Sunteți pe pagina 1din 6

Huang, Z., Broch, E., Lu, M. Formation and stabilization of rock cavern roof arches.

ISRM 2003–Technology roadmap for rock mechanics, South African Institute of Mining and Metallurgy, 2003.

Formation and stabilization of rock cavern roof arches


Huang, Z.1, Broch, E.2, Lu, M.2
Rogaland Research1, Norway
Norwegian University of Science and Technology, Norway2

Abstract: The formation and mechanism of rock cavern roof arches are studied and effects of
rockbolts reinforcement are evaluated. It is concluded that a self-supported roof arch may be
formed by the excavation. To stabilize such a roof arch, fully grouted rockbolts are effective.
Tensioned cable anchors may have a negative influence on the arch stability.

Zusammenfassung: Die Formation und der Mechanismus von Deckenbögen in Bergkavernen


wird studiert und der Effekt von Verstärkung mit Bergbolzen wird bewertet. Es wird festgestellt,
dass die Exkavation einen selbst-stützenden / freitragenden Deckenbogen formen kann.
Eingegossene Bergbolzen sind effektiv um einen solchen Deckenbogen zu stabilisieren.
Spannkabel können unter Umständen eine negative Einwirkung auf die Stabilität des Bogens
haben.

Résumé: Le mécanisme et la formation de voûtes dans les cavernes rocheures sont étudiés et
l'effet du renforcement par boulonnage est évalué. Nous arrivons à la conclusion qu'une voûte
autosupportêe peut être formée par excavation. Des boulons entièrement scellés par coulis de
bêton s'avèrent efficaces pour stabiliser de telles voûtes. Les tirants d'ancrage peuvent quant à eux
nuire à la stabilité de la voûte.

the whole arch is assured by the compaction under gravity


Introduction of the various elements and high capacity of compressive
strength of masonry blocks. Coulomb, in his memoir on
When a rock cavern roof is excavated, a self-supported statics in 1773, examined the behavior of the masonry
roof arch structure may be formed. The characteristics of structure in the light of three assumptions as (Westergaard,
the roof arch may inherit from the voussoir arch, in which 1964):
the voussoir has 'unlimited' compressive strength. The arch • voussoir has no tensile strength,
shape has advantage to make use of the high compressive • voussoir has an unlimited compressive strength, and
strength in order to transfer loads, meanwhile, to compact • sliding failure does not occur.
the arch itself and thus forms a stable structure. To ensure
the stability of the arch, conditions that induce tensile stress
or/and sliding along masonry joints should be avoided. In
stabilization of rock masses, rockbolting is a routine
practice as the bolts are inexpensive, flexible to apply in
changing ground conditions of underground excavation and
easy and fast to install. Rockbolting contributes to the
modern rock reinforcement system that is based on
assisting the rock mass to form a self-supporting structure
such as the cavern roof arch. Rockbolts mobilize the
inherent strength of the rock mass by offering confining Figure 1 A typical voussoir arch application
pressure, increase the stiffness of the rock, provide shear
resistance to the rock joints or discontinuities and suspend Compared with construction of a masonry arch, a rock
loosed rock blocks. However, it is important to distinguish cavern roof arch can be established by excavation due to
the effects of full grouted rockbolts and the tensioned cable the existence of the in-situ horizontal stress. The in-situ
anchors in reinforcing the roof arches. horizontal stress is favorable to maintain the arch shape by
decreasing the roof subsidence during excavation, offering
Formation of roof arch and reinforcement compressive stress to directly enhance the bearing capacity
of the rock mass, compacting the rock block to form the
Formation of voussoir arch and cavern roof arch arch. So that extra support may not necessarily be
Voussoir arch (Figure 1) action arises directly from the beneficial for the arch forming. The favorable effect of the
properties of the material - masonry blocks are laid in weak reasonable in-situ horizontal stress in roof arch forming was
mortar or placed one on another to form the arch. This found also by Gerdeen et al. (1977).
method of construction ensured that the structure would In the classical arch theory, an assumption has been
sustain no tension and sliding between blocks. Stability of made that the masonry material is infinitely strong. There is

