Documente Academic
Documente Profesional
Documente Cultură
AIDS
TABLE OF CONTENTS
STRUCTURAL SPECIFICATIONS
SECTIONS
601 : Materials
602 : Standards Symbols and Nomenelature
603 : Camber
100.0 GENERAL REQUIREMENTS
SECTIONS
101.3 In case of conflict between the Structural Plans and the Structural
Specifications, the Plans shall govern.
The design dead loads unless otherwise specified in the structural plans
are as follows:
The design live loads unless otherwise specified in the Plans are as
follows:
These design live loads shall never be exceeded at any time during the
life of the structure without the written consent of the Structural Engineer.
The design earthquake loads are as per the provision of the “Uniform
Building Code (UBC) Edition” for earthquake zone 4; “1991 ASEP Guide
for the Design
102.4 LOADS
The design wind load is as per the provision of the “National Structural
Code of the Philippines (NSCP) 1992”.
Equipment not indicated in the plans shall not be installed without the
approval of the Structural Engineer.
The Manufacturer shall submit equipment data specifying the weight, and
its reaction at the base, and its vibration characteristics.
103.2 Concrete aggregate shall conform to ASTM C33 except aggregate failing
to meet these specifications but which have produced concrete of
adequate strength and durability may be subject to the approval of the
Structural Engineer.
103.3 Water used in mixing shall be clean and free from injurious amounts of
oils, acids, alkalis, salts, organic materials or other substances deleterious
to concrete shall not contain deleterious amount of chloride ions.
103.5 Wires and standard for tendons in pre-stressed concrete shall conform to
ASTM 416 and ASTM 421 respectively.
103.8 Concrete cylinder samples for strength test of each class of concrete shall
be taken neither less than once per day nor less than once for each 115
cubic meters of concrete or for each 465 square meters of the surface
area.
The cylinder samples for strength test shall be taken cured and tested in
accordance with ASTM C 172, ASTM C3 1, and ASTM C3 9.
103.13 CURING
104.1 Unless otherwise indicated in the drawing, the minimum 28-day cylinder
compressive strength shall be as follows:
105.1 Unless otherwise indicated in the plans, the allowable soil pressure shall
be at least 150 KPa.
105.2 Excavation for footings shall be carried to a depth at least 0.60m of the
virgin soil or 1.00m below the original ground, whichever is deeper.
105.3 To make sure of the depth of excavation, the Contractor shall excavate
first at least four (4) footings located at the comers of the proposed
building. The depth of excavation shall be confirmed by the Structural
Engineer as a basis of the excavation for all other footings.
105.4 The Structural Engineer shall be informed of any deviation of the soil
layering as compared to the first four (4) excavations.
105.5 Existing underground pipes, tunnels, etc. shall be brought to the attention
of the Structural Engineer for evaluation.
105.6 Any excavation adjacent to any existing structure shall be provided with
adequate sheet piling by the Contractor. The sheet piles shall be properly
designed to resist the earth and water pressures as well as surcharge
loadings on the footings of the adjacent existing structures.
105.7 Unless otherwise specified by the Structural Engineer, the CHB wall
footing shall be as shown in the Structural Plan.
105.8 Reinforced Concrete Slabs on fill shall be 100mm thick with 12mm
diameter reinforcing bars at 0.30m o.c. each way unless otherwise
specified in the plans.
106.1 Unless otherwise noted in the plans or specifications, camber all R.C.
Beams at least 6mm for every 4,500mm of clear span except cantilevers
which shall be 18mm for every 3,000mm of clear span.
106.2 If there are two (2) or more layers of reinforcing bars, use 25mm
separators spaced at 0.90m o.c. In no case shall there be less than two
(2) separators between layers of bars.
106.3 If beams reinforcing bars end in wall, the clear distance from the bar to the
face of the wall shall not be less than 5 bar diameter. The reinforcing bar
shall terminate on standard 90 degree hook. Minimum embedment shall
be 40 bar diameter for tension and, 20 bar diameter for compression bars.
106.4 When a beam crosses a girder, rest beam bars on top of the girder bars.
At column intersection, girder bars shall be on top of the beam bars.
106.5 Length of bar cut-offs and bar clearances shall be as shown in the
Structural Plans.
