GE Oil & Gas

Technical Proposal
Project: Pemex / Lakach / Fr5 Power Gen
Customer: PEMEX EXPLORACIÓN Y PRODUCCIÓN

Proposal Number: 13/UP/0911/R/E rev. 0


Contact Person: Mauro, Joao
Date: 30/12/2013

GE Proprietary & Confidential Information. This proposal is submitted in confidence for evaluation by the Buyer and its contents
are proprietary to GE. By receiving this document, the Buyer agrees not to reveal its contents except to those in the Buyer’s organization
who must evaluate it. Copies of this proposal may not be made without the prior written consent of GE. This proposal shall not be provided
to any Party outside of the Buyer’s organization. If the preceding is not acceptable, this proposal shall be returned to GE. The Buyer shall
return this proposal to GE if requested to do so by GE.

GE Oil & Gas


GE Proprietary & Confidential Information
GE Oil & Gas

Proposal Highlights
This section defines the basis of GE Oil & Gas technical offer for the supply of Power Generation train(s)
complete with relevant auxiliaries to be installed in MEXICO for PEMEX EXPLORACIÓN Y PRODUCCIÓN.

During the development of this technical offer we have made the greatest effort to comply with your
requirement, exploiting the experience that GE Oil & Gas has gained in the Gas Turbine Power Generation
market studying the best technical solutions in order to:

Ensure delivery time for the plant.


Optimize the operating conditions of the plant regarding both its reliability and performances.
Maximize the overall efficiency.
Minimize the life cycle costs.
Ensure the greatest operating flexibility.
We have prepared our proposal in response to your application requirements and have selected the following
GE Oil & Gas products to meet your needs:

2 MS5001PA Power generation train(s)


Each of the proposed units basically consists of:
Gas Turbine driver.
Gearbox.
Electric Generator.
Auxiliaries and BoP equipments.
The mechanical design of proposed units provides high reliability of all equipment to allow continuous
operation under the most severe duty.

The Gas Turbine package is engineered, manufactured and tested at GE workshops, under the supervision and
the responsibility of one Project Manager who will act as single contact for the Client.

GE engineers and QC specialists will carefully monitor the whole production cycle of these items with
scheduled audits, to ensure that all the design, manufacturing, procedures specified, NDT controls and any
other requirement of ISO 9001-2000 are fully met.
All testing activities supplied will be carried out in Florence or Massa workshops and in Electric Generator sub-
suppliers workshop.

GE Oil & Gas


GE Proprietary & Confidential Information
GE Oil & Gas

Table of Contents
CHAPTER A Scope of Supply
Scope Of Supply & Exclusions
A.1.1. Gas Turbine Package
A.1.2. Acoustical Enclosure
A.1.3. Air Inlet System
A.1.4. Exhaust Gas System
A.1.5. Lube Oil System
A.1.6. Cooling System
A.1.7. Gearbox
A.1.8. Electric Generator
A.1.9. Control System
A.1.10. Electrical System
A.1.11. Miscellaneous & Testing
A.1.12. Exclusions
A.1.13. Purchaser Connections
A.1.14. List of GE Oil & Gas Standards
A.1.15. Techs. Doc Order of Precedence
CHAPTER B Driver
GT Technical Description
B.1.1. MS5001 Technical Description
GT Performance
B.2.1. GT Performance
B.2.2. Simple Cycle Performance Curve
GT Data Sheet
B.3.1. MS5001 Data Sheet
CHAPTER C Driven Equipment
Gearbox and Coupling
C.1.1. Gearbox Data Sheet
Electric Generator
C.2.1. Electric Generator
CHAPTER D Control System
Descriptions
D.1.1. MK VIe Technical Description

GE Oil & Gas


Pag. I
GE Proprietary & Confidential Information
GE Oil & Gas

D.1.2. RM&D Service Description


Control System Drawings
D.2.1. HD GT Control System Schematic
D.2.2. HD GT CS Power Schematic
D.2.3. HD GT CS Layout
CHAPTER E Miscellanea
Utilities
E.1.1. Prel. Utility Consumption List
E.1.2. Electric Load List
Special Tools
E.2.1. Special Tools
Vendor Documents Register
E.3.1. Document and Drawing Format
E.3.2. Vendor Documents Register
Vendor List
E.4.1. Vendor List Statement
Manuals
E.5.1. Installation Manual
Site Container
E.6.1. Installation Site Container
Reference List
E.7.1. Reference List
Box & Packing
E.8.1. Box & Packing
CHAPTER F Instrumentation Technical Spec
GT Instrument Specification
F.1.1. MS5001 Instrum. Specification
Aux Instrument Specification
F.2.1. Aux Instrument Specification
CHAPTER G Auxiliaries
Auxiliaries Data Sheets
G.1.1. Lube oil air cooler data sheet
CHAPTER H Drawings
P&ID Diagrams
H.1.1. Gas Turbine P&ID

GE Oil & Gas


Pag. II
GE Proprietary & Confidential Information
GE Oil & Gas

Electrical System Drawings


H.2.1. Single Line Diagram
General Arrangement
H.3.1. General Arrangement
CHAPTER I Comment & Exceptions
C&E Introduction
I.1.1. C&E Introduction
Exceptions to Customer Spec
I.2.1. C&E to Customer Specifications
Exceptions to Intl. Stand
I.3.1. C&E to API 614
I.3.2. C&E to API 616
I.3.3. C&E to API 670
I.3.4. C&E to API 671
I.3.5. C&E to API 613
CHAPTER J Quality
Quality Control Plans
J.1.1. Quality Control Plans

GE Oil & Gas


Pag. III
GE Proprietary & Confidential Information
GE Oil & Gas

CHAPTER A

Scope of Supply

GE Oil & Gas


Pag. A
GE Proprietary & Confidential Information
GE Oil & Gas

Scope Of Supply & Exclusions

GE Oil & Gas


Pag. A.1
GE Proprietary & Confidential Information
GE Oil & Gas

Gas Turbine Package

MS5001 model GE Oil & Gas Heavy Duty Gas Turbine single shaft, simple cycle, ISO rated at 26060 kW.

The gas turbine package includes the following components.


Gas Turbine DLN combustion system including:
• Ten reverse flow type combustion chambers (axial orientation).

• Multiple fuel nozzles (primary and secondary nozzles).


• Two spark plugs with retracting electrode.
• Two ignition transformers.

On-base fuel gas system for natural gas, at the gas turbine inlet flange, in accordance with the GEI41040
specification and complete with the following equipment:
• Single "Y" inlet gas strainer.

• Combined gas stop/speed ratio and control valves.

• Gas header to nozzles.


• AISI316L fuel gas interconnecting piping within the unit skid.

• Instrumentation, valves and all necessary protection devices.


A multi-point structural steel baseplate, supporting the gas turbine and its auxiliaries, and the air inlet/exhaust
gas plenums. The gearbox, electric generator and associated auxiliaries are installed on a separate baseplate.
An epoxy painted carbon steel lube oil tank is located within the gas turbine baseplate and is suitable for
supplying lubricating oil to the gas turbine and associated auxiliaries, and the driven equipment.

The lube oil tank is transported empty.


Fully automatic starting system employing a medium voltage A.C. electric motor (450 KW approx.) and torque
converter.

Dry flexible type auxiliary coupling located between the gas turbine/axial compressor shaft and the accessory
gear.
Heavy duty, multi-shaft accessory gearbox located between the starting system and the gas turbine/axial
compressor shaft.
Turning device for axial compressor and gas turbine rotor (hydraulic ratchet).
Cooling and sealing air system (complete with porous filter and piping) with air extracted through a slot
between the stator blade platforms in the axial compressor.
Axial air compressor antisurge system.
Header and nozzles for compressor cleaning (on-line and off-line operation).

Bearing instrumentation:
• Velocity type vibration detectors (four seismic probes) to alarm and trip the unit -- installed on the
bearing #1 casing (two probes) and the bearing #2 casing (two probes).

GE Oil & Gas


Pag. A.1.1/1
GE Proprietary & Confidential Information
GE Oil & Gas

• Non-contacting vibration probes and proximitors (four Bently Nevada radial probes) for vibration
monitoring system.

• Non-contacting axial displacement probes and proximitors (two Bently Nevada axial probes) on thrust
bearing #1.
• Key phasor probe on gas turbine shaft (one probe).

• Bearing temperature detectors (Thermocouples) on journal bearing and thrust bearing oil drain lines.
• Two bearing metal temperature detectors (four TCs) on journal bearings #1 and #2.

• Two bearing metal temperature detectors on thrust bearing active side.


• One bearing metal temperature detectors on thrust bearing inactive side.
• Magnetic speed pick-ups for gas turbine (three probes).

All necessary wiring and cabling within the gas turbine skid limits and up to the junction boxes installed on
baseplates.
Electrical system suitable for ZONE 2, Gas Group II B, Temperature T3. DC motors will be Eexd.
Instrumentation devices suitable for ZONE 2, Gas Group II B, Temperature T3.

Equipment certification will meet the CENELEC standard.


Flexible type dry load coupling between gas turbine load gearbox, with associated non-sparking guard.

GE Oil & Gas


Pag. A.1.1/2
GE Proprietary & Confidential Information
GE Oil & Gas

Acoustical Enclosure

The proposed acoustical enclosure, suitable for Onshore outdoor covering the gas turbine and associated
auxiliaries, with removable panels manufactured in painted carbon steel material (according to class 0 per
DMG 26/6/84 – ISO/DIS 1182.2).

Mounted and anchored on the gas turbine baseplate, to assure acoustical abatement and thermal separation
from the outside environment.
The overall expected max sound emission level of the GT train enclosure is 85 dB(A) pressure level at 1.5
meter(s) from the unit enclosure, at 1.5 meter(s) height from ground level at free field over a reflecting plan.

The following equipments and systems are provided inside the enclosure:

Fire Detection System with 10 heat rise detectors (1ooN voting philosophy).
Catalytic gas detectors.

Fire resistant instrument cables in accordance with IEC 331 for firefighting system.

Access & maintenance doors, suitable for turbine auxiliaries assembly/removal.


Carbon steel fire fighting dampers installed on the ventilation inlet & exhaust.
Internal A.C. Normal and DC Emergency lighting system, as per GE O&G design suitable for the
conditions inside the GT enclosure.
Ventilation air inlet ducting of carbon steel (aisi 304l lagging) material, between the gas turbine inlet
air filter and the gas turbine enclosure.

Ventilation exhaust ducting of carbon steel (aisi 304l lagging) material, up to the turbine enclosure.

Two centrifugal fans (main and stand-by) of painted carbon steel material driven by EEx-n A.C. electric
motor.
A DC electric motor-driven emergency fan is not necessary.
Manual bridge crane for gas turbine auxiliaries removal and maintenance (excluding gas turbine
starting system and complete auxiliary gear box).

Fire Fighting System


Fire protection and HP CO 2 fire fighting system including CO 2 bottle cabinet, for initial and extended
discharge; in accordance with NFPA 12 Code, and piping and nozzles within the enclosure.
The fire fighting system is equipped with 100% spare capacity.
The bottle skid will be installed outside the GT enclosure by others. Interconnecting piping between
the gas turbine compartment and bottle cabinet will be provided by others.

NOTE Lifting device installed inside gas turbine enclosure for the maintenance / removal of gas turbine
engine is not provided.

Disassembly and removal of the gas generator components and power turbine components will be carried out
by an external lifting facilities (By Others), removing enclosure panels.

GE Oil & Gas


Pag. A.1.2/1
GE Proprietary & Confidential Information
GE Oil & Gas

Air Inlet System

Gas turbine air inlet system with In-Line configuration (above arrangement) in accordance with the preliminary
general arrangement included in our technical proposal. (The option for pre-assembly at the supplier's shop is
available to the Customer. Pre-assembly reduces the on-site filter house installation time by up to 70%. This
option will be quoted on request).
The inlet air system is made of aisi 316l and includes the following equipment:
• Multi-stage inlet filter with weather hood, complete with:
- First stage: rain hood + droplet separators of carbon steel material.

- Second stage: bag prefilter/ coalescer stage of carbon steel material.


- Third stage: high efficiency stage of carbon steel material.

• C.s. zinc plated supporting structure for air filter chamber.


• Ladders walkways and platform for air filter chamber inspection and maintenance.
• Necessary instrumentation and normal AC internal lighting.

• Air inlet silencer of aisi 316l material (Internal parallel baffle type Aisi 316l material).
• Air inlet ducts of aisi 316l material from silencer up to gas turbine intake plenum including 90° elbow.

• Expansion joint with frame material in aisi 316l.


• Aisi 316l intake plenum (above orientation).
• Walkways, ladders and platform to reach parts requiring servicing (ventilation fans and motors).

GE Oil & Gas


Pag. A.1.3/1
GE Proprietary & Confidential Information
GE Oil & Gas

Exhaust Gas System

The exhaust gas system is made of carbon steel material, internally lined with 409 stainless steel sheets, and
includes the following equipment:

• Carbon steel exhaust plenum (vertical orientation).


• Expansion joint (high temperature textile compensator type).
• Transition duct tapered section between expansion joint and silencer.

• Exhaust silencer (internal parallel baffle type).


• Vertical stack up to a height of approximately 18 meters from center line.

• Thermal insulation for personnel protection.

GE Oil & Gas


Pag. A.1.4/1
GE Proprietary & Confidential Information
GE Oil & Gas

Lube Oil System

Closed, forced-fed mineral lube oil system, in accordance with GE Oil & Gas standard design criteria, to supply
oil to the gas turbine and associated auxiliaries, the gearbox and the electric generator.

The mineral lube oil system is integrated into the gas turbine baseplate, and consists of the following main
equipment:
• Painted carbon steel lube oil reservoir integrated into the gas turbine structural steel baseplate. The
interior surfaces have a corrosion protection treatment (a coat of inorganic paint followed by a finish
coat of epoxy paint).

• Local instrumentation, gauge and pressure switch panel.

• Main lube oil pump shaft-driven by axial compressor through the accessory gearbox, suitable for
supplying lube oil to the gas turbine, gearbox and electric generator.
• Auxiliary lube oil pump driven by an AC electric motor. The pump is capable of meeting the total
requirements of the unit at full speed. In normal operation, this pump supplies lubricating oil during
the starting and stopping sequences.
• Emergency lube oil pump driven by a DC electric motor, which serves for cooling the gas turbine
bearings in the event of an AC power failure during the post-lubrication period.
• Lube oil electric heater.
• Twin β 12 μ c>1000 (as per ISO 16889) full flow oil filters complete with transfer valve.

• Pressure and temperature regulating valves.


• Instrumentation and protection devices.

• Interconnecting piping within the gas turbine and generator skids.

• Stainless steel AISI 316L lube oil piping for downstream filters. The lube oil piping for upstream filters,
oil filters and drain lines are of carbon steel, in accordance with GE Oil & Gas standard design.

Lube oil vapor separator with side channel blower (single fan operated type) complete with its own support
structure (fan of aluminum; filter casing, drain box, valves and piping of carbon steel). The lube oil vapor
separator will be installed outside the gas turbine/auxiliary skids.
Hydraulic oil system (high pressure oil system) for gas turbine hydraulic oil actuator devices, complete with:
• Shaft-driven main hydraulic oil pump.

• Twin full flow oil filter with transfer valve.

• Stainless steel piping within the gas turbine and auxiliary skids.
• Control valve, instrumentation and all protection devices.

GE Oil & Gas


Pag. A.1.5/1
GE Proprietary & Confidential Information
GE Oil & Gas

Cooling System

Double oil-to-air fin fan cooler mounted outside the gas turbine enclosure for lube oil and hydraulic
cooling system with the following features:

- AISI304 head material.


- AISI304L piping material.
- The lube oil cooler is complete with its own carbon steel supporting structure, walkways and
ladders to reach the parts requiring servicing (oil cooler and associated accessories will be
supplied loose, to be installed by others).

- Remote regulated valve VTR-1 to be installed on interconnecting piping.


Instrumentation, valves and all the necessary protection devices according to P&Id.

GE Oil & Gas


Pag. A.1.6/1
GE Proprietary & Confidential Information
GE Oil & Gas

Gearbox

Speed reduction gear horizontal off-set coupled to the gas turbine through a dry flexible type coupling, and
directly coupled to the generator through a quill shaft, is installed on generator skid and provided with the
following auxiliary facilities:

• 5100 / 1800 rpm ratio.


• Seismic vibration detector located on the gear case and connected to the turbine
monitoring/protection system.
• Fire detection/extinguishing system connected to the turbine control system.

• Non contacting vibration probes and proximitors (series 3300).


• Bearing embedded RTDs for bearing temperature control.

• Painting in accordance with Manufacturer’s standard specification.


• Testing and Inspections in accordance with Manufacturer’s standard QC Plan.

GE Oil & Gas


Pag. A.1.7/1
GE Proprietary & Confidential Information
GE Oil & Gas

Electric Generator

The electric generator is a synchronous machine with the following characteristics (please also refer to the
generator manufacturer proposals):

• CACA type.
• Nominal voltage: 13.8 kV.
• No. of phases: 3.

• No. of poles: 4.
• Frequency: 60 Hz.

• Nominal speed: 1800 RPM.


• All on-skid control cabling.
• Power factor (cos phi): 0.8.

• Insulation class: F.
• Temperature rise class: B.
• Fabricated structural multiple-point basement supporting the generator and the speed reduction
gear.
• Cooling air and stator winding RTDs and associated terminal junction boxes.
• RTD’s Duplex (White Metal on Bearing) for bearing temperature control.

• Seismic vibration detector connected to the gas turbine monitoring/protection system.

• Non-contact vibration probes and proximitors on bearings for monitoring only.


• Brushless excitation with necessary equipment suitable for excitation control.

• Ventilation fans on the generator shaft ends.

• Section with current and potential transformers (CTs & PTs) for metering and protection.
• Pressure Transmitter on NDE Bearing for Mineral Oil Pressure Control.
• Neutral earthing resistor.

Please note that above description is preliminary and is subject to modification in accordance with the
detailed generator spec.

GE Oil & Gas


Pag. A.1.8/1
GE Proprietary & Confidential Information
GE Oil & Gas

Control System

GE Oil & Gas will furnish a Unit Control Panel (UCP) suitable for the control and protection of the turbo-
generator unit and auxiliaries. The UCP and all other panels provided by GE Oil & Gas shall be installed (by
others) in a non-hazardous, air conditioned area.

The maximum acceptable cable length between the GTG and UCP is 300m.

The unit control panel will include the following primary equipment:
• Turbine control panel Speedtronics MARK VIe TMR suitable to manage:

- All gas turbine control & protection logic, including auxiliaries.

- Integrated generator control.


• Auxiliary control panel (ACP) containing the following items:
- One Fire & Gas Detection Monitor Rack (standard manufacturer).
- One 120 Vac / 24 Vdc power supply for F&G.
- One 17 inch color monitor.
- One rack mounted panel PC (industrial type).
- One keyboard with integrated pointing device.
- One A4 size dot matrix printer.

• Generator control and protection panel, including metering and synchronizing devices.
• Generator excitation board complete with Automatic Voltage Regulator (A.V.R.).

• One additional remote desktop HMI (industrial type).


Note:

Panels are certified for seismic zone 2 as per UBC. In case the seismic zone is higher than Zone 2, the proposed
panels are to be installed in a building acting as damper to meet Zone 2 seismic classification for equipment
installed inside.

GE Oil & Gas


Pag. A.1.9/1
GE Proprietary & Confidential Information
GE Oil & Gas

Electrical System

The electrical system includes the following items:


• DC battery system for entire supply, including Nicd vented batteries with 100% spare capacity (two x
100%), battery charger and DC distribution panel for the GTG DC auxiliary requirements.
Note:
Panels are certified for seismic zone 2 as per UBC. In case the seismic zone is higher than Zone 2, the proposed
panels are to be installed in a building acting as damper to meet Zone 2 seismic classification for equipment
installed inside.

GE Oil & Gas


Pag. A.1.10/1
GE Proprietary & Confidential Information
GE Oil & Gas

Miscellaneous & Testing

• Fuel gas skid with 2 x 100[%] scrubbers installed on separate skid and complete with the following
items:

- Solid particle filter (100% for Dp > 3µ -- 99.5% for 0.5µ < Dp < 3µ).
- Liquid particle filter (100% for Dp > 8µ -- 99.5% for 3µ < Dp < 8µ).
- Necessary instruments and control devices.

- Stainless steel piping within the unit skid of AISI316/316L dual stamped material.
• Anchor bolts, sole plates and leveling screws for supporting structures of gas turbine and auxiliaries.

• Stairs, ladders and walkways to access gas turbine and accessory skids.
• Painting in accordance with GE Oil & Gas and sub-supplier painting specifications.
• 2 paper copy(ies) and 1 cd-rom copy(ies) (total common to all packages) of operation and
maintenance manuals in accordance with GE Oil & Gas standard in Spanish language.
• Basic and detailed engineering for all Items included in GE Oil & Gas scope of supply.
• Job customer drawings and job documentation in Spanish language as per Vendor Document List.

• 1 combined water washing trolley(ies) suitable for on-line and off-line washing of gas turbine axial
compressor, common to all gas turbines.
• 1 special tools for gas turbine package maintenance, common to all gas turbines.
• 1 Set of Lifting beam and shackles for the entire supply (GT and driven equipment).
• Site container for installation.

• Commissioning & start-up spare parts for gas turbine. (see separate list)

• Packing for the entire supply in accordance with GE Oil & Gas standard packing specification, suitable
for six months outdoor storage.
• Tests and inspections in accordance with GE Oil & Gas Quality Control Plan.

• Q.A. activities in accordance with GE Oil & Gas Q.A. Manual.


• No-load standard mechanical running test for gas turbines in accordance with GE Oil & Gas standard
procedure.

• Functional test of control panel in accordance with GE Oil & Gas standard procedure.

GE Oil & Gas


Pag. A.1.11/1
GE Proprietary & Confidential Information
GE Oil & Gas

Exclusions

Equipment and services not listed under the above Scope of Supply are on Purchaser's responsibility.

The main exclusions from the GE Oil & Gas "Scope of Supply" include but are not limited to the following major
components:
• Lifting facilities installed inside/outside the gas turbine/auxiliary enclosure for disassembly/removal of
the gas turbine rotor and auxiliaries.

• Any gas turbine wet NOx abatement system (steam or water injection).
• Fuel gas heater.
• Fuel gas booster.

• Fuel gas analyzer.


• Any shut off valve/vent valve installed on Customer fuel gas piping.
• All process piping.
• All other interconnecting piping outside the gas turbine train skid edge limits.
• All vent and drain piping outside the gas turbine skid edge limits.

• All power cables.


• All interconnecting control cables between the gas turbine unit and the control room panels, cabling
and wiring.
• Local control cab.

• Step up transformer.

• Auxiliaries transformer.
• Circuit breaker.
• Bus duct /H.V. cables.
• Power management system.

• Control system relevant to the process equipment.

• Performance monitoring system.


• DC UPS Inverter.
• Low voltage MCC.
• AC UPS System.

• Medium voltage MCC.


• Engineering for foundations.
• Instrument air.

• Plant earthling system.


• Grouting system and materials for the turbocompressor unit foundations.

GE Oil & Gas


Pag. A.1.12/1
GE Proprietary & Confidential Information
GE Oil & Gas

• Fuel and consumable materials for unit testing at the site.

• All consumable materials.


• Flushing oil and flushing device necessary at the site.

• First filling lube oil.


• Capital spare parts.
• Any on-site tests for gas turbine packages.

• Hydrostatic testing for gas turbine casings (not feasible).


• Gas turbine post-test inspection (not recommended).
• Separate performance test of gas generator.

• Wrenches for gas turbine package maintenance.


• Gas turbine performance test in accordance with ISO 2314 or ASME PTC 22.
• String test (FSFL, FSNL, Partial Load).

• Erection, commissioning, start-up and testing activities to be performed at the site.


• Any civil works to be carried out at the site.

• Any on-site activities.


• Technical Advisors.

Gas Turbine site performance test in accordance with ASME PTC22/ISO2314 is excluded by the
standard GE O&G scope of supply.

In case the site performance test is required, Customer and GE O&G will hold dedicated discussion in
order to make sure full power delivered by the Gas Turbine can be absorbed by driven equipment and
associated process plant.

Anything not expressly indicated in the Scope of Supply.

GE Oil & Gas


Pag. A.1.12/2
GE Proprietary & Confidential Information
GE Oil & Gas

Purchaser Connections

The following points delimit the Scope of Supply:

• Inlet air system: suction side of inlet filter house (front of filter inlet).
• Exhaust gas system: flange at top of vertical stack of gas turbine.
• Exhaust ventilation air: flange on ventilation duct at the limit of the gas turbine enclosure.

• Drains/vents: all connections will be at the turbogenerator skid edge limits.


• Instrument air: on turbogenerator base/separate skid connections.
• Earthing: on turbogenerator base/separate skids/panels connections.

• Base frame: machined foundation plates under gas turbine/auxiliaries/generator base plate frame.
• Fuel gas: inlet flange of fuel gas system at gas turbine skid edge limit and inlet/outlet flange fuel gas
treatment skid.

• Lube oil: inlet/outlet flanges at turbogenerator skid edge limits.


• Cooler: inlet/outlet flanges at separate lube oil-to-air cooler edge limits.
• Electrical/Power supply:

- Junction boxes on turbogenerator baseplates/separate skids.


- Terminal strips of control panels.

- Motors: JBs on individual motors.

- Lighting.

GE Oil & Gas


Pag. A.1.13/1
GE Proprietary & Confidential Information
GE Oil & Gas

List of GE Oil & Gas Standards

The scope of supply is based on the GE Oil & Gas standard procedures/specifications listed below:

Gas turbine axial compressor washing general criteria (ITN 07831).


Earthing system in accordance with GE Oil & Gas Standard (ITN 04220).
Painting in accordance with GE Oil & Gas Standard (ITN 02173 & ITN 07810) and Sub-Supplier
standards.

Storage in accordance with GE Oil & Gas Standard (ITN 02175).


Marking, preservation and packing for shipping in accordance with GE Oil & Gas Standard (ITN 54750).

Instruction Manual in accordance with GE Oil & Gas Standard (ITN 00400).
Inspection and testing in accordance with GE Oil & Gas Standard Quality Control Plan.
• Dispatching of documentation in accordance with GE Oil & Gas standard procedure (ITN 00105).

• Specification for lines in accordance with GE Oil & Gas Standard (SOM 6612993).
Mineral Lube Oil in accordance with SOM17366, grade ISO VG32 ISO3448.
Fuel gas quality in accordance with GE Oil & Gas Document GEI41040.

• Gas turbine mechanical running test in accordance with GE Oil & Gas Standard (SOM 27553).
• Test certification in accordance with GE Oil & Gas Standard (ITN 07771).

The above mentioned procedures/specifications can be provided upon request.

GE Oil & Gas


Pag. A.1.14/1
GE Proprietary & Confidential Information
GE Oil & Gas

Technical Documentation Order of Precedence

In the event of any inconsistency among any of the technical documents listed in the Letter of Intent or
Purchase Order, the following order of precedence shall apply:

1) GE Oil & Gas Final Technical Proposal.


2) Material Requisition, as amended by GE Oil & Gas exceptions.
3) Requisition Data Sheets, as amended by GE Oil & Gas exceptions.

4) Project Specifications, as amended by GE Oil & Gas exceptions.


5) Project Procedures, as amended by GE Oil & Gas exceptions.

6) International Codes and Standards (API, ASME, ISA etc) specifically recalled in the contract (with GE Oil
& Gas comments and exceptions).
Notwithstanding anything to the contrary, GE Oil & Gas shall comply only with the specifications listed in the
Material Requisition as amended by GE's exceptions. It is understood and agreed between the parties that GE
Oil & Gas shall not be responsible to accomplish with the embedded specifications, unless such embedded
specifications are clearly mentioned & listed in the Material Requisition as applicable specifications.

GE Oil & Gas


Pag. A.1.15/1
GE Proprietary & Confidential Information
GE Oil & Gas

CHAPTER B

Driver

GE Oil & Gas


Pag. B
GE Proprietary & Confidential Information
GE Oil & Gas

GT Technical Description

GE Oil & Gas


Pag. B.1
GE Proprietary & Confidential Information
MS5001 Technical Description
Gas Turbine

GE Oil & Gas


Pag. B.1.1/1
GE Proprietary & Confidential Information
Introduction
The MS5000 heavy duty gas turbine is available in both single-shaft and two-shaft
versions.

The MS5001 (single-shaft - generator drive) is a compact and reliable prime mover,
designed for long life and ease of maintenance. It consists of a 17-stage, high efficiency,
axial-flow compressor coupled to a two-stage turbine and a combustion system with 10
chambers, able to burn a wide range of fuels, from liquid distillates to all gaseous fuels,
including low BTU gas and residuals. It also has a mixed fuel capability.

The design electric output is 26,300 kW base load and 27,830 kW peak load with a heat
rate of 12,650 kJ/kWh at ISO conditions (15°C, 60% Relative Humidity, at Sea Level) with
88.9 mm H2O inlet loss and 63.5 mm H2O exhaust loss.

It is a very suitable unit for combined cycle and cogeneration plants and can achieve very
high fuel utilization indexes allowing considerable fuel savings.

The gas turbine package consists of two compartments, one housing the gas turbine
engine and the other the auxiliaries. Both gas turbine and auxiliaries are mounted on a
common integral base-plate and have a common ventilation system. The accessory
compartment contains the mechanical auxiliaries, including both mechanically (via a
multi-shaft accessory gear) and electrically driven, the lube oil system, the fuel systems
and the gas turbine starting means. The turbine compartment is partially separated from
the accessory compartment by the combustion air inlet plenum.

GE Oil & Gas


Pag. B.1.1/2
GE Proprietary & Confidential Information
MS5001 Gas Turbine Engine
Axial Compressor
The MS5001 gas turbine has a 17-stage axial-flow compressor with two-position inlet
guide vanes (Custom 450 material). The compressor is constructed of individual forged
discs (AISI 403) fastened with through bolts.

The IGV (inlet guide vanes) and the first two stages of rotor blades and stator vanes are
uncoated Custom 450. From stages 3 to 7, the blades and vanes are AISI 403 GECC1
coated for corrosion protection, while the other blades and vanes (stages 8-17) are
uncoated AISI 403. The rotor blades have dovetailed bases of a wide angle design which
fit into the matching dovetail openings in the wheels. The stator vanes also have dovetail
shaped bases that fit into dovetail shaped openings in a two-piece, semi-circular ring.
Locking keys prevent rotation of the blade rings

The compressor rotor is dynamically balanced before assembling to the pre-balanced


turbine rotor components. The whole rotor assembly is then dynamically balanced.

Bleed air can be extracted from the 4th and the 10th rotor stages to:

- cool the turbine parts subject to high operating temperatures


- seal all the turbine bearings
- provide atomizing air for liquid fuel (if any)
- provide an operating air supply for control valves

GE Oil & Gas


Pag. B.1.1/3
GE Proprietary & Confidential Information
Combustion System
The MS5001 machine incorporates a reverse flow combustion system consisting of an
assembly of 10 combustion chambers with associated fuel nozzles, 2 spark plugs and 4
flame detectors.

The combustion chambers are arranged concentrically around the axial flow compressor
and are bolted to the compressor discharge section bulkhead. Air for combustion is
supplied directly from the axial-flow compressor to the combustion chambers. Fuel is fed
into the chambers through fuel nozzles that extend into each chamber's liner cap.
Combustion of the fuel and air mixture is initiated by retracting electrode type spark
plugs. The chambers without spark plugs are fired with flame from the fired chambers
through interconnecting crossfire tubes. The cap and liner are Hastelloy X material (nickel
based super alloy) while the external shell is carbon steel.

The 4 flame detectors are installed in the combustion system to actuate an alarm in case
a flame failure occurs.

High pressure air coming from the axial compressor is directed around the transition
pieces cooling the transition pieces and preheating the combustion air. The transition
pieces (Hastelloy X) direct the hot gas to the first-stage nozzle.

The combustion chamber system for the MS5001 gas turbine is available in both
standard and DLN (Dry Low NOx) versions.

GE Oil & Gas


Pag. B.1.1/4
GE Proprietary & Confidential Information
Standard system
The standard configuration consists of 10 reverse flow conventional diffusion
combustion chambers. The fuel is injected by each nozzle to multiple injection points in
order to obtain an optimum flame distribution. A dual fuel configuration is available as an
option. Water or steam injection can be used for NOx emission reduction or, in case of
steam injection, for power augmentation.

DLN system (Option)


Thermal NOx is generated within the liner when the temperature is higher than 1800°C.
NOx generation is tightly linked to the temperature and any slight temperature drop
results in a significant decrease in NOx without affecting the combustion efficiency.

The DLN (Dry Low NOx) system is based on ‘premix’ combustion chambers which burn a
‘lean premixed mixture’ of fuel and air in order to achieve a lower firing temperature and
therefore lower NOx emissions. Indeed the role of premixing is to obtain a homogenous
mixture with an equivalent ratio of 0.7 (1 is the stoichiometric ratio).

In the conventional mode of combustion with a diffusion flame, fuel is injected into a
turbulent mass of burning air and there are regions of wide ranges of equivalent ratios.
The high equivalent ratio regions will lead to high local combustion temperatures, which
generates high NOx levels.

The DLN System uses staged multi-nozzle combustors with special DLN valves to regulate
the distribution of fuel delivered to the different nozzles. During normal loading and
unloading the system will progress through different stages of operation from diffusion
up to the premix steady state (full load).

Water Injection (Option)


Injection of water into the liner is done to reduce the temperature in the primary zone.
The injection rate (water to fuel ratio) is a function of the desired reduction of the NOx
emission level.

Water injection affects the gas turbine performance with an increase in output, and a
decrease in efficiency (increase in heat rate).

The water injection device feeds each fuel nozzle assembly. A connecting device on the
outer face of the combustion chamber cover connects each nozzle to the water
manifold.

GE Oil & Gas


Pag. B.1.1/5
GE Proprietary & Confidential Information
Steam Injection (Option)
The steam injection rate (steam to fuel ratio) is a function of the desired reduction of the
NOx emission level.

Steam injection affects the gas turbine performance with an increase in output, and an
increase in efficiency (decrease in heat rate).

The steam injection device feeds each fuel nozzle assembly. A connecting device on the
outer face of the combustion chamber cover connects each nozzle to the steam
manifold.

Unlike injection for NOx reduction, in the case of steam injection for power augmentation,
the steam is injected into the compressor discharge casing.

GE Oil & Gas


Pag. B.1.1/6
GE Proprietary & Confidential Information
Turbine
The turbine section consists of a two-stage impulse turbine rotor. The first-stage, or high
pressure wheel and the second-stage, or low pressure wheel, are bolted together to make
up a single unit. These components, with associated air seal and deflectors, are contained
within the turbine shell.

Compressor fourth-stage extraction air is piped to cool the shell and then discharged at
the aft end of the shell to cool the aft surface of the second stage turbine wheel.

The first-stage nozzle assembly (uncoated FSX 414 ) consists of airfoil-shaped partitions
between an inner and outer sidewall. The nozzle assembly is divided into segments, which
are mounted in a retaining ring assembly that is fixed in the turbine shell by a clamping
ring.

The nozzle ring and partitions are cooled to reduce metal temperature using compressor
discharge air that is bled from the combustion chamber transition space.

The second-stage nozzle (uncoated FSX 414) with diaphragm assembly is located
between the first- and second-stage turbine wheels. It is supported by a clamping
arrangement in the turbine shell. The assembly has airfoil-shaped partitions between the
inner and outer sidewalls which direct the gas flow into the second-stage turbine buckets.
The buckets are designed with long shanks to isolate the turbine wheel rim from the hot
gas path. Precision cast buckets are used for each turbine stage with the second stage
incorporating an integral tip shroud. First-stage buckets are GTD111 with GT29+ coating,
while second-stage buckets are U500. Compressor discharge and extraction air are used
to cool the turbine wheels.

GE Oil & Gas


Pag. B.1.1/7
GE Proprietary & Confidential Information
Bearings
The gas turbine unit has two main bearings (one located in the inlet casing and the other
located in the exhaust frame) that support the compressor/turbine rotor. The No. 1
bearing assembly actually contains three bearings; loaded thrust (active), unloaded thrust
(non-active), and journal. The No. 2 bearing assembly contains only a journal bearing. The
bearing assembly consists of the oil seal system, an oil ring and the surrounding housing.

The main turbine bearings are pressure-lubricated by the lube oil supplied from the lube
oil header. The drain oil returns through passages in the bearing housing, and then into
the drain line to the oil tank.

The oil seals control the oil flow along the shaft. The seals consist of labyrinth packing of
teeth assembled at the extremities of the bearing assemblies.

Support Frame
The forward end of the gas turbine is supported by a flexible plate that is welded to the
base and bolted and doweled to the air inlet casing.

A rigid leg type support, close-fitted on a support trunnion, is provided on each side of the
turbine shell. The supports permit lateral and axial movement caused by thermal
expansion.

Gas Turbine Casing


The compressor casing encloses the compressor portion of the rotor and is divided into
four sections: the inlet, forward and aft sections, which are made of grey cast iron; and
the discharge section made of ductile iron. All of these sections are split horizontally to
facilitate servicing. The inlet section contains the inlet guide vane system and the No.1
bearing assembly.

The bearing casing is connected to the external casing with struts. The loads are then
transferred to the baseplate by the anterior mount.

The turbine casing, which is horizontally split, contains the two-stage turbine and the
transition piece.

The exhaust casing contains an inner casing which is externally cooled by air from the
compressor 4th stage. It also supports the rear bearing casing with struts.

GE Oil & Gas


Pag. B.1.1/8
GE Proprietary & Confidential Information
Baseplate
The unit is mounted on a structural steel baseplate made of two longitudinal H beams
connected by additional H-beams and steel plates.

The mineral oil tank, which contains the lube oil for the gas turbine and driven units, is
fabricated as an integral part of the base at its forward end. The mineral oil tank is made
of carbon steel with a special internal coating.

The following components are located on the baseplate:

- Load coupling
- Starting system
- Fuel system
- Oil system
- Accessory gear with coupling
- Inlet plenum
- Exhaust diffuser

Control System
The Mark VIe turbine control platform is the current state-of-the-art control for GE
turbines. It is designed with the flexibility to fit the entire scope of control, from the
stand alone core engine controller to the complete integrated control, protection, and
monitoring system for generator and mechanical drive applications of gas turbines.
It is also an ideal platform for integrating the balance of plant controls.

Control system architecture


The Mark VIe control system consists of a modular and expandable platform of
microprocessor-based modules, housed in 13 or 21 slot standard VME card rack(s). Each
card takes one slot except for the main processor, which can take one or two slots,
depending on the required options. Field I/O signals are wired to standard Termination
Boards (TB), which provide terminal blocks and passive signal conditioning. Connections
between termination boards and I/O cards are provided through multi-core cables
terminated with connectors on both ends.

GE Oil & Gas


Pag. B.1.1/9
GE Proprietary & Confidential Information
TMR Configuration
The Triple Module Redundant (TMR) system is based on three redundant Control Modules
"R", "S", and "T", completely separate and independent. Each Control Module is provided
with its own VME power supply, main processor card, communication card, I/O cards, and
IONet for all of the control, protection and monitoring of the gas turbine.

GE Oil & Gas


Pag. B.1.1/10
GE Proprietary & Confidential Information
Technical Data
Expected performance at ISO condition, 60% RU, NG = 100% methane, No Inlet/exhaust
losses, Base Load, Rated speed

DLN STD (Natural Gas) STD (Distillate2)


Shaft output 26600 26300 25800 KW
Efficiency 28,62 28,45 28,26 %
Heat rate 12580 12650 12740 KJ/KWhr
Exhaust gas flow 125,2 124,1 124,4 kg/s
Exhaust gas temperature 482,8 487 487 °C

Emissions
Combustion Type Dry/water/steam Load (%) Fuel NOx CO
STD Dry 100 NG 142 10
STD Water Injection 100 NG 42 10
STD Steam Injection 100 NG 42 10
STD Dry 100 D2 219 10
STD Water Injection 100 D2 65 10
STD Steam Injection 100 D2 65 10
DLN Dry 100 NG 25 25
Lean head (gas only) Dry 100 NG 114 10
Lean head (Dual fuel) Dry 100 NG 121 10
Lean head (Dual fuel) Dry 100 D2 186 10

GE Oil & Gas


Pag. B.1.1/11
GE Proprietary & Confidential Information
GE Oil & Gas

GT Performance

GE Oil & Gas


Pag. B.2
GE Proprietary & Confidential Information
GE Oil & Gas

B.2.1. Performance

B.2.1.1 Guaranteed Performance on Fuel Gas

GT model (1) MS5001PA-DLN

Operating Point Base load

Fuel Lakach, as described on item B.2.1.3


Electric Power at Electric Generator
20 470
Terminals (kW)
Heat Rate (Electric Generator)
13 875
(kJ/kWh) (2)

Notes:

1. The above guaranteed values do not take into account tolerance on instrumentation
used during the performance test.

2. The above guaranteed values do not take into account of additional electrical
auxiliary consumption. In case of additional electrical consumption, the provided
power and heat rate shall be recalculated accordingly.

3. Performance Data referred to GT in New & Clean condition.

4. In case performance test is purchased by Customer, it shall be clearly stated in the


contract that Customer will provide enough loads to reach GT base load; no
correction curves for guarantee verification from partial load will be provided.

5. The submitted gas fuel is feasible for start-up/ shut down and normal operation of the
GT.

6. Above performance considers that gas turbine generator is going to operate in Grid
Mode.

7. Heat Rate = Fuel Gas Consumption (LHV) / Output (kW).

GE Oil & Gas


Pag. B.2.1/1
GE Proprietary & Confidential Information
GE Oil & Gas

B.2.1.2. Basis for Unit Performance on Fuel Gas

The performance guarantees listed above are given at the gas turbine shaft output
and on the gear box and the electric generator expected efficiency. It is based on the
scope of equipment supply as defined in the proposal and as stated for the following
operating conditions and parameters:

Measurement Value
Atmospheric pressure Bars 1.00941
Ambient temperature °C 38
Relative humidity % % 80
Inlet system pressure drop mm H2O 100
Outlet static pressure @ ISO
mm H2O 100
condition
Gas Fuel heating value (LHV) kJ/kg 46595
Recommended Gas Fuel
°C 0 - 50
Temperature at TP100
Supply pressure Range at
Bar(g) 18.5 – 24
TP100
Combustion system DLN

Notes:

1. Gas turbine is operating at steady state base load.


2. Tests to demonstrate guaranteed performance shall be conducted in accordance
with ASME Modified Performance Test Procedure as defined in Seller’s GEK-107551.
3. Performance is measured at the gas turbine shaft output and checked on the electric
generator terminals.
4. Guarantees are based on new and clean condition of the gas turbine. New and clean
condition is defined by the following:
a. The gas turbine has less than 200 fired hours for natural gas.
b. The gas turbine has been subjected to an offline water/detergent wash
within 25 hours of the performance test.
5. Performance curves such as ambient effects curves after contract award. These
curves along with correction factors such as fuel property corrections are to be used
during the site performance test to correct performance readings back to the site
conditions at which the performance guarantees were provided.
6. Compressor air extraction from gas turbine = 0.
7. Gas Fuel Analysis composition used for guarantees: refer to item B.2.1.3.

GE Oil & Gas


Pag. B.2.1/2
GE Proprietary & Confidential Information
GE Oil & Gas

B.2.1.3. Emissions Guarantees

Gas feasibility
- The submitted fuel gas is suitable for Gas Turbine start-up / shut-down and normal
operation.
Gas supply conditions
- Minimum gas supply temperature should be at least 28°C above Dew Point.
Supply temperature range at TP100 for the submitted gas shall be between 0°C <-->
+50°C.
As the heavy hydrocarbons affect the dew point, in case of different heavy hydrocarbons
distribution respect to the submitted one the above fuel gas temperature range could be
modified.
- Gas supply pressure range @ TP100 shall be between 18.5 Bar(g) - 24 Bar(g) .

Guaranteed emissions

Guarantees on NOx equal to 26.25 ppmvd@15%O2 [70 ppmvd@5%O2] and CO equal to


112 ppmvd@15%O2 [300 ppmvd@5%O2] are respected with IBH installed, in Premixed
mode ONLY, within the green operating window shown here below.
The guarantees are valid for the whole ambient temperature range of 10°C and 41°C and
relative humidity of 80%.

GE Oil & Gas


Pag. B.2.1/3
GE Proprietary & Confidential Information
GE Oil & Gas

GE Oil & Gas


Pag. B.2.1/4
GE Proprietary & Confidential Information
GE Oil & Gas

pressure
low
Lakach Gas

0
Hydrogen H2 %Vol
Methane CH4 Mol Fr 90.4766 90.4766
Ethane C2H6 Mol Fr 5.4339 5.4339
Propane C3H8 Mol Fr 0.2362 0.2362
i-Butane C4H10 Mol Fr 0.0185 0.0185
n-Butane C4H10 Mol Fr 0.0197 0.0197
i-Pentane C5H12 Mol Fr 0.0056 0.0056
n-Pentane C5H12 Mol Fr 0.0037 0.0037
Neopentane C5H12 %Vol
n-Hexane C6H14 Mol Fr 0.0008 0.0008
n-Heptane C7H16 %Vol
n-Octane C8H18 %Vol
n-Nonane C9H20 %Vol
n-Decane C10H22 %Vol
n-Undecane C11H24 %Vol
n-Dodecane C12H26 %Vol
Ethylene C2H4 %Vol
Propylene C3H6 %Vol
1-Butylene C4H8 %Vol
i-Butene C4H8 %Vol
1-Pentene C5H10 %Vol
Benzene C6H6 %Vol
Toluene C7H8 %Vol
p-Xylene C8H10 %Vol
Ammonia NH3 %Vol
Hydrogen Sulfide H2S %Vol
Ethyl Mercaptan C2H6S %Vol
Sulfur Dioxide SO2 %Vol
Carbon Monoxide CO %Vol
Carbon Dioxide CO2 Mol Fr 0.2517 0.2517
Nitrogen N2 Mol Fr 3.5533 3.5533
Nitrogen Oxide NO %Vol
Nitrogen Dioxide NO2 %Vol
Oxigen O2 %Vol
Argon Ar %Vol
Water Vapor H2O %Vol

GE Oil & Gas


Pag. B.2.1/5
GE Proprietary & Confidential Information
GE Oil & Gas

EXPECTED PERFORMANCE PG5371 DLN Combustor

Load Condition BASE BASE BASE


Site Pressure bar 1.00941 1.00941 1.00941
Inlet Loss mmH2O 100 100 100
Exhaust Pressure Loss mmH2O 100 100 100
Relative Humidity % 80 80 80
Ambient Temperature deg C 10 16 22
Fuel Type Gas Fuel Gas Fuel Gas Fuel
Fuel LHV Kj/Kg 46595 46595 46595
Output kW 26915 25840 24595
Heat Rate (LHV) kJ/kWh 12510 12695 12920

Load Condition BASE BASE BASE


Site Pressure bar 1.00941 1.00941 1.00941
Inlet Loss mmH2O 100 100 100
Exhaust Pressure Loss mmH2O 100 100 100
Relative Humidity % 80 80 80
Ambient Temperature deg C 28 34 41
Fuel Type Gas Fuel Gas Fuel Gas Fuel
Fuel LHV Kj/Kg 46595 46595 46595
Output kW 23380 22230 20945
Heat Rate (LHV) kJ/kWh 13170 13435 13785

GE Oil & Gas


Pag. B.2.1/6
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. B.2.2/1
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. B.2.2/2
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. B.2.2/3
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. B.2.2/4
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. B.2.2/5
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. B.2.2/6
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. B.2.2/7
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. B.2.2/8
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. B.2.2/9
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. B.2.2/10
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. B.2.2/11
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. B.2.2/12
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. B.2.2/13
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. B.2.2/14
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. B.2.2/15
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. B.2.2/16
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. B.2.2/17
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. B.2.2/18
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. B.2.2/19
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. B.2.2/20
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. B.2.2/21
GE Proprietary & Confidential Information
GE Oil & Gas

GT Data Sheet

GE Oil & Gas


Pag. B.3
GE Proprietary & Confidential Information
PROJECT PEMEX PEP - LAKACH 2XGTG 20 MW

CLIENT PEMEX EXPLORACIÓN Y PRODUCCIÓN

COMBUSTION GAS TURBINE (API 616-4TH) Project No. Unit Type of Doc.Code & Progressive Rev Sheet
DATA SHEET
S I UNITS 1 of 10
1 APPLICABLE TO: X PROPOSAL PURCHASE AS BUILT ITEM
2 FOR PEMEX EXPLORACIÓN Y PRODUCCIÓN UNIT MR
3 SITE MEXICO SERIAL NUMBER
4 SERVICE NUMBER REQUIRED
5 X CONTINUOUS INTERMITTENT STANDBY DRIVEN EQUIPMENT Electric Generator
6 MANUFACTURER GE O&G X MODEL MS5001PA ISO RATING (3.17) 26.090 kW @ 5100 RPM
7 NOTE: INFORMATION TO BE COMPLETED: BY PURCHASER BY MANUFACTURER BY MFR IF NOT BY PURCHASER
8 GENERAL
9 CYCLE: REGEN X SIMPLE EXHAUST HEAT RECOVERY TYPE: X SINGLE SHAFT MULTI SHAFT
10 DRIVEN EQUIPMENT: NORMAL SHAFT, kW @ RPM RATED SHAFT kW @ RPM
11 OUTPUT SHAFT SPEED RANGE (4.1.5) X MIN 4947 X MAX 5100 RPM
12 DESIRED MINIMUM SITE POWER kW @ RPM
13 OPERATION ATTENDED UNATTENDED POTENTIAL MAXIMUM POWER (3.33) kW

14 PERFORMANCE LOCATION (4.1.19)


15 GAS TURBINE INCLUDING ALL LOSSES INDOOR X OUTDOOR GRADE
16 SITE NORMAL SITE SITE HEATED UNDER ROOF MEZZANINE
17 RATED DUTY MAX MIN UNHEATED PARTIAL SIDES
18 (3.45) (3.26) TEMP TEMP ELECTRICAL AREA CLASSIFICATION (4.1.14)
(2)
19 DRY BULB TEMP °C NON-HAZARDOUS X HAZARDOUS
20 RELATIVE HUMIDITY % APPLICABLE CODE: NEC 500 NEC 505 X IEC
21 BAROMETER mBAR CLASS: II GROUP: B TEMPERATURE CODE: T3
22 OUTPUT kW AREA CLASSIFICATION DIVISION X ZONE 2
Please Refer to Dedicated Section
23 HEAT RATE, LHV, THIRD PARTY CERTIFICATION REQUIRED
GT Performance Table
24 MJ/kW-HR X WINTERIZATION REQD
25 OUTPUT SHAFT SPEED RPM X TROPICALIZATION REQD (5.4.6.6)
26 AIR FLOW kg/SEC UNUSUAL CONDITIONS: X DUST FUMES
27 EXHAUST FLOW kg/SEC CORROSIVE AGENTS (4.10.1.1)
28 FIRING TEMPERATURE °C
29 GAS GEN. EXHAUST TEMP °C OTHER (5.5.3.4)
30 PT EXHAUST TEMP °C NOISE SPECIFICATIONS: (4.1.10)
(3)
31 CERTIFIED POINT (3.26) X APPLICABLE TO MACHINE: (5.7.4.1)
32 (1) INCLUDING STEAM WATER EFFECTS FOR SEE SPECIFICATION
33 EMISSION CONTROL AUGMENTATION (4.1.9) APPLICABLE TO NEIGHBORHOOD: (5.7.4.2)
34 STEAM FLOW kg/HR SEE SPECIFICATION
35 WATER FLOW m3/HR
36 PAINTING:
(1)
37 APPLICABLE SPECIFICATIONS: X MANUFACTURER'S STANDARD
38 X API 616 GAS TURBINES FOR THE PETROLEUM, CHEMICAL, OTHER
39 & GAS INDUSTRY SERVICES
40 GOVERNING SPECIFICATION (IF DIFFERENT) NOTE: All Data Sheets References to GG=Gas Generator,
41 SS = Single Shaft, and PT = Power Turbine
42 VENDOR HAVING UNIT RESPONSIBILITY (4.1.2) REMARKS:
(1)
43 Including GE Oil & Gas comments and Exception to

44 SHIPMENT: (6.4) API 616 STD.


(2)
45 DOMESTIC X EXPORT EXPORT BOXING REQUIRED Area around GT package shall be SAFE-AREA. Due to
46 X OUTDOOR STORAGE MORE THAN 6 MONTHS (6.4.1) ventilation air flow, area inside enclosure is consid. safe.
47 SPARE ROTOR ASSEMBLY PACKAGED FOR (6.4.3.10) During shut-down without ventilation uncertified
48 DOMESTIC X EXPORT SHIPMENT INSTRUMENTS will be powered off.
(3)
49 COMMENTS: Expected aver. sound level is 85dBA. Press level @1Mt
50 from GT enclosure, @1.5Mt elev in free field conditions

GE Oil & Gas


Pag. B.3.1/1
GE Proprietary & Confidential Information
PROJECT PEMEX PEP - LAKACH 2XGTG 20 MW

CLIENT PEMEX EXPLORACIÓN Y PRODUCCIÓN

COMBUSTION GAS TURBINE (API 616-4TH) Project No. Unit Type of Doc.Code & Progressive Rev Sheet
DATA SHEET
S I UNITS 2 of 10
1 FUEL SYSTEM (5.8)
2 TYPE X GAS (5.8.2) LIQUID (5.8.3) DUAL (5.8.1.5.1)
3 DUAL SYSTEM REQMTS (5.8.1.5.1) GAS/GAS GAS/LIQUID LIQUID/LIQUID
4 COMPLETE FUEL RECEIVING SYSTEM (5.8.1.1) MAXIMUM TIME ALLOWED TO COMPLETE TRANSFER SECONDS
5
[1] LIQUID FUELS (5.8.3)
6 GAS FUELS (5.8.2)
7 FUEL GRADE (5.8.3.3)
8 ASTM D1655 ASTM 0GT 1GT
9 FUEL ANALYSIS - MOL % (5.8.2.1) JET A A-1 B D2880 2GT 3GT 4GT
10 COMPOSITION: M.W. NORMAL STARTING ALT OTHER, INDICATE ANALYSIS BELOW (5.8.3.3 c)
11 AIR 29 LIQUID FUEL TREATMENT REQUIRED YES NO
12 OXYGEN 32 TREATMENT SYSTEM BY VENDOR OTHER
13 NITROGEN 38 FUEL TRANSFER EQUIP REQUIRED (5.8.1.4.5) YES NO
14 WATER VAPOR 18 HEATER REQUIRED (5.8.1.4.4) YES NO
15 CARBON MONOXIDE 28 LIQUID FUEL PRESS REQUIRED, MAX/MIN, BARg
16 CARBON DIOXIDE 44 FUEL ANALYSIS DATA (5.8.3.3) ASTM MEASURED
17 HYDROGEN 2 PROPERTY METHOD VALUE
18 METHANE 16 Please Refer to VISCOSITY, SSU @ 38°C D-445
19 ETHYLENE 26 Dedicated Section DISTILLATION DATA D-86
20 ETHANE 30 GT Performance Table 50% RECOVERY, °C MAX
21 PROPYLENE 42 END POINT, °C MAX
22 PROPANE 44 SULFUR CONTENT %WEIGHT, MAX. (SELECT APPL. METHOD)
23 I-BUTANE 58 BOMB METHOD D-129
24 n-BUTANE 58 LAMP METHOD D-1266
25 I-PENTANE 72 HIGH-TEMP METHOD D-1552
26 n-PENTANE 72 CARBON RESIDUE (ON 10%
27 HEXANE PLUS BOTTOMS) % WT. MAX.
28 CONRADSON D-189
29 TOTAL RAMSBOTTOM D-524
30 AVG. MOL. WT. COPPER STRIP CORROSION PLATE D-130
31 CORS AGNTS (5.8.2.3) PPM 3 HOURS AT 100°C MAXIMUM
32 CONTMNTS (5.8.2.2.1) PPM AROMATIC CONTENT D-1319
33 LHV MJ/Nm³ (5.8.2.4) ASH CONTENT D-482
34 FUEL PRESS.MAX/MIN, BARg SPECIFIC GRAVITY, 15°C D-1298
(3)
35 FUEL TEMPERATURE MAX/MIN, °C FLASH POINT, °C D-56
36 X FUEL PRESSURE REQUIRED POUR POINT, °C D-97
37 MAXIMUM/MINIMUM, BARg WATER D-95
38 COMPRESSION SYS REQD (5.8.1.2.2) YES NO FILTERABLE DIRT, MG/100ML D-2276
39 HEATER REQD (5.8.2.1) YES X NO TRACE METALS (ATOMIC
40 RATE OF CHANGE OF LHV (5.8.2.4) ABSORPTION PREFERRED) D-3605
41 SODIUM
42 REMARKS: POTASSIUM
[1]
43 FUEL GAS SHALL BE IN COMPLIANCE WITH GEI41040 VANADIUM
(3)
44 Fuel gas temperature required at battery limit: Min 28°C above dew CALCIUM
45 point temperature in any case above 0°C but no above 130°C LEAD
46 OTHER METALS
47 LOWER HEATING VALUE, MJ/kg D-2382
48
48 FUEL SYSTEM PIPING

49 BY PASS AND VENT VALVE (3.7.1.3) ISOLATION BLOCK VALVES X ANSI FLANGE RATING #300
50 TWIN Y-TYPE STRAINER WITH CONTINUOUS FLOW NACE MATERIAL STANDARDS (4.10.1.8)
51 TRANSFER VALVE (5.8.1.2.4)

GE Oil & Gas


Pag. B.3.1/2
GE Proprietary & Confidential Information
PROJECT PEMEX PEP - LAKACH 2XGTG 20 MW

CLIENT PEMEX EXPLORACIÓN Y PRODUCCIÓN

COMBUSTION GAS TURBINE (API 616-4TH) Project No. Unit Type of Doc.Code & Progressive Rev Sheet
DATA SHEET
S I UNITS SP 3 of 10
(1)
1 CONSTRUCTION FEATURES
2 X SPEEDS: MATERIALS OF CONSTRUCTION (4.10)
3 MAX. CONT. 5100 RPM TRIP 5610 RPM COMPRESSOR ROTOR BLADES 450GTD (st.0-1)- AISI403(12%Cr st.2-16)
4 X LATERAL CRITICAL SPEEDS (DAMPED) COMPRESSOR STATOR VANES 450GTD (IGV-1)- AISI403(12%Cr st.2-16)
5 FIRST CRITICAL RPM MODE SHAFT Ni Cr Mo V BLADE/VANE COATING GE CC1 on st2-6
6 SECOND CRITICAL RPM MODE TURBINE WHEELS OR
7 THIRD CRITICAL RPM MODE STAGE NOZZLES BLADES DISCS
8 FOURTH CRITICAL RPM MODE Cr Mo V Alloy
1 FSX 414 GTD 111+GT29
9 PROTOTYPE OR MODIFIED ROTOR SUPPORT (4.7.3.5) Steel Forging

10 TRAIN LATERAL ANALYSIS REQUIRED (D.1.3) Cr Mo V Alloy


2 FSX 414 Inconel 738
11 X TRAIN TORSIONAL ANALYSIS REQUIRED (2.7.4.5) Steel Forging

12 TORSIONAL CRITICAL SPEEDS:


13 FIRST CRITICAL During job activities RPM
14 SECOND CRITICAL During job activities RPM
15 THIRD CRITICAL During job activities RPM
16 FOURTH CRITICAL During job activities RPM COMBUSTORS LINER: Hast X (TBC Coating) - TRANSITION: Hast X
17 VIBRATION: (4.7.4.5) (7.2.3 o): COMPRESSOR CASING ASTM A48
18 ALLOWABLE TEST LEVEL: SHAFT MICRONS P/P COMBUSTOR CASING ASTM A516 - Gr 70
19 CASE mm/SEC TURBINE CASING ASTM A 395

20 X ROTATION, VIEWED FROM DRIVE END X CW CCW GAUGE BOARDS AND CONTROL PANELS
21 AIR COMPRESSOR:
22 STAGES 17 MAXIMUM TIP SPEED 332 m/SEC GAUGE BOARDS
23 TYPE Axial PRESSURE RATIO 10.5:1 X LOCATION BASE PLATE
24 CASING SPLIT (2.2.3) X AXIAL RADIAL CONTROL CONSOLES (5.4.5.1.1) ON-SKID OFF SKID LOCAL
25 ROTOR SOLID X BUILT UP X OFF SKID REMOTE
26 TURBINE: WEATHER PROTECTION REQUIRED YES X NO
27 STAGES 2 MAXIMUM TIP SPEED 438 m/SEC X SPECIFICATION GE / NP Standard (IP10)
28 CASING SPLIT (4.2.3) X AXIAL RADIAL ANNUNCIATOR REQUIRED (5.4.4.8.5)
29 ROTOR SOLID X BUILT UP X VISUAL DISPLAY UNIT (VDU) X KEYBOARD
30 COMBUSTORS: (4.3.2)
31 SINGLE X MULTIPLE, NUMBER 10
32 X GAS LIQUID DUAL FUEL
33 MAXIMUM ALLOWABLE TEMP. VARIATION °C CONTROL SYSTEMS
34 APPLICABLE PLANE TYPE (5.4.1.5)
35 FUEL NOZZLES PER COMBUSTOR 5 MECH PNEU HYDRA ELECTRIC X ELECTRONIC
36 WOBBE INDEX NO REQD (4.3.7) MAX MIN X MICROPROCESSOR BASED COMBINED

37 MAINTENANCE INTERVALS, HOURS X SIGNAL SOURCE 4-20 mA


38 HOT GAS PATH INSPECTIONS SENSITIVITY RANGE TO
39 X MAJOR OVERHAULS TIME OF AC OUTAGE PROTECTION MIN (5.4.1.6)
40 X COMBUSTION INSPECTION SHUT OFF VALVES FOR SHUT DOWN SENSORS (5.4.4.9)
41 X COMBUSTION INSPECTION + TRANSITION STARTING SYSTEM (5.4.2.1)
42 GOVERNOR (5.4.3) MANUAL SEMI AUTOMATIC X AUTOMATIC
43 X MFR'S STD. OTHER X MAKE GE MODEL MK VIe PURGE (5.4.2.2) MINUTES
44 CONSTANT SPEED VARIABLE SPEED SEPARATE SHUTDOWN VALVE TEST DURING OPERATION
(1)
45 ISOCHRONOUS DROOP FOR MULTIPLE SHAFT TURBINES, COMPLETE ALL APPLICABLE
46 REMOTE SHUTDOWN SIGNAL X ELECTRIC PORTIONS FOR EACH SHAFT.
47 PNEUMATIC HYDRAULIC NONE REMARKS:
48 MANUAL SPEED CHANGER, RPM MAX. MIN.
49 X MAINTAIN TURBINE SPEED UPON FAILURE OF CONTROL
50 SIGNAL OR ACTUATOR

GE Oil & Gas


Pag. B.3.1/3
GE Proprietary & Confidential Information
PROJECT PEMEX PEP - LAKACH 2XGTG 20 MW

CLIENT PEMEX EXPLORACIÓN Y PRODUCCIÓN

COMBUSTION GAS TURBINE (API 616-4TH) Project No. Unit Type of Doc.Code & Progressive Rev Sheet
DATA SHEET
S I UNITS SP 4 of 10
(1)
1 CONSTRUCTION FEATURES CONTINUED
2 BEARINGS AND BEARING HOUSINGS (4.8)
(2) (3) (3)
3 RADIAL BRG #1 BRG #2 THRUST ACTIV INACTIV
4 X TYPE Elliptical Elliptical X TYPE Tilting Pads Tilting Pads
5 X MANUFACTURER Kingsb. or Eq Kingsb. or Eq X MANUFACTURER Kingsb. or Eq Kingsb. or Eq
6 X LENGTH, mm 152.14 152.14 X UNIT LOAD (ULTIMATE), BAR > 54
7 X SHAFT DIAMETER, mm 202.5 202.5 UNIT LOAD (SITE RATED), BAR
8 X UNIT LOAD (ACT/ALLOW), BAR > 30 > 30 UNIT LOAD (MAX POTEN.), BAR
9 X BASE MATERIAL Carbon Steel Carbon Steel X NO. OF PADS/AREA, cm2 6 / 720 18 / 270
10 X BABBITT THICKNESS, mm MFR STD MFR STD X BASE MATERIAL Carbon Steel Carbon Steel
11 NO. PADS X BABBITT THICKNESS, mm MFR STD MFR STD
12 LOAD: BETWEEN/ON PAD X PIVOT: CENTER/OFFSET, % 10% CENTER
13 PIVOT: CENTER/OFFSET, % LUBRICATION: FLOODED X DIRECTED
14 DAMPER BEARING THRUST COLLAR: X INTEGRAL REPLACEABLE
15 BEARING MATERIAL
16 BEARING TEMPERATURE DEVICES SEE ATTACHED API-670 VIBRATION DETECTORS (4.8.5.3) SEE ATTACHED API-670
(*) (*)
17 (4.8.5.5) DATA SHEET RADIAL VIBRATION DETECTORS: DATA SHEET
18 X THERMOCOUPLES X TYPE No Contact X MODEL 3300
19 SELECTOR SWITCH & IND. BY: PURCH MFR X MFR BENTLY NEVADA
20 RESISTANCE TEMPERATURE DETECTORS X NO. PER BRG N° 1-2 2 TOTAL NO. 4
21 RESISTANCE MATERIAL OHMS X OSCILLATOR-DEMODULATOR SUPPLIED BY GT VENDOR
22 SELECTOR SWITCH & IND. BY: PURCH MFR X MFR BENTLY NEVADA X MODEL 3300
23 X LOCATION-JOURNAL BEARING X MONITOR SUPPLIED BY (5.4.7.8.2) GT VENDOR
24 NUMBER 2 EA PD EVERY OTH PAD PER EACH BRG X LOCATION UCP ENCLOSURE on MK VIe
25 OTHER TOTAL 4 TC X MFR BENTLY NEVADA X MODEL 3500
26 X LOCATION-THRUST BEARING SCALE RGE ALARM SET @ MICRONS
27 NO. (ACT) 2 EA PD EVERY OTH PAD PER BRG SHUTDOWN SET @ MICRONS TIME DLY SEC
28 OTHER TOTAL 2 TC AXIAL POSITION DETECTOR (4.8.5.3):
29 NO.(INACT) 1 EA PD EVERY OTH PAD PER BRG SEE ATTACHED API-670 DATA SHEETS (*)
30 OTHER TOTAL 1 TC X Non contact Proximity X MODEL 3300
31 X MONITOR SUPPLIED BY (5.4.7.5) G.T. Vendor X MFR BENTLY NEVADA X NO. REQUIRED 2
32 X LOCATION Control Panel ENCLOSURE X OSCILLATOR-DEMODULATOR SUPPLIED BY 3300
33 X MFR GE/NP X MODEL MK VIe X MFR BENTLY NEVADA MODEL
34 SCALE RANGE X ALARM SET @ 115 °C X MONITOR SUPPLIED BY (3.4.7.8.2)
35 SHTDWN X SET @ 130 °C TIME DLY SEC X LOCATION UCP ENCLOSURE
36 REMARKS: X MFR BENTLY NEVADA X MODEL 3500
(4)
37 API STD 670 to be applied including GE Oil & Gas Comment & SCALE RGE ALARM SET @ 60 MICRONS
Exceptions.
38 X SHTDWN X SET @ 80 MICRONS TIME DLY SEC
39 VELOCIMETER TRANSDUCERS
40 SEE ATTACHED API-670 DATA SHEETS
41 X MFR Vitec or Equivalent X MODEL 4033
42 X LOCATION Brg Casing#1/2 X NUMBER 2+2
43 X MONITOR SUPPLIED BY (3.4.7.8.4) GT VENDOR
44 X LOCATION UCP ENCLOSURE on MK VIe
45 X MFR GE X MODEL MK VIe
46 X SCALE RGE 0-25.4 mm/s X ALARM SET @ 12.5 mm/s
47 X SHTDWN X SET @ 25.4 mm/s TIME DELAY SEC

(1)
48 VENDOR SHALL INSTALL SEISMIC TRANSDUCERS ON CASING OF GAS TURBINE, GEARBOX AND GENERATOR
(2)
49 FOR THREE BEARING SHAFTS, USE A SEPARATE SHEET FOR THE EXTRA BEARING.
(3)
50 FOR ROLLING ELEMENT BEARINGS, MODIFY ENTRIES AS REQUIRED. SHOW L-10 BEARING LIFE.

