around the structures should not be allowed.
10.36.7 Timely painting of all buildings & structures after proper surface
preparation will go a long way giving good appearance and ensuring
longer life.
LPG OPERATIONS MANUAL
10.37.2 Inspection and maintenance of level gauges used in the LPG storage
vessels have been covered under Product transfer facilities.
10.38.1 These terminals are akin to a process Plant with Distributed Control
System (DCS), having heater exchangers, condensers and Steam
boilers, DM Plant, refrigerated LPG Storage tanks storing
Propane/Butane at their boiling point etc. M&I of such plant I not
covered in this manual. M&I shall be carried out as per the various
codes and standards applicable to the various facility at the Plant.
11
LPG OPERATIONS MANUAL
11.1 GENERAL
11.1.2 To achieve better control over the product stock and loss control within
the plant, it must be ensured that only competent persons measure,
calculate and record all the stocks carefully, accurately and in
conformity with the standard procedures. It must also be ensured that
proper security arrangements and operating practices given in the
previous chapters of the manual are enforced in the plant to keep the
real losses/gains to the barest minimum.
11.2.1 LPG bulk and packed stock levels should be maintained within the
limitation of available safe storage capacity, which in turn should be
related to the estimated market demand and forecast for supplies. In no
case the stock levels should be in excess of the CCOE licensed
capacity.
11.2.2 The Plant Manager should ensure that sufficient stock of the product
and cylinders are available to cover the expected sales and stock-
transfer.
LPG OPERATIONS MANUAL
The sample format for Gauge Book is given in the Annexure No.12
(b) Stock held in bulk vehicles reported at the parking area of the
plant awaiting delivery/collection should be recorded in the Daily
Activity Report.
(e) Plant Manager should periodically cross check that the gauge
book readings and data uploaded in SAP/ AC2A are the same
LPG OPERATIONS MANUAL
11.3.2 The maximum quantity of the product which may be stored in each
vessel should be worked out and entered in the vessel’s calibration
tables and stock control records. The maximum safe storage level must
not be exceeded (in practice. This is achieved by filling the vessel only
by setting of ‘High Level Alarm’ which is normally set at 85% of water
capacity of the vessel.
11.3.3 The Plant Manager should analyse stock loss/gain and take necessary
corrective actions. In case of any abnormal stock loss/gain, the same
shall be intimated to state office by the Location In Charge..The
analysis of stock loss/gain data will enable the Plant Manager to ensure
the following:
As per OISD Std 144, LPG storage vessels shall be provided with 2 level
measuring gauges for monitoring the stocks in vessels. Both the level
gauges are expected to be in working condition and in case one level
gauge fails, stock monitoring is to be done through other level gauges.
11.4.2 The Plant Manager should ensure that sufficient stocks of serviceable
empty and filled cylinders are available at the plant to cover the
anticipated sales, deliveries and stock transfers. These stocks should be
related to the available cylinder filling capacity, number of cylinders,
packed trucks and the efficient operation of the plant. As a general
guideline, empty cylinders to cover 4 hours bottling and filled cylinders
equivalent to 2 hours bottling should be kept in stock. However, stock
of filled cylinders should be limited to the licensed capacity .
11.4.3 New cylinders (before purging) procured for enrolment should be kept
on a strong cement concrete floor (not covered) and replenishment
against the depleted stock should be made good from time to time.
Planning should be made to avoid aging of new cylinders in the open
storage. Unserviceable cylinders found in the receipt of empties should
be evacuated, de-gassed and kept in the open space for inspection /
certification by the competent authority for scrapping. Disposal of the
scrap should be done quickly to avoid accumulation. Buffer stock of
LPG OPERATIONS MANUAL
11.4.4 Report of physical stocks of cylinders giving the following details should
be maintained on daily basis. Category of 14.2 ,19.0, 5.0 and 47.5 Kg.
inventory of cylinders . oil company wise should be maintained
separately. Daily Physical inventory of all cylinders are to undertaken by
Security in the night shift and submitted for review to Plant Manager.
Monthly Physical inventory is to be done jointly by Security personnel,
one Officer nominated by Plant Manager and Finance Officer and
certified by each of them at the end of the inventory.
11.4.6 Accurate and up-to-date record of cylinders of different types and sizes
should be maintained at the plant
LPG OPERATIONS MANUAL
(b) Detailed calculation is enclosed for 14.2 Kg. cylinders for purging
vide Annexure No.13. Around 200 gm per cylinder should be
considered as purging quantity. While doing statutory testing (ST)/
hot repairs (HR)/ scrapping, the cylinders are de-gassed. All the
new, ST completed and HR completed cylinders are to be
purged with LPG,
(c) While carrying out 5 year testing of storage vessels, utmost efforts
to be made to recover LPG vapor, by vapor compressor and
venting of vapor to be as minimum as possible. For calculation of
stock loss, in carrying out 5 year testing of storage vessels, due to
venting of vapor, vapor pressure of 2.0 kg/cm2 be taken for 15%
of the vessel volume.
LPG OPERATIONS MANUAL
(d) All instruments are provided for each function and it is used,
installed and maintained properly and efficiently.
(e) To keep the knowledge alive and useful in day to day working,
the Plant Manager should share the knowledge by conducting
meetings and carrying out quiz tests from time to time.
11.5.3 As is prevalent in other petroleum products, losses / gains of LPG fall into
two categories :
11.6.3 To minimise the product losses / gains and for safety reasons, water and
other contaminants must be drained off carefully from the storage
vessels as detailed in Chapter No.7. The quantity of water drained
should be assessed and recorded in the gauge book.
11.6.7 It should be checked that all receipts (tank wagons, tank trucks etc.)
tally with the quantity as per the supply documents. Booking of losses /
gains is to be done as brought out in the section.
11.6.10 Monitoring and controlling the transit loss is very highly important. It
shall be ensured that the bullet tankers are weighed before and after
unloading by designated officers . The officer weighing the bullet
tankers shall take the print outs of weighment slips and the weighment
slips shall be signed. The signed weighment slips shall be preserved
safely and kept under safe custody. Transit loss shall be monitored
continuously and corrective actions taken then and there. Loading
locations and Regional LPG to be informed in case of transit loss,
besides taking possible corrective actions by plant. Calibration of
weighbridge to be done quarterly and record maintained.
11.7.2 Apparent losses / gains in LPG operations are usually due to the
following reasons :
(a) Not accounting for the liquid equivalent of LPG vapour (LEV) held in
the system. Sample calibration chart considering LEV for 14 M & 18
M dia Horton Sphere is given in Annexure No.14.
11.8.2 For the effective control of the stock and deliveries / receipts, the
practice necessitates accurate determination of the volume, weight,
temperature, pressure and density and also correct recording and
correct calculations / conversion. However, accurate measurement
begins with the accurate calibration of the tanks, meters, gauges etc.
Many of the procedures applicable to the measurement of general
petroleum products also apply to LPG, but the following points are
peculiar to LPG:
(c) LPG is to be measured both in liquid and vapour forms, but the
method / equipment used must differentiate between them,
e.g., vapour must be excluded from the liquid, if the accuracy is
required.
(f) The quantity of vapour above the liquid phase in the storage and
the transport vessels can be significant in relation to the liquid
volume.
(h) At tank wagon loading locations, the tare weight of the empty
tank wagons should be taken after purging of the tank wagons for
newly inducted, re-tested POH wagons.
LPG OPERATIONS MANUAL
(b) The ‘liquid equivalent’ of the vapour in a vessel half full of liquid at
30C is approximately 3% of the liquid contents but for the same
vessel one quarter full (at 30C) the ‘liquid equivalent’ of the
vapour rises to approximately 10% of the liquid contents. All LPG
storage vessels should, therefore, be provided with at least one
thermometer located in each of the liquid and vapour phases.
LPG OPERATIONS MANUAL
.
(b) Pressure Gauges are also useful for operational control purposes
as they provide details of the pump differential pressures and thus
performance. They can also give warning of the incorrect
opening or the closure of the valves or pipeline / equipment
failure during the operations.
(d) Operators should be trained for the use and correct reading of
the gauge.
(a) Bulk stock quantities in weight unit can be worked out from the
volume measurement, only if the density of the product is known.
Dispatching location should ensure that the dispatch document
carries quality certificate containing the details of density,
composition etc. along with the invoice. The unloading location
to take up with the loading location periodically for quality
certificate in case the same is not received along with invoice .
(b) Since the density has a major role in determining the stock, online
precision equipment suitable for LPG application for measuring
the density and temperature should be provided.
LPG OPERATIONS MANUAL
(a) Although mass flow meters are sufficiently accurate for the stock
control purposes, their accuracy is inadequate where the safety
controls are concerned. For example, a meter may show that a
quantity of 10m3 has been pumped into the vehicle, but will not
show when the vehicle has been filled to its maximum safe level,
which is the function of the maximum ullage gauge.
(b) Meters can be relied upon to measure the quantities with the
required degree of accuracy only when incorporated in a
properly designed and maintained system which include the
following :
i. the meter
ii. a fine mesh strainer to catch small particles
iii. automatic vapour eliminator to remove the vapour to avoid
false reading
iv. a back pressure / differential valve to prevent vapourisation
of the product.
(c) The above units are normally included as a part of the meter
package. To work satisfactorily, meter system should meet the
following design requirements :
11.11.7 WEIGHING
(i) the storage vessel has been accurately calibrated and its
calibration table is correct.
(ii) the level of liquid in the vessel is measured and recorded
correctly.
(iii) the meters used are correctly installed, calibrated and used.
iii. the temperatures of both the liquid and vapour are properly
determined or in the case of temperature compensated meter,
the correct coefficient of expansion is applied to the
compensating device.
viii. ASTM-IP Petroleum measurement tables are suitable for the use
with computing aids and are prepared in order to provide the
required degree of accuracy. The use of these tables is,
therefore, desirable for the conversions instead of any abridged
tables or other short-cut methods.
11.12.3 CALCULATIONS
(a) GENERAL
Example : 1
90 x 1000
= ——————
560
= 160.714 m3
ii. For the weights in air, multiply the weights by the factors for he
volumes as per the unit weight given in the appropriate ASTM-
IP tables (i.e. No. 56 of Metric edition). Weights obtained by
direct weighing (i.e. weight of LPG in a cylinder) are the
weight ‘in air’.
LPG OPERATIONS MANUAL
Example : 2
Enter the ASTM-IP table no. 56 with 0.560 Kgs./Litre density under
“Density at 15C column and note that the volume occupied by
1 metric ton (under ‘Litre per Metric ton’ column) is 1789.3 Litres.