106.6 Top bars splices shall be at midspan and bottom bar splices at 100m from
the face of the column. Unless otherwise indicated in the plans, spliced
lengths and development lengths shall be in accordance with the
following:
Basic development length bar shall be multiplied by 1.30 for top bars.
107.1 Unless otherwise noted in the plans or specifications, camber all R.C.
slabs 3mm for every 3,300mm of the shorter span.
107.2 If slabs are reinforced both ways, bars along the shorter span shall be
placed below those along the longer span at the center and over the
longer bars near the supports,
107.3 Lengths of bar cut-offs shall be shown in the Structural Plans.
107.4 For flat slabs, span bottom bars shall be placed below the shorter span
bars and top bars, vice versa.
107.5 Concrete covering shall be 20mm clear for top and bottom bars.
107.6 Unless otherwise specified by the Structural Engineer, bar chairs shall be
provided at least 600mm each way to support the top and bottom bars
separately.
108.1 Unless otherwise indicated, the column pedestal embedded in the ground
shall be larger than the column as per plan at the ground floor level.
108.2 Construction joints in columns shall be located at the top of the pedestal
(ground floor line) or at least a distance above the floor equal to the
maximum dimension of the column or one-sixth (1/6) storey height.
108.3 All ties shall be fastened to column vertical reinforcement by wires at all
intersection points of ties and column rebars.
108.4 Not more than one-half (1/2) of the total number of bars shall be spliced at
the same level. The lap splice shall be 1.3 of the development length.
Splices shall be staggered at a distance of at least 40 bar diameter.
108.5 Column bar splice lengths shall be as shown in the Structural Plan.
108.6 Lap welded splices may be used in lieu of the above. The welded splice
must develop at least 125 percent of the bigger bar yield strength, 1.25
Ab*fy. Not butt-weld splices are allowed unless otherwise permitted by the
Structural Engineer.
109.1 Unless otherwise indicated in the Plans, the R.C. Wall vertical bars shall
enclose the horizontal bars.
109.2 Reinforcing bars shall have at least 30mm concrete clearance except at
100mm wall where they shall be at the center.
109.3 Extend vertical bars 600mm above the floor level to provide for splices
when necessary.
109.4 Horizontal and vertical bars conforming to ASTM A615 shall have a
minimum splice lapping and wired #16 G.I. tie wire provided that splices in
adjacent bars are staggered at least 1.50m o.c. Not more than one-half
(1/2) of the total number of bars shall be spliced at the same line. Splices
shall be staggered at a distance of at least 40 bar diameter.
109.6 At wall intersections and corners, anchorage length provided shall be as
shown in the Structural Plan or otherwise specified by the Structural
Engineer.
110.1 Unless otherwise specified, the vertical and horizontal reinforcements for
CHB shall be 1000mm and 400mm o.c. respectively for all wall thickness.
Lap splices shall be at least 300mm.
110.3 Lintel beams shall be provided at the top of the CHB wall openings. It shall
be extended at least 0.20m beyond the openings.
110.4 For high walls, lintel beams shall be provided at 3.0m o.c.
110.5 For long walls, lintel beams acting as column shall be provided at 6.0m
o.c.
110.6 Where CHB wall adjoins R.C. columns and beams prior to pouring to
match CHB wall reinforcement. The dowel shall be 12mm bars at 3.0m
o.c.
110.7 Where the top CHB walls adjoins a beam a 50mm gap to be filled with a
soft material like styrophor.
110.8 Where the side if the CHB wall adjoins a column provide a 50mm gap to
with a soft material like styrophor.
110.9 Where columns and beams are to be poured without CHB wall dowel,
provide ramsets and 16 gauged galvanized steel straps 0.40m o.c. No
chipping of concrete columns and beams is allowed unless otherwise
permitted by the Structural Engineer.
111.1 Unless otherwise specified by the Structural Engineer the following are the
acceptable structural tolerances for cast-in-place concrete construction. All
dimensions which are not within the required tolerances shall be corrected
prior to pouring of concrete. Tolerances for pre-cast concrete construction
shall be ½ of the values given below:
112.1 The following minimum concrete cover shall be provided for reinforcing
bars, pre-stressing tendons or ducts. For bundled bars, the minimum
cover shall be equal the equivalent diameter of the bundled bars needed
but not more than 50mm on the tabulated minimum whichever is greater.