GE Oil & Gas


Pag. B.3.1/4
GE Proprietary & Confidential Information
PROJECT PEMEX PEP - LAKACH 2XGTG 20 MW

CLIENT PEMEX EXPLORACIÓN Y PRODUCCIÓN

COMBUSTION GAS TURBINE (API 616-4TH) Project No. Unit Type of Doc.Code & Progressive Rev Sheet
DATA SHEET
S I UNITS SP 5 of 10
1 UTILITIES: CONNECTIONS
2 UTILITY CONDITIONS: TOTAL UTILITY CONSUMPTION:
3
3 STEAM: AUXILIARY DRIVERS HEATING COOLING WATER m /HR
4 INLET MIN BARg °C BARg °C STEAM LEVEL
5 NORM BARg °C BARg °C STEAM, NORMAL kg/HR
6 MAX BARg °C BARg °C STEAM, MAX Please Refer to kg/HR
3
7 EXHST MIN. BARg °C BARg °C INSTRUMENT AIR Dedicated Section Nm /HR
8 NORM BARg °C BARg °C MOTORS (AUXILIARIES) kW
9 MAX BARg °C BARg °C BATTERY CHARGERS GT Utility List kW
10 STARTING INJECTION HEATERS kW
11 INLET MIN BARg °C BARg °C PURGE (AIR OR N2) Nm3/HR

12 NORM BARg °C BARg °C TURBINE AIR EXTRACTION REQUIRED: (4.1.22)


13 MAX BARg °C BARg °C NM3/HR @ BARg
14 EXHST MIN. BARg °C MAXIMUM PRESSURE AVAILABLE AT MINIMUM SPEED: BARg
15 NORM BARg °C MINIMUM SPEED: RPM
16 MAX BARg °C DISCHARGE TEMPERATURE: °C
17 ELECTRICITY: (5.4.6.1) PILOT LIGHT INDICATORS COMPRESSOR EXTRACTION STAGE NUMBER:
18 MOTORS HEATING CONTROL SHUTDOWN REMARKS:
19 VOLTAGE Please Refer to
20 HERTZ Dedicated Section
21 PHASE GT Electric Load List
22 COOLING WATER:
23 INLET TEMPERATURE °C MAX RETURN °C
24 DESIGN TEMPERATURE °C
25 NORM PRESS BARg MIN RETURN BARg
26 DESIGN PRESS BARg MAX ALLOW D P BAR
27 WATER SOURCE
28 INSTRUMENT AIR PRESSURE DESIGN, BARg
29 MAX NORMAL MIN
30 REMARKS:
31
32
33
34
35
36
37

38 PURCHASER CONNECTIONS
39
40 DESIGN FACING FLANGED MATING FLG GAS
41 CONNECTION APPROVAL SIZE and POSITION OR & GASKET VELOCITY
42 REQUIRED RATING (4.4.1) STUDDED BY VENDOR M/SEC
43 (4.10.4.6.4) (4.4.1) (4.4.5.4)
44 INLET
45 EXHAUST
46 FUEL SUPPLY
47 STEAM
48 WATER
49
50
51

GE Oil & Gas


Pag. B.3.1/5
GE Proprietary & Confidential Information
PROJECT PEMEX PEP - LAKACH 2XGTG 20 MW

CLIENT PEMEX EXPLORACIÓN Y PRODUCCIÓN

COMBUSTION GAS TURBINE (API 616-4TH) Project No. Unit Type of Doc.Code & Progressive Rev Sheet
DATA SHEET
S I UNITS SP 6 of 10
1 INSTRUMENTS
2 INSTRUMENT INSTRUMENT TRANS-
CONTROL ROOM
MITTERS
3 TYPE LOCATION RECEIVERS
FURNISHED
FUNISHED BY
4 (Function) (Indication location) BY

Local gauge or MKVIe

CONTROL ROOM
(*)
Switch or trasmitter
DESCRIPTION

RECORDING

MK VIe UCP
INDICATING

LOCAL PANEL
(GAUGE BOARD)

VENDOR

VENDOR
OTHERS

OTHERS
LOCAL
VDU
6
.. 7
..8
..9
10
11 GAS GENERATOR OR SINGLE SHAFT GAS TURBINE
12 TACHOMETER(S) (No. 3)
13 D P AIR INLET SYSTEM
14 COMPRESSOR DISCHARGE PRESSURE
15 FUEL FILTER D P
16 FUEL SUPPLY PRESSURE
17 STARTING GAS SUPPLY PRESSURE
18 STARTING GAS EXHAUST PRESSURE
19 TEMP COMBUSTOR MEASUREMENT (6 PTS MIN) (4.3.2)
20 TEMP GAS TURB CONTROL PLANE (6 PTS MIN)
21 INLET AIR TEMPERATURE
22 TEMPERATURE, GG COMPRESSOR DISCHARGE
23 TEMPERATURE, THRUST BEARING OIL DRAIN (Common With Journal)
24 TEMPERATURE, EACH JOURNAL BEARING DRAIN
25 TEMPERATURE, FUEL MANIFOLD
26 TEMPERATURE, LUBE OIL RESERVOIR
27 FIRED HOUR METER
28 A) NUMBER STARTS COUNTER
29 B) START SEQUENCE TIMER
30 LUBE OIL RESERVOIR LEVEL
31 LUBE OIL PUMP PRESSURE INDICATORS (No. )
32 LUBE OIL COOLER OIL INLET TEMPERATURE
33 LUBE OIL COOLER OIL OUTLET TEMPERATURE
34 LUBE OIL COOLER COOLANT INLET TEMPERATURE
35 LUBE OIL COOLER COOLANT OUTLET TEMPERATURE
36 LUBE OIL FILTER D P
37 LUBE OIL PRESSURE EACH LEVEL (No. 2)
38 CONTROL OIL PRESSURE
39 SITE FLOW INDICATOR EACH DRAIN (No. )
40 INLET GUIDE VANE POSITION INDICATOR
41 EXHAUST DUCT DIFFERENTIAL PRESSURE INDICATOR
42 ENCLOSURE COOLING AIR EXHAUST TEMPERATURE
43 POWER TURBINE
44 TACHOMETER(S) (No. )
45 EXHAUST TEMPRTATURE (2 PTS MIN)
46 JOURNAL BEARING TEMPERATURE
47 THRUST BEARING TEMPERATURE
48 BEARING DRAIN TEMPERATURE SEE LINE 24
49 SITE FLOW INDICATOR EACH DRAIN (No. ) SEE LINE 39
50 LUBE OIL INLET PRESSURE
51 LUBE OIL INLET TEMPERATURE
(*)
LOCAL PANEL MEANS "MKVIe CONTROL PANEL"

GE Oil & Gas


Pag. B.3.1/6
GE Proprietary & Confidential Information
PROJECT PEMEX PEP - LAKACH 2XGTG 20 MW

CLIENT PEMEX EXPLORACIÓN Y PRODUCCIÓN

COMBUSTION GAS TURBINE (API 616-4TH) Project No. Unit Type of Doc.Code & Progressive Rev Sheet
DATA SHEET
S I UNITS SP 7 of 10
1 ALARMS AND SHUTDOWNS (5.4.4)

LIGHT ONLY
APPLIES (5.4.4.8.5) SENSING

INDICATING
TO: ANNUNCIATOR DEVICES TO
3
POINT IN BE FURNISHED
..4
5 DESCRIPTION VENDOR FURNISHED BY
CONTROL PANEL
(1)
6 SINGLE SEP
7 SHAFT PWR ALARM SHUT- VENDOR OTHERS
DOWN (2)
8 OR G.G. TURB.
9 RADIAL SHAFT VIBRATION (No. 2 Each BRG-Option)
10 AXIAL THRUST POSITION (No. 2)
11 OVERSPEED (No. 3) (Pick-Up sensors)
12 CASING VIBRATION (No. 2)
13 HIGH THRUST BEARING TEMPERATURE
14 HIGH RADIAL BEARING TEMPERATURE
15 LOW FUEL SUPPLY PRESSURE
16 HIGH FUEL FILTER D P
17 GAS TURBINE TEMPERATURE SPREAD HIGH
18 EXHAUST OVER TEMPERATURE
19 FAILURE OF OVER-TEMPERATURE SHUTDOWN DEVICE
20 HIGH INLET AIR D P EACH FILTER
21 COMBUSTOR FLAME-OUT (1)
22 CHIP DETECTOR, ANTI FRICTION BEARING
23 FAILURE STARTING CLUTCH TO ENGAGE OR DISENGAGE
24 LOW OIL PRESSURE (No. 2)
25 HIGH LUBE OIL TEMPERATURE
26 LOW LUBE OIL RESERVOIR LEVEL
27 HIGH LUBE OIL RESERVOIR LEVEL
28 HIGH OIL FILTER D P (No. 1)
29 LUBE OIL SPARE PUMP OPERATING
30 LOW CONTROL OIL PRESSURE
31 LOW STARTING GAS PRESSURE
32 ANTI-ICING SYSTEM - NOT OPERATING
33 LOW D.C. VOLTAGE
34 EMERGENCY D.C. PUMP OPERATING
35 RESERVOIR HEATER "ON"
36 IMPLOSION DOOR OPEN
37 EXTERNAL PERMISSIVE START SIGNAL
38 EXTERNAL SHUTDOWN SIGNAL
39 LOSS OF AUXILIARY COOLING AIR
40 LAMP TEST PUSH BUTTON
41 ENCLOSURE HIGH TEMPERATURE
42 CONTROL SIGNAL FAILURE
43 CONTROL SYSTEM ACTUATOR FAILURE
44 GOVERNOR FAILURE
45 ENCLOSURE VENT FAN FAILURE
46
47
48
(1)
49 VENDOR TO ADVISE METHOD OF ANNUNCIATION
(2)
50 VDU MAY USE MESSAGE INDICATOR

GE Oil & Gas


Pag. B.3.1/7
GE Proprietary & Confidential Information
PROJECT PEMEX PEP - LAKACH 2XGTG 20 MW

CLIENT PEMEX EXPLORACIÓN Y PRODUCCIÓN

COMBUSTION GAS TURBINE (API 616-4TH) Project No. Unit Type of Doc.Code & Progressive Rev Sheet
DATA SHEET
S I UNITS SP 8 of 10
1 ACCESSORIES SUPPLIED BY GAS TURBINE MANUFACTURER
2 STARTING AND HELPER DRIVERS (5.1) X GEARS: SEE SEPARATE API 613 GEAR DATA SHEETS (5.2.1.1)
3 X STARTER ONLY (5.1.1.2) STARTER/HELPER (5.1.1.3) X DRIVEN EQUIPMENT, SEE SEPARATE API DATA SHEETS
4 TYPE (5.1.1.1) X MOTOR STEAM TURBINE X FIRE PROTECTION EQUIPMENT (5.7.3.1)
5 GAS EXPANDER IC ENGINE HYDRAULIC TYPE HALON 1301 HALON 1211 X CO2 H2 O
6 GAS TURBINE X STARTER IS CLUTCHED (5.1.1.7) X TYPE OF SENSOR X NUMBER OF DETECTORS
7 HELPER RATING (5.1.2.2) kW UV / IR NUMBER
8 X STARTER RATING (5.1.2.1) 450 kW X HEAT RISE NUMBER 10
9 SHAFT TURNING DEVICE REQUIRED (5.1.3.1) ADDITIONAL LEVELS (5.7.3.2)
10 X MOTOR:
11 TYPE Induction RATING 450 kW MOUNTING PLATES (5.3)
12 MFR Later MODEL Later TYPE (5.3.1.1) SOLEPLATE X BASEPLATE

13 STEAM TURBINE (REFERENCE API DATA SHEETS) X SHIM PACK THICKNESS 44 mm (5.3.1.2.9)
14 MFR MODEL
15 KW MAX. STEAM FLOW kg/HR BASEPLATE (5.3.2)
16 TOTAL/START kg X FURNISHED BY G.T. Vendor (5.3.2.1)
(5.3.2.1)
17 GAS EXPANDER GAS TURBINE ONLY X EXTENDED FOR Auxiliaries
18 APPLICABLE SPEC. (5.1.1.6) SUB-SOLEPLATES REQUIRED (5.3.2.7) DRIP RIM
19 MFR MODEL COLUMN MOUNTING (5.3.2.4) (3-POINT) LEVELING PADS (5.3.2.3)
20 kW MAX. GAS FLOW kg/HR ENCLOSURES (5.7.5)
21 TOTAL/START KG X ENCLOSURE REQUIRED
22 GAS FOR EXPANSION TURBINE: REQUIREMENTS (5.7.5.1):
23 MIN MAX NORMAL X ACOUSTICAL
24 INLET PRESSURE, BAR WEATHERPROOF
25 EXHAUST PRESS, BAR SAFETY
26 GAS TEMPERATURE, °C INLET FIREPROTECTION
27 GAS TEMPERATURE, °C EXHAUST ADDITIONAL VENTILATION (5.7.5.6.3)
28 MOLECULAR WEIGHT COUPLINGS AND GUARDS (5.2.2)
29 SPEED CONTROL GOVERNOR PRESSURE REGULATOR SEE ATTACHED API-671 DATA SHEETS
30 YES NO X MANUFACTURER Kopflex X TYPE Diaphragm
31 INLET CONTROL VALVE FURNISHED X MODEL Later X GUARD SUPPLIED BY Vendor
32 STAINLESS STEEL PIPING MANIFOLD X MAXIMUM OUTSIDE DIAMETER Later mm
33 CARBON STEEL FLANGES X HUB WEIGHT Later kg
34 Y-STRAINER W/BREAKOUT FLANGES SPACER LENGTH mm SPACER WEIGHT kg
35 LOW SPEED CAPABILITY IDLING ADAPTER REQUIRED SOLO PLATE REQUIRED
36 (FOR COMPRESSOR CLEANING) X GUARD SUPPLIED BY G.T. Vendor
37 RELIEF VALVE PRESSURE SET POINT BARg TYPE: X FULLY ENCLOSED SEMI-OPEN OTHER
38 CASING MATERIAL LUBRICATING REQUIREMENTS:
39 SEAL TYPE X NON-LUBE GREASE CONT. OIL LUBE
40 QUANTITY PER HUB kg or m3/HR
41 INTERNAL COMBUSTION ENGINE
42 TYPE SPARK IGNITED DIESEL
43 APPLICABLE SPECIFICATION (5.1.1.6) REMARKS:
44 MANUFACTURER MODEL
45 SPEED RPM POWER kW
46
47 COMBUSTION GAS TURBINE
48 APPLICABLE SPECIFICATION (5.1.1.6)
49 MANUFACTURER MODEL
50 SPEED RPM POWER kW

GE Oil & Gas


Pag. B.3.1/8
GE Proprietary & Confidential Information
PROJECT PEMEX PEP - LAKACH 2XGTG 20 MW

CLIENT PEMEX EXPLORACIÓN Y PRODUCCIÓN

COMBUSTION GAS TURBINE (API 616-4TH) Project No. Unit Type of Doc.Code & Progressive Rev Sheet
DATA SHEET
S I UNITS SP 9 of 10
1 ACCESSORIES SUPPLIED BY GAS TURBINE MANUFACTURER
2 INLET SYSTEM EXHAUST SYSTEM
3 X AIR FILTER (5.5.4.1) EXTENT OF FURNISHED INSULATION (SEE SKETCH) (5.7.1.2)
4 INERTIAL TYPE SEPARATOR X MEDIA FILTERS (RELIEF) (DIVERSION) VALVE (5.5.6.8)
5 PAD TYPE PREFILTERS X COMBINATION EXHAUST HEAT RECOVERY SYSTEM (5.5.3.1)
6 SELF CLEANING (JET PULSE TYPE) X EMISSION CONTROL SYSTEM (5.5.3.1)
7 SINGLE STAGE WITH PROVISION FOR X EXHAUST SILENCER PLATE ELEMENT MATERIAL (5.5.5.2.3)
8 FUTURE EXTRA STAGES YES NO Stainless Steel
9 NORMAL DUST LOADING kg/Nm3/HR EMISSIONS SAMPLING SYSTEM (5.5.6.10)
10 X WIND DESIGN VELOCITY 109 km/HR X EXPANSION JOINT MFR Later TYPE Tex. Compens.
11 X SNOW LOAD 0 kg/m² X DUCTING GAUGE/MATERIAL 5 mm / C.S. OUTER + AISI409 INNER
12 X SEISMIC ZONE 2A X SILENCER MFR DP mm H2O
13 LOCATION: GROUND LEVEL X ELEVATED (5.5.4.6) HEAT RECOVERY DEVICE
14 X FILTRATION EFFICIENCY See Scope of Supply % (5.5.4.3) MFR TYPE D P mm H2O
15 X MAINTENANCE INTERVAL ON Condition MONTHS STEAM GEN: PRESS BARg TEMP °C
16 X CLEANING FREQUENCY ON Condition DAYS RATE kg/HR
17 IMPLOSION DOOR (5.5.4.5) MANOMETER MFR MODEL RANGE mm H2O
18 EVAPORATIVE COOLER (5.6.1.1) ANTI-ICING (5.5.3.10) ATMOSPHERIC RELIEF DEVICE (5.5.6.8)
19 LIQUID TO AIR EXCHANGER (5.6.2.2) TYPE MFR LOCATION
20 X WALKWAY, LADDERS, HANDRAILS REQUIRED (5.6.1.5) X SYSTEM SITE RATED PRESSURE DROP 100 mm H2O
21 X COMPRESSOR CLEANING SYSTEM, TYPE Crank W. (5.5.3.9)
22 X SILENCER PLATE ELEMENT MAT'L (5.5.5.1.4) AISI 316L ATMOSPHERIC EMISSIONS
23 X FILTER MFR. MODEL STATIC - Multistage X EMISSION SUPPRESSION SYSTEM REQUIRED (5.8.4.1)
24 @ 110% RATED AIR FLOW D P mm H2O NOx REQUIREMENTS (5.5.3.1.1)
25 CLEAN mm H2O ALARM mm H2O X NOx EMITTED See Note Below
26 COOLER MFR. MODEL DP mm H2O EMISSIONS REDUCTION METHOD (IF REQUIRED)(5.8.4.2)

27 EXCHANGER MFR (5.6.2.3) WATER INJECTION (5.8.4.4) SCR


28 MODEL DP mm H2O STEAM (5.8.4.4) X DRY COMBUSTOR
29 X DUCTING GAUGE / MATERIAL 5 mm / AISI 316L OTHER
30 X EXPANSION JOINT MFR TYPE Compensated SOx REQUIREMENTS
31 X SILENCER MFR DP mm H2O SULFUR CONTENT OF FUEL
32 MANOMETER MFR MODEL SOx EMITTED (BASED ON STATED SULFUR CONTENT)
33 RANGE mm H2O

34 X SYSTEM SITE RATED PRESSURE DROP 100 Expected mm H2O CO REQUIREMENTS


35 @ 110% RATED AIR FLOW X CO EMITTED
Please Refer
36 REMARKS: PARTICULATE REQUIREMENTS
to Dedicated Section
37 PARTICULATE EMITTED
GT Performance Table
38 UNBURNED HC REQUIREMENTS
39 UNBURNED HC EMITTED
40 APPLICABLE EMISSION CODES OR REGULATIONS
41 EPA - TITLE 40 - CFR OTHERS
42
43
44 SPECIALIZED INSTRUMENTS
45 TACHOMETERS: (5.4.7.2.2) SWITCHES: (5.4.4.8.2)
46 TYPE ELECTRICAL ELECTRONIC CIRCUIT SHALL
47 ANALOG X DIGITAL ENERGIZE DEENERGIZE TO ALARM
48 X MANUFACTURER Later ENERGIZE DEENERGIZE TO SHUTDOWN
49 OIL FILLED PRESSURE GAUGES (5.4.7.6) ENCLOSURES
50 EXPLOSION PROOF WEATHER PROOF

GE Oil & Gas


Pag. B.3.1/9
GE Proprietary & Confidential Information
PROJECT PEMEX PEP - LAKACH 2XGTG 20 MW

CLIENT PEMEX EXPLORACIÓN Y PRODUCCIÓN

COMBUSTION GAS TURBINE (API 616-4TH) Project No. Unit Type of Doc.Code & Progressive Rev Sheet
DATA SHEET
S I UNITS SP 10 of 10
1 INSPECTION AND TESTING; LUBRICATION, WEIGHTS
(1)
2 SHOP INSPECTION AND TESTS: (6.1.1) WIT- OBSER- LUBRICATION SYSTEMS (4.9)

3 REQ NESSED VED X SEE API 614 (With NP comments/Exceptions)


4 SHOP INSPECTION (6.1.2) X LUBE OIL VISCOSITY (4.9.8) ISO GRADE VG 32
5 CLEANLINESS (6.2.3.3) COMMON TO X GAS GENERATOR/SINGLE SHAFT TURBINE
(2)
6 HYDROSTATIC (6.3.2) FREE POWER TURBINE X LOAD GEAR
7 MECHANICAL RUN (6.3.3) X X DRIVEN EQUIPMENT X AUXILIARIES
8 CONTRACT IDLING (COMBINED) (SEPARATE) LUBE/SEAL SYSTEM (4.9.5)
9 COUPLING ADAPTOR(S) SYSTEM DESIGNED FOR SYNTHETIC LUBRICANT (4.9.2)
10 CONTRACT SHOP LUBE SPECIFICATION
11 PROBES PROBES COMMON TO GAS GENERATOR POWER TURBINE
12 VIBRATION PLOTS(6.3.3.3.4) LOAD GEAR DRIVEN EQUIPMENT
13 TAPE RECORD VIB DATA (6.3.3.3.6) AUXILIARIES
14 PERFORMANCE TEST (6.3.4.1)
15 COMPLETE UNIT TEST (6.3.4.2) FLOW PRESSURE HEAT LOAD
16 PACKAGE TEST(6.3.4.2.1) X OIL REQUIREMENTS m3/HR BARg MJ/HR

17 LOAD GEAR TEST (6.3.4.3) X GG OR SS TURBINE


18 SOUND LEVEL TEST (6.3.4.4) DRIVEN EQUIPMENT
19 AUXILIARY EQUIPMENT (6.3.4.5) GEAR
20 POST TEST INSPECTION (6.3.4.6) COUPLINGS
21 HYDRAULIC COUPLING INSP (6.3.4.7) POWER TURBINE
22 GOVERNOR RESPONSE TEST (6.3.4.8) TOTAL
23 SPARE PARTS (6.3.4.9)
24 FIRE PROTECTION (6.3.4.10) MOUNTING ARRANGEMENT
25 OTHER (6.3.4.11) CONSOLE COLUMN X BASEPLATE
26
(1)
27 MATERIALS INSPECTION REQUIREMENTS (6.2.1.3) WEIGHTS DRY
28 SPECIAL CHARPY TESTING (4.10.5.3) INSTALLED SHIPPING DIMEN
29 RADIOGRAPHY REQUIRED FOR WT. (kg) WT. (kg) LxWxH (m)

30 MAGNETIC PARTICLE REQUIRED FOR WHEELS TURBINE


31 LIQUID PENETRANT REQUIRED FOR COMPRESSOR ROTOR
32 ULTRASONIC REQUIRED FOR COOLERS (QTY 2)
33 WELD INSPECTION (4.10.4.6.1) BASE AND PIPING
34 WELDING HARDNESS TESTING (6.2.3.4) COMBUS. WRAPPER
35 STRTG. MEAN.& ACC.
(1)
36 MISCELLANEOUS: FILTER
37 VENDOR'S REVIEW & COMMENTS ON PURCHASER'S INLET PLENUM
38 PIPING & FOUNDATION (4.1.18) EXHAUST PLENUM
39 FINAL ASSEMBLY CLEARANCES (6.2.1.1 e) ATOM. AIR COM.
40 COORDINATION MEETING SITE (7.1.3) PIPING ARRANG.
41 SPEED-TORQUE CURVE (7.2.4-a) ON BASE ENCLOS.
42 INCREASE POWER FOR STEAM/WATER (7.2.4 b) TOTAL WEIGHT
43 EFFECTS OF AMB. COND. ON EXHAUST FLOW (7.2.4 c) MAX ERECTION
44 RUN DOWN CURVES (7.2.4 d) WEIGHT (kg) ITEM
45 PURCHASER REVIEW OF CAMP./GOODMAN DIAG. (4.5.3.3) MAX MAINTENANCE
46 VENDOR WITNESS ALIGNMENT (4.1.18) WEIGHT (kg) ITEM

47 TECHNICAL DATA MANUAL (7.3.6.4) REMARKS:


(1)
48 NUMBER OF PROPOSAL COPIES (7.2.1) Test and inspections will be carried according to GE O&G quality
49 control plan.
(2)
50 On piping speeds only, not applicable to GT

GE Oil & Gas


Pag. B.3.1/10
GE Proprietary & Confidential Information
GE Oil & Gas

CHAPTER C

Driven Equipment

GE Oil & Gas


Pag. C
GE Proprietary & Confidential Information
GE Oil & Gas

Gearbox and Coupling

GE Oil & Gas


Pag. C.1
GE Proprietary & Confidential Information
Preliminary information. A Load gear data sheet will be made
according to project requirements, during engineering phase.
For information only.

GE Oil & Gas


Pag. C.1.1/1
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. C.1.1/2
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. C.1.1/3
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. C.1.1/4
GE Proprietary & Confidential Information
GE Oil & Gas

Electric Generator

GE Oil & Gas


Pag. C.2
GE Proprietary & Confidential Information
GE Power Conversion

1. Technical
ITEM 1.1 – Synchronous Generator:
- (2) Synchronous generators, with brushless exciter mounted on the generator’s shaft, 21400 kW, 26750 kVA
(at 38°C of air inlet temp), 0.80 power factor, 4 poles, 60 Hz, 13800 V, 1800 rpm, IP56 TEAAC (Totally Enclosed
Air to Air Cooled), insulation class F, 1.0 service factor, 40 degrees C ambient temperature range, with class B
temperature rise.

Accessories and Components:

- (1) Set of space heater thermostat controlled


- (6) Stator winding temperature detector, type simplex RTD Pt 100 Ohm (0 °C), 2 per phase
- (2) Bearing temperature detector, type duplex RTD Pt 100 Ohm (0 °C), 1 per bearing
- (1) Lube oil sight flow glass, 1 on NDE bearing
- (4) Cooling air temperature detectors, type simplex RTD Pt 100 Ohm, 2 for hot air and 2 for cold air
- (1) Line side cubicle including the following:
A) 1 CT 15VA 1500:1A Cl 0,5 for AVR
B) 3 CTs 30VA 1500:5A 5P20 for Protections
C) 3 CTs 30VA 1500:5A 5P20 for Diff. Protection
D) 3 VTs with 2 secondary
E) (3) Surge Arrester
F) (3) Surge Capacitor
G) (1) Set of space heater – 120V – 1Ph
- (1) Neutral Side Cubicle including the following:
A) 3 CT 15VA Cl. 0.5-FS: 5 for measurements
B) 3 CT 30VA 1500:5A 5P20 for differential protection
- (1) Neutral Side Cubicle (to be installed in a safe area) including the following:
A) 1 Neutral Grounding Resistor 10A-10s (with transformer)
- (1) Set of auxiliary junction boxes of stainless steel 316
- Generator Excitation Panel with redundant AVR with PSS (Optional price)
- 1 x 100% capacity air-to-air heat exchangers with 3 blowers (no redundancy)
- Rotor Removal Tool (Shaft extension only)
- Standard Painting
- PMG
- (1) Set of Bently Nevada 3300 Series Proximity Vibration Probes and Proximitors, Extension Cable and Junction
Box – 2 probes and 2 proximitors per bearing
- (1) Set of Bently Nevada Velometer
- Base + Gearbox installation without noise enclosure for gearbox and fire-fighting system. (Optional price)
- GDS (will be sent as loose equipment to be mounted by customer)
- Insulation suitable for 15kV
- Final engineering documents in Spanish language

This document contains GE Confidential Information. The receipt of this proposal shall not share this document or its contents with any third party without GE’s written consent.

Page 2 of 13
GE Oil & Gas
Pag. C.2.1/1
GE Proprietary & Confidential Information
GE Power Conversion

Generator Marks and Certifications:

- Installation in Class 1, Division 2 Group D (certified by CSA)


- ITN 62010/A, ANSI, NEMA MG-1
This request for quotation meets the above standards and certifications and does not guarantee additional
country compliance requirements. Additional technical regulations and standards may apply based on
requirements of the end destination. Evaluation will be necessary if the end destination mandates additional
requirements, which may lead to additional lead time, cost and, in some cases, restrictions on sale.

This document contains GE Confidential Information. The receipt of this proposal shall not share this document or its contents with any third party without GE’s written consent.

Page 3 of 13
GE Oil & Gas
Pag. C.2.1/2
GE Proprietary & Confidential Information
GE Power Conversion

ITEM 1.2 – TEST


The tests will be executed with the equipment completely mounted.

Tests during Manufacturing (non-witnessed and included on Generator Price)

• Ultrasonic inspection of the shaft forging


• Hydrostatic test on the water coolers
• Insulation between conductors (Surge Comparison test) after manufacturer of the coils and before coil-to-coil
connections
• Dielectric tests at the end of the bars after assembling (in rotor)
• Impedance measurement with rotor withdrawn
• Polarity of field coils
• Air gap measurement

Routine Test (Included in the Generator Price)

• Insulation resistance measurement of generator windings, exciter windings, heaters and temperature
detectors.
• Resistance measurement
• Terminal markings and direction of rotation
• Vibration tests complete
• Dielectric tests on generator windings, exciter windings, heaters and temperature detectors.
• Measurement of losses, at full load and at ¾ load
• No load losses/current
• No load saturation test
• Sustained three phase short circuit current / Short-circuit characteristic determination
• Sub transient and transient reactance value verification at reduced voltage
• Bearing temperature rise
• Over speed test
• No load saturation test
• Visual Check of dimensions
• Check of auxiliary circuits
• Check of thermo-elements
• Inspection of bearings
• Measurement of bearing insulation

Type Test (

• Measurement of losses
• Efficiency calculation at ¾ and full load
• Determination of reactances and time constants
• Check of wave form and voltage distortion
• Heat run test per IEEE 115 method 4

This document contains GE Confidential Information. The receipt of this proposal shall not share this document or its contents with any third party without GE’s written consent.

Page 4 of 13
GE Oil & Gas
Pag. C.2.1/3
GE Proprietary & Confidential Information
GE Power Conversion

Item 1.3 – EXCLUSIONS (out of scope)


Following materials and/or services are excluded from this proposal:
not included in generator manufacturer, but included in GE O&G scope of supply. Please refer to the
- Control panel control system chapter attached to the technical proposal.
- Start up and erection supervision Please refer to the GE commercial proposal.
- Generator Start up and commissioning supervision Please refer to the GE commercial proposal.
- Control project for the mechanical auxiliary services: exhaustion systems, compressed air, lubrication, drinkable
water, etc;
- Electric installation project, starting from the command situations of the mechanical auxiliary services: exhaustion
system, compressed air, drinkable water, etc;
- Civil and Mechanic project of the Power House and Substation;
- Electro Mechanic Project for substation and of Power House;
- Equipment erection /electromechanical connections;
- Jacking down over foundation blocks;
- Internal connection of the power plant equipment, substation, mechanical auxiliary services;
- Wiring "diagram from - To";
- Estimate of control cables for AC and DC;
- Short circuit study, coordination of protection relay settings;
- Sub-automatisms of the generating unit, such as: regulator oil pumps, circulation pumps of limp oil, brake, emergency
floodgate, of speed, Power;
- Special tools for commissioning or operation for proposal equipment; for special tools, please refer to the technical
- Plant (turbine + generator) etc; proposal scope of supply chapter.

- External wiring and connections;


- Terminals for cables;
- Specialized and not specialized labor for assembly, field tests and initial equipment operation;
- Supervisory System as well as any acquisition unit;
- Material installation, group control, lap/top, commissioning, start up and assembly supervision / assembly in field;
- Buses and cables AC/DC for the connection of the excitation system to other panels as control and protection, and
the generator;
- Generator or system stability study;
- Modifications and changes on project and or drawings after site installation/test;
- Retrofit/Update of existing equipment;
not included in generator manufacturer, but included in GE O&G scope of supply. Please refer to the
- Turbine control; control system chapter attached to the technical proposal.
- Measure, protection panel and synchronizing panel; not included in generator manufacturer, but included in GE O&G scope of supply
- Generator Protection; not included in generator manufacturer, but included in GE O&G scope of supply. Please refer to
the control system chapter attached to the technical proposal.
- Cable Glands;
- Rotor temperature monitoring system complete with auxiliaries
- On-line partial discharge measurement for stator winding with all the necessary auxiliaries,
- Rates for assistance to Generator startup and commissioning
- Jacking Oil System
- Other items not specifically mentioned
- 3rd Party certification

This document contains GE Confidential Information. The receipt of this proposal shall not share this document or its contents with any third party without GE’s written consent.

Page 5 of 13
GE Oil & Gas
Pag. C.2.1/4
GE Proprietary & Confidential Information
GE Power Conversion

Item 1.4 - DECS-200N Redundant Regulator Excitation System with PSS:

Basler DECS-200 Voltage Regulator System


Basler Electric DECS-200 based digital automatic voltage regulator system - with remote control provisions - consisting
of the devices itemized below, mounted and wired and tested in one enclosure - for use with a brushless synchronous
generator.
The DECS-200 has a continuous current rating of 15 amperes, with a 10-seconds forcing rating of 200 volts (When
powered from a 240VAC 3 phase source at 3070KVA). For operation at ambient temperatures up to 40°C.
The equipment consists of enclosure, IP 31, measuring approximately 30”W x 30”D x 90”H and weighting
approximately 600lbs, containing:
Two DECS-200 digital excitation controller, with the following features:
Var and Power Factor Controller
Field Current Regulator
Voltage Regulation 0.25%, true RMS sensing
Power Bridge-15 Ampere Capacity
Under excitation limiter (UEL)
Stator Current Limiter (SCL)
Over excitation limiting (OEL)
Protection
Over/undervoltage
Field overvoltage
Field overcurrent
Loss of voltage sensing to internal FCR Mode (Manual)
Rotating Diode Fault Detector (ripple detector)
Metering, real time at local LCD or at personal computer
Reference Adjusters: AVR, FCR, Var/PF
Preposition setpoints (maintain or release)
Setpoint position indication
RS-485 communication for monitoring, annunciation, control
Control
Front panel keypad switches
Provisions for external hardwired contacts and switches
Software through personal computer
Local/remote interface
Start/stop relay
AC/DC Control power module
Control Power Isolation Transformer
Standard Factory Tests
One Set DECS-200 BESTCOMS Software – compatible with Windows™

This document contains GE Confidential Information. The receipt of this proposal shall not share this document or its contents with any third party without GE’s written consent.

Page 6 of 13
GE Oil & Gas
Pag. C.2.1/5
GE Proprietary & Confidential Information
GE Power Conversion

Item 1.5 – Data Sheet

DATA SHEET SYNCHRONOUS GENERATOR


Customer: GE OIL AND GAS
Project:
Proposal Number:
Item: 1 Quantity: 1
Driven by: GasTurbine Power Generator
Max. Altitude: <1000 m.s.n.m. Air Temperature: 38 °C
Estimated Frame Size: 9000 Bearing Type: Sleeve
Type: ATB Bearing Lubrication: Recirculating oil
Poles Number: 4 Total End Play: 0.5 in
26750 kVA Load (%) P.F. (pu) Efficiency (pu)
Rated Output:
21400 kW 115 --- ---
Speed: 1800 RPM 100 0.80 0.972 *
Rated Voltage: 13800 V 75 0.80 0.970 *
Frequency: 60 Hz 50 0.80 0.955 *
Phases Number: 3 Xd: 1.57 Xq: 0.79
Reactances
Enclosure/Cooling: IP 56 TEAAC X'd: 0.24 X''q: 0.19
Unsaturated (pu):
Stator Conection: Y X''d: 0.16 Xd sat: 1.47
Service Factor: 1.00 Total Weight (estimated): 58000 kgf
Duty Cycle: Continuous Rotor GD2 (estimated): 8900 kgf.m²
Rotor Pole Type: Salient with Solid Poles Outline Number: Later
Stator Ins. Class: F Rotation Opp. D.E.: CCW
Stator Temp. Rise: 80 ° C by Res
Rotor Ins. Class: F Type: Brushless
Rotor Temp. Rise: 80 ° C by Res Excitation: Rated Output: 50 kW
Rated Current: 1119 A Rated Voltage: 60.2 V
Short Circ. Ratio: 0.6 *
Coupling Type: Rigid

Additional Generator Data:


- Maximum overspeed 2160 RPM (120% of synchronous speed).
- The generator bearings need recirculating lubrication, however the system is not included in our scope of supply.
- The generator bearings will use recirculating oil provided by the turbine oil system.
- Design offered is salient pole rotor construction
* Performance parameters according NEMA Std.

Tests:
According to Item 1.2

Accessories:
According to Item 1.1

Prepared by: Marila Revision Number: 0


Date: Dec/12/2013 Date: Sheet 1 of 1

Preliminary data (estimated values, to be confirmed after final desing):


Heat Exchanger load consumption: 3 blowers x 12.5kW (each)
Efficiency @ 25% load: 0.935 pu
The total harmonic distortion of the open circuit line to line terminal voltage will not exceed 5%, according to NEMA
MG-1 Part 33, item 33.3.4.3.

Estimated Brushless consumption: 5kW


This document contains GE Confidential Information. The receipt of this proposal shall not share this document or its contents with any third party without GE’s written consent.

Page 7 of 13
GE Oil & Gas
Pag. C.2.1/6
GE Proprietary & Confidential Information
GE Power Conversion

Item 1.6 – Curves (estimated)

This document contains GE Confidential Information. The receipt of this proposal shall not share this document or its contents with any third party without GE’s written consent.

Page 8 of 13
GE Oil & Gas
Pag. C.2.1/7
GE Proprietary & Confidential Information
GE Power Conversion

This document contains GE Confidential Information. The receipt of this proposal shall not share this document or its contents with any third party without GE’s written consent.

Page 9 of 13
GE Oil & Gas
Pag. C.2.1/8
GE Proprietary & Confidential Information
GE Power Conversion

This document contains GE Confidential Information. The receipt of this proposal shall not share this document or its contents with any third party without GE’s written consent.

Page 10 of 13
GE Oil & Gas
Pag. C.2.1/9
GE Proprietary & Confidential Information
GE Oil & Gas

CHAPTER D

Control System

GE Oil & Gas


Pag. D
GE Proprietary & Confidential Information
GE Oil & Gas

Descriptions

GE Oil & Gas


Pag. D.1
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. D.1.1/1
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. D.1.1/2
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. D.1.1/3
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. D.1.1/4
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. D.1.1/5
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. D.1.1/6
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. D.1.1/7
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. D.1.1/8
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. D.1.1/9
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. D.1.1/10
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. D.1.1/11
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. D.1.1/12
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. D.1.1/13
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. D.1.1/14
GE Proprietary & Confidential Information
GE Oil & Gas

RM&D for New Equipment

RM&D System description


The Remote Monitoring and Diagnostics (RM&D) System„s goal is to collect and archive equipment operating
data making them available to RM&D engineers and the project manager community. Data collection,
reprocessing, and fault detection are carried out using the On Site Monitor (OSM). The OSM is a server grade PC
equipped with operating system and data acquisition software designed to collect data from control systems
and external devices as needed (PLCs, Vibration monitoring systems, etc.).
The OSM System will be provided by GE and will be included in the Unit Control Panel.
The OSM is a READ-ONLY device, which cannot modify any control logic.
In addition to the OSM, the RM&D system requires also the networking devices to connect the system on site
with GE network and enable continuous flow of information from the remote site to the GE headquarter.
Customer shall provide at its expense a dedicated Internet access suitable for site to site secure connectivity of
the Monitoring System to the GE Center and a network link between the Unit Control Panel and the router
provided by GE.
Data acquisition is done on a continuous basis at the maximum sampling rate allowed by the data to insure
that a precise assessment of the machine condition can be made even during transient operation. Typical
data frequencies are 1 sample/ second and 1 sample/ minute. Data are stored in a local database: analog
data are stored both at high frequency (typically once per second) and low frequency (typically once per
minute), alarms and events are stored on a „change detection‟ basis.
Acquired data are normally transferred to the RM&D Center several times per day and stored in the central
database; data are checked by RM&D engineers and used to assess machines status and potential problems
or anomalies.
Cumulated equipment data will be stored in the OSM nominally for three consecutive months; older data will
be automatically deleted. Under normal circumstances low frequency and alarm/event data will be
periodically retrieved by the RM&D Center and archived in the central database for a minimum of one year.
High frequency data are transferred only on an „on demand‟ basis for limited time intervals, thus enabling the
analysis of specific events with the highest data resolution available. Also direct connection is available on “on
demand” basis.
In general the system is designed not only to support RM&D on historical data but also to allow GE technicians
to connect to the OSM and to the control system HMI; this is a key feature to ensure prompt commissioning
support and remote troubleshooting during critical operating phases.
The system will be maintained active during the Warranty period to enable remote data analysis. At the end of
that period the Customer will decide how to manage the service thru a separate agreement.

GE Oil & Gas


Pag. D.1.2/1
GE Proprietary & Confidential Information
GE Oil & Gas

RM&D Activity
Commissioning & Startup support
RMD connectivity deployment enables a comprehensive remote support during the commissioning & startup
phases.
As needed, onsite TAs can effectively leverage HQ expertise and HQ experts are allowed to reach real time and
historical data for trending and further detailed analysis. The main advantages are here below reported:
By means of RMD data transfer:
• Creation of an historical data repository.
• Reliable, automated and continuous diagnostic data collection and transfer.
• Machine monitoring from starting phases.
• Data driven troubleshooting and root cause analysis.
• Triplog information.
By accessing the HMI:
• Commissioning support and real time engineering troubleshooting for both driver and driven
equipment and relevant systems (e.g. DGS, Lube Oil).
• Trace trends with high resolution (40 ms for MkV and MkVI).

GE Oil & Gas


Pag. D.1.2/2
GE Proprietary & Confidential Information
GE Oil & Gas

• If in the same LAN of the HMI, it is possible to access Bently Nevada racks (3500) thru the Rack
configurator and examine configuration and diagnostic alarms sent to the HMI.
• Apply a software TIL.
• Double check potential issues arisen from RMD remarks.
Operations support
Machine experts working 24 hours a day at the RM&D Center are dedicated to determine conditions of site
equipment, to help in operating the asset below the alarm levels, to identify anomalous trends and to
determine incipient failures by analyzing data acquired by the RM&D System. GE proprietary performance
evaluation programs are then used to evaluate current performance level and degradation effects during
equipment operating life.
The aim of remote monitoring service is to detect potential problems before an equipment shutdown occurs or
before certain operating phases can lead to components or system failure. If necessary, maintenance or repair
action are suggested to customer and GE site technicians quickly, thus minimizing the extent of repair and
avoiding potential collateral damages.
In general the RM&D System gathers hundreds of gas turbines and driven equipment parameters from site
devices that become available for historical and statistical analyses and trending. The long-term analysis
executed on data is mainly aimed to define degradation effects on main machine systems; the main machine
parameters are selected and plotted against time as raw or normalized value. Also design behavior is used to
determine anomalous conditions. Focus of this analysis is on data steps, threshold crossing or increase of the
values also when the measure is below alarm or trip level. The short-term analysis is mainly performed on
one-second data resolution and is used to find correlation between signals and anomalies starting point.
Equipment data used on trend analysis mainly include:
• Equipment and system trips, alarms and other significant events.
• Lube oil system pressure and temperatures.
• Compressor seal systems (i.e. pressures and leakage flows).
• Thermodynamic parameters such as pressures, temperatures and flows.
• Counters status (fired hours, starts, trips, etc.).
• Control parameters (i.e. compressor anti-surge parameters).
• Shaft radial vibrations and axial position, and casing vibration.
Performance assessment programs have been developed to provide estimation and trending of equipment
main components efficiencies and output. These tools are based on GE proprietary algorithms and provide
information about the main machine sections; the availability and details of results depend on the machine
available instrumentation.
The calculated machine performances are compared with expected values specific for each machine; the
comparison between values takes into account the analysis of historical data belonging to the specific unit
and the set of data collected from the whole installed fleet as well.
The preliminary elaboration carried out with the data validation, operating running status definition and actual
performance evaluation produces data used to fully describe the actual engine thermodynamic behavior.
As general approach, after a first period of data storage and analyses, diagnostic engineers produce and
configure (on the RMD central system) a set of diagnostic thresholds that will be used as trigger for anomalies.
A prognostic engine scanning continuously raw and normalized data will then promptly alert diagnostic

GE Oil & Gas


Pag. D.1.2/3
GE Proprietary & Confidential Information
GE Oil & Gas

engineers about incipient failures and type of threshold that have been violated. The main recipients of any
following notification are GE project manager and site technicians.

RM&D Service benefits


Main benefits of the RM&D system deployment are:
• Reduction of time to reach stable and reliable operations.
• Start production earlier.
• Historical Data availability in case of investigations and troubleshooting from GE Oil & Gas HQ.
• Possibility to provide real time support to site control engineers during critical start up phase.
• Opportunity to avoid damages increasing MTBF.
• Demonstrated Availability increase.

GE Oil & Gas


Pag. D.1.2/4
GE Proprietary & Confidential Information
GE Oil & Gas

Control System Drawings

GE Oil & Gas


Pag. D.2
GE Proprietary & Confidential Information
GE NuovoPignone-Electronically Approved Drawing-Checked: Meloni P., Approved: Carletti F.-Internal DT-'N'
GE Oil & Gas Product Structuring
CONTROL SYSTEM SCHEMATIC
(SIL Architecture)

CONTROL ROOM CONFIGURATION


for
HEAVY DUTY APPLICATIONS

TITLE DOCUMENT CODE REVISION


CONTROL SYSTEM SCHEMATIC (SIL ARCHITECTURE)
CONTROL ROOM CONFIGURATION FOR HEAVY DUTY APPLICATIONS SOM6753633 2
REVISION DESCRIPTION APPROVED
Revised Sheets: 3, 8, 9 DATE SECURITY CODE
CHECKED
01-Oct-2013 N
EXECUTED BY Tamborrelli D.
SCALE REPLACE / DERIVED FROM 1st ISSUE ORIGINAL JOB SIZE LANGUAGE
N.A N.A 08-Aug-2012 0402222 3 A
THIS DOCUMENT IS AND CONTAINS CONFIDENTIAL AND PROPRIETARY INFORMATION OF Nuovo Pignone S.r.l WHICH SHALL NOT BE USED OR DISCLOSED TO OTHERS, EXCEPT WITH THE SHEET
WRITTEN PERMISSION OF Nuovo Pignone S.r.l UNPUBLISHED WORK ©2013 Nuovo Pignone S.r.l ALL RIGHTS RESERVED.
1
Pag. D.2.1/1
of 9
GE Oil & Gas
GE Proprietary & Confidential Information
ACRONYMS LEGEND
REVISION INDEX
ADH Atlanta Data Highway Network
SHEET TITLE 0 1 2 3 4 5 B/N Bently Nevada
DCP Direct Current Panel
1 COVER SHEET x x DCS Distributed Control System
ESD Emergency Shutdown System
2 REV. INDEX, LEGEND AND GENERAL REMARKS x x
FF Fire Fight System
GCPP Generator Control & Protection Panel
3 HARDWIRED CONFIGURATION x x x
HMI Human Machine Interface
4 UCS NETWORKS TOPOLOGY x x HST Historian
MCC Motor Control Center
5 REMOTE NETWORKS TOPOLOGY (UP TO 4 UNITS) x x MCS Master Control System
NTP Network Time Protocol
6 REMOTE NETWORKS TOPOLOGY (FROM 5 TO 11 UNITS) x x OSM On Site Monitoring
PDH Plant Data Highway Network
7 IP NETWORK ADDRESSING TABLE x x PLC Programmable Logic Controller
PMS Power Management System
8 SWITCH PORTS TABLES (UP TO 4 UNITS) x x x SIL Safety Integrity Level
UCS Unit Control System
9 SWITCH PORTS TABLES (FROM 5 TO 11 UNITS)
x x x UDH Unit Data Highway Network
VPN Virtual Private Network
VSDs Variable Speed Drives

Limits of Supply

OTHERS GE O&G

TITLE DOCUMENT CODE REVISION


CONTROL SYSTEM SCHEMATIC (SIL ARCHITECTURE)
CONTROL ROOM CONFIGURATION FOR HEAVY DUTY APPLICATIONS SOM6753633 2
REVISION DESCRIPTION PAGE MARKER SECURITY CODE
Revised Sheets: 3, 8, 9 N.A. N
ORIGINAL JOB SIZE LANGUAGE
0402222 3 A
THIS DOCUMENT IS AND CONTAINS CONFIDENTIAL AND PROPRIETARY INFORMATION OF Nuovo Pignone S.r.l WHICH SHALL NOT BE USED OR DISCLOSED TO OTHERS, EXCEPT WITH THE SHEET
WRITTEN PERMISSION OF Nuovo Pignone S.r.l UNPUBLISHED WORK ©2013 Nuovo Pignone S.r.l ALL RIGHTS RESERVED.
2
Pag. D.2.1/2
of 9
GE Oil & Gas
GE Proprietary & Confidential Information
CUSTOMER
CUSTOMER (Note 9) CUSTOMER
PMS GCPP MCC DCP Always Manned
DCS ESD
(Note 1) (Note 1) (Note 3) (Note 3)
Location
(Note 3)

CUSTOMER PERMISSIVES

SIGNALS, MCC STATUS

SIGNALS, DCP STATUS


GENERATOR BUS VOLTAGE
DIG. SIGNALS

DIG. CONTROL SIGNALS

DIG. CONTROL SIGNALS

DC MOTORS STARTS/
INTERFACE

STOP AND RUNNING


AC MOTORS, START/
INTERFACE

STOP AND RUNNIG


SIGNALS
ANALOG
TRIP NOTIFICATION
SIGNALS
ANALOG

STATUS
(2) (2) (2)

STOP COMMAND
(2)

GALVANIC
GALVANIC
ISOLATORS PROFIBUS HUB
UNIT CONTROL
ISOLATORS (Note 7)
SYSTEM [UCS]
(2)

(Note 7)
Profibus DP Master
PPRF
(Note 9)
MARK VIe
TORQUE TORQUE SIGNAL REPETITION
TURBINE CONTROLLER
MarkVIe
METER Speed/Overspeed & Shut-off
Module (SIL3)

(Note 5)

PERMISSIVES, COMMON ALARM &


TRIP SIGNALS, HEALTHY STATUS

CUMULATIVE FIRE TRIP SIGNAL


COMMON ALARM OK STATUS

GENERATOR BUS VOLTAGE

GAS COMMON ALARM

PERMISSIVES, FIRE ALARMS


VENTILATION CUTOUT, IGNITION
DYNAMIC PRESSURE REPETITION &

SAFETY ESD CMD / NOTIFICATION


DIG. CONTROL SIGNALS

TRIP MUL. REQUEST


VIB COMMON NORMAL STOP

TRANSFORMERS CMD
VIB TRIP MULT CMD

VIB COMMON TRIP

HEALTHY STATUS
TEMP COMMON STOP/TRIP SIGNALS
COMMON ALARM OK STATUS SAFETY RELAY TRIP CMD MARK VIeS
(KSIS1)

B/N VIBRATION B/N TEMPERATURE SAFETY CONTROLLER


LOCAL ESD PB [5ESD1] SIS TRIP ACTIVE [LSL1] (SIL3)
MONITOR MONITOR HUMMING MONITOR CUMULATIVE FIRE TRIP TO SIS FIRE FIGHTING SYSTEM
[TEMP1A][TEMP1B] [HMON]
(Note 7) [VIB1A][VIB1B]
Zener Barriers
(Note 2) (Note 8) (applicable for
GCV & SRV)
OFF-SKID FUEL GAS BLOCK & BLEED VALVES

ANALOG, DIGITAL CONTROL SIGNALS

GAS VENT VALVE, LIMIT SWITCH &


CONTROL OIL TRIP VALVES &FUEL

VSDS WINDING AND BEARING TEMP


GT PROTECTION SPEED PICK-UP’S

DIGITAL & ANALOG SIGNALS


GEAR BOX VIB. PROBES (ACCEL.,

LOAD BEARING TEMPERATURES


LOAD BEARING TEMPERATURES
(RADIAL, AXIAL) & KEY PHASORS

GT CONTROL SPEED PICK-UP’S

SERVO VALVES COMMANDS

ANALOG & DIGITAL CONTROL &


RADIAL, AXIAL) & KEY PHASOR

VSDS VIBRATION BEARING


DYNAMIC PRESSURE SIGNALS
GT BEARING TEMPERATURES

GT BEARING TEMPERATURES

GT BEARING TEMPERATURES
FIRE DETECTION SENSORS &
MANUAL DISCHARGE PB’s

VSDS BEARING TEMP


ANALOG SIGNALS
PROTECTION SIGNALS
GEAR BOX BEARING

DIGITAL SIGNALS
GEAR BOX BEARING
GT SEISMIC PROBES

LOAD VIB. PROBES


VALVES COMMAND
FIRE SUPPRESSION
GT ENCLOSURE DP
GT TEMPERATURES

FLAME DETECTION
TORQUE SIGNALS

TEMPERATURES
COMB. CHAMBER

(SEISM., RADIAL)
LIMIT SWITCHES

TEMPERATURES
GT VIB. PROBES

ESD FIELD PB’S


GAS SENSORS
COMMAND

(Note 6)
Limits of supply
OFF-SKID GAS TURBINE GEAR BOX LOAD PROCESS VSDs
(NOTE 4)
FUEL GAS
BLOCK & OTHERS GE O&G
BLEED
UNIT CONFIGURATION
General Notes
1. Barriers have to be selected during Job requisition phase. TITLE DOCUMENT CODE REVISION
CONTROL SYSTEM SCHEMATIC (SIL ARCHITECTURE)

Options CONTROL ROOM CONFIGURATION FOR HEAVY DUTY APPLICATIONS SOM6753633 2


1. Only for Generator Drive applications
2. Option “B/N Temperature monitor” REVISION DESCRIPTION PAGE MARKER SECURITY CODE
3. Check if in GE O&G scope of supply or supplied by others. Update drawing accordingly. "Generator Bus Voltage" signal routed to Mark VIeS controller N.A. N
4. Option “Gear Box”
ORIGINAL JOB SIZE LANGUAGE
5. Option “Torque Meter”
6. Option for MS7001 and MS9001 Mechanical Drive Application 0402222 3 A
7. Includes “Additional Vibration Monitor” if foreseen THIS DOCUMENT IS AND CONTAINS CONFIDENTIAL AND PROPRIETARY INFORMATION OF Nuovo Pignone S.r.l WHICH SHALL NOT BE USED OR DISCLOSED TO OTHERS, EXCEPT WITH THE SHEET
8. Applicable only for MS5002E WRITTEN PERMISSION OF Nuovo Pignone S.r.l UNPUBLISHED WORK ©2013 Nuovo Pignone S.r.l ALL RIGHTS RESERVED.
9. Option “Profibus Connection” 3
Pag. D.2.1/3
of 9
GE Oil & Gas
GE Proprietary & Confidential Information
ADDITIONAL LOCAL HMI (AHMIL1)

(note 12)
UNIT CONTROL SYSTEM
HART
[UCS] HMI
MULTIPLEXER
COMMUNICATION MASTER
(13) A (9)
(10)
(note 1) (note 13) DOT MATRIX PRINTER
NTP SERVER [NTP1] (2)
[PRN1] (1)
(1)
Links Legend: (2) (1) (2)
(SUPPLIED LOOSE)
(1) EGD (Ethernet Global Data) protocol over Ethernet (UDH)
(2) TCP/IP, SNMP, NTP over Ethernet (11)
(note 4)
(3) Trunk Connection: -
(8)
(4) Stacking connection for Cisco 2960-S OSM (1)
[OSM1] (1)
(5) B/N Proprietary Protocol over Ethernet (RJ45) (2) (1) (1) (note 10)
(2) (2)
(6) B/N Proprietary Protocol over Fiber Optic (Multi-Mode)
(7) Modbus over Ethernet TCP/IP To Internet (2)
CUSTOMER CONTROL
LOCAL HMI [HMIL1]
(8) OPC Link over Ethernet TCP/IP
(9) Coaxial cable
VPN
(note 11)
ROOM
(10) Irig-b cohaxial cable
(11) USB connection ADH #1
(12) Stacking cable for Cisco 3750-X Switch R (1)
MarkVIe
(13) Vendor Proprietary Protocol over RS485 Turbine Controller S (1) PDH #1
(14) Direct connection to DCS: Modbus RTU or T (1)
Modbus/OPC/GSM over Ethernet TCP/IP UDH #1 BN network switch (6) B
(15) Temporary Connection to UDH for maintenance

PATCH CORD PANELS


PDH UDH ADH TRUNK STACK (6) (note 10)
MarkVIeS R (1)
Protection System S (1) Network switch #1 [ESW1A] To Sheet
(3)
General Notes: T (1) (3) 5 and 6
(4)(4)
- Number of Engineering Workstations: - B/N SYSTEM 1
PDH UDH ADH TRUNK STACK
- Comm. Gateway direct connection type to DCS:
- Network switch #2 [ESW1B]
(note 5)
(7) (note 7)
FIRE FIGHTING SYSTEM
[FF1A][FF1B] (7)
UDH #2

(1) PDH #2
DCS
(1)
(note 8)
(2)
B/N VIBRATION
3500/22
3500/91
3500/91

MONITOR (15) (2)


[VIB1A][VIB1B] .
Notes (Options): CUSTOMER DCS
1. Option “HART Multiplexer connectivity”. Optional (14)
HART multiplexer serial RS-485 connection can be provided. (5) (14)
(2) (1)
2. Option “B/N Temperature monitor” (2) (1) (2) (1)
3. Please, check if in GE O&G scope of supply or (1)
supplied by others. Update drawing accordingly. (1)
4. Dot Matrix is Optional; (note 8)
5. Fire Monitor second connection is Optional. To be ENGINEERING WORKSTATION COMMUNICATION COMMUNICATION
B/N TEMP GATEWAY #1 GATEWAY #2
3500/22
3500/91
3500/91

quoted as extra; [EWST] CUSTOMER


6. “Additional Vibration monitor” if foreseen
MONITOR (SUPPLIED LOOSE)
[CMG1A] [CMG1B] A (13)
INSTRUMENTS
[TEMP1A][TEMP1B] MNGMT SYSTEM
7. Patch cord panels is Optional. To be quoted as extra (note 9)
8. Bently-Nevada 3500/91 second port is Optional (note 14)
To be quoted as extra (note 2) (5)
9. Option “B/N System 1 Connectivity” (1)
in case B/N System 1 connectivity is required, (1)
dedicated network switch will be supplied; (note 8)
ADD. B/N
3500/91

10. Option “Additional Local HMI”


3500/91
3500/22

VIBRATION
11. Option “OSM device” MONITOR B/N network switch (6)
B
12. Option “Stand Alone NTP Server”: synchronize [AVIB1A][AVIB1B] [BNSW1]
both PDH and UDH networks via GPS antenna.
(note 9)
13. Optional Irig B input from customer provided. (5)
14. Option “Redundant Communication Gateway”:
embedded ind. PC for OCP DA&AE /Modbus
communication with customer systems.