Example : 3
at 15C?
Example : 4
Step : 1
Vapour volume = water capacity of storage vessel minus volume
of liquid LPG@ 30C = 1420 — 570 = 850 m3
Step : 2
Convert the vapour volume at 30C and 6 Kg/cm2 pressure to
NTP ( i.e. Normal Temperature and Pressure ) where the
normal temperature is 5C and normal pressure is 0 Kg./cm2..Using
the following formulae.
P1 V1 P2 V2
———— = ————
T1 T2
where
P1 = Observed gauge pressure + atmospheric pressure (i.e. 1.0335
Kgs./ cm2 )
V1 = Volume of vapour at observed temperature (i.e. 300C)
T1 = Observed temperature + 2730C.
P2 = Zero pressure in the vessel + atmospheric pressure (1.0335
Kgs./Cm2)
V2 = Volume of vapour at150C and zero pressure
T2 = 150C (Standard Temp.) + 2730C
LPG OPERATIONS MANUAL
P1 xV1 xT2
Therefore, V2 =
T 1 xP 2
(6.0 1.0335) x(1420 570) x(15 0 C 273 0 C )
=
(30 0 273 0 C ) x(0 1.0335)
Step : 3
Using liquid-vapour ratio of 247.7: 5498, vapour volume at zero
gauge pressure and 150C would work out to liquid equivalent of :
Example No. 5
Step — 1
Step — 2
Step — 3
Step — 4
Using ASTM—IP table No. 56 work out W.R.F (Weight Reduction Factor)
for LPG having density of560 @ 150C. Against the reading of 560, a figure
of 558.9 would be observed ‘gm/m3’.
LPG OPERATIONS MANUAL
Step — 5
To arrive at weight of total LPG in the vessel, multiply the total volume at
150C (Step No. 3) with W.R.F. (Step No.4).
11.13.2 CALIBRATION
It should be ensured that all vessels are calibrated and that the certified
calibration tables for each storage vessel are available. If the accuracy
of any calibration is in doubt, then re-calibration should be considered.
(b) The volumetric vapour content of the vessel for any given liquid
content can be obtained by subtracting the liquid volume from
the total volumetric capacity of the vessel, which should
appear on the calibration table.
(a) For accurate and effective control of stocks and losses / gains
the Plant Manager must compile and maintain complete control
documentation. The documentation should include bulk receipts,
deliveries, stock transfers and cylinder receipts, deliveries, and
filling as applicable. Sample format for daily stock loss / gain
analysis is enclosed in Annexure No. 16.
The information required for stock and loss control at plant is based on
the following :
LPG OPERATIONS MANUAL
i. For each vessel, calculate and record both the liquid and
vapour volume at observed temperature, using the
measurements and calibration tables. For each vessel, record
observed temperature of both liquid and vapour, the pressure
in the vapour phase and density of the liquid. As temperature
gauge is not provided in the vapor phase of storage vessel,
temperature reading of liquid LPG be taken as the base for
vapor temperature. Density of LPG for calculation purpose to
be taken as 0.54 gram/cc irrespective of variation in
temperature and density of LPG, to ensure uniformity, in stock
calculations. LEV to be arrived at and recorded in the gauge
book on daily basis for all LPG Plants. Each plant to arrive at
stock accounting as above.
iv. (For each vessel calculate and record the total volumetric
quantity at standard temperature (liquid + liquid equivalent of
vapour)
v. For each vessel calculate and record product weight from
total volume.
vi. Record the day’s bulk receipts (through pipeline, tank
wagons, and tank trucks).
vii. Summarise and record the day’s deliveries/transfers.
viii. Calculate and record the day’s total loss / gain. Any
ix. abnormal loss or gain should be promptly investigated.
QUALITY CONTROL
QUALITY CONTROL OF LPG IS MORE
IMPORTANT FROM SAFETY POINT OF
VIEW THAN ANYTHING ELSE BECAUSE
CONTAMINATION OF LPG ; SPECIALLY
WITH WATER ; IS A SERIOUS
SAFETY HAZARD
LPG OPERATIONS MANUAL
12.1 GENERAL
12.1.1 The quality control assumes all the more importance where more
than one grade of LPG is stored at the same plant / location.
Presently, at any bottling plant, only one grade of LPG is being
stored / handled. It is likely that in the coming years, it may be
required to handle more than one grade of LPG at the same plant.
It is with this background that the details of various aspects of
quality control of LPG are covered below. Many of the measures
described relate to the plants handling single grade LPG also.
12.1.3 This chapter covers not only the quality control of bulk LPG but also
random quality control of filled LPG cylinders which is very vital
both from safety as well as customers’ satisfaction point of view.
12.2 OBJECTIVES
12.2.1 Uniform Quality Control procedures are to be evolved for handling
LPG at following places:
12.3 PURPOSE
12.3.1 The purpose of the procedures outlined is to ensure:
12.4.4 All those associated with the delivery of LPG bear the responsibility
to ensure that the product is delivered in a clean and good
condition meeting the relevant quality standards. Delivery of “Off
Specification / contaminated Product” should not be made.
12.6 DOCUMENTATION
12.6.1 All quality control activities are to be documented and duly
reviewed by the Plant Manager and the documents are to be
preserved for a period of one year for the next annual inspection.
(c) (In case the quality of LPG fails in any of the characteristics,
the same shall not be released for despatch. The quality of
the product must be corrected by re-processing, before
releasing the product.
(e) The water from the storage vessel shall be drained off daily to
ensure that the product is free of water and the observation
shall be recorded. Water draining shall be done as per the
procedure given in Chapter No. 6.
LPG OPERATIONS MANUAL
(b) The tank truck and Tank wagon in which the product is to be
loaded shall be checked for compatibility of the same e.g.
the vessel in which propane is to be loaded should be of
propane rating. However, presently in LPG bottling plants,
propane alone is not handled.
(b) After loading the product, the sample shall be drawn from
the individual tank of the tanker for retention and conducting
tests, if required, in case of any dispute in the quality. Two sets
of each sample shall be drawn as follows :
ii. From the individual tanks of the tanker jointly taken with
the Master of the tanker. One set shall be retained with
the Marketing Company and the second set shall be
handed over to the Master of the tanker for handing
over to the receiving company at the disport.
(c) All the sample(s) shall be retained, till the quality of the
product is established at the disport or maximum up to 30
days, whichever is earlier. In case of failure in the quality of
the product either in the pre-discharge test or batch
formation test, the sample shall be retained till further advice
from the Controlling Office.
(b) Before discharging the import cargoes, the load port quality
certificate shall be verified with contractual specification.
1) Vapour Pressure
2) Copper strip corrosion
3) Volatility* (See Note No. 1&2)
4) Density
LPG OPERATIONS MANUAL
Note 1: In case the load port quality certificate indicates the test
only for the gas composition, the volatility test shall be
carried out in line with BIS specification IS: 4576-1999 and the
test method. If the product meets the limit of this
specification, the product shall be discharged.
(c) In case the product fails in the volatility and the supplier has
certified in respect of gas composition only, the laboratory
shall carry out the gas composition test as per either of the
following test methods:
(d) If the product is not cleared for discharge, the detailed test
results along with pertinent information shall be
communicated to the Controlling Office and HO Shipping
Department immediately for necessary advice. Meanwhile,
without loss of time, 3 sets of fresh samples shall be drawn
jointly with the representatives from the concerned agencies.
LPG OPERATIONS MANUAL
(a) After tanker discharge, the product shall be tested in line with
BIS specification. In case the product does not meet the
specification, necessary corrective action shall be taken in
consultation with Controlling Office/ Quality Control
Department to ensure release of the product to the market as
per BIS specification. In case dosing is done on-line during the
despatch of the certified product, a sample has to be drawn
after dosing for odour test. The testing of the product is to be
done shift-wise and the record of the same shall be
maintained.
(a) The frequency of testing and types of tests required for LPG
quality control depend upon the local conditions. Excessive
sampling and testing add to operating costs, involve product
loss and introduce hazard on account of venting of the
product to the atmosphere. It should, therefore, be ensured
that the instructions regarding sampling and testing are
closely followed and sampling should be done whenever
required only.
LPG OPERATIONS MANUAL
12.9.4 DENSITY
(a) The density of the liquid phase of LPG is useful guide for the
quality of the product and is indispensable for converting
volumes to weight and vice-versa.
12.9.5 ODOUR
(c) (If LPG, during the draining operation involving venting to the
atmosphere, fails to produce a distinctive odour, the
product (unless known to be odourless grade) shall not be
LPG OPERATIONS MANUAL
(b) Water may be present in LPG in its free state i.e. as droplets or
in solution. Water in solution at one temperature can be
precipitated as free water by a fall in temperature. Hence,
the routine draining operation should be preferably carried
out early in the morning.
LPG OPERATIONS MANUAL
(a) Before any LPG system is made operational, air in the vessels,
pipelines and equipment, etc., are to be replaced by LPG.
Detailed procedures for purging the storage vessels and the
cylinders are outlined in the Annexure No. 10. Checking and
testing of the product for contamination by air are, therefore,
non-routine procedures and are necessary only during and
after the initial commissioning or after the plant is opened for
maintenance, etc.
(b) Air must be removed from all LPG cylinders because its
presence creates a flammability hazard. The presence of air
can also lead to over-pressurisation of LPG system.
12.9.9 DRAINING
(g) In order to prevent the escape of spilled LPG into the main
drainage system, surface water from the storage area shall
be directed to the main drainage through a water seal to
avoid the spread of Hydrocarbon.
(b) The frequency and extent of the need for the quality control
checks and tests vary with local circumstances.
(a) It must be ensured that the new empty cylinders and the
empty cylinders received from Statutory Testing Plants / Hot
Repairers and other cylinders containing air are purged
before filling operations.
12.10.3 Before each and every filled cylinder leaves the plant, it shall be
critically examined for the following aspects:
(a) Cylinder is genuine (not spurious) and fit for filling as per BIS
norms.
(d) The ‘O’ ring is present in the Self Closing valve and is not
defective.
12.10.4 For ensuring that the cylinder is genuine and fit for filling as per BIS
norms, following action shall be taken:
(a) All the filled cylinders shall be checked for bung leak in the
‘in-line’ bath / Electronic bung leak detector.
(c) The record of total number of bung leak / valve leak cylinders
and cylinders with missing / defective ‘O’ rings should be
maintained in the proforma given in Annexure No. 27 and the
trend will be monitored.
12.10.8 From the consumer point of view, it is extremely important that the
filled cylinders, while leaving the plant, must have ‘O’ rings in the
SC type valve outlets and that the ‘O’ rings fixed are not defective.