Minimum Cover
a. Cast against and permanently
exposed to earth ……………………… 75mm
Minimum Cover
Other Members
20mm (h to 32mmCp) ………………… 40mm
16mm bar, W3 1 or D3 1 wire,
and smaller ……………………………. 30mm
113.2 Unless otherwise noted in the plans the minimum yield strength of the
reinforcing bars corresponding to the structural member shall be as
enumerated:
fy …….. 230MPa
Footing and Tie Beams
Columns, R.C. Floor Beams and girders
Suspended Slabs
Parapets and Curtain Walls, Stairs
Filler Walls, Gutter
Slab on Fill/Grade, Bedded Slab, Partitions
Catch Basins, Sump Pits, Sidewalks
Pavements, Sedimentation Tanks, Manholes
and other related Sanitary Structures
Retaining Walls and Loads Bearing Walls
113.3 Splice and anchorage lengths shall follow those set for development
lengths (Ld) unless otherwise indicated in the plans or approved by the
Structural Engineer.
114.1 A standard hook for rebars if required shall be either of the following:
114.2 Minimum diameter of bend measured on the inside of the bar shall be as
follows:
115.1 Welding is to be allowed only if the reinforcing bars are weld able.
115.2 The welded splices must developed at least 125% of the bigger bar yield
strength 1.25 Ab*fy.
115.3 Built-welded splice when used shall be considered 75% efficient. The
remaining 50% capacity to develop 125% of the tensile capacity of the bar
shall be provided for by an additional welded lap splice connection on the
same joint.
115.4 Details of all splices shall be submitted by the contractor for approval by
the Structural Engineer.
116.1 Construction joints shall be located near the middle of the span of slabs,
beams or girders.
116.3 Construction joints in column shall be located a distance above the floor
equal to maximum dimension or 1/6 the storey height.
116.5 Construction joints in walls, slabs and other structures that are subjected
to water pressure shall be provided with water stops. Kind, type, and size
of water stops shall be as approved by the Structural Engineer.
116.6 All construction joints should be bounded by epoxy (old to new) before the
resumption of pouring.
117.1 All electrical conduits shall be placed between the top and bottom
reinforcements in slabs and R.C. walls.
117.2 The spacing of these conduits shall be at least three (3) diameter.
118.0 PIPES EMBEDDED IN CONCRETE
118.1 Pipes and their fittings shall not displace more than four (4) percent of the
cross-sectional area of the column.
118.4 Concrete cover for pipes shall be at least 40mm for concrete surfaces
exposed to weather or in contact with the ground or 20mm for concrete
surfaces not exposed to the ground or weather.
119.1 Forms shall be removed in such a manner as to the safety of the structure.
119.2 Unless otherwise specified by the Structural Engineer, the following shall
be the basis of removal of forms and shoring for Reinforced Concrete
(R.C.) construction:
Age of Concrete
Foundations 24 days
Columns 2 days
Walls 2 days
Sides of Beams and Girder 2 days
Floor Slabs 14 days
Shoring for Beams and Girder 14 days
Suspended Slabs 14 days
119.3 For post-tensioned (P.T.) construction the following shall be the basis of
removal of forms and shoring:
Age of Concrete
P.T. Beams’ side forms 2 days
R.C. Columns’ side forms 2 days
R.C. Slab shoring and bottom forms 7 days
P.T. Beam shoring after post-tensioning
P.T. Slab shoring after post-tensioning
201.1 Furnish all materials, equipment, labor, plant and other facilities to
complete the structural excavation.
201.2 All works included under this division shall be subject to the General
Conditions accompanying these specifications. The Contractor and Sub
contractor are required to refer especially thereto.
201.3 Examine the site, records of existing utilities and construction, records of
the test borings and sub-surface exploration reports and soil samples to
determine all conditions under which will be performed. The records of test
boring are not guaranteed to represent all conditions that will be
encountered.
202.1 The Standards and Codes applicable to only a portion of the work
specified in this section are referenced in the relevant parts or clauses.