TITLE DOCUMENT CODE REVISION


CONTROL SYSTEM SCHEMATIC (SIL ARCHITECTURE)
Limits of supply CONTROL ROOM CONFIGURATION FOR HEAVY DUTY APPLICATIONS SOM6753633 2
REVISION DESCRIPTION PAGE MARKER SECURITY CODE
NO REVISION IS INTRODUCED IN THIS PAGE N.A. N
OTHERS GE O&G
ORIGINAL JOB SIZE LANGUAGE
0402222 3 A
THIS DOCUMENT IS AND CONTAINS CONFIDENTIAL AND PROPRIETARY INFORMATION OF Nuovo Pignone S.r.l WHICH SHALL NOT BE USED OR DISCLOSED TO OTHERS, EXCEPT WITH THE SHEET
WRITTEN PERMISSION OF Nuovo Pignone S.r.l UNPUBLISHED WORK ©2013 Nuovo Pignone S.r.l ALL RIGHTS RESERVED.
4
Pag. D.2.1/4
of 9
GE Oil & Gas
GE Proprietary & Confidential Information
UNIT CONTROL SYSTEM
[UCS1] UP TO 4 UNITS (note 8)
UNIT CONTROL SYSTEM
[UCSn]
Inside “UCS Network Topology for Single Unit” applies see Sh.4 Inside “UCS Network Topology for Single Unit” applies see Sh.4
(note 5)
(note 5)

(4) (4)
(4) (4)

PDH UDH ADH TRUNK STACK PDH UDH ADH TRUNK STACK PDH UDH ADH TRUNK STACK PDH UDH ADH TRUNK STACK

Network switch #1 [ESW1A] Network switch #2 [ESW1B] Network switch #1 [ESWnA] Network switch #2 [ESWnB]

(3) (3) (3)


(3)

Links Legend:
(1) EGD (Ethernet Global Data) protocol over Ethernet (UDH)
(2) TCP/IP, SNMP, NTP over Ethernet BN network switch (6) B CUSTOMER CONTROL
(3) Trunk Connection: -
B/N SYSTEM 1 ROOM
(4) Stacking connection for Cisco 2960-S
(5) B/N Proprietary Protocol over Ethernet (RJ45) CUSTOMER
(6) B/N Proprietary Protocol over Fiber Optic (Multi-Mode) (6) A (13)
INSTRUMENTS
MNGMT SYSTEM
(7) Modbus over Ethernet TCP/IP (note 9)
(8) OPC Link over Ethernet TCP/IP (note 10)
(9) Coaxial cable
(10) Irig-b cohaxial cable
(11) USB connection
(12) Stacking cable for Cisco 3750-X Switch (note 2)
COMMUNICATION COMMUNICATION (4)
(13) Vendor Proprietary Protocol over RS485 GATEWAY #1 GATEWAY #2 (4)
(14) Direct connection to DCS: Modbus RTU or Modbus/OPC/GSM over Ethernet TCP/IP [RCMG1A] [RCMG1B] NETWORK PRINTER
PDH UDH ADH TRUNK STACK PDH UDH ADH TRUNK STACK [NPRN1]
General Notes: (note 11) Remote Network switch #1 [ESWR1A] Remote Network switch #2 [ESWR1B]
- Number of Remote HMIs: - (1) (2)
(2)
(1) (2) UDH #1 UDH #2
- Comm. Gateway direct connection type to DCS: - (14) (note 4)
DCS (14)
PDH #1 PDH #2
Notes (Options):
1.Option “Remote HMI”
2.Option “Remote Network”: mandatory if Option “Remote HMI” or Option (2)
“Historian” Or Option “Multiunit Configuration” or option “NTP Server” are (2)
selected. (note 7)
.
CUSTOMER DCS
3.Option “Historian”
4. Option “Network Printer”. (1)
(2)
5.Base Configuration for Local HMI GraphIc Pages is “Single unit”. Option
“MultiUnit Configuration” is available.
6. # NTP SERVER depends on # of Units according to the following table:
(2)
# Unit Base Option Redundant Option
1 1 (in UCS) N.A. (note 6.1) HMI HST
2 1 (supplied loose) 2 (in UCS’s) (9)
(10)
>=3 1 (supplied loose) 2 (supplied loose)
(1)
6.1 Optional Irig B input from customer provided. (2) (2) (2)
REMOTE NTP SERVER [RNTP1] (1)
7. Option “Customer Connection” (1) (1)
7.1 Connection to Remote Network Switch. Supported protocols over (note 6)
REMOTE HMI [HMIR1] HISTORIAN [HST1]
Ethernet TCP/IP copper or Fiber: (note 1) (note 3)
- Modbus
- OPC DA (OPC DA/AE only if option 5 “Redundant Communication Gateway” is
selected)
DOCUMENT CODE REVISION
- GSM Limits of supply TITLE
CONTROL SYSTEM SCHEMATIC (SIL ARCHITECTURE)
7.2 Direct connection to DCS. Supported protocols: Modbus RTU or connection CONTROL ROOM CONFIGURATION FOR HEAVY DUTY APPLICATIONS SOM6753633 2
over Ethernet TCP/IP (see 7.1)
The two connections are mutually exclusive. OTHERS GE O&G REVISION DESCRIPTION PAGE MARKER SECURITY CODE
8. Up to 4 units NO REVISION IS INTRODUCED IN THIS PAGE N.A. N
9. Option “HART Multiplexer connectivity”. Optional HART multiplexer serial RS- ORIGINAL JOB SIZE LANGUAGE
485 connection can be provided. 0402222 3 A
10. Option “B/N System 1 Connectivity” THIS DOCUMENT IS AND CONTAINS CONFIDENTIAL AND PROPRIETARY INFORMATION OF Nuovo Pignone S.r.l WHICH SHALL NOT BE USED OR DISCLOSED TO OTHERS, EXCEPT WITH THE SHEET
11. Option “Redundant Communication Gateway in Customer Control Room” WRITTEN PERMISSION OF Nuovo Pignone S.r.l UNPUBLISHED WORK ©2013 Nuovo Pignone S.r.l ALL RIGHTS RESERVED.
5 of 9
GE Oil & Gas
Pag. D.2.1/5
GE Proprietary & Confidential Information
UNIT CONTROL SYSTEM
[UCS1] 5 TO 11 UNITS (note 8)
UNIT CONTROL SYSTEM
[UCSn]
Inside “UCS Network Topology for Single Unit” applies see Sh.4 Inside “UCS Network Topology for Single Unit” applies see Sh.4
(note 5) (note 5)

(4) (4)
(4) (4)

PDH UDH ADH TRUNK STACK PDH UDH ADH TRUNK STACK PDH UDH ADH TRUNK STACK PDH UDH ADH TRUNK STACK

Network switch #1 [ESW1A] Network switch #2 [ESW1B] Network switch #1 [ESWnA] Network switch #2 [ESWnB]

(3) (3) (3) (3)

Links Legend:
(1) EGD (Ethernet Global Data) protocol over Ethernet (UDH)
(2) TCP/IP, SNMP, NTP over Ethernet
BN network switch (6) B CUSTOMER CONTROL
(3) Trunk Connection: -
(4) Stacking connection for Cisco 2960-S B/N SYSTEM 1 CUSTOMER ROOM
(5) B/N Proprietary Protocol over Ethernet (RJ45) A (13)
INSTRUMENTS
MNGMT SYSTEM
(6) B/N Proprietary Protocol over Fiber Optic (Multi-Mode) (note 9)
(6)
(7) Modbus over Ethernet TCP/IP
(8) OPC Link over Ethernet TCP/IP
(9) Coaxial cable (note 10)
(12)
(10) Irig-b cohaxial cable (12)
(11) USB connection
(12) Stacking cable for Cisco 3750-X Switch FIBER FIBER
(note 2)
STACK STACK
(13) Vendor Proprietary Protocol over RS485
Fiber Optic Switch #1 [TSWR1A] (3) Fiber Optic Switch #2 [TSWR1B] (3)
(14) Direct connection to DCS: Modbus RTU or Modbus/OPC/GSM over Ethernet TCP/IP COMMUNICATION COMMUNICATION
GATEWAY #1 GATEWAY #2 NETWORK PRINTER
[RCMG1A] [RCMG1B] [NPRN1]
(4)
(4)
General Notes:
- Number of Remote HMIs: - (note 11)
PDH UDH ADH TRUNK STACK PDH UDH ADH TRUNK STACK
(2) (note 4)
- Comm. Gateway direct connection type to DCS: - (14) (1) (2)
(14) (1)
Remote Network switch #1 [ESWR1A] Remote Network switch #2 [ESWR1B]
DCS (2)
UDH #1 UDH #2
Notes (Options):
1.Option “Remote HMI” PDH #1 PDH #2

2.Option “Remote Network”: mandatory if Option “Remote HMI” or Option “Historian”


Or Option “Multiunit Configuration” or option “NTP Server” are selected.
3.Option “Historian” . (note 7)
CUSTOMER DCS (2)
4. Option “Network Printer”. (2)
5.Base Configuration for Local HMI GraphIc Pages is “Single unit”. Option “MultiUnit
(1)
Configuration” is available.
(2)
6. # NTP SERVER depends on # of Units according to the following table:
# Unit Base Option Redundant Option
1 1 (in UCS) N.A. (note 6.1)
2 1 (supplied loose) 2 (in UCS’s) (9)
HMI HST
>=3 1 (supplied loose) 2 (supplied loose) (10) (2)
6.1 Optional Irig B input from customer provided.
REMOTE NTP SERVER [RNTP1] (2) (2) (2)
7. Option “Customer Connection” (1) (1) (1) (1)
7.1 Connection to Remote Network Switch. Supported protocols over Ethernet (note 6)
TCP/IP copper or Fiber: REMOTE HMI [HMIR1] HISTORIAN [HST1]
(note 1) (note 3)
- Modbus
- OPC DA (OPC DA/AE only if option 5 “Redundant Communication Gateway” is
selected)
- GSM TITLE DOCUMENT CODE REVISION
7.2 Direct connection to DCS. Supported protocols: Modbus RTU or connection over Limits of supply CONTROL SYSTEM SCHEMATIC (SIL ARCHITECTURE)
CONTROL ROOM CONFIGURATION FOR HEAVY DUTY APPLICATIONS SOM6753633 2
Ethernet TCP/IP (see 7.1)
The two connections are mutually exclusive. PAGE MARKER
REVISION DESCRIPTION SECURITY CODE
8. Up to 4 units OTHERS GE O&G NO REVISION IS INTRODUCED IN THIS PAGE N.A. N
9. Option “HART Multiplexer connectivity”. Optional HART multiplexer serial RS-485
ORIGINAL JOB SIZE LANGUAGE
connection can be provided.
10. Option “B/N System 1 Connectivity” 0402222 3 A
11. Option “Redundant Communication Gateway in Customer Control Room” THIS DOCUMENT IS AND CONTAINS CONFIDENTIAL AND PROPRIETARY INFORMATION OF Nuovo Pignone S.r.l WHICH SHALL NOT BE USED OR DISCLOSED TO OTHERS, EXCEPT WITH THE SHEET
WRITTEN PERMISSION OF Nuovo Pignone S.r.l UNPUBLISHED WORK ©2013 Nuovo Pignone S.r.l ALL RIGHTS RESERVED.
6
Pag. D.2.1/6
of 9
GE Oil & Gas
GE Proprietary & Confidential Information
IP Ethernet Address: 172.16.ABC.XYZ
(note 3)
Subnetmask: 255.255.240.0

TAG Description UDH PDH ADH Network ABC X YZ


CORE - R Turbine Control System (R core) 172.16.1BC.101 NA NA Type Unit number Controller/Device Type Of Device
Number
CORE - S Turbine Control System (S core) 172.16.1BC.102 NA NA
UDH 101 = Unit 1 1 = Gas Turbine 01 = Core R0
CORE - T Turbine Control System (T core) 172.16.1BC.103 NA NA (ABC range: 96-111) . 2= Steam Turbine 02 = Core S0
SAF - R Safety Control System (R core) 172.16.1BC.104 NA NA . 03 = Core T0
SAF - S Safety Control System (S core) 172.16.1BC.105 NA NA 111 = Unit 11 04 = Saf R0
SAF - T Safety Control System (T core) 172.16.1BC.106 NA NA 05 = Saf SO
06 = Saf TO
VIB1 A Vibration Monitor (3500/91) 172.16.1BC.107 NA NA
07 = VIB. MON.
VIB1 B Vibration Monitor (3500/91) 172.16.101.110 NA NA 08 = ADD. VIB. MON.
AVIB1 A Add. Vibration Monitor (3500/91) 172.16.1BC.108 NA NA 09 = TEMP. MON.
AVIB1 B Add. Vibration Monitor (3500/91) 172.16.1BC.111 NA NA 10 = VIB. MON. (optional)
TEMP1 A Temperature Monitor (3500/91) 172.16.1BC.109 NA NA 11 = ADD. VIB. MON. (optional)
12 = TEMP. MON. (optional)
TEMP1 B Temperature Monitor (3500/91) 172.16.1BC.112 NA NA
0 = All other devices on 02 = Local HMI
OSM1 On Site Monitor PC 172.16.1BC.4 172.16.201.BC4 172.25.6.Y UDH in local units 03 = Additional Local HMI
NTP1 Network Time Protocol Server 172.16.1BC.7 172.16.201.BC7 NA 04 = OSM
RNTP1 Remote Network Time Protocol Server 172.16.100.6 172.16.201.6 NA 05 = Comm. Gateway A
FF1A Fire Fighting system NA 172.16.201.BC8 NA 06 = Comm. Gateway B
07 = NTP
FF1B Fire Fighting system NA 172.16.201.BC9 NA 08 = Eng. Workstation
HMIL1 Human Machine Interface - Local 172.16.1BC.2 172.16.201.BC2 NA 100 = Remote 0 = Remote devices on 02 = Remote HMI
AHMIL1 Human Machine Interface - Local 172.16.1BC.3 172.16.201.BC3 NA (common to all UDH 03 = Historian
CMG1A Communication Gateway A 172.16.1BC.5 172.16.201.BC5 NA units) 04 = Remote Comm. Gateway A
CMG1B Communication Gateway B 172.16.1BC.6 172.16.201.BC6 05 = Remote Comm. Gateway B
NA
06 = Remote NTP
RCMG1A Remote Communication Gateway A 172.16.100.4 172.16.201.4 NA
RCMG1B Remote Communication Gateway B 172.16.100.5 172.16.201.5 NA PDH 201 01z-11z for Unit 1 to Unit 11 reserved for local devices on PDH
ESW1A/B Local Ethernet Switch A&B NA 172.16.201.2YZ NA (ABC range: 192-207)
ESWR1A/B Remote Ethernet Switch A&B NA 172.16.201.240 NA 00z reserved for remote devices on PDH
TSWR1A/B Remote Fiber Optic Switch A&B NA 172.16.201.241 NA
2YZ with YZ = 01-11 are reserved for Ethernet Local Switches
NPRN1 Network Printer NA 172.16.201.100 NA
HMIR1 Remote HMI 172.16.100.2 172.16.201.2 NA
HST1 Historian PC 172.16.100.3 172.16.201.3 NA Note 1:
BNSW1 Bently Nevada switch for System1 NA NA NA Devices such as HMI Servers, Communication Gateways,
Historian, Remote HMIs and Remote NTP that are both on the
EWST Engineering Workstation 172.16.1BC.8 NA NA
UDH and PDH should use the same z number for the last octal
in the IP address
Table1: Devices IP Addresses

Table2: Ethernet addressing rules


General Notes:

(1) n = number of units ;


(2) BC from 01 to 11 identifies the unit number
(3) 172.16.ABC.XYZ is the standard IP address for NEW UNIT APPLICATION; 192.168.ABC.XYZ is also available for
REVAMPING JOB
(4) Refer to Table 2 for the second port 3500/91 IP address of Vibration Monitor, Additional Vibration Monitor and
Temperature Monitor
TITLE DOCUMENT CODE REVISION
(5) Stacked switches (i.e. A&B switches connected by a stacking cable) share the same IP address CONTROL SYSTEM SCHEMATIC (SIL ARCHITECTURE)
(6) ABC range means that all the IP addresses having the ABC octet included in that range are on the same subnet CONTROL ROOM CONFIGURATION FOR HEAVY DUTY APPLICATIONS SOM6753633 2
REVISION DESCRIPTION PAGE MARKER SECURITY CODE
NO REVISION IS INTRODUCED IN THIS PAGE N.A. N
ORIGINAL JOB SIZE LANGUAGE
0402222 3 A
THIS DOCUMENT IS AND CONTAINS CONFIDENTIAL AND PROPRIETARY INFORMATION OF Nuovo Pignone S.r.l WHICH SHALL NOT BE USED OR DISCLOSED TO OTHERS, EXCEPT WITH THE SHEET
WRITTEN PERMISSION OF Nuovo Pignone S.r.l UNPUBLISHED WORK ©2013 Nuovo Pignone S.r.l ALL RIGHTS RESERVED.
7
Pag. D.2.1/7
of 9
GE Oil & Gas
GE Proprietary & Confidential Information
UP TO 4 UNITS
Switch: ESWYA Switch: ESWYB Switch: ESWR1A Switch: ESWR1B
Location: UCS Location: UCS Location: Customer Control Room Location: Customer Control Room
IP Address: 172.16.201.2BC IP Address: 172.16.201.2BC IP Address: 172.16.201.240 IP Address: 172.16.201.240
Ports Device Cable Subnet Ports Device Cable Subnet Ports Device Cable Subnet Ports Device Cable Subnet
PORT_1 FF1A CAT 5e PDH PORT_1 FF1B CAT 5e PDH PORT_1 DCS A CAT 5e PDH PORT_1 HMIR1 (backup) CAT 5e PDH
PORT_2 OSM1 CAT 5e PDH PORT_2 NTP1 CAT 5e PDH PORT_2 SPARE CAT 5e PDH PORT_2 RNTP1 CAT 5e PDH
PORT_3 SPARE CAT 5e PDH PORT_3 SPARE CAT 5e PDH PORT_3 SPARE CAT 5e PDH PORT_3 DCS B CAT 5e PDH
PORT_4 SPARE CAT 5e PDH PORT_4 SPARE CAT 5e PDH PORT_4 SPARE CAT 5e PDH PORT_4 RCMG1B CAT 5e PDH
PORT_5 AHMIL1 (main) CAT 5e PDH PORT_5 SPARE CAT 5e PDH PORT_5 SPARE CAT 5e PDH PORT_5 NPRN1 CAT 5e PDH
PORT_6 SPARE CAT 5e PDH PORT_6 SPARE CAT 5e PDH PORT_6 HMIR1 (main) CAT 5e PDH PORT_6 SPARE CAT 5e PDH
PORT_7 HMIL1 (main) CAT 5e PDH PORT_7 AHMIL1 (backup) CAT 5e PDH PORT_7 RCMG1A CAT 5e PDH PORT_7 SPARE CAT 5e PDH
PORT_8 CMG1A (main) CAT 5e PDH PORT_8 HMIL1 (backup) CAT 5e PDH PORT_8 HST1 (main) CAT 5e PDH PORT_8 HST1 (backup) CAT 5e PDH
PORT_9 SPARE CAT 5e PDH PORT_9 CMG1A (backup) CAT 5e PDH PORT_9 SPARE CAT 5e PDH PORT_9 SPARE CAT 5e PDH
PORT_10 SPARE CAT 5e PDH PORT_10 CMG1B CAT 5e PDH PORT_10 SPARE CAT 5e PDH PORT_10 SPARE CAT 5e PDH
PORT_11 CORE-R CAT 5e UDH PORT_11 CORE-T CAT 5e UDH PORT_11 HMIR1 (main) CAT 5e UDH PORT_11 HST1 (backup) CAT 5e UDH
PORT_12 CORE-S CAT 5e UDH PORT_12 SAF-R CAT 5e UDH PORT_12 RCMG1A CAT 5e UDH PORT_12 HMIR1 (backup) CAT 5e UDH
PORT_13 NTP1 CAT 5e UDH PORT_13 SAF-S CAT 5e UDH PORT_13 SPARE CAT 5e UDH PORT_13 RCMG1B CAT 5e UDH
PORT_14 VIB1 CAT 5e UDH PORT_14 OSM1 (backup) CAT 5e UDH PORT_14 SPARE CAT 5e UDH PORT_14 SPARE CAT 5e UDH
PORT_15 AVIB1 CAT 5e UDH PORT_15 TEMP1 (optional) CAT 5e UDH PORT_15 SPARE CAT 5e UDH PORT_15 SPARE CAT 5e UDH
PORT_16 HMIL1 (main) CAT 5e UDH PORT_16 VIB1 (optional) CAT 5e UDH PORT_16 SPARE CAT 5e UDH PORT_16 SPARE CAT 5e UDH
PORT_17 CMG1A (main) CAT 5e UDH PORT_17 AVIB1 (optional) CAT 5e UDH PORT_17 SPARE CAT 5e UDH PORT_17 SPARE CAT 5e UDH
PORT_18 SPARE CAT 5e UDH PORT_18 HMIL1 (backup) CAT 5e UDH PORT_18 SPARE CAT 5e UDH PORT_18 SPARE CAT 5e UDH
PORT_19 OSM1 (main) CAT 5e UDH PORT_19 CMG1A (backup) CAT 5e UDH PORT_19 HST1 (main) CAT 5e UDH PORT_19 SPARE CAT 5e UDH
PORT_20 TEMP1 CAT 5e UDH PORT_20 CMG1B CAT 5e UDH PORT_20 SPARE CAT 5e UDH PORT_20 SPARE CAT 5e UDH
PORT_21 AHMIL1 (main) CAT 5e UDH PORT_21 EWST CAT 5e UDH PORT_21 RNTP1 CAT 5e UDH PORT_21 SPARE CAT 5e UDH
PORT_22 SAF-T CAT 5e UDH PORT_22 AHMIL1 (backup) CAT 5e UDH PORT_22 SPARE CAT 5e UDH PORT_22 SPARE CAT 5e UDH
PORT_23 To internet VPN CAT 5e ADH PORT_23 SPARE CAT 5e ADH PORT_23 SPARE CAT 5e ADH PORT_23 SPARE CAT 5e ADH
PORT_24 OSM1 CAT 5e ADH PORT_24 SPARE CAT 5e ADH PORT_24 SPARE CAT 5e ADH PORT_24 SPARE CAT 5e ADH
PORT_25 SPARE Fiber Optic TRUNK PORT_25 SPARE Fiber Optic TRUNK PORT_25 ESW1A Fiber Optic TRUNK PORT_25 ESW1B Fiber Optic TRUNK
PORT_26 ESWR1A Fiber Optic TRUNK PORT_26 ESWR1B Fiber Optic TRUNK PORT_26 ESW2A (note 1) Fiber Optic TRUNK PORT_26 ESW2B (note 1) Fiber Optic TRUNK
Stacking Stacking PORT_27 ESW3A (note 1) Fiber Optic TRUNK PORT_27 ESW3B (note 1) Fiber Optic TRUNK
PORT_27 ESWYB STACK PORT_27 ESWYA STACK
Cable Cable PORT_28 ESW4A (note 1) Fiber Optic TRUNK PORT_28 ESW4B (note 1) Fiber Optic TRUNK
PORT_28 ESWYB Stacking STACK PORT_28 ESWYA Stacking STACK Stacking Stacking
PORT_29 ESWR1B STACK PORT_29 ESWR1A STACK
Cable Cable Cable Cable
PORT_30 ESWR1B Stacking STACK PORT_30 ESWR1A Stacking STACK
Cable Cable
Table 1: Local Switch A Table 2: Local Switch B

Table 3: Remote Switch A Table 4: Remote Switch B


Notes:
1. To be replaced as SPARE according to the units number

General Notes:
n = number of units
Y = i-unit ; i can be a number between 1 and 4
BC: 01-04
1. All unused copper and fiber ports shall be disabled as described in SOM6759061.
All switches http access shall be disabled after configuration as described in SOM6759061.
It is suggested to change the switches configuration passwords according to customer
specific job password policies.
2. All switches ports shall be monitored and properly alarmed for cable disconnection,
topology errors, unknown device connection and intrusion detection. For configuration
details see GEI-1000693 (GE Control ST Documentation)

Cable Type legend:


Cat5e: Ethernet RJ45 category 5e cable
Stacking cable: FlexStack cable. See Links legend (4) in sheet 4
Fiber Optic: See Links Legend (3) in sheet 4
TITLE DOCUMENT CODE REVISION
CONTROL SYSTEM SCHEMATIC (SIL ARCHITECTURE)
CONTROL ROOM CONFIGURATION FOR HEAVY DUTY APPLICATIONS SOM6753633 2
REVISION DESCRIPTION PAGE MARKER SECURITY CODE
Added General Notes 1, 2 (Cyber-security policies compliance) N.A. N
ORIGINAL JOB SIZE LANGUAGE
0402222 3 A
THIS DOCUMENT IS AND CONTAINS CONFIDENTIAL AND PROPRIETARY INFORMATION OF Nuovo Pignone S.r.l WHICH SHALL NOT BE USED OR DISCLOSED TO OTHERS, EXCEPT WITH THE SHEET
WRITTEN PERMISSION OF Nuovo Pignone S.r.l UNPUBLISHED WORK ©2013 Nuovo Pignone S.r.l ALL RIGHTS RESERVED.
8
Pag. D.2.1/8
of 9
GE Oil & Gas
GE Proprietary & Confidential Information
5 TO 11 UNITS
Switch: ESWYA Switch: ESWYB Switch: ESWR1A Switch: ESWR1B
Location: UCS Location: UCS Location: Customer Control Room Location: Customer Control Room
IP Address: 172.16.201.2BC IP Address: 172.16.201.2BC IP Address: 172.16.201.240 IP Address: 172.16.201.240
Ports Device Cable Subnet Ports Device Cable Subnet Ports Device Cable Subnet Ports Device Cable Subnet
PORT_1 FF1A CAT 5e PDH PORT_1 FF1B CAT 5e PDH PORT_1 DCS A CAT 5e PDH PORT_1 HMIR1 (backup) CAT 5e PDH
PORT_2 OSM1 CAT 5e PDH PORT_2 NTP1 CAT 5e PDH PORT_2 SPARE CAT 5e PDH PORT_2 RNTP1 CAT 5e PDH
PORT_3 SPARE CAT 5e PDH PORT_3 SPARE CAT 5e PDH PORT_3 SPARE CAT 5e PDH PORT_3 DCS B CAT 5e PDH
PORT_4 SPARE CAT 5e PDH PORT_4 SPARE CAT 5e PDH PORT_4 SPARE CAT 5e PDH PORT_4 RCMG1B CAT 5e PDH
PORT_5 AHMIL1 (main) CAT 5e PDH PORT_5 SPARE CAT 5e PDH PORT_5 SPARE CAT 5e PDH PORT_5 NPRN1 CAT 5e PDH
PORT_6 SPARE CAT 5e PDH PORT_6 SPARE CAT 5e PDH PORT_6 HMIR1 (main) CAT 5e PDH PORT_6 SPARE CAT 5e PDH
PORT_7 HMIL1 (main) CAT 5e PDH PORT_7 AHMIL1 (backup) CAT 5e PDH PORT_7 RCMG1A CAT 5e PDH PORT_7 SPARE CAT 5e PDH
PORT_8 CMG1A (main) CAT 5e PDH PORT_8 HMIL1 (backup) CAT 5e PDH PORT_8 HST1 (main) CAT 5e PDH PORT_8 HST1 (backup) CAT 5e PDH
PORT_9 SPARE CAT 5e PDH PORT_9 CMG1A (backup) CAT 5e PDH PORT_9 SPARE CAT 5e PDH PORT_9 SPARE CAT 5e PDH
PORT_10 SPARE CAT 5e PDH PORT_10 CMG1B CAT 5e PDH PORT_10 SPARE CAT 5e PDH PORT_10 SPARE CAT 5e PDH
PORT_11 CORE-R CAT 5e UDH PORT_11 CORE-T CAT 5e UDH PORT_11 HMIR1 (main) CAT 5e UDH PORT_11 HST1 (backup) CAT 5e UDH
PORT_12 CORE-S CAT 5e UDH PORT_12 SAF-R CAT 5e UDH PORT_12 RCMG1A CAT 5e UDH PORT_12 HMIR1 (backup) CAT 5e UDH
PORT_13 NTP1 CAT 5e UDH PORT_13 SAF-S CAT 5e UDH PORT_13 SPARE CAT 5e UDH PORT_13 RCMG1B CAT 5e UDH
PORT_14 VIB1 CAT 5e UDH PORT_14 OSM1 (backup) CAT 5e UDH PORT_14 SPARE CAT 5e UDH PORT_14 SPARE CAT 5e UDH
PORT_15 AVIB1 CAT 5e UDH PORT_15 TEMP1 (optional) CAT 5e UDH PORT_15 SPARE CAT 5e UDH PORT_15 SPARE CAT 5e UDH
PORT_16 HMIL1 (main) CAT 5e UDH PORT_16 VIB1 (optional) CAT 5e UDH PORT_16 SPARE CAT 5e UDH PORT_16 SPARE CAT 5e UDH
PORT_17 CMG1A (main) CAT 5e UDH PORT_17 AVIB1 (optional) CAT 5e UDH PORT_17 SPARE CAT 5e UDH PORT_17 SPARE CAT 5e UDH
PORT_18 SPARE CAT 5e UDH PORT_18 HMIL1 (backup) CAT 5e UDH PORT_18 SPARE CAT 5e UDH PORT_18 SPARE CAT 5e UDH
PORT_19 OSM1 (main) CAT 5e UDH PORT_19 CMG1A (backup) CAT 5e UDH PORT_19 HST1 (main) CAT 5e UDH PORT_19 SPARE CAT 5e UDH
PORT_20 TEMP1 CAT 5e UDH PORT_20 CMG1B CAT 5e UDH PORT_20 SPARE CAT 5e UDH PORT_20 SPARE CAT 5e UDH
PORT_21 AHMIL1 (main) CAT 5e UDH PORT_21 EWST CAT 5e UDH PORT_21 RNTP1 CAT 5e UDH PORT_21 SPARE CAT 5e UDH
PORT_22 SAF-T CAT 5e UDH PORT_22 AHMIL1 (backup) CAT 5e UDH PORT_22 SPARE CAT 5e UDH PORT_22 SPARE CAT 5e UDH
PORT_23 To internet VPN CAT 5e ADH PORT_23 SPARE CAT 5e ADH PORT_23 SPARE CAT 5e ADH PORT_23 SPARE CAT 5e ADH
PORT_24 OSM1 CAT 5e ADH PORT_24 SPARE CAT 5e ADH PORT_24 SPARE CAT 5e ADH PORT_24 SPARE CAT 5e ADH
PORT_25 SPARE Fiber Optic TRUNK PORT_25 SPARE Fiber Optic TRUNK PORT_25 SPARE Fiber Optic TRUNK PORT_25 SPARE Fiber Optic TRUNK
PORT_26 ESWR1A Fiber Optic TRUNK PORT_26 ESWR1B Fiber Optic TRUNK PORT_26 TSWR1B Fiber Optic TRUNK PORT_26 TSWR1B Fiber Optic TRUNK
Stacking Stacking Stacking Stacking
PORT_27 ESWYB STACK PORT_27 ESWYA STACK PORT_27 ESWR1B STACK PORT_27 ESWR1A STACK
Cable Cable Cable Cable
PORT_28 ESWYB Stacking STACK PORT_28 ESWYA Stacking STACK Stacking PORT_28 ESWR1A Stacking STACK
PORT_28 ESWR1B STACK
Cable Cable Cable Cable

Table 1: Local Switch A Table 2: Local Switch B Table 3: Remote Switch A Table 4: Remote Switch B

Switch: TSWR1A Switch: TSWR1B


Location: Customer Control Room Location: Customer Control Room
IP Address: 172.16.201.241 IP Address: 172.16.201.241
Ports Device Cable Subnet Ports Device Cable Subnet
PORT_1 ESW1A Fiber Optic FIBER OPTIC PORT_1 ESW1B Fiber Optic FIBER OPTIC
PORT_Y ESWYA Fiber Optic FIBER OPTIC PORT_Y ESWYB Fiber Optic FIBER OPTIC
PORT_n+1 ESWR1A Fiber Optic FIBER OPTIC PORT_n+1 ESWR1B Fiber Optic FIBER OPTIC

Table 5: Remote Fiber Optic Switch A Table 6: Remote Fiber Optic Switch B

Notes:
1. To be replaced as SPARE according to the units number

General Notes:
n = number of units
Y = i-unit ; i can be a number between 1 and 11
BC: 01-11
1. All unused copper and fiber ports shall be disabled as described in SOM6759061.
All switches http access shall be disabled after configuration as described in SOM6759061.
It is suggested to change the switches configuration passwords according to customer
specific job password policies. TITLE DOCUMENT CODE REVISION
2. All switches ports shall be monitored and properly alarmed for cable disconnection, CONTROL SYSTEM SCHEMATIC (SIL ARCHITECTURE)
topology errors, unknown device connection and intrusion detection. For configuration CONTROL ROOM CONFIGURATION FOR HEAVY DUTY APPLICATIONS SOM6753633 2
details see GEI-1000693 (GE Control ST Documentation)
REVISION DESCRIPTION PAGE MARKER SECURITY CODE
Added General Notes 1, 2 (Cyber-security policies compliance) N.A. N
Cable Type legend: ORIGINAL JOB SIZE LANGUAGE
Cat5e: Ethernet RJ45 category 5e cable 0402222 3 A
Stacking cable: FlexStack cable. See Links legend (4) in sheet 4
THIS DOCUMENT IS AND CONTAINS CONFIDENTIAL AND PROPRIETARY INFORMATION OF Nuovo Pignone S.r.l WHICH SHALL NOT BE USED OR DISCLOSED TO OTHERS, EXCEPT WITH THE SHEET
Fiber Optic: See Links Legend (3) in sheet 4 WRITTEN PERMISSION OF Nuovo Pignone S.r.l UNPUBLISHED WORK ©2013 Nuovo Pignone S.r.l ALL RIGHTS RESERVED.
9
Pag. D.2.1/9
of 9
GE Oil & Gas
GE Proprietary & Confidential Information
GE NuovoPignone - Electronically Approved Drawing - Checked: Meloni P.; Approved: Nocentini C. - Internal DT-'N'
GE Oil & Gas Product Structuring

CONTROL SYSYEM POWER SUPPLY SCHEMATIC

Control Room configuration for


HEAVY DUTY GAS TURBINE

TITLE DOCUMENT CODE REVISION

REVISION DESCRIPTION APPROVED


DATE SECURITY CODE
STANDARD UPDATE, ALL SHEETS REVISED CHECKED

EXECUTED BY

SCALE REPLACE / DERIVED FROM 1st ISSUE ORIGINAL JOB SIZE LANGUAGE

THIS DOCUMENT IS AND CONTAINS CONFIDENTIAL AND PROPRIETARY INFORMATION OF WHICH SHALL NOT BE USED OR DISCLOSED TO OTHERS, EXCEPT WITH THE SHEET
WRITTEN PERMISSION OF UNPUBLISHED WORK ©2013 ALL RIGHTS RESERVED.

GE Oil & Gas


Pag. D.2.2/1
GE Proprietary & Confidential Information
REVISION
SH.N° TITLE
0 1 2 3 4 5
1 COVER SHEET X X
2 REVISION INDEX AND GENERAL REMARKS X X
3 UCS INTERNAL POWER SUPPLY DISTRIBUTION -UCP X X
4 UCS INTERNAL POWER SUPPLY DISTRIBUTION -UCP X X
5 UCS INTERNAL POWER SUPPLY DISTRIBUTION -UCP X X
6 UCS INTERNAL POWER SUPPLY DISTRIBUTION -UCP X X
7 UCS INTERNAL POWER SUPPLY DISTRIBUTION -UCP X X
8 UCS ELECTRIC LOAD LIST AND HEAT REJECTION TABLES -UCP X X

UCS DESIGN:

POWER FEEDER EARTHING SYSTEM: TN or TT suitable

GENERAL REMARKS:

The Mark VIe/S and other UCS components are designed for using a grounded neutral supply like in the TN or TT
systems (see the picture below as example).

In case of presence of IT system, where the transformer neutral is not earthed, if phase to phase voltage is greater
than 240 Vac, a single-phase shielded isolation transformer shall be installed inside the UCS. The isolation
transformer output winding shall be bonded to the UCS PE earth bar at the time of installation.

TITLE DOCUMENT CODE REVISION

REVISION INDEX AND GENERAL REMARKS


REVISION DESCRIPTION PAGE MARKER SECURITY CODE

ORIGINAL JOB SIZE LANGUAGE

THIS DOCUMENT IS AND CONTAINS CONFIDENTIAL AND PROPRIETARY INFORMATION OF WHICH SHALL NOT BE USED OR DISCLOSED TO OTHERS, EXCEPT WITH THE SHEET
WRITTEN PERMISSION OF UNPUBLISHED WORK ©2013 ALL RIGHTS RESERVED.

GE Oil & Gas


Pag. D.2.2/2
GE Proprietary & Confidential Information
ACRONYMS LEGEND

AUTOMATIC CIRCUIT
BREAKER
FUSE SWITCH PDM Power Distribution Module
B/N Bently Nevada
DCP Direct Current Panel
FF Fire Fighting System
HMI Human Machine Interface
ISOLATING SWITCH TSHL THERMOSTAT MCC Motor Control Center
OSM On Site Monitoring
SIL Safety Integrity Level
UCS Unit Control System
NTP Network Time Protcol

DOOR LIMIT SWITCH FUSE HOLDER

SEMICONDUCTOR
PLUG & SOCKET DIODE

Limits of Supply

OTHERS GE O&G

TITLE DOCUMENT CODE REVISION

SYMBOLS AND ACRONYMS LEGEND


REVISION DESCRIPTION PAGE MARKER SECURITY CODE

ORIGINAL JOB SIZE LANGUAGE

THIS DOCUMENT IS AND CONTAINS CONFIDENTIAL AND PROPRIETARY INFORMATION OF WHICH SHALL NOT BE USED OR DISCLOSED TO OTHERS, EXCEPT WITH THE SHEET
WRITTEN PERMISSION OF UNPUBLISHED WORK ©2013 ALL RIGHTS RESERVED.

GE Oil & Gas


Pag. D.2.2/3
GE Proprietary & Confidential Information
125Vdc
230Vac – 50Hz
From DCP2
From MAIN
Required for 30 min

UNIT CONTROL PANEL [UCP]

EMI EMI
FILTER FILTER

125Vdc from DCP2


Sh.5

POWER SUPPLY
INVERTER
(OUT 230Vac, 50 Hz)
400VA

230Vac, 50Hz

Sh.5

Sh.6

Sh.7

Sh.8

REMOTE
ETHERNET ETHERNET
HMI PRINTER DIAGNOSTIC NTP SERVER TORQUEMETER
SWITCH 1 SWITCH 2
OSM PC

40W 30W 250W 30W 55W 55W


Note 2 Note 2 Note 2 Note 2
Note 3 Note 3 Note 3 Note 3 Note 3 Note 3

TITLE DOCUMENT CODE REVISION


GENERAL NOTES:
1. Modules quantity is related to UCS total power consumption. 100% redundant configuration. UCS INTERNAL POWER SUPPLY DISTRIBUTION UCS
Power supply requirements: 100-240 Vac/Vdc 50/60 Hz auto ranging. REVISION DESCRIPTION PAGE MARKER SECURITY CODE
2. Available as option upon request.
If required, the total power consumption and heat rejection values shall be updated. ORIGINAL JOB SIZE LANGUAGE
3. Standard SCHUKO type. 10A max current for both 110/230Vac 50/60Hz power supplies.
THIS DOCUMENT IS AND CONTAINS CONFIDENTIAL AND PROPRIETARY INFORMATION OF WHICH SHALL NOT BE USED OR DISCLOSED TO OTHERS, EXCEPT WITH THE SHEET
WRITTEN PERMISSION OF UNPUBLISHED WORK ©2013 ALL RIGHTS RESERVED.

GE Oil & Gas


Pag. D.2.2/4
GE Proprietary & Confidential Information
UNIT CONTROL PANEL [UCP]

Sh.4
230Vac, 50Hz from MAIN

Sh.6
125Vdc, from DCP1

Sh.4
125Vdc, from DCP2

480W 480W
125Vdc 230Vac

24Vdc 24Vdc

Note 4 Note 4

B/N
B/N B/N
I.S. GALVANIC HART HMI PANEL COMMUNICATION COMMUNICATION TEMP.
VIBRATION VIBRATION
BARRIERS ISOLATORS MULTIPLEXER PC GATEWAY 1 GATEWAY 2 MONITOR
MONITOR [VIB1] MONITOR [VIB2]
[TEMP1]

20W 20W 20W 200W 45W 45W 100W 100W 100W


Note 2 Note 2 Note 2 Note 2 Note 3 Note 2

GENERAL NOTES:
1. Modules quantity is related to UCS total power consumption. 100% redundant configuration.
Power supply requirements: 100-240 Vac/Vdc 50/60 Hz auto ranging. TITLE DOCUMENT CODE REVISION
2. Available as option upon request.
If required, the total power consumption and heat rejection values shall be updated. UCS INTERNAL POWER SUPPLY DISTRIBUTION UCS
3. As per GT & Train configuration. REVISION DESCRIPTION PAGE MARKER SECURITY CODE
4. Redundancy modules have to be selected to comply with on line maintenance.
ORIGINAL JOB SIZE LANGUAGE

THIS DOCUMENT IS AND CONTAINS CONFIDENTIAL AND PROPRIETARY INFORMATION OF WHICH SHALL NOT BE USED OR DISCLOSED TO OTHERS, EXCEPT WITH THE SHEET
WRITTEN PERMISSION OF UNPUBLISHED WORK ©2013 ALL RIGHTS RESERVED.

GE Oil & Gas


Pag. D.2.2/5
GE Proprietary & Confidential Information
125Vdc
From DCP1
10hrs for MS5001/MS5002,
12 hrs for MS6001,
14 hrs for MS7001,
14 hrs for MS9001 UNIT CONTROL PANEL [UCP]

Sh.4
230Vac, 50Hz from MAIN
EMI
FILTER

Sh.5

Sh.8

480W 480W 480W 480W


125Vdc 230Vac 125Vdc 230Vac

24Vdc 24Vdc 24Vdc 24Vdc

Note 3 Note 3
Note 3 Note 3 230Vac

DACA
Note 2
125Vdc 24Vdc PDM

125/28Vdc PDM Note 2

125Vdc 125Vdc 125Vdc

28Vdc 28Vdc 28Vdc

FIRE FIGHTING MARK VIe MKVIe MKVIeS


FIRE FIGHTING
FIELD Note 1 I/O WETTING I/O WETTING
SYSTEM MARK VIe MARK VIeS
INSTRUMENTATION VOLTAGE VOLTAGE
Note 1 MARK VIeS CPU, I/O, PACK,
SOLENOID VALVES SWITCH
200W 80W 400W 720W – MARKVIe 20W 20W
Note 1 280W – MARKVIeS Note 1

GENERAL NOTE:
1. For SIL Application only
2. 125Vdc and 24Vdc buses are floating and monitored for ground fault. TITLE DOCUMENT CODE REVISION
3. Redundancy modules have to be selected to comply with on line maintenance.
UCS INTERNAL POWER SUPPLY DISTRIBUTION UCS
REVISION DESCRIPTION PAGE MARKER SECURITY CODE

ORIGINAL JOB SIZE LANGUAGE

THIS DOCUMENT IS AND CONTAINS CONFIDENTIAL AND PROPRIETARY INFORMATION OF WHICH SHALL NOT BE USED OR DISCLOSED TO OTHERS, EXCEPT WITH THE SHEET
WRITTEN PERMISSION OF UNPUBLISHED WORK ©2013 ALL RIGHTS RESERVED.

GE Oil & Gas


Pag. D.2.2/6
GE Proprietary & Confidential Information
UNIT CONTROL PANEL [UCP]

Sh.4
230Vac, 50Hz from MAIN

Id 30mA Id 30mA

TH TH TH TL TL TL

. . . . . .
. . .
SERVICE
SOCKET FLUORESCENT FLUORESCENT FLUORESCENT VENTILATION VENTILATION VENTILATION ANTICOND. ANTICOND. ANTICOND.
(MAX 1000W) LAMP #1 LAMP #2 LAMP #n FAN #1 FAN #2 FAN #n HEATER #1 HEATER #2 HEATER #n
(AVERAGE 500W) (15W) (15W) (15W) (40W) (40W) (40W) (150W) (150W) (150W)

HALF DOOR OPENED, AVERAGE LOAD 25% OPERATES FOR TEMPERATURE >40°C, OPERATES FOR TEMPERATURE <10°C,
AVERAGE LOAD 50% AVERAGE LOAD 25%
Note 1 Note 2 Note 3 Note 4

GENERAL NOTE:
1. Socket type according to installation country. 10A max current for both 110/230Vac 50/60Hz power supplies. TITLE DOCUMENT CODE REVISION
2. Lamps quantity shall be updated once selected the UCS layout.
3.Ventilation fans quantity quantity shall be updated once selected the UCS layout UCS INTERNAL POWER SUPPLY DISTRIBUTION UCS
4. Available as option. UCS total power consumption and heat rejection values shall be updated. REVISION DESCRIPTION PAGE MARKER SECURITY CODE

ORIGINAL JOB SIZE LANGUAGE

THIS DOCUMENT IS AND CONTAINS CONFIDENTIAL AND PROPRIETARY INFORMATION OF WHICH SHALL NOT BE USED OR DISCLOSED TO OTHERS, EXCEPT WITH THE SHEET
WRITTEN PERMISSION OF UNPUBLISHED WORK ©2013 ALL RIGHTS RESERVED.

GE Oil & Gas


Pag. D.2.2/7
GE Proprietary & Confidential Information
UNIT CONTROL PANEL [UCP] – MAIN COMPONENT ELECTRIC LOAD LIST
ETHERNET SWITCH 2 230Vac 50/60 Hz 30W DCP2
NTP SERVER 230Vac 50/60 Hz 50W MAIN DEVICE AVAILABLE AS OPTION UPON REQUEST
HMI PRINTER 230Vac 50/60 Hz 40W DCP2 DEVICE AVAILABLE AS OPTION UPON REQUEST
BENTLY NEVADA VIBRATION MONITOR 1 230Vac/125Vdc 50/60 Hz 100W MAIN/DCP2 50W
BENTLY NEVADA VIBRATION MONITOR 2 230Vac/125Vdc 50/60 Hz 100W MAIN/DCP2 50W DEVICE AVAILABLE AS OPTION UPON REQUEST
ON SITE MONITOR SYSTEM 230Vac 50/60 Hz 250W DCP2 100W DEVICE AVAILABLE AS OPTION UPON REQUEST
FIRE FIGHTING SYSTEM 230Vac/125Vdc 50/60 Hz 80W MAIN/DCP1 50W
SPEEDTRONIC MKRK Vie 230Vac/125Vdc 50/60 Hz 720W MAIN/DCP1 500W
SPEEDTRONIC MKRK VieS 230Vac/125Vdc 50/60 Hz 450W MAIN/DCP1 500W
MARK VIe WETTING VOLTAGE 24 Vdc 20W MAIN/DCP1
MARK VIeS WETTING VOLTAGE 24 Vdc 20W MAIN/DCP1
MARK VIe SOLENOID VALVES 230Vac/125Vdc 50/60 Hz 200W MAIN/DCP1
MARK VIeS SOLENOID VALVES 230Vac/125Vdc 50/60 Hz 300W MAIN/DCP1
COMMUNICATION GATEWAY 1 24 Vdc 45W MAIN/DCP2 15W DEVICE AVAILABLE AS OPTION UPON REQUEST
COMMUNICATION GATEWAY 2 24 Vdc 45W MAIN/DCP2 15W DEVICE AVAILABLE AS OPTION UPON REQUEST
GALVANIC ISOLATOR + IS BARRIER 24 Vdc 20W MAIN/DCP2 5W DEVICE AVAILABLE AS OPTION UPON REQUEST
HART MULTIPLEXER 24 Vdc 20W MAIN/DCP2 5W DEVICE AVAILABLE AS OPTION UPON REQUEST
BENTLY NEVADA TEMPERATURE MONITOR 230Vac/125Vdc 50/60 Hz 70W MAIN/DCP1 40W DEVICE AVAILABLE AS OPTION UPON REQUEST
UCS SERVICE SOCKET 230Vac 50/60 Hz 1000W MAIN
UCS FLUORESCENT LAMP (EACH) 230Vac 50/60 Hz 15W MAIN 15W TOTAL VALUE ACCORDING TO SELECTED LAYOUT
UCS VENTILATION FAN (EACH) 230Vac 50/60 Hz 40W MAIN 10W TOTAL VALUE ACCORDING TO SELECTED LAYOUT
UCS NON-CONDENSING HEATER (EACH) 230Vac 50/60 Hz 150W MAIN 150W DEVICE AVAILABLE AS OPTION UPON REQUEST
TORQUEMETER 230Vac 50/60 Hz 40W MAIN DEVICE AVAILABLE AS OPTION UPON REQUEST
SOLENOID VALVES 230Vac/125Vdc 50/60 Hz 200W MAIN/DCP1
LOCAL HMI DESKTOP 230Vac 50/60 Hz 200W CUST. MAIN PREFERRED FEEDS BY CUSTOMER UPS
LOCAL ETHERNET SWITCHES 230Vac 50/60 Hz 60W CUST. MAIN
LOCAL NTP SERVER DESKTOP MOUNTED 230Vac 50/60 Hz 50W CUST. MAIN
LOCAL HMI MONITOR 230Vac 50/60 Hz 100W CUST. MAIN
REMOTE HMI DESKTOP 230Vac 50/60 Hz 200W CUST. MAIN PREFERRED FEEDS BY CUSTOMER UPS

ELECTRIC LOAD LIST AND HEAT DISSIPATION BASE RESULTS: VOLTAGE RATED /KW
TOTAL HEAT
MAIN DCP1 DCP2 CUST. MAIN
DISSIPATION
APPLICATION TYPE (230Vac) (125Vdc) (125Vdc) (125Vdc)
UCS NO SIL 5,3 KW 2,6KW 1.4 0,72 1,6KW
UCS SIL 4,2KW 1,7KW 1.3 0,72 1,3KW

TITLE DOCUMENT CODE REVISION


GENERAL NOTE:
UCS ELECTRIC LOAD LIST AND HEAT REJECTION TABLE UCS
1. the total power consumption is calculated as sum of base equipment add additional 20% for supply sizing.
Options are not included. REVISION DESCRIPTION PAGE MARKER SECURITY CODE
2. the total heat rejection is calculated as sum of base equipment dissipation add additional 20% of margin.
Options are not included. ORIGINAL JOB SIZE LANGUAGE

THIS DOCUMENT IS AND CONTAINS CONFIDENTIAL AND PROPRIETARY INFORMATION OF WHICH SHALL NOT BE USED OR DISCLOSED TO OTHERS, EXCEPT WITH THE SHEET
WRITTEN PERMISSION OF UNPUBLISHED WORK ©2013 ALL RIGHTS RESERVED.