Towards this objective, the following steps shall be taken:
(a) All incoming empty cylinders shall be visually examined for
the presence of ‘O’ rings before they reach the carousel or
unit filling machine. Cylinders not having ‘O’ rings shall be
fixed with new ‘O’ rings immediately.
(b) With the help of Compact Valve Tester (CVT)/ AVTS/ Pressure
transmitter, test must be conducted to check each and every
filled cylinder for effectiveness of ‘O’ ring (as per the
manufacturer’s instructions). Sufficient time as prescribed by
the manufacturer shall be given for the test. Presently
permissible limit of leakage is 0.5 gm per hour.
Categories
New cylinder
Cylinder received after statutory testing
Cylinder received after hot repairs
Body leak
Leakage through weld joint (bung/circumferential)
Bung leak
Valve leak
Details beyond permissible limit as per IS 15966: 2013
(IS:13258- in the case of cylinders received after hot
repairs & IS16054 for cylinders recived after statutory
testing. In the case of new cylinders there should not be
any dent)
Quality of the punch mark
Quality of stenciling (tare weight and due date of
testing)
12.11.4 Samples of the product should be taken from the tank wagons,
tank trucks (or pipelines) before receiving the product into the
plant only when this prescribed procedure is specifically
authorised. Such samples should be checked/tested for vapour
pressure, temperature, odour, colour, appearance and density.
Presently, the system of checking of tank wagon, tank truck or
pipeline samples, before the receipt should not be followed as a
routine, but should be adopted in specific cases only where
contamination is suspected. The sampling must be done by a
competent person trained for the purpose with the help of
approved apparatus.
12.11.6 In the case of tanker discharge when two or more grades are
carried, individual tank of the tanker is to be checked regularly
LPG OPERATIONS MANUAL
12.11.7 When a common line is used and the product grade change is to
be made, representative line samples should be taken at intervals
before and after switching over in order to detect the stop
interface and to confirm the change and the quality of the
product switched over to the new vessel.
12.11.10 After the receipt of shipment and settling time of minimum one
hour, the following checks/tests should be carried out:
(d) The vapour pressure and the temperature are checked for
the bulk supplying vessels.
(b) Before the discharge is made, the vapour pressure and the
temperature of the product in both the delivery vehicles and
the receiving vessel, must be checked to ensure that they are
within the acceptable limits and that the products are
compatible. If not, the delivery must be deferred till full
investigation is carried out.
(a) Daily checks for the liquid level, pressure and temperature.
(b) Check for draining water should be made daily until no water
or contamination is found on successive tests. Draining should
then be stopped till the receipt of next replenishment, unless
climatic conditions (colder days) might cause soluble water in
LPG to be precipitated.
(b) Storage vessel and pipelines are checked for the presence of
water, if any and properly purged to ensure air is not present.
12.17 PRECAUTIONS
12.17.1 MOVEMENT OF LPG
If during the initial testing at the plant {refer Clause No. 12.9.1(b) } it
does not remove the doubt regarding the quality of LPG, the
suspect stocks should be frozen and State Office / Regional Office /
Head Office be informed immediately. At the same time samples
should be taken, marked for identification and submitted to the
nominated laboratory for testing.
(a) If testing at the plant before, during and after the receipt of
LPG shows that the vapour pressure/temperature and/or the
density are found to be outside the accepted range for the
grade, State Office / Regional Office/Head Office should be
consulted for further instructions.
(a) The Plant Manager should report all the cases of product
contamination to State Office / Regional Office / Head Office
giving full details of the grade and storage vessel involved
and additional stock and ullage available in the plant. The
causes of the contamination should also be indicated, if
known, together with the proposal for dealing with it and to
prevent its recurrence.
12.19 SAMPLING
12.19.1 PURPOSE
(d) Liquid LPG causes serious cold burns on contact with the skin.
Protective gloves and goggles should, therefore, be worn
during the sampling.
(g) The discharge of LPG from a sampling bomb can cause static
electricity. Sampling bomb must, therefore, be earthed
effectively before and during the discharge.
(i) Each bomb should be marked with its tare weight, working
pressure, test pressure and the dates on which it was originally
and last tested. The markings are to be etched on the bomb
or stamped on the metal plate attached securely to it.
The size of the sample should be related to the test and analysis to
be carried out on it and will influence the size and type of the
sampling container used. The sampling procedure as under shall
be followed:
(a) The liquid content in the bomb is vented out after checking
that there is no source of ignition in the vicinity.
(c) The outlet and inlet valves on the bomb are opened.
(d) The sample source valve is opened and the outlet valve on
the bomb is closed to minimise boiling of Liquid LPG in the
bomb.
(e) When the liquid appears, the liquid outlet valve is closed
followed by the inlet valve and the sample source valve.
LPG OPERATIONS MANUAL
(g) When the liquid ceases to flow, the outlet valve is closed and
the bomb is re-inverted by slackening and re-tightening the
connection.
(m) The bomb, the connection tube and the seal/plug sampling
point are disconnected
12.19.8 PURPOSE
BACK
13
ADMINISTRATION
LPG OPERATIONS MANUAL
13.1 GENERAL
13.1.1 The importance of safety and security at LPG Bottling Plant cannot
be over emphasised. Any activity related to the operations in the
plant should be directed with safety upper most in the minds of the
personnel operating it. The Plant Manager has great responsibility to
ensure that all regular employees within the Plant and all others
associated with the Plant working, such as casual/contract
labourers, Loader / unloaders, transport crew members, etc. are
well aware of the hazards involved at the plant, various safety
precautions and action in case of emergency, to achieve all time
safety.
13.1.1.1 To achieve the above objective all the persons connected with the
plant operations and its working must undergo proper training as
per OISD 154, both on and off the job.
13.2 RESPONSIBILITY
The prime responsibility lies with the individual for the
assignment being carried out by the individual. However, the
overall responsibility of the Plant Manager is to ensure that the
plant operates safely and efficiently. To achieve this objective
following areas need specific attention of the Plant Manager.
13.3 REGULATIONS
LPG operations should be carried out in accordance with the
Statutory Regulations in force and also any local Regulations
applicable at the place where the plant is situated. Likewise,
instructions in the form of a manual, circulars, bulletins, letters etc.
should be strictly enforced.
13.4 SECURITY
LPG OPERATIONS MANUAL
13.4.1 The efficient security of the plant, the assets it contains and the
deliveries made from it should be ensured through proper checks
and systems.
ii. VIP visitor: Necessary entries in the register, visitor slip and
visitor pass will be kept ready before the arrival of the VIP
and given to him immediately on arrival. The visitor card
for the VIP will be used for the visitor. However, visitor to
be considered as VIP will be decided by the Plant
Manager. The visitor slip and the card shall be
surrendered at the time of exit of the visitor from the plant.
13.4.10 Measures must be adopted to ensure that the persons entering the
licensed premises do not carry match box, lighter, lighted
cigarette/ bidi , cell phone or any other source of ignition. This
check is all the more necessary, in case of casual/contract
workers, who may not be initially fully aware of the hazards
involved. Frisking should be adopted in such cases as a regular
practice. Door frame metal detector and hand held metal
detector should always be used.
13.4.11 Proper caution signs should be placed at the gate and at all
other vulnerable locations within the plant to caution against
unauthorized entry and also use of any item providing source of
ignition. These caution signs should be so designed that they could
be understood by all persons entering and working in the plant.
Prohibited area declaration to be obtained from state government
and to be prominently displayed. outside all the gates, as a
deterrent against unauthorized entry.
13.4.14 All the operating gates should be manned round the clock and
special attention should be paid during night hours. Watch towers
should be fitted with revolving type flood lights. CCTVs is to be
LPG OPERATIONS MANUAL
13.4.15 Security staff should not be asked to carry out any other activity
except ensuring the security. However, as Security is responsible for
securing Plant and properties and also for checking
outgoing/incoming materials, Checking of cylinders, PRs, SC valves
and other incoming/ outgoing materials physically for correctness
with respect to invoices/ challans to be carried out physically by
security and records maintained. In case of differences between
the invoice challan and physical quantity, the same to be
recorded and to be brought to the notice of Plant Manager in
writing immediately. Necessary instructions to be issued to security
agency in this regard.
13.4.21 All the vehicles entering the plant should be searched with under
carriage mirror, inside the driver cabin and the carriage to ensure
non-availability of any explosive material.
13.4.32 ROLE OF UNITS: The following are the role of location, not
comprehensive but illustrative, with regard to security aspect
of the Location.
13.5 HOUSEKEEPING
13.5.1 Although cleanliness and tidiness are desirable for the safe and
efficient handling of general products, they are essential for LPG,
because of inherent hazards of bad housekeeping.
13.5.3 Some of the items that may need specific attention in relation to
housekeeping are as under:
(a) To ensure that all the cylinders in the plant are neatly stacked
in the areas licensed for the purpose and have proper sign
boards to identity the category of the cylinders stacked such
LPG OPERATIONS MANUAL
(e) Items such as safety caps, aluminium / plastic seals, `O’ rings,
neck labels, worn out maintenance materials etc. should not
be littered all around the floor in the sheds. Proper bins should
be used for neat storage and handling of such items.
(f) Soap solution, oils and greases should not spill over the floor
and area to be kept cleaned of these slippery items to avoid
accidental falling.
(i) All the pipelines and valves should be properly colour coded.
(k) Roads inside the plant should be maintained free from the
digs, pits and potholes etc.
13.5.4 ‘Place for Everything and Everything on its Place’ is the basic
concept of a good housekeeping and must be followed.
13.6 SAFETY
13.6.1 Safety precaution applicable to the storage, handling and
distribution of LPG are sufficiently covered in Chapter No. 4
exclusively devoted to the subject of safety at LPG plants. It should
LPG OPERATIONS MANUAL
System, etc.) from the control room itself. The system should be
provided as per Clause No. OISD 11.11. IV)
13.7.3 Each plant should develop its own “Plant Operating Manual”
based on the facilities, equipment available and the nature /
period of work. The manual should basically cover the details of
basic facilities / equipment provided at the plant and specific
guidelines / check-lists for their operation, inspection, maintenance
and repairs. The manual should be updated as and when
LPG OPERATIONS MANUAL
13.7.6 The report of handing over / taking over the charge of the plant
should cover handing over / taking over of the various manuals,
licenses, certificates, etc. referred above with specific mention of
licenses / certificates that might have been sent out for renewals.