549
in fact no question about an overall criterion of strength. The stability against collapse of funicular voussoir arch
Rather it is the shape of the structure that must be requires the thrust line within the 'middle third' area of the
examined. As Heyman (1995) pointed out, the stability of arch ring. For various profiles of voussoir arches, it is
the structure will be assured primarily by its shape, and not necessary to determine a minimum thickness of the arches,
at all (or only very marginally) by the strength of the which comprise the ring the thrust line does not pass
component material. Thus it is essential to design and outside. Following Inglis (1963), Irvine (1981) gave the
excavate the arch shaped roof. answer for the classical Roman voussoir arch assuming the
Under such conditions, a natural rock roof arch may be collapse mechanism illustrated in Figure 2.
formed and self-supported. Apart from the experimental
experience reported by Bergman and Bjurstron (1983), sita (degree)

evidences of natural arch forming were given by Hibino, et 20 25 30 35 40


0,16 0,16
al. (1983). A typical example of a natural roof arch formed
0,12 0,12
is at Gjøvik ice hockey cavern constructed in 1991 in

t/R
Norway. The cavern has span of 61m and height of 24m. 0,08 0,08

The rock cover varies from 25m to 50m. The quality of 0,04 0,04
rock mass (Precambrian gneiss) is fair to good with Q=4 to 0 5 10 15 20 25 30 35 40
c/R
40. Horizontal to vertical stress ratio is 3.5. Numerical Figure 2 Assumed collapse Figure 3 t/R vs. c/R and t/R
studies and measurement gave the maximum roof mechanism showing hinge vs. θ relation curves
displacement of about 7mm. Due to the high horizontal in- locations and thrust line (
situ stresses some initial episodes of arching upwards are from Irvine, 1981)
found (Broch et al. 1996). 6-12m long bolts/cables with
spacing 2.5 x 2.5m were used. Broch et al. (1996) suggest a For infinite overburden (c), the general results of the
shorter bolt of 3-4m will do the support job since the minimum voussoir thickness t and the angle locating the
measured load in the bolts is very low and occurs only in a hinge at the intrados θ as a function of the radius R, are
limited length of the bolt. shown in Figure 3 and are given as
θ = sin −1 (1 / 3 ) ≅ 35.3 o (3)
Arch action t
= 2(7 − 4 3 ) ≅ 15% (4)
Arch action can be visualized by the compressive stress R
zone uniformly distributed along the arch from numerical The minimum thickness of the arch is about 15% of the
modeling. The visualization indicates the load transferring arch radius. It is noted that a threefold increase in t/R is
from the crown to the abutments and further down to the associated with only a 50% increase of θ. This indicated
sidewalls, and the compaction by which the arch is self- that the location of the hinge at the intrados varies little
supported. In classical voussoir arch theory, the action of even for widely differing forms of the arch, implying the
the arch can be described by the line of thrust. The thrust critical of the arch rib in stability. In the proceeding, the
line is a polygon representing the equilibrium of given horizontal load is not considered. From Eq.(3), with
loads. The thrust line for a general arch shape of rock increase in the horizontal in-situ stress, a thicker arch is
cavern roof is derived based on limit equilibrium analysis required. And thus a very high horizontal in-situ stress may
(Huang, 2001). Under vertical loads (q(x)) only, and not always be beneficial to the roof arch forming. A
including both the vertical and horizontal in-situ stress favorable magnitude of the horizontal stress should be
components, the thrust line of the left part of the arch is related to a certain size of the span.
Eq.(1) and Eq.(2), respectively:
Roof arch reinforcing
V W (1)
y= x − x ( x − xd ) Excavation may induce plastic/tensile zones that lead
H H to failure of the rock mass. The shear failure in weak
V Wx (2) discontinuities and shear failure due to incomplete arch
y= x− ( x − xd )
H' H' forming is common (Stille, 1992). If adequate support is not
where provided, aggressive air or water can cause further
x L
W x = ∫ γq ( x)dx ; V = W / 2 = ∫ γq ( x )dx / 2 ;
deterioration of the exposed rock. Water may build up
0 0 water pressure that increases tensile stress in
discontinuities, further dilates the joints, decreases the shear
x d = ∫ q ( x) xdx / ∫ q( x)dx ; γ = unit weight of the rock
x x