GE Oil & Gas


Pag. D.2.2/8
GE Proprietary & Confidential Information
GE NuovoPignone-Electronically Approved Drawing-Checked: Meloni P., Approved: Innocenti I.-Internal DT-'N'
GE Oil & Gas Product Structuring
MS units

FRONT & REAR ACCESS TYPE


SIL ARCHITECTURE

CUSTOMER:
PLANT LOCATION:
PLANT:
N.P. JOB: 0402222 TITLE DOCUMENT CODE REVISION
TAG:
REVISION DESCRIPTION APPROVED
DATE SECURITY CODE
CHECKED

EXECUTED BY

SCALE REPLACE / DERIVED FROM 1st ISSUE ORIGINAL JOB SIZE LANGUAGE

THIS DOCUMENT IS AND CONTAINS CONFIDENTIAL AND PROPRIETARY INFORMATION OF WHICH SHALL NOT BE USED OR DISCLOSED TO OTHERS, EXCEPT WITH THE SHEET
WRITTEN PERMISSION OF UNPUBLISHED WORK ©2013 ALL RIGHTS RESERVED.
GE Oil & Gas
Pag. D.2.3/1
GE Proprietary & Confidential Information
REVISION N°
SHEET DESCRIPTION
0 1 2 3 4 5 6 7
1 COVER SHEET X
2 REVISION INDEX X
3 DATASHEET X
4 INTERNAL WIRING INFORMATION X
5 FRONT VIEW X X
6 REAR VIEW X X
7 TOP VIEW X X
8 MOUNTED EQUIPMENT LIST X
9 MOUNTED EQUIPMENT LIST X

TITLE DOCUMENT CODE REVISION

REVISION DESCRIPTION PAGE MARKER SECURITY CODE

ORIGINAL JOB SIZE LANGUAGE

THIS DOCUMENT IS AND CONTAINS CONFIDENTIAL AND PROPRIETARY INFORMATION OF WHICH SHALL NOT BE USED OR DISCLOSED TO OTHERS, EXCEPT WITH THE SHEET
WRITTEN PERMISSION OF UNPUBLISHED WORK ©2013 ALL RIGHTS RESERVED.
GE Oil & Gas
Pag. D.2.3/2
GE Proprietary & Confidential Information
A GENERAL DATA
MANUFACTURER STANDARD RITTAL TS8 EMC HIGH
A1 TYPE
GRADE C PAINTING
A2 REFERENCE CODE TYPE IEC UL C1 REFERENCE SPECIFICATIONS MANUFACTURER STD
A3 CONTRACTUAL LANGUAGE ITALIANO ENGLISH FRENCH
EXTERIOR SMOOTH PEEL TYPE
SAFE AREA, AIR CONDITIONING CONTROL ROOM/CAB C2 RAL 7035 RAL 7032 RAL 7030 RAL 6011
A4 INSTALLATION
HEAVY INDUSTRY ENVIRONMENT PLINT AS EXTERIOR BLACK
A5 OPERATING TEMPERATURE +5°C TO +40°C SMOOTH PEEL TYPE
C3 INTERIOR
RAL 7035 GALVANISED
A6 OPERATING HUMIDITY 20 TO 80 % RH NOT CONDENSING
C4 INTERNAL MOUNTING PLATES GALVANISED
A7 MARSHALLING TERMINAL STRIP WITH WITHOUT
 
A8 TERMINAL STRIPS MIRROR OF JUNCTION BOX NOT MIRROR OF JUNCTION BOX
D ELECTRICAL DATA
NO YES, NOT WIRED YES, JUMPERED TO I.E. OR I.S.
A9 SPARE TERMINALS
BAR UPS UPS
SUPPLY LINE DCP MAIN
LINE1 LINE2
A10 CABLE AND CABLE TRAY STD HALOGEN FREE _
D1 SUPPLY VOLTAGE 230 Vac - 110 Vdc 230 Vac
INTRINSECALLY SAFE
A11 NO YES D2 FREQUENCY 50/60 Hz - - 50/60 Hz
BARRIERS/ISOLATORS
A12 SURGE ARRESTORS NO YES D3 LOAD Note 1 - Note 1 Note 1
 
D4 HEAT REJECTION Note 1
D5 INTERNAL LIGHTENING INCANDESCENT FLUORESCENT (VOLTAGE 220V-50Hz)
B MECHANICAL DATA
 
OVERALL DIMENSION (NOTE 2) 5600 mm x 1000 mm x 2380 mm (L x D x H)
B1
ALLOWED TOLERANCE ON = +/- 2% of the total length of the panel, in any case the maximum
E NAMEPLATES
QUOTES tolerance for panel with two columns or more is +/- 50mm
B2 MECHANICAL PROTECTION IP 41 IP 42 IP 54 TO IEC 60529 EXTERNAL PANEL INTERNAL PANEL

B3 STEEL STRUCTURE STICKNESS 2 mm E1 MATERIAL TRAFFOLYTE TAPE

B4 CABLE ENTRY TOP BOTTOM E2 BACKGROUND COLOUR SEE DETAIL ON NEXT PAGES WHITE

B5 CABLE ENTRY FIXING REMOVABLE PLATES CLAMPS CABLE GLAND E3 TEXT COLOUR SEE DETAIL ON NEXT PAGES BLACK

B6 ACCESSIBILITY FRONT ONLY FRONT / REAR E4 FIXING ADHESIVE WITH SCREWS SELF-ADHESIVE
 
B7 DOOR LOCKS OPENING LOCK 95° , RITTAL STD

B8 VENTILATION FANS ON DOOR ON TOP ON ROOF


B9 LIFTING LIFTING BAR “L” TYPE LIFTING EYE BOLT
ONE PIECE COMMON FOR ALL SECTIONS
B10 BASE PLINTH
SINGLE PIECE FOR EACH SECTIONS
B11 APPROX. WEIGHT 3000 KG
 
TITLE DOCUMENT CODE REVISION
Note 1: as per project requirements
Note 2: overall dimension changes according to number of sections REVISION DESCRIPTION PAGE MARKER SECURITY CODE

Remark: internal components location and arrangement can be subject to modification by ORIGINAL JOB SIZE LANGUAGE

manufacturer during construction


THIS DOCUMENT IS AND CONTAINS CONFIDENTIAL AND PROPRIETARY INFORMATION OF WHICH SHALL NOT BE USED OR DISCLOSED TO OTHERS, EXCEPT WITH THE SHEET
WRITTEN PERMISSION OF UNPUBLISHED WORK ©2013 ALL RIGHTS RESERVED.
GE Oil & Gas
Pag. D.2.3/3
GE Proprietary & Confidential Information
Colour notes LEGEND
Cable Type Size
Wire colour External colour
P.E. (GND) = PROTECTION EARTH (GROUND, FRAME CHASSIS)
(1 x 2,5 mm2) (1 x 4 mm2) (1 x 6 mm2) (1 x 10 mm2) NOTE 1 BROWN - AC LINE
I.E. (F.E.) = INSTRUMENT EARTH (NOISELESS), FUNCTIONAL EARTH
(1 x 2,5 mm2) (1 x 4 mm2) (1 x 6 mm2) (1 x 10 mm2) NOTE 1 LIGHT BLUE - AC NEUTRAL
I.S. (I.S.E.) = INTRINSECALLY SAFE EARTH
(1 x 2,5 mm2) (1 x 4 mm2) (1 x 6 mm2) (1 x 10 mm2) NOTE 1 RED - DC POSITIVE (24 VDC)

(1 x 2,5 mm2) (1 x 4 mm2) (1 x 6 mm2) (1 x 10 mm2) NOTE 1 BLACK - DC NEGATIVE (24 VDC)
Note 1:
(1 x 2,5 mm2) (1 x 4 mm2) (1 x 6 mm2) (1 x 10 mm2) NOTE 1 RED - DC POSITIVE (110 VDC)
Max 1,5 mm2 for UCS internal lamps, limit switches,fans, thermostats, isolators
(1 x 2,5 mm2) (1 x 4 mm2) (1 x 6 mm2) (1 x 10 mm2) NOTE 1 BLACK - DC NEGATIVE (110 VDC) power supply.
(1 x 1,5 mm2) (1 x 2,5 mm2) RED - SOLENOID POSITIVE
(1 x 1,5 mm2) (1 x 2,5 mm2) BLACK - SOLENOID NEGATIVE
Note 2:
YELLOW – GREEN
(1 x 2,5 mm2) (1 x 6 mm2) (1 x 16 mm2) (1 x 25 mm2) - EARTH
NOTE 2 Yellow/Green for PE (Protection Earth)
1 x 1 mm2 GREY - DIGITAL SIGNALS
Yellow/Green with Red ring for I.E. (Instrument Earth)
(2 x 0,5 mm2) + shield BROWN-WHITE GREY BIPOLAR ANALOG SIGNALS
Yellow/Green with Blue ring for I.E. (Safety Earth)
BROWN-WHITE-
(3 x 0,5 mm2) + shield GREY TRIPOLAR ANALOG SIGNALS
GREEN
(2 x 0,5 mm2) + shield YELLOW-RED YELLOW THERMOCOUPLES K
GE MARK VI SIMPLEX INTERNAL WIRING
 
Black = Positive
White = Negative

X034
TYPICAL WIRE MARKING
CABLE PIN TERMINAL STRIP NAME

6.33 TERMINAL TYPE


6.33 6.33 TERMINAL COLOR AND QUANTITY (B=BLUE, G= GREY)

UCS WIRING PROGRESSIVE B30


DIAGRAM SHEET N° NUMBER CABLE LABEL DISCONNECTING TERMINAL

TERMINAL WITH FUSE


+
- TERMINAL FOR THERMOCOUPLE

TITLE DOCUMENT CODE REVISION

REVISION DESCRIPTION PAGE MARKER SECURITY CODE

ORIGINAL JOB SIZE LANGUAGE

THIS DOCUMENT IS AND CONTAINS CONFIDENTIAL AND PROPRIETARY INFORMATION OF WHICH SHALL NOT BE USED OR DISCLOSED TO OTHERS, EXCEPT WITH THE SHEET
WRITTEN PERMISSION OF UNPUBLISHED WORK ©2013 ALL RIGHTS RESERVED.
GE Oil & Gas
Pag. D.2.3/4
GE Proprietary & Confidential Information
MP1 TCP1 TCP2 MP & PD ACP1 ACP2
80

(14) (14) (14) (14) (14) (14)


(7A)
(7B)
(8)
(10B)

(9)

(4) (16)
Note 3
(3)
2200

(10A)

(5) (11)

(13)
(6)

(15) (15) (15) (15) (15) (15)


100

800 800 400 800 400 800 800 800

1200 1200

5600 (note 2)
Note 4 Note 1

Note 1: ACP2 is needed only if BN additional vibration Monitor and BN temperature Monitor are provided;
ACP2 is mandatory for MS5002E
Note 2: Evaluate the overall dimension
Note 3: Humming Monitor to be provided only with MS5002E units
Note 4: Evaluate the presence of this section according to the number of signals to be cabled TITLE DOCUMENT CODE REVISION

REVISION DESCRIPTION PAGE MARKER SECURITY CODE


DIMENSION IN MILLIMETER
ORIGINAL JOB SIZE LANGUAGE

THIS DOCUMENT IS AND CONTAINS CONFIDENTIAL AND PROPRIETARY INFORMATION OF WHICH SHALL NOT BE USED OR DISCLOSED TO OTHERS, EXCEPT WITH THE SHEET
WRITTEN PERMISSION OF UNPUBLISHED WORK ©2013 ALL RIGHTS RESERVED.
GE Oil & Gas
Pag. D.2.3/5
GE Proprietary & Confidential Information
MP7 MP6 MP5 MP4 MP3 MP2
80
2200
100

800 800 800 800 400 800 400 800


1200 1200

5600 (note 2)

Note 1 Note 3

Note 1: ACP2 is needed only if BN additional vibration Monitor and BN temperature Monitor are provided;
ACP2 is mandatory for MS5002E
Note 2: Evaluate the overall dimension
Note 3: Evaluate the presence of this section according to the number of signals to be cabled TITLE DOCUMENT CODE REVISION

DIMENSION IN MILLIMETER REVISION DESCRIPTION PAGE MARKER SECURITY CODE

ORIGINAL JOB SIZE LANGUAGE

THIS DOCUMENT IS AND CONTAINS CONFIDENTIAL AND PROPRIETARY INFORMATION OF WHICH SHALL NOT BE USED OR DISCLOSED TO OTHERS, EXCEPT WITH THE SHEET
WRITTEN PERMISSION OF UNPUBLISHED WORK ©2013 ALL RIGHTS RESERVED.
GE Oil & Gas
Pag. D.2.3/6
GE Proprietary & Confidential Information
Note 4 Note 2

MP2 MP3 MP4 MP5 MP6 MP7

MP MARKVIe/MARKVIeS MARKVIe/MARKVIeS MP MP MP
1000

MP1 TCP1 TCP2 MP & PD ACP1 ACP2


ROTATING RACK 19'’ ROTATING RACK 19'’

PD
MP MP PD MP MP MP
Note 1

(13)

ROTATING RACK 19'’


HMI TRANSPARENT DOOR

TRANSPARENT DOOR

800 800 400 800 400 800 800 800


1200 1200

5600 (note 3)

TCP: TURBINE CONTROL PANEL


MP: MARSHALING PANEL
Note 1: Internal distribution MarkVIe & MarkVIeS relocable PD: POWER DISTRIBUTION
Note 2: ACP2 is needed only if BN additional vibration Monitor and BN temperature Monitor are provided; HMI: HUMAN MACHINE INTERFACE
ACP2 is mandatory for MS5002E ACP: AUXILIARY CONTROL PANEL
Note 3: Evaluate the overall dimension
Note 4: Evaluate the presence of this section according to the number of signals to be cabled
TITLE DOCUMENT CODE REVISION

DIMENSION IN MILLIMETER
REVISION DESCRIPTION PAGE MARKER SECURITY CODE

ORIGINAL JOB SIZE LANGUAGE

THIS DOCUMENT IS AND CONTAINS CONFIDENTIAL AND PROPRIETARY INFORMATION OF WHICH SHALL NOT BE USED OR DISCLOSED TO OTHERS, EXCEPT WITH THE SHEET
WRITTEN PERMISSION OF UNPUBLISHED WORK ©2013 ALL RIGHTS RESERVED.
GE Oil & Gas
Pag. D.2.3/7
GE Proprietary & Confidential Information
NAMEPLATE COLORS
POS. DESCRIPTION QUANTITY MANUFACTURER TYPE N.P. CODE NAMEPLATE TEXT
TEXT/BACKGROUND
GENERAL ELECTRIC
1 TURBINE CONTROLLER 1 - - -
MARKVIe
GENERAL ELECTRIC
2 SAFETY PLC 1 - - -
MARKVIeS
ESD MUSHROOM PUSHBUTTON
3 1 - NA EMERGENCY SHUTDOWN WHITE/RED
WITH PROTECTION COVER
TCP MARKVIe HMI PANEL PC
4 1 - - PANEL PC BLACK/WHITE
(FRONT PANEL MOUNTED)
TCP MARKVIe HMI – KEYBOARD & MOUSE
5 1 - - HMI KEYBOARD & MOUSE BLACK/WHITE
(FRONT UP SHELF)
TCP MARKVIe HMI – DOT MATRIX PRINTER
6 1 - - HMI PRINTER BLACK/WHITE
(RACK MOUNTING)

7 ETHERNET SWITCH 2 - - ETH-1 BLACK/WHITE

-
8 NTP SERVER 1 - NTP BLACK/WHITE
(Note 1)

9 FIRE DETECTION & ESTINGUISHING RACK 1 To be defined - FIRE DETECTION BLACK/WHITE

10 VIBRATION MONITOR RACK 1 BENTLY NEVADA 3500 SERIES - VIBRATION MONITOR BLACK/WHITE

-
11 TEMPERATURE MONITOR RACK 1 BENTLY NEVADA 3500 SERIES TEMPERATURE MONITOR BLACK/WHITE
(note 1)
 

Note 1: This rack is avalaible as option, upon request

TITLE DOCUMENT CODE REVISION

REVISION DESCRIPTION PAGE MARKER SECURITY CODE

ORIGINAL JOB SIZE LANGUAGE

THIS DOCUMENT IS AND CONTAINS CONFIDENTIAL AND PROPRIETARY INFORMATION OF WHICH SHALL NOT BE USED OR DISCLOSED TO OTHERS, EXCEPT WITH THE SHEET
WRITTEN PERMISSION OF UNPUBLISHED WORK ©2013 ALL RIGHTS RESERVED.
GE Oil & Gas
Pag. D.2.3/8
GE Proprietary & Confidential Information
NAMEPLATE COLORS
POS. DESCRIPTION QUANTITY MANUFACTURER TYPE N.P. CODE NAMEPLATE TEXT
TEXT/BACKGROUND
ADVANCED FANLESS EMBEDDED COMMUNICATION
12 2 - - BLACK/WHITE
CONTROLLER GATEWAY
-
13 OSM PC 1 - OSM BLACK/WHITE
(note 1)

14 VENTILATION FAN

15 AIR FILTER

-
16 VM600 1 (note 2) VIBRO-METER HUMMING MONITOR BLACK/WHITE
(note 1)

Note 1: This rack is avalaible as option, upon request


Note 2: Humming Monitor to be provided only with MS5002E units

TITLE DOCUMENT CODE REVISION

REVISION DESCRIPTION PAGE MARKER SECURITY CODE

ORIGINAL JOB SIZE LANGUAGE

THIS DOCUMENT IS AND CONTAINS CONFIDENTIAL AND PROPRIETARY INFORMATION OF WHICH SHALL NOT BE USED OR DISCLOSED TO OTHERS, EXCEPT WITH THE SHEET
WRITTEN PERMISSION OF UNPUBLISHED WORK ©2013 ALL RIGHTS RESERVED.
GE Oil & Gas
Pag. D.2.3/9
GE Proprietary & Confidential Information
GE Oil & Gas

CHAPTER E

Miscellanea

GE Oil & Gas


Pag. E
GE Proprietary & Confidential Information
GE Oil & Gas

Utilities

GE Oil & Gas


Pag. E.1
GE Proprietary & Confidential Information
GE Oil & Gas

Preliminary Utility Consumption List

Fuel Gas
Service: For dual fuel or single gas combustion system
Flow: please refer to gas turbine performance table
Pressure: min 18, max 24 barg (STD); min 22, max 24 barg (DLN)
Temperature: 28°C above due point (above 0°C and below 140°C) unless otherwise specified on
gas turbine performance table
Quality: in accordance with GE spec GEI-41040
Instrument Air
Service: Fuel gas scrubber drain on/off valve
Flow: approx. 4 Nm3/h
Pressure: min 6.5, max 8 barg
Quality: instrument air as per ISO8573.1 Class 3.13
Lube and Hydraulic Oil
Tank capacity: 9000 lt. (approx.)
Oil type: mineral ISO VG32
Sample check: 24 hrs after oil change, then every 4000 hrs
Expected consumption: 0.5 lt. per day
Water Washing
Type: water and detergent in accordance with ITN07831.01 sect. 6.1, 6.2, 6.3
Tank capacity: 1000 lt.

GE Oil & Gas


Pag. E.1.1/1
GE Proprietary & Confidential Information
ELECTRIC LOAD LIST SOM

MS5001 + GEAR BOX + GENERATOR

ELECTRIC LOAD LIST

PRELIMINARY FOR BID PROPOSAL –

NOT VALID FOR CONSTRUCTION

TITLE: DOCUMENT CODE REVISION


ELECTRIC LOAD LIST SOM 0
REVISION DESCRIPTION: DATE APPROVED
ISSUED SECURITY
Click here  CHECKED CODE
to enter a  N
EXECUTED Click here to enter 
1 date
st
SCALE REPLACES/DERIVED FROM ISSUE ORIGINAL JOB SIZE LANGUAGE
N/A N/A 05-Dec-13 0401107 4 A
THIS DOCUMENT IS AND CONTAINS CONFIDENTIAL AND PROPRIETARY INFORMATION OF Nuovo Pignone S.r.l. WHICH SHALL NOT BE USED OR SHEET
DISCLOSED
GE Oil & Gas TO OTHERS, EXCEPT WITH THE WRITTEN PERMISSION OF Nuovo Pignone S.r.l. . UNPUBLISHED WORK ©2012 Nuovo Pignone S.r.l.. ALL Pag. E.1.2/1
RIGHTS RESERVED. 1 of 4
GE Proprietary & Confidential Information
480Vac (3Ph - 60Hz) from MCC

Rated Rated Operation


N.P. Voltage Power
Description Stand-by Starting Running Cool Down Emerg.
ITEM (Vac) (kW)

88CR-1 GT Starting motor 480 450 X

Lube oil tank immersion


23QT-1
heater
480 5 X

Lube oil tank immersion


23QT-2
heater
480 5 X

Lube oil tank immersion


23QT-3
heater
480 5 X

Lube oil tank immersion


23QT-4
heater
480 5 X

Auxiliary lube oil pump X X X


88QA-1
motor
480 45

Oil vapour separator fan


88QV-1
motor
480 5,5 X X X X

88QG-1 Electric generator fan motor 480 12.5 X X X

88QG-2 Electric generator fan motor 480 12.5 X X X

88QG-3 Electric generator fan motor 480 12.5 X X X

88QFC-1 Oil/Air Fan cooler 480 22 X X X

88QFC-2 Oil/Air Fan cooler 480 22 X X X

88QFC-3 Oil/Air Fan cooler 480 22 X

88BA - 1 Ventilation fan motor (main) 480 55 X X X

Ventilation fan motor


88BA - 2
(auxiliary)
480 55 X

Washing water skid local


23TW-1
88TW-1
panel (include pump, heater 480 18 X
and lights)

23EG-1-n
Generator winding heaters 480 02 X

Battery charger 1 & DC


BR-1
distribution panel supply
480 25 X X X

TITLE: DOCUMENT CODE REVISION


ELECTRIC LOAD LIST SOM 1
REVISION DESCRIPTION: PAGE MARKER SECURITY
ISSUED N/A CODE
ORIGINAL JOB SIZE N
LANGUAGE
0401107 4 A
THIS DOCUMENT IS AND CONTAINS CONFIDENTIAL AND PROPRIETARY INFORMATION OF Nuovo Pignone S.r.l. WHICH SHALL NOT BE USED OR SHEET
DISCLOSED
GE Oil & Gas TO OTHERS, EXCEPT WITH THE WRITTEN PERMISSION OF Nuovo Pignone S.r.l. . UNPUBLISHED WORK ©2012 Nuovo Pignone S.r.l.. ALL Pag. E.1.2/2
RIGHTS RESERVED. 2 of 4
GE Proprietary & Confidential Information
Battery charger 2 & DC
BR-2
distribution panel supply
480 25 X

Uninterruptible power 15
UPS
supply panel
480 X X X

127 Vac (60Hz) from MCC

Rated Rated Operation


N.P. Voltage Power Cool
Description Stand-by Starting Running Emerg.
ITEM (Vac) (kW) Down

Gas turbine ignition


95-TR-1/10
transformers
127 1 X

AL-9÷14 Filter house normal light 127 0.5 X X X X

23CR-1 Starting motor heater 127 0,4 0,4 0,4 0,4

23QA Aux. pump motor heater 127 0,07 0,07 0,07 0,07 0,07

Emergency pump motor


23QE
heater
127 0,075 0,075 0,075 0,075 0,075

Accessory/turbine
AL-1÷6 compartment normal 127 1 X
lighting
Electric generator fan motor
23QG-1 heater 127 0,025 X

Electric generator fan motor


23QG-2 heater 127 0,025 X

Electric generator fan motor


23QG-3 heater 127 0,025 X

23BA-1 Cooling air fan motor 127 0,08 X X X X

23BA-2 Cooling air fan motor 127 0,08 X X X X

UCS (include lights, fans,


socket, bn, mark VI)
127 3.5 X X X X

Generator excitation panel


aux. supply
127 0.2 X X X X

Generator control/protection
panel aux. supply
127 0.2 X X X X

TITLE: DOCUMENT CODE REVISION


ELECTRIC LOAD LIST SOM 1
REVISION DESCRIPTION: PAGE MARKER SECURITY
ISSUED N/A CODE
ORIGINAL JOB SIZE N
LANGUAGE
0401107 4 A
THIS DOCUMENT IS AND CONTAINS CONFIDENTIAL AND PROPRIETARY INFORMATION OF Nuovo Pignone S.r.l. WHICH SHALL NOT BE USED OR SHEET
DISCLOSED
GE Oil & Gas TO OTHERS, EXCEPT WITH THE WRITTEN PERMISSION OF Nuovo Pignone S.r.l. . UNPUBLISHED WORK ©2012 Nuovo Pignone S.r.l.. ALL Pag. E.1.2/3
RIGHTS RESERVED. 3 of 4
GE Proprietary & Confidential Information
127Vac (1Ph - 60Hz) from UPS

Rated Rated Operation


N.P. Voltage Power Cool
Description Stand-by Starting Running Emerg.
ITEM (Vac) (kW) Down

UCS fire & gas monitor 127 1 X X X X

UCS (include bn, mark VI HMI,


monitor, printer,es)
127 2 X X X X

125Vdc DIRECT CURRENT from DCP

Rated Rated Operation


N.P. Voltage Power Cool
Description (Vdc) (kW) Stand-by Starting Running Emerg.
ITEM Down

88HR Hydraulic ratchet pump motor 125 0.63 X X

Emergency lube oil pump


88QE
motor
125 6.5 X

Accessory/turbine
DL-1/2/3 compartment emergency 125 1 X
lighting

Gearbox enclosure emergency


lighting
125 0.2 X

Filter house compartment


DL-5/6
emergency lighting
125 0.4 X

UCS turbine control panel


mark VI + BN
125 3.5 X X X X

TITLE: DOCUMENT CODE REVISION


ELECTRIC LOAD LIST SOM 1
REVISION DESCRIPTION: PAGE MARKER SECURITY
ISSUED N/A CODE
ORIGINAL JOB SIZE N
LANGUAGE
0401107 4 A
THIS DOCUMENT IS AND CONTAINS CONFIDENTIAL AND PROPRIETARY INFORMATION OF Nuovo Pignone S.r.l. WHICH SHALL NOT BE USED OR SHEET
DISCLOSED
GE Oil & Gas TO OTHERS, EXCEPT WITH THE WRITTEN PERMISSION OF Nuovo Pignone S.r.l. . UNPUBLISHED WORK ©2012 Nuovo Pignone S.r.l.. ALL Pag. E.1.2/4
RIGHTS RESERVED. 4 of 4
GE Proprietary & Confidential Information
GE Oil & Gas

Special Tools

GE Oil & Gas


Pag. E.2
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. E.2.1/1
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. E.2.1/2
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. E.2.1/3
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. E.2.1/4
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. E.2.1/5
GE Proprietary & Confidential Information
GE Oil & Gas

Vendor Documents Register

GE Oil & Gas


Pag. E.3
GE Proprietary & Confidential Information
GE Oil & Gas

Document and Drawing Format

The standard submission of GE Oil & Gas documents and drawings is in electronic format.
Documents and drawings will be submitted in PDF format only.
The following are the rules/guidelines for electronic data exchange:
An Internet Web Site (O&G Collaboration Tool) will be created by GE Oil & Gas and access will be authorized to
the Customer’s Engineering and Project Management teams.
Documents will be published on O&G Collaboration Tool in PDF format, and exchange of comments will be
done electronically.
O&G Collaboration Tool contains all necessary tools for document viewing and light editing (mark-ups)
compatible with all major CAD and Office software.
No hardcopies will be provided by GE Oil & Gas for documents/drawings published on O&G Collaboration Tool.
Notes:
• The drawing lead time shown in the following list starts from PO or LOI sign-off.
• The drawings without lead time will be delivered along with the Instruction and Operating Manual.
• Test procedures will be delivered six weeks prior to the test.

GENuovo
Oil & Gas
Pag. E.3.1/1
Pignone
GE Proprietary
GE Proprietary & Confidential
& Confidential Information
Information
VENDOR DOCUMENT REGISTER

STANDARD DOCUMENTS

Issued for
VDR REF.# Title Typical Content Lead Time Customer Code Customer Title Note Train Applicability
Approval/Info
CE00M65 STARTING MOTOR General arrangement 34 I Madero
GENERAL ARRANGEMENT, drawing of starting motor
FOUNDATION DRAWING
AND TERMINAL BOX
OUTLINE
CE00U10 GENERATOR WIRING Wiring diagram and 40 I Madero
DIAGRAM connecting auxiliary
terminal boards.
CE00U12 GENERATOR CONTROL Wiring diagram og 42 I Madero
& PROTECTION PANEL protection and control
WIRING DIAGRAM panel
CE00U35 FIELD ELECTRICAL Schematic diagram of 20 A Madero
HOOK-UP AND WIRING the electric connections
DIAGRAM  showing the connections
between each field
instruments and the
junction boxes and
Drawing relevant to the
typical electric connections
to be realized for each
instrument (for G.T.
Package are excluded
instruments on Generator)
CE00U38 SUPPLIER UNIT CONTROL Scheme of the electric 38 I Madero
SYSTEM WIRING DIAGRAM wiring inside the control
panel.
CM00U30 GENERAL ARRANGEMENT Drawing of Customer 20 A Madero
AND MECHANICAL Mechanical Connections
PURCHASER CONNECTION and indication of
DRAWING instrumental junction
boxes approximate
position.

GE Oil & Gas


Pag. E.3.2/1
GE Proprietary & Confidential Information
Issued for
VDR REF.# Title Typical Content Lead Time Customer Code Customer Title Note Train Applicability
Approval/Info
CS00U00 GENERATOR PROTECTION Table summarizing the 24 I Madero
OPERATION TABLE functions carried out
by each single electric
protection.
CS00U01 GENERATOR PROTECTION Generator protection 40 I Madero
RELAYS SETTING STUDY setting study with
recommended setting
values.
CS00U05 CONTROL SYSTEM Description step by step 26 A Madero
FUNCTIONAL DESCRIPTION of the control system
including: Start up
procedures, shut-down
procedures, auxiliares
sequences, description of
the control loop carried out
by PCL. It doesn`t cover
control and protection of
the "core engine".
DS00M01 G.T. DATA SHEET (API616) Data Sheet according to 12 A Madero
API616 (applicable edition)
listing the main data and
project/characteristic
construction of the Gas
Turbine.
DS00U00 GENERATOR DATA SHEET Data sheet customer 24 I Madero
format filled-in by supplier.
DS00U01 GENERATOR Generator curves: no load, 24 I Madero
CHARACTERISTIC CURVES short circuit, V, capability
AND DATA and power conditions as
a function of temperature,
etc.
DS01M00 G.T. PERFORMANCE Curves indicating the 20 I Madero
CURVES calculated gas turbine
performances based on
installation conditions.
FD00M03 G.T. AUXILIARY Drawing showing the 35 I Madero
FOUNDATION DWG. accessories foundations
(ducts, skids, etc.)

GE Oil & Gas


Pag. E.3.2/2
GE Proprietary & Confidential Information
Issued for
VDR REF.# Title Typical Content Lead Time Customer Code Customer Title Note Train Applicability
Approval/Info
assembled outside the
turbogroup package and
referred to the G.T. axes.
The overall dimensions
outside the turbogroup
foundations are shown
with a broken line.
FD00U02 MACHINERY FOUNDATION It show the foundations 14 I Madero
LOADS & NOTES of the unit with relevant
static and dynamic loads.
The interaxes between the
found bolts, the relevant
dimensions and indicative
found. Pits are shown. It
shows the list of materials
supplied for the foundation,
it also includes the main
recommendations to be
followed for the calculation
of the turbogroup
foundation.
GA00U00 GENERATOR GENERAL Overall dimension drawing 28 I Madero
ARRANGEMENT showing dimensions,
weight, coupling/fixing
elements, accessory
arrangement, etc.
GA00U11 PLOT PLAN DWG. Drawing with the plot plan 18 A Madero
of the supply.
GA00U12 INTERCONNECTING PIPING Drawing showing all 48 A Madero
LAYOUT interconnecting pipes
between turbine skid
and auxiliaries skid of
NP supply (with relevant
support).On this drawing all
users piping are shown.
GA00U47 TURBOGROUP GENERAL General assembly drawing 12 A Madero
ARRANGEMENT showing showing the

GE Oil & Gas


Pag. E.3.2/3
GE Proprietary & Confidential Information
Issued for
VDR REF.# Title Typical Content Lead Time Customer Code Customer Title Note Train Applicability
Approval/Info
disposition of the main "on
skid" equipments.
GA00U49 SKIDS WEIGHT AND Document describing in 20 I Madero
CENTR.OF GRAVITY DATA detail the weight of the skid
SHEET and the centre of gravity
GA02M01 G.T. WEIGHT AND CENTR. Drawing showing the 36 I Madero
OF GRAVITY location of the center of
gravity and the weights
of the gas turbine, the
casings, rotors and other
single parts that are
dismounted assembled.
The main dimensions of the
parts in question and the
directions for part slinging
and lifting.
IO00U00 ELECTRIC INTERFACE List of the electric signals 32 A Madero
SIGNAL LIST interfacing the customers
equipment.
IO00U02 UNIT CONTROL SYSTEM I/O List of hardwired signals 26 A Madero
LIST at the control panel
input and output. This
document shows the
provenience/destination of
the signals, their function
(alarm,trip,etc.), the type,
the state of the contacts
and, for analog signals, the
range of measure.
IO00U03 SUPPLIER SERIAL List of the signals available 38 I Madero
COMMUNICATION LIST on the serial line of the
U.C.P. For each signal is
indicated the registrer
address, the tag no. and all
the information needed by
the DCS manufacturer to
the configure his system.

GE Oil & Gas


Pag. E.3.2/4
GE Proprietary & Confidential Information
Issued for
VDR REF.# Title Typical Content Lead Time Customer Code Customer Title Note Train Applicability
Approval/Info
MA00U00 INSTRUCTION Index of Operation and 34 A Madero
FOR OPERATION & Maintenance Manuals
MAINTENANCE MANUAL volumes and sections titles
(INDEX) provided for approval of
the basic structure of O &
M Manuals.
MA00U01 INSTRUCTION Operation and At delivery I Madero
FOR OPERATION & Maintenance Manuals for
MAINTENANCE MANUAL site operation. Manuals
(COMPLETE) include: description
of machineries, part
list for machineries,
technical drawings and
manuals for auxiliaries and
instrumentation by OEM.
MA00U03 QUALITY DATA BOOK (MDR) Index of all the certfication 26 weeks A Madero
INDEX and test report provided for before
the Project delivery
MA00U04 QUALITY DATA BOOK (MDR) Collection of all the 4 weeks I Madero
COMPLETE cetification and test after
reports provided for hte delivery
project (material, test and
inspection certification /
report)
MA00U56 TPI - TECHNICAL PACKAGE At delivery I Madero
FOR INSTALLATION
MANUAL (COMPLETE)
MA00U66 TPC - TECHNICAL PACKAGE 10 weeks I Madero
FOR COMMISSIONING after delivey
INSTALLATION MANUAL
(COMPLETE)
MC02M02 G.T. LATERAL ANALYSIS (NP Analysis of the critical 12 I Madero
SUPPLY) frequencies of lateral
vibrations of the gas
turbine rotors.
OE00U00 LOCAL GAUGE BOARD Outline of the local 28 I Madero
LAYOUT gauge board with its
main dimensions. Here is

GE Oil & Gas


Pag. E.3.2/5
GE Proprietary & Confidential Information
Issued for
VDR REF.# Title Typical Content Lead Time Customer Code Customer Title Note Train Applicability
Approval/Info
evidenced the diposition of
the enclosed instruments.
OE00U02 BATTERY LAY-OUT AND Overall dimension drawing 34 I Madero
CONNECTION DIAGRAM showing dimensions,
weight, fixing parts,
batteries arrangement and
relevant connection.
OE00U03 DC PANEL OUTLINE Overall dimension drawing 34 I Madero
DRAWING showing dimensions,
weight, fixing parts and
equipment arrangement
on the front panel.
OE00U12 GENERATOR MAIN Overall dimension drawing 38 I Madero
TERMINAL BOX OUTLINE showing dimensions,
(INCLUDING INTERNAL connection elements,
ARRANGEMENT OF equipment arrangement,
LINE/NEUTRAL CUBICLES) etc.
OE00U14 GENERATOR EXCITATION Overall dimension drawing 26 I Madero
PANEL OUTLINE DRAWING showing dimensions,
weight, fixing elements,
equipment arrangement of
the front panel .
OE00U21 GENERATOR CONTROL Overall dimension drawing 30 I Madero
& PROTECTION PANEL showing dimensions,
OUTLINE DRAWING weight, fixing elements,
equipment arrangement
on the front panel.
OE00U23 PLANT ELECTRICAL Drawing showing the 24 A Madero
OUTLINE DWG. location of the junction
boxes on the Turbogroup
and auxiliary skids.
OE00U26 UNIT CONTROL SYSTEM Outline of the control 12 A Madero
LAYOUT & MAIN panel with its main
COMPONENTS LIST dimensions. Here is
evidenced the disposition
of the macro-components
and the structure of
the panel (sectional

GE Oil & Gas


Pag. E.3.2/6
GE Proprietary & Confidential Information
Issued for
VDR REF.# Title Typical Content Lead Time Customer Code Customer Title Note Train Applicability
Approval/Info
drawing,doors,protection
degree, cable entrance,
estimated weight
and painting). All the
macro-component
OM01M04 FUEL GAS SCRUBBER SKID Drawing showing the 30 I Madero
OUTLINE DWG. outline of the skid, its
overall dimensions, positon
and dimensions of all
process connections,
weight, center of gravity,
tipology of the foundation
connection, main
characteristic data.
OM01M16 FIRE EXTINGUISHING Outline drawing of the 28 I Madero
BOTTLE SKID OUTLINE extinguishing bottle locker
DWG. used for the fire-fighting
system.
PI00U00 FUNCTIONAL SCHEMATIC ISA symbology legend 10 A Madero
DIAGRAMS (P&I). LOAD, for Functional Schematic
UTILITY AND CONNECTION Drawing. Tabular list of
LIST the electrical consumption
data of electrical power
absorbing device within
the supply and indicated
on P&ID drawings. Tabular
list of required (type and
q.ty) of fluid utilities needed
for machines operation
with reference to P&ID
indication. List includes,
when applicable: - Fuel
Gas - Lube oil - Cooling
mediums - Compressed
air Tabular list of teminal
point connection with
indication of size and rating
with reference to P&ID
indication.

GE Oil & Gas


Pag. E.3.2/7
GE Proprietary & Confidential Information
Issued for
VDR REF.# Title Typical Content Lead Time Customer Code Customer Title Note Train Applicability
Approval/Info
PI00U01 FIELD INSTRUMENT LIST Summarizing table 17 I Madero
including all instruments
installed on the
turbogroup. For each
of them the following is
stated : JOB and NP tags,
instrument description
and service, NP purchase
code, supplier''s name and
model, range and settings,
alarm and trip
QP00U00 GENERATOR QUALITY List of quality activity 26 A Madero
CONTROL PLAN performed in conjunction
with customer on the
generator(provided by sub
supplier).
QP00U01 PROJECT QUALITY PLAN ( 12 A Madero
PQP )
QP01U28 QUALITY CONTROL PLAN The Quality Control 8 A Madero
(Q.C.P.) Plan summarizes the
Tests and Inspections
carried out on main
components within the
manufacturing stages of
the GE O&G NP Products(s)
in subject with associated
certificates according to
EN 10204. Quality Control
Plan is the reference
document for: ? Listing
of testing associated
documentation : Reference
Documentation, Procedure
and Acceptance Criteria. ?
Definition of the Customer
Inspector(s) level of
participation associated
to each testing (according
to API Standards: R =

GE Oil & Gas


Pag. E.3.2/8
GE Proprietary & Confidential Information
Issued for
VDR REF.# Title Typical Content Lead Time Customer Code Customer Title Note Train Applicability
Approval/Info
Review, O = Observed,
W = Witness). ? It is also
used to set the Project
Manufacturer Data
Records Index and his
conten of certifcations.
Site Tests/Activities (if
any) are excluded from
this document . H Points)-
Type of certification
supplied:- It is used also
for Manufacturer Data
Records Index.
SL00U00 GENERAL SINGLE LINE Single Line diagram of the 8 A Madero
DIAGRAM whole supply.
SP00U00 PAINTING SPECIFICATION Detailed description of 12 A Madero
Painting System(s) to be
applied for anticorrosion
purpose on the various
part of the supply.
It includes surface
preparation, coating
description and tests.
SP00U02 PIPING LINES Document listing details 18 I Madero
SPECIFICATIONS of piping lines. Some of
these details are: - ASME
references - Materials -
Bolting, gaskets, valves,
tubing details - Testing
TE00M02 G.T. MECHANICAL TEST Procedure describing 6 before test A Madero
PROCEDURE the test of the only gas
turbine without loading for
checking its mechanical
asset.
TE00U00 SUPPLIER UNIT CONTROL Description of the testing 38 I Madero
SYSTEM TEST SUPPLIER procedure of the control
PROCEDURE panel. This document
shows all the types of

GE Oil & Gas


Pag. E.3.2/9
GE Proprietary & Confidential Information
Issued for
VDR REF.# Title Typical Content Lead Time Customer Code Customer Title Note Train Applicability
Approval/Info
test that are to be led,
and, for each test, the
reference instruction
document issued by N.P. to
be followed.
TE01M02 G.T. MECHANICAL TEST Test report of the machine 6 after test I Madero
REPORT without loading for (included
checking its mechanical in MDR)
asset.

GE Oil & Gas


Pag. E.3.2/10
GE Proprietary & Confidential Information
VENDOR DOCUMENT REGISTER

DOCUMENTS INCLUDED IN MANUAL

VDR REF.# Title Typical Content Customer Code Customer Title Note Train Applicability
AD00M01 LOAD COUPLING GUARD Drawing showing the main Madero
ASSEMBLY DWG. dimensions,assembly indication, part list
AD00U01 LOAD COUPLING ASSEMBLY main dimensions;bolting detailed Madero
DRAWING WITH DESIGN description and tightenigh torque;taper
DATA detailed description with interference;parts
and material list; operative condition as
specified; request rating; coupling rating
including API service factor; limit torque;
coupling misalignment capability in
transient and steady state condition, axial
thrust.
AD00U04 FILTER HOUSE ASSEMBLY Drawing showing all necessary parts Madero
DWG. for the assembly of the filter house and
its supporting structure. It also shows
quantities, denominations, NP codes,
dimensions and all component weight.
AD01M03 EXHAUST DUCT ASSEMBLY Drawing showing all parts necessary for Madero
DWG. the exhaust duct assembly. It also shows
quantities, denominations, NP codes,
dimensions and weights of all components.
AD01M06 VENTILATION DUCT Drawing showing all parts necessary for Madero
OUTLINE DWG. the assembly of inlet and exhaust ducts
of the enclosure ventilation. It also shows
the quantity, denominations, NP codes,
dimensions and weights of all components.
AD01M11 G.T. ON BASE ENCLOSURE Drawing showing all parts necessary to Madero
ASSEMBLY DWG. assemble the enclosure on the turbine base
(structure, panels, doors, end-walls, etc.).
It also shows quantities, denominations,
NP codes, dimensions and weights of all
components.
CD00M04 FUEL GAS SCRUBBER Drawing stating the construction elements Madero
CONSTRUCTION DWG. of the device pressure parts.

GE Oil & Gas


Pag. E.3.2/11
GE Proprietary & Confidential Information
VDR REF.# Title Typical Content Customer Code Customer Title Note Train Applicability
CD00M09 HYDRAULIC OIL FILTER Drawing showing the construction elements Madero
CONSTRUCTION DRAWING of the filter pressure parts.
CD00U05 LIFTING DEVICE DWG. Detailed drawing of lifting device ( Lifting Madero
Beam, etc.) and instuctions for its use.
CD00U06 LUBE OIL AIR COOLER Drawing showing the constuction elements Madero
CONSTRUCTION DWG. of the Lube oil air cooler pressure parts.
CE00U33 PRIMARY AND PNEUMATIC Drawing relevant to the primary and Madero
HOOK-UP pneumatic connections to be realized for
each instrument included in G.T. Package
or auxiliary skids (excluding instruments on
Generator)
CO01M01 G.T. SPECIAL TOOL LIST List of special tools supplied for the Madero
disassembly and maintenance of the Gas
Turbine
DS00U14 L.V. MOTOR DATA SHEET Data sheet summarizing the main operation Madero
parameters of the L.V. electric motor.
DS00U19 LUBE OIL AIR COOLER DATA Data sheet contain document for Lube oil Madero
SHEET cooler.
DS00U68 LOAD GEAR DATA SHEET Madero
(API613)
HA00M02 G.T. CLASSIFICATION OF Drawing showing the position of danger Madero
THE HAZARDOUS AREA centers on the gas turbine and the relevant
DWG. classified zones nearby.
HA09U33 CUSTOMER Madero
DOCUMENTATION FOR CE
MARKING
HA09U34 SAFETY MAINTENACE Madero
MANUAL FOR SIL LOOPS
HA09U36 HAZARDOUS AREA Drawing showing the position of danger Madero
CLASSIFICATION centers and the relevant classified zones
TECHNICAL REPORT nearby.
MC00U01 TORSIONAL ANALYSIS train modelization in terms of springs and Madero
inertias,critical speed calculation, campbell
diagramm
OL00U71 INLET DUCT OUTLINE DWG. Drawing showing Inlet duct overall Madero
dimensions listing the main components.

GE Oil & Gas


Pag. E.3.2/12
GE Proprietary & Confidential Information
VDR REF.# Title Typical Content Customer Code Customer Title Note Train Applicability
OM00M24 EXHAUST DUCT OUTLINE Drawing showing Exhaust Duct overall Madero
DWG. dimensions listing the main components.
OM00U08 LOAD GEAR OUTLINE DWG. main dimensions, weight, oil flow required, Madero
ratio, pressure and temperature operative
range,
OM00U09 FILTER HOUSE OUTLINE Drawing showing filter housing overall Madero
DWG. dimensions listing the main components.
OM00U10 LUBE OIL CONSOLE INSTR. Drawing showing the outline of the Madero
LAY-OUT device, its overall dimensions, position and
dimensions of all process connections,
weight, center of gravity, tipology of the
foundation connection, main characteristic
data.
SD00M01 G.T. CROSS SECTIONAL Sectional drawing showing the turbine Madero
DWG. flange-to-flange, inlet and exhaust plenums,
and the baseplate.
SD01U46 INLET DUCT ASSEMBLY Drawing showing all necessary parts for the Madero
DWG. inlet duct assembly. It also shows quantities,
denominations, NP codes, dimensions and
weights of all components.
SP00U01 MAIN SKID WEIGHTING Specification describing all the operations Madero
SPECIFICATION. necessary for the weighting of the various
parts included in N.P. scope of supply.
SP00U03 ALIGNMENT SPECIFICATION Specification with the indications (numeric) Madero
about alignments of machines rotor ends in
skid, string configuration in cold conditions.
UL00U04 LUBRICANT LIST List of lubricants (oil/grease) needed for Madero
machines/auxiliares operation.

GE Oil & Gas


Pag. E.3.2/13
GE Proprietary & Confidential Information
GE Oil & Gas

Vendor List

GE Oil & Gas


Pag. E.4
GE Proprietary & Confidential Information
GE Oil & Gas

Vendor List Statement

Unless otherwise provided for in the Purchase Order, GE Oil & Gas reserves the right to select specific sub-
vendors for the purpose of better meeting the specific needs of the Project. All selected sub-vendors will be
duly qualified by the GE Oil & Gas Sourcing Department to ensure the highest degree of reliability and
performance.
GE Oil & Gas has and maintains a high quality global supplier base. These suppliers are subjected to rigorous
approval, qualification and surveillance processes to maintain this high level of quality.
GE Oil & Gas will make additions and deletions from time to time to the current selected suppliers in an effort
to improve quality and delivery.
More detailed information on specific suppliers can be obtained from the GE Oil & Gas representative upon
request.

GE Oil & Gas


Pag. E.4.1/1
GE Proprietary & Confidential Information
GE Oil & Gas

Manuals

GE Oil & Gas


Pag. E.5
GE Proprietary & Confidential Information
GE Oil & Gas

Installation Manual (Installation and Commissioning/Start-up Manual)

The Technical Package for Installation (TPI) is a collection of all the technical documentation required at the
site to support Installation, Commissioning & Startup of the GE OIL & GAS equipment. It is customized job by
job even though there is a standard structure.
The TPI includes the following primary components:
• Applicable Drawings.
• Applicable Procedures.
• Assembly Sequences.
• Required Tools.
• Site QCP.
• Installation & Commissioning Check Lists.
• Preservation Check Lists.
• Job Safety Cards.

Applicable Drawings and Procedures; Assembly Sequences, including:


• Job design documents (such as drawings & specs, etc.), collected “as is” from Engineering systems,
using the available GE Oil & Gas tools (Iman, EDM, etc.).
• Installation design documents (such as assembly instructions & procedures applying GE Oil & Gas
Field Service best practices and know-how; details and special views derived from job drawings; etc.)
issued directly under the control of the Global Field Service TPI Team.
The Installation Manual is subdivided by systems and/or components, and includes detailed descriptions of
installation activities, the applicable design documents, the reference standard procedures, the Job Safety
Analysis cards, etc. The Commissioning & Startup Manual has the same structure, including the description of
the commissioning of each system, while the startup operations are described in a check list format.
Note: Both documents are intended to provide additional advisory support beyond the TA, and are not
intended to replace the TA in any case.

The Site Quality Control Plan (ITP) defines the quality standards to be observed during site activities. It lists all
the quality verifications, the reference applicable documents (design data), the verification procedures, the
acceptance criteria, the Customer/Third Party/GE Oil & Gas Supervisor attendance rules and the certifications
to be issued at the completion of tests.
It also defines the minimum required checks to be attended, as Hold Points, by GE Oil & Gas inspectors. These
include at least:
• Positioning on foundation, alignment and installation of couplings of machines.
• Process main piping connection to machines.
• Cleaning/blowing/flushing of piping systems.
• Check of conformity with installation drawings for each system/component.
• Equipment integrity & preservation check.
• Commissioning & startup.

GE Oil & Gas


Pag. E.5.1/1
GE Proprietary & Confidential Information
GE Oil & Gas

Installation, Commissioning and Start-up Check Lists enable the traceability of the execution of site
activities. They include, for each system and/or component, a brief description of activities, the applicable
design documents, the reference standard procedures (where applicable), and the certification to be issued, if
required. By signing it, all involved parties acknowledge the correct execution of each main step in the site
activities.

The Preservation Check List is a new document developed to have all the procedures applicable (pre-shipping
and site) to each item consolidated in a single document which also clearly identifies responsibilities (signature
from Client/GE supervisor when applicable).

Job Safety Cards are gathered from the existing dedicated EHS team and are included as an appendix.

GE Oil & Gas


Pag. E.5.1/2
GE Proprietary & Confidential Information
GE Oil & Gas

Site Container

GE Oil & Gas


Pag. E.6
GE Proprietary & Confidential Information
GE Oil & Gas

Installation Site Container

Definition
The Installation Site Container (the “Container”) is a “mobile” warehouse complete with a full set of incidental
consumable materials and tools. It is critical that a completely stocked Container be at hand and available for
use during the installation phase. The Container will be located on site to facilitate installation by stocking c-
class items on-site for immediate use, if necessary.
The Container will help to eliminate typical lead-time issues during installation, which may result from missing
or defective items.
The parts included in the Container are installation consumables and therefore GE Oil & Gas will not
reintegrate any part or item used during installation.
The Container will remain at the disposal of GE Oil & Gas once the installation has been completed.
In case the GE Oil & Gas scope of supply includes installation activities or supervision, GE Oil & Gas shall have
exclusive rights over both the Container and the entirety of its contents for the period up to the expiration of
the Warranty Period.

Item List
The following list is an example of materials usually found in the Container:
• Compression fittings.
• Bolts, nuts, washers and helicoils.
• Spiro-metallic gaskets.
• Tubing.
• Adhesive neoprene gaskets, VITON o-rings and rolls.
• Klinger and graphite sheets.
• Threaded rods.
• Screen meshes.
• Blind flanges and orifices.
• Isolation valves.
• Cable glands and lugs.
• Fuses and thermo-proximiters.
• Thermocouples.
• Sets of tools (riveting machine, grinder, drill, tubing cutter and bending machine, etc).

Container Arrangement
The Container is a Standard 20’ ISO Marine Container, certified R.I.N.A. with a lockable door.
• External dimensions (mm): 6058x2435x2591.
• Internal dimensions (mm): 5995x2345x2380.

GE Oil & Gas


Pag. E.6.1/1
GE Proprietary & Confidential Information
GE Oil & Gas

It is equipped internally with shelves and workbench with drawers. The shelves are identified by letters and
numbers.
Example of the Container – Internal arrangement

GE Oil & Gas


Pag. E.6.1/2
GE Proprietary & Confidential Information
GE Oil & Gas

Reference List

GE Oil & Gas


Pag. E.7
GE Proprietary & Confidential Information
MS5001PA GAS TURBINE REFERENCE LIST

Shipped Env. Temp. Env. Temp. Speed Secondary Combustion


Equipment Job Model Site Country (Nation) Climatic Area Use Cycle Fuel Primary Fuel
Date min. (°C) max (°C) [Rpm] Fuel System

17080 MS 5001PA FERRARA ITALY CONTINENTAL 1966 GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL FUEL ---
17080 MS 5001PA FERRARA ITALY CONTINENTAL 1966 GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL FUEL ---
17081 MS 5001PA PICO TRUNCADO ARGENTINA CONTINENTAL 1969 GENERATOR DRIVER 5094 SIMPLE CYCLE LPG-RO ---
17082 MS 5001PA PICO TRUNCADO ARGENTINA CONTINENTAL 1969 GENERATOR DRIVER 5094 SIMPLE CYCLE LPG-RO ---
1600009 MS 5001PA RAGUBA LIBYA DESERTIC 1968 GENERATOR DRIVER 5094 SIMPLE CYCLE LPG-RO ---
1600013 MS 5001PA DELFZIJL NETHERLANDS CONTINENTAL 1969 GENERATOR DRIVER 5094 SIMPLE CYCLE DISTILLATE OIL ---
1600014 MS 5001PA GRENOBLE FRANCE CONTINENTAL 1969 5094 SIMPLE CYCLE DISTILLATE OIL ---
1600015 MS 5001PA TARANTO ITALY CONTINENTAL 1969 GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL FUEL ---
1600015 MS 5001PA TARANTO ITALY CONTINENTAL 1969 GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL FUEL ---
1600015 MS 5001PA TARANTO ITALY CONTINENTAL 1969 GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL FUEL ---
1600018 MS 5001PA DELFZIJL NETHERLANDS CONTINENTAL 1970 GENERATOR DRIVER 5094 SIMPLE CYCLE DISTILLATE OIL ---
1600019 MS 5001PA ST. THOMAS VIRGIN ISLANDS TROPICAL 1969 GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL FUEL ---
1600020 MS 5001PA USA CONTINENTAL 1970 GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL FUEL ---
1600022 MS 5001PA FOS SUR MER USA CONTINENTAL 1970 GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL FUEL ---
1600023 MS 5001PA GRENOBLE FRANCE CONTINENTAL 1969 GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL FUEL ---
1600034 MS 5001PA CJAUDA JUAREZ MEXICO TROPICAL 1967 GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL FUEL ---
1600034 MS 5001PA CJAUDA JUAREZ MEXICO TROPICAL 1967 GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL FUEL ---
1600037 MS 5001PA NORTHEM NECK VIRGINIA USA CONTINENTAL 1971 GENERATOR DRIVER 5094 SIMPLE CYCLE DISTILLATE OIL ---
1600037 MS 5001PA NORTHEM NECK VIRGINIA USA CONTINENTAL 1971 GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL FUEL ---
1600038 MS 5001PA NORTHEM NECK VIRGINIA USA CONTINENTAL 1970 GENERATOR DRIVER 5094 SIMPLE CYCLE DISTILLATE OIL ---
1600038 MS 5001PA NORTHEM NECK VIRGINIA USA CONTINENTAL 1971 GENERATOR DRIVER 5094 SIMPLE CYCLE DISTILLATE OIL ---
1600039 MS 5001PA DELFZIJL NETHERLANDS CONTINENTAL 1969 GENERATOR DRIVER 5094 SIMPLE CYCLE DISTILLATE OIL ---
1600040 MS 5001PA PORTO VESME ITALY CONTINENTAL 1972 GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL FUEL ---
1600040 MS 5001PA PORTO VESME ITALY CONTINENTAL 1972 GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL FUEL ---
1600043 MS 5001PA HASSI MESSAOUD ALGERIA DESERTIC 1968 GENERATOR DRIVER 5094 SIMPLE CYCLE DISTILLATE OIL ---
1600043 MS 5001PA HASSI MESSAOUD ALGERIA DESERTIC 1972 GENERATOR DRIVER 5094 SIMPLE CYCLE DISTILLATE OIL ---
1600044 MS 5001PA ST. THOMAS VIRGIN ISLANDS TROPICAL 1971 GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL FUEL ---
1600056 MS 5001PA ROME ITALY CONTINENTAL 1971 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS --- ---
1600056 MS 5001PA ROME ITALY CONTINENTAL 1971 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS --- ---
1600057 MS 5001PA BUENOS AIRES ARGENTINA CONTINENTAL 1973 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS --- ---
1600057 MS 5001PA BUENOS AIRES ARGENTINA CONTINENTAL 1973 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS --- ---
1600058 MS 5001PA MILANO ITALY CONTINENTAL 1975 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS --- ---
1600059 MS 5001PA ACAPULCO MEXICO TROPICAL 1973 GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL FUEL ---
1605112 MS 5001PA ROME ITALY CONTINENTAL 1973 GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL FUEL ---
1605246 MS 5001PA UMM SAID QATAR DESERTIC 1982 GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL FUEL ---
1605247 MS 5001PA UMM SAID QATAR DESERTIC 1982 GENERATOR DRIVER 5094 SIMPLE CYCLE NAPHTA ---
1605284 MS 5001PA MEDEA ALGERIA DESERTIC 1982 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS --- ---
1605287 MS 5001PA UMM SAID QATAR DESERTIC 1982 GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL FUEL ---
1605311 MS 5001PA MARMUL OMAN DESERTIC 1977 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS --- ---
1605312 MS 5001PA MARMUL OMAN DESERTIC 1978 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS --- ---
1605362 MS 5001PA NAMRUP INDIA DESERTIC 1985 N.A. N.A. GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL FUEL ---
1605363 MS 5001PA LUCKNOW INDIA DESERTIC 1986 N.A. N.A. GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL FUEL ---
1605364 MS 5001PA JAGDISHPUR INDIA DESERTIC 1986 N.A. N.A. GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL FUEL ---
1605365 MS 5001PA LIAO-HE CHINA CONTINENTAL 1986 -30 35 GAS COMPRESSOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS --- ---
1605366 MS 5001PA ULSAN SOUTH KOREA TROPICAL 1988 N.A. N.A. GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL FUEL ---
1605367 MS 5001PA SANNAZZARO DE' BURGUNDI (PAITALY CONTINENTAL 1988 N.A. N.A. GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL FUEL ---
1605368 MS 5001PA DEDEDO GUAM TROPICAL 1990 N.A. N.A. GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL LIQUID ---
1605369 MS 5001PA MILAZZO (SICILIA) ITALY CONTINENTAL 1989 N.A. N.A. GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS --- STEAM INJECTION
1605370 MS 5001PA PHILADELPHIA USA CONTINENTAL 1990 N.A. N.A. GENERATOR DRIVER / COMBINED 5094 SIMPLE CYCLE DUAL FUEL STEAM INJECTION
1605371 MS 5001PA SANNAZZARO DE' BURGUNDI ITALY CONTINENTAL 1989 N.A. N.A. GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL FUEL STEAM INJECTION
1605372 MS 5001PA LIVORNO (TOSCANA) ITALY CONTINENTAL 1990 N.A. N.A. GENERATOR DRIVER / COMBINED 5094 SIMPLE CYCLE DUAL FUEL WATER INJECTION
1605373 MS 5001PA COCHABAMBA BOLIVIA CONTINENTAL 1990 N.A. N.A. GENERATOR DRIVER / COMBINED 5094 SIMPLE CYCLE DUAL FUEL WATER INJECTION
1605374 MS 5001PA HAVEN UNITED KINGDOM CONTINENTAL 1990 N.A. N.A. GENERATOR DRIVER / COMBINED 5094 SIMPLE CYCLE DUAL FUEL STEAM INJECTION
1605375 MS 5001PA PORTO MARGHERA (VENETO) ITALY CONTINENTAL 1992 N.A. N.A. GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL FUEL ---
1605376 MS 5001PA ADRAR ALGERIA DESERTIC 1992 N.A. N.A. GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS --- ---
1605377 MS 5001PA ADRAR ALGERIA DESERTIC 1992 N.A. N.A. GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS --- ---
1605378 MS 5001PA ADRAR ALGERIA DESERTIC 1992 N.A. N.A. GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS --- ---
1605379 MS 5001PA ADRAR ALGERIA DESERTIC 1992 N.A. N.A. GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS --- ---
1605380 MS 5001PA DEDEDO GUAM TROPICAL 1992 N.A. N.A. GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS --- ---
1605381 MS 5001PA HAMRA ALGERIA DESERTIC 1992 -5 45 GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL FUEL NATURAL GAS DUAL LIQUID ---
1605382 MS 5001PA HAMRA ALGERIA DESERTIC 1992 -5 45 GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL FUEL NATURAL GAS DUAL LIQUID ---
1605383 MS 5001PA ANGOLA "COB P1" ANGOLA 1994 18 35 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS DUAL LIQUID ---
1605384 MS 5001PA ANGOLA "COB P1" ANGOLA 1994 18 35 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS DUAL LIQUID ---

GE Oil & Gas


Pag. E.7.1/1
GE Proprietary & Confidential Information
Shipped Env. Temp. Env. Temp. Speed Secondary Combustion
Equipment Job Model Site Country (Nation) Climatic Area Use Cycle Fuel Primary Fuel
Date min. (°C) max (°C) [Rpm] Fuel System

1605385 MS 5001PA ANGOLA "COB P1" ANGOLA 1994 18 35 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS DUAL LIQUID ---
1605386 MS 5001PA COLLOMBEY SWITZERLAND CONTINENTAL 1995 -7 29 GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL FUEL STEAM INJECTION
1605387 MS 5001PA DUBAI SAUDI ARABIA DESERTIC 1997 0 50 GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL FUEL NATURAL GAS DUAL LIQUID ---
1605388 MS 5001PA DUBAI SAUDI ARABIA DESERTIC 1997 0 50 GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL FUEL NATURAL GAS DUAL LIQUID ---
1605389 MS 5001PA DUBAI SAUDI ARABIA DESERTIC 1997 0 50 GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL FUEL NATURAL GAS DUAL LIQUID ---
1605390 MS 5001PA MONTEMARTINI (LAZIO) ITALY CONTINENTAL 1997 0 40 GENERATOR DRIVER 5094 SIMPLE CYCLE RESIDUAL OIL NATURAL GAS DUAL LIQUID ---
1605391 MS 5001PA MONTEMARTINI (LAZIO) ITALY CONTINENTAL 1997 0 40 GENERATOR DRIVER 5094 SIMPLE CYCLE RESIDUAL OIL NATURAL GAS DUAL LIQUID ---
1605392 MS 5001PA ROME ITALY CONTINENTAL 1997 0 40 GENERATOR DRIVER 5094 SIMPLE CYCLE RESIDUAL OIL NATURAL GAS DUAL LIQUID WATER INJECTION
1605393 MS 5001PA NORTH SLOPE ALASKA ARCTIC 1998 -45 27 GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL FUEL WATER INJECTION
1605400 MS 5001PA MARMUL OMAN DESERTIC 1981 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS ND ---
1605401 MS 5001PA AZZAWIYA LIBYA DESERTIC 1982 GENERATOR DRIVER 5094 SIMPLE CYCLE RESIDUAL OIL / NATURAL GAS NATURAL GAS ND ---
1605405 MS 5001PA ROME ITALY CONTINENTAL 1983 GENERATOR DRIVER 5094 SIMPLE CYCLE RESIDUAL OIL / NATURAL GAS DUAL LIQUID ---
1605473 MS 5001PA NAMRUP INDIA DESERTIC 1983 0 37 GAS COMPRESSOR DRIVER 5094 SIMPLE CYCLE DUAL FUEL NATURAL GAS ---
1605476 MS 5001PA BAHRAIN DESERTIC 1984 0 41 GAS COMPRESSOR DRIVER 5094 SIMPLE CYCLE RESIDUAL OIL / NATURAL GAS NATURAL GAS ---
1605490 MS 5001PA ALAMEDA CALIFORNIA USA CONTINENTAL 1985 0 41 GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL FUEL NATURAL GAS ND WATER INJECTION
1605491 MS 5001PA LODI CALIFORNIA USA CONTINENTAL 1985 0 41 GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL FUEL NATURAL GAS ND WATER INJECTION
1605492 MS 5001PA ROSEVILLE CALIFORNIA USA CONTINENTAL 1985 0 41 GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL FUEL NATURAL GAS ND WATER INJECTION
1605493 MS 5001PA ROSEVILLE CALIFORNIA USA CONTINENTAL 1985 0 41 GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL FUEL NATURAL GAS ND WATER INJECTION
1605494 MS 5001PA UKIAH CALIFORNIA USA CONTINENTAL 1985 0 41 GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL FUEL NATURAL GAS DUAL LIQUID WATER INJECTION
1605497 MS 5001PA KHARTOUM SUDAN DESERTIC 1985 2 50 GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL FUEL NATURAL GAS DUAL LIQUID ---
1605498 MS 5001PA KHARTOUM SUDAN DESERTIC 1984 2 50 GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL FUEL NATURAL GAS DUAL LIQUID ---
1705500 MS 5001PA GIRASSOL PLATFORM ANGOLA 1999 18 35 GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL FUEL NATURAL GAS DUAL LIQUID ---
1705501 MS 5001PA GIRASSOL PLATFORM ANGOLA 1999 18 35 GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL FUEL NATURAL GAS DUAL LIQUID ---
1705502 MS 5001PA GIRASSOL PLATFORM ANGOLA 1999 18 35 GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL FUEL NATURAL GAS DUAL LIQUID ---
1705503 MS 5001PA OBIAFU OBRIKOM NIGERIA TROPICAL 1999 16 36 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS --- WATER INJECTION
1705504 MS 5001PA OBIAFU OBRIKOM NIGERIA TROPICAL 1999 16 36 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS --- ---
1705505 MS 5001PA OBIAFU OBRIKOM NIGERIA TROPICAL 1999 16 36 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS --- ---
1705506 MS 5001PA ARAR SAUDI ARABIA DESERTIC 1999 -6 50 GENERATOR DRIVER 5094 SIMPLE CYCLE DISTILLATE OIL --- --- STEAM INJECTION
1705507 MS 5001PA PLOIESTI ROMANIA CONTINENTAL 2000 -30 35 GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL FUEL NATURAL GAS DUAL LIQUID STEAM INJECTION
1705508 MS 5001PA PLOIESTI ROMANIA CONTINENTAL 2000 -30 35 GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL FUEL NATURAL GAS DUAL LIQUID STEAM INJECTION
1705509 MS 5001PA SRIRACHA THAILAND TROPICAL 2000 17 39 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS --- STEAM INJECTION
1705510 MS 5001PA TAYMA SAUDI ARABIA DESERTIC 2000 -18 55 GENERATOR DRIVER 5094 SIMPLE CYCLE DISTILLATE OIL --- --- ---
1705511 MS 5001PA TAYMA SAUDI ARABIA DESERTIC 2000 -18 55 GENERATOR DRIVER 5094 SIMPLE CYCLE DISTILLATE OIL --- --- ---
1705512 MS 5001PA MALAYSIA LNG MALAYSIA TROPICAL 2001 19 36 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS --- DRY LOW NOX
1705513 MS 5001PA MALAYSIA LNG MALAYSIA TROPICAL 2001 19 36 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS --- DRY LOW NOX
1705514 MS 5001PA MALAYSIA LNG MALAYSIA TROPICAL 2001 19 36 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS --- DRY LOW NOX
1705515 MS 5001PA MALAYSIA LNG MALAYSIA TROPICAL 2001 19 36 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS --- DRY LOW NOX
1705516 MS 5001PA MALAYSIA LNG MALAYSIA TROPICAL 2001 19 36 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS --- DRY LOW NOX
1705517 MS 5001PA PULAU SERAYA SINGAPORE TROPICAL 2000 19.4 35.8 GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL FUEL NATURAL GAS DUAL LIQUID ---
1705518 MS 5001PA PULAU SERAYA SINGAPORE TROPICAL 2000 19.4 35.8 GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL FUEL NATURAL GAS DUAL LIQUID ---
1705519 MS 5001PA WIDURI INDONESIA TROPICAL 2001 18 32 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS --- DRY LOW NOX
1705520 MS 5001PA ATTAHADDY LIBYA DESERTIC 2001 -3 54 GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL FUEL NATURAL GAS DUAL LIQUID STEAM INJECTION
1705521 MS 5001PA ATTAHADDY LIBYA DESERTIC 2001 -3 54 GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL FUEL NATURAL GAS DUAL LIQUID STEAM INJECTION
1705522 MS 5001PA OMOKU NIGERIA TROPICAL 2001 25 45 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS --- ---
1705523 MS 5001PA OMOKU NIGERIA TROPICAL 2001 25 45 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS --- ---
1705524 MS 5001PA BONTANG KALIMANTAN INDONESIA TROPICAL 2001 20 35 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS --- ---
1705525 MS 5001PA OMOKU NIGERIA TROPICAL 2002 25 45 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS --- ---
1705526 MS 5001PA KWALE NIGERIA TROPICAL 2002 25 45 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS --- ---
1705534 MS 5001PA WAFA LIBYA DESERTIC 2002 -2.5 45 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS --- ---
1705535 MS 5001PA WAFA LIBYA DESERTIC 2002 -2.5 45 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS --- ---
1705536 MS 5001PA WAFA LIBYA DESERTIC 2002 -2.5 45 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS --- ---
1705537 MS 5001PA WAFA LIBYA DESERTIC 2002 4 41 GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL FUEL NATURAL GAS ---
1705538 MS 5001PA WAFA LIBYA DESERTIC 2002 4 41 GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL FUEL NATURAL GAS DUAL LIQUID ---
1705539 MS 5001PA WAFA LIBYA DESERTIC 2002 4 41 GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL FUEL NATURAL GAS DUAL LIQUID ---
1705540 MS 5001PA PHU MY VIETNAM TROPICAL 2002 18 40 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS --- ---
1705541 MS 5001PA OMOKU NIGERIA TROPICAL 2002 19.4 35.8 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS --- ---
1705542 MS 5001PA OMOKU NIGERIA TROPICAL 2002 19.4 35.8 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS --- ---
1705546 MS 5001PA TUBAN INDONESIA TROPICAL 2004 17 36 GENERATOR DRIVER 5094 ---
1705547 MS 5001PA TUBAN INDONESIA TROPICAL 2004 17 36 GENERATOR DRIVER 5094 ---
1705548 MS 5001PA TUBAN INDONESIA TROPICAL 2004 17 36 GENERATOR DRIVER 5094 ---
1705549 MS 5001PA MALABO ISLAND EQUATORIAL GUINEA 2003 18 40 GENERATOR DRIVER 5094 ---
1705550 MS 5001PA MALABO ISLAND EQUATORIAL GUINEA 2003 18 40 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS --- ---
1705551 MS 5001PA INAMENAS ALGERIA DESERTIC 2004 -5 45 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS --- LEAN HEAD END
1705552 MS 5001PA INAMENAS ALGERIA DESERTIC 2004 -5 45 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS --- LEAN HEAD END
1705553 MS 5001PA INAMENAS ALGERIA DESERTIC 2004 -5 45 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS --- DRY LOW NOX
1705554 MS 5001PA DAS ISLAND UNITED ARAB EMIRATES DESERTIC 2003 5094 SIMPLE CYCLE DUAL FUEL NATURAL GAS ---
1705555 MS 5001PA SAKHALIN ISLAND RUSSIA 2004 -33 34 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS --- DRY LOW NOX
1705556 MS 5001PA SAKHALIN ISLAND RUSSIA 2004 -33 34 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS --- DRY LOW NOX