Physical inventory /stock of cylinders, pressure regulators, sc
valves, bulk LPG, HSD etc to be taken and the same is to be
reconciled with SAP book stock. Differences if any to be clearly
brought out and recorded, while handing over/taking over the
charge. Various SAP documents on the same to be signed jointly.
Gauge book for LPG Bulk stock , HSD stock and register for Physical
inventory of cylinders to be jointly signed at the time of handing
over/taking over of location by in charges.
13.7.11 Gauge book as per format given in the LPG OPS Manual for
physical stock of Bulk LPG to be maintained. Gauge book to be
maintained also for Diesel in case of Consumer Pump on daily
basis.
13.7.12 It shall be ensured that bulk and packed payments are effected as
per RTD and also rates duly approved by competent authority.
RTD re-verification shall be once in three years in general.
Thereafter, payment for transportation shall be released on re-
verification of RTD. In case of new markets or diverted routes,
payments to transporters may be made maximum for a period of
one month on the basis of provisional RTD. RTD for the new route is
to be certified within the said period.. Location to maintain details
of various markets to which supplies are effected/sources from
which bulk is received along with RTD details and also their
validity. Co-Ordination with area office/state office to be
maintained by Plant in advance so as to get the RTD verification
including approvals by competent authority in time.
LPG OPERATIONS MANUAL
Alert when the situation becomes tense due to strike notice, civil
disturbance, terrorist activity, etc.
No visitor
would be allowed inside the plant area. In exceptional cases Unit
Head/ Location In-charge may accord permission to enter.
LPG OPERATIONS MANUAL
TRAINING
THE SAFETY AND PRODUCTIVITY LEVEL OF ANY
LPG PLANT IS DIRECTLY PROPORTIONAL TO THE
OPERATING PERSONNEL’S KNOWLEDGE OF THE
PRODUCT AND TRAINING IMPARTED TO THEM
FOR CARRYING OUT VARIOUS OPERATIONS AT
THE PLANT SAFELY
LPG OPERATIONS MANUAL
PAGE No.
TRAINING 14-1
March 2014
14.1 GENERAL
14.1.1 The only reason why this subject has been taken at the end is that it must
be regarded as most vital.
14.1.2 There is no point in having fulfilled to the highest extent, what all has been
mentioned in the previous Chapters, if the persons working do not know
how to ensure safe working or react in an emergent situation .
14.1.3 Within the same organisation, the conditions for two or more filling plants
will not be precisely the same. Even if the components at two plants are
completely identical, the physical conditions under which they are
installed and operated will seldom be the same. Therefore, constant
efforts are needed at each individual plant to turn out better “LPG
people” imparting the related training.
14.1.4 LPG training should include constant training on the job and participation
in exercises particularly for fire / spillage controls.
14.2.2 In view of the special conditions under which the product is stored and
handled, it calls for a specialised training at all levels. Unless the persons
LPG OPERATIONS MANUAL
PAGE No.
TRAINING 14-2
March 2014
14.2.3 With the above in mind, it is obvious that an all around mechanical know-
how is not sufficient to run the LPG plant safely.
14.2.4 Many accidents at LPG plants are caused not only by carelessness or non-
observance of the precautionary measures, but also primarily because of
insufficient knowledge of the product handled, lack of education or
training in the performance of the actual operations or ignorance and
insufficient understanding of the safety regulations. Such accidents are
absolutely unnecessary and it is emphasised that the LPG plant is not a
risky or a dangerous plant to work as long as the regulations are observed,
or to put it in another way – the safety level of any LPG plant is directly
proportional to the staff’s knowledge of the product and training imparted
to them for running the plant.
14.2.5 It takes time to become a competent LPG man, but an investment in the
training of the personnel operating the plant will yield interest in the form of
more effective production and higher safety level. This result is achieved
when the staff knows exactly what to do at any time and in any given
situation and last but not the least, knows what not to do.
14.2.7 With change in technology, many new equipment / systems have been
added while handling LPG. Proper know how and maintenance of these
equipments requires structured training about design philosophies and
operability of these equipments.
PAGE No.
TRAINING 14-3
March 2014
PAGE No.
TRAINING 14-4
March 2014
Participants : Workmen.
Duration : Two days.
Objective : To familiarize with safety aspects of LPG handling
and emergency procedure.
Course contents :
Characteristics of LPG and associated hazards.
Safety regulations (Statutory and in IOC).
Safe operating and maintenance procedures in :
Bulk handling and storage.
Bottling.
Despatch of cylinders.
Fire prevention and control.
Disaster Management Plan, Emergency Procedures and
Drills.
Industrial First Aid.
Housekeeping.
Relevant security systems.
LPG OPERATIONS MANUAL
PAGE No.
TRAINING 14-5
March 2014
PAGE No.
TRAINING 14-6
March 2014
PAGE No.
TRAINING 14-7
March 2014
Standing orders.
Participants : Officers
Duration : Five days.
Objective : To inculcate safety consciousness, to update the
knowledge of correct operating procedures and prevalent
statutory regulation.
Course contents :
Characteristics of LPG.
Design aspects of LPG bottling plant.
Details of codes.
Facility planning.
LPG cylinder, valve manufacturing / testing.
Detailed description / specification of Cylinders
/ valves.
Activities of ST/ HR of cylinders.
Chemistry of the fire and theory of extinguishments.
Basics about fire triangle.
Various means for extinguishing and
controlling LPG fire.
Fire protection system and operation at plants :
Details of fire protection facilities at plant.
Details about their operation and maintenance.
Control of leakages without fire.
Safety equipment handling :
Details of safety equipment provided at plant.
Demonstration of their handling and maintenance.
OISD standards and salient features pertaining to LPG.
Acts, rules governing LPG operations – SMPV rules, Gas
Cylinder Rules, Factories Act, Pollution Control Act,
Weights and Measures Act, Contract Labour Act, ESI & PF
Act, Standing Orders, CDA rules, Industrial Dispute Act,
Minimum Wages Act etc.
Layout / facilities at LPG bottling plant :
Aspects regarding finalisation of plant layout.
Criterion for selection of facilities.
Overview of typical Plant facilities.
LPG OPERATIONS MANUAL
PAGE No.
TRAINING 14-8
March 2014
PAGE No.
TRAINING 14-9
March 2014
14.4.3 Any person before initiation to LPG operations should be properly trained
as explained in Clause No. 14.3 above. Training facilities at the Plant level
will, therefore, be of immense help.
14.4.4 Besides a suitable hall for the class room training, various associated
training facilities as under should be provided:
14.4.5 In addition to training of the employees, the training facilities at the plant
can also be used for training :
ANNEXURES
LPG OPERATIONS MANUAL
ANNEXURE-1-A
ANNEXURE- 1B
ANNEXURE 2
STATE
OPERATING
Tankage
SR. BOTTLING
(
N CAPACITY
REGN BOTTLING PLANTS M
O (TMTPA)
T
. AS ON
)
01.04.2013
ANNEXURE 3
GLOSSARY OF TERMS
ABSOLUTE PRESSURE
See under "Pressure"
ATMOSPHERIC PRESSURE
See under "Pressure"
BAROMETRIC PRESSURE
See under "Pressure"
BLOW DOWN PRESSURE
I See under "Pressure"
BOILING
This is the action which takes place when a liquid changes its state
from a liquid into a gas or vapour. The heat required to bring this
change of state is called Latent Heat.
BOILING POINT
The Boiling Point of a liquid is defined as the temperature at which the
vapour pressure is one atmospheric absolute.
BOYLE'S LAW
See under "Gas Laws"
BULLET
A horizontal pressure vessel designed for storage of LPG. Horizontal
tanks mounted on pedestals at the Plants, mounted on a truck chassis
or a rail chassis are also known as Bullets.
CO-EFFICIENT OF EXPANSION
It is defined as the increase in volume of unit volume of a
substance when its temperature rises by 1°C.
COMMERCIAL BUTANE
Butane used as a fuel or for other purposes. It is not a chemically
LPG OPERATIONS MANUAL
FILLING RATIO
The ratio of weight of liquefied gas allowed in a pressure vessel to
the weight of water that the vessel will hold at 15°C.
FLAMMABLE COMPRESSED GAS
Gas, 13 per cent or less of which when mixed with air forms a
flammable mixture or whose flammable range with air is greater
than 12 per cent.
FLAMMABLE
controlling fires.
FREEZING POINT
The temperature at which liquid changes to a solid state : solidifies
GAS CYLINDER OR CYLINDER
Any closed metal container intended for the storage and transport
of compressed gas. designed not to be fitted to a special transport
or under-carriage. and having a volume exceeding 500 ml. but not
exceeding 1 0 0 0 liters.
GAS LAWS
(a) AVOGADRO'S HYPOTHESIS
Equal volumes of different gases at the same pressure and
temperature contain the same number of molecules.
(b) BOYLE'S LAW
The volume occupied by a given mass of gas varies inversely with
the absolute pressure if the temperature IS not allowed to
change.
INERT GAS
A gas which will not support combustion and normally does not
react with other compounds under normal conditions and
temperature (e.g. Nitrogen)
INFLAMMABLE
See "Flammable".
INFLAMMABILITY RANGE
See "Flammability Range".
INLET PRESSURE
See under 'Pressure'.
INSTALLATION
Any premises wherein any place has been specially prepared for the
manufacture
(filling) or storage of compressed gas in cylinder.
INSPECTOR
A person authorized by the licensing authority for the purpose of
inspecting vessels i n accordance with the approved design &
specification and code.
LATENT HEAT
See under "Heat".
LATENT HEAT OF VAPOURISATION
The quantity of heat absorbed by a unit mass when changing
from the liquid to gaseous phase while remaining at the same
temperature.
LPG OPERATIONS MANUAL
PERMANENT GAS
A gas whose critical temperature is below (-) 10°C that is to say a
gas which cannot be liquefied under any pressure at a temperature
above(-) 10°C.
QUICK CLOSING VALVE
A valve which can be closed quickly by the movement of release of
a lever instead of by the rotation of a stem.
RECEIVING TANK
A storage tank into which liquid is loaded.
REGULATOR
A device used to reduce the pressure of a fluid from a higher
pressure to a lower controlled pressure.
RELIEF DEVICE
·A device used to prevent a dangerous condition of pressure or temperature
from occurring in an enclosed space. Refer 'Safety Relief Device'.
LPG OPERATIONS MANUAL
TEST PRESSURE
See under 'Pressure'.
VALVE, AUTOMATIC CUT·OFF
A valve either pressure or electrically energized which automatically
closes when certain undesirable conditions such as an abnormal low or
high pressure are experienced.