Standards and Codes which are generally applicable to the work of this
section are listed hereinafter:
203.0 SUBMITTALS
203.1 Samples of any materials or product to be used in the works. They shall
be properly marked and accompanied by a letter of transmittal clearly
listing the samples, their intended use and locations in the works.
203.2 TEST REPORTS
The Testing Laboratory shall perform all tests and submit reports specified
in this section. The testing Laboratory shall be responsible for conducting
and interpreting the tests; shall state each report whether or not the test
specimens comply with all requirements of the Contract Documents and
shall especially note any deviation there from.
The Testing Laboratory shall perform all tests herein specified and any
additional tests as may be required.
1. Footing Subgrades
At least three (3) Field Density Tests ASTM D1556 or ASTM D2167
shall be taken at locations and elevations as directed.
205.5 TOLERANCES
Finish areas top receive top soil 25mm (1 in) below the required
subgrade elevation, grades and cross-sections.
Finish areas under pavement and walks within 12mm below the
required sub-base.
3. Footings
5. Other Areas
206.0 MATERIALS
207.0 PREPARATION
207.1 Clear and grub shrubs, stumps, roots, brush, vegetation, rubbish and
debris within the construction limit lines, except as otherwise designated to
remain or to be relocated.
\
208.0 EXCAVATION
208.1 GENERAL
1. Structural Members
Structural members shall include frame slabs, grade beams, and utility
tunnels.
2. Subgrades
b. If the subgrade does not meet the above requirements, compact the
subgrade by rolling with suitable compaction equipment to obtain the
density specified.
Materials for fill and backfill shall be general fill as herein before specified,
obtained from the required excavation on site, if acceptable, or from
borrowed sources.
209.4 PLACING
209.5 COMPACTION
Provide specified gravel fill beneath all concrete slabs on grade and as
shown elsewhere. Place gravel fill to depth shown and in no case less
than 4in (100mm) deep. Compact fill with vibratory or tamping methods to
key the stone into a firm base; except hand tamp over subsoil drains.
209.7 BACKFILLING AGAINST FOUNDATION WALLS
After the completion of foundation walls and removal of forms, clean the
surface of application before applying damp-proofing or waterproofing and
placement of backfill as herein before specified for fill operations. Maintain
symmetrical backfill loading and compact each layer by hand tampers or
other unsatisfactory conditions.
3. Place drainage fill from top of left above footing subsoil drains to within
18in (450mm) of finished grade, except as otherwise shown. Place and
compact as necessary to obtain the required densities under paved
areas and areas general grading as specified herein.
301.1 Furnish all materials, equipment, labor, plant and other facilities to
complete concrete reinforcement as shown on the drawings and herein
specified.
301.2 All works under this division shall be subject to general conditions
accompanying these specifications. The Contractor and Subcontractor are
to refer especially thereto.
302.1 The standards and codes applicable to only portion of the work specified
in this section are referenced in the relevant parts of clauses. Standards
and codes which are generally applicable to the works of this section are
listed hereinafter.
303.0 SUBMITTALS
Shop test shall show the result of required shop tests of materials,
equipment or systems certified in writing by the manufacturer or its
authorized representative.
Field test reports shall show the results of required tests and compliance
with approved procedures, certified by the contractor.
304.0 MATERIALS
304.1 Bars ASTM Grade 40, 40 Ksi (276MPa) for 10mm bars and above
3. Exposed Painted or
Concealed Protected: Class D “Stainless Steel”
4. Exterior Unpainted
Or Exposed Protected: Class E “Special Stainless”
305.1 REINFORCEMENT
Provide concrete reinforcement made from billet steel and from dirt, rust,
oil and grease, and any other foreign substance that will decrease bonding
of concrete with steel reinforcement. Accurately bend or form fabricated
bars to the shapes and dimensions shown using method that will not
damage materials. Do not weld unless especially shown or approved by
the Construction Manager.
305.2 IDENTIFICATION
306.2 TOLERANCES
306.3 DOWELS
307.0 SPLICES
307.1 Lap splices all bars up to no. 11 (36mm) in accordance with ACI 318
unless otherwise shown. Follow AWS D121 recommendations for welded
splices where shown.
308.0 REPAIR
501.1 Furnish all labor, materials, equipment, plant and other facilities to
complete the cast – in – place concrete as shown and hereinafter
specified.