GE Oil & Gas


Pag. E.7.1/2
GE Proprietary & Confidential Information
Shipped Env. Temp. Env. Temp. Speed Secondary Combustion
Equipment Job Model Site Country (Nation) Climatic Area Use Cycle Fuel Primary Fuel
Date min. (°C) max (°C) [Rpm] Fuel System

1705557 MS 5001PA SAKHALIN RUSSIA 2004 -33 34 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS --- DRY LOW NOX
1705558 MS 5001PA SAKHALIN RUSSIA 2004 -33 34 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS --- DRY LOW NOX
1705559 MS 5001PA SAKHALIN RUSSIA 2004 -33 34 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS ---
1705562 MS 5001PA SOUTH BAGHDAD IRAQ DESERTIC 2004 -20 55 GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL LIQUID DUAL LIQUID
1705563 MS 5001PA SOUTH BAGHDAD IRAQ DESERTIC 2004 -20 55 GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL LIQUID DUAL LIQUID
1705564 MS 5001PA SOUTH BAGHDAD IRAQ DESERTIC 2004 -20 55 GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL LIQUID DUAL LIQUID
1705565 MS 5001PA SOUTH BAGHDAD IRAQ DESERTIC 2004 -20 55 GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL LIQUID DUAL LIQUID
1705566 MS 5001PA SOUTH BAGHDAD IRAQ DESERTIC 2004 -20 55 GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL LIQUID DUAL LIQUID
1705567 MS 5001PA SOUTH BAGHDAD IRAQ DESERTIC 2004 -20 55 GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL LIQUID DUAL LIQUID
1705569 MS 5001PA OMOKU NIGERIA TROPICAL 2004 25 45 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS ---
1705570 MS 5001PA ELEME NIGERIA TROPICAL 2004 25 45 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS ---
1705571 MS 5001PA ELEME NIGERIA TROPICAL 2004 25 45 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS ---
1705572 MS 5001PA BIOKO ISLAND EQUATORIAL GUINEA 2005 18 40.5 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS ---
1705573 MS 5001PA BIOKO ISLAND EQUATORIAL GUINEA 2005 18 40.5 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS ---
1705574 MS 5001PA ILAM IRAN 2004 -13 42 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS ---
1705575 MS 5001PA ILAM IRAN 2004 -13 42 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS ---
1705576 MS 5001PA ILAM IRAN 2004 -13 42 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS ---
1705579 MS 5001PA DAS ISLAND ABU DHABI 2004 9 48 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS ---
1705580 MS 5001PA YEOCHEON SOUTH KOREA 2005 -12 40 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS ---
1705581 MS 5001PA ALGERIA DESERTIC 2006 -5 55 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS ---
1705582 MS 5001PA ALGERIA DESERTIC 2005 -5 55 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS ---
1705583 MS 5001PA ALGERIA DESERTIC 2005 -5 55 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS ---
1705584 MS 5001PA ALGERIA DESERTIC 2006 -5 55 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS ---
1705585 MS 5001PA SOUTH BAGHDAD IRAQ 2005 -20 55 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS ---
1705586 MS 5001PA SOUTH BAGHDAD IRAQ 2005 -20 55 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS ---
1705587 MS 5001PA BOU - ISAMIL - TIPAZA ALGERIA DESERTIC 2005 -5 50 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS ---
TROPICAL /
1705588 MS 5001PA MELAKA MALAYSIA 2005 19.5 36.5 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS --- STEAM INJECTION
MARINE
TROPICAL /
1705589 MS 5001PA MELAKA MALAYSIA 2005 19.5 36.5 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS --- STEAM INJECTION
MARINE
TROPICAL /
1705590 MS 5001PA MELAKA MALAYSIA 2005 19.5 36.5 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS --- STEAM INJECTION
MARINE
TROPICAL /
1705591 MS 5001PA MELAKA MALAYSIA 2005 19.5 36.5 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS --- STEAM INJECTION
MARINE
1705592 MS 5001PA OBIAFU OBRIKOM NIGERIA 2005 16 36 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS ---
1705593 MS 5001PA OMOKU NIGERIA 2005 25 45 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS ---
1705594 MS 5001PA TRANS AMADI NIGERIA 2005 25 45 GENERATOR DRIVER 5094 SIMPLE CYCLE
1705595 MS 5001PA TRANS AMADI NIGERIA 2005 25 45 GENERATOR DRIVER 5094 SIMPLE CYCLE
N.A. MS 5001PA ST. CROIX VIRGIN ISLANDS TROPICAL 1964 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS --- ---
N.A. MS 5001PA ST. CROIX VIRGIN ISLANDS TROPICAL 1968 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS --- ---
N.A. MS 5001PA BALTIMORA USA CONTINENTAL 1968 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS --- ---
N.A. MS 5001PA ST. CROIX VIRGIN ISLANDS TROPICAL 1969 GENERATOR DRIVER 5094 SIMPLE CYCLE DISTILLATE OIL ---
N.A. MS 5001PA ILLINOIS USA CONTINENTAL 1969 GENERATOR DRIVER 5094 SIMPLE CYCLE DISTILLATE OIL ---
N.A. MS 5001PA N.A. USA CONTINENTAL 1969 GENERATOR DRIVER 5094 SIMPLE CYCLE DISTILLATE OIL ---
N.A. MS 5001PA GENESEE MICHIGAN USA CONTINENTAL 1970 GENERATOR DRIVER 5094 SIMPLE CYCLE DISTILLATE OIL ---
N.A. MS 5001PA GENESEE MICHIGAN USA CONTINENTAL 1970 GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL FUEL ---
N.A. MS 5001PA GENESEE MICHIGAN USA CONTINENTAL 1970 GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL FUEL ---
N.A. MS 5001PA DAYTON USA CONTINENTAL 1970 GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL FUEL ---
N.A. MS 5001PA DAYTON USA CONTINENTAL 1970 GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL FUEL ---
N.A. MS 5001PA CHICAGO USA CONTINENTAL 1969 GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL FUEL ---
N.A. MS 5001PA CHICAGO USA CONTINENTAL 1969 GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL FUEL ---
N.A. MS 5001PA CHICAGO USA CONTINENTAL 1969 GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL FUEL ---
1705618 MS 5001PA BOHAY BAY CHINA 2006 -17 35 GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL FUEL
1705619 MS 5001PA BOHAY BAY CHINA 2006 -17 35 GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL FUEL
1705626 MS 5001PA SOUTH KOREA CONTINENTAL 2005 -12 40 GENERATOR DRIVER SIMPLE CYCLE NATURAL GAS NATURAL GAS --- STEAM INJECTION
1705627 MS 5001PA GIALO STATION LIBYA DESERTIC 2006 0 50 GENERATOR DRIVER SIMPLE CYCLE NATURAL GAS / DISTILLATE OIL NATURAL GAS DISTILLATE OIL SAC
1705628 MS 5001PA ELEME NIGERIA DESERTIC 2006 25 45 GENERATOR DRIVER 5094 SIMPLE CYCLE
1705629 MS 5001PA ELEME NIGERIA DESERTIC 2006 25 45 GENERATOR DRIVER 5094 SIMPLE CYCLE
1705630 MS 5001PA COVE POINT USA CONTINENTAL 2006 -18 38 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS ---
1705631 MS 5001PA COVE POINT USA CONTINENTAL 2006 -18 38 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS ---
1705632 MS 5001PA VIRGIN ISLANDS USA CONTINENTAL 2006 15.5 35 GENERATOR DRIVER 5094 SIMPLE CYCLE DUAL GAS
1705633 MS 5001PA LUMUT BRUNEI CONTINENTAL 2006 19 37.5 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS ---
1705634 MS 5001PA OBIAFU OBRIKOM NIGERIA GENERATOR DRIVER 5094 SIMPLE CYCLE
1705636 MS 5001PA BAL HAF YEMEN 2006 15 43 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS ---
1705637 MS 5001PA BAL HAF YEMEN 2006 15 43 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS ---
1705638 MS 5001PA BAL HAF YEMEN 2006 15 43 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS ---
1705639 MS 5001PA BAL HAF YEMEN 2006 15 43 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS ---
1705641 MS 5001PA VANKOR RUSSIA GENERATOR DRIVER
1705642 MS 5001PA VANKOR RUSSIA GENERATOR DRIVER

GE Oil & Gas


Pag. E.7.1/3
GE Proprietary & Confidential Information
Shipped Env. Temp. Env. Temp. Speed Secondary Combustion
Equipment Job Model Site Country (Nation) Climatic Area Use Cycle Fuel Primary Fuel
Date min. (°C) max (°C) [Rpm] Fuel System

1705643 MS 5001PA VANKOR RUSSIA GENERATOR DRIVER


1705644 MS 5001PA VANKOR RUSSIA GENERATOR DRIVER
1705645 MS 5001PA BINTULU MALAYSIA TROPICAL 2007 19.5 36.5 GENERATOR DRIVER
TROPICAL /
1705652 MS 5001PA MELAKA MALAYSIA 2008 19.5 36.5 GENERATOR DRIVER 5190 SIMPLE CYCLE NATURAL GAS NATURAL GAS STEAM INJECTION
MARINE
1705653 MS 5001PA EL FEEL LIBYA DESERTIC 2007 -5 50 GENERATOR DRIVER SIMPLE CYCLE DUAL FUEL ---
1705654 MS 5001PA EL FEEL LIBYA DESERTIC 2007 -5 50 GENERATOR DRIVER SIMPLE CYCLE DUAL FUEL ---
1705655 MS 5001PA EL FEEL LIBYA DESERTIC 2007 -5 50 GENERATOR DRIVER SIMPLE CYCLE DUAL FUEL ---
1705656 MS 5001PA EL FEEL LIBYA DESERTIC 2007 -5 50 GENERATOR DRIVER SIMPLE CYCLE DUAL FUEL ---
1705657 MS 5001PA DAHARKI PAKISTAN TROPICAL 2008 2 50 GENERATOR DRIVER 5100 SIMPLE CYCLE DUAL GAS NATURAL GAS --- ---
1705663 MS 5001PA MULTAN PAKISTAN TROPICAL 2008 0 49 GENERATOR DRIVER COMBINED CYCLE NATURAL GAS NATURAL GAS --- ---
1705664 MS 5001PA MULTAN PAKISTAN TROPICAL 2008 0 49 GENERATOR DRIVER COMBINED CYCLE NATURAL GAS NATURAL GAS --- ---
1705665 MS 5001PA CONGO TROPICAL 2008 15 34 GENERATOR DRIVER SIMPLE CYCLE NATURAL GAS NATURAL GAS --- ---
1705670 MS 5001PA AL-JALAMID SAUDI ARABIA DESERTIC 2008 -8 44 GENERATOR DRIVER SIMPLE CYCLE DISTILLATE OIL --- --- WATER INJECTION
1705671 MS 5001PA AL-JALAMID SAUDI ARABIA DESERTIC 2008 -8 44 GENERATOR DRIVER SIMPLE CYCLE DISTILLATE OIL --- --- WATER INJECTION
1705672 MS 5001PA AL-JALAMID SAUDI ARABIA DESERTIC 2008 -8 44 GENERATOR DRIVER SIMPLE CYCLE DISTILLATE OIL --- --- WATER INJECTION
1705673 MS 5001PA VENEZUELA TROPICAL 2008 13 35 GENERATOR DRIVER 5100 SIMPLE CYCLE DUAL FUEL NATURAL GAS DISTILLATE OIL SAC
1705666 MS 5001PA VANKOR RUSSIA ARCTIC -60 33 GENERATOR DRIVER COMBINED CYCLE NATURAL GAS NATURAL GAS --- SAC
1705667 MS 5001PA VANKOR RUSSIA ARCTIC -60 33 GENERATOR DRIVER COMBINED CYCLE NATURAL GAS NATURAL GAS --- SAC
1705668 MS 5001PA VANKOR RUSSIA ARCTIC -60 33 GENERATOR DRIVER COMBINED CYCLE NATURAL GAS NATURAL GAS --- SAC
1705669 MS 5001PA VANKOR RUSSIA ARCTIC -60 33 GENERATOR DRIVER COMBINED CYCLE NATURAL GAS NATURAL GAS --- SAC
1705676 MS 5001PA SAUDI ARABIA DESERTIC 2008 4 50 GENERATOR DRIVER 5100 SIMPLE CYCLE DISTILLATE OIL --- --- ---
1705677 MS 5001PA SAUDI ARABIA DESERTIC 2008 4 50 GENERATOR DRIVER 5100 SIMPLE CYCLE DISTILLATE OIL --- --- ---
1705678 MS 5001PA SAUDI ARABIA DESERTIC 2008 4 50 GENERATOR DRIVER 5100 SIMPLE CYCLE DISTILLATE OIL --- --- ---
1705679 MS 5001PA SAUDI ARABIA DESERTIC 4 50 GENERATOR DRIVER 5100 SIMPLE CYCLE DISTILLATE OIL --- --- ---
1705680 MS 5001PA SAUDI ARABIA DESERTIC 4 50 GENERATOR DRIVER 5100 SIMPLE CYCLE DISTILLATE OIL --- --- ---
1705681 MS 5001PA SAUDI ARABIA DESERTIC 4 50 GENERATOR DRIVER 5100 SIMPLE CYCLE DISTILLATE OIL --- --- ---
1705682 MS 5001PA CREMONA ITALY CONTINENTAL -15 40 GENERATOR DRIVER SIMPLE CYCLE DUAL GAS NATURAL GAS STEAM INJECTION
1705703 MS 5001PA BAGDAD IRAQ DESERTIC -8 55 GENERATOR DRIVER SIMPLE CYCLE DUAL LIQUID SAC
1705704 MS 5001PA BAGDAD IRAQ DESERTIC -8 55 GENERATOR DRIVER SIMPLE CYCLE DUAL LIQUID SAC
1705693 MS 5001PA SKIKDA ALGERIA DESERTIC 2008 1 47 GENERATOR DRIVER SIMPLE CYCLE NATURAL GAS NATURAL GAS --- SAC
1705694 MS 5001PA SKIKDA ALGERIA DESERTIC 2008 1 47 GENERATOR DRIVER SIMPLE CYCLE NATURAL GAS NATURAL GAS --- SAC
1705695 MS 5001PA SKIKDA ALGERIA DESERTIC 2009 1 47 GENERATOR DRIVER SIMPLE CYCLE NATURAL GAS NATURAL GAS --- SAC
1705696 MS 5001PA SKIKDA ALGERIA DESERTIC 2009 1 47 GENERATOR DRIVER SIMPLE CYCLE NATURAL GAS NATURAL GAS --- SAC
1705697 MS 5001PA SKIKDA ALGERIA DESERTIC 2009 1 47 GENERATOR DRIVER SIMPLE CYCLE NATURAL GAS NATURAL GAS --- SAC
1705708 MS 5001PA BASRAH IRAQ DESERTIC 0 50 GENERATOR DRIVER 5100 SIMPLE CYCLE NATURAL GAS NATURAL GAS --- SAC
1705709 MS 5001PA BASRAH IRAQ DESERTIC 0 50 GENERATOR DRIVER 5100 SIMPLE CYCLE NATURAL GAS NATURAL GAS --- SAC
1705710 MS 5001PA DONGGI SENORO LNG PLANT INDONESIA TROPICAL 20 33 GENERATOR DRIVER SIMPLE CYCLE NATURAL GAS NATURAL GAS --- LEAN HEAD END
1705711 MS 5001PA DONGGI SENORO LNG PLANT INDONESIA TROPICAL 20 33 GENERATOR DRIVER SIMPLE CYCLE NATURAL GAS NATURAL GAS --- LEAN HEAD END
1705712 MS 5001PA DONGGI SENORO LNG PLANT INDONESIA TROPICAL 20 33 GENERATOR DRIVER SIMPLE CYCLE NATURAL GAS NATURAL GAS --- LEAN HEAD END
1705713 MS 5001PA ALRAR ALGERIA DESERTIC 2009 -5 50 GENERATOR DRIVER SIMPLE CYCLE NATURAL GAS NATURAL GAS --- DRY LOW NOX
1705714 MS 5001PA ALRAR ALGERIA DESERTIC 2009 -5 50 GENERATOR DRIVER SIMPLE CYCLE NATURAL GAS NATURAL GAS --- DRY LOW NOX
1705715 MS 5001PA ALRAR ALGERIA DESERTIC 2009 -5 50 GENERATOR DRIVER SIMPLE CYCLE NATURAL GAS NATURAL GAS --- DRY LOW NOX
1705716 MS 5001PA BASRAH IRAQ DESERTIC -5 50 GENERATOR DRIVER SIMPLE CYCLE NATURAL GAS NATURAL GAS --- SAC
DESERTIC /
1705718 MS 5001PA ARZEW ALGERIA 2010 8 35 GENERATOR DRIVER SIMPLE CYCLE NATURAL GAS NATURAL GAS --- DRY LOW NOX
MARINE
1705719 MS 5001PA NIGERIA TROPICAL 20 40 GENERATOR DRIVER 5100 SIMPLE CYCLE DUAL FUEL NATURAL GAS DISTILLATE OIL SAC
1705720 MS 5001PA NIGERIA TROPICAL 20 40 GENERATOR DRIVER 5100 SIMPLE CYCLE DUAL FUEL NATURAL GAS DISTILLATE OIL SAC
1705721 MS 5001PA NIGERIA TROPICAL GENERATOR DRIVER 5100 SIMPLE CYCLE
1705722 MS 5001PA IRAQ DESERTIC -5 50 GENERATOR DRIVER SIMPLE CYCLE NATURAL GAS NATURAL GAS --- SAC
1705727 MS 5001PA NIGERIA TROPICAL GENERATOR DRIVER 5100 SIMPLE CYCLE
1705728 MS 5001PA NIGERIA TROPICAL GENERATOR DRIVER 5100 SIMPLE CYCLE
1705729 MS 5001PA NIGERIA TROPICAL GENERATOR DRIVER 5100 SIMPLE CYCLE
1705730 MS 5001PA NIGERIA TROPICAL GENERATOR DRIVER 5100 SIMPLE CYCLE
1705731 MS 5001PA NIGERIA TROPICAL GENERATOR DRIVER 5100 SIMPLE CYCLE
1705732 MS 5001PA AYDIN SAUDI ARABIA DESERTIC -2 53 GENERATOR DRIVER 5100 SIMPLE CYCLE DISTILLATE OIL SAC
1705740 MS 5001PA BIR SEBA ALGERIA DESERTIC -5 45 GENERATOR DRIVER 5100 SIMPLE CYCLE DUAL FUEL SAC
1705741 MS 5001PA BIR SEBA ALGERIA DESERTIC -5 45 GENERATOR DRIVER 5100 SIMPLE CYCLE DUAL FUEL SAC
1705755 MS 5001PA BINTULU MALAYSIA INDUSTRIAL / MARINE / TROPIC 19.0 36.0 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS --- DRY LOW NOX
1705756 MS 5001PA BINTULU MALAYSIA INDUSTRIAL / MARINE / TROPIC 19.0 36.0 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS --- DRY LOW NOX
1705757 MS 5001PA BINTULU MALAYSIA INDUSTRIAL / MARINE / TROPIC 19.0 36.0 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS --- DRY LOW NOX
1705758 MS 5001PA BINTULU MALAYSIA INDUSTRIAL / MARINE / TROPIC 19.0 36.0 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS --- DRY LOW NOX
1705759 MS 5001PA BINTULU MALAYSIA INDUSTRIAL / MARINE / TROPIC 19.0 36.0 GENERATOR DRIVER 5094 SIMPLE CYCLE NATURAL GAS NATURAL GAS --- DRY LOW NOX

GE Oil & Gas


Pag. E.7.1/4
GE Proprietary & Confidential Information
GE Oil & Gas

Box & Packing

GE Oil & Gas


Pag. E.8
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. E.8.1/1
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. E.8.1/2
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. E.8.1/3
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. E.8.1/4
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. E.8.1/5
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. E.8.1/6
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. E.8.1/7
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. E.8.1/8
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. E.8.1/9
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. E.8.1/10
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. E.8.1/11
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. E.8.1/12
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. E.8.1/13
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. E.8.1/14
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. E.8.1/15
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. E.8.1/16
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. E.8.1/17
GE Proprietary & Confidential Information
GE Oil & Gas

CHAPTER F

Instrumentation Technical Spec

GE Oil & Gas


Pag. F
GE Proprietary & Confidential Information
GE Oil & Gas

GT Instrument Specification

GE Oil & Gas


Pag. F.1
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. F.1.1/1
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. F.1.1/2
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. F.1.1/3
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. F.1.1/4
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. F.1.1/5
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. F.1.1/6
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. F.1.1/7
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. F.1.1/8
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. F.1.1/9
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. F.1.1/10
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. F.1.1/11
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. F.1.1/12
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. F.1.1/13
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. F.1.1/14
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. F.1.1/15
GE Proprietary & Confidential Information
GE Oil & Gas

Aux Instrument Specification

GE Oil & Gas


Pag. F.2
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. F.2.1/1
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. F.2.1/2
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. F.2.1/3
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. F.2.1/4
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. F.2.1/5
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. F.2.1/6
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. F.2.1/7
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. F.2.1/8
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. F.2.1/9
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. F.2.1/10
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. F.2.1/11
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. F.2.1/12
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. F.2.1/13
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. F.2.1/14
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. F.2.1/15
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. F.2.1/16
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. F.2.1/17
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. F.2.1/18
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. F.2.1/19
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. F.2.1/20
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. F.2.1/21
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. F.2.1/22
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. F.2.1/23
GE Proprietary & Confidential Information
GE Oil & Gas

CHAPTER G

Auxiliaries

GE Oil & Gas


Pag. G
GE Proprietary & Confidential Information
GE Oil & Gas

Auxiliaries Data Sheets

GE Oil & Gas


Pag. G.1
GE Proprietary & Confidential Information
g Oil & Gas Nuovo Pignone
2 Technical section.

2.1 Scope of supply.

The items included in scope of supply are identified by symbol “☒” while items excluded are identified
by symbol “□”.
2.1.1 ☒ Tube bundle.
2.1.1.1 ☒ Internals cleaning: Lube oil flushing.
2.1.1.2 ☒ Internals preservation: VpCI.
2.1.1.3 Coatings.
2.1.1.3.1 ☐ Headers: Painting.
2.1.1.3.2 ☐ Unfinned zones of finned tubes (for extruded type only): Metallizing.
2.1.1.3.3 ☒ Bundle frame: Hot dip galvanizing.
2.1.2 ☒ Structural steel.
2.1.2.1 ☒ Supporting structure.
2.1.2.1.1 ☐ Module supporting beams (for pipe rack mounted units only).
2.1.2.1.2 ☐ Piping supports.
2.1.2.1.3 ☐ Clips for fireproofing (also if applied by others).
2.1.2.1.4 ☒ Foundation bolt (for grade mounted units only).
2.1.2.1.5 ☒ Coatings: Hot dip galvanizing.
2.1.2.2 ☒ Plenum chamber and machinery mount. Coatings: Hot dip galvanizing.
2.1.2.3 ☒ Platforms, walkways, ladders and stairs.
2.1.2.3.1 ☒ Headers walkways: Both sides.
2.1.2.3.2 ☐ Side interconnecting walkways.
2.1.2.3.3 ☐ Motors walkways (for pipe rack mounted units only).
2.1.2.3.4 ☐ Fans walkways (for induced draught units only).
2.1.2.3.5 ☐ Floor (for winterized units only).
2.1.2.3.6 ☐ Finned tubes platform.
2.1.2.3.7 ☒ Access: Ladders.
2.1.2.3.8 ☒ Flooring: Hot dip galvanized grating.
2.1.2.3.9 ☒ Coatings: Hot dip galvanizing.
2.1.2.4 ☒ Guards.
2.1.2.4.1 ☒ Fan: Hot dip galvanized.
2.1.2.4.2 ☒ Speed reducer/drives: Hot dip galvanized.
2.1.2.4.3 ☐ Headers: Hot dip galvanized.
2.1.2.4.4 ☐ Finned tubes: Hot dip galvanized.
2.1.2.5 ☐ Screens.
2.1.2.5.1 ☐ Insect/lint: Stainless steel wire cloth.
2.1.2.5.2 ☐ Hail: Stainless steel wire cloth.
2.1.2.6 ☐ Wind skirts, side walls and roofs (for winterized units only): Hot dip galvanized.
2.1.2.7 ☒ Bolting and hardware: Hot dip galvanized.
2.1.3 ☒ Drivetrain.
2.1.3.1 ☒ Electric motor.
2.1.3.1.1 ☒ Space heaters.
2.1.3.1.2 ☐ Cable gland.
2.1.3.2 ☒ Speed reducer: V-belts
2.1.3.3 ☐ Coupling joint (for gear type speed reducer or induced draught direct coupled fans only).
2.1.3.4 ☒ Shaft.
2.1.3.4.1 ☐ Antirotation device.
2.1.3.5 ☒ Lubrication.
2.1.3.5.1 ☒ Lines: Separate.
2.1.3.5.2 ☐ Pump: Manual.
2.1.3.6 ☒ Axial flow fan.

GE PROPRIETARY INFORMATION Date: 17 December 2013 - Sheet:


Pag. 2/5
G.1.1/1
GE Oil & Gas
GE Proprietary & Confidential Information
g Oil & Gas Nuovo Pignone
2.1.4 ☒ Instruments and electric/pneumatic system.
2.1.4.1 ☒ Vibration switch.
2.1.4.2 ☐ Vibration sensor.
2.1.4.3 ☐ I/P converter (for AV fans and/or automatic louvers).
2.1.4.4 ☐ Air temperature transmitter (for winterized units only).
2.1.4.5 ☐ Fluid temperature transmitter.
2.1.4.6 ☐ Level transmitter (for water tank only).
2.1.4.7 ☐ Level switch (for water tank only).
2.1.4.8 ☐ Level glass indicator (for water tank only).
2.1.4.9 ☒ Instruments wiring system (cables, cable trays and junction box).
2.1.4.10 ☐ Pneumatic system (tubing, fittings and air manifold).
2.1.5 ☒ Others.
2.1.5.1 ☐ Louvers.
2.1.5.1.1 ☐ Pneumatic actuators.
2.1.5.2 ☐ Heaters (for winterized units only): Scegliere una opzione.
2.1.5.3 ☐ Variable speed drive.
2.1.5.4 ☐ Expansion tank and connection line (for water cooler only).
2.1.5.5 ☐ Distribution manifolds.
2.1.5.6 ☐ Pipe spools.
2.1.5.7 ☐ Vent/drain valves.
2.1.5.8 ☐ Headers thermal insulation.
2.1.5.9 ☒ Special tools.
2.1.5.9.1 ☒ Motor hoisting device.
2.1.5.9.2 ☒ Belt tensioner.
2.1.5.9.3 ☒ Fan blades inclinometer.
2.1.5.9.4 ☒ Finned tubes comb.
2.1.6 ☒ Spare parts.
2.1.6.1 ☒ Commissioning & start up (included in base price).
2.1.6.1.1 ☒ 1% plugs (for box headers only).
2.1.6.1.2 ☒ 5% plug gaskets (for box headers only) or 1 of each different dimension cover gasket (for
cover plate headers only).
2.1.6.1.3 ☒ 10% of flange bolting of each different dimension.
2.1.6.2 ☐ Two years of operations (quoted as option).
2.1.6.2.1 ☐ 5% plugs (for box headers only).
2.1.6.2.2 ☐ 20% plug gaskets (for box headers only) or 2 of each different dimension cover gasket (for
cover plate headers only).
2.1.6.2.3 ☐ 20% of each different dimension flange bolting.
2.1.6.2.4 ☐ 25% of each different dimension motor bearing set.
2.1.6.2.5 ☐ 50% of each different dimension motor seal set.
2.1.6.2.6 ☐ 100% belts (for belted speed reducer).
2.1.6.2.7 ☐ 1 of each different dimension coupling joint (for gear speed reducer).
2.1.6.2.8 ☐ 25% of each different dimension shaft bearing set.
2.1.6.2.9 ☐ 50% of each different dimension shaft seal set.
2.1.6.2.10 ☐ 10% of each different dimension fan blade.
2.1.6.2.11 ☐ 1 of each different dimension fan rotating joint (for AV fans only).
2.1.7 ☒ Supplementary tests. Extension: One bay per each different item.
2.1.7.1 ☒ Trial fit of: complete assembled machine excluding valves, instruments, and
electrical/pneumatic system.
2.1.7.2 ☒ Running of drivetrain.
2.1.7.3 ☐ Functional of louvers and pneumatic actuators if present.
2.1.7.4 ☒ Absorbed power.
2.1.7.5 ☒ Air flow.
2.1.7.6 ☒ Vibration.

GE PROPRIETARY INFORMATION Date: 17 December 2013 - Sheet:


Pag. 3/5
G.1.1/2
GE Oil & Gas
GE Proprietary & Confidential Information
g Oil & Gas Nuovo Pignone
2.1.7.7 ☒ Noise.
2.1.8 ☒ Packing. Sea shipping standard package as per ITN54750.00.
2.1.8.1 ☐ Machine will be shipped in loose parts except tube bundle that will be shipped fully
assembled and tested.
2.1.8.1.1 ☐ Tube bundle: Thermo shrinking.
2.1.8.1.2 ☐ Structural steel and louvers: Wooden crate.
2.1.8.1.3 ☐ Drivetrain, instruments and electric/pneumatic system, others, spare parts and
miscellaneous: Wooden box.
2.1.8.2 ☒ Machine will be shipped partially modularized according to lifting and transport limitations.
Walways, ladders, lower support structure and miscellaneous will be shipped loose.
2.1.8.2.1 ☒ Module: Thermo shrinking.
2.1.8.2.2 ☒ Structural steel: Wooden crate.
2.1.8.2.3 ☒ Drivetrain, instruments and electric/pneumatic system, others, spare parts and
miscellaneous: Wooden box.
2.1.8.3 ☐ Machine will be shipped fully modularized except miscellaneous that will be shipped loose.
2.1.8.3.1 ☐ Complete module: Thermo shrinking.
2.1.8.3.2 ☐ Spare parts and miscellaneous: Wooden box.

Remarks: All items not clearly included in scope of supply shall be considered out of scope
2.2 Applicable documents.

Our quotation is developed strictly in accordance to applicable document list attached.


2.3 Deviation/clarification list.

Our quotation is developed strictly in accordance to applicable deviation/clarification list attached.


2.4 VDR/document list.

Documents that we will submit along job execution shall be according to our standard vendor document
register attached.
2.5 Technical attachments.

 Data sheets
 Annex I: GE-NP List of Received Documentation.
 Annex II: GE Technical Notes & Deviation List.
 VDR/document list

GE PROPRIETARY INFORMATION Date: 17 December 2013 - Sheet:


Pag. 4/5
G.1.1/3
GE Oil & Gas
GE Proprietary & Confidential Information
g
GE Oil & Gas
Nuovo Pignone S.p.A. ACHE Specification Sheet
1 Customer NP x ICA FLUOR x PETROLEOS MEXICANOS Proposal N. 13/UP/1263/V/E
2 Plant PEMEX PEP - LAKACH 2XGTG 20 MW Purchase Order
3 Unit Job Proposal
4 Service Gas Turbine MS5001PA Lube Oil Air cooler TAG No. HXL-2
5 Draft type INDUCED No. of units 2 Bays/unit 1 Bundles/bay 1
6 Structural Mount. At Grade Bundles in parallel / series 1 / 0 Bays in parallel / series 1 / 0
7 Bundle size m 3.14 x 11.34 Bay size m 3.21 x 11.34 Unit plot area m 3.51 x 11.34
8 Bare Surface per unit 90.78 m² Finned Surface per unit 3143.00 m²
9 Heat exchanged 0.581 MW MTD 17.80 K
10 Transfer rate bare service 359.57 W/m²K Transfer rate finned 10.39 W/m²K
11 PERFORMANCE DATA - TUBESIDE
12 Fluid name / Fluid condition OIL ISOVG32 Latent heat kJ/kg
13 Total fluid entering kg/s 14.891 Dew point °C
14 IN OUT Bubble point °C
15 Vapor kg/s Pour point °C
16 Liquid kg/s 14.891 14.891 Fouling In/Out m²K/W 0.000172 / 0.000352
17 Steam kg/s Inlet pressure bar(a) 3.00
18 Water kg/s Pressure drop calc./all. bar 1.55 / 3.00
19 Non condensables kg/s PERFORMANCE DATA - AIR SIDE
20 Temperature °C 69.4 50.0 Temperature In/Out °C 38.00 / 41.76
21 MW vapor kg/kmol Min. design ambient °C 0.0
22 MW non condensables kg/kmol Altitude m 0
23 Density (L/V) kg/m³ 836.600 / 849.310 / Air flow rate per item kg/s 101.34
24 Specific heat (L/V) kJ/kgK 2.046 / 1.974 / Actual air flow rate/fan m³/s 51.35
25 Thermal conductivity (L/V) W/mK 0.123 / 0.125 / Static pressure Pa 150.0
26 Viscosity (L/V) cP 8.771 / 17.407 / Power / unit kW 30.20
27 CONSTRUCTION EACH BUNDLE MATERIALS
28 Design pressure bar(g) 12.00 Tube type High-Fin Tube A-213 Tp 316L M.W.
29 Test pressure bar(g) CODE No. No 160 Fin Aluminium
30 Design temperature °C 100 Tube OD / THK mm 25.40 1.651 M.W. Header A-240 Gr. 316L
31 MDMT °C Total length mm 10,900 Plug A-182 F316L
32 Code ASME VIII DIV.1 Stamp Yes Pitch mm 63.5 Gasket Stainless steel
33 Header type Plug Box Fin type Extruded Nozzle A-312 Tp 316L Smls.
34 Passes 2 Rows 4 No. Fins No/m 433.0 Side frame Carbon Steel Hdg
35 Slope None mm/m 0 Fin O.D. / THK mm 57.15 0.35 Plenum Carbon Steel Hdg
36 Corrosion allowance mm 0 Connections No Size Rating Facing Structure Carbon Steel Hdg
37 Tube joint Seal Welded Nozzles in 1 6 150 RF Ladder Carbon Steel Hdg
38 Plug type Shoulder Nozzles out 1 6 150 RF Walkway Carbon Steel Hdg
39 Split No Vent 1 3/4 6000 Vent / Drain A-182 F304L
40 Split below row on Fixed on Float Drain 1 3/4 6000 Bolts, Nuts ASTM
41 MECHANICAL EQUIPMENT
42 Fans / bay 3 Pitch AV 0% Drivers / bay 3 RPM TBD Speed reducers / bay 3
43 Diameter m 2.438 fan rpm TBD Type DOL poles 4 Type V-BELT
44 Fan power kW 15.10 Power kW 22 Voltage V 440 Ratio TBD
45 No. of blades 4 min. Cycle Hz 60 phase 3 Service factor API661
46 Blades / Hub material Aluminum / GRP Enclosure IP55 MFR TBD
47 MFR TBD MFR TBD Vibraswitch Mechanic
48 CONTROLS WEIGHTS & VOLUMES
49 Louvers No Control action on air failure Bundle / unit weight kg
50 Heating coil No Fan pitch Internal bundle volume dm3 790(x bundle); 790(x unit)

51 Recirculation No Louvers Unit shipping volume m3


52 TUBES/PASS LAYOUT EACH BUNDLE
53 Pass N° 1 2
54 Tubes/pass 80 80
55 Tube finned Length = 10800mm
56 Provided 3x50% fan arrangement with two fans running and one in stand-by
57 Provided internal turbulence promoters wire mesh type Cal Gavin Type 4 or equivalent
58 SPL max: 85 dB(A) @ 1 m at side
59
60
Job Proposal
Item
HXL-2

Dwg
0 Issue SFC GP GP 21/11/2013 Lingua - Language Pagina - Sheet
rev Description Prepared Checked Approved Date A 1 / 1
Il presente documento è di proprietà NUOVO PIGNONE. A termine di legge ogni diritto è riservato. Sostituisce il / Replaces
This document is the property of NUOVO PIGNONE. All rights are reserved according to law Sostituito da / Replaced by ACES 86z8, release June 2013

GE Oil & Gas


Pag. G.1.1/4
GE Proprietary & Confidential Information
Annex I: GE-NP List of Received Documentation.
Filename Title Rev Date Notes
NRF-134-PEMEX-2012_EN.docx AIR COOLED HEAT EXCHANGERS 0 July 14, 2012
*********************************-- END -- ********************************

GE Oil & Gas


Pag. G.1.1/5
GE Proprietary & Confidential Information
Annex II: GE Technical Notes & Deviation List.
Ref. Spec.
Line Ref. Spec. File_Name Ref. Spec. Title Contractual request GE's Deviation/Clarification Client's Reply
Par.

Clarification: Only documents, specifications, codes and standards


listed in attached GE_NP_Applicable_Document_List and not declared
1 n.a. general n.a. Project documentation as not applicable along this clarification/deviation list, will be applied.
Reference documentation listed and or referenced in applicable
documents will be NOT taken into consideration.

part 2
Lubrication, Shaft-sealing and Special- 4.5.1.2 Unless otherwise specified, coolers shall be shell-
2 specs\api 614.pdf Oil-control Systems and Auxiliaries purpose oil and-tube type and shall be in accordance with the Clarification: Coolers are of the aircooler type.
MAY 2008 systems requirements of 4.5.1.4.

part 2
4.5.1.17 If specified, the coolers shall be fabricated with
Lubrication, Shaft-sealing and Special-
flanged vent and drain nozzles. Screwed and sealwelded
3 specs\api 614.pdf Oil-control Systems and Auxiliaries purpose oil Clarification: Provided NPT V&D connections
or socket-welded pipe and flange additions to coolers after
MAY 2008 systems
cooler certification are not acceptable.
part 2 4.5.4.4 If specified, and in addition to the requirements of
Lubrication, Shaft-sealing and Special- the general cooler section, air coolers shall be in
4 specs\api 614.pdf Oil-control Systems and Auxiliaries purpose oil accordance with the following provisions a) to g). Exception: provided 3x50% fan redundance in lieu of 2 x 100%
MAY 2008 systems a) The cooler shall be provided with two fans. Each fan shall
be capable of 100 % of the duty requirement.
part 2 4.5.4.4 If specified, and in addition to the requirements of
Lubrication, Shaft-sealing and Special- the general cooler section, air coolers shall be in
Exception: Mechanical vibration switch provided in lieu of the electronic
5 specs\api 614.pdf Oil-control Systems and Auxiliaries purpose oil accordance with the following provisions a) to g).
type.
MAY 2008 systems e) Electronic vibration switches shall be provided for each
fan and shall alarm on high vibration.
4.5.4.4 If specified, and in addition to the requirements of
part 2
the general cooler section, air coolers shall be in
Lubrication, Shaft-sealing and Special-
accordance with the following provisions a) to g). Clarification: Turbulators Cal Gavinwire mesh type 4 provided inside
6 specs\api 614.pdf Oil-control Systems and Auxiliaries purpose oil
g) Turbulence promoters may only be used with purchaser tubes.
MAY 2008 systems
approval. When supplied, turbulence promoters shall be
austenitic stainless steel.

GE Proprietary Information
Technical Notes and Deviation List
- Page 1 of 1 -
GE Oil & Gas
Pag. G.1.1/6
GE Proprietary & Confidential Information
Standard Vendor Document Register - Main documents
Items N°: 1
Extimated Issue Date
Pos. Title Description NOTE WEEKS AFTER ORDER
LIST OF CONTRACTUAL DOCUMENTS REGARDING THE AIR COOLER. IN THIS
DOCUMENT ARE INCLUDED THE FOLLOWING GENERAL INFORMATIONS: 1)
1 Vendor Document Register Required, planned and effective issued date; 2) Identification drawing 2
(number and description); 3) Number of trasmittal; 4) Number and type of
copy (electronic or hard); 5) Issue typology (approval, information or final).
TECHNICAL DRAWING WITH AIR COOLER GENERAL INFORMATION. IN THIS
DRAWING ARE INCLUDED THE FOLLOWING GENERAL INFORMATION: 1)
General layout; 2) Foundation loads table; 3) Load (wind, sismic, nozzles,
2 General Arrangement 5
etc); 4) Mechanical battery limits; 5) Drive train layout; 6) Material
identification; 7) Process data; 8) Electrical data; 9) Lifting layout (if shipped
in modularized condition).
TECHNICAL DOCUMENT. IN THIS DOCUMENT ARE INCLUDED THE
FOLLOWING GENERAL INFORMATION: 1) Process Data; 2) Air Side Data; 3)
3 Air-Cooler Data Sheet 3
Drive Train Data; 4) Structural Data; 5) Design Condition; 6) Mechanical Lay
Out; 7) Fluid Process Information; 8) Additional Technical Requirements.

CROSS SECTIONAL DRAWING OF TUBE BUNDLE. IN THIS DOCUMENT ARE


INCLUDED THE FOLLOWING GENERAL INFORMATIONS: 1) Outline drawing;
2) Tubes and nozzle connections; 3) Process data; 4) List of material with
4 Tube Bundles 7
characteristic and additional requirements; 5) Information for construction
and assembling; 6) Design pressure and temperature; 7) Hydrostatic
pressure value; 8) Weight and volume of bundle; 9) Applicable code.
5 List of Materials MATERIAL LIST OF TUBE BUNDLE. Included in Pos.4 7
TECHNICAL DOCUMENT. IN THIS DOCUMENT ARE INCLUDED THE
FOLLOWING GENERAL INFORMATIONS: 1) Construction step of the
6 Tube Bundle Quality Control Plan 8
component; 2) Check required for each step; 3) Acceptance criteria and
procedure; 4) Attendance data and notification details.
TECHNICAL DOCUMENT. IN THIS DOCUMENT ARE INCLUDED GENERAL
INFORMATION FOR ASSEMBLING & MAINTENANCE AND FOLLOWING
DRAWINGS: 1) General Arrangement; 2) Steel Structure Details Drawings; 3)
7 Installation Manual AT DELIVERY
Steel Structure Assembly Drawings; 4) Tube Bundle; 5) Bundle Frame; 6)
Fans Specification; 7) Motor Specification; 8) Belt Specification; 9)
Vibration/Sensor Switch Specification; 10) Manual Equipment Device.

Issued 04/12/2013 - Sheet 1/1


GE Oil & Gas
Pag. G.1.1/7
GE Proprietary & Confidential Information
GE Oil & Gas

CHAPTER H

Drawings

GE Oil & Gas


Pag. H
GE Proprietary & Confidential Information
GE Oil & Gas

P&ID Diagrams

GE Oil & Gas


Pag. H.1
GE Proprietary & Confidential Information
ly
on
n
io
at
orm
nf
ri
Fo

GE Oil & Gas


Pag. H.1.1/1
GE Proprietary & Confidential Information
ly
on
n
io
at
orm
nf
ri
Fo

GE Oil & Gas


Pag. H.1.1/2
GE Proprietary & Confidential Information
ly
on
n
io
at
orm
nf
ri
Fo

GE Oil & Gas


Pag. H.1.1/3
GE Proprietary & Confidential Information
ly
on
n
io
at
orm
nf
ri
Fo

GE Oil & Gas


Pag. H.1.1/4
GE Proprietary & Confidential Information
ly
on
n
io
at
orm
nf
ri
Fo

GE Oil & Gas


Pag. H.1.1/5
GE Proprietary & Confidential Information
ly
on
n
io
at
orm
nf
ri
Fo

GE Oil & Gas


Pag. H.1.1/6
GE Proprietary & Confidential Information
ly
on
n
io
at
orm
nf
ri
Fo

GE Oil & Gas


Pag. H.1.1/7
GE Proprietary & Confidential Information
ly
on
n
io
at
orm
nf
ri
Fo

GE Oil & Gas


Pag. H.1.1/8
GE Proprietary & Confidential Information
ly
on
n
io
at
orm
nf
ri
Fo

GE Oil & Gas


Pag. H.1.1/9
GE Proprietary & Confidential Information
ly
on
n
io
at
orm
nf
ri
Fo

GE Oil & Gas


Pag. H.1.1/10
GE Proprietary & Confidential Information
ly
on
n
io
at
orm
nf
ri
Fo

GE Oil & Gas


Pag. H.1.1/11
GE Proprietary & Confidential Information
ly
on
n
io
at
orm
nf
ri
Fo

GE Oil & Gas


Pag. H.1.1/12
GE Proprietary & Confidential Information
ly
on
n
io
at
orm
nf
ri
Fo

GE Oil & Gas


Pag. H.1.1/13
GE Proprietary & Confidential Information
ly
on
n
io
at
orm
nf
ri
Fo

GE Oil & Gas


Pag. H.1.1/14
GE Proprietary & Confidential Information
ly
on
n
io
at
orm
nf
ri
Fo

GE Oil & Gas


Pag. H.1.1/15
GE Proprietary & Confidential Information
ly
on
n
io
at
orm
nf
ri
Fo

GE Oil & Gas


Pag. H.1.1/16
GE Proprietary & Confidential Information
ly
on
n
io
at
orm
nf
ri
Fo

GE Oil & Gas


Pag. H.1.1/17
GE Proprietary & Confidential Information
ly
on
n
io
at
orm
nf
ri
Fo

GE Oil & Gas


Pag. H.1.1/18
GE Proprietary & Confidential Information
ly
on
n
io
at
orm
nf
ri
Fo

GE Oil & Gas


Pag. H.1.1/19
GE Proprietary & Confidential Information
ly
on
n
io
at
orm
nf
ri
Fo

GE Oil & Gas


Pag. H.1.1/20
GE Proprietary & Confidential Information
ly
on
n
io
at
orm
nf
ri
Fo

GE Oil & Gas


Pag. H.1.1/21
GE Proprietary & Confidential Information
GE Oil & Gas

Electrical System Drawings

GE Oil & Gas


Pag. H.2
GE Proprietary & Confidential Information
Electronically approved draw. GE NuovoPignone Internal DT-'N'
Bianchi F. Lastrucci T.

GE Oil & Gas


Pag. H.2.1/1
GE Proprietary & Confidential Information
GE Oil & Gas

General Arrangement

GE Oil & Gas


Pag. H.3
GE Proprietary & Confidential Information
ly
on
n
io
at
orm
nf
ri
Fo

GE Oil & Gas


Pag. H.3.1/1
GE Proprietary & Confidential Information
ly
on
n
io
at
orm
nf
ri
Fo

GE Oil & Gas


Pag. H.3.1/2
GE Proprietary & Confidential Information
GE Oil & Gas

CHAPTER I

Comment & Exceptions

GE Oil & Gas


Pag. I
GE Proprietary & Confidential Information
GE Oil & Gas

C&E Introduction

GE Oil & Gas


Pag. I.1
GE Proprietary & Confidential Information
C&E INTRODUCTION

The machines proposed are designed considering the customer specifications over the applicable International standards. In spite of all our efforts to comply with the
General note on specification, there are exceptions to the specification as listed below. Please note that GE O&G complies ONLY to specifications listed below as attached to the Request for
applicable specifications Quotation (RFQ), as amended by exceptions / clarifications listed here and attached with the GE O&G proposal. GE O&G shall not be responsible for the compliance with any
other embedded specifications, even if they are called within the specifications of RFQ.

To avoid repetitive comments on the same item, if a requirement appears in more than one specification, it will be commented (when necessary) only once in one of the
Repetitive comments
specifications.
Scope of supply is as given in GE O&G proposal scope of supply section, with the comments to material requisition. Any additional scope inclusions arising from other
Scope of Supply
specifications are not applicable unless specifically commented and agreed by GE O&G
Mechanical and Electrical Proposed auxiliary systems mechanical and electrical design is based on GE O&G standard practices applicable for the project environmental conditions and country
Packaging installation. For more details refer to techincal section of the proposal.

Documents to be submitted to Customer shall be only those listed in the agreed VDR. The agreed VDR shall include document description, scope and exchange schedule. The
following stand on documentation is applicable unless agreed otherwise.
VDR & Project All the project documents shall be in English only. The measuring units followed shall be (S.I.), [Length: meter, Mass flow: kg/h, Volume flow: m3/h, Pressure: Bar, Power: KW,
Documentation Temperature: °C, Level in percentage 0-100],
As a standard, GE Oil & Gas delivers drawings/documents in electronic format (PDF) through ProjectNet (P-Net), a web-based application with secure access control.
The return of commented drawings/documents to GE O&G is required in electronic copies through ProjectNet.

GE O&G standard Vendor list, or customer Vendor list commented by GE, as provided in the proposal will be followed. Items not covered in customer’s vendor list will be
Vendor list
according to GE O&G vendor list.
Quality Control & Procedures for inspection and tests will be in accordance with GE O&G standard Quality Control Plan. Customer or Third Party withnessed tests will be jointly agreed during Pre
Inspection Inspection Meeting.
Protection and Packing for shipment, selected on the basis of transportation method and storage requirements, will be according to GE O&G standard specification and in
Packing and Protection
compliance with statutory requirements.
Protective coatings shall be as per GEO&G std qualified and tested painting cycles. The painting cycles selected for the project will be consistent with requirements for
Painting
environmental conditions of the installation. Final color as per customer requirement may be provided upon request.
Guarantee & Warranty As per the commercial proposal
The Comments & exceptions provided in the subsequent sections are given with a categorization to ease the technical alignment process.
C&E CATEGORIZATION Legend for the categorization flags:
LEGEND E : E referes to all mandatory deviations.
C: C refers to Clarification type of comments. These are additional Comments given to explain our position clearly.

Page 1 of 1
GE Oil & Gas
Pag. I.1.1/1
GE Proprietary & Confidential Information
GE Oil & Gas

Exceptions to Customer Spec

GE Oil & Gas


Pag. I.2
GE Proprietary & Confidential Information
Pr Rev# General Comments

GE O&G shall comply ONLY to specification here below listed as attached to the Request
for Quotation (RFQ) and as amended by exceptions / clarifications here listed and
0 Embedded Specifications attached to the GE O&G bid. C
GE O&G shall not be responsible for the compliance with any other specification. even if
mentioned into the specifications of RfQ ("embedded specs").

1 Code Stamping for pressure vessels The ASME code stamping for pressure vessels can be provided at extra cost. C

The PMI procedure shall be as per GE O&G internal standard ITN 07070.01. This document
covers the requirements, practices and reporting of the inspection results. The PMI is
2 PMI performed only for the alloy steel material, the level of inspection is stipulated by the GE C
O&G Quality Control Plan document which is unique for the project scope of supply.
Further details related to the inspection shall be made available in the bid / KoM.

External hot surfaces will be maintained at max. 60°C by means of insulation as per GE
O&G standard procedure. Materials will be used for this insulation will be:
- Non hygroscopic
- Fireproof
- Compliant to the HSE requirements in force on installation site
3 Insulation C
- Asbestos free
Piping (and relevant tanks) Insulation and/or provision for Insulation extents will be
according to GE O&G Scope of Supply and shown on the P&I Diagrams attached to the
Technical Proposal.
However, the scope of insulation shall be as per GE O&G scope of supply.

The GE O&G standard practice for Name / Tag plates is attached herewith for the
information to purchaser. The convention shall be followed througout the project
excution phase.
4 Tag Plates C
Name plate

All valves installed on GE O&G machines are part of pre-engineered systems, strictly
related and optimized for the function of the supplied machine.
This items have a dedicated design that have been developed on the basis of well proven
field experience, in order to obtain: high reliability, optimized dimensions, reduced weight
5 Valves - General comment C
and delivery time.
Different and/or additional customer requirements are not applied since they may imply
redesign of the system itself and the concept and could eventually drive loss of reliability
and operability.

Piping within GE O&G supply will be designed as per ASME B31.3 and pipe fittings will be
selected according to applicable ASME and API standards.
Piping layout and design will be according to GE O&G design practice..
Material selection and design will be as per GE O&G standard practice guided by
appropriate API, ASTM and ASME standards.
Pipe supports will be provided according to ASME B31.3 and AISC standard.

As most often the customer specifcation deals with the whole plant level piping, please
6 Piping/bolting line design and specification C
refer the exclusions part of the technical proposal where you can find the piping covered
by GE scope of supply.

The bolts will be hot dip galvanised and selected as per ASME B 1.1 and ASTM standrads.
Typically the MOC: A193 B7, A194 2H shall be used for the bolts. Gaskets will be choosen
according to ISO 3601-3, ASME B16.20. The flanges for process piping will be according to
ASME B16.5 standards. No special coatings (polymer, corrosion resistant paints etc) shall
be provided.

Line and cable numbering shall be as per GE O&G standard.


7 Device, instruments and line numbering C
Instrument numbering will be ISA type, numbers range will be agreed with customer
during early project phase.
P&ID and instrumentation symbols will be according to ISA 5.1 / PIP standard codes,
8 Instrumentation Symbols C
recognized and approved by major companies.

Page 1 of 9
GE Oil & Gas
Pag. I.2.1/1
GE Proprietary & Confidential Information
Valves will be manufactured as per ASME 16.34,ASME 16.1,ASME 16.5, API 600 & API 602
standards.
Customer requirements will be evaluated during detailed engineering phase with possible
extracosts.
Control valves will be selected according to ANSI/ISA.
Control valves shall be ANSI FCI70-2 Class IV
On-Off valves shall be ANSI FCI70-2 Class V
9 Valves - Standards Safety valves will be selected according to API RP 520/521/526/527 C
- BS5352 Forged Gate valves
- API600 Cast Gate valves
- BS5352 Forged Globe valves
- BS1873 Cast Globe valves
- BS1868 Forged and Cast Check valves
- API594 Cast Check valves (Wafer Type)
- BS5351 and API 6D Ball valves

The centrifugal fans are applicable in Mist eliminator, Enclosure Ventillation, Dust
extraction, etc applications. The fans shall be supplied as per the manufacturer
10 Centrifugal Fans/ Blowers C
standards based on GE O&G supplier specifications. Fans covered under GE O&G scope of
supply shall be designed as per AMCA and IS standards.

The Isolation philosophy is typically related to the overall plant. However, GE O&G
equipments are designed based on internal and Internaltional standards applicable to the
product. Hence, this specification will be considered only for information during the
11 Isolation Philosophy design of battery limits. The equipment supplied shall be in the form of self-standing C
package skid. The process piping needs to be connected to the skid tie-in points to start
operation. For details on Isolation purchaser to refer the P&ID attached to the Technical
Proposal.

The cleaning, pickling and pressure testing shall be carried out at the manufacturing shop
premises. The procedures can be witnessed by purchaser during the QCP test at the GE
O&G manufacturing site premises. Flushing of lines in the pre commissioning stage will be
carried out in installation site, please refer the Installation manual for further details. The
shop flushing generally follows the below steps.
1.Precleaning to remove dust chips and other contaminations which is done by hot water
jet under high pressure/Compressed air blowing/Mechanical or manual brushing,
grinding, milling and scraping
2.Degreasing is a process that removes oils, grease, and solid dirt particles from metal
12 Flushing and Cleaning of pipework surfaces. Degreasing prepares a material for finishing applications such as primers, C
paints, or bonds.
3.Water rinse is carried out with demineralised water to remove the product to be rinsed
completely. Water jets can also be used other than immersion process.
4Chemical pickling- It is a process in which the metallic surfaces are immersed in pickling
baths containing strong mineral acids, in order to remove impurities, stains, rust or scale.
5.Water rinse
6.Passivation- It is a chemical process to avoid any possible oxidation of the metal
particles with oxygen.
7.Drying- to remove the moisture from the items.

Welding preparation for piping will be as per ASME B31.3 and weld specifications will be
as per ASME IX for pressure vessels and AWS D1.1 for structures including baseplates
(with exceptions)
Welding and NDE procedures are internal documents which may be reviewed during the
QCP witness test at GE O&G manufacturing premises.
13 Welding In addition to ASME IX (and AWS D.1.1): C
- welding execution
- welding procedures (welding dossier)
- qualification of welders
according to equivalent European Standard (e.g. EN 288-3) are
also accepted.

The structural items (e.g. aux piping supports, walkways supports etc.) will be
designed/fabricated according to applicable GE O&G standard methods.
Structural parts within the GE O&G Scope of Supply will be welded according to AWS D1.1
14 Structures C
with no additional amendments. AISC will be followed for structural design and
fabrication along with appropriate ASTM for materials. The detailed engineering stage
shall consider the required safety considerations for the structural system.

GE O&G shall follow UBC 97 and UBC 2000 standards for design of structural supports for
15 Seismic Loads C
equipment. The GE O&G packages are suitable for UBC 4 Zone classification.

Anchor bolts used for GE O&G packages are dimensioned according to S355J2G3, EN
10025 for material (C40). All components will be hot dip galvanized to prevent corrosion.
16 Anchor Bolts Details related to material, dimensions of anchor bolts etc will be available in the VDR C
document "Machinery Foundation Loads and Notes". No other additional coatings shall
be provided to these bolts.

Page 2 of 9
GE Oil & Gas
Pag. I.2.1/2
GE Proprietary & Confidential Information
It depends upon the type of pump, seal type and API code (614/610/676) selected. Pumps
within the scope of supply are integral/optimized part of auxiliary systems and are not API
17 Shaft Sealing Systems For Centrifugal And Rotary Pumps designed. If the customer needs pumps to be designed according to API then we get the C
standard exceptions to API from the sub supplier with their technical offer. Mechanical
seals are most of the time engineered type.

The Lube and control oil system is designed in compliance with API 614 with applicable
comments & exceptions as provided in the proposal.
18 Lubrication, Shaft Sealing And Control Oil Systems Scope of supply section of the proposal gives the details of the Lube oil system. The P&ID C
explains the various components of the system. Any differences can be discussed during
the clarification meeting.

Compliance to ASME VIII Div. 1 will be guaranteed. Pressure Vessels installed on GE O&G
machines are part of pre-engineered systems, strictly related and optimized for the
function of the supplied machine. Dedicated design that has been developed on well
19 Pressure Vessel proven field experience basis, in order to obtain: high reliability, reduced dimensions, C
weights and reduced delivery time. Different and/or additional Customer Requirements
are considered not applied since they imply redesign the system itself and its concept and
they could drive loss of reliability and operability.

Compliance to ASME VIII Div. 1 will be guaranteed. Pressure Vessels installed on GE O&G
machines are part of pre-engineered systems, strictly related and optimized for the
function of the supplied machine. Dedicated design that has been developed on well
20 Shell & Tube Heat Exchangers proven field experience basis, in order to obtain: high reliability, reduced dimensions, C
weights and reduced delivery time. Different and/or additional Customer Requirements
are considered not applied since they imply redesign the system itself and its concept and
they could drive loss of reliability and operability.