ANNEXURE 4
© PCB RELATED
1 AIR CONSENT
2 WATER CONSENT
3 Hazardous Waste ( MHIHC) Rule 1989
4 Water test (Potability)
5 Air quality monitoring Test
6 Water quality monitoring Test
7 Noise Monitoring Test
8 DG sets approvals as required from EB/ERC as applicable.
(F) 1 License from Labor Department for engaging labors for various works
Intimation regarding change/commencement/completion of contract and
2 change of occupier for amendment of license
(E) General
1 Hydro Test of LPG Pipeline- Above ground-Every Five years
2 RTO Approval for Motor Driving Institute-Hazardous endorsement for Cyl TTs and BTs
3 LPG Hose Testing record- Every four months
4 Electrical Audit - Internal-Every year
5 Electrical Audit - External-Every four years
LPG OPERATIONS MANUAL
ANNEXURE 5
ANNEXURE 6
TYPICAL PROPERTIES OF COMMERCIAL PROPANE & BUTANE
Specification
Commercial Propane Commercial Butane
Formula C3H8 (Propane) C4H10 (Butane)
Boiling Point 0C - 45 -7 to -0.5
Freezing Point 0C -186 -150
Critical Temperature °C 97 152
Critical Pressure at (Kg/cm2) 43 39
ANNEXURE 7
1.0 GENERAL
1.1 One of the most important safety aspects at LPG bottling plant is to
ensure that the LPG containers are not over-filled. LPG containers
should be so filled that there is always sufficient vapour space left to
allow the liquid LPG to expand with the expected maximum increase
in temperature as stipulated in relevant statutory rules.
1.3 “The Static & Mobile Pressure Vessels (Unfired) Rules 1981” pertaining to
safe-filling of bulk LPG containers, reads as under .
(1) Maximum quantity of liquefiable gas filled into any vessel shall be
limited by the filling density of the gas, and shall be such that the
vessel shall not be liquid full due to expansion of the contents with
rise of temperature to 55°C, if vessel is uninsulated or to the highest
temperature which the contents are likely to reach in service, it the
vessel is refrigerated or insulated. This requirement shall be
applicable irrespective of the ambient temperature of the product
at the time of filling.”
1.5 A vapour space or OUTAGE must be left above the liquid to permit
room for expansion under any temperature conditions. In India Design
Pressure or Maximum Working Pressure for filling LPG in cylinders has
been fixed at 65°C. Since LPG in liquid form has relatively high co-
efficient of expansion (10 times more in case of Butane and 15 times in
case of Propane compared to water) and in case sufficient outage is
not left in LPG cylinder due to defective cut-oil system/weighing
machine, the hydrostatic pressure inside the cylinder would shoot up
by 14 to 15 Kg/cm’ per 1°C rise in temperature once the container
becomes liquid full. This would cause great strain over cylinder body
which could burst with normal increase in ambient temperature and
release LPG in the surrounding areas, This in turn could instantly form
flammable mixture which could spread and get ignited if it reaches a
source of ignition which may otherwise be away at a safer distance in
the un-licensed premises or even outside the plant area. This could
lead . worst possible disaster and the catastrophe that could be
caused by such a mishap could well be imagined. It is therefore,
imperative. that all possible care Is exercised to avoid overfilling of
containers beyond prescribed safe limits.
1.7 The safe-filling quantities can be worked out either in terms of weight
(Kg or MT) or volume (Lts. or KL). Weight method should be used if the
container is designed and equipped to be filled by weight (e.g.
cylinders, LPG tank truck or LPG tank wagon), using following formula:
W = FR x WC where
W = Safe-filling weight in Kg,
FR = Filling Ratio,
WC = Water capacity of the container in litres.
1.8 Whenever LPG tank wagons or tank trucks are required to be filled on
volumetric basis, ‘it must be ensured that the quantity so filled is not in
excess of the maximum permitted filling density on weight basis when
the liquid LPG reaches the temperature of 55°C. Maximum volume of
liquid LPG that can be “filled in a vessel at given temperature can be
worked out using the following formula
FR x WC
V = ________ where
D x VRF
Vl = safe maximum volume in Litres at temp. t°C,
FR = Filling Ratio (Refer Table J-2),
WC=Water Capacity of the vessel in Litres,
D =Density@15°C of liquid LPG in Kgs/Litre,
VRF = Volume Reduction Factor for Density D at temp t°C
using ASTM - table 54
Based on the above formula, safe maximum volume for a
container could be worked out in terms of “percent volume”
of the container as under
%Vl = Vl x 100
WC
or = FR x100
D x VRF
LPG OPERATIONS MANUAL
1.9 To comply with the requirement set out In clause 1.8 above, It is
essential to ascertain temperature of liquid LPG at the time of tilling
when working out safe filling volume at any particular temperature.
TABLE J-1
TABLE .J-2
1.12 EXAMPLES :
EXAMPLE: 1
If volumetric capacity of a Horten Sphere is 1418 M3 and LPG to be stored
has a density of 0.5430 Kg/Litre @ 15°C, calculate the safe filling capacity for
the Horton Sphere in terms of
(a) Metric Tons,
(b) % volume of the total volumetric capacity of the Horton Sphere, at 15°C.
STEP—1
Density of 0.5430 @ 15°C is equal to 0.5429 D 15.5°C.
STEP — 2
As per clause 1.8 of the annexure
W = FR x WC, where;
W = safe-filling weight in Kgs. (to be ascertained),
FR = Filling Ratio; 0.46 (as per table J-2),
WC = Water capacity in Litres, 1418 x 1000 (given),
=46/05430
=84.7%
EXAMPLE — 2
An LPG tank wagon having a gross weight of 34.0 MT, tare-weight of 18.8
MT and 33 M3 water capacity is to be loaded on volumetric basis at a
temperature of 25°C. The density of LPG to be loaded is 0.5450 Kgs/Litre @
15°C. Calculate safe-filling volume at 25°C and safe-filling quantity in MT
for the tank wagon.
STEP—i:
Maximum carrying capacity of LPG tank wagon, as permitted by the
railways, is the difference of gross weight and tare weight of the tank
wagon subject to maximum limit of 15.4 MT. In the present case maximum
carrying capacity as per railways would be 15.2 MT (34.0 gross wt. 18.8
tare weight).
STEP — 2
Using formula in clause 1.8 of the annexure it must be verified that the
filling ratio for the tank wagon bullet is not exceeded, if the LPG is loaded
as per carrying capacity worked out on the basis of Step-i above. In case
filling ratio is exceeded based on the carrying capacity, the loading
should be limited to safe- filling quantity worked out on the basis of
formula in clause 1.8 of the annexure.
STEP — 3
Using formula given in clause 1,9 of the annexure, safe filling volume at
25°C can be worked out as under
FR x WC
V1 = ________ where;
D x VRF
V1 = Safe max. volume in Litres at 25°C (to be ascertained),
FR = Filling Ratio; 0.47 (from table J-2)
WC = Water Capacity in Litres 33 x 1000 (given),
D = Density @ 15°C; 0.5450 (given),
VRF= Volume Reduction Factor for Density of 0.5450 @ 15°C
and temperature 25°C; 0.9760 (from ASTM table — 54).
0.47 x 33 x 1000
Therefore, VI= _________________ = 29158 Litres.
0.5450 x 0.9760
EXAMPLE — 3
Volumetric capacity of an LPG tank truck bullet is 22 M3 . LPG having
liquid density of 0.5440 Kg/Litre @ 15°C is to be loaded in the tank truck.
Calculate the safe vapour space in terms of percentage volume for fixing
the fixed level gauge.
STEP—i:
For the purpose of working out safe maximum volume for a “fixed level
gauge”, the minimum operating temperature should be considered. LPG
tank truck bullets are designed for operating temperature range of —
6°C, to (+)55°C, therefore, safe maximum volume should be calculated
for (—) 6°C in the present case.
LPG OPERATIONS MANUAL
STEP — 2
As per formula in clause 1.9 of the annexure
FRxWC
Vi = ________ where;
DxVRF
0.46 x 22 x 1000
Therefore, V1= ________________ = 17751 Litres.
0.5450 x 1.048
Or % V1= 17751 x 100 = 80.6%
22 x 1000
STEP — 3
Percentage safe vapour space ( (-) 6°C would therefore,
be
100 — 80.6 = 19.4%
EXAMPLE — 4:
Calculate the minimum water capacity required for LPG tank truck bullet
for carrying 10 MT of LPG, with the assumption that the lowest density of LPG
to be transported would be 0.5280 @ 15°C.
STEP— 1:
As per formula given in clause 1.8 of the annexure
LPG OPERATIONS MANUAL
W = FRxWC, or,
WC = W / FR ; where
WC = Water capacity in Litres, (to be ascertained),
W = Safe maximum capacity in Kgs; 10 x 1000 (given),
FR = Filling Ratio, 0.45 (as per table J-2).
Therefore, WC 10 X 1000 = 22,222 Litres or 22.3 m3
0.45
EXAMPLE — 5:
An LPG tank truck is having a bullet with a volumetric capacity of 13,200
Litres. If it is required to be filled on volumetric basis, calculate the
percentage setting for Rotogauge it liquid LPG with density of 0.5400
Kg/Litre is to be titled at a temperature of 28°C.
STEP — I
As per formula given in clause 1.9 of the annexure
V1 = FR x WC ; where
D x VRF
V1 = Safe maximum volume in Litres; (to be calculated),
FR = Filling Ratio; 0.46 (as per table J-2),
WC = Water capacity in Litres; 13,200 (given)
D = Density of LPG at 15°C; 0.5400 (given)
VRF = Volume Reduction Factor, based on density of 0.5400 at
15°C and temperature 25°C; 0.967 (from ASTM table 54),
Therefore, v1 = 0.46 x 13200 = 11628 Litres
0.54 x 0.967
or %V1= 11,628x 100 = 88
13,200
NOTE :
(1) As a normal practice, LPG tank trucks are filled on weight basis only.
(2) Whenever the tank truck is filled on volumetric basis, care must be
exercised to ensure that
(3) Even though the tank truck is filed on volumetric basis it is advisable
to determine through weigh bridge, the weight of the product
loaded to ensure that the weight does not exceed the safe filling
weight. This also helps to work out transit loss at unloading point.
EXAMPLE — 6
Calculate safe-filling quantity for cylinder of 33.3 Litres water capacity
@ 15.0°C. assuming that the density of LPG to be filled in is 0.550
Kg/Litres @ 15.0°C.