501.2 All work under this division shall be subject to the General Conditions
companying these specifications. The Contractor and sub – contractor for
this portion of the work is required to refer especially thereto.
503.0 SUBMITTALS
503.5 SAMPLES
Shop fest shall show the results of required shop test of materials,
equipment or system certified in writing by the manufacturer or its
authorized representative.
Field Test Reports shall show the results of required field test and
compliance with approved procedures, certified by the Contractor.
Upon the delivery at site of work, cement and admixtures shall be stored
separately in dry, weathertight, properly ventilated structure with adequate
provision for prevention of absorption of moisture.
504.2 AGGREGATES
1. Cement
2. Aggregates
3. Water
4. Admixtures
The Contractor shall provide three (3) sets of test specimen for test purposes
taken under the supervision of the Construction Manager from each 115 cubic
meter fraction thereof of each class of concrete placed. At least one (1) set of
test specimens for each class of concrete placed shall be provided in each
eight (8) hour shift. Samples shall be secured in accordance with ASTM
C172. Test specimens shall be made and cured in accordance with ASTM
C39 or ACI 214. Test specimen shall be evaluated for each class of concrete
specified in conformance with ACI 318, Chapter 4. Concrete Quality.
Specimen may be tests seven (7) days and 28 day strength of the concrete is
established.
506.0 MATERIALS
Only one (1) brand of any type of cement shall be used for exposed
concrete surfaced of any individual structure.
FS SS-1302, Type II, that can be painted without evidence of bleeding and
that after final set will be unaffected y high humidity and moisture.
506.3 AGGREGATES
1. Fine Aggregates
2. Coarse Aggregates
506.4 WATER
Water for washing aggregate and for mixing and curing concrete shall be
portable water (clean and free from injurious amount of oil, acid, salt,
alkali, organic matter, or other deleterious substances as determined by
CE CRD-C400). Chlorides and hardeners shall not exceed specified limits
of ASTM D512.
506.5 ADMIXTURES
506.7 GROUT
Mix of one (1) part Portland cement type 1 and iA parts of fine aggregate
proportioned by weight and more than 4-1/2gal of water per bag, 94lb of
cement.
3. Expansion Grout
1. Impervious Sheeting
ASTM C171, type optional, except that Polythene sheeting shall be 4mm
minimum thickness, white opaque. In areas of high winds the impervious
sheeting shall not be used.
2. Burlap
Cloth made of jute or kenaf shall conform with AASHTO MI 82 and shall
weight a minimum of 0.06psf.
1. Metallic
2. Non-Metallic
507.1 Concrete of the various classes indicated and as required under other
section for different usage shall be proportioned and mixed by volumetric
batching and continuous mixing in accordance with ASTM C685.
Trial design batches for various classes required shall be the responsibility
of the Contractor. Trial mixtures having a proportions, consistencies and
air contents suitable for the work shall be made based on ACI 211.1, using
at least three (3) different water-cemented ratios, which will produce a
range of strength encompassing those, required for the work. Trial
mixtures shall be designed for maximum permitted slump and air content.
The temperature of concrete in each trial batch shall be reported. For each
water-cemented ratio at least three (3) strength shall be determined by
ACI 301, Chapter 3, paragraph 3.8 Method 1 or 2.
507.4 SLUMP
508.1 BATCHPLANT
1. Site-Mixed Concrete
2. Reinforcing steel and forms shall be protected from direct sun rays and
shall be cooled with water immediately before concrete placing so that
concrete temperature specified can be maintained.
3. When cold joints tends to form or where surfaces set aqnd dry too
rapidly or plastic shrinkage cracks tend to appear, concrete shall be
kept moist by fog sprays a[[lied shortly after placement and before
finishing.
509.6 CONVEYING CONCRETE
2. Pumps
510.0 COMPACTION
511.0 BONDING
511.1 Before depositing new concrete on or against concrete that has set, the
surfaces of the set concrete shall be thoroughly cleaned so as to expose
the coarse aggregates. Forms shall be retightened and all surfaces
moistened.