Color coding shall not be done for GE O&G packages. For nameplate related lettering,
21 Lettering and Color Coding C
please refer to the note on Tag plates section above.
Pumps are designed according to the applicable API standard with the relevant C&E from
22 Pumps (centrifugal, rotary, screw) the pump vendor. Any redeign of the pump to match customer specification is not C
feasible.

The thermal insulation composed of A5 aluminium sheet elements (thickness : 2 mm),


with blanket insulation (mineral wool type) covered with glass fabric.
For auxilary items,Insulation is not applicable. Mineral wool blanket with aluminium
jacketing is provided around steam turbine and centrifugal compressor, around
23 Acoustic insulation Compressor process piping and steam turbine exhaust steam piping which functions C
both as insulation & acoustic barrier. An exclusive noise barrier may be required
depending upon the noise limitation required. The scope of supply section and/ or the
product data sheet will provide the description of the noise attenuation system
considered for the proposed package.

LV motors are designed in accordance with EN 60034-1/5/8/9/11/12/14, EN 60072-1 / EN


24 LV motors for LO console 60085, EN 60079. Detailed description of these motor characteristics are available in the C
last section of instructmentation specification of the proposal.

Electrical design of the package follow the IEC/CENELAC guidelines. Detailed description
25 Electrical Design of electrical characteristics of the items within the package are available in the electrical C
connections section of the instrumentation description of the proposal.

Auxilliary electrical systems within the GE supplied packages comply with IEC/CENELAC
26 Auxiliary Electrical Systems For Packaged Equipment guidelines. Any additional requirements shall be discussed during the clarification C
meetings for mutual agreement

GE will comply with the following standards, with comments and exceptions attached to
the proposal:
API 616 5th edition
API 614 4th edition
API 613 5th edition
AGMA 6011
API 670 4th edition
API 671 3rd edition
27 Applicable Standards. E
NPFA 12
ASME PTC 22
ASME VIII div. 1
ASME B31.1
IEC 60034

All other standards, including PEMEX specifications, except to the ones listed below will
not be considered for this supply.

Page 3 of 9
GE Oil & Gas
Pag. I.2.1/3
GE Proprietary & Confidential Information
For the proposal preparation, it has been considered the following specifications, with the
comments and exceptions as below (embedded specifications are not considered):
AV-EAG-L-ET-W-04 Rev. 1 INSTITUO MEXICANO DE PETROLEO
D-F.27958-A-101 Rev.0 DIAGRAMA DE FLUJO DE PROCESO SISTEMA DE ACONDICIONAMIENTO DE
GAS COMBUSTIBLE PLANTA DE ARRIBO, EAGL
MANUALES ANEXO B-1 Rev.0 ALCANCE DE TRABAJO Y ESPECIFICACIONES PARTICULARES - pages
126 a 133
ANEXO B-1 Rev.0 ALCANCE DE TRABAJO Y ESPECIFICACIONES PARTICULARES - pages 266 to 267
NRF-034-PEMEX-2011 AISLAMIENTOS TÉRMICOS PARA ALTAS TEMPERATURAS EN EQUIPOS,
RECIPIENTES Y TUBERIA SUPERFICIAL
NRF-046-PEMEX-2003 PROTOCOLOS DE COMUNICACIÓN EN SISTEMAS DIGITALES DE
MONITOREO Y CONTROL
NRF-048-PEMEX-2007 DISENO DE INSTALACIONES ELÉCTRICAS
NRF-053-PEMEX-2006 SISTEMAS DE PROTECCIÓN ANTICORROSIVA A BASE DE RECUBRIMIENTOS
28 General Comments C
PARA INSTALACIONES SUPERFICIALES.
NRF-095-PEMEX-2013 MOTORES ELÉCTRICOS.
NRF-100-PEMEX-2009 TURBINAS DE GAS PARA ACCIONAMIENTO DE EQUIPO MECANICO EN
INSTALACIONES COSTA FUERA
NRF-102-PEMEX-2011 SISTEMAS FIJOS DE EXTINCIÓN A BASE DE BIÓXIDO DE CARBONO.
NRF-105-PEMEX-2005 SISTEMAS DIGITALES DE MONITOREO Y CONTROL
NRF-134-PEMEX-2012 CAMBIADORES DE CALOR ENFRIADOS POR AIRE.
NRF-146-PEMEX-2011 TABLEROS DE DISTRIBUCIÓN EN MEDIA TENSIÓN
NRF-148-PEMEX-2011 INSTRUMENTOS PARA MEDICIÓN DE TEMPERATURA.
NRF-164-PEMEX-2011 MANÓMETROS
NRF-196-PEMEX-2008 CARGADOR Y BANCO DE BATERIAS
NRF-235-PEMEX-2010 SISTEMAS DE CONTROL Y PROTECCIONES TURBOGENERADORES.
NRF-238-PEMEX-2009 GENERADOR DE ENERGIA ELÉCTRICA
NRF-242-PEMEX-2010 INSTRUMENTOS TRANSMISORES DE TEMPERATURA

Since GE is proposing two identical MS5001PA GTG trains which will be installed near to each
other, the items as below identified have been proposed only one, which are common to both
trains:
Generator rotor disassembly tool;
transmitters setting interface supply;
Exhaust duct template;
29 Scope fo supply Commissioning and start-up spare parts supply;
Set of sepcial tools;
load coupling alignment tool;
lifting tools;
Site container for installation;
Combined off/ on line washing system;
Gas turbine and generator tests.

Pr Rev# Spec Title Spec#

1 AV-EAG-L-ET-W-04 INSTITUTO MEXICANO DE PETROLEO

Progr Par.Id Subject O&G Comment C/E

Applicable API, ISO, ASME, ISA standards shall be followed.


NFPA 70-2011 NATIONAL ELECTRIC CODE will be applied with extraprice
3.0 3.0 DESIGN AND MANUFACTURING NORMS, CODES AND STANDARDS Please clarify if NACE MR01 75/ISO 15156 is applicable E
NRF standards and PEMEX specification are missings
ISA 84.00.01 Please refer to the SIL Policy attached in Proposal
4.0 GENERAL SCOPE
4.0 The details shall be considered for information during the detailed engineering phase. C
Site conditions

The CONTRACTOR is the responsible for the installation and shall take
care of the carrying, mounting, leveling of the turbo generators in the This is EPC responsability. For GE technical services at site, please refer to GE O&G
4.0 E
Arrival Plant of the Gas Conditioning Station Lakach (EAGL). As well as for commercial proposal.
the commissioning of the electric generation system

The CONTRACTOR shall supply all the pipings, cabling, ducts and all the
materials needed for the operation of the system. He shall finish all the
4.0 Out of GE O&G scope of supply. This is EPC responsability. E
piping interconnections in the border of the module and the electric
interconnections in his own connection boxes mounted in the module

This is referring to the overall EPC scope of supply, cointaining items and services not
covered by gas turbine generator supplier scope of supply. For GE O&G scope of supply,
please refer to GE technical and commercial proposal for details of the equipment &
4.2 4.2 Scope of the Works auxiliaries provided. The information regarding the documents provided in VDR and the
4.3 4.3 Scope of supply of equipments and components tests performed on the equipment are also part of the proposal. The P&ID provides
information regarding the tie-in points for the various battery limits of the GE equipment.
Any on-site activity is also not in GE O&G scope. Further discussions can happen
regarding the services to be required and can be mutually agreed upon.

All the materials of the air admission system shall be supplied in stainless
5.1.1 Support structures are provided in CS Zinc plated. E
steel.
EPC to guarantee a fuel pressure from 18.5 to 24 Bar g in the inlet of the combustion
5.1.3 Fuel gas system C
chamber. If a gas booster is required, to be provided by others.

Page 4 of 9
GE Oil & Gas
Pag. I.2.1/4
GE Proprietary & Confidential Information
5.1.3 The main valve of the fuel shall have manual and electric opening,
automatic closing device when the stop signal is actuated due to over
speed or there is any of the stop conditions indicated in the data sheet-
Fuel gas stop valve to be provided by EPC. Please refer to the P&ID attached to the
5.1.3 The automatic trip shall operate with 24 VDC and shall have four contacts E
technical proposal.
of limit position; one to operate on the opening side and three for the
closing side. Likewise, it shall send a discrete signal to the PLC for opening
and closing, including the emergency tripping.

5.1.3 The gas turbine shall be supplied with a fuel gas system fully
installed, which shall include valves (including the main one), regulators, Fuel gas system will be mounted in the GT skid. Fuel gas scrubber shall be on a separate
5.1.3 E
filters, controls, electronic governor and piping and shall be mounted in skid.
the skid of the gas turbine.
5.1.5 The washing system for the turbine shall be on line and shall include
5.1.5 01 washing system combined on/ off-line trolley type is proposed to both GTGs. E
the accessories
5.2 5.2 Electric Generator Please refer to the comments & exceptions section related to the electrical generator. C
5.4 The piping, valves, connections and accessories for the supply and
return of the lubrication system shall be of stainless steel. Body of valves, tank material, filter material shall be in carbon steel. Also, pump casing
5.4 E
The oil tank shall have the necessary capacity and shall be manufactured will be in cast iron.
in stainless steel.
5.4 The pumps for pre-post lubrication shall be electric driven with Main oil pump shall be accessory gear driven while the stand-by pump shall be AC
5.4 E
alternate current- Electric motor driven.
5.6.1 The accessories for the enclosure like hinges, closing and opening The enclosure shall be designed with painted carbon steel panels with all the fixtures in
5.6.1 E
mechanisms for doors, screws, etc. shall be of stainless steel. the same material.

5.6.2 The fire detection shall consist in a primary system and a secondary
system located inside the enclosure of the gas turbine.
The primary system shall consist of UV-IR detectors (ultraviolet and
infrared)
The secondary system shall consist in a network of thermal detectors.
The primary system will be heat rise detectors as per P&Id in Proposal.
The system shall include a supervision board, with indicator lights and a
5.6.2 As option in cold area we can add 3IR or UV/IR sensors. E
notifying system (alarms). This system shall have redundant
Fuel monitoring to be defined
communication for its integration to the network.
The system shall also include the fuel monitoring inside the enclosure.
It shall be provided a portable equipment for calibration of the fuel
detection system and UV/IR test.

Gas turbine and Generator shall be mounted on separate consoles. Auxiliary baseplate
5.7 The gas turbine, the electric generator and all the auxiliary equipments
5.7 shall be integrated in the GT baseplate. Other auxiliaries like fuel gas scrubber skid, oil C
shall be mounted in a rigid skid of structural steel.
vapor separator, air coolers, etc. are mounted separately.

5.9 For the supply of the instrumentation the supplier or the contractor
shall stick to the General Specification for Instrumentation and Control
Systems in Package Equipments EPI-P-701.
It is responsibility of the supplier or contractor the supply, installation and EPI-P-701 is missing
interconnection of the instrumentation, equipment and accessories, as Interconnecting cables from JBs to UCP are not in GE scope of supply.
5.9 E
well as the material required for its installation and interconnection. Please clarify If Fuel gas shut off and vent valve outside GT Package is in GE Scope of
The electric devices shall be normally energized. supply
The blocking valves for emergency stop (SDV) and for venting (BDV) shall
be operated with pneumatic actuator.

5.9 Vibration and temperature detection system.


It shall be provided a temperature detection system based on resistances
(RTD´s).
It shall be supplied the vibration detection system, with non-contact type
5.9 detectors, in bearings. The vibration and temperature detection systems Bearing vibrations and temperatures can be directly connected to the BN3500 as option R
shall include the primary sensors, cables, transducers, monitor, alarms
and stop elements due to vibration and temperature. The monitoring and
signaling due to alarm and stop shall be included in the PLC´s.

5.10 The cabling of the packages shall be in accordance to the


specifications of the supplier, national norms and standards like API, ANSI,
NEMA among others.
For the external cabling of the interconnection points shall be considered
5.10 Cables according to SOM6621236 and SOM6621238 included in Proposal E
the armed type, three-phase, with aluminum bind armature with external
insulation of PVC anti-flame for 600 VAC, copper and bare wire
conductors for ground, which shall be biodegradables and not toxic.

5.11 The CONTRACTOR shall supply, interconnect and install in the interior
5.11 Gas detectors will be installed in filter house and ventilation outlet E
of the enclosure a gas and fire detection subsystem.

5.13 The electric classification for the interior of the enclosure of the turbo Instrument execution according to SOM6621236 and SOM6621238 included in Proposal.
generator package, it shall be according to API-RP 500 FIG. 106, class 1, The units (inside and outside enclosure) shall be designed for IEC Zone 2 II B T3 (equivalent
5.13 division 1, group C and D. For the rest of the turbo generator package the to NEC Division 2 Gas group C T3) E
area classification will be class 1, division 2 groups C and D (included the Filter house shall be installed in Safe Area, since gas turbine cannot ingest air with gas.
lubricating oil cooler). Filter house is equipped with gas detection.

5.14 5.14 Identification nameplates and anticorrosive protection Nameplates in SS316 according to SOM6621236. Tagging according project requirements E

Page 5 of 9
GE Oil & Gas
Pag. I.2.1/5
GE Proprietary & Confidential Information
5.15 The piping connections shall end either in flanges or threads as it is Certain connections like vent and drain shall be provided plugged for extension by
5.15 E
determined by the project and shall be ready for its connections. customer.

Quality control & inspection requirements are as per GE O&G QCP. Inspection hold,
witness & observation points are mentioned in the plan which can be discussed during
pre-inspection meeting. Certificates are provided for the tests conducted as per the MDR
6.0 6.0 TESTS Index submitted as part of VDR. Parts already in our stocks and off-the-shelf components
E
7.0 7.0 PREPARATION FOR SHIPMENT will be provided with certification according to GE O&G standard.
Protection for the storage and shipment of machines, machine components and plant
components will be as per GE O&G standard ITN02175.
ITNs can only be available for review in GE O&G manufacturing facility.
9 9.0 SPARE PARTS AND SPECIAL TOOLS Please refer to technical & commercial proposal for details. C
10.0 The CONTRACTOR shall present in his proposal a quotation dully
documented for two courses for training of 20 persons in operation and
10 The requirement for training shall be discussed in the bid meeting. C
maintenance of the turbo generators and with a lasting of 14 natural
days each one,

Pr Rev# Spec Title Spec#

0 ALCANCE DE TRABAJO Y ESPECIFICACIONES PARTICULARES ANEXO B-1

Progr Par.Id Subject O&G Comment C/E

General Comments This specification is not applicable to GTG vendor. To be considered by EPC company. C

Customer to refer to the GE O&G "Scope of Supply" attached with the technical proposal
for details of the equipment & auxiliaries provided. The information regarding the
documents provided in VDR and the tests performed on the equipment are also part of
12.45.2 MECHANICS DYNAMIC.
12.45.2 the proposal. The P&ID provides information regarding the tie-in points for the various E
SCOPE:
battery limits of the GE equipment. Any on-site activity is also not in GE O&G scope.
Further discussions can happen regarding the services to be required and can be
mutually agreed upon.

Pr Rev# Spec Title Spec#

0 IDENTIFICACIÓN DE INSTALACIONES FIJAS. NRF-009-PEMEX-2012

Progr Par.Id Subject O&G Comment C/E

General Comments This specification is not applicable to GTG vendor. To be considered by EPC company.

Pr Rev# Spec Title Spec#

AISLAMIENTOS TÉRMICOS PARA ALTAS TEMPERATURAS EN EQUIPOS,


0 NRF-034-PEMEX-2011
RECIPIENTES Y TUBERIA SUPERFICIAL

Progr Par.Id Subject O&G Comment C/E

This specification is not applicable to GTG vendor. To be considered by EPC company. For
General Comments thermal insulation relevant to the Gas Turbine Generator, please refer to the 'Insulation' E
clause in the General Comments above mentioned.

Pr Rev# Spec Title Spec#

CLASIFICACIÓN DE AREAS PELlGROSAS Y SELECCIÓN DE EQUIPO


0 NRF-036-PEMEX-2010
ELÉCTRICO.

Progr Par.Id Subject O&G Comment C/E

General Comments This specification is not applicable to GTG vendor. To be considered by EPC company.

Pr Rev# Spec Title Spec#

COMMUNICATION PROTOCOLS IN DIGITAL MONITORING AND CONTROL


4 NRF-046-PEMEX-2003
SYSTEMS

Progr Par.Id Subject O&G Comment C/E

Integration between turbogenerator control panel and customer system it is possible on


the basis of following interfaces :

1) Hardwired interface
General Comments C
2) Simplex or redundant communication link based on Serial Modbus.
3) Simplex or redundant communication link based on TCP/IP Modbus.
4) Simplex or redundant communication link based on OPC DA & AE.(if communicatio
gateway are chosen as options available at extra cost).

Page 6 of 9
GE Oil & Gas
Pag. I.2.1/6
GE Proprietary & Confidential Information
Pr Rev# Spec Title Spec#

0 INSPECCION DE BIENES Y SERVICIOS NRF-049-PEMEX-2010

Progr Par.Id Subject O&G Comment C/E

General Comments This specification is not applicable to GTG vendor. To be considered by EPC company.

Pr Rev# Spec Title Spec#

0 SISTEMAS DE PROTECCIÓN A TIERRA PARA INSTALACIONES PETROLERAS NRF-070-PEMEX-2011

Progr Par.Id Subject O&G Comment C/E

General Comments This specification is not applicable to GTG vendor. To be considered by EPC company.

Pr Rev# Spec Title Spec#

0 MOTORES ELÉCTRICOS NRF-095-PEMEX-2013

Progr Par.Id Subject O&G Comment C/E

Following LV induction motors will be in AC


88QA-1 Auxiliary lube oil pump motor
88CR -1 Starting motor
88BA-1 Ventilation Main fan motor
88BA-2 Ventilation Stand-by fan motor
Following LV motors will be in DC
88HR-1 Hydraulic ratchet pump motor
88QE-1 Emergency lube oil pump motor
General Comments E
These motors will be according to NEMA MG codes and Explosion proof, TEFC type
NMX or NOM codes are missing

Other details will be defined once selected the LV motor manufacturer in the agreed
Vendor List

Datasheets will be available during detailed engineering phase as agreed as per VDR

Pr Rev# Spec Title Spec#

TURBINAS DE GAS PARA ACCIONAMIENTO DE EQUIPO MECANICO EN


0 NRF-100-PEMEX-2009
INSTALACIONES COSTA FUERA

Progr Par.Id Subject O&G Comment C/E

This specification is not applicable to the type og gas turbine quoted (heavy duty,
single shaft, power generation and on-shore application). GE has considered on the
item of NRF-100-PEMEX-2009 which were called in the document AV-EAG-L-ET-W-04
General Comments
Rev. 01, which are: 8.2.9 related to nameplate, 8.3 related to the GT auxiliaries, item
8.4 (8.4.1 to 8.4.3.4.2.1) related to the inspections, tests and shipment preparation, as
well as table 3. Any other items of this specification have being disregarded.

The GE O&G standard practice for Name / Tag plates is attached herewith for the
8.2.9 8.2.9 Data plate and rotation shaft information to purchaser. The convention shall be followed throughout the project E
execution phase.
8.3.1.2 The supplier must indicate in its proposal and in the
8.3.1.2 datasheets the maximum allowed moments and forces in the inlet nozzle Allowable nozzle loads shall be communicated during the detailed engineering phase. C
of the gas turbine.
8.3.1.6 Humidity indicator after the filters with alarm for high humidity
8.3.1.6 Humidity transmitter are not foreseen in the base offer. E
with local and remote signals.
8.3.1.8 When required in the datasheets of the gas turbine, supplier
must provide a heat exchanger air-refrigerant for cooling the inlet air
8.3.1.8 Air chiler has not being required and therefore not quoted. C
cooling, with the purpose of increasing the onsite power of the gas
turbine.
8.3.3.3.8 Stainless steel pipes, valves and accessories for injection (oil Body of valves, tank material, filter material shall be in carbon steel. Also, pump casing
8.3.3.3.8 E
to the components to lubricate) and return (oil to the recipient). will be in cast iron.
8.3.3.3.9 Oil tank made of stainless steel with enough capacity to
8.3.3.3.9 Oil tank shall be in carbon steel. E
sustain the emergency …

Page 7 of 9
GE Oil & Gas
Pag. I.2.1/7
GE Proprietary & Confidential Information
8.3.3.3.11 Instrumentation
b) Discharge head pressure indicator and transmitter in the lubricating
pumps Instrumentation on Lube Oil System as per P&Id in proposal:
d) Temperature indicator and transmitter, one immediately after the b) on lubricating pumps will be supplied a pressure indicator
8.3.3.3.11 E
cooler and the other one in the injection head to the bearings or any other d) Temperature indicator immediately before and after will not be provided
part to lubricate. e) alarm and shutdown for high pressure
e) Alarm and shutdown for low pressure.

Instrumentation for Fuel Gas System as per P&Id in proposal>


8.3.4.6.1 8.3.4.6.1 f Flow indicator and transmitter flow indicator and transmitter will not be provided E

8.3.5.5.1 Electric Supply to Control System Both MarkVIe & MarkVIeS operate at 28Vdc . C
8.3.5.11 Alarms and stops The alarms shall appear on HMI alarm banner. C
8.3.5.8.1.4 Vibration monitoring It shall be performed in BN vibration monitor. C
This can be integrated in MarkVie itself. BN Temperature can be provided as an
8.3.5.8.1.5 Temperature Monitoring C
option at extra cost.
Safety PLC MarkVIeS will take care of safety loops of gas turbine , namely:
1) Overspeed protection; 2) Starter overspeed protection; 3) Vibration Protection; 4)
Enclosure gas leakage protection; 5) Exhaust duct purging during start-up; 6) Loss
8.3.5.8.1.6 Module for safety and protection, of flame protection; 7) Excessive fuel at start-up; 8) Drain valve position check at C
start-up ( for liquid fuel application ); 9) Exhaust duct purging ( for liquid fuel
application ); 10) Emergency shut-down push button
8.3.7.1.1.2 The cabin should have one or more access doors, as required
equipped with: stainless steel locks…... The enclosure shall be designed with painted carbon steel panels with all the fixtures in
8.3.7.1.1.2 E
The bolt of support and turn (hinges) of the door should be of stainless the same material.
steel.
8.3.7.2.1 The ventilation should allow having a maximum temperature of
338,15 K (65°C) in the interior of the cabin, avoid the entering of gases
8.3.7.2.1 The enclosure shall be designed to assure a ventilation outlet temperature of 80 degree C. E
towards the interior and avoid the increment of the temperature in the
cabin
8.3.7.3.1 The equipment for maintenance maneuvers should be formed
but not limited for the following components: fixed crane runway with A monorail shall be provided as part of the standard arrangement inside the GT enclosure
8.3.7.3.1 E
folding extension to be moved outside, reeving formed by: truck, pulley, for the maintenance purpose.
load and command chain and cargo hook.
Gas detection shall be performed in MarkVIes itself. For fire protection , an individual
8.3.8 Gas and Fire detection and fire protection system. Fire fighting PLC shall be provided.This PLC sends out Fire trips summary to C
MarkVIe , and MArkVIeS, and receives reset and silence from MarKVIe.It is
connected to local network switches on PDH.
CO2 extinguishing system shall be provided, which is a pre-engineered type, tested and
8.3.8 8.3.8 Gas and Fire detection and fire protection system C
designed according to NFPA 12.
8.3.9.3 The skid or base should be design and manufacture with structural
8.3.9.3 Material used for baseplate is S275JR (FE430B). E
element of carbon steel…
IT is not considered or integrated in MArkVIE.
8.3.11 Monitoring system for contaminant gases emission to atmosphere. E

8.3.12 Couplings and guards will be as per API 671 with manufacturer standard exceptions E
8.3.12 Couples and couple guards.
8.3.13 8.3.13 Gear Boxes The standard GE O&G comments & exceptions to API 613 shall be followed. E
8.3.14.1 The wash system should be off line, unless otherwise is specified
8.3.14.1 A combined off/on line washing system shall be provided. E
in the data sheet.
8.3.16 8.3.16 Special tools for maintenance in site Please refer to technical proposal for details. C

Quality control & inspection requirements are as per GE O&G QCP. Inspection hold,
witness & observation points are mentioned in the plan which can be discussed during
pre-inspection meeting. Certificates are provided for the tests conducted as per the MDR
Index submitted as part of VDR. Parts already in our stocks and off-the-shelf components
will be provided with certification according to GE O&G standard.
8.4 8.4 Inspection, tests and shipping preparation Protection for the storage and shipment of machines, machine components and plant E
components will be as per GE O&G standard ITN02175.
ITNs can only be available for review in GE O&G manufacturing facility.
Please refer to the comments related to item 8.4 of NRF-100-PEMEX-2009, in the
comments and exception related to the Inspections and tests attached to the
technical proposal.

8.5 8.5 Warranties As per General Comments above mentiones]d, these items have not being considered
E
8.6 8.6 Supplier Documents and therefore will be as per GE O&G standard procedures.

Pr Rev# Spec Title Spec#

0 INSTRUMENTOS PARA MEDICIÓN DE TEMPERATURA NRF-148-PEMEX-2011

Progr Par.Id Subject O&G Comment C/E

NMX, NOM, NRF are missing. NEC&NEMA will be followed


6 References TCs will be ANSI MC 96.1 (inside GT Package), RTDs will be according to IEC60751 E
ISO 15156-1:2009> please clarify if NACE are applicable

9.1.1 The bimetallic dial thermometers, the protector element thermo well
and the temperature elements of thermo couple and RTD shall comply
with the requested in the specification sheet of Annex 12.2 of this NRF Specification sheets will not be followed E
and/or what is indicated in the Bid Bases, as well as the requisites
indicated in this NRF.

Page 8 of 9
GE Oil & Gas
Pag. I.2.1/8
GE Proprietary & Confidential Information
Inside Gas Turbine Package K type TCs will be in INCONEL 600 material and according to
ANSI MC96.1:
CT-DA-1/2 Single TC type K Axial compressor discharge temperature
TT-XD-1÷13 Single TC type K Exhaust temperature Monitoring
CT-IA-1/2 Single TC type K
Axial compressor inlet temperature
9.1.3 Thermocouples E
LO-OT-1 Single TC type K Lube oil tank temperature
LT-TH-1A/B/C Single TC type K Lube oil header temperature
TT-WS1FO/AO Wheelspace temperature
LT-B1D-A/LT-B2D-1/LT-BT1D-1 Lube oil bearing

Outside GT Package Customer specification will be applied as option

Inside Gas Turbine Package RTD will be in INCONEL 600 material according to IEC60751:
TG-FG-1 Fuel gas inlet temperature
9.1.4 RTD TT-BA-2A/B/C Turbine compartment internal temp E
BT-J1/BT-J2/BT-TA/BT-TI Bearing temperature
Outside GT Package Customer specification will be applied as option

Inside Gas Turbine Package SS316 threaded thermowells (1”NPT-M or ¾” NPT-M) only for
piping installation (Lube oil drain bearings, upstream fuel
9.1.5 Thermowells E
gas valves) and inlet ventilation duct.
Outside GT Package Customer specification will be applied as option

8.3 Manufacturing This paragraphs will not be applied because NMX are missing E
8.6.2 Manufacturing drawings for PEMEX revision Manufacturing drawings will not be delivered E

Pr Rev# Spec Title Spec#

EQUIPO DE MANIOBRA PARA INSTAlACIONES: GRÚAS VIAJERAS, MAlACATES Y


0 NRF-183-PEMEX-2007
POLIPASTOS.

Progr Par.Id Subject O&G Comment C/E

General Comments This specification is not applicable to GTG vendor. To be considered by EPC company.

Pr Rev# Spec Title Spec#

5 Control & Protection System for turbogenerators NRF-235-PEMEX-2010

Progr Par.Id Subject O&G Comment C/E


Zero-speed monitoring is not supplied because not requested by GT control
8.1.2 III Dynamic Equipment Detection and Diagnosis System (Vibration Monitor) C
requirements.
We are offering G60 Multilien Relay .
Following protection are not included ,
49-Thermal Protection - this protection function is not available in G60 relay, same was
8.1.2 General Automation of the Turbo Generator
covering with RTD temperature measurment input to G60. C
V. Generator Protection Relay
As transformer is not in GE scope,
The following protection are not included in scope.
63,62B,71,87T,87U
Ge has included a network printer (dot matrix pinter is not included).
8.3.3.2.6 Peripherals E

Page 9 of 9
GE Oil & Gas
Pag. I.2.1/9
GE Proprietary & Confidential Information
NAMEPLATES

All equipment as motors, junction boxes, terminal boxes, control stations shall be
marked with indelible easy-to-read tags, with the same code by which they are
identified in the wiring diagram and electrical outline, by indicating number and
function.

All nameplates, including Nuovo Pignone and Customer tag numbers, according
P&ID last issue, including but not limited to:
- Manifolds;
- Valves;
- Instruments and accessories;
- Junction boxes;
- Electrical equipments as motors, heaters, pushbuttons, local control stations;
- Terminal points (MP,TP, BL).

All instruments shall have the following labels:


- N°3 for pressure instruments: On primary connecti on, on manifold and on the
instrument
- N°2 for temperature instrument: On primary connec tion and on the instrument
- N°1 on all the other instruments.

Labels on instruments and primary connections shall be fixed with stainless steel
wires, on other devices shall be fixed by stainless steel screws or rivets.

All labels shall be in English language.

GE Oil & Gas


Pag. I.2.1/10
GE Proprietary & Confidential Information
Nameplate for Junction Boxes, Motors, Pumps…

MATERIAL ................. : AISI 316


THICKNESS ................ : 2 mm
TEXT COLOR ............. : BLACK
DIMENSIONS.............. : 90x20 mm
STYLE FONT .............. : IBM EXECUTIVE

Nameplate for Instrumentation, Manifolds, Root valves…

MATERIAL ................. : AISI 316


THICKNESS ................ : 2 mm
TEXT COLOR ............. : BLACK
DIMENSIONS.............. : 60x15 mm
STYLE FONT .............. : IBM EXECUTIVE

Nameplate for Lube Oil Local Panel

MATERIAL ................. : AISI 316


THICKNESS ................ : 2 mm
TEXT COLOR ............. : BLACK
DIMENSIONS.............. : 76x32 mm
STYLE FONT .............. : IBM EXECUTIVE
MAX CHARACTERS n°: 27
LINE 1 ......................... : INSTRUMENT TAG
LINE 2/3/4 ................... : DESCRIPTION

GE Oil & Gas


Pag. I.2.1/11
GE Proprietary & Confidential Information
All cables and wires, shall be labeled at both ends with indelible marked ferrules
according to the tagging shown in the wiring diagrams.

All B/N extension cables, RTD’s and/or TC’s cables (see note 2 sheet 18), shall
be labeled at both ends with indelible marked ferrules according to the tagging
shown in the wiring diagrams.

GE Oil & Gas


Pag. I.2.1/12
GE Proprietary & Confidential Information
GE OIL & GAS COMMENTS AND EXCEPTIONS LIST ABOUT CUSTOMER INSPECTIONS AND TESTS REQUIREMENTS - DOCUMENT NRF-100-PEMEX-
2009, ITEM 8.4
Document Reference Comment Exception
Item No. Rev. Page / Para. Bidder Comment/Exception Details
(Spec, Code, Std etc) - Including (Yes / No) (Yes / No)
Program for inspections will be provided on monthly
basis together with Project Monhtly Report.
PEMEX representative will have access to GE and
SubSupplier premises for notified tests and for agreed
1 NRF-100-PEMEX-2009_ENG 0 8.4.1.1 Y N meetings.
All other accesses shall be agreed with Project
Representatives.

For this scope of supply 2 main Quality Control Plans


will be created:
2 NRF-100-PEMEX-2009_ENG 0 8.4.1.2 Y N
one for the MS5001PA DLN + gearbox and another one
for generator
Only project specific test procedures will be provided.
3 NRF-100-PEMEX-2009_ENG 0 8.4.1.3 Y Y All GE MFR Standards (i.e. ITN's) cannot be shared.

In case of test date revision we may not have the


possibility to postpone the test for 5 days, above all for
4 NRF-100-PEMEX-2009_ENG 0 8.4.1.4 Y Y tests that require the use of a test bench for which GE
plans are made many weeks in advance.

Customer to specify how much in advance this


5 NRF-100-PEMEX-2009_ENG 0 8.4.1.5 Y N
communication shall be sent.
Customer to clarify this requirement, as the point
6 NRF-100-PEMEX-2009_ENG 0 8.4.1.6 Y N
8.4.1.4 requires 5 working days of notice
Customer to clarify this requirement, as the point
7 NRF-100-PEMEX-2009_ENG 0 8.4.1.7 N N
8.4.1.4 requires 5 working days of notice
Not all weldings may be Rx'ed, in case of not
12 NRF-100-PEMEX-2009_ENG 0 8.4.2.1.3.1 Y Y accessibility customer shall consider UT as alternative.

In case of non ferromagnetic material, customer to


13 NRF-100-PEMEX-2009_ENG 0 8.4.2.1.3.2 Y Y consider the Dye Penetrant as alternative to MT.

GE Oil & Gas


Pag. I.2.1/13
GE Proprietary & Confidential Information
No Hydrostatic Test can be performed on Gas Turbines.
22 NRF-100-PEMEX-2009_ENG 0 8.4.3.1.1 Y Y
Performance Test is a standard. In case of more than 1
Gas Turbine, the GT subject to Performance Test shall
24 NRF-100-PEMEX-2009_ENG 0 8.4.3.1.3 Y Y
be decided at the beginning of the project.

Optional Test were not asked by Pemex through a GT


25 NRF-100-PEMEX-2009_ENG 0 8.4.3.1.4 Y N data sheet and therefore they are not quoted.

NRF-049-PEMEX-2006 to be provided for comments. It


28 NRF-100-PEMEX-2009_ENG 0 8.4.3.1.7 Y Y has not being considered as it is an embedded
specification.
Standard MRT, includes only the Flange to Flange Gas
Turbine, and shop auxiliaries are used. Each auxiliaries
36 NRF-100-PEMEX-2009_ENG 0 8.4.3.3.1 Y Y
is tested separately at supplier premises.

GE Oil & Gas


Pag. I.2.1/14
GE Proprietary & Confidential Information
8.4.3.3.2.1 A Test Procedure will be provided via VDR. Customer
8.4.3.3.2.2 Approval will be required.
8.4.3.3.2.3
8.4.3.3.2.4
8.4.3.3.2.5
8.4.3.3.2.6
8.4.3.3.2.7
8.4.3.3.2.8
8.4.3.3.2.9
8.4.3.3.3.1
8.4.3.3.3.2
8.4.3.3.3.3
37 NRF-100-PEMEX-2009_ENG 0 N N
8.4.3.3.3.4
8.4.3.3.3.5
8.4.3.3.4.1
8.4.3.3.4.2
8.4.3.3.4.3
8.4.3.3.4.4
8.4.3.3.4.5
8.4.3.3.5.1
8.4.3.3.5.2
8.4.3.3.5.3
8.4.3.4.1
8.4.3.4.2

GE Oil & Gas


Pag. I.2.1/15
GE Proprietary & Confidential Information
GE OIL & GAS COMMENTS AND EXCEPTIONS LIST TO CUSTOMER REQUIREMENTS ABOUT ELECTRICAL GENERATOR

Ref. to Tech. Spec./Document/ International Code and 
Exception to Customer's Techn. Requirement (2)
Paragraph (1)

Generators quoted with consideration of the NEMA MG‐1 and IEEE sdt 
112 standards only with the following comments and exceptions. Please 
NRF-238-PEMEX-2009F note, only the specifications expressly stated in this BQF clarification file 
GENERADOR DE ENERGIA ELECTRICA - General have been considered applicable to the offered generators. Cross‐
referenced documents contained within these specifications have not 
been considered

Regarding API 670 requirement, bearing RTDs will be installed 180° 
NRF-238-PEMEX-2009F apart, one at right side face the bearing and the other at left side.
GENERADOR DE ENERGIA ELECTRICA - General It is the STD bearing housing configuration of the main market suppliers 
(RENK, ZOLLERN, etc.).
NRF-238-PEMEX-2009F
We are offering generators with solid rotor and with salient poles.
GENERADOR DE ENERGIA ELECTRICA - Item 6.3
NRF-238-PEMEX-2009F
We are offering generator with 1800 rpm (4 poles).
GENERADOR DE ENERGIA ELECTRICA - Item 8.1.2.c and d
NRF-238-PEMEX-2009F
We are offering IP 56 degree of protection
GENERADOR DE ENERGIA ELECTRICA - Item 8.1.2.n
NRF-238-PEMEX-2009F Please note generators should be properly handled, stored, installed,
GENERADOR DE ENERGIA ELECTRICA - Item 8.1.3.1 operated and maintained, according to our manual.
NRF-238-PEMEX-2009F
Please refer to our proposal datasheet for offered efficiency values
GENERADOR DE ENERGIA ELECTRICA - Item 8.1.3.8
Terminal box will be designed to withstand 42kA during 0.25 seconds, by
NRF-238-PEMEX-2009F
following the design criteria of successfully designed and 3rd party tested
GENERADOR DE ENERGIA ELECTRICA - Item 8.1.3.12
TB. Please note that this terminal box will not be tested/certified.

NRF-238-PEMEX-2009F
Maximum overspeed will be 2250RPM, based on a 1800RPM design
GENERADOR DE ENERGIA ELECTRICA - Item 8.1.3.15

We are offering RTD instalation in the hottest parts of the coils, which are
NRF-238-PEMEX-2009F within the stator core, according to our design. Our design does not
GENERADOR DE ENERGIA ELECTRICA - Item 8.1.3.18 includes RTD installation outside of the core. Please note the part of coil
outside the core is not an effective part to have temperature measured.
NRF-238-PEMEX-2009F Since this generator will be installed in a hazardous location we are
GENERADOR DE ENERGIA ELECTRICA - Item 8.1.3.23 offering our standard space heaters without thermostat
NRF-238-PEMEX-2009F
Please refer to our proposal datasheet for offered values.
GENERADOR DE ENERGIA ELECTRICA - Item 8.1.3.24
Control Power Supply - The AVR AC input accepts voltage over the
range of 82 to 132 Vac at 50 or 60 hertz. The DC input accepts voltage
NRF-238-PEMEX-2009SF_ENG -14.10.13.docx - Item 8.1.4.2
over the range of 90 to 150 Vdc. Any values out of the ranges herein
Clarification
mentioned will be considered incompatible and is on customer
responsibility to provide proper voltage power supply.
NRF-238-PEMEX-2009SF_ENG -14.10.13.docx - Item 8.1.4.2 Limitation of stator current is not on the excitation panel. It is related to
Clarification the load on the generator.

NRF-238-PEMEX-2009SF_ENG -14.10.13.docx - Item 8.1.4.3


The structure of the panel will be 14USG
Clarification

NRF-238-PEMEX-2009SF_ENG -14.10.13.docx - Item 8.1.4.3 All painting and ant corrosive treatement will be according GE paint
Clarification specifications.

NRF-238-PEMEX-2009SF_ENG -14.10.13.docx - Item 8.1.4.4


Signals cables will not be separe from other cables
Clarification

NRF-238-PEMEX-2009SF_ENG -14.10.13.docx - Item 8.1.4.4


All materials will comply with IEC standards
Clarification

GE Oil & Gas


Pag. I.2.1/16
GE Proprietary & Confidential Information
NRF-238-PEMEX-2009F
Control room is not included in our scope
GENERADOR DE ENERGIA ELECTRICA - Item 8.1.4.5
NRF-238-PEMEX-2009F
This item is not applicable to offered generator
GENERADOR DE ENERGIA ELECTRICA - Item 8.1.5
NRF-238-PEMEX-2009F
Generator Breaker to be provided by others.
GENERADOR DE ENERGIA ELECTRICA - Item 8.1.6
NRF-238-PEMEX-2009F
We understand this should not be included in our scope.
GENERADOR DE ENERGIA ELECTRICA - Item 8.1.6
NRF-238-PEMEX-2009F We are offering Neutral Ground resistor with transformer. Please note 
GENERADOR DE ENERGIA ELECTRICA - Item 8.1.7 this panel shall be installed in a safe area 
NRF-238-PEMEX-2009F
This item is not included in GE scope.
GENERADOR DE ENERGIA ELECTRICA - Item 8.1.8
Seismic Classification Zone is not considered in our proposal. Seismic
loading: The Uniform Building Code does not define g forces for motor
design. Our motor design is based on NEMA MG-1.20.32.4
recommendation. For induction motors covered by NEMA part 20, it is
NRF-238-PEMEX-2009F recommended the supporting base structure for the induction machine
GENERADOR DE ENERGIA ELECTRICA - Item 8.1.15.4 limit the peak acceleration due to earthquakes to the following maximum
values: a) One and one-half g's in any direction. b) One g vertically
upward and downward in addition to the normal downward gravity of 1g.
The loads imposed as a result of the foregoing inputs can be assumed to
have negligible effect upon the operation of the induction machine.
NRF-238-PEMEX-2009F Partial discharge sensors installed inside stator core are under evaluation 
GENERADOR DE ENERGIA ELECTRICA - Item 8.2.2 (monitoring system not included).
Ultrasound test in rotor winding welds is not available, there is no space
enough to perform this test due to pole configuration.

Due to the Classified Area, the sparking device (Grounding Brush) will
NRF-238-PEMEX-2009F not be installed on the motor. Therefore, the shaft grounding must be
GENERADOR DE ENERGIA ELECTRICA - Item 8.2.3 Rotor. made on the driven machine. GE needs to get confirmation from the
Customer if they can install a grounding device on their machine before
confirming this proposal or releasing the motor for production.

Residual magnetism value is under engineering evaluation.


NRF-238-PEMEX-2009F Partial discharge sensors installed inside stator core are under evaluation 
GENERADOR DE ENERGIA ELECTRICA - Item 8.2.3 (monitoring system not included).

Metal enclosure is included for Gas turbine. A noise enclosure is also 
NRF-238-PEMEX-2009F included for the gearbox. It is not required a noise enclosure for the 
GENERADOR DE ENERGIA ELECTRICA - Item 8.2.5 generator in order that the maximum overall GTG sound level is meet 
(85 dBa at 1,5 meters distance and 1,5 meters height).
NRF-238-PEMEX-2009F NRF-053-PEMEX-2006 is an embedded specification. We are offering
GENERADOR DE ENERGIA ELECTRICA - Item 8.2.6 our standard painting procedure.
Please refer to the Control system description as well as to the
NRF-238-PEMEX-2009F CONTROL SYSYEM POWER SUPPLY SCHEMATIC, UNIT CONTROL
GENERADOR DE ENERGIA ELECTRICA - Item 8.3 SYSTEM LAYOUT & MAIN EQUIPMENT LIST, CONTROL SYSTEM
SCHEMATIC attached to the technical proposal.
NRF‐238‐PEMEX‐2009F 
We understand Prototype tests are not applicable to the offered panel
GENERADOR DE ENERGIA ELECTRICA ‐ Item 8.4.2.2
NRF-238-PEMEX-2009F Please refer to the GE O&G commercial proposal for proposed site
GENERADOR DE ENERGIA ELECTRICA - Item 8.4.3 activities.
We are offering our standard export boxing for transportation only 
NRF-238-PEMEX-2009F
suitable for ocean freight. Our standard export boxing is not suitable for 
GENERADOR DE ENERGIA ELECTRICA - Item 8.5
storage. 
We are offering our standard submittal documentation package, as
follow: Motor outline drawing with overall weight and dimensions;
accessories schematic and wiring diagrams; main terminal box with
NRF-238-PEMEX-2009F
overall dimensions and details of internal arrangement; data sheet;
GENERADOR DE ENERGIA ELECTRICA - Item 8.6.2.2
performance curves; starting curves; thermal limit curves; nameplate
drawing; GE constructions, operation and maintenance manual. The data-
pack submittal date will be confirmed by the time of order

GE Oil & Gas


Pag. I.2.1/17
GE Proprietary & Confidential Information
NRF‐238‐PEMEX‐2009F 
For documentation exchanged during job execution, please refer to the 
GENERADOR DE ENERGIA ELECTRICA ‐ Item 8.6.2.2 a), b), g), h), 
VDR attached to GE O&G technical proposal.
i), t), u), w)

NRF‐238‐PEMEX‐2009F 
These information is stated on outline drawing
GENERADOR DE ENERGIA ELECTRICA ‐ Item 8.6.2.2 c), k), y)

NRF‐238‐PEMEX‐2009F 
These information is stated on generator manual
GENERADOR DE ENERGIA ELECTRICA ‐ Item 8.6.2.2 l)
NRF‐238‐PEMEX‐2009F 
These information is stated on generator data sheet
GENERADOR DE ENERGIA ELECTRICA ‐ Item 8.6.2.2 o)
Please refer to GE O&G technical and commercial proposal for spare
NRF‐238‐PEMEX‐2009F  parts and special tools that will be provided with the gas turbine
GENERADOR DE ENERGIA ELECTRICA ‐ Item 8.6.2.2 x) generator.
NRF-238-PEMEX-2009F
Services are not included in the scope of this proposal.
GENERADOR DE ENERGIA ELECTRICA - Item 8.7
Generators quoted with consideration of the NEMA MG‐1 and IEEE sdt 
NRF-238-PEMEX-2009F
112 standards only and spec AV‐EAG‐L‐ET‐W‐04 Rev. 1 with comments 
GENERADOR DE ENERGIA ELECTRICA - Item 10
stated on this BQF

Regarding API 670 requirement, bearing RTDs will be installed 180° 
CLARIFICATIONS TO API-546 SECOND EDITION apart, one at right side face the bearing and the other at left side.
General: It is the STD bearing housing configuration of the main market suppliers 
(RENK, ZOLLERN, etc.).

The machine and its electrical components will be suitable for the area
classification specified by the purchaser and will meet the requirements
of NFPA 70, Articles 500, 501, 502 and 505 (Class, Group, and Div.) or
CLARIFICATIONS TO API-546 SECOND EDITION IEC 79-1 (Zone, Group). Please furnish any applicable local codes or
Item 2.1.7 page 5: regulations for review. Approval of this machine for use in a hazardous
location can only be granted by the authority having jurisdiction. It is the
responsibility of the user/purchaser to obtain this approval.

Starting currents are related to the generator starting and pull-in torque
requirements and the net terminal voltage at the generator terminals.
CLARIFICATIONS TO API-546 SECOND EDITION Low inertia (WK2) low starting torque loads such as many centrifugal
Item 2.2.7.1 a page 8: pump applications have an inrush current at rated voltage estimated at
500 - 600% rated current for unity power generators and 400 - 500% for
0.8 power factor generators. Please inform load data.
We need to review angular position torque curve in order to confirm the
CLARIFICATIONS TO API-546 SECOND EDITION
maximum current pulsation or to inform the necessary additional inertia
Item 2.2.7.1 c page 8:
to meet this requirement.
Seismic loading: The Uniform Building Code does not define g forces for
machine design. Our machine design is based on NEMA
CLARIFICATIONS TO API-546 SECOND EDITION recommendation. Out-of-phase reclosing: We limit the resultant vectorial
Item 2.4.2.2 page 10: between the generator residual and the incoming source to 1.33 pu volts
per hertz (generator bases) per ANSI C50.41 item 15.

The rigid bearing critical speed of Custom 8000(R) Machines will be at


least 15% above the 60 Hz running speed. The assembled critical speed
CLARIFICATIONS TO API-546 SECOND EDITION
of Custom 8000(R) Machines may be below the 60 Hz running speed
Item 2.4.6.1.1 page 14:
due the reduced stiffness of the bearings (particularly sleeve
bearings), end shield, and foundation. Sleeve bearings provide damping
which reduces the amount of vibration at the critical speed.
CLARIFICATIONS TO API-546 SECOND EDITION GE can not confirm if this test is pratical at this stage, which will depend
Item 2.4.9.5 page 22 & 4.3.1.5 page 29: on the size of coupling. It will be confirmed during job execution.

CLARIFICATIONS TO API‐546  SECOND EDITION
Item 2.5.1.5:  Excitation field power is on purchaser scope of supply

CLARIFICATIONS TO API‐546  SECOND EDITION
Purchaser must supply a secure voltage source the excitation system 
Item 2.5.1.6: 
control.

GE Oil & Gas


Pag. I.2.1/18
GE Proprietary & Confidential Information
CLARIFICATIONS TO API‐546  SECOND EDITION
Item 2.5.2.2:  Cables will not be physically isolated from each other

CLARIFICATIONS TO API‐546  SECOND EDITION
We are considering secure voltage sources from purchaser panels and 
Item 2.5.2.5: 
thus surge protection is not required
CLARIFICATIONS TO API-546 SECOND EDITION
Switches minimum current capacity will be calculated according circuit 
Item 3.6.4.1 page 26:
current rate.
The exciter consists of an a-c generator with a revolving armature
mounted on the generator shaft and a stationary field. Direct current for
the exciter field is provided from the generator control or switchgear. The
output of the a-c exciter is converted to direct current by a shaft-mounted
rectifier. The field-protective function and the field shorting and
CLARIFICATIONS TO API-546 SECOND EDITION
application function are accomplished by the use of static switching. The
Item 3.6.4.1 page 26:
semi-conductor elements are mounted on heat sinks and are arranged
on the shaft in such a way that they are ventilated by the rotation of the
machine. The field discharge resistors, when required, are rotor-
mounted. The brushless excitation control system provided will be
commensurate with the generator characteristics and the torque
requirements.
CLARIFICATIONS TO API-546 SECOND EDITION
Non-contacting vibration probes will be mounted outboard of the bearing,
Item 3.8.1.1 page 26:
but not near a nodal point, due to machine construction characteristics.

CLARIFICATIONS TO API-546 SECOND EDITION We utilize only fillet welds on our frames (no structural welds are utilized)
Item 4.2.2.2 page 28: so a radiographic test has no meaning for acceptance of these welds.
Therefore we do not offer radiographic tests on frame welds.

Final inspection prior to shipment, if required, is the only hold point


included as a normal part of our proposal. Witnessing of tests may be
included as a customer option, for published price additions. No other
CLARIFICATIONS TO API-546 SECOND EDITION hold points, witness points, or inspection points are included for work in
Item 4.1.1/3 page 27 & 4.3.1.1 page 29: process. Any such points desired will be subjected to mutual agreement
and, depending on the nature of the inspection and work in process,
additional prices may be quoted to cover the necessary notifications,
personnel, special scheduling, and other extra factory activity involved.

Storage - Panel storage is on customer responsibility. Although the panel


Clarification
will be prepared and will come with instructions for properly storage.
PMG - The AVR require a 3 phase, 240V, 161-420Hz PMG. PMG power
Clarification
consumption to be defined.
Control Power Supply - The AVR AC input accepts voltage over the
range of 82 to 132 Vac at 50 or 60 hertz. The DC input accepts voltage
Clarification over the range of 90 to 150 Vdc. Any values out of the ranges herein
mentioned will be considered incompatible and is on customer
responsibility to provide proper voltage power supply.
Reference set point for plant p.f. regulation - We are not considering
General Clarification
reference set point for p.f. regulation in this proposal.
Tropicalized - We are not considering tropicalized parts/equipment.
General Clarification
Panels must be installed in acclimatized rooms.
AVR & protection functions - We are NOT considering in this proposal:
-Reference set point for p.f. regulation;
General Clarification -Excitation Voltage/Current 4-20mA output signals;
-Power system stabilizer;
-Over Excitation Protection by external relay.

General Clarification Special Tests - AVR will be tested only according GEVISA Test Plan.

Generators quoted with consideration of the NEMA MG‐1 and IEEE sdt 
112 standards only with the following comments and exceptions. Please 
AV‐EAG‐L‐ET‐W‐04 REV 1 ENG 
note, only the specifications expressly stated in this BQF clarification file 
TECHNICAL SPECIFICATION ‐ ELECTRIC TURBO GENERATORS ‐ 
have been considered applicable to the offered generators. Cross‐
General
referenced documents contained within these specifications have not 
been considered

GE Oil & Gas


Pag. I.2.1/19
GE Proprietary & Confidential Information
AV‐EAG‐L‐ET‐W‐04 REV 1 ENG  Please refer to GE O&G technical proposal for scope of supply that will 
TECHNICAL SPECIFICATION ‐ ELECTRIC TURBO GENERATORS ‐  be provided with the gas turbine generator, as well as to the comments 
Item 4.3 and exceptions attached to the technical proposal.

AV‐EAG‐L‐ET‐W‐04 REV 1 ENG  Please refer to GE O&G technical proposal for scope of supply that will 
TECHNICAL SPECIFICATION ‐ ELECTRIC TURBO GENERATORS ‐  be provided with the gas turbine generator, as well as to the comments 
Item 5.2.7 and exceptions attached to the technical proposal.

AV‐EAG‐L‐ET‐W‐04 REV 1 ENG 
GE is offering standard generator manufacturer painting procedure for 
TECHNICAL SPECIFICATION ‐ ELECTRIC TURBO GENERATORS ‐ 
corrosive environment.
Item 5.14
AV‐EAG‐L‐ET‐W‐04 REV 1 ENG 
Please refer to QCP attached to the technical proposal as well to the 
TECHNICAL SPECIFICATION ‐ ELECTRIC TURBO GENERATORS ‐ 
comments to customer specifications.
Item 6
GE is offering generator manufacturer standard export boxing for ocean 
AV‐EAG‐L‐ET‐W‐04 REV 1 ENG  freight, which is not suitable for storage. For further instruction please 
TECHNICAL SPECIFICATION ‐ ELECTRIC TURBO GENERATORS ‐  refer to the Receiving, Handling and Storage Instructions attached to this 
Item 7 proposal. If requested, we can provide export box suitable for storage as 
additional price
AV‐EAG‐L‐ET‐W‐04 REV 1 ENG 
Spare parts and special tools are offered as option through the GE O&G 
TECHNICAL SPECIFICATION ‐ ELECTRIC TURBO GENERATORS ‐ 
commercial proposal.
Item 9

Generators quoted with consideration of the NEMA MG‐1 and IEEE sdt 
112 standards only with the following comments and exceptions. Please 
note, only the specifications expressly stated in this BQF clarification file 
NRF‐048‐PEMEX‐2007 
have been considered applicable to the offered generators. Cross‐
DESIGN OF ELECTRICAL SYSTEMS ‐ General
referenced documents contained within these specifications have not 
been considered. Adder for API 546 compliant generator is offered as 
option.

NRF‐048‐PEMEX‐2007 
We understand only the item 8.3 is applicable to generator scope
DESIGN OF ELECTRICAL SYSTEMS ‐ General

Generators quoted with consideration of the NEMA MG‐1 and IEEE sdt 
112 standards only with the following comments and exceptions. Please 
NRF‐048‐PEMEX‐2007  note, only the specifications expressly stated in this BQF clarification file 
DESIGN OF ELECTRICAL SYSTEMS ‐ Item 8.3.2 have been considered applicable to the offered generators. Cross‐
referenced documents contained within these specifications have not 
been considered

NRF‐048‐PEMEX‐2007  We are offering generator characteristics according to customer 
DESIGN OF ELECTRICAL SYSTEMS ‐ Item 8.3.3 requirements

Please refer to GE O&G technical proposal for scope of supply that will 
NRF‐048‐PEMEX‐2007 
be provided with the gas turbine generator, as well as to the comments 
DESIGN OF ELECTRICAL SYSTEMS ‐ Item 8.3.4 and 8.3.5 
and exceptions attached to the technical proposal.

Specification NRF‐134‐PEMEX‐2012 will be not applicable to generator´s 
NRF‐134‐PEMEX‐2012 
heat exchanger (the construction method described on this spec is very 
CAMBIADORES DE CALOR ENFRIADOS POR AIRE ‐ General
complex, different from generator’s manufacturer air‐air heat exchanger

NRF‐146‐PEMEX‐2011  We understand this specification is not applicable to generator scope of 
TABLEROS DE DISTRIBUCION EN MEDIA TENSION ‐ General supply.

GE Oil & Gas


Pag. I.2.1/20
GE Proprietary & Confidential Information
GE Oil & Gas

Exceptions to Intl. Stand

GE Oil & Gas


Pag. I.3
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. I.3.1/1
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. I.3.1/2
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. I.3.1/3
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. I.3.1/4
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. I.3.1/5
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. I.3.1/6
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. I.3.1/7
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. I.3.1/8
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. I.3.1/9
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. I.3.1/10
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. I.3.1/11
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. I.3.2/1
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. I.3.2/2
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. I.3.2/3
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. I.3.2/4
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. I.3.2/5
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. I.3.2/6
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. I.3.2/7
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. I.3.2/8
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. I.3.2/9
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. I.3.2/10
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. I.3.2/11
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. I.3.2/12
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. I.3.2/13
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. I.3.2/14
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. I.3.2/15
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. I.3.2/16
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. I.3.2/17
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. I.3.2/18
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. I.3.2/19
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. I.3.2/20
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. I.3.2/21
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. I.3.2/22
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. I.3.2/23
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. I.3.2/24
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. I.3.2/25
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. I.3.3/1
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. I.3.3/2
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. I.3.3/3
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. I.3.3/4
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. I.3.3/5
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. I.3.3/6
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. I.3.3/7
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. I.3.3/8
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. I.3.4/1
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. I.3.4/2
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. I.3.4/3
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. I.3.4/4
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. I.3.4/5
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. I.3.4/6
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. I.3.5/1
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. I.3.5/2
GE Proprietary & Confidential Information
GE Oil & Gas
Pag. I.3.5/3
GE Proprietary & Confidential Information
GE Oil & Gas

CHAPTER J

Quality

GE Oil & Gas


Pag. J
GE Proprietary & Confidential Information
GE Oil & Gas

Quality Control Plans

GE Oil & Gas


Pag. J.1
GE Proprietary & Confidential Information
GE O&G NUOVO PIGNONE Std. QUALITY CONTROL PLAN
FOR
TURBO-GENERATOR TRAIN
GT (Heavy Duty Type) + GENERATOR

Updated May 2013

GE Oil & Gas


Pag. J.1.1/1
GE Proprietary & Confidential Information
INTRODUCTION NOTES

PURPOSE

This document (Quality Control Plan) summarizes the Tests and Inspections done within the manufacturing stages of the GE O&G Nuovo Pignone Products(s) in subject
with an associated certificate according to EN 10204. Site Tests/Activities (if any) are not in the scope of this QCP.

Quality Control Plan is the reference document for:

 Define the quality documentation to be given to GE O&G Nuovo Pignone Customer (or his Contractor Company/EPC) as Manufacturer Data Report (MDR). MDR
Format (covers, index and contents), will be issued in according to GENP procedure MFG-WI-033.
 List of test associated documentation (Reference Doc., Procedure and Acceptance).
 Define the Customer Inspector(s) level of participation associated to each testing (Review, Observed, Witness). See also following “Inspection Activities” section.

Pages on this Quality Control Plan are identified through description/nomenclature of the component(s). This description/nomenclature conforms as much as possible to
API Standards definitions.

This Quality Control Plan will be sent for Customer approval via Vendor Document Register (VDR).

It is understood that all Quality, Design, Manufacturing, Installation and Service activities will withstand on an ISO 9001 Quality Management System.

In case of conflict, following order of precedence shall be considered (first listed will lead):

 Contractual Documents, including Data Sheets (with agreed comments, if any)


 GE O&G Design Review
 GE O&G Internal Specifications
 This Quality Control Plan

PRE INSPECTION MEETING (PIM)

Since this Quality Control Plan lists both GE O&G Nuovo Pignone standard tests and inspections as well as project specific ones, it is GE O&G Nuovo Pignone responsibility
to issue the Quality Control Plan taking account of this. This issue will be officially discussed and shared with Customer at Pre Inspection Meeting and/or via VDR (Vendor
Document register). A preliminary copy of this document can be supplied to Customer before PIM (when PIM is scheduled).

Note that in case a dedicated Quality Control Plan for a sub item is issued (typically for Electric Main drivers, Main Gear Box, etc.), at Pre Inspection Meeting it will be also
agreed how to integrate this Quality Control Plan and the Sub Item Quality Control Plan(s).

GE Oil & Gas


Pag. J.1.1/2
GE Proprietary & Confidential Information
INSPECTOR(S) ACTIVITIES

According to contractual documentation (including M.o.M.), each test will specify the level of participation of following parties:

 GE O&G Nuovo Pignone Inspector or its representative


 Customer Inspector(s) or its representative
 Third Party Inspector(s) (if any)
 End User Inspector(s) or its representative

According to API Standards, for each Party above, the following Level of Participation are possible:

 Review “R”:

Purchaser will perform a Documentation Review of the inspection or test.

 Observed “O”:

Purchaser is notified of the timing of the inspection or test and the inspection or test is performed as scheduled, regardless of whether the Purchaser or his
representative is present

 Witnessed “W”:

Purchaser is notified of the timing of the inspection or test and a hold is placed on the inspection or test until the Purchaser or his representative is in attendance. In case
of non-attendance of Purchaser or his representative, a formal notification shall be notified (in written) to GE O&G Nuovo Pignone by Purchaser or his representative.

 Approval “A”

QCP test may be integrated with the “A” tag. This is the Purchaser approval request of the quality documentation in subject that has to be done before the relevant
manufacturing stages begin.

REMOTE WITNESSING

For some running tests and rotor balancing tests, when available and upon agreement, on-line (using internet connection) Customer remote witnessing of testing can be
considered substitutive of Inspector(s) physical presence.

GE Oil & Gas


Pag. J.1.1/3
GE Proprietary & Confidential Information
MATERIAL TRACEABILITY

Material Identification for Traceability to be according to ITN07038.

CERTIFICATION

In the Manufacturer Data Report (MDR) will be contained all certificates listed in the column “Cert. Type” of this document. Each test will be associated with a certification
according to EN 10204 ed.2004 (ITN07771 is the equivalent Nuovo Pignone document used for the extents of this Quality Control Plan). According to ITN07771, type of
certificates can be:

 2.1 type: Manufacturer statement of compliance with the order.