STEP — 1:
As per formula given in clause 1.8 of the annexure
W = FR x WC ; where ;
W = Safe filling quantity in Kgs; (to be ascertained),
FR = Filling Ratio; 0.454 (from Table J-1),
WC = Water capacity in Litres, 33.3 (given),
Therefore, W = 0.454 x 33.3,
= 15.1182 Kg. (say 15 kg.).
LPG OPERATIONS MANUAL
ANNEXURE 8
S. NO DOs DON’T’s
1. Adhere to the Dos listed Do not ignore points listed below
below.
2. Get familiarised with the Do not ignore Statutory Rules and
Glossary of Terms (Annexure Regulations.
No. 3)
3. Understand Properties, Do not undertake modifications without
Characteristics and Hazards of proper approvals.
LPG (Chapter No. 3)
4. Ensure that all relevant Do not undertake any operation without
licensees as per Statutory competent supervision.
Regulations are available,
valid and renewed in time.
5. Comply with the conditions of Do not carry out hot work without
applicable licenses. adequate precautions and hot work
permit.
6. Avoid presence of water and Do not start any LPG operation without
air in LPG system including proper grounding and bonding
cylinders. Purge wherever arrangement.
necessary (Annexure No. 8)
7. Wear protective gloves / Do not enter into a storage vessel until
clothing at vulnerable points all connecting lines are disconnected,
of liquid exposure. blanked-off, vessel thoroughly purged
of residual gases and certified Gas Free’
in writing by a competent person.
8. Familiarise with Do not commission plant or a facility
(i) Common sources of without detailed inspection and all
leakage; applicable licenses and certificates.
(ii) Common sources of
ignition;
(iii) Common sources of fire.
9. Avoid venting of LPG to Do not use LPG system for the grade
LPG OPERATIONS MANUAL
S. NO DOs DON’T’s
atmosphere having higher vapour pressure than that
of the grade for which it was designed.
10. Drain water from storage Do not fill any container beyond its safe
vessels regularly and carefully. filling capacity.
11. Ensure good house-keeping Do not use LPG system for the grade
having higher vapour pressure than that
of the grade for which it was designed.
12. Strictly enforce “NO SMOKING” Do not use pressurised system beyond its
within the plant area. due date of re-testing
13. Discontinue operation at the Do not place any part of the body over
first sign of major leak. a slip tube device nor over the
discharge end of a pressure relief valve.
14. Ensure all plant personnel are Do not expose hands, face or any part
familiar with the knowledge of of the body to liquid
action in emergencies.
15. Report accidents as per laid LPG without protective clothing /
down procedures and equipment.
investigate causes.
16. Conduct regular Safety Audit Do not carry out any operation after
of the Plant to eliminate daylight unless adequate flame-proof
hazards. lighting arrangement is provided,
17. Prepare and display ‘Fire Do not drain water from storage vessel
Fighting Organisation Plan’ at without provision of double valve on the
prominent water drain.
18. locations in the plant ensuring Do not bang or roll the cylinders during
that all concerned understand loading / unloading and handling
their role and responsibility operations.
clearly.
19. Check fire protection and Do not store filled cylinders or cylinders
safety devices regularly. containing LPG vapour in open.
20. Maintain liaison with Local Fire Do not vent out cylinder contents to
Brigade and involve them in atmosphere at plant.
regular exercises.
21. Maintain proper records of fire
Do not dispose off condemned
drills, checks, incidents,
cylinders as scrap unless they are de-
accidents etc. shaped by pressing and marked as de-
faced.
22. Ensure periodic checking of Do not store empty and filled cylinders
LPG OPERATIONS MANUAL
S. NO DOs DON’T’s
pressure relief valves beyond stacking or the licensed
capacity, whichever is less.
23. Before filling LPG tank truck, Do not throw cylinders from a height.
ensure that valid CCOE’s
license is available and the
receiving location has a
storage license.
24. Check tightness of hose Do not send cylinders to the repairers
connections for tank wagon without making them gas-free.
and tank truck operations with
soap solution by only cracking
the valve initially.
25. Always replace caps and Do not leave any over-filled / leaky
plugs of transfer connections cylinder at the close of working hours.
ensuring that they are leak
free.
26. Ensure that the receiving vessel Do not transport filled cylinders by rail.
has sufficient ullage before
discharging tank wagons or
tank trucks.
27. Apply chock blocks on tank Do not use stake trucks for
wagons and tank trucks during
operation.
28. Disconnect LPG hoses from cylinder transportation which do not
tank wagons and tank trucks meet basic safety requirements.
during prolonged suspension
of operation.
29. Place caution signs on railway Do not transport leaky cylinders.
siding, whenever the
operation is on.
30. Keep the sealing material Do not transport LPG cylinders with
away other goods.
31. from the end of the threads, Do not use lifting magnet for loading of
while making any threaded cylinders.
connection.
32. Maintain operating log for Do not fill a cylinder whose due date of
commissioning testing has expired.
/decommissioning of storage
LPG OPERATIONS MANUAL
S. NO DOs DON’T’s
vessels and all other important
operations within the plant.
33. Educate tank truck drivers for Do not dip cylinder valve threads into a
over the road procedure, sealing compound.
parking during transit, vehicle
parking in the plant, vehicle
garaging, vehicle repairing,
emergencies in transit,
accident reporting
34. Ensure strict checks for Do not use LPG hose beyond its due
segregation of cylinders due date of testing.
for statutory testing.
35. Ensure correct tare weight Do not attempt sampling of LPG unless
marking and check for proper sampling arrangement exists,
presence of water, at random, concerned person is trained for the job,
specifically in case of new sampling is required for a specific
cylinders, cylinders returning purpose and authorized by SO/RO/HO.
from testing plants and
repairers.
36. Ensure test for ‘O’-ring of filled Do not continue operations if safety /
cylinders with SC type valve, fire protection devices are rendered
using dummy regulators or ineffective.
CVT.
37. Ensure that water / dust from Do not allow entry of vehicles not
the cavity of the ‘SC’ type conforming to statutory requirements.
valve outlet is blown using air
pressure.
38. Ensure use of conveyor system Do not release the truck loaded with
to the maximum. filed cylinders unless check is carried
out with Explosimeter and readings are
within permissible limits.
39. Ensure 100% check weighing of Do not compromise on any norm
filled LPG cylinders. governing safety.
40. Use portable trolleys within the Do not allow unauthorised / untrained
plant for transporting cylinders persons when unsafe condition is
in vertical position and to noticed.
avoid rolling wherever use of
conveyor is not practicable.
LPG OPERATIONS MANUAL
S. NO DOs DON’T’s
41. Ensure cylinders are Do not leave any LPG operation
evacuated before filling in unattended.
case of filling through
machines operating on ‘Tare-
Off’ system.
42. Use evacuation units for Do not continue LPG operation, if any
evacuating contents from leak or unsafe condition is noticed
leaky / defective cylinders.
43. Ensure security nut on the Do not allow weed / vegetation to grow
cylinder valve outlet is fixed at in yard area.
all times except for the
duration when removal is
necessary for any specific
operation.
44. Leave adequate pathways Do not stack filled cylinders horizontally.
around stacks of cylinders for
easy detection and removal
of leaky cylinders.
45. Minimise manual handling of Do not allow rough handling or filled /
cylinders as far as practicable. empty cylinders.
46. Earmark storage areas for Do not despatch any filled cylinder
different categories of without proper valve protection seal
cylinders and provide proper and neck-label.
sign boards for identification of
each stack.
47. Stack filled cylinders verticallyDo not ignore liquid-equivalent of vapor
only. quantities while accounting LPG bulk
stocks.
48. Evacuate leaky and overfilled Do not allow accumulation of vapour in
cylinders on priority. plant area, especially in low lying areas
such as drains, sumps, etc.,
49. De-pressure the cylinder Do not carry out cylinder repairs in the
before valve removal. filling- shed.
50. Use proper clamp / vice for Do not carry out water draining
holding the cylinder at the operation in dark hours.
time of valve removal / fixing
51. Inspect critical area around Do not open back cover of the truck
internal periphery of the foot and cross bars used in the truck for
LPG OPERATIONS MANUAL
S. NO DOs DON’T’s
ring during visual inspection supporting the cylinders prior to parking
and painting operation of LPG of the truck.
cylinders.
52. Verify the due date of testing Do not roll cylinders on belly for faster
at the test plant, before unloading of cylinders.
undertaking the testing
operations.
53. Examine defective valves Do not start unloading operation,
carefully for retrieval-worthy without counting the numbers by
condition before sending for supervisor.
retrieval.
54. Maintain proper records at all Do not drop cylinders from a height
stages of operations. during unloading operations .
55. Ensure test certificate is issued Do not start the truck till the back cage
for cylinders tested at the cover is closed and locked.
Statutory testing plant.
56. Follow inspection and Do not attempt lubrication of carousel
maintenance schedules filling guns when carousel is in operation
strictly. as it may lead to oil spillage.
57. Test LPG hoses at stipulated Do not lubricate the running rail.
intervals.
58. Measure, calculate and Do not tamper with speed of rotation of
record all stocks care-fully, carousel.
accurately, regularly and in
conformity with standard
procedures.
59. Investigate promptly, any Do not bypass gas stop valve under any
abnormal loss or gain. circumstances.
60. Keep close watch on pressure Do not remove or introduce cylinders
and temperature in the either after encoding or before check
storage / transport vessels
during operation.
61. Ensure training for all regular scale in electronic carousal system as it
employees within the plant disturbs the sequence
and all others associated with
the plant working such as
truck crew/ contract
labourers.
LPG OPERATIONS MANUAL
S. NO DOs DON’T’s
62. Ensure strict security checks at Incase of cylinders struck up at check
the gate to prevent scale platform do not forcibly pull or
unauthorised entry and drag the cylinders.
carrying of match box,
cigarette lighters or any other
source of ignition.
63. Ensure display of identity No jet of water/air should be used to
badge for each person within clean the surrounding floor which may
the plant. lead to water seepage to load cell
check scale and junction boxes.
64. Place proper caution signs at Do not tamper settings of electronic
the gate and all other check scale.
vulnerable locations within the
plant.
65. Enforce random checks by Do not allow dust accumulation around
frisking of persons by electronic parts.
authorised officers to ensure
that they are not in possession
of any items which may
provide a source of ignition.
66. Maintain copies of all Manuals, Do not increase the rejection range from
applicable Statutory rules, 0.5 gm/hr
manufacturers instructions for
operations/ maintenance /
inspection, etc. Secure them
in plant library.
67. Keep fire fighting equipment in Do not allow air leaks from the
good order and condition, pneumatic hoses.
ready for immediate use at all
times.
68. Conduct fire drills atleast once Do not use oil other than Kerosene.
in a month.