512.0 SLABS ON GRADE
512.1 Submerge under slabs within the building shall be covered with the vapor
barrier. Edges shall be lapped not less than 150mm and sealed with a
pressured sensitive tape, not less than 2in (50mm) wide, compatible with
the membrane. Concrete shall be placed continuously so that each unit of
operation will be monolithic in construction. Concrete shall be placed in
alternate checkerboard pattern terminating at crack control joints. Crack
control joints shall be expansion, control, or construction joints.
512.3 SEALING
Concrete joints shall be filled with the joint sealant except where floor
covering is required.
513.1 After being plumbed and properly positioned, base plates shall be
provided with full bearing with n0n-shrink grout except where expansive
grout indicated. The grout shall be packed by tamping or ramming with a
bar or rod until voids is completely filled. For clearances of 2in (50mm) or
more the expansive grout shall be provided. Mixing and placing shall be in
accordance with manufacturer’s instruction. Grout shall not be retempered
or subject to vibration. Temperature of the ground and the surfaces
receiving the grout shall not exceed 90 degrees Fahrenheit.
514.0 SUSPENDEDSLAB
Finished floor and roof slab surfaces shall be true place surfaces with 0
deviations in excess of Sin (200mm) when tested with a 10-foot (3.00m)
straight edge.
515.2 OTHER THAN FLOOR AND ROOF SLAB
Within 12 hours after forms are removed, surface defects shall be repaired
as specified hereinafter or as directed by the Construction Manager.
Temperature of the concrete, ambient air and mortar during repair work
including curing shall not exceed 90 degrees Fahrenheit. Fine and loose
material shall be removed. Honeycomb, aggregate pockets, voids over
1.2in (12mm) in diameter and holes left by the rods or bolt wetted brush
coated with neat cement grout and filled with mortar. Holes shall be
packed full and all patchwork shall be damp cured for seven (7) days
minimum.
For surfaces which are not to receive architectural finish, the following
additional measures shall be taken.
The concrete shall receive smooth finish by brush coating surfaces with
cement grout composed by volume of one part Portland cement and not
more than two parts fine aggregates passing no. 30 mesh sieve and
mixed with water to the consistency of thick paint. Excess grout shall be
scraped off with a towel and the surface rubbed with burlap to remove any
visible grout film. The grout shall be kept damp by means of fog spray
during the setting period.
The concrete shall be screed and floated to the required finished level with
no coarse aggregate visible. Abrasive aggregate shall be uniformly
sprinkled over the floated surface at a rate recommended by the
manufacturer. The surface shall be then being steel troweled to a smooth,
even finish that is uniform in texture and appearance. Immediately after
curing, cement coating or laitance covering the abrasive aggregates shall
be removed by steel brushing, rubbing or light sand blasting to exposed
abrasive particles.
515.4 HARDENER
1. Monolithic Finish
Slab shall be screed and floated with straight edge to bring the surface
to the required finish level with no coarse aggregate visible. The
concrete while still green but sufficiently hardened to bear a man’s
weight without deep imprint, shall be wood troweled to a smooth even
dense finish free from blemishes including trowel marks, rough
surfaces shall be provided for resilient flooring, thin-set ceramic tile,
carpeting and where no other finish is specified.
2. Power Machine Finish (Option)
Tamp the concrete to force the aggregate away from the surface, then
screed with straight edge to produce a uniform surface. Rough slab
finish surfaces shall be provided for ceramic tile except thin-set
installation, quarry tile, floor toppings, insulation, built-up roofing of
terrazzo.
4. Broom Finish
The concrete shall be screed and floated to the required finish level
with no coarse aggregate visible. While concrete is still green, steel or
wood trowel to an even smooth finish and the broom with fiber bristle
brush in a direction transverse to that of the main traffic. Broom finish
surfaces shall be provided for driveways and ramps.
5. Wood Float
Curing procedure shall conform with ACI 308 and ACI 305. During the
specified curing period, the concrete shall be maintained in a moist
condition at temperatures not over 90 degrees Fahrenheit.
601.0 MATERIAL
Structural steel, ASTM 36,248 MPa Tensile Strength, Cold-formed Welded and
Seamless Carbon Steel Structural Tubing in Rounds and Shapes, ASTM A500.
Steel Structural Rivets, ASTM A502 Carbons Steel Bolts and Studs, ASTM A307,
414 MPa Tensile Strength Covered Carbon Steel Welding Electrodes, AWS A5
1.