0 0 strength of the joints and causes both tensile stress and


mass; H = horizontal component of the thrust in the sliding within the arch. All these are in contradiction with
arch; H ' = H − k 0γhb y b / 2 ; k0 = horizontal to vertical in- the arch assumptions. Roof bolting or/and lining are
designed to provide confining pressure to improve the
situ stress ratio; L = span of the arch.
bearing capacity of the rock, to eliminate the tensile stress
Comparing Eq.(1) with Eq.(2), shows that the presence
and resist sliding along joints in order to keep the blocks in
of the horizontal in-situ stress will cause the thrust line
place and form an integrated reinforced roof arch. With
higher. The higher the k0 value, the higher the thrust line.
This is in agreement with the numerical modeling shown in increase of σ3, the peak strength increases, there is a
Figure 9. transition from typically brittle to fully ductile behavior

550 ISRM 2003 – TECHNOLOGY ROADMAP FOR ROCK MECHANICS


with plastic deformation, the region incorporating the peak reinforced roof arch forming. It shows that 2<L/s<3 for
strength gets widen and the progressive strain-softening effective in systematic rockbolting.
post-failure behavior is getting important. As the rock For example, the rockbolt support for the Xiaolangdi
obeys the Mohr-Coulomb strength criterion, the underground powerhouse roof includes 6m and 8m
incremental confining stress by the rockbolts contributes to rockbolts, each type of bolt with a spacing of 3m x 3m, and
the bearing capacity of the rock that can be expressed by tensioned 25m-cables with spacing 4.5m x 6m. The bolts
the form: give an average L/s of 4.6, which is conservative. With the
φ (5) arch radius of 18m, according to Eq.(3), the minimum
∆σ = N ∆σ = tan 2 (45o + )∆σ
1 φ 3 3
2 thickness of the arch required for stable is about 3m. As
Or in terms of an increased cohesion of the rock, ∆c, there was not instable record, it is reasonable to infer that a
1 (6) natural roof arch was formed. And thus the arch is at least
σ 1 = Nφσ 3 + 2c* Nφ , where c* = c + ∆c, ∆c = ∆σ 3 Nφ
2 3m thick. After systematic rockbolting, the thickness of the
Through studies of cases of applications of rockbolts in arch will increase. Even if there is a clay seam above the
practical rock supports as well as in experimental tests arch, it is out of question so long as the arch is stable. If the
(Rabcewicz 1969; Egger 1973; Bjustrom, 1974; Stillborg, seam is located within the arch, it should have been
1984; Stjern, 1995). The apparent mechanical response of stabilized by the rockbolts since the arch is stable. Consider
rockbolting has been categorized as various reinforcement the factor of safety is low, efforts should be focused on the
effects: 1) improve material property;2)internal key-stone and the rib. From Figure 4 and analytical study
pressure;3)suspension;4)beam building and 5)arch forming. (Huang, 2001; Huang et al, 2002), a closely spaced
With regard to arch forming, traditional concept is based on rockbolts will be more efficient than a longer rockbolt. On
that a loose zone exits below a natural arch fairly high from the other hand, the use of fully grouted rockbolts is
the flat roof surface. Tensioned grouted rockbolts are used effective to prevent the sliding, opening and offer confining
to reinforce the loose zone and build an artificial voussoir pressure fast than the point anchored rockbolt/cable that can
arch near the surface. However, a large cavern roof is not offer shear resistance before significant shearing has
generally designed as an arch shape by which the loose already taken place. Therefore, the extra use of the 25m
zone is excavated. In such a case, a natural roof arch that is long cable may be described as not rational. This is in
inherently stable may be expected near the roof surface. agreement with the numerical modelling results in the
Among the idealized analytical solutions on design of following.
reinforced rock structures, Lang and Bischoff (1984) have
made very useful efforts to provide a rational basis for Numerical modeling on forming and
explanation of rockbolt design. For a reinforced roof unit of reinforcing of Xiaolangdi powerhouse cavern
height of H with a bolt having a length of L, the average
normalized confining pressure σA/γ= T/(Aγ) offered by the Geology and rock support
rockbolt is The Xiaolangdi Multipurpose Dam Project is located in
Hs T 1 1 − e −4 µk0 H / s the middle reach of the Yellow River, China. The installed
= = = f ( H / s, L / s, φ , k 0 ) (7)
s Aγs 4µk 0 1 − e − 4 µk0 L / s capacity is 1800MW. The underground powerhouse
where complex (see Figure 5) is situated in sedimentary rocks of
σA= T/A, average confining stress offered by rockbolts; fair to good quality (Q=8 - 12). The measured compressive
φ = friction angle of the rock mass; Hs = equivalent (rock)
height of the confining pressure offered by rockbolts; A =
area of reinforced rock unit (s2 for a rockbolt pattern with s
x s spacing); T = rockbolt tension force; L/s = rockbolts
length-to-spacing ratio or density.