69. Conduct checks for gas Do not allow gap between cylinders
leakage through Explosimeter while entering test bath, to avoid falling
at all vulnerable points within of cylinder.
the plant on daily basis.
70. Ensure periodic earthling test. Do not allow filling of evacuation vessel
more than 85%.
LPG OPERATIONS MANUAL
S. NO DOs DON’T’s
71. Ensure proper colour coding of Do not keep leaky cylinders
pipelines and valves. unevaluated at the end of the shift.
72. Ensure daily draining of ‘air Do not use non standard tools for
compressor’ tanks. evacuating cylinders having pin struck /
broken valves
73. Ensure proper cushioning on Do not remove valves with out properly
cylinder storage / filling shed clamping the cylinders.
flooring.
74. Provide and maintain first-aid Do not keep cylinders haphazardly near
kits at strategic locations. the valve ON/OFF screw machine.
75. Conduct hydrostatic stretch Do not over tighten the valve.
test instead of hydrostatic test
at the time of third Statutory
re-testing. Ensure supports of
Horton Sphere are encased in
cement concrete.
76. Ensure one of the ends of Do not use worn out head for screw and
bullet supports has provision unscrewing of valves as it may damage
for sliding. hexagonal portion of the valves.
77. Provide effective Do not leave any serviceable
communication system cylinderwith open bung after removal
(PA/Paging) in the plant, of the valve.
ensuring that the system is
Flame-Proof within licensed
area.
78. Replace dirty water in cylinder Do not roll the cylinders on belly.
test baths with clean water.
79. Paint interior surface of test Do not store filled cylinders beyond the
baths with white paint and licensed capacity.
provide adequate lighting
(FLP) for better visibility of
leaks.
80. Keep the water drain Do not stack filled cylinders horizontally.
connection of storage vessels
locked and sealed when not
in us.
81. Do set maximum inventory Do not allow rough handling of filled
levels for the stocks of filled cylinders.
LPG OPERATIONS MANUAL
S. NO DOs DON’T’s
and empty cylinders
individually as well as
maximum inventory level for
combined stock of filled and
empty cylinders as per norms.
82. Unloading of serviceable
empty cylinders should be
made at unloading platforms
only.
83. Trucks should be securely
parked with hand brake and
gear.
84. Engine should be put off and
master cut off switch should
be isolated prior to any
unloading operations.
85. The unloading contract
labourers should wear shoes
and hand gloves.
86. Telescopic conveyers should
be used to unload the
cylinders.
87. Cylinders while unloading
should be handled carefully
without dropping or rolling.
88. Ensure oil level in FRL &
Hydraulic oil tank prior to
starting the carousel.
89. Ensure filling heads are
properly earthed.
90. Any leak of LPG from filling
head to be attended
immediately.
91. Monitor pressure of LPG &Air
for the accuracy of filling.
92. Ensure carousel is interlocked
with vapour extraction unit.
93. Accuracy of the electronic
LPG OPERATIONS MANUAL
S. NO DOs DON’T’s
filling machine are to be
checked in intervals of every
four hours & maintain records.
94. Filling hoses should be tested
periodically, once in four
months.
95. Only stamped and certified
scales by Dept. of Legal
Metrology should be used.
96. Accuracy of check scale
should be checked at an
interval of every 2 Hrs by
standard weight.
97. Adequate air pressure should
be maintained
98. FRL need to be checked for oil
level and cleaning of the
filter element.
99. The maximum limit of rejection
at check scale should be
within +200/-100 grams.
100. Always keep the kerosene
chamber clean in CVT.
Replace if required.
101. Ensure CVT Clamping properly
on the cylinder valve.
102. CVT should be periodically
checked with the CVT verifier
and also after any repair to
the CVT.
103. AVTS/GD-PD should be
calibrated weekly with
comparator and checked for
functioning at both rejection
level of 0.5 gm/hr and also at
acceptable level say 0.3 gm/hr
104. Ensure air pressure between
5-6 Kg/sq cm.
LPG OPERATIONS MANUAL
S. NO DOs DON’T’s
105. Re-check ‘O’ ring effectivenss
after replacement.
106. Ensure the water level in the
bath for complete immersion
up to the bung level of
cylinders.
107. Ensure clean water in the bath.
Evacuate the leaky cylinders
immediately.
108. Use cold flare line to vent out
residual LPG.
109. Ensure proper earthing of
evacuation adopters.
110. Ensure proper stacking of leaky
cylinders.
111. Ensure capping of cylinders
before and after the
evacuation Handle the
cylinders in vertical position at
all stages of loading .
112. Attend leaky adapters
immediately.
113. LPG hoses should be tested
periodically once in 4
months.
114. Ensure cylinders are
depressurised before
removing the valve.
115. Do not change the valve for
bung defect cylinders unless
the valve thread found to be
damaged.
116. Check the torque setting of
the machine in the beginning
of the shift and also every two
hours with a torque wrench.
117. Ensure bung cleaning and
checking before fixing of
LPG OPERATIONS MANUAL
S. NO DOs DON’T’s
valve .
118. Ensure proper application of
thread sealant.
119. Use portable trolley for cylinder
movement inside the plant, if
conveyor is not available.
120. Store cylinders vertically only,
within the plant shed.
121. Ensure safety cap is fitted on
all cylinders stored in the
plant.
122. Ensure different categories of
cylinderslike(filled, serviceable
empty /ST due, new etc), with
Identity Boards.
123. Separate tags should be
maintained for 14.2 Kg, 19 Kg,
, 5 Kg and 47.5 Kg cylinders.
124. Ensure de-gassing of
unserviceable cylinders.
125. Handle the cylinders in vertical
position at all stages of
loading .
126. Trucks should be properly
parked keeping on the gear
and hand brake with ignition
‘OFF’ and key removed.
127. Fire extinguishers of the trucks
should be taken out of the
cabin and position suitably
for easy access, in case of
emergency .
128. Use of personal protective
clothing like hand gloves,
shoes, helmets etc should be
ensured.
129. Use Telescopic conveyer for
loading cylinders on to the
LPG OPERATIONS MANUAL
S. NO DOs DON’T’s
truck.
130. Ensure positioning of wooden
crossbars for supporting of
cylinders and back cover are
closed and locked prior to
movement of the truck from
the loading platform.
LPG OPERATIONS MANUAL
ANNEXURE 9
BAY WISE CHECKLIST BEFORE START & AFTER COMPLETION OF TLD/TLF OPERATION
1 TT NO
2 Record Pressure (psi) / Temp
oC
3 Rotogauge Readiing
4 Master cut-off switch in Off
Position & Hand Brakes
applied
5 TT Fire Extinguisher placed in
front of the vehicle
6 Wheel chokes placed at
front and back tyre
7 Ignition Keys of TT handed
over by driver to workman
and kept in the key box
under lock and key by the
Workman
8 Earthing connectors
connected to chassis and
Tank
9 Unloading arms/ Hoses
connected to TT flange
through SS metallic gaskets
and eight nos. studs and nuts
and bonding of flange
done. No CAF/Rubber/Non
metallic gaskets used
10 No LPG leakage from
flange/coupling/swivel joint.
LPG OPERATIONS MANUAL
Unloading/Loading started at ( in
24 hr. format
Driver Signature
Signature of Workman
- ANNEXURE 10
- PURGING
8.1 GENERAL
8.1.1 Presence of air in any LPG system; be it a storage vessel, pipeline, transport
vessel, or a Cylinder; is undesirable. Therefore, necessary to remove air from
LPG systems before filling it with LPG. The process of replacement of air in a
closed containers/system by LPG vapour, using safe methods, is known as
‘purging into service” commonly referred as “purging”.
8.1.5 As the term itself suggests, “purging out of service” is required when LPG
container/system is required to be taken out of service for inspection,
maintenance, repairs or any other purpose.
8.2.1.1 Once new tank wagons are ready they are sent to refinery points for loading.
However, before actual loading, they are required to be “purged into
service”,
8.2.1.2 The normal method of “purging” using water to displace air and LPG vapour
to displace water is not practicable in case of LPG tank wagons in
drain connection at bottom of the tank wagon bullet. In view of this, the
procedure described in Clause 8.2.1.3. below is followed.
8.2.1.3 Approximately 50 Kg. of liquid LPG is tilled into the tank wagon initially and
vapour released to the atmosphere gradually using sate venting means.
Again 200 kg. of liquid LPG is tilled thereafter and similarly released to the
atmosphere using safe venting means. The tank wagon is thereafter ready for
loading.
8.3.1 Inspection, maintenance and repair of LPG tank wagons is done by the
railways who take care to purge the tank wagons “out of service” before
attempting inspection, maintenance or repair.
8.4.1 (a) A set of cylinders to be purged(the number can vary depending upon
the requirement) is connected to air-line manifold which in turn is connected
to suction side of a vacuum pump.
(b) Vacuum pump is started. The air is sucked from all the connected
cylinders simultaneously. The delivery side of the vacuum pump is connected
to a suitable sate venting system.
c) As soon as pressure on the suction side of the vacuum pump reaches the
level of (- 0.65 kg/cm?/(-)494 mm Hg (indicated through pressure gauge
mounted on the air-line manifold. This gauge pressuire is equivalent to 0.35
kg/cm2 absolute) air-line connections are closed and vacuum pump suction
switched over to next batch of cylinders which are kept connected.
(d) Control valve on LPG vapour line is opened to allow entry of LPG vapours
into the cylinders from filled LPG cylinder connected to LPG line (or LPG
vapour line directly). Once positive pressure (minimum 1.0 kg/cm2) is attained
LPG OPERATIONS MANUAL
within the cylinders, LPG vapour supply is cut-off and the cylinders are
disconnected which can thereafter be used for LPG filling. (e) The cycle is
repeated for the next batch of cylinders.
8.5.2 In case of hot repairs. assurance must be gained that the cylinder is “gas-
free” before attempting the repairs.
8.5.3 Most common method for purging the cylinders ‘out of service” is to remove
the cylinder valve, fill the cylinder with water allowing to over-flow and keep
the water filled for minimum one hour before draining.
ANNEXURE 11
ANNEXURE 11 ( cont’d)
2. CALIBRATION CHART FOR TANK WAGONS ( 8 – WHEELER)
ANNEXURE 12
FORMAT FOR GAUGE BOOK
PAGE NO.
Time Storage Vessel Opening LPG Liquid – Pressure Temp Density Remarks
Gauge Qty (MT)
Reading
1.