Welding and inspection symbols to be used in the plans and shop drawings shall
be the American Welding Society Symbols.
603.0 CAMBER
Shop drawings giving complete information, including the location, type and size
of welds, bolts and rivets, shall be submitted by the Contractor to the Structural
Engineer for approval, before fabrication. They shall be made in conformity with
the best practice and with due regard to speed and economy in fabrication and
erection.
Unless otherwise specified, all steelwork shall be given one coat of shop paint,
aside from corrosion protection.
609.0 BRACING
The Contractor shall provide quality control procedures to assure that all work is
performed according to this specification and standard industry practice. The
owner has the right to do inspection any time and may demand random tests of
critical items and materials. The cost of these tests will be incorporated by the
Contractor in his tender.
701.0 Do not drive piles damaged by handling, Deliver the driving blows square on the
axis of the pile.
702.0 Properly protect the pile head by the use of helmet and cushions (hardwood,
rope or any resilient materials).
703.0 Stop driving as soon as the penetration reaches the desired resistance. Consult
the Structural engineer for the stopping criteria.
1. It is damaged by driving.
Refer any defective pile to the structural engineer for corrective action.
705.0 Pile splicing method to be submitted by the pile contractor to the structural
engineer for approval. However, pile splicing is to be avoided as much as
possible.
706.1 One load is mandatory for every 500 piles, with a maximum of four for the
project. Results of the load test should be referred immediately to the
structural engineer to determine if the number of test pile should be
reduced or increased.
706.2 A rest period of at least three days should be allowed before application of
loads on test piles to permit the disturbed soil to retain most of its strength.
Otherwise, the test results erroneously low.
1. It is loaded twice the working load without any sign of pile distress.
2. The settlement from the start of loading to 40 hours after completion of
loading is not more than 0.26mm/KN of load.
706.5 To ensure pile concrete strength, test results of the same should be
submitted by the pile contractor for approval.
401.1 Furnish all labor, materials, equipment, plant and other facilities to
complete the concrete formwork as shown and hereinafter specified.
401.2 All works under this division shall be subject to the General Conditions
accompanying these specifications. The Contractor and Sub-Contractor
are to refer especially thereto.
402.1 The standards and codes applicable to only portion of the work specified
in this section are referenced and codes which are generally applicable to
the works of this section are listed hereinafter.
403.1 Detail Drawings and Shop Drawings for all parts of the work in sufficient
detail to enable the Construction Manager to check conformity with the
Contract Requirements. Drawings shall show the details and dimensions
of all component parts including plan and elevation views, cross sections
and details.
404.1 CONSTRUCTION
405.0 MATERIALS
2. Form Lumber
405.3 TIES
Bolt of standard snap ties for snap off 25mm from surfaces with minimum
working capacity of 3000lb. Maximum size cones shall be 19mm in
diameter.
Standard size, gauged 20 galvanized steel with removable filler install for
abutting masonry and at 24in (600mm) o.c. for facing masonry where
shown.
Approved propriety type inserts for the load capacity and use shown.
406.1 FORMS
406.2 SHORES
Clean forms before each use. All steel forms shall be free of rust and
scale.
406.6 CLEANOUTS
Coat removable forms with form release agent before reinforcing is placed
and in accordance with manufacturer’s instructions. Remove release
agent from reinforcing steel embedment’s with solvent recommended by
the manufacturer.
407.1 GENRAL
Do not remove forms or shoring until the concrete members have acquired
sufficient strength to support their weight and subsequent construction
loads without deflection. Forms shall be removed in a manner to assure
safety of the structure.
407.2 TIME
Forms and support shall remain in place until the concrete has attained
sufficient strength to support the loads to be applied, but in case shall they
be stripped in less than the following minimum periods.
Foundation 24 hours
Columns 2 days
Walls 2 days
Sides of Beams and Girders 2 days
Floor Slabs 14 days
Shoring for Beams and Girders 14 days
Beams and Girders 14 days
407.3 RESHORE
Reshore immediately after stripping slabs, beams and girders that support
subsequent formwork. Retain reshores for as many levels as required to
combine the liveload capacities of cured floors to support the loads of the
subsequent fresh construction loads. Reshore a minimum of two (2)
consecutive levels.