5
2,0
4 k0=0.4 1,5
k0=0.8
3
Hs /s

Hs /s

1,0
2
0,5
1

0 0,0
0 1 2 3 4 5 6 7 8 0 1 2 3 4 5 6 7 8
L/s L/s
Phi=20 Phi=30 Phi=20 Phi=30 Phi=40 Phi=45
Figure 5 Perspective view of Figure 6 Deformed
Phi 40 Phi 45
Xiaolangdi powerhouse geometry(F1-DIANA)
Figure 4 Relations of Hs/s and L/s
strength of the rocks is in the order of 60 - 150 MPa. The
Assume a large H/s value, the variation of Hs/s with L/s lateral in-situ stress ratio (k0) is about 0.8. There are several
and φ(Phi) for k0=0.4, k0=0.8 can be plotted as shown in clay seams with thickness of 1mm to 20mm parallel with
Figure 4. As L/s increases to some extent the confining bedding planes. The existence of the clay seams became a
pressure decreases and approaches a minimum value. So major concern for the stability of the cavern crown.
that very long bolts/cables are not necessarily beneficial for Combining with other considerations such as support

551
pressure (further discussion on this issue refers to Huang et changes were taking place in the roof during
al. (2002)), this leads to a total of about 345 1500kN excavation, which means a natural roof arch may be
tensioned 25m long cable anchors installed in the machine already formed, and after pattern rockbolting the roof
hall (251.5m long, 26.2m wide, 61.4m high) roof, in arch is more stable.
addition to pattern 6-8m long rockbolts spacing 1.5m x • The cables may increase wall displacements due to the
1.5m, and 20cm wire mesh shotcrete (Wang and Solymar, mechanism of the coupling of roof deformation with
1997). the wall deformation in the cavern with high walls. The
cables cause irregular stress distribution and stress
Numerical modeling concentration in the arch. The extra upward support
force may rotate rock blocks in a way that resists the
The objective of the numerical modeling is to find a
forming of the arch, and induce sliding along joints and
rational rockbolts support design in stabilization of the
tensile stress. These turn out contrary to the
Xiaolangdi underground powerhouse roof arch and the
expectations.
walls. This is achieved by simulation of different geological
models in combination with rockbolting alternatives. Base
Table 1 Displacement (mm) calculated in the UDEC and
on the geological structures, the geological models consist
the DIANA modeling
of intact rock model (F), stratified rock mass model (E) and
jointed rock mass model (K). Rockbolting alternatives Model k0 UDEC DIANA
include no support at all (‘1’), only fully grouted rockbolts C UW DW C UW DW
(‘3’) and both tensioned cables and grouted rockbolts (‘7’). F1 0.8 6.7 19.1 22.9 5.3 16.6 19.7
For comparison and verification, both the UDEC and the F7 0.4 8.4 13.6 20.0 6.6 6.9 16.1