2
3
4
5
6
Shift Officer’s
Signature
Plant Manager
Signature
LPG OPERATIONS MANUAL
ANNEXURE 13
QUANTITY OF LPG IN A 14.2 KG CYLINDER
What is the quantity of LPG required for vapour filling inside a cylinder of 33.3 ltrs.
capacity having a vapour content at a temperature of 30.C and a pressure of 2
Kgs/ cm2
Find the liquid equivalent of the vapour. Density of liquid LPG is 0.56 kg/litres.
Step : 1
Vapour volume = 33.3 litres.
Step : 2
Convert the vapour volume at 30C and 1.5 Kg/ cm2 pressure to NTP (i.e. Normal
Temperature and pressure where normal temp. = 15C and normal pressure =
0) using the following formulae.
P1 V1 P2 V2
———— = ————
T1 T2
P1 xV1 xT2
Therefore, V2 =
T1 xP2
= 92.90 litres.
Step : 3
Using liquid / vapour ratio of 247.7: 92.90 litres of vapour volume at zero gauge
pressure and 150C would work out to liquid equivalent of :
LPG OPERATIONS MANUAL
Step:4
Density of LPG of 0.560 kg/litres at 15 degrees cent.
Hence the weight of LPG i= 0.21 kg. say 200 gms
LPG OPERATIONS MANUAL
ANNEXURE 14
CALIBRATION CHART FOR 14 MT DIA HORTON SPHERE INCLUDING LEV
OBSERVED 35
TEMP.
OBSERVED PR. 6
DENSITY 0.54
HORTON DIA. 14
LIQ. LIQ. VOL. LIQ. QTY. VAP. SPACE VAP. VOL LEV PRODUCT
LEVEL
0 0.00 0.00 14 1437.33 19.94 19.94
0.5 5.37 2.90 13.5 1431.96 19.87 22.76
1 20.95 11.31 13 1416.38 19.65 30.96
1.5 45.96 24.82 12.5 1391.37 19.30 44.12
2 79.62 42.99 12 1357.71 18.84 61.83
2.5 121.13 65.41 11.5 1316.20 18.26 83.67
3 169.71 91.65 11 1267.62 17.59 109.23
3.5 224.58 121.28 10.5 1212.75 16.82 138.10
4 284.95 153.87 10 1152.38 15.99 169.86
4.5 350.04 189.02 9.5 1087.30 15.08 204.10
5 419.05 226.29 9 1018.29 14.13 240.41
5.5 491.20 265.25 8.5 946.13 13.13 278.37
6 565.71 305.49 8 871.62 12.09 317.58
6.5 641.80 346.57 7.5 795.54 11.04 357.61
7 718.67 388.08 7 718.67 9.97 398.05
7.5 795.54 429.59 6.5 641.80 8.90 438.49
8 871.62 470.67 6 565.71 7.85 478.52
8.5 946.13 510.91 5.5 491.20 6.81 517.73
9 1018.29 549.87 5 419.05 5.81 555.69
9.5 1087.30 587.14 4.5 350.04 4.86 592.00
10 1152.38 622.29 4 284.95 3.95 626.24
10.5 1212.75 654.89 3.5 224.58 3.12 658.00
11 1267.62 684.51 3 169.71 2.35 686.87
LPG OPERATIONS MANUAL
ANNEXURE 15
As per BS 5500, the tolerance allowed in the circularity of the vessels is based on
the following Formula :
= 4/3x22/7x(d/2)3
= 4/3x22/7x14.076x14.076x14.076/8
= 1460 cum.
Water capacity of the vessel is taken as 1437 cum. as per the manufacturer’s
recommendation.
Hence variation in water capacity = (1460-1437) to ( 1437-1414)
= +/- 23 cum.
= +/- 12.42 MT( taking LPG density as 0.54)
ANNEXURE 16
Total
BOTTLING
Shift Vessel Opening Bottling (No of Total no. Qty. Book Vessel Physical Loss/
Qty. cyl) of cyls. (MT) balance Readin Balance Gain
14.2 Kg 19 kg
Total
LPG OPERATIONS MANUAL
RAIL RECEIPT
Date Vess Opening Opening Date Closing Qt Recd CC/ Loss/ Remarks
& el Reading Qty. & reading y. .Qty. AC-5 gain
Hrs. Used Hrs. Qty.
A Shift B Shift
HS # HS #
Evacuation by pass open in
ANNEXURE 17
YES / NO
a. Is QC Manual on LPG available ?
b. Are all QC circulars/bulletin available properly filled ?
QC APPARATUS
PRODUCT MONITORING
FAILURES
COMPLIANCE
SUGGESTIONS
TANKERS RECEIPT
a. Is the product release only after the lab? Conformed that the product
meets IS specifications.
b. Is the test report sent to respective receiving locations ?
NAME
SIGNATURE
LPG OPERATIONS MANUAL
ANNEXURE 18
Note 1 :
Hydrogen Sulphide by UOP 212.77 test method is also acceptable, with limit for
Hydrogen Sulphide Max 5 ppm. “Pass” test as per test method D 2420 indicates
Hydrogen Sulphide not more than 5 ppm.
Note 2 :
Water content by ASTM E-700 test method is also acceptable, with limit of max. 10
ppm.
LPG OPERATIONS MANUAL
ANNEXURE 19
Note 1 :
Hydrogen Sulphide by UOP 212.77 test method is also acceptable, with limit for
Hydrogen Sulphide Max 5 ppm. “Pass” test as per test method D 2420 indicates
Hydrogen Sulphide not more than 5 ppm.
Note 2 :
Water content by ASTM E-700 test method is also acceptable, with limit of max. 10
ppm.
LPG OPERATIONS MANUAL
ANNEXURE 20
Note 1 :
Hydrogen Sulphide by UOP 212.77 test method is also acceptable, with limit for
Hydrogen Sulphide Max 5 ppm. “Pass” test as per test method D 2420 indicates
Hydrogen Sulphide not more than 5 ppm.
Note 2 :
Water content by ASTM E-700 test method is also acceptable, with limit of max. 10
ppm.
LPG OPERATIONS MANUAL
ANNEXURE 21
REQUIREMENT FOR LIQUIFIED PETROLEUM GASES AS PER IS 4576 1999
ASTM Test Methods can be followed till “P” of IS 1448 method under revision are finalised
LPG OPERATIONS MANUAL
Note 1 – Vapour pressure may be determined at any other temperature and converted
to 40OC by means of suitable vapour pressure – temperature graph. The
same can also be determined by analysing the gas by means of a gas
chromatograph and then using the composition, the vapour pressure can be
calculated at 40OC from the standard values of vapour pressures at various
temperatures.
Note 3 - ‘Pass’ test indicates Hydrogen Sulphide not more than 5 ppm.
Note 4 – Subject to agreement between the purchaser and the supplier, odour
requirements of LPG may be changed for certain applications when
unodourized LPG is required.
Note 5 - Product shall contain 20 ppm minimum ethyl mercaptan at the first
despatching location to ensure the detection of odour.
ANNEXURE 22
Signature Signature
(Name) (Name)
Surveyor Master
*Tanker tank fitness certificate to be issued either by the master and surveyors, wherever
surveyor has been appointed.
LPG OPERATIONS MANUAL
ANNEXURE 23
Details of defects
Date HR/ST) Party Actu Pun sten Pun Ste meeting
a c c quality
c n
l h i h c
e l e i
d e d l
d e
d
ANNEXURE 24
LOCATION :
______________________________________________DATE
:_______________SHIFT :_______
CHECK NO CHECK -1 CHECK -2 CHECK -3 CHECK -4 CHECK -5
Time of checking
Filling Machine Observe Checke Observe Checke Observe Checke Observe Checke Observe Checke
no. d d by d d by d d by d d by d d by
variation variation variation variation variation
FM –1
FM -2
FM -3
FM -22
FM -23
FM -24
LPG PRESSURE
KG/CM2
AIR PRESSURE
(KG/CM2)
Checked by
Shift in Charge
Plant Manager
LPG OPERATIONS MANUAL
ANNEXURE 25
ANNEXURE 26
Average for
previous
month
generation O/F,
Lowest
achieved C/F
cylinders
LPG OPERATIONS MANUAL
ANNEXURE 27
Date Shift Total No. Categorywise Details of Defective Cylinders Analysis of Initials of
of Valve % Bung % Bung Body % Body O-Ring % O-Ring O-Ring % O-Ring Probable Causes Plant
Cylinders L V L L L L M M D andD Remedial Manager
Filled e a e e e e i i e Measures
e Taken
a l a a a a s s f f
k v k k k k s s e e
y e y y y y i i c c
n n t t
L g g i i
e v v
a e e
k
y
ANNEXURE 28
Date Name of the Truck No. Erv. No. Name of the No. of Cyls Remedial Initials
Transporter and Date Distributor Without O- measures Taken of PM
Ring
BACK
LPG OPERATIONS MANUAL
ANNEXURE 29
DATE:
Gross wt. Tare wt Net wt Diffe Valve Bung Body Due for Oth Remarks
in Kg renc leak leak leak 5yr test/ ers
O –Ring
Missing
O-Ring
defect
e in Hot
wt repair
LOCATION : COMMENTS:
Details Inspecting
Location-in-charge
Officer
Signature
Name
Designation
Time
n.b. Data to be recorded by the officer concerned in his / her own handwriting.
LPG OPERATIONS MANUAL
ANNEXURE 30
1.1 All pipelines, valves and fittings at LPG plant should be colour-doded as
per details given below.
1.2 Colour-coding is adapted to cover liquid LPG lines, LPG vapour lines, Pressure
Relief Valves, other valves/fittings, compressed air lines for pneumatic
operations and water service lines.
1.5 Pipeline, valves and fittings mounted on IOC’s LPG tank trucks should also be
colour coded as per above colour scheme.
2.2 One colour band of 500 mm width with lettering for service grade to
be painted as per colour scheme detailed in Clause 1.3 above.
For illustration, refer enclosed diagram.
2.4 Direction of flow also to be indicated on the pipelines with the help of arrows.
Arrows to be marked close to the colour bends.
2.5 The width of the additional bands for auto LPG and Propylene shall be 50 mm
each and spaced 25mm apart i.e from the center of the base colour band
two bands of 50 mm width on either side shall be provided and the same
shall be at a distance of 12.5 mm from the center of the base colour band.
20"
yellow
20"
D (LPG) VAPOUR D/2
green
20"
D COMPRESSED AIR D/2
grey
LPG OPERATIONS MANUAL
20"
D SERVICE WATER D/2
black
ANNEXURE 31
Serial number -
Name of location -
Date sample drawn -
Time sample drawn -
Type of product -
Sample drawn from -