 2.2 type: Manufacturer statement of compliance with the order based on results of a non-specific inspection/test(s).
 3.1 type: The same as “2.1 Certificate” with the following minimum additions: the indication of results (e.g. numeric) of the specific inspection/test(s), the univocal
ID of part(s) (e.g. Serial Number).
 3.2 type: The same as “3.1 Certificate”, co-issued with the Purchaser inspector, or its Representative, or a designated Third Party.

REFERENCE DOCUMENTATION

If not otherwise agreed, all NP/GE referenced documentation called out in this Quality Control Plan, when not part of VDR, cannot be disclosed in any form because of
Intellectual Propriety (ref. To NP/GE “Technical Documents Security” OTR-EN-11-F-PLANT-02). This referenced documentation include: procedures, documents for
acceptance criteria and all others documents in this Quality Control Plan.

In order to allow Customers to be aware of the contents of this referenced documentation, consider the following scenarios:

 Upon request, these documents may be shown to Customer during PIM.


 These documents will be present hardcopy in integral form for consultation at each test premises where a test will have place (at each test premises will be
available applicable documentation concerning only that test).

All certificate originate from this Quality Control Plan, has to contain the actual / positive reference to the relevant documentation (including its revision) that has been
used for the test itself.

CAPITAL SPARE PARTS

When/if capital spare parts are supplied within the Scope of Supply, it is understood that these spares will have the same level of inspections than the main parts (unless
not applicable).

GE Oil & Gas


Pag. J.1.1/4
GE Proprietary & Confidential Information
STRING TEST (INSPECTOR TRAVEL AND LIVING), WHERE APPLICABLE

Where string test(s) is applicable, consider that, due to its specific nature, the availability of Customer Inspector(s) shall cover all necessary time to complete the test
(typically 7 consecutive days for 24 hours/day).

In this case, after receiving the string test advance notification request, before Customer Inspector(s) booking arrangement will be done (travel ticketing and hotel
reservation), Customer shall ask Nuovo Pignone for an additional confirmation.

CUSTOMER NOTIFICATION ABOUT OCCURRED NON-CONFORMANCES

When a test, which is listed in this Quality Control Plan, will origin a non-conformance, if no more stringent clauses are agreed into the Contract (including M.o.M.(s)),
following policies will apply:

 MFG-WI-015 “Management of nonconformities in manufacturing phase” (this includes “Std. Repair Cycles”)
 ITM01200 “Customer notification about the occurred non-conformance (for Gas Turbines)”

Above documents define the Customer Notifications about occurred non-conformances. Note that these documents are mainly based on:

 Contractual API Standards. for Main Rotating Machines


 ASTM/ASME Requirements of materials as applicable

STANDARD REPAIR PROCEDURES

GE O&G Nuovo Pignone Engineering has consolidated standard repair procedures to be used by manufacturing to perform repair(s) without prior engineering approval.
The relevant defects categories and application range are listed in the following documents:

 ITN07762 “Standard repair procedure for Gas Turbines”

The certificates originated by this Quality Control Plan shall be in English language.

The certificates originated by this Quality Control Plan shall use the S.I. (International System of Units according to ISO/IEC 80000)

OBSERVED OR WITNESSED TESTS SHALL HAVE FOLLOWING ADVANCE NOTIFICATION TIME:


 Observed tests: 14 calendar days in advance
 Witnessed tests: 14 calendar days in advance

GE Oil & Gas


Pag. J.1.1/5
GE Proprietary & Confidential Information
Legend:

Prog Print + Particolare + Parte + Prog Parte —> Test 11dgt ID number. Prog Print “01” means Gas Turbine F/F.
Prog Print “05” means Auxiliares.
Prog Print “06” and “12” means Electrical System and Electronic System.
Prog Print “07” means Final Check on Main Skid.

Name + Formal note —> Test name/description.


Reference Docs + Procedure + Acceptance —> Test reference documentation.
Certification Type —> How the test will be certified according to EN 10204 (ITN07771).
O&G/Customer Activity —> NP GE O&G and Customer participation level according to API definition.

Customer_Activity
Certification_Type
Reference_Docs

O&G_Activity
formal_note

Acceptance
Prog_Parte
Particolare
Prog_Print

Procedure
MACHINE

Name
Parte

GT 01 0005 00 000 INLET PLENUM


01 0005 02 000 RAW
01 0005 02 002 LADLE ANALYSIS FOR MAIN COMPONENT ONLY ITN02199.01 MAT STD MAT STD 2.1 R R
01 0005 02 004 MECHANICAL PROPERTIES FOR MAIN COMPONENT ONLY ITN02199.01 MAT STD MAT STD 2.1 R R
01 0005 04 000 FABRICATED / ASSEMBLED
01 0005 04 010 INSPECTION OF WELDS INCLUDING LIFTING POINTS ITN02199.01 ITN03402.03 ITN03402.03 3.1 O R
2.1 CERTIFICATION WILL BE
ISSUED - ON A SPOT CHECK BASIS
01 0005 04 012 DIMENSIONAL CHECK CUSTOMER CAN ASK TO REVIEW ITN02199.01 ITN02199.01 / ITN04001 DWG 2.1 O R
THE RELEVANT MFR. INTERNAL
RECORDS
01 0005 04 016 CLEANLINESS CHECK ITN02199.01 ITN02199.01 / ITN04001 ITN02199.01 / ITN04001 3.1 O R
INCLUDING THE INSPECTION OF
01 0005 04 020 FINAL AND VISUAL CHECK ITN02199.01 ITN02199.01 / ITN04001 ITN02199.01 / ITN04001 2.1 O R
DOCUMENTATION
GT 01 0010 00 000 EXHAUST PLENUM
01 0010 02 000 RAW
01 0010 02 002 LADLE ANALYSIS FOR MAIN COMPONENT ONLY ITN02199.02 MAT STD MAT STD 2.1 R R
01 0010 02 004 MECHANICAL PROPERTIES FOR MAIN COMPONENT ONLY ITN02199.02 MAT STD MAT STD 2.1 R R
01 0010 04 000 FABRICATED / ASSEMBLED
01 0010 04 010 INSPECTION OF WELDS ITN02199.02 ITN03402.03 ITN03402.03 3.1 O R
2.1 CERTIFICATION WILL BE
ISSUED - ON A SPOT CHECK BASIS
01 0010 04 012 DIMENSIONAL CHECK CUSTOMER CAN ASK TO REVIEW ITN02199.02 ITN02199.02 / ITN04001 DWG 2.1 O R
THE RELEVANT MFR. INTERNAL
RECORDS
INCLUDING THE INSPECTION OF
01 0010 04 020 FINAL AND VISUAL CHECK ITN02199.02 ITN02199.02 / ITN04001 ITN02199.02 / ITN04001 2.1 O R
DOCUMENTATION
GT 01 0030 00 000 INLET CASING

GE Oil & Gas


Pag. J.1.1/6
GE Proprietary & Confidential Information
01 0030 02 000 RAW
01 0030 02 002 LADLE ANALYSIS ITN07761.27 ASTM E350 ITN07761.09 3.1 R R
01 0030 02 004 MECHANICAL PROPERTIES ITN07761.27 ASTM A370 ITN07761.09 3.1 R R
01 0030 02 006 MAGNETIC PARTICLE TEST ITN07761.27 ITN02158 ITN07761.09 3.1 R R
01 0030 02 010 ULTRASONIC TEST ITN07761.27 ITN07770.36 ITN07761.09 3.1 R R
01 0030 02 012 RADIOGRAPHIC EXAMINATION ITN07761.27 ITN02196 ITN07761.09 3.1 R R
GT 01 0065 00 000 AXIAL COMPRESSOR CASING
01 0065 02 000 RAW
01 0065 02 002 LADLE ANALYSIS ITN07761.27 ASTM E350 ITN07761.09 3.1 R R
01 0065 02 004 MECHANICAL PROPERTIES ITN07761.27 ASTM A370 ITN07761.09 3.1 R R
01 0065 02 006 MAGNETIC PARTICLE TEST ITN07761.27 ITN02158 ITN07761.09 3.1 R R
01 0065 02 010 ULTRASONIC TEST ITN07761.27 ITN07770.36 ITN07761.09 3.1 R R
01 0065 02 012 RADIOGRAPHIC EXAMINATION ITN07761.27 ITN02196 ITN07761.09 3.1 R R
GT 01 0100 00 000 AXIAL COMPRESSOR DISCHARGE CASING
01 0100 02 000 RAW
01 0100 02 002 LADLE ANALYSIS ITN07761 ASTM E350 ITN07761 3.1 R R
01 0100 02 004 MECHANICAL PROPERTIES ITN07761 ASTM A370 ITN07761 3.1 R R
01 0100 02 006 MAGNETIC PARTICLE TEST ITN07761 ITN02158 ITN07761 3.1 R R
ITN07770.36 / ITN02141
01 0100 02 010 ULTRASONIC TEST / RADIOGRAPHIC EXAMINATION ITN07761 / ITN07761.08 / ITN07761 3.1 R R
ITN02196
GT 01 0120 00 000 TURBINE CASING
01 0120 02 000 RAW
01 0120 02 002 LADLE ANALYSIS ITN07761 ASTM E350 ITN07761 3.1 R R
01 0120 02 004 MECHANICAL PROPERTIES ITN07761 ASTM A370 ITN07761 3.1 R R
01 0120 02 008 MAGNETIC PARTICLE TEST ITN07761 ITN02158 ITN07761 / ITN02158 3.1 R R
GT 01 0215 00 000 TURBINE EXHAUST CASING
01 0215 02 000 RAW
ITN07761 / ITN11725 /
SMO0619299 / ITN07761 / ASTM STD /
01 0215 02 002 LADLE ANALYSIS ASTM E350 / ASTM STD 3.1 R R
SMO0619300 / ITN11725
SMO0619301
ITN07761 / ITN11725 /
SMO0619299 / ITN07761 / ASTM STD /
01 0215 02 004 MECHANICAL PROPERTIES ASTM E350 / ASTM STD 3.1 R R
SMO0619300 / ITN11725
SMO0619301
GT 01 0260 00 000 COMBUSTION CHAMBER CASING (WRAPPER)
01 0260 02 000 RAW
01 0260 02 002 LADLE ANALYSIS DWG ASTM STD A516 Gr.60 2.1 R R
01 0260 02 004 MECHANICAL PROPERTIES DWG ASTM STD A516 Gr.60 2.1 R R
01 0260 04 000 MACHINED
01 0260 04 002 NON DESTRUCTIVE EXAMINATIONS ON WELDS DWG ITN07770.10 DWG 2.1 R R
GT 01 0270 00 000 COMBUSTION CHAMBER CAP & LINER
01 0270 02 000 RAW
01 0270 02 002 LADLE ANALYSIS ITN07769.03 ASTM E354 ITN07769.03 3.1 R R
01 0270 02 004 MECHANICAL PROPERTIES ITN07769.03 ASTM E139 ITN07769.03 3.1 R R
01 0270 04 000 COMPOSED / ASSEMBLED
01 0270 04 006 FLUORESCENT DYE PENETRANT TEST ON WELDS ITN07769.23 ITN02192 ITN07769.23 3.1 R R
GT 01 0330 00 000 TRANSITION PIECE
01 0330 02 000 RAW

GE Oil & Gas


Pag. J.1.1/7
GE Proprietary & Confidential Information
01 0330 02 002 LADLE ANALYSIS ITN07769 ASTM STD ITN07769 3.1 R R
01 0330 02 004 MECHANICAL PROPERTIES ITN07769 ASTM STD ITN07769 3.1 R R
01 0330 06 000 MACHINED
01 0330 06 008 FLUORESCENT DYE PENETRANT TEST ITN07769 ITN02192 ITN07769 3.1 R R
2.1 CERTIFICATION WILL BE
ISSUED - ON A SPOT CHECK BASIS
01 0330 06 010 DIMENSIONAL CHECK CUSTOMER CAN ASK TO REVIEW ITN07769 STD. MFR. DWG 2.1 R R
THE RELEVANT MFR. INTERNAL
RECORDS
ITN07769 / ITN07040
01 0330 06 012 VISUAL INSPECTION ITN07769 ITN07040 2.1 R R
CL.0
STUBS AND WHEELS (HIGH PRESSURE ROTOR / ROTOR
GT 01 0667 00 000
CPRS. STACK ASSEMBLY)
01 0667 02 000 RAW
B50A368E / B50A368E / B50A420B10
01 0667 02 002 LADLE ANALYSIS MAT. STD. / ASTM E350 3.1 R R
B50A420B10 / ITN07763 / ITN07763
B50A368E / MAT. STD. / ASTM A370 B50A368E / B50A420B10
01 0667 02 006 MECHANICAL PROPERTIES B50A420B10 / ITN07763 / ASTM E292 / ITN07763 3.1 R R
01 0667 02 010 ULTRASONIC TEST P29A-AG215 / ITN07763 P29A-AG215 / ITN02151 P29A-AG215 / ITN07763 3.1 R R
TURBINE WHEEL (1st. AND 2nd. STG. / HIGH PRESSURE
GT 01 0668 00 000
ROTOR)
01 0668 02 000 RAW
01 0668 02 002 LADLE ANALYSIS B50A565A / B50A368 MAT. STD. B50A565A / B50A368 3.1 R R
01 0668 02 006 MECHANICAL PROPERTIES B50A565A / B50A368 MAT. STD. B50A565A / B50A368 3.1 R R
01 0668 02 010 ULTRASONIC TEST P3B-AG10 / P29A-AG212 P29A-AG212 P29A-AG212 3.1 R R
GT 01 0670 00 000 ROTOR / HIGH PRESSURE ROTOR
01 0670 04 000 ASSEMBLED
SOM33262, SOM15479 / SOM33262, SOM15479 / SOM33262, SOM15479 /
01 0670 04 002 DYNAMIC BALANCING (AT LOW SPEED) SOM15647 / SOM63300 SOM15647 / SOM63300 SOM15647 / SOM63300 3.1 W R
/ SOM6674690 / SOM6674690 / SOM6674690
INCLUDING RESIDUAL
01 0670 04 004 COMBINED RUN OUT TEST (ON PROBES TARGET AREAS) ITN02183 ITN02183 ITN02183 3.1 W R
MAGNETISM CHECK
01 0670 08 000 HIGH SPEED BALANCING if applicable
01 0670 08 004 HIGH SPEED BALANCING CHECK JOB SPEC JOB SPEC JOB SPEC 3.1 W O
01 0670 08 012 LOW SPEED BALANCING CHECK AFTER HSB JOB SPEC JOB SPEC INFO ONLY 3.1 W O
GT 01 0677 00 000 SHAFT (LOW PRESSURE ROTOR) Only for 2-Stages GT
01 0677 02 000 RAW
01 0677 02 002 LADLE ANALYSIS B50A420B10 / ITN07763 MAT. STD. / ASTM E350 B50A420B10 / ITN07763 3.1 R R
01 0677 02 006 MECHANICAL PROPERTIES B50A420B10 / ITN07763 MAT. STD. / ASTM E370 B50A420B10 / ITN07763 3.1 R R
01 0677 02 010 ULTRASONIC TEST P29A-AG215 / ITN07763 P29A-AG215 / ITN02151 P29A-AG215 / ITN07763 3.1 R R
TURBINE WHEELS (1st. AND 2nd. STG. - LOW PRESSURE
GT 01 0678 00 000 Only for 2-Stages GT
ROTOR)
01 0678 02 000 RAW
01 0678 02 002 LADLE ANALYSIS B50A565A / ITN07763 MAT STD / ASTM E350 B50A565A / ITN07763 3.1 R R
MAT STD / ASTM A370 /
01 0678 02 006 MECHANICAL PROPERTIES B50A565A / ITN07763 B50A565A / ITN07763 3.1 R R
ASTM E21 / ASTM E292
01 0678 02 10 ULTRASONIC TEST P29A-AG212 / ITN07763 P29A-AG212 / ITN02151 P29A-AG212 / ITN07763 3.1 R R
GT 01 0680 00 000 LOW PRESSURE ROTOR Only for 2-Stages GT
01 0680 04 000 ASSEMBLED
01 0680 04 002 DYNAMIC BALANCING (AT LOW SPEED) SOM15648 / SOM65762 SOM15648 / SOM65762 SOM15648 / SOM65762 3.1 W R
01 0680 04 004 COMBINED RUN OUT TEST (ON PROBES TARGET AREAS) INCLUDING RESIDUAL ITN02183 ITN02183 ITN02183 3.1 W R

GE Oil & Gas


Pag. J.1.1/8
GE Proprietary & Confidential Information
MAGNETISM CHECK
GT 01 0760 00 000 GAS TURBINE
01 0760 16 000 ASSEMBLED
01 0760 16 002 NO LOAD MECHANICAL RUNNING TEST SOM27553 / JOB SPEC. SOM27553 / JOB SPEC. SOM27553 / JOB SPEC. 3.1 W W
OFF-
SKID 05 0005 00 000 LOAD COUPLINGS
05 0005 02 000 RAW
ON ALL TORQUE TRANSMITTING
05 0005 02 002 LADLE ANALYSIS API671 MAT STD MAT STD 3.1 R R
COMPONENTS
ON ALL TORQUE TRANSMITTING
05 0005 02 004 MECHANICAL PROPERTIES API671 MAT STD MAT STD 3.1 R R
COMPONENTS
ON ALL TORQUE TRANSMITTING
05 0005 02 008 NON DESTRUCTIVE EXAMINATIONS API671 ASME V ASME VIII 3.1 R R
COMPONENTS
05 0005 04 000 MACHINED / ASSEMBLED
05 0005 04 006 NON DESTRUCTIVE EXAMINATIONS ON MACHINED PARTS API671 ASME V / MFR STD API671 / ASME VIII 3.1 R R
05 0005 04 016 COMPONENTS BALANCE WITH ASSEMBLY BALANCE JOB SPEC. API671 API671 3.1 O R
05 0005 04 022 UNBALANCE REPEATABILITY CHECK JOB SPEC. API671 API671 3.1 O R
ON INTERFACE DIMENSIONS TO
05 0005 04 024 INTERFACE DIMENSIONAL CHECK DWG MFR STD DWG 3.1 O R
GENP MACHINES
OFF-
SKID 05 0010 00 000 AUXILIARY COUPLING
05 0010 02 000 RAW
05 0010 02 002 LADLE ANALYSIS ON MAIN COMPONENTS MAT STD MAT STD MAT STD 2.1 R R
05 0010 02 004 MECHANICAL PROPERTIES ON MAIN COMPONENTS MAT STD MAT STD MAT STD 2.1 R R
05 0010 04 000 MACHINED / ASSEMBLED
INCLUDING CHECK OF MATCH
05 0010 04 004 BALANCING CHECK DWG API 671 API 671 3.1 R R
MARKING
ACCORDING TO VENDOR PRINT
OFF- SCHEDULE, THIS PAGE WILL BE
05 0020 00 000 LOAD GEAR BOX
SKID REPLACED BY SUPPLIER QCP
REFERENCE
05 0020 02 000 RAW
ON CASING, PINION, BULL GEAR,
05 0020 02 002 LADLE ANALYSIS SHAFTS AND INTERNAL/EXTERNAL MAT STD MAT STD MAT STD 3.1 R R
PIPING (IF PRESENT)
ON CASING, PINION, BULL GEAR,
05 0020 02 004 MECHANICAL PROPERTIES SHAFTS AND INTERNAL/EXTERNAL MAT STD MAT STD MAT STD 3.1 R R
PIPING (IF PRESENT)
05 0020 02 006 NON DESTRUCTIVE EXAMINATIONS MAT STD MAT STD MAT STD 3.1 R R
05 0020 04 000 MACHINED WHEEL AND PINION
05 0020 04 002 HARDNESS TEST ON TOOTH MFR STD MFR STD MFR STD 3.1 R R
05 0020 04 004 ULTRASONIC TEST API 613 MFR STD MFR STD 3.1 R R
05 0020 04 006 BALANCING CHECK API 613 MFR STD API 613 3.1 R R
05 0020 08 000 ASSEMBLED
05 0020 08 004 TAPE LIFT CONTACT CHECK DWG MFR STD DWG 3.1 O R
WITH JOB PROBES AND SHOP
05 0020 08 014 MECHANICAL RUNNING TEST API 613 JOB SPEC API 613 3.1 W O
LUBE OIL SYSTEM
WITH JOB PROBES AND SHOP
05 0020 08 016 MECHANICAL RUNNING TEST LUBE OIL SYSTEM - ON SPARE API 613 JOB SPEC API 613 3.1 W O
GEAR SET
05 0020 08 020 OIL INLET RANGE TEST API 613 JOB SPEC API 613 3.1 W O

GE Oil & Gas


Pag. J.1.1/9
GE Proprietary & Confidential Information
05 0020 08 022 OIL SYSTEM, CASING JOINT AND SHAFT SEALS TIGHTNESS API 613 JOB SPEC API 613 2.1 W O
05 0020 08 030 NOISE EMISSION TEST API 613 MFR STD JOB SPEC 3.1 W O
05 0020 08 032 UNBALANCE VERIFICATION TEST API 613 JOB SPEC JOB SPEC 3.1 W O
AFTER MRT (N/A to EPICYCLOIDAL
05 0020 08 040 TOOTH MESH CONTACT CHECK API 613 MFR STD DWG 3.1 W O
GEARS)
AFTER MRT (N/A to EPICYCLOIDAL
05 0020 08 042 BEARINGS INSPECTION API 613 MFR STD API 613 2.1 W O
GEARS)
05 0020 09 000 INSTRUMENT, ELECTRICAL AND PAINTING CHECK
05 0020 09 002 PAINTING CHECK JOB PAINTING SPEC. ITN07791 / ITN04001 JOB PAINTING SPEC. 3.1 W O
P&Id, WIRING DIA., P&Id, WIRING DIA.,
05 0020 09 004 INSTRUMENT INSTALLATION CHECK (INCLUDING TAGGING) ELECTRICAL HOOK-UP ITN04001 ELECTRICAL HOOK-UP 2.1 W O
05 0020 12 000 FINAL
DIMENSIONAL CHECK ON LIMIT OF ASSEMBLY DWG. /
05 0020 12 002 ITN04001 ASSEMBLY DWG. 3.1 W O
SUPPLY/INTERFACES/CONNECTIONS/TERMINAL POINTS SUPPL. CHECK LIST
THIS ALSO INCLUDES THE REVIEW DWG / SUPPL. CHECK
05 0020 12 004 FINAL VISUAL CHECK ITN04001 JOB DOC. 2.1 W O
OF SUPPLIER DOCUMENTATION LIST
OFF-
SKID 05 0025 00 000 AUXILIARY GEAR BOX
05 0025 02 000 RAW
05 0025 02 002 LADLE ANALYSIS (FOR MAIN COMPONENT ONLY) MAT STD MAT STD MAT STD 2.1 R R
05 0025 02 004 MECHANICAL PROPERTIES (FOR MAIN COMPONENT ONLY) MAT STD MAT STD MAT STD 2.1 R R
05 0025 06 000 ASSEMBLED
05 0025 06 002 MECHANICAL RUNNING TEST JOB PROCEDURE JOB PROCEDURE JOB PROCEDURE 3.1 O O
DIMENSIONAL CHECK ON LIMIT OF
05 0025 06 010 ASSEMBLY DWG. ITN04001 ASSEMBLY DWG. 2.1 O R
SUPPLY/INTERFACES/CONNECTIONS/TERMINAL POINTS
THIS ALSO INCLUDES THE REVIEW
05 0025 06 012 FINAL AND VISUAL CHECK ITN04001 ITN04001 ITN04001 2.1 O R
OF SUPPLIER DOCUMENTATION
OFF-
SKID 05 0050 00 000 PIPING
05 0050 02 000 RAW / MATERIAL CERTIFICATES OF PIPING COMPONENTS
JOB SPEC. / PIPING LINE
05 0050 02 002 LADLE ANALYSIS MAT STD MAT STD 2.1 R R
SPECIFICATION
JOB SPEC. / PIPING LINE
05 0050 02 004 MECHANICAL PROPERTIES MAT STD MAT STD 2.1 R R
SPECIFICATION
05 0050 04 000 ASSEMBLED / WELDED PIPING
ONLY FOR PIPING BELONGING TO
WELDING MAP (WM), WELD. PROC. SPECIFICATIONS (WPS)
05 0050 04 002 CLASS 1ST. and 2ND. OF PIPING ASME IX ASME IX ASME IX 2.1 A R
AND PROCEDURE QUALIF. REC. (PQR)
LINE SPECIFICATION
ASME V / ITN02196 (RX),
PIPING LINE ITN07039 (UT), PIPING LINE
05 0050 04 008 NDT ON WELDINGS 3.1 O R
SPECIFICATION ITN02119 (MP), SPECIFICATION
ITN02192 (PT)
2.1 WATER QUALITY ANALYSIS PIPING LINE
05 0050 04 014 HYDROSTATIC PRESSURE TEST ITN07021 ITN07021 3.1 O R
CERTIFICATE TO BE ATTACHED SPECIFICATION
05 0050 04 030 STAINLESS STEEL PICKLING & PASSIVATION CHECK ITN02136 ITN02136 ITN02136 2.1 R R
05 0050 04 034 PAINTING CHECK (WHERE APPLICABLE) PAINTING SPEC. ITN07791 / ITN04001 PAINTING SPEC 3.1 O R
FINAL, VISUAL INSPECTION (THIS INCLUDES CLEANLINESS
05 0050 04 038 ITN03401 ITN04001 ITN03401 2.1 O R
CHECK)
WELDS PERFORMED DURING
05 0050 06 000 ON-SKID ASSEMBLING WELDING
MECHANICAL SKID ASSEMBLY

GE Oil & Gas


Pag. J.1.1/10
GE Proprietary & Confidential Information
ONLY FOR PIPING BELONGING TO
WELDING MAP (WM), WELD. PROC. SPECIFICATIONS (WPS)
05 0050 06 002 CLASS 1ST. and 2ND. OF PIPING ASME IX ASME IX ASME IX 2.1 A R
AND PROCEDURE QUALIF. REC. (PQR)
LINE SPECIFICATION
ASME V / ITN02196 (RX),
PIPING LINE ITN07039 (UT), PIPING LINE
05 0050 06 006 NDT ON WELDINGS 3.1 O R
SPECIFICATION ITN02119 (MP), SPECIFICATION
ITN02192 (PT)
2.1 WATER QUALITY ANALYSIS PIPING LINE
05 0050 06 008 HYDROSTATIC PRESSURE TEST ITN07021 ITN07021 3.1 O R
CERTIFICATE TO BE ATTACHED SPECIFICATION / DWG
05 0050 06 012 MECHANICAL MANUAL CLEANING MFR STD MFR STD MFR STD 2.1 O R
FINAL, VISUAL INSPECTION (THIS INCLUDES CLEANLINESS
05 0050 06 014 ITN03401 ITN04001 ITN03401 2.1 W R
CHECK)
OFF- BETWEEN GT STARTING MOTOR
05 0055 00 000 TORQUE CONVERTER
SKID AND CLUTCH
05 0055 02 000 RAW / MATERIAL CERTIFICATES
FOR MAIN ROTATING PARTS AND
05 0055 02 002 MATERIAL CERTIFICATES ITM40102 MAT STD MAT STD 2.1 R R
PRESSURE RETAINING PARTS
05 0055 04 000 ASSEMBLED
INCLUDING: LEAK TEST, NOISE
05 0055 04 004 PERFORMANCE TEST (MRT) EMISSIONS CHECH AND SMOOTH ITM40102 STD. MFR. STD. MFR. 3.1 O R
RUN
05 0055 04 006 DIMENSIONAL CHECK ITM40102 STD. MFR. DWG 2.1 R R
05 0055 04 008 PAINTING CHECK ITM40102 STD. MFR. STD. MFR. 2.1 R R
05 0055 04 018 FINAL AND VISUAL CHECK ITM40102 STD. MFR. STD. MFR. 2.1 R R
OFF- BETWEEN GT TORQUE
05 0057 00 000 CLUTCH
SKID CONVERTER AND AUX GEAR
05 0057 02 000 RAW / MATERIAL CERTIFICATES
05 0057 02 002 MATERIAL CERTIFICATES FOR MAIN ROTATING PARTS ITM40101 MAT STD MAT STD 2.1 R R
05 0057 02 004 HARDNESS TEST ON CLUTCH TEETH ITM40101 MAT STD MAT STD 2.1 R R
05 0057 04 000 ASSEMBLED
05 0057 04 004 BALANCING CHECK FOR MAIN ROTATING PARTS ITM40101 STD. MFR. STD. MFR. 2.1 R R
OFF-
SKID 05 0060 00 000 STARTING MEANS: EXPANSION TURBINE
05 0060 02 000 RAW
05 0060 02 004 LADLE ANALYSIS (FOR MAIN COMPONENT ONLY) SOM30869 MAT STD MAT STD 2.1 R R
05 0060 02 006 MECHANICAL PROPERTIES (FOR MAIN COMPONENT ONLY) SOM30869 MAT STD MAT STD 2.1 R R
05 0060 04 000 MACHINED
ACCORDING TO
05 0060 04 002 HYDROSTATIC PRESSURE TEST MFR STD MFR STD 3.1 R R
APPLICABLE CODE
05 0060 06 000 ASSEMBLED
05 0060 06 002 MECHANICAL RUNNING TEST SOM30869 MFR STD MFR STD 3.1 R R
05 0060 06 006 FINAL, VISUAL AND DIMENSIONAL CHECK DWG COMMON PRACTICE ITN04001 3.1 R R
CROSS CHECK AT MFR. PREMISES,
05 0060 06 008 COMPLETENESS THREE WAY CHECK BEFORE SHIPMENT, AMONG: LISL, DWG / LISL ITN07068.00 ITN07068.00 PAR. 7.a 2.1 W R
DWG AND MATERIAL
OFF-
SKID 05 0065 00 000 STARTING MEANS: DIESEL MOTOR
05 0065 02 000 ASSEMBLED
05 0065 02 002 FUNCTIONAL TEST CERTIFICATE MFR STD MFR STD MFR STD 3.1 R R
05 0065 02 006 FINAL, VISUAL AND DIMENSIONAL CHECK DWG COMMON PRACTICE ITN04001 3.1 R R

GE Oil & Gas


Pag. J.1.1/11
GE Proprietary & Confidential Information
CROSS CHECK AT MFR. PREMISES,
05 0065 02 008 COMPLETENESS THREE WAY CHECK BEFORE SHIPMENT, AMONG: LISL, DWG / LISL ITN07068.00 ITN07068.00 PAR. 7.a 2.1 W R
DWG AND MATERIAL
OFF-
SKID 05 0070 00 000 LV AUX. ELECTRIC MOTORS
05 0070 02 000 RAW
ITN62110 (AC) / MAT
05 0070 02 002 MATERIAL CERTIFICATES FOR MAJOR COMPONENTS STD MAT STD MAT STD 2.1 R R
05 0070 04 000 ASSEMBLED AC ELECTRIC MOTORS ONLY
THIS TEST INCLUDES: COLD
WINDING RESISTANCE
MEASUREMENT, NO LOAD AND
LOCKED ROTOR TESTS,
INSULATION MEASUREMENT OF
05 0070 04 002 ROUTINE TEST ITN61502 ITN61502 ITN61502 3.1 R R
WINDINGS AND AUXILIARIES,
HIGH VOLTAGE TEST ON THE
WINDINGS AND AUXILIARIES,
VIBRATION TEST, BEARING
INSPECTION
05 0070 04 006 PAINTING CHECK ITN62110 ITN62110 ITN62110 2.1 R R
05 0070 04 010 DIMENSIONAL CHECK DWG CTQ MFR STD DWG CTQ 2.1 R R
THIS ALSO INCLUDES:
NAMEPLATES CHECK, CLEANING
05 0070 04 012 FINAL AND VISUAL CHECK CHECK, PRESERVATION CHECK ITN62110 ITN62110 ITN62110 2.1 R R
AND REVIEW OF SUPPLIER
DOCUMENTATION
05 0070 06 000 ASSEMBLED DC ELECTRIC MOTORS ONLY
THIS TEST INCLUDES: WINDING
RESISTANCE MEASUREMENT,
05 0070 06 002 ROUTINE TEST AUXILIARY ACCESSORIES ITN62120 ITN62120 ITN62120 3.1 R R
CONTINUITY, NO LOAD TEST,
DIELECTRIC TEST
05 0070 06 006 PAINTING CHECK ITN62120 ITN62120 ITN62120 2.1 R R
05 0070 06 010 DIMENSIONAL CHECK DWG CTQ MFR STD DWG CTQ 2.1 R R
THIS ALSO INCLUDES:
NAMEPLATES CHECK, CLEANING
05 0070 06 012 FINAL AND VISUAL CHECK CHECK, PRESERVATION CHECK ITN62120 ITN62120 ITN62120 2.1 R R
AND REVIEW OF SUPPLIER
DOCUMENTATION
OFF-
SKID 05 0090 00 000 AUX. VOLUMETRIC PUMPS
05 0090 02 000 RAW
FOR MAIN ROTATING PARTS AND
05 0090 02 002 MATERIAL CERTIFICATES MAT STD MAT STD MAT STD 2.1 R R
PRESSURE RETAINING PARTS
05 0090 04 000 MACHINED / ASSEMBLED
ACCORDING TO
05 0090 04 002 HYDROSTATIC PRESSURE TEST (ON PUMP BODY) JOB SPEC. MFR STD 3.1 R R
APPLICABLE CODE
05 0090 04 004 FUNCTIONAL TEST JOB SPEC. MFR STD MFR STD 3.1 R R
05 0090 04 010 PAINTING CHECK JOB SPEC. ITN07791 / ITN04001 JOB SPEC. 3.1 R R
05 0090 04 012 FINAL, VISUAL AND DIMENSIONAL CHECK DWG, JOB DOC COMMON PRACTICE DWG, JOB DOC 2.1 R R
OFF- 05 0095 00 000 AUX. CENTRIFUGAL PUMPS

GE Oil & Gas


Pag. J.1.1/12
GE Proprietary & Confidential Information
SKID
05 0095 02 000 RAW
FOR MAIN ROTATING PARTS AND
05 0095 02 002 MATERIAL CERTIFICATES MAT STD MAT STD MAT STD 2.1 R R
PRESSURE RETAINING PARTS
05 0095 04 000 MACHINED / ASSEMBLED
ACCORDING TO
05 0095 04 002 HYDROSTATIC PRESSURE TEST (ON PUMP BODY) JOB SPEC. MFR STD 3.1 R R
APPLICABLE CODE
05 0095 04 006 FUNCTIONAL TEST JOB SPEC. MFR STD MFR STD 3.1 R R
05 0095 04 014 DIMENSIONAL CHECK DWG COMMON PRACTICE DWG 2.1 R R
05 0095 04 016 PAINTING CHECK JOB SPEC. ITN07791 / ITN04001 JOB SPEC. 3.1 R R
05 0095 04 020 FINAL AND VISUAL CHECK DWG, JOB DOC COMMON PRACTICE DWG, JOB DOC 2.1 R R
OFF-
SKID 05 0110 00 000 ACOUSTIC ENCLOSURE
05 0110 02 000 RAW
05 0110 02 002 MATERIAL CERTIFICATES OF MAIN COMPONENTS MAT STD MAT STD MAT STD 2.1 R R
05 0110 04 000 MACHINED / ASSEMBLED For OFF BASE ENCLOSURES
05 0110 04 008 STRUCTURE WELDING NDT CONSTR. DWG ITN03402.03 ITN03402.03 LEV. D 3.1 R R
ITN07791 / ASTM A123 /
05 0110 04 020 PAINTING / GALVANIZING COMPONENTS CHECK CONSTR. DWG JOB SPEC. / ASTM A123 2.1 R R
ITN04001
DIMENSIONAL CHECK ON LIMIT ON
05 0110 04 024 DWG ITN04001 DWG 3.1 O R
SUPPLY/INTERFACES/CONNECTIONS/TERMINAL POINTS
THIS ALSO INCLUDES THE REVIEW
05 0110 04 026 FINAL, VISUAL CHECK DWG ITN04001 ITN04001 2.1 O R
OF SUPPLIER DOCUMENTATION
CROSS CHECK AT MFR. PREMISES,
05 0110 04 038 COMPLETENESS THREE WAY CHECK BEFORE SHIPMENT, AMONG: LISL, DWG / LISL ITN07068.00 ITN07068.00 PAR. 7.a 2.1 W R
DWG AND MATERIAL
05 0110 08 000 MACHINED / ASSEMBLED For ON BASE ENCLOSURES
05 0110 08 008 STRUCTURE WELDING NDT CONSTR. DWG ITN03402.03 ITN03402.03 LEV. D 3.1 R R
ITN07791 / ASTM A123 /
05 0110 08 020 PAINTING / GALVANIZING COMPONENTS CHECK CONSTR. DWG JOB SPEC. / ASTM A123 2.1 R R
ITN04001
DIMENSIONAL CHECK ON LIMIT ON
05 0110 08 024 DWG ITN04001 DWG 3.1 O R
SUPPLY/INTERFACES/CONNECTIONS/TERMINAL POINTS
THIS ALSO INCLUDES THE REVIEW
05 0110 08 026 FINAL, VISUAL CHECK DWG ITN04001 ITN04001 2.1 O R
OF SUPPLIER DOCUMENTATION
CROSS CHECK AT MFR. PREMISES,
05 0110 08 038 COMPLETENESS THREE WAY CHECK BEFORE SHIPMENT, AMONG: LISL, DWG / LISL ITN07068.00 ITN07068.00 PAR. 7.a 2.1 W R
DWG AND MATERIAL
OFF-
SKID 05 0155 00 000 MINERAL OIL / WATER PLATE COOLER
05 0155 02 000 RAW
05 0155 02 002 LADLE ANALYSIS JOB SPEC MAT STD MAT STD 3.1 R R
05 0155 02 004 MECHANICAL PROPERTIES JOB SPEC MAT STD MAT STD 3.1 R R
05 0155 04 000 MACHINED / ASSEMBLED
05 0155 04 002 NON DESTRUCTIVE EXAMINATIONS ASME VIII DIV. 1 ASME V ASME VIII DIV. 1 3.1 R R
2.1 WATER QUALITY ANALYSIS ACCORDING TO
05 0155 04 006 HYDROSTATIC PRESSURE TEST ASME VIII DIV. 1 ITN07021 3.1 O R
CERTIFICATE TO BE ATTACHED APPLICABLE CODE
DIMENSIONAL CHECK (ON CONNECTIONS AND FIXING DWG / ITM43501.01 /
05 0155 04 014 ITN04001 DWG 2.1 O R
POINTS) ITM43502.01
THIS ALSO INCLUDES NAMEPLATE
ITM43501.01 /
05 0155 04 016 FINAL, VISUAL AND CLEANNESS CHECK CHCK, REVIEW OF SUPPLIER ITN04001 ITN04001 2.1 O R
ITM43502.01 / ITN04001
DOCUMENTATION AND PACKING

GE Oil & Gas


Pag. J.1.1/13
GE Proprietary & Confidential Information
AND SHIPPING CHECK

CROSS CHECK AT MFR. PREMISES,


05 0155 04 018 COMPLETENESS THREE WAY CHECK BEFORE SHIPMENT, AMONG: LISL, DWG / LISL ITN07068.00 ITN07068.00 PAR. 7.a 2.1 W R
DWG AND MATERIAL
OFF-
SKID 05 0175 00 000 OIL COOLER/WATER COOLER (SHELL AND TUBE)
05 0175 02 000 RAW
05 0175 02 002 LADLE ANALYSIS JOB SPEC. MAT STD MAT STD 2.1 R R
05 0175 02 004 MECHANICAL PROPERTIES JOB SPEC. MAT STD MAT STD 2.1 R R
05 0175 04 000 MACHINED / WELDED / ASSEMBLED
WELDING MAP (WM), WELD. PROC. SPECIFICATIONS (WPS)
05 0175 04 002 ASME IX ASME IX ASME IX 2.1 A R
AND PROCEDURE QUALIF. REC. (PQR)
05 0175 04 008 ULTRASONIC TEST ON WELDS ASME VIII DIV. 1 ASME V ASME VIII DIV. 1 3.1 O R
WHEN MT IS NOT FEASABLE (E.G.
05 0175 04 010 MAGNETIC PARTICLE TEST ON WELDS ON NOT MAGNETIC MATERIALS), ASME VIII DIV. 1 ASME V ASME VIII DIV. 1 3.1 O R
PT WILL BE PERFORMED INSTEAD
05 0175 04 012 VISUAL CHECK ON WELDS JOB SPEC. / DWG ITN07040 ASME VIII DIV. 1 2.1 O R
05 0175 04 016 CLEANLINESS CHECK JOB SPEC. / DWG ITN04001 ITN04001 2.1 R R
2.1 WATER QUALITY ANALYSIS ACCORDING TO
05 0175 04 022 HYDROSTATIC PRESSURE TEST JOB SPEC. / DWG STD. MFR. 3.1 O R
CERTIFICATE TO BE ATTACHED APPLICABLE CODE
05 0175 04 026 DIMENSIONAL CHECK JOB SPEC. / DWG ITN04001 / ITN02039 ITN04001 / ITN02039 3.1 R R
THIS ALSO INCLUDES NAMEPLATE
05 0175 04 028 FINAL, VISUAL AND CLEANNESS CHECK CHCK AND REVIEW OF SUPPLIER JOB SPEC. / DWG ITN04001 ITN04001 3.1 W R
DOCUMENTATION
DIAM>150 MM. AND P>103 KPA:
OFF-
05 0180 00 000 PRESSURE VESSEL FILTERS, COOLERS,
SKID
ACCUMULATORS
05 0180 02 000 RAW PARTS
05 0180 02 002 LADLE ANALYSIS JOB SPEC. MAT STD MAT STD 3.1 R R
05 0180 02 004 MECHANICAL PROPERTIES JOB SPEC. MAT STD MAT STD 3.1 R R
05 0180 04 000 MACHINED / WELDED / ASSEMBLED
WELDING MAP (WM), WELD. PROC. SPECIFICATIONS (WPS)
05 0180 04 004 ASME IX ASME IX ASME IX 2.1 A R
AND PROCEDURE QUALIF. REC. (PQR)
05 0180 04 010 CLEANLINESS CHECK JOB SPEC. / DWG ITN04001 ITN04001 2.1 R R
WHEN RT IS NOT PHISICALLY ASME V (UW-51 or UW-
ASME VIII DIV. 1
05 0180 04 012 RADIOGRAPHIC EXAMINATION ON WELDS FEASABLE, UT WILL BE ASME VIII DIV. 1 52 spot check) / 3.1 O R
Appendix 4
PERFORMED INSTEAD ITN02196
ASME V / ITN07039 / ASME VIII DIV. 1
05 0180 04 014 ULTRASONIC TEST ON WELDS ASME VIII DIV. 1 3.1 O R
ITN07073 Appendix 12
WHEN MT IS NOT FEASABLE (E.G.
ASME VIII DIV. 1
05 0180 04 016 MAGNETIC PARTICLE TEST ON WELDS ON NOT MAGNETIC MATERIALS), ASME VIII DIV. 1 ASME V / ITN02119 3.1 O R
Appendix 6
PT WILL BE PERFORMED INSTEAD
ASME VIII DIV. 1
05 0180 04 018 PT OF FILLET WELDS ASME VIII DIV. 1 ASME V / ITN02192 3.1 O R
Appendix 8
05 0180 04 020 VISUAL CHECK ON WELDS JOB SPEC. / DWG ITN07040 ASME VIII DIV. 1 2.1 O R
2.1 WATER QUALITY ANALYSIS ACCORDING TO
05 0180 04 022 HYDROSTATIC PRESSURE TEST JOB SPEC. / DWG JOB SPEC. / DWG 3.1 O O
CERTIFICATE TO BE ATTACHED APPLICABLE CODE
DIMENSIONAL CHECK (ON CONNECTIONS AND FIXING
05 0180 04 036 JOB SPEC. / DWG ITN04001 DWG 3.1 O R
POINTS)

GE Oil & Gas


Pag. J.1.1/14
GE Proprietary & Confidential Information
THIS ALSO INCLUDES NAMEPLATE
05 0180 04 050 FINAL AND VISUAL CHECK CHCK AND REVIEW OF SUPPLIER JOB SPEC. / DWG ITN04001 ITN04001 2.1 O O
DOCUMENTATION
CROSS CHECK AT MFR. PREMISES,
05 0180 04 052 COMPLETENESS THREE WAY CHECK BEFORE SHIPMENT, AMONG: LISL, DWG / LISL ITN07068.00 ITN07068.00 PAR. 7.a 2.1 W R
DWG AND MATERIAL
FOR TESTINGS AND INSPECTIONS
OF MAJOR SUB ITEMS
INCLUDED/ASSEMBLED ON THIS
SKID, REFER TO THE DEDICATED
OFF-
05 0200 00 000 AIR COOLER PAGE(S) OF THIS QCP -
SKID
ACCORDING TO VENDOR PRINT
SCHEDULE, THIS PAGE WILL BE
REPLACED BY SUPPLIER QCP
REFERENCE
05 0200 02 000 RAW / MACHINED / WELDED
ON PLATES, FORGINGS, BOLTING, EN10204 / ASTM / ASME
05 0200 02 002 LADLE ANALYSIS SPEC / DWG ASTM / ASME / DWG 3.1 R R
TUBES / MAT STD
ON PLATES, FORGINGS, BOLTING, EN10204 / ASTM / ASME
05 0200 02 004 MECHANICAL PROPERTIES SPEC / DWG ASTM / ASME / DWG 3.1 R R
TUBES / MAT STD
05 0200 02 012 POST WELD STRESS RELIEVING PWHT SPEC / DWG MAT STD / SOG0003785 ASTM / ASME 3.1 R R
05 0200 02 014 NDE ON WELDS ON PRESSURE RETAINING PARTS SPEC / DWG / API 661 ASME V ASME VIII DIV. 1, API 661 3.1 O R
ITN02174 / ITN07791 /
05 0200 02 024 PAINTING CHECK JOB SPEC. ITN02174 / JOB SPEC. 3.1 R R
ITN04001
2.1 WATER QUALITY ANALYSIS ASME VIII DIV. 1 / API ACCORDING TO
05 0200 02 026 HYDROSTATIC PRESSURE TEST SOG00018 3.1 O O
CERTIFICATE TO BE ATTACHED 661 APPLICABLE CODE
05 0200 02 028 OIL FLUSHING SOG0017042 SOG0017042 SOG0017042 3.1 W R
05 0200 04 000 ASSEMBLED
THIS ALSO INCLUDES NAMEPLATE
05 0200 04 030 FINAL AND VISUAL CHECK CHECK AND REVIEW OF SUPPLIER ITM65700 ITN04001 ITN04001 2.1 W O
DOCUMENTATION
CROSS CHECK AT MFR. PREMISES,
05 0200 04 036 COMPLETENESS THREE WAY CHECK BEFORE SHIPMENT, AMONG: LISL, DWG / LISL ITN07068.00 ITN07068.00 PAR. 7.a 2.1 W R
DWG AND MATERIAL
OFF-
SKID 05 0215 00 000 FILTER HOUSE
05 0215 02 000 RAW
SMO9969860 /
05 0215 02 002 MATERIAL CERTIFICATES (MAIN COMPONENTS ONLY) MAT STD MAT STD 2.2 R R
SMO9969861
FOR TESTINGS AND INSPECTIONS
OF MAJOR SUB ITEMS
05 0215 04 000 MACHINED / ASSEMBLED INCLUDED/ASSEMBLED ON THIS
SKID, REFER TO THE DEDICATED
PAGE(S) OF THIS QCP
SMO9969860 / SMO9969860 /
05 0215 04 004 NDT ON WELDS ITN03402.03 3.1 R R
SMO9969861 SMO9969861
APPLICABLE ONLY FOR
SMO9969860 /
05 0215 04 016 PICKLING AND PASSIVATION CHECK UNPAINTED STAINLESS SURFACES. ITN02136.02 ITN02136.02 2.1 R R
SMO9969861
N/A FOR OTHER CASES.
THIS CHECK IS N/A IN CASE OF SMO9969860 /
05 0215 04 020 PAINTING CHECK ITN07791 / ITN04001 PAINT. SPEC. 3.1 W R
STAINLESS STEEL UNPAINTED F.H. SMO9969861

GE Oil & Gas


Pag. J.1.1/15
GE Proprietary & Confidential Information
DIMENSIONAL CHECK ON LIMIT OF
05 0215 04 026 ASSEMBLY DWG. ITN04001 ASSEMBLY DWG. 3.1 O R
SUPPLY/INTERFACES/CONNECTIONS/TERMINAL POINTS
DIRT AND WELD SPLATTER
SMO9969860 /
05 0215 04 032 FINAL, VISUAL AND CLEANLINESS CHECK REMOVAL ON COMBUSTION AIR ITN04001 ITN04001 3.1 W R
SMO9969861
PATHS
CROSS CHECK AT MFR. PREMISES,
05 0215 04 038 COMPLETENESS THREE WAY CHECK BEFORE SHIPMENT, AMONG: LISL, DWG / LISL ITN07068.00 ITN07068.00 PAR. 7.a 2.1 W R
DWG AND MATERIAL
OFF-
SKID 05 0220 00 000 INLET DUCT
05 0220 02 000 RAW
SMO9970451 /
05 0220 02 002 MATERIAL CERTIFICATES (MAIN COMPONENTS ONLY) MAT STD MAT STD 2.2 R R
SMO9970497
05 0220 04 000 MACHINED / ASSEMBLED
SMO9970451 / SMO9970451 /
05 0220 04 004 NDT ON WELDS ITN03402.03 3.1 R R
SMO9970497 SMO9970497
APPLICABLE ONLY FOR
SMO9970451 /
05 0220 04 006 PICKLING AND PASSIVATION CHECK UNPAINTED STAINLESS SURFACES. ITN02136.02 ITN02136.02 2.1 R R
SMO9970497
N/A FOR OTHER CASES.
THIS CHECK IN N/A IN CASE OF
SMO9970451 /
05 0220 04 010 PAINTING CHECK STAINLESS STEEL UNPAINTED ITN07791 / ITN04001 JOB SPEC. 3.1 R R
SMO9970497
DUCT
DIRT AND WELD SPLATTER
SMO9970451 /
05 0220 04 014 FINAL, VISUAL & CLEANNESS CHECK REMOVAL ON COMBUSTION AIR ITN04001 ITN04001 2.1 W R
SMO9970497
PATHS
CROSS CHECK AT MFR. PREMISES,
05 0220 04 016 COMPLETENESS THREE WAY CHECK BEFORE SHIPMENT, AMONG: LISL, DWG / LISL ITN07068.00 ITN07068.00 PAR. 7.a 2.1 W R
DWG AND MATERIAL
OFF-
SKID 05 0225 00 000 EXHAUST DUCT
05 0225 02 000 RAW
SMO9971061 /
05 0225 02 002 MATERIAL CERTIFICATES (MAIN COMPONENTS ONLY) MAT STD MAT STD 2.2 R R
SMO9971102
05 0225 04 000 MACHINED / ASSEMBLED
SMO9971061 / SMO9971061 /
05 0225 04 004 NDT ON WELDS ITN03402.03 3.1 R R
SMO9971102 SMO9971102
APPLICABLE ONLY FOR
SMO9971061 /
05 0225 04 006 PICKLING AND PASSIVATION CHECK UNPAINTED STAINLESS SURFACES. ITN02136.02 ITN02136.02 2.1 R R
SMO9971102
N/A FOR OTHER CASES.
THIS CHECK IN N/A IN CASE OF
SMO9971061 /
05 0225 04 010 PAINTING CHECK STAINLESS STEEL UNPAINTED ITN07791 JOB SPEC. 3.1 R R
SMO9971102
DUCT
SMO9971061 /
05 0225 04 014 FINAL, VISUAL CHECK ITN04001 ITN04001 2.1 W R
SMO9971102
CROSS CHECK AT MFR. PREMISES,
05 0225 04 022 COMPLETENESS THREE WAY CHECK BEFORE SHIPMENT, AMONG: LISL, DWG / LISL ITN07068.00 ITN07068.00 PAR. 7.a 2.1 W R
DWG AND MATERIAL
OFF-
SKID 05 0230 00 000 VENTILATION DUCTS
05 0230 02 000 RAW
05 0230 02 002 MATERIAL CERTIFICATES (FOR MAIN COMPONENTS ONLY) SMO9909620 MAT STD SMO9909620 2.2 R R

GE Oil & Gas


Pag. J.1.1/16
GE Proprietary & Confidential Information
05 0230 04 000 MACHINED / ASSEMBLED
APPLICABLE ONLY FOR
05 0230 04 006 PICKLING AND PASSIVATION CHECK UNPAINTED STAINLESS SURFACES. SMO9909620 ITN02136.02 ITN02136.02 2.1 R R
N/A FOR OTHER CASES.
THIS CHECK IN N/A IN CASE OF
05 0230 04 010 PAINTING CHECK STAINLESS STEEL UNPAINTED SMO9909620 ITN07791 / ITN04001 JOB SPEC. 3.1 R R
DUCTS
05 0230 04 012 FINAL, VISUAL, DIMENSIONAL & CLEANNESS CHECK SMO9909620 ITN04001 ITN04001 3.1 W R
CROSS CHECK AT MFR. PREMISES,
05 0230 04 014 COMPLETENESS THREE WAY CHECK BEFORE SHIPMENT, AMONG: LISL, DWG / LISL ITN07068.00 ITN07068.00 PAR. 7.a 2.1 W R
DWG AND MATERIAL
OFF-
SKID 05 0235 00 000 SUPPORTING STRUCTURE
05 0235 02 000 RAW
05 0235 02 002 MATERIAL CERTIFICATES (MAIN COMPONENTS ONLY) SMO9970453 MAT STD MAT STD 2.2 R R
05 0235 08 000 FABRICATED / ASSEMBLED
05 0235 08 006 NDT ON WELDS SMO9970453 ITN03402.03 SMO9970453 3.1 R R
JOB SPEC. / ITN07801
05 0235 08 010 PAINTING / GALVANIZING CHECK JOB SPEC. / ITN07801 (ASTM A123 / ASTM JOB SPEC. / ITN07801 3.1 W R
A153)
05 0235 08 012 FINAL VISUAL AND DIMENSIONAL CHECK SMO9970453 SMO9970453 SMO9970453 3.1 W R
CROSS CHECK AT MFR. PREMISES,
05 0235 08 014 COMPLETENESS THREE WAY CHECK BEFORE SHIPMENT, AMONG: LISL, DWG / LISL ITN07068.00 ITN07068.00 PAR. 7.a 2.1 W R
DWG AND MATERIAL
OFF-
05 0236 00 000 GRATES, WALKWAYS, LADDERS, PLATFORMS AND STAIRS
SKID
05 0236 02 000 FABRICATED / ASSEMBLED
G.A. DWG / ITN02800 / G.A. DWG / ITN02800 /
05 0236 02 002 DIMENSIONAL CHECK ITN02809.02 / ITN04001 ITN02809.02 / 2.1 W R
ITN02810.02 ITN02810.02
ITN07791 / ASTM A123 /
05 0236 02 004 PAINTING / GALVANIZING CHECK JOB SPEC. / ASTM A123 JOB SPEC. / ASTM A123 3.1 O R
ITN04001
G.A. DWG / ITN02800 / G.A. DWG / ITN02800 /
05 0236 02 006 FINAL VISUAL CHECK ITN02809.02 / ITN04001 ITN02809.02 / 2.1 W R
ITN02810.02 ITN02810.02
CROSS CHECK AT MFR. PREMISES,
05 0236 02 008 COMPLETENESS THREE WAY CHECK BEFORE SHIPMENT, AMONG: LISL, DWG / LISL ITN07068.00 ITN07068.00 PAR. 7.a 2.1 W R
DWG AND MATERIAL
FOR TESTINGS AND INSPECTIONS
OF MAJOR SUB ITEMS
OFF-
05 0240 00 000 VENTILATION/EXTRACTION FANS INCLUDED/ASSEMBLED ON THIS
SKID
SKID, REFER TO THE DEDICATED
PAGE(S) OF THIS QCP
05 0240 02 000 MACHINED / ASSEMBLED FAN
05 0240 02 002 MATERIAL CERTIFICATES (MAIN COMPONENTS ONLY) MFR STD MAT. STD. MAT. STD. 2.1 R R
05 0240 04 000 ASSEMBLED FAN AND EL. MOTOR
05 0240 04 002 MECHANICAL RUNNING TEST JOB SPEC MFR STD MFR STD 3.1 O R
05 0240 04 010 PAINTING CHECK JOB SPEC. ITN07791 / ITN04001 JOB SPEC. 3.1 W R
05 0240 04 014 DIMENSIONAL CHECK DWG ITN04001 DWG 3.1 W O
05 0240 04 018 FINAL AND VISUAL CHECK DWG ITN04001 ITN04001 2.1 W R

GE Oil & Gas


Pag. J.1.1/17
GE Proprietary & Confidential Information
CROSS CHECK AT MFR. PREMISES,
05 0240 04 020 COMPLETENESS THREE WAY CHECK BEFORE SHIPMENT, AMONG: LISL, DWG / LISL ITN07068.00 ITN07068.00 PAR. 7.a 2.1 W R
DWG AND MATERIAL
OFF-
SKID 05 0255 00 000 CONTROL VALVES
05 0255 02 000 RAW
05 0255 02 002 LADLE ANALYSIS PARTS UNDER PRESSURE ITN04204.36 ASTM STD ASTM STD 3.1 R R
05 0255 02 004 MECHANICAL PROPERTIES PARTS UNDER PRESSURE ITN04204.36 ASTM STD ASTM STD 3.1 R R
05 0255 02 006 NON DESTRUCTIVE EXAMINATIONS ITN04204.36 ITN04204.36 ITN04204.36 3.1 R R
05 0255 04 000 ASSEMBLED
ANSI B16.104 / ANSI B16.104 / ANSI/FCI-
05 0255 04 002 PNEUMATIC TEST OF SEAT-PLUG SEAL ITN04204.36 3.1 R R
ANSI/FCI-70-2,2006 70-2,2006
PNEUMATIC TEST OF ACTUATOR SHELL AND DIAPHRAGMS ACCORDING TO
05 0255 04 004 ITN04204.36 MFR STD 3.1 R R
SEAL APPLICABLE CODE
HYDROSTATIC PRESSURE TEST (ON PARTS UNDER 2.1 WATER QUALITY ANALYSIS
05 0255 04 006 ITN04204.36 API STD 6D ITN04204.36 3.1 R R
PRESSURE) CERTIFICATE TO BE ATTACHED
FOR THROTTLING CONTROL
VALVES, THIS INCLUDES CHECK OF
05 0255 04 008 FUNCTIONAL TEST TRAVELLING AT FOLLOWING ITN04204.36 MFR STD SPEC. VALUES 3.1 R R
POINTS: 0%, 25%, 50%, 75%,
100%
INCLUDING: SHIPPING,
PRESERVATION, BLANKING ITN04204.36 /
05 0255 04 026 FINAL AND VISUAL CHECK REQUIREMENTS AND INSPECTION ITN04204.44 / ITN04001 ITN04001 2.1 R R
OF CERTIFICATE AND ITN04204.45
DOCUMENTATION
OFF-
SKID 05 0260 00 000 SAFETY VALVES
05 0260 02 000 RAW
05 0260 02 002 LADLE ANALYSIS PARTS UNDER PRESSURE ITN04204.37 ASTM STD ASTM STD 3.1 R R
05 0260 02 004 MECHANICAL PROPERTIES PARTS UNDER PRESSURE ITN04204.37 ASTM STD ASTM STD 3.1 R R
05 0260 02 006 NON DESTRUCTIVE EXAMINATIONS ITN04204.37 ITN04204.37 ITN04204.37 3.1 R R
05 0260 04 000 ASSEMBLED
05 0260 04 002 DISK-NOZZLE SEAL LEAKAGE TEST ITN04204.37 MFR STD API 527 3.1 R R
05 0260 04 004 BELLOWS (IF ANY) SEAL TEST ITN04204.37 MFR STD ITN04204.37 3.1 R R
2.1 WATER QUALITY ANALYSIS
05 0260 04 006 HYDROSTATIC PRESSURE TEST (PARTS UNDER PRESSURE) ITN04204.37 ANSI B 16.5 ITN04204.37 3.1 R R
CERTIFICATE TO BE ATTACHED
VALVE DATA SHEET /
05 0260 04 008 SET PRESSURE TEST ITN04204.37 MFR STD MFR. TEST PROCEDURE 3.1 R R
INCLUDING: SHIPPING,
PRESERVATION, BLANKING
05 0260 04 026 FINAL AND VISUAL CHECK REQUIREMENTS AND INSPECTION ITN04204.37 ITN04001 ITN04001 2.1 R R
OF CERTIFICATE AND
DOCUMENTATION
FOR TESTINGS AND INSPECTIONS
OF MAJOR SUB ITEMS
OFF-
05 0285 00 000 FIRE FIGHTING SKID INCLUDED/ASSEMBLED ON THIS
SKID
SKID, REFER TO THE DEDICATED
PAGE(S) OF THIS QCP
05 0285 02 000 RAW
05 0285 02 002 LADLE ANALYSIS FOR MAIN COMPONENTS ONLY ITM65300 MFR STD MFR STD 2.1 R R