DIANA codes were used. F7 0.8 6.1 17.4 20.9 4.4 11.8 17.8
F7 1.0 5.5 20.1 22.1 3.4 15.4 20.8
General results Note:C=Crown,UW=UpstreemWall,DW=DownstreemWall
Response of the rock mass to the excavation:
• The maximum value of roof subsidence and
downstream wall displacement is about 5.3 - 6.7mm
and 19.7 - 22.9mm for intact rock model F1, see Table
1 and Figure 6.
• Plastic zones extend to more than 20m in the walls and
E7
to a maximum depth of 5m in the roof, see Figure 7. E3
10m-18m deep tensile zones are calculated in the Figure 7 Plastic zone in rock mass-model E3,E7 (UDEC)
walls, Figure 8(a). Only in jointed rock mass model
K1, a tensile zone of 5m deep in the roof exists.
• Figure 8(a) shows that the arch shaped roof fits the
elliptical rock ring surrounding the opening, and thus
leaves a limited range of the plastic/tensile zone. The F7F1F3 F3
high walls do not fit it. E3
• A natural roof arch with about 5m thick uniform stress
zone near the roof surface is established by the
favorable in situ stress, the good quality of rock and the
arch shape of the roof. The location and thickness of
the roof arch may be determined by use of a new
concept of invert principal stress cone.
(a) (b)
• There is the mechanism of coupling of the deformation
Figure 8 (a) Minor principal stress contour with tensile
of roof and the deformation of high walls in the cavern.
zone (red) in the rock mass with DIANA; (b) bolt load
distributions with UDEC.
Characteristics of rockbolting in stabilization of the
powerhouse cavern:
• The rockbolt should be long enough to facilitate the
• The pattern fully grouted rockbolts reduce the roof maximum shear stress that may develop and to cross
subsidence and the wall displacements, see Table1. critical joints (Figure 8(b)). The critical joint might be
Comparing with the tensioned cables, the rockbolts are defined by its critical location less than double
more effective way. Further evidences include that the thickness of the rock roof arch. When a joint is loacted
grouted rockbolts efficiently reduce the plastic zone, beyond the ctitical location, no special attension should
tensile zone and opening of the clay seams in the roof. be paid if the rock roof arch is ensured. As Figure 7
• The load built up in the rockbolts in the crown is low shows, the length of 6-8m rockbolts is long enough to
and within about 2m from the surface, see Figure 8(b), cover the plastic zone in the roof, and it is in agreement
small loads changed in the tensioned cables. The with empirical rules (Huang, 2001); while in model E7,
strength of the rockbolts is not considerably mobilized, the 25m-cables are too long to be rational.
nor the cables. These also indicate that small stress

552 ISRM 2003 – TECHNOLOGY ROADMAP FOR ROCK MECHANICS


• It is rational to design the rockbolting in a way that the determined. By this method, the determined arch thickness
reinforcement is helpful to form a uniformly reinforced is in agreement with the preceding study.
rock ring (Figure 8(a)) surrounding the cavern.
Further discussion on roof arch reinforcing
Further modelling on roof arch forming During the natural roof arch forming, the stress
The preceding study comes out that a self-supported readjustment in the rock mass causes rotation and
roof arch may have been established by the excavation. It is deformation of rock blocks. In highly fractured or jointed
found that the in-situ horizontal stress plays important role rock mass, the movements may cause a significant change
in the forming of a natural roof arch. The increase in of the rock arch geometry, sliding along joints and tensile
horizontal in-situ stress causes decrease in the roof stress. So emphasis should be put on keystone bolting,
displacement coupling with the increase in the inward systematic bolting - aiming at knitting rock blocks together
displacement of the walls. The strength/stress contour and to keep the arch geometry complete in order to form the
the principal stress vectors visualized in Figures 9 show that natural segmented or voussoir arch of rock.
under high horizontal stresses (k0=0.8 and 1.0) a uniform The strength/stress contour plots demonstrate that the
arch shaped compressive stress zone near the roof surface is natural roof arch is reinforced without any distortion of
formed as a result of stress readjustment to fit the arch stresses by untensioned grouted rockbolts. The load
shape after the excavation. The higher the k0 value, the building up in the rockbolts is compatible with the
thicker the arch. The uniform compressive stress in both deformation or rotation of the rock mass; meanwhile the
radial and circumferential directions characterizes the roof rockbolts limit the deformation or rotation by strengthening
arch. Under low horizontal stresses of k0=0.4, there is not a the rock especially resisting the opening and shearing of
uniform compressive stress zone in the roof due to lack of rock joints. In contrast, the tensioned cables cause irregular
horizontal bearing pressure and thus the mechanism to stresses in the arch and stress concentration at arch ribs
transfer loads. It is hard to say a stable roof arch is set up. because of the existence of the area between cables that
To compare with an arch roof, a flat roof cavern is apply high tension forces to the rock blocks nearby.
simulated and results in a large loosened zone from the Furthermore, the tensioned cables passing through the arch
surface which should be either suspended by apply additional upwards internal support pressure on the
rockbolts/cables to form an artificial roof arch, or simply roof, which counteracts the forming of the arch as shown in
excavated. In the later case, it is necessary to remove the Figure 10 (a)-(b). The unfavorable rotation of the rock
loosened rock in accordance with a designed arch roof such blocks and the upward moving of the keystone in the arch
as that drawn in Figure 9. Then a natural rock roof arch will has potential to induce sliding along joints and tensile stress
be expected. or even opening of the joints as shown in Figure 10 (c)-(d).
Rotate and contact, forms arch No contact, no arch

Natural roof arch


No uniform stress with thickness (a) Arch formed by (b) Upward force resist
zone, k0=0.4 ≈5m, k0=0.8 downward forces and rotations of the blocks
blocks rotations

Keystone Keystone
opening
& sliding

Natural roof arch with


Natural roof arch thickness ≈ 5m
with thickness ≈ 6m k0=0.8
k0=1 Upward force
Figure 9 Strength/Stress contour and principal stress Thickness of arch changed
vector- model F1 (k0=0.4,0.8,1.0) by upward force
(c) Compaction forms voussoir arch (d) Upward forces destroy the arch

By visualization of the stress field in the rock mass of


Figure 10 Natural rock arch formed by compaction,
the roof from the modelling, a new concept of invert
damaged or destroyed by upward force (arrows
principal stress cone is proposed to determine the location
indicate forces)
and thickness of the roof arch (Huang, 2001). The invert
principal stress cone is defined so that within the cone the
Because a reinforced rock cavern roof arch is not
principal stresses are vertical and horizontal only. Beneath
freestanding like an arch bridge, the displacement of rock
the cone the location and the thickness of arch is then

553
blocks is pertinent to spaces available behind the arch. It is subsidence and wall displacement. Tensioned cables may
the presence of the clay seam in the crown - a weakness be used to suspend large rock wedges or blocks locally.
zone that probably provides spaces for such an
unfavourable rotation and displacement. This reduces the Reference
thickness of the arch namely the factor of safety. Thus the
high tensioned cables take the risk to reduce rather than Bergman, Sten G.A.B and Bjurstrom, Sten.1983. Swedish
increase the factor of safety. experience of rock bolting. Proc. of the Int. Symp. On Rock
Bolting, Abisko, pp243-255.
Bjurstrom, S. 1974. Shear strength of hard rocks reinforced
Comparison between simulation and by grouted untensioned bolts. Proc. 3rd Congr. ISRM,
measurement Denver, pp.B1194-1199.
Most of the instruments in the Xiaolangdi powerhouse Broch, E, Myrvang, A. M. and Stjern, G. (1996) Support of
were installed too late during the excavation. For such a large rock caverns in Norway. Tunnelling and Underground
large and important project, the delay may simply indicate Space Technology, Vol. 11, No. 1, pp. 11-19.
that the geological conditions in the area in question were Egger, P. 1973. Rock stabilisation. Rock Mechanics,
regarded as being generally good. The first monitoring data Courses and Lectures, Udine, pp241-297
were recorded after the top heading excavation and the Gerdeen, J. C. et al. 1977. Design Criteria for Roof Bolting
installation of the cables were completed. From the data of Plans Using Fully Resin-Grouted Nontensioned Bolts ro
multiple-point borehole extensometers, rock/cable Reinforce Bedded Mine Roof, USBM, Contract No.
dynamometer, important conclusions are as follows: J=366004, Michigan Technological University, Vol. IV.
Heyman, J. 1995. The stone skeleton - structural
• During benching excavation a maximum roof
engineering of masonry architecture. Cambridge University
settlement of 2mm was recorded, much less than the
Press. 160p.
expected in the report of rock support design (YRCC,
Hibino, S., Motojima, M. and Kanagawa, T. 1983.
1994), and it confirms the results of model F.
Behavior of rocks around large caverns during excavations,
• The cavern roof has uplift movement during the first
Proc. 5th Congr. ISRM. Melbourne, pp.D199-202
benching excavation. So does the DIANA modelling of
Huang,Z. 2001. Stabilizing of rock cavern roofs by
model E7.
rockbolts. Ph.D thesis. Norwegian University of Science
• The monitored maximum displacement at lower part of and Technology, Norway.
the downstream wall, coincides with the modeling Huang,Z., Broch, E., Lu, M. 2002. Rockbolt support of
results. cavern roofs based on analytical solutions. EUROCK 2002,
• From the monitored data, it is deduced a maximum of Lisbon, Portugal
6 mm subsidence at vault and 15mm inward Inglis, Sir Charles. 1963. Applied mechanics for engineers.
displacement of the downstream wall during Dover Publications, Inc. New York.
excavation. These are close to the intact rock model F Irvine, H. Max. 1981. Cable Structures. The MIT Press.
result. Lang, T. A. and Bischoff J.A. 1984. Stability of reinforced
• Among 9, only one cable dynamometer exceeded the rock structure. In Design and performance of underground
tension load by 14% in 1998, at the same year, highest excavations (edited by Brown, E. T. and Hudson, J.A.),
load of about 79kN was recorded in bolt dynamometer pp11-18. British Geotechnical Society, London.
with others less than 20kN. These imply that small Rabcewicz, L. 1969. Stability of tunnels under rock load.
stress changes were taking place in the roof and the Water Power, 225-229 (June), 266-273(July), 297-302
cavern roof arch is self-supported. This is in (Aug.)
accordance with the numerical modeling results. Stillborg, B. 1984. Experimental investigation of steel
cables for rock reinforcement in hard rock. Ph.D. thesis.
Conclusions Luleå Univeristy, Luleå, Sweden.
Stille, H. 1992. Keynote lecture: rock support in theory and
With a certain magnitude of in-situ horizontal stress,
reasonable quality of the rock mass and arch shaped roof, a practice. Proceedings of Rock support in mining and
natural self-supported rock cavern roof arch structure may underground construction, Kaiser and McCreath (