GE Oil & Gas


Pag. J.1.1/18
GE Proprietary & Confidential Information
05 0285 02 004 MECHANICAL PROPERTIES FOR MAIN COMPONENTS ONLY ITM65300 MFR STD MFR STD 2.1 R R
05 0285 04 000 ASSEMBLED
05 0285 04 018 FUNCTIONAL TEST ITM65300 MFR STD JOB SPEC 3.1 W O
05 0285 04 026 CHECKS AFTER ELECTRICAL INSTALLATION INCLUDING TAGGING ITM65300 ITM65300 ITM65300 2.1 O R
05 0285 04 028 PAINTING CHECK JOB SPEC. ITN07791 / ITN04001 JOB SPEC. 3.1 W R
DIMENSIONAL CHECK ON LIMIT ON GENERAL GENERAL
05 0285 04 030 ITN04001 3.1 W R
SUPPLY/INTERFACES/CONNECTIONS/TERMINAL POINTS ARRANGEMENT DWG ARRANGEMENT DWG
THIS ALSO INCLUDES THE REVIEW GENERAL
05 0285 04 036 FINAL AND VISUAL CHECK ITN04001 ITN04001 2.1 O R
OF SUPPLIER DOCUMENTATION ARRANGEMENT DWG
CROSS CHECK AT MFR. PREMISES,
05 0285 04 038 COMPLETENESS THREE WAY CHECK BEFORE SHIPMENT, AMONG: LISL, DWG / LISL ITN07068.00 ITN07068.00 PAR. 7.a 2.1 W R
DWG AND MATERIAL
FOR TESTINGS AND INSPECTIONS
OF MAJOR SUB ITEMS
OFF-
05 0290 00 000 MINERAL OIL VAPOUR SEPARATOR SKID INCLUDED/ASSEMBLED ON THIS
SKID
SKID, REFER TO THE DEDICATED
PAGE(S) OF THIS QCP
05 0290 02 000 RAW
05 0290 02 002 MATERIAL CERTIFICATES (FOR MAIN COMPONENTS) MAT STD MAT STD MAT STD 2.1 R R
05 0290 04 000 ASSEMBLED
FUNCTIONAL TEST: VIBRATION/NOISE TEST ON MOTOR-
05 0290 04 008 ITN40950.00 MFR STD ITN40950.00 3.1 O R
FAN GROUP
05 0290 04 010 PAINTING CHECK JOB SPEC. ITN07791 / ITN04001 JOB SPEC. 3.1 O R
DIMENSIONAL CHECK ON LIMIT ON GENERAL GENERAL
05 0290 04 018 ITN04001 3.1 O R
SUPPLY/INTERFACES/CONNECTIONS/TERMINAL POINTS ARRANGEMENT DWG ARRANGEMENT DWG
P&Id, WIRING DIA., P&Id, WIRING DIA.,
ELECTRICAL HOOK-UP, ELECTRICAL HOOK-UP,
05 0290 04 020 INSTRUMENT INSTALLATION CHECK (INCLUDING TAGGING) ITN04001 2.1 O R
PRIMARY/PNEUMATIC PRIMARY/PNEUMATIC
HOOK-UP HOOK-UP
THIS ALSO INCLUDES THE REVIEW
05 0290 04 034 FINAL AND VISUAL CHECK DWG ITN04001 ITN04001 2.1 O R
OF SUPPLIER DOCUMENTATION
CROSS CHECK AT MFR. PREMISES,
05 0290 04 038 COMPLETENESS THREE WAY CHECK BEFORE SHIPMENT, AMONG: LISL, DWG / LISL ITN07068.00 ITN07068.00 PAR. 7.a 2.1 W R
DWG AND MATERIAL
FOR TESTINGS AND INSPECTIONS
OF MAJOR SUB ITEMS
OFF-
05 0300 00 000 OFF/ON LINE WASHING SKID (FOR GT AXIAL CPRS.) INCLUDED/ASSEMBLED ON THIS
SKID
SKID, REFER TO THE DEDICATED
PAGE(S) OF THIS QCP
05 0300 02 000 RAW
05 0300 02 006 MATERIAL CERTIFICATES (FOR MAIN COMPONENTS) MAT STD MAT STD MAT STD 2.1 R R
05 0300 04 000 ASSEMBLED
05 0300 04 006 FUNCTIONAL TEST MFR STD MFR STD MFR STD 3.1 W R
05 0300 04 008 PAINTING CHECK JOB SPEC. ITN07791 / ITN04001 JOB SPEC. 3.1 W R
DIMENSIONAL CHECK ON LIMIT ON GENERAL GENERAL
05 0300 04 010 ITN04001 3.1 O R
SUPPLY/INTERFACES/CONNECTIONS/TERMINAL POINTS ARRANGEMENT DWG ARRANGEMENT DWG
P&Id, WIRING DIA., P&Id, WIRING DIA.,
ELECTRICAL HOOK-UP, ELECTRICAL HOOK-UP,
05 0300 04 012 INSTRUMENT INSTALLATION CHECK (INCLUDING TAGGING) ITN04001 2.1 O R
PRIMARY/PNEUMATIC PRIMARY/PNEUMATIC
HOOK-UP HOOK-UP
05 0300 04 014 FINAL AND VISUAL CHECK THIS ALSO INCLUDES THE REVIEW GENERAL ITN04001 ITN04001 2.1 O R

GE Oil & Gas


Pag. J.1.1/19
GE Proprietary & Confidential Information
OF SUPPLIER DOCUMENTATION ARRANGEMENT DWG
CROSS CHECK AT MFR. PREMISES,
05 0300 04 024 COMPLETENESS THREE WAY CHECK BEFORE SHIPMENT, AMONG: LISL, DWG / LISL ITN07068.00 ITN07068.00 PAR. 7.a 2.1 W R
DWG AND MATERIAL
FOR TESTINGS AND INSPECTIONS
OF MAJOR SUB ITEMS
OFF-
05 0305 00 000 HYDRAULIC STARTING SKID INCLUDED/ASSEMBLED ON THIS
SKID
SKID, REFER TO THE DEDICATED
PAGE(S) OF THIS QCP
05 0305 02 000 RAW
FOR MAIN STRUCTURAL
05 0305 02 002 LADLE ANALYSIS COMPONENTS ITN47001.01 ASTM STD ASTM STD 2.1 R R
FOR MAIN STRUCTURAL
05 0305 02 004 MECHANICAL PROPERTIES COMPONENTS ITN47001.01 ASTM STD ASTM STD 2.1 R R
05 0305 04 000 ASSEMBLED
05 0305 04 014 FUNCTIONAL TEST MFR STD MFR STD MFR STD 3.1 O R
ITN47001.01 / P&Id,
P&Id, WIRING DIA.,
WIRING DIA.,
ELECTRICAL HOOK-UP,
05 0305 04 018 INSTRUMENT INSTALLATION CHECK (INCLUDING TAGGING) ELECTRICAL HOOK-UP, ITN04001 2.1 O R
PRIMARY/PNEUMATIC
PRIMARY/PNEUMATIC
HOOK-UP
HOOK-UP
JOB PAINTING
05 0305 04 020 PAINTING CHECK ITN47001.01 ITN07791 / ITN04001 3.1 W R
SPECIFICATION
DIMENSIONAL CHECK ON LIMIT ON GENERAL GENERAL
05 0305 04 022 ITN04001 3.1 O R
SUPPLY/INTERFACES/CONNECTIONS/TERMINAL POINTS ARRANGEMENT DWG ARRANGEMENT DWG
THIS ALSO INCLUDES THE REVIEW ITN47001.01 / GENERAL
05 0305 04 024 FINAL, VISUAL CHECK ITN04001 ITN04001 2.1 O R
OF SUPPLIER DOCUMENTATION ARRANGEMENT DWG
CROSS CHECK AT MFR. PREMISES,
05 0305 04 034 COMPLETENESS THREE WAY CHECK BEFORE SHIPMENT, AMONG: LISL, DWG / LISL ITN07068.00 ITN07068.00 PAR. 7.a 2.1 W R
DWG AND MATERIAL
FOR TESTINGS AND INSPECTIONS
OF MAJOR SUB ITEMS
OFF-
05 0310 00 000 FUEL GAS TREATMENT SKID INCLUDED/ASSEMBLED ON THIS
SKID
SKID, REFER TO THE DEDICATED
PAGE(S) OF THIS QCP
05 0310 02 000 RAW
MATERIAL CERTIFICATES (FOR BASEPLATE MAIN
05 0310 02 002 MAT STD MAT STD MAT STD 2.1 R R
STRUCTURAL COMPONENTS)
05 0310 04 000 ASSEMBLED
DIMENSIONAL CHECK ON LIMIT ON GENERAL GENERAL
05 0310 04 008 ITN04001 2.1 W R
SUPPLY/INTERFACES/CONNECTIONS/TERMINAL POINTS ARRANGEMENT DWG ARRANGEMENT DWG
05 0310 04 010 PAINTING CHECK JOB SPEC. ITN07791 / ITN04001 JOB SPEC. 3.1 W R
P&Id, WIRING DIA., P&Id, WIRING DIA.,
ELECTRICAL HOOK-UP, ELECTRICAL HOOK-UP,
05 0310 04 018 INSTRUMENT INSTALLATION CHECK (INCLUDING TAGGING) ITN04001 2.1 O R
PRIMARY/PNEUMATIC PRIMARY/PNEUMATIC
HOOK-UP HOOK-UP
THIS ALSO INCLUDES THE REVIEW GENERAL
05 0310 04 022 FINAL, VISUAL CHECK ITN04001 ITN04001 2.1 O R
OF SUPPLIER DOCUMENTATION ARRANGEMENT DWG
CROSS CHECK AT MFR. PREMISES,
05 0310 04 034 COMPLETENESS THREE WAY CHECK BEFORE SHIPMENT, AMONG: LISL, DWG / LISL ITN07068.00 ITN07068.00 PAR. 7.a 2.1 W R
DWG AND MATERIAL

GE Oil & Gas


Pag. J.1.1/20
GE Proprietary & Confidential Information
FOR TESTINGS AND INSPECTIONS
OF MAJOR SUB ITEMS
OFF-
05 0325 00 000 MINERAL OIL CONSOLE/AUX SKID INCLUDED/ASSEMBLED ON THIS
SKID
SKID, REFER TO THE DEDICATED
PAGE(S) OF THIS QCP
05 0325 02 000 RAW (BASEPLATE)
05 0325 02 004 LADLE ANALYSIS OF MAIN COMPONENTS ITW71000 ASTM STD ASTM STD 3.1 R R
05 0325 02 008 MECHANICAL PROPERTIES OF MAIN COMPONENTS ITW71000 ASTM STD ASTM STD 3.1 R R
05 0325 04 000 FABRICATED / MACHINED (BASEPLATE)
05 0325 04 006 NON DESTRUCTIVE EXAMINATIONS ON WELDS ITW71000 ITN03402.03 ITW71000 3.1 O R
05 0325 04 008 EYEBOLTS/LIFTING BITTS WELDS NDT ITW71000 ITN03402.03 ITW71000 3.1 O R
2.1 WATER QUALITY ANALYSIS
05 0325 04 012 STATIC SEAL TEST OF OIL TANK ITW71000 ITN07036 ITW71000 3.1 O R
CERTIFICATE TO BE ATTACHED
DIMENSIONAL CHECK ON LIMIT ON
05 0325 04 020 ITW71000 ITW71000 DWG 3.1 O R
SUPPLY/INTERFACES/CONNECTIONS/TERMINAL POINTS
THIS ALSO INCLUDES THE REVIEW
05 0325 04 024 FINAL, VISUAL AND CLEANLINESS CHECK DWG ITN04001 ITN04001 2.1 O R
OF SUPPLIER DOCUMENTATION
05 0325 22 000 ASSEMBLED (SKID)
05 0325 22 010 FUNCTIONAL TEST API 614 ITM01011.20 ITM01011.20 3.1 O R
P&Id, WIRING DIA., P&Id, WIRING DIA.,
ELECTRICAL HOOK-UP, ELECTRICAL HOOK-UP,
05 0325 22 016 INSTRUMENT INSTALLATION CHECK (INCLUDING TAGGING) ITN04001 2.1 O R
PRIMARY/PNEUMATIC PRIMARY/PNEUMATIC
HOOK-UP HOOK-UP
05 0325 22 020 PAINTING CHECK JOB SPEC. ITN07791 / ITN04001 JOB SPEC. 3.1 O R
DIMENSIONAL CHECK ON LIMIT ON GENERAL
05 0325 22 024 ITN04001 DWG 3.1 O R
SUPPLY/INTERFACES/CONNECTIONS/TERMINAL POINTS ARRANGEMENT DWG
THIS ALSO INCLUDES THE REVIEW
05 0325 22 028 FINAL, VISUAL CHECK ITN04001 ITN04001 ITN04001 2.1 O R
OF SUPPLIER DOCUMENTATION
CROSS CHECK AT MFR. PREMISES,
05 0325 22 078 COMPLETENESS THREE WAY CHECK BEFORE SHIPMENT, AMONG: LISL, DWG / LISL ITN07068.00 ITN07068.00 PAR. 7.a 2.1 W R
DWG AND MATERIAL
OFF-
SKID 05 0450 00 000 LIFTING EQUIPMENTS
05 0450 02 000 RAW
05 0450 02 002 LADLE ANALYSIS (FOR MAIN COMPONENTS ONLY) MAT STD MAT STD MAT STD 2.1 R R
MECHANICAL PROPERTIES (FOR MAIN COMPONENTS
05 0450 02 004 MAT STD MAT STD MAT STD 2.1 R R
ONLY)
05 0450 06 000 MACHINED
05 0450 06 006 NON DESTRUCTIVE EXAMINATIONS ON WELDS BEFORE AND AFTER PROOF TEST JOB SPEC/DOC ITN03402.03 ITN03402.03 3.1 R R
JOB PAINT SPEC. / ASTM ITN07791 / ASTM A123 / JOB PAINT SPEC. / ASTM
05 0450 06 010 PAINTING / GALVANIZING COMPONENTS CHECK 3.1 R R
A123 ITN04001 A123
05 0450 06 012 VISUAL AND DIMENSIONAL CHECK JOB SPEC / DWG ITN04001 ITN04001 3.1 R R
05 0450 06 014 LIFTING EQUIPMENT PROOF TEST JOB SPEC / DWG JOB SPEC/DOC JOB SPEC/DOC 3.1 W R
FOR TESTINGS AND INSPECTIONS
OF MAJOR SUB ITEMS
OFF-
05 0455 00 000 COOLING WATER PUMP SKID INCLUDED/ASSEMBLED ON THIS
SKID
SKID, REFER TO THE DEDICATED
PAGE(S) OF THIS QCP
05 0455 02 000 RAW
FOR MAIN STRUCTURAL
05 0455 02 002 LADLE ANALYSIS ITW71000 / JOB SPEC. MAT. STD. MAT. STD. 3.1 R R
COMPONENTS

GE Oil & Gas


Pag. J.1.1/21
GE Proprietary & Confidential Information
FOR MAIN STRUCTURAL
05 0455 02 004 MECHANICAL PROPERTIES ITW71000 / JOB SPEC. MAT. STD. MAT. STD. 3.1 R R
COMPONENTS
05 0455 08 000 ASSEMBLED
P&Id, WIRING DIA., P&Id, WIRING DIA.,
ELECTRICAL HOOK-UP, ELECTRICAL HOOK-UP,
05 0455 08 032 INSTRUMENT INSTALLATION CHECK (INCLUDING TAGGING) ITN04001 2.1 R R
PRIMARY/PNEUMATIC PRIMARY/PNEUMATIC
HOOK-UP HOOK-UP
JOB PAINTING JOB PAINTING
05 0455 08 034 PAINTING CHECK ITN07791 / ITN04001 3.1 R R
SPECIFICATION SPECIFICATION
DIMENSIONAL CHECK ON LIMIT ON GENERAL GENERAL
05 0455 08 040 ITN04001 3.1 R R
SUPPLY/INTERFACES/CONNECTIONS/TERMINAL POINTS ARRANGEMENT DWG ARRANGEMENT DWG
THIS ALSO INCLUDES THE REVIEW GENERAL
05 0455 08 044 FINAL, VISUAL CHECK ITN04001 ITN04001 2.1 R R
OF SUPPLIER DOCUMENTATION ARRANGEMENT DWG
CROSS CHECK AT MFR. PREMISES,
05 0455 08 050 COMPLETENESS THREE WAY CHECK BEFORE SHIPMENT, AMONG: LISL, DWG / LISL ITN07068.00 ITN07068.00 PAR. 7.a 2.1 W R
DWG AND MATERIAL
FOR TESTINGS AND INSPECTIONS
OF MAJOR SUB ITEMS
OFF-
05 0490 00 000 JACKING OIL SYSTEM INCLUDED/ASSEMBLED ON THIS
SKID
SKID, REFER TO THE DEDICATED
PAGE(S) OF THIS QCP
05 0490 02 000 RAW
MATERIAL CERTIFICATES (FOR MAIN STRUCTURAL
05 0490 02 004 MAT STD MAT STD MAT STD 2.1 R R
COMPONENTS)
05 0490 08 000 ASSEMBLED
05 0490 08 002 FUNCTIONAL TEST MFR STD MFR STD MFR STD 3.1 O R
05 0490 08 022 PAINTING CHECK JOB SPEC. ITN07791 / ITN04001 JOB SPEC. 3.1 W R
DIMENSIONAL CHECK ON LIMIT ON GENERAL GENERAL
05 0490 08 028 ITN04001 3.1 O R
SUPPLY/INTERFACES/CONNECTIONS/TERMINAL POINTS ARRANGEMENT DWG ARRANGEMENT DWG
P&Id, WIRING DIA., P&Id, WIRING DIA.,
ELECTRICAL HOOK-UP, ELECTRICAL HOOK-UP,
05 0490 08 032 INSTRUMENT INSTALLATION CHECK (INCLUDING TAGGING) ITN04001 2.1 O R
PRIMARY/PNEUMATIC PRIMARY/PNEUMATIC
HOOK-UP HOOK-UP
THIS ALSO INCLUDES THE REVIEW GENERAL
05 0490 08 034 FINAL, VISUAL CHECK ITN04001 ITN04001 2.1 O R
OF SUPPLIER DOCUMENTATION ARRANGEMENT DWG
CROSS CHECK AT MFR. PREMISES,
05 0490 08 040 COMPLETENESS THREE WAY CHECK BEFORE SHIPMENT, AMONG: LISL, DWG / LISL ITN07068.00 ITN07068.00 PAR. 7.a 2.1 W R
DWG AND MATERIAL
OFF-
SKID 05 0535 00 000 RUNDOWN TANK / NOT PRESSURIZED TANKS
05 0535 02 000 RAW
ON STRUCTURAL PARTS AND
05 0535 02 002 LADLE ANALYSIS ITW71000 MAT STD MAT STD 2.1 R R
WETTED PARTS
ON STRUCTURAL PARTS AND
05 0535 02 004 MECHANICAL PROPERTIES ITW71000 MAT STD MAT STD 2.1 R R
WETTED PARTS
05 0535 04 000 ASSEMBLED / FABRICATED
05 0535 04 004 NDT ON WELDS ITW71000 ITN03402.03 ITW71000 3.1 O R
05 0535 04 006 LEAK TEST ITN07036 ITN07036 ITN07036 3.1 O R
05 0535 04 008 CLEANLINESS CHECK ITN04001 ITN04001 ITN04001 2.1 R R
05 0535 04 010 PAINTING CHECK IF APPLICABLE JOB SPEC. ITN07791 / ITN04001 JOB SPEC. 3.1 O R
05 0535 04 014 DIMENSIONAL CHECK ON LIMIT ON GENERAL ITN04001 GENERAL 3.1 O R

GE Oil & Gas


Pag. J.1.1/22
GE Proprietary & Confidential Information
SUPPLY/INTERFACES/CONNECTIONS/TERMINAL POINTS ARRANGEMENT DWG ARRANGEMENT DWG
THIS ALSO INCLUDES THE REVIEW GENERAL
05 0535 04 016 FINAL, VISUAL INSPECTION ITN04001 ITN04001 2.1 W R
OF SUPPLIER DOCUMENTATION ARRANGEMENT DWG
CROSS CHECK AT MFR. PREMISES,
05 0535 04 020 COMPLETENESS THREE WAY CHECK BEFORE SHIPMENT, AMONG: LISL, DWG / LISL ITN07068.00 ITN07068.00 PAR. 7.a 2.1 W R
DWG AND MATERIAL
OFF- GAS CHROMATOGRAPHY/CALORIMETER/WOBBE METER
05 0750 00 000
SKID SYSTEM
05 0750 02 000 RAW
05 0750 02 002 MATERIAL CERTIFICATES (FOR MAIN COMPONENTS) ITN66650 MAT STD MAT STD 2.1 R R
05 0750 04 000 ASSEMBLED
05 0750 04 002 FUNCTIONAL TEST ITN66650 JOB SPEC JOB SPEC 3.1 W O
DIMENSIONAL CHECK ON LIMIT ON GENERAL GENERAL
05 0750 04 012 ITN04001 3.1 O R
SUPPLY/INTERFACES/CONNECTIONS/TERMINAL POINTS ARRANGEMENT DWG ARRANGEMENT DWG
05 0750 04 016 FINAL, VISUAL INSPECTION ITN66650 ITN04001 ITN04001 2.1 O R
CROSS CHECK AT MFR. PREMISES,
05 0750 04 020 COMPLETENESS THREE WAY CHECK BEFORE SHIPMENT, AMONG: LISL, DWG / LISL ITN07068.00 ITN07068.00 PAR. 7.a 2.1 W R
DWG AND MATERIAL
FOR TESTINGS AND INSPECTIONS
OF MAJOR SUB ITEMS
OFF-
05 0795 00 000 DLN/METERING VALVES SKID INCLUDED/ASSEMBLED ON THIS
SKID
SKID, REFER TO THE DEDICATED
PAGE(S) OF THIS QCP
05 0795 02 000 RAW
MATERIAL CERTIFICATES (FOR MAIN STRUCTURAL
05 0795 02 002 MAT STD MAT STD MAT STD 3.1 R R
COMPONENTS)
05 0795 04 000 ASSEMBLED
05 0795 04 014 PAINTING CHECK JOB SPEC ITN07791 / ITN04001 JOB SPEC 3.1 O O
P&Id, WIRING DIA., P&Id, WIRING DIA.,
ELECTRICAL HOOK-UP, ELECTRICAL HOOK-UP,
05 0795 04 022 INSTRUMENT INSTALLATION CHECK (INCLUDING TAGGING) ITN04001 2.1 O R
PRIMARY/PNEUMATIC PRIMARY/PNEUMATIC
HOOK-UP HOOK-UP
DIMENSIONAL CHECK ON LIMIT ON GENERAL GENERAL
05 0795 04 028 ITN04001 3.1 O R
SUPPLY/INTERFACES/CONNECTIONS/TERMINAL POINTS ARRANGEMENT DWG ARRANGEMENT DWG
THIS ALSO INCLUDES THE REVIEW GENERAL
05 0795 04 030 FINAL, VISUAL CHECK ITN04001 ITN04001 3.1 O R
OF SUPPLIER DOCUMENTATION ARRANGEMENT DWG
CROSS CHECK AT MFR. PREMISES,
05 0795 04 038 COMPLETENESS THREE WAY CHECK BEFORE SHIPMENT, AMONG: LISL, DWG / LISL ITN07068.00 ITN07068.00 PAR. 7.a 2.1 W R
DWG AND MATERIAL
FOR TESTINGS AND INSPECTIONS
OF MAJOR SUB ITEMS
OFF-
05 0805 00 000 OIL PURIFIER / OIL CLARIFIER INCLUDED/ASSEMBLED ON THIS
SKID
SKID, REFER TO THE DEDICATED
PAGE(S) OF THIS QCP
05 0805 02 000 RAW
MATERIAL CERTIFICATES (FOR MAIN STRUCTURAL
05 0805 02 002 MAT STD MAT STD MAT STD 2.1 R R
COMPONENTS AND WETTED OIL PARTS)
05 0805 04 000 ASSEMBLED
05 0805 04 006 PAINTING CHECK JOB SPEC. ITN07791 / ITN04001 JOB SPEC. 3.1 O R
THIS ALSO INCLUDES THE REVIEW GENERAL
05 0805 04 008 FINAL, VISUAL CHECK ITN04001 ITN04001 3.1 O R
OF SUPPLIER DOCUMENTATION ARRANGEMENT DWG

GE Oil & Gas


Pag. J.1.1/23
GE Proprietary & Confidential Information
DIMENSIONAL CHECK ON LIMIT ON GENERAL GENERAL
05 0805 04 010 ITN04001 3.1 O R
SUPPLY/INTERFACES/CONNECTIONS/TERMINAL POINTS ARRANGEMENT DWG ARRANGEMENT DWG
CROSS CHECK AT MFR. PREMISES,
05 0805 04 014 COMPLETENESS THREE WAY CHECK BEFORE SHIPMENT, AMONG: LISL, DWG / LISL ITN07068.00 ITN07068.00 PAR. 7.a 2.1 W R
DWG AND MATERIAL
OFF-
SKID 06 0005 00 000 DIESEL GENERATOR SET
06 0005 01 000 RAW
06 0005 01 002 LADLE ANALYSIS ON MAIN COMPONENTS ASTM STD ASTM STD ASTM STD 3.1 R R
06 0005 01 006 MECHANICAL PROPERTIES ON MAIN COMPONENTS ASTM STD ASTM STD ASTM STD 3.1 R R
NON DESTRUCTIVE EXAMINATIONS ON MAIN
06 0005 01 010 ASTM STD ASTM STD ASTM STD 3.1 R R
COMPONENTS
06 0005 02 000 MACHINED / ASSEMBLY
CERTIFICATE TEST OF GENERATOR
06 0005 02 002 GENERATOR TESTING JOB DOC. JOB DOC. JOB DOC. 3.1 R R
MANUFACTURER
CERTIFICATE TEST OF GENERATOR
06 0005 02 004 ENGINE TESTING JOB DOC. JOB DOC. JOB DOC. 3.1 R R
MANUFACTURER
06 0005 04 000 ASSEMBLED
CHECK ON CONTROL PANEL AND
FUNCTIONAL CHECK
MEASUREMENT OF
CONVENTIONAL POWER AND
RATED POWER MEASUREMENT
06 0005 04 002 ROUTINE TESTS OF START UP TIME AND LOAD ITN61520 IEC STD+JOB DOC. IEC STD+JOB DOC. 3.1 O R
TAKING USING AN OSCILLOGRAPH
MEASUREMENT OF e.m.f.
WAVEFORM MECHANICAL
VIBRATION NOISE
MEASUREMENTS
P&Id, WIRING DIA., P&Id, WIRING DIA.,
ELECTRICAL HOOK-UP, ELECTRICAL HOOK-UP,
06 0005 04 004 INSTRUMENT INSTALLATION CHECK (INCLUDING TAGGING) ITN04001 2.1 O R
PRIMARY/PNEUMATIC PRIMARY/PNEUMATIC
HOOK-UP HOOK-UP
THIS ALSO INCLUDES THE REVIEW GENERAL
06 0005 04 008 FINAL, VISUAL AND DIMENSIONAL CHECK ITN04001 ITN04001 3.1 O R
OF SUPPLIER DOCUMENTATION ARRANGEMENT DWG
CROSS CHECK AT MFR. PREMISES,
06 0005 04 012 COMPLETENESS THREE WAY CHECK BEFORE SHIPMENT, AMONG: LISL, DWG / LISL ITN07068.00 ITN07068.00 PAR. 7.a 2.1 W R
DWG AND MATERIAL
ACCORDING TO VENDOR PRINT
OFF- SCHEDULE, THIS PAGE WILL BE
06 0015 00 000 SYNCHRONOUS GENERATOR
SKID REPLACED BY SUPPLIER QCP
REFERENCE
06 0015 01 000 RAW
06 0015 01 002 LADLE ANALYSIS ON MAIN COMPONENTS ASTM STD. ASTM STD. ASTM STD. 3.1 R R
06 0015 01 006 MECHANICAL PROPERTIES ON MAIN COMPONENTS ASTM STD. ASTM STD. ASTM STD. 3.1 R R
06 0015 15 000 ROUTINE TEST ACCEPTANCE TEST
06 0015 15 004 WINDING RESISTANCE AT COLD ITN62010 ITN62010 ITN62010 3.1 O R
06 0015 15 006 LOSSES AND EFFICIENCY ITN62010 ITN62010 ITN62010 3.1 O R
06 0015 15 008 NO LOAD SATURATION CHARACTERISTIC ITN62010 ITN62010 ITN62010 3.1 O R
06 0015 15 010 THREE-PHASE SHORT CIRCUIT CHARACTERISTIC ITN62010 ITN62010 ITN62010 3.1 O R
06 0015 15 012 SHAFT VOLTAGE AT NO LOAD ITN62010 ITN62010 ITN62010 3.1 O R

GE Oil & Gas


Pag. J.1.1/24
GE Proprietary & Confidential Information
PHASE SEQUENCE, DIRECTION OF ROTATION AND
06 0015 15 014 ITN62010 ITN62010 ITN62010 3.1 O R
VOLTAGE BALANCE CHECK
DIELECTRIC TEST ON GENERATOR WINDINGS (STATOR AND
06 0015 15 016 ROTOR), HEATERS AND BUILT-IN TEMPERATURE ITN62010 ITN62010 ITN62010 3.1 O R
DETECTORS
INSULATION RESISTANCE ON GENERATOR WINDING
06 0015 15 018 AFTER DIELECTRIC TEST ITN62010 ITN62010 ITN62010 3.1 O R
(STATOR AND ROTOR)
INSULATION RESISTANCE ON HEATERS, BUILT-IN
06 0015 15 020 ITN62010 ITN62010 ITN62010 3.1 O R
TEMPERATURE DETECTORS, BEARING INSULATION
06 0015 15 022 POLARIZATION INDEX ITN62010 ITN62010 ITN62010 3.1 O R
06 0015 15 024 OVERSPEED TEST ITN62010 ITN62010 ITN62010 3.1 O R
TO BE CARRIED OUT WITH
06 0015 15 026 VIBRATION TEST BEARING OIL AT RATED ITN62010 ITN62010 ITN62010 3.1 O R
TEMPERATURE
06 0015 18 000 TYPE TESTS CERTIFICATE
CERTFICATE OF TEST CONDUCTED
06 0015 18 002 TYPE TESTS ITN62010 ITN62010 ITN62010 2.1 R R
ON PROTOTYPE OR SIMILAR ITEM
06 0015 30 000 FINAL TESTS
P&Id, WIRING DIA., P&Id, WIRING DIA.,
ELECTRICAL HOOK-UP, ELECTRICAL HOOK-UP,
06 0015 30 002 INSTRUMENT INSTALLATION CHECK (INCLUDING TAGGING) ITN04001 2.1 O R
PRIMARY/PNEUMATIC PRIMARY/PNEUMATIC
HOOK-UP HOOK-UP
06 0015 30 004 PAINTING CHECK JOB SPEC. ITN07791 / ITN04001 JOB SPEC. 3.1 O R
DIMENSIONAL CHECK ON LIMIT ON GENERAL GENERAL
06 0015 30 006 ITN04001 3.1 O R
SUPPLY/INTERFACES/CONNECTIONS/TERMINAL POINTS ARRANGEMENT DWG ARRANGEMENT DWG
THIS ALSO INCLUDES THE REVIEW
06 0015 30 008 FINAL AND VISUAL CHECK ITN04001 ITN04001 ITN04001 2.1 O O
OF SUPPLIER DOCUMENTATION
CROSS CHECK AT MFR. PREMISES,
06 0015 30 012 COMPLETENESS THREE WAY CHECK BEFORE SHIPMENT, AMONG: LISL, DWG / LISL ITN07068.00 ITN07068.00 PAR. 7.a 2.1 W R
DWG AND MATERIAL
OFF-
SKID 06 0020 00 000 OIL INSULATED THREE-PHASE TRANSFORMER
06 0020 10 000 ROUTINE TESTS
06 0020 10 002 WINDING RESISTANCE AT COLD ITN61503 IEC STD IEC STD 3.1 O R
06 0020 10 004 MEASUREMENT OF VOLTAGE RATIO AND VECTOR GROUP ITN61503 IEC STD IEC STD 3.1 O R
06 0020 10 006 MEASUREMENT OF SHORT CIRCUIT VOLTAGE AT MAIN TAP ITN61503 IEC STD IEC STD 3.1 O R
MEASUREMENT OF SHORT CIRCUIT IMPEDANCE AND LOAD
06 0020 10 008 ITN61503 IEC STD IEC STD 3.1 O R
LOSSES
06 0020 10 010 MEASUREMENT OF NO LOAD LOSSES AND CURRENT ITN61503 IEC STD IEC STD 3.1 O R
06 0020 10 012 INDUCED AC VOLTAGE WITHSTAND TEST SHORT DURATION ITN61503 IEC STD IEC STD 3.1 O R
06 0020 10 014 ON-LOAD TAP CHANGER TEST ITN61503 IEC STD IEC STD 3.1 O R
06 0020 13 000 TYPE TESTS CERTIFICATE
CERTFICATE OF TEST CONDUCTED
06 0020 13 002 TYPE TESTS ITN61503 IEC STD IEC STD 2.1 R R
ON PROTOTYPE OR SIMILAR ITEM
06 0020 25 000 FINAL TESTS
06 0020 25 006 PAINTING CHECK JOB SPEC. ITN07791 / ITN04001 JOB SPEC. 3.1 O R
DIMENSIONAL CHECK ON LIMIT ON GENERAL GENERAL
06 0020 25 008 ITN04001 3.1 O R
SUPPLY/INTERFACES/CONNECTIONS/TERMINAL POINTS ARRANGEMENT DWG ARRANGEMENT DWG
THIS ALSO INCLUDES THE REVIEW
06 0020 25 010 FINAL AND VISUAL CHECK JOB SPEC. ITN04001 ITN04001 2.1 O R
OF SUPPLIER DOCUMENTATION

GE Oil & Gas


Pag. J.1.1/25
GE Proprietary & Confidential Information
CROSS CHECK AT MFR. PREMISES,
06 0020 25 014 COMPLETENESS THREE WAY CHECK BEFORE SHIPMENT, AMONG: LISL, DWG / LISL ITN07068.00 ITN07068.00 PAR. 7.a 2.1 W R
DWG AND MATERIAL
OFF-
SKID 06 0025 00 000 RESIN TYPE THREE-PHASE TRANSFORMER
06 0025 10 000 ROUTINE TESTS
06 0025 10 002 MEASUREMENT OF WINDING RESISTANCE ITN61510 IEC STD IEC STD 3.1 O R
MEASUREMENT OF VOLTAGE RATIO AND CHECK OF
06 0025 10 004 ITN61510 IEC STD IEC STD 3.1 O R
VOLTAGE VECTOR GROUP
MEASUREMENT OF VOLTAGE IMPEDANCE (AT MAIN TAP)
06 0025 10 006 ITN61510 IEC STD IEC STD 3.1 O R
AND LOAD LOSSES
MEASUREMENT OF NO-LOAD LOSSES AND NO-LOAD
06 0025 10 008 ITN61510 IEC STD IEC STD 3.1 O R
CURRENT
06 0025 10 010 SEPARATE SOURCE AC WITHSTAND VOLTAGE TEST ITN61510 IEC STD IEC STD 3.1 O R
SHORT DURATION INDUCED AC WITHSTAND VOLTAGE
06 0025 10 012 ACSD ITN61510 IEC STD IEC STD 3.1 O R
TEST
06 0025 10 014 PARTIAL DISCHARGE TEST ITN61510 IEC STD IEC STD 3.1 O R
06 0025 13 000 TYPE TESTS CERTIFICATE
CERTFICATE OF TEST CONDUCTED
06 0025 13 002 TYPE TESTS ITN61510 IEC STD IEC STD 2.1 R R
ON PROTOTYPE OR SIMILAR ITEM
06 0025 25 000 FINAL TESTS
06 0025 25 004 PAINTING CHECK JOB SPEC. ITN07791 / ITN04001 JOB SPEC. 3.1 O R
DIMENSIONAL CHECK ON LIMIT ON GENERAL GENERAL
06 0025 25 006 ITN04001 3.1 O R
SUPPLY/INTERFACES/CONNECTIONS/TERMINAL POINTS ARRANGEMENT DWG ARRANGEMENT DWG
THIS ALSO INCLUDES THE REVIEW
06 0025 25 008 FINAL AND VISUAL CHECK JOB SPEC. ITN04001 ITN04001 2.1 O R
OF SUPPLIER DOCUMENTATION
CROSS CHECK AT MFR. PREMISES,
06 0025 25 012 COMPLETENESS THREE WAY CHECK BEFORE SHIPMENT, AMONG: LISL, DWG / LISL ITN07068.00 ITN07068.00 PAR. 7.a 2.1 W R
DWG AND MATERIAL
OFF-
SKID 06 0030 00 000 HIGH VOLTAGE SWITCHGEAR
06 0030 02 000 ROUTINE TEST
06 0030 02 002 DIELECTRIC TEST ON THE MAIN CIRCUIT ITN62803 IEC STD IEC STD 3.1 O R
INSPECTION OF AUXILIARY AND CONTROL CIRCUITS AND
06 0030 02 004 VERIFICATION OF CONFORMITY TO THE CIRCUIT ITN62803 IEC STD IEC STD 3.1 O R
DIAGRAMS AND WIRING DIAGRAMS
TEST ON AUXILIARY AND
06 0030 02 006 FUNCTIONAL TEST ITN62803 IEC STD IEC STD 3.1 O R
CONTROL CIRCUITS
VERIFICATION OF PROTECTION AGAINST ELECTRICAL TEST ON AUXILIARY AND
06 0030 02 008 ITN62803 IEC STD IEC STD 3.1 O R
SHOCK CONTROL CIRCUITS
POWER - FREQUENCY VOLTAGE
06 0030 02 010 DIELECTRIC TEST ON THE MAIN CIRCUIT ITN62803 IEC STD IEC STD 3.1 O R
TEST
06 0030 02 012 MEASUREMENT OF THE RESISTANCE OF THE MAIN CIRCUIT ITN62803 IEC STD IEC STD 3.1 O R
06 0030 02 014 MECHANICAL OPERATION TEST ITN62803 IEC STD IEC STD 3.1 O R
TEST OF AUXILIARY ELECTRICAL, PNEUMATIC AND
06 0030 02 016 ITN62803 IEC STD IEC STD 3.1 O R
HYDRAULIC DEVICES
06 0030 04 000 TYPE TESTS CERTIFICATE
CERTFICATE OF TEST CONDUCTED
06 0030 04 002 TYPE TESTS ITN62803 IEC STD IEC STD 2.1 R R
ON PROTOTYPE OR SIMILAR ITEM

GE Oil & Gas


Pag. J.1.1/26
GE Proprietary & Confidential Information
IN CASE OF MULTIPLE AND
SYMILAR ITEMS WITHIN THE
06 0030 08 000 FINAL TESTS
SAME P.O. THIS TEST HAS TO BE
PERFORMED ONLY ON ONE UNIT
P&Id, WIRING DIA., P&Id, WIRING DIA.,
ELECTRICAL HOOK-UP, ELECTRICAL HOOK-UP,
06 0030 08 002 INSTRUMENT INSTALLATION CHECK (INCLUDING TAGGING) ITN04001 2.1 O R
PRIMARY/PNEUMATIC PRIMARY/PNEUMATIC
HOOK-UP HOOK-UP
06 0030 08 004 PAINTING CHECK JOB PAINTING SPEC. ITN07791 / ITN04001 JOB PAINTING SPEC. 3.1 O R
DIMENSIONAL CHECK ON LIMIT ON GENERAL GENERAL
06 0030 08 006 ITN04001 3.1 O R
SUPPLY/INTERFACES/CONNECTIONS/TERMINAL POINTS ARRANGEMENT DWG ARRANGEMENT DWG
THIS ALSO INCLUDES THE REVIEW
06 0030 08 008 FINAL AND VISUAL CHECK ITN62803 ITN04001 ITN04001 2.1 O O
OF SUPPLIER DOCUMENTATION
CROSS CHECK AT MFR. PREMISES,
06 0030 08 012 COMPLETENESS THREE WAY CHECK BEFORE SHIPMENT, AMONG: LISL, DWG / LISL ITN07068.00 ITN07068.00 PAR. 7.a 2.1 W R
DWG AND MATERIAL
ACCORDING TO VENDOR PRINT
OFF- HIGH VOLTAGE VARIABLE SPEED DRIVE SYSTEMS / SCHEDULE, THIS PAGE WILL BE
06 0045 00 000
SKID VARIABLE FREQUENCY DRIVER REPLACED BY SUPPLIER QCP
REFERENCE
06 0045 03 000 ASSEMBLED
CONVERTER FUNCTIONAL TEST
INCLUDING: COOLING UNIT PUMP
06 0045 03 002 ROUTINE TESTS ITN61513 IEC STD IEC STD 3.1 W R
SKID (IF ANY), VFD CONTAINER (IF
ANY)
06 0045 20 000 FINAL TESTS
P&Id, WIRING DIA., P&Id, WIRING DIA.,
ELECTRICAL HOOK-UP, ELECTRICAL HOOK-UP,
06 0045 20 002 INSTRUMENT INSTALLATION CHECK (INCLUDING TAGGING) ITN04001 2.1 O R
PRIMARY/PNEUMATIC PRIMARY/PNEUMATIC
HOOK-UP HOOK-UP
06 0045 20 004 PAINTING CHECK JOB SPEC. ITN07791 / ITN04001 JOB SPEC. 3.1 W R
DIMENSIONAL CHECK ON LIMIT ON GENERAL GENERAL
06 0045 20 006 ITN04001 3.1 W R
SUPPLY/INTERFACES/CONNECTIONS/TERMINAL POINTS ARRANGEMENT DWG ARRANGEMENT DWG
THIS ALSO INCLUDES THE REVIEW
06 0045 20 008 FINAL AND VISUAL CHECK ITN61513 ITN04001 ITN04001 2.1 W R
OF SUPPLIER DOCUMENTATION
CROSS CHECK AT MFR. PREMISES,
06 0045 20 012 COMPLETENESS THREE WAY CHECK BEFORE SHIPMENT, AMONG: LISL, DWG / LISL ITN07068.00 ITN07068.00 PAR. 7.a 2.1 W R
DWG AND MATERIAL
ACCORDING TO VENDOR PRINT
OFF- SCHEDULE, THIS PAGE WILL BE
06 0050 00 000 HARMONIC FILTER
SKID REPLACED BY SUPPLIER QCP
REFERENCE
06 0050 02 000 ASSEMBLED
FINAL TEST ON FILTER FINAL TEST
06 0050 02 002 ROUTINE TESTS ON MV SWITCHGEAR FINAL TEST JOB DOC. IEC STD IEC STD 3.1 W R
ON CONTAINER (IF ANY)
THIS ALSO INCLUDES THE REVIEW
06 0050 02 006 FINAL, VISUAL, PAINTING AND DIMENSIONAL CHECK JOB DOC. ITN04001 ITN04001 3.1 W R
OF SUPPLIER DOCUMENTATION
CROSS CHECK AT MFR. PREMISES,
06 0050 02 010 COMPLETENESS THREE WAY CHECK BEFORE SHIPMENT, AMONG: LISL, DWG / LISL ITN07068.00 ITN07068.00 PAR. 7.a 2.1 W R
DWG AND MATERIAL

GE Oil & Gas


Pag. J.1.1/27
GE Proprietary & Confidential Information
OFF-
SKID 06 0055 00 000 ELECTRIC STARTING MOTOR
06 0055 15 000 ROUTINE TESTS
06 0055 15 002 WINDING RESISTANCE AT COLD IEC 60034 IEC 60034 IEC 60034 3.1 R R
06 0055 15 004 NO LOAD TEST IEC 60034 IEC 60034 IEC 60034 3.1 R R
06 0055 15 006 SHORT CIRCUIT VOLTAGE IEC 60034 IEC 60034 IEC 60034 3.1 R R
06 0055 15 008 VIBRATION TEST IEC 60034 IEC 60034 IEC 60034 3.1 R R
06 0055 15 010 LOCKED ROTOR CURRENT IEC 60034 IEC 60034 IEC 60034 3.1 R R
06 0055 15 012 LOCKED ROTOR TORQUE IEC 60034 IEC 60034 IEC 60034 3.1 R R
06 0055 15 014 DIELECTRIC TEST IEC 60034 IEC 60034 IEC 60034 3.1 R R
06 0055 15 016 INSULATION TEST WINDINGS AND AUXILIARIES IEC 60034 IEC 60034 IEC 60034 3.1 R R
06 0055 15 018 AUXILIARY CIRCUITS CONTROL IEC 60034 IEC 60034 IEC 60034 3.1 R R
06 0055 15 020 DIRECTION OF ROTATION CONTROL IEC 60034 IEC 60034 IEC 60034 3.1 R R
06 0055 18 000 TYPE TESTS CERTIFICATE
CERTFICATE OF TEST CONDUCTED
06 0055 18 002 TYPE TESTS IEC 60034 IEC 60034 IEC 60034 2.1 R R
ON PROTOTYPE OR SIMILAR ITEM
06 0055 30 000 FINAL TESTS
06 0055 30 004 PAINTING CHECK JOB PAINTING SPEC. ITN07791 / ITN04001 JOB PAINTING SPEC. 3.1 O R
DIMENSIONAL CHECK ON LIMIT ON GENERAL GENERAL
06 0055 30 006 ITN04001 3.1 O R
SUPPLY/INTERFACES/CONNECTIONS/TERMINAL POINTS ARRANGEMENT DWG ARRANGEMENT DWG
THIS ALSO INCLUDES THE REVIEW
06 0055 30 008 FINAL AND VISUAL CHECK ITN61511 / JOB DOC ITN04001 ITN04001 2.1 O R
OF SUPPLIER DOCUMENTATION
CROSS CHECK AT MFR. PREMISES,
06 0055 30 012 COMPLETENESS THREE WAY CHECK BEFORE SHIPMENT, AMONG: LISL, DWG / LISL ITN07068.00 ITN07068.00 PAR. 7.a 2.1 W R
DWG AND MATERIAL
OFF-
SKID 06 0060 00 000 MOTOR CONTROL CENTER PANEL
06 0060 10 000 ROUTINE TESTS
AT VOLTAGE VALUE REQUIRED BY
06 0060 10 002 DIELECTRIC TEST ITN62802 / JOB DOC. IEC STD IEC STD 3.1 O R
DATA SHEET
06 0060 10 004 DIELECTRIC TEST ON AUXILIARY CIRCUITS ITN62802 / JOB DOC. IEC STD IEC STD 3.1 O R
06 0060 10 006 TEST OF MECHANICHAL FUNCTIONING ITN62802 / JOB DOC. IEC STD IEC STD 2.1 O R
TEST OF CONTACTORS WITH
TEST OF FUNCTIONING OF ALL MAIN AND AUXILIARY AUXILIARY VOLTAGES AT
06 0060 10 008 ITN62802 / JOB DOC. IEC STD IEC STD 2.1 O R
EQUIPMENT EXTREME LIMITS OF REQUIRED
VALUES
CHECKING OF THE WIRING AND OF THE CONTROL
06 0060 10 012 ITN62802 / JOB DOC. IEC STD IEC STD 2.1 O R
SEQUENCES
06 0060 10 014 MEASUREMENT OF INSULATION RESISTANCE ITN62802 / JOB DOC. IEC STD IEC STD 3.1 O R
06 0060 15 000 TYPE TESTS CERTIFICATE
CERTFICATE OF TEST CONDUCTED
06 0060 15 002 TYPE TESTS ITN62802 / JOB DOC. IEC STD IEC STD 2.1 R R
ON PROTOTYPE OR SIMILAR ITEM
06 0060 25 000 FINAL TESTS
P&Id, WIRING DIA., P&Id, WIRING DIA.,
ELECTRICAL HOOK-UP, ELECTRICAL HOOK-UP,
06 0060 25 002 INSTRUMENT INSTALLATION CHECK (INCLUDING TAGGING) ITN04001 2.1 O R
PRIMARY/PNEUMATIC PRIMARY/PNEUMATIC
HOOK-UP HOOK-UP
06 0060 25 004 PAINTING CHECK JOB SPEC. ITN07791 / ITN04001 JOB SPEC. 3.1 O R
DIMENSIONAL CHECK ON LIMIT ON GENERAL GENERAL
06 0060 25 006 ITN04001 3.1 O R
SUPPLY/INTERFACES/CONNECTIONS/TERMINAL POINTS ARRANGEMENT DWG ARRANGEMENT DWG

GE Oil & Gas


Pag. J.1.1/28
GE Proprietary & Confidential Information
THIS ALSO INCLUDES THE REVIEW
06 0060 25 008 FINAL AND VISUAL CHECK ITN04001 ITN04001 ITN04001 2.1 O R
OF SUPPLIER DOCUMENTATION
CROSS CHECK AT MFR. PREMISES,
06 0060 25 012 COMPLETENESS THREE WAY CHECK BEFORE SHIPMENT, AMONG: LISL, DWG / LISL ITN07068.00 ITN07068.00 PAR. 7.a 2.1 W R
DWG AND MATERIAL
OFF-
SKID 06 0070 00 000 GENERATOR CONTROL & PROTECTION PANEL
06 0070 02 000 ASSEMBLED
06 0070 02 006 DIELECTRIC TEST SOK7260891 IEC STD / MFR STD IEC STD / MFR STD 3.1 O R
06 0070 02 008 MEASUREMENT OF INSULATION RESISTANCE SOK7260891 IEC STD / MFR STD IEC STD / MFR STD 3.1 O R
SOK7260891 / JOB
06 0070 02 012 PAINTING CHECK SOK7260891 SOK7260891 / ITN04001 2.1 O R
PAINTING SPEC.
DIMENSIONAL CHECK ON LIMIT ON GENERAL
06 0070 02 014 SOK7260891 ITN04001 3.1 O R
SUPPLY/INTERFACES/CONNECTIONS/TERMINAL POINTS ARRANGEMENT DWG
THIS ALSO CHECK OF
NAMEPLATES AND INCLUDES THE
06 0070 02 016 FINAL AND VISUAL CHECK SOK7260891 ITN04001 ITN04001 2.1 O R
REVIEW OF SUPPLIER
DOCUMENTATION
CROSS CHECK AT MFR. PREMISES,
06 0070 02 018 COMPLETENESS THREE WAY CHECK BEFORE SHIPMENT, AMONG: LISL, DWG / LISL ITN07068.00 ITN07068.00 PAR. 7.a 2.1 W R
DWG AND MATERIAL
OFF- BATTERY CHARGER, D.C. DISTRIBUTION AND INVERTER
06 0075 00 000
SKID PANELS
06 0075 10 000 ROUTINE TESTS
06 0075 10 002 CHECK OF THE DEGREE PROTECTION ITN62000.01 IEC STD IEC STD 2.1 O R
06 0075 10 004 STATIC PERFORMANCE TEST ITN62000.01 IEC STD IEC STD 3.1 O R
06 0075 10 006 DYNAMIC PERFORMANCE TEST ITN62000.01 IEC STD IEC STD 3.1 O R
06 0075 10 008 RIPPLE MEASUREMENT ITN62000.01 IEC STD IEC STD 3.1 O R
06 0075 10 010 MECHANICAL OPERATION TEST ITN62000.01 IEC STD IEC STD 3.1 O R
06 0075 10 012 ELECTRICAL OPERATION TEST ITN62000.01 IEC STD IEC STD 3.1 O R
06 0075 10 014 WIRING AND SEQUENCE TEST ITN62000.01 IEC STD IEC STD 2.1 O R
EXCLUDING THOSE UTILIZING
06 0075 10 016 DIELECTRIC TEST FOR MAIN AND AUXILIARY CIRCUITS ITN62000.01 IEC STD IEC STD 3.1 O R
ELECTRONIC DEVICES
EXCLUDING THOSE UTILIZING
06 0075 10 018 INSULATION RESISTANCE MEASUREMENT ITN62000.01 IEC STD IEC STD 3.1 O R
ELECTRONIC DEVICES
06 0075 15 000 TYPE TESTS CERTIFICATE
CERTFICATE OF TEST CONDUCTED
06 0075 15 002 TYPE TESTS ITN62000.01 IEC STD IEC STD 2.1 R R
ON PROTOTYPE OR SIMILAR ITEM
06 0075 25 000 FINAL TESTS
P&Id, WIRING DIA., P&Id, WIRING DIA.,
ELECTRICAL HOOK-UP, ELECTRICAL HOOK-UP,
06 0075 25 002 INSTRUMENT INSTALLATION CHECK (INCLUDING TAGGING) ITN04001 2.1 O R
PRIMARY/PNEUMATIC PRIMARY/PNEUMATIC
HOOK-UP HOOK-UP
06 0075 25 004 PAINTING CHECK JOB SPEC. ITN07791 / ITN04001 JOB SPEC. 3.1 O R
DIMENSIONAL CHECK ON LIMIT ON GENERAL GENERAL
06 0075 25 006 ITN04001 3.1 O R
SUPPLY/INTERFACES/CONNECTIONS/TERMINAL POINTS ARRANGEMENT DWG ARRANGEMENT DWG
THIS ALSO INCLUDES THE REVIEW
06 0075 25 008 FINAL AND VISUAL CHECK ITN04001 ITN04001 ITN04001 2.1 O R
OF SUPPLIER DOCUMENTATION
CROSS CHECK AT MFR. PREMISES,
06 0075 25 012 COMPLETENESS THREE WAY CHECK BEFORE SHIPMENT, AMONG: LISL, DWG / LISL ITN07068.00 ITN07068.00 PAR. 7.a 2.1 W R
DWG AND MATERIAL

GE Oil & Gas


Pag. J.1.1/29
GE Proprietary & Confidential Information
OFF-
SKID 06 0080 00 000 GENERATOR ELECTRIC PROTECTIONS
06 0080 02 000 ASSEMBLED
DIMENSIONAL CHECK AND
VISUAL INSPECTION, PAINTING
CHECK, CHECK OF LIST OF
COMPONENTS (TYPE AND SIZE),
CHECK THAT PROTECTION RELAY
TERMINALS ARE ACCORDIND TO
PROTECTION CONNECTION
DIAGRAM, TEST OF CORRECT
06 0080 02 002 ROUTINE TEST OPERATION OF EACH IEC STD / JOB DOC IEC STD / JOB DOC IEC STD / JOB DOC 3.1 O R
PROTECTION FUNCTION, DIGITAL
INPUT/OUTPUTAND INDICATING
LED ACCORDING TO PROTECTION
SETTING STUDY DIELECTRIC TEST,
TEST OF SYNCRONIZING RELAYS IF
INCLUDED IN SCOPE, CHECK OF
CERTIFICATES AND FINAL
DOCUMENTATION
CROSS CHECK AT MFR. PREMISES,
06 0080 02 004 COMPLETENESS THREE WAY CHECK BEFORE SHIPMENT, AMONG: LISL, DWG / LISL ITN07068.00 ITN07068.00 PAR. 7.a 2.1 W R
DWG AND MATERIAL
NICKEL-CADMIUM OR LEAD-ACID
OFF-
06 0090 00 000 STATIONARY BATTERIES (VENTED TYPE OR VALVE
SKID
REGULATED TYPE)
06 0090 02 000 ASSEMBLED
ITN61506 / ITN61507 /
06 0090 02 002 FACTORY TESTS INCLUDING CAPACITY TEST IEC STD IEC STD 3.1 O R
ITN61508
ITN61506 / ITN61507 /
06 0090 02 004 DIMENSIONAL CHECK ITN04001 ITN04001 2.1 O R
ITN61508
ITN61506 / ITN61507 /
06 0090 02 006 FINAL, VISUAL CHECK ITN04001 ITN04001 2.1 O R
ITN61508
OFF-
SKID 06 0105 00 000 EXCITATION PANEL
06 0105 02 000 ASSEMBLED
THIS INCLUDES: TEST OF
CORRECT OPERATION OF EACH
PROTECTION AND ALL OTHER
EQUIPMENT, WIRING AND
CONTROL SEQUENCES CHECK,
DIELECTRIC TEST, MEASUREMENT
OF INSULATION RESISTANCE,
SYNCHRONIZING EQUIPMENT,
INSTRUMENTATION AND
PROTECTION RELAYS
06 0105 02 002 FUNCTIONAL TEST FUNCTIONAL TEST SOK7260891 MFR STD MFR STD 3.1 O R
06 0105 02 006 DIMENSIONAL CHECK SOK7260891 MFR STD JOB SPEC/DWG 2.1 O R
INCLUDING TAGGING AND
06 0105 02 010 FINAL VISUAL CHECK SOK7260891 ITN04001 JOB SPEC/DWG 2.1 O R
TERMINAL BOARD CHECK

GE Oil & Gas


Pag. J.1.1/30
GE Proprietary & Confidential Information
CROSS CHECK AT MFR. PREMISES,
06 0105 02 012 COMPLETENESS THREE WAY CHECK BEFORE SHIPMENT, AMONG: LISL, DWG / LISL ITN07068.00 ITN07068.00 PAR. 7.a 2.1 W R
DWG AND MATERIAL
FOR TESTINGS AND INSPECTIONS
OF MAJOR SUB ITEMS
07 0010 00 000 MACHINE(S) SKID INCLUDED/ASSEMBLED ON THIS
SKID, REFER TO THE DEDICATED
PAGE(S) OF THIS QCP - GT
07 0010 02 000 RAW BASEPLATE
07 0010 02 002 LADLE ANALYSIS OF COMPONENTS ITN07759 ASTM STD ASTM STD 2.1 R R
07 0010 02 006 MECHANICAL PROPERTIES OF COMPONENTS ITN07759 ASTM STD ASTM STD 2.1 R R
07 0010 06 000 FABRICATED / MACHINED BASEPLATE
07 0010 06 010 NON DESTRUCTIVE EXAMINATIONS ON WELDS ITN07759 ITN03402.03 ITN07759 3.1 O R
07 0010 06 014 EYEBOLTS/LIFTING BITTS WELDS NDT ITN07759 ITN03402.03 ITN07759 3.1 O R
STATIC SEAL TEST OF OIL TANK (WHEN OIL TANK IS 2.1 WATER QUALITY ANALYSIS
07 0010 06 022 ITN07759 ITN07036 ITN07759 3.1 O R
INTEGRATED IN THE BASEPLATE) CERTIFICATE TO BE ATTACHED
JOB PAINTING
07 0010 06 030 PAINTING CHECK ITN07759 ITN07791 / ITN04001 SPECIFICATION 3.1 O R
DIMENSIONAL CHECK ON LIMIT ON
07 0010 06 034 ITN07759 ITN07759 DWG 3.1 O R
SUPPLY/INTERFACES/CONNECTIONS/TERMINAL POINTS
THIS ALSO INCLUDES THE REVIEW
07 0010 06 038 FINAL, VISUAL AND CLEANLINESS CHECK API614 ITN04001 ITN04001 3.1 O R
OF SUPPLIER DOCUMENTATION
CROSS CHECK AT MFR. PREMISES,
07 0010 06 046 COMPLETENESS THREE WAY CHECK BEFORE SHIPMENT, AMONG: LISL, DWG / LISL ITN07068.00 ITN07068.00 PAR. 7.a 2.1 W R
DWG AND MATERIAL
07 0010 30 000 ELECTRICAL SYSTEM ASSEMBLY SKID
07 0010 30 002 EQUIPMENT TO JBs WIRING CHECK WIRING DIA. ITN04004 WIRING DIA. 2.1 W W
P&Id, WIRING DIA., P&Id, WIRING DIA.,
ELECTRICAL HOOK-UP, ELECTRICAL HOOK-UP,
07 0010 30 004 INSTRUMENT INSTALLATION CHECK (INCLUDING TAGGING) ITN04004 2.1 W W
PRIMARY/PNEUMATIC PRIMARY/PNEUMATIC
HOOK-UP HOOK-UP
07 0010 42 000 FINAL TESTS ON SKID
07 0010 42 006 PAINTING CHECK ITN04004 JOB SPEC. ITN07791 / ITN04004 JOB SPEC. 3.1 W O
DIMENSIONAL CHECK (ON LIMITS OF SUPPLY AND GENERAL GENERAL
07 0010 42 008 ITN04004 2.1 W W
FOUNDATIONS) ARRANGEMENT DWG ARRANGEMENT DWG
07 0010 42 020 FINAL, VISUAL CHECK ITN04004 ITN04004 ITN04004 2.1 W W
OFF-
SKID 12 0270 00 000 UNIT CONTROL SYSTEM
12 0270 02 000 ASSEMBLED
VISUAL AND DIMENSIONAL
12 0270 02 004 SYSTEM HARDWARE AND STEELWORK CHECK CHECK OF STRUCTURAL ITN04240 MFR STD MFR STD 3.1 O R
CHARACTERISTICS
INCLUDING: WIRING INSPECTION,
VERTICAL SELECTIVITY OF
AUTOMATIC BREAKERS, CHECK OF
CORRECT SIGNALS
12 0270 02 012 ELECTRIC INSPECTION SPLITTING/SEGREGATION, POINT ITN04240 MFR STD MFR STD 3.1 O R
TO POINT WIRING VERIFICATION,
AC/DC FUNCTIONALITY TEST,
DIELECTRIC AND INSULATION
TEST, PROTECTIVE BONDING

GE Oil & Gas


Pag. J.1.1/31
GE Proprietary & Confidential Information
CIRCIUT CONTINUITY TEST,
EARTHING CHECK

ON JOB FUNCTIONS ONLY; I/O


12 0270 02 016 FUNCTIONAL TEST CHECK SPOT (e.g. 20%), MAIN ITN04240 MFR STD MFR STD 3.1 O O
START/STOP/AUX. SEQUENCES
COMMUNICATION LINKS
BETWEEN ALL SYSTEMS INSIDE
12 0270 02 032 COMMUNICATION TEST UCS AND THE EXTERNAL SYSTEMS ITN04240 MFR STD MFR STD 3.1 O R
TO WHICH THEY ARE CONNECTED
(e.g. Bently Nevada, CCC)
12 0270 02 084 PAINTING CHECK ITN04240 ITN07791 / ITN04001 PAINTING SPEC 3.1 W R
INCLUDING TERMINAL BOARD
12 0270 02 090 FINAL VISUAL CHECK CHECK AND CERTIFICATION AND ITN04240 MFR STD MFR STD 2.1 W R
MDR DOCUMENTATION CHECK
CROSS CHECK AT MFR. PREMISES,
12 0270 02 100 COMPLETENESS THREE WAY CHECK BEFORE SHIPMENT, AMONG: LISL, DWG / LISL ITN07068.00 ITN07068.00 PAR. 7.a 2.1 W R
DWG AND MATERIAL

GE Oil & Gas


Pag. J.1.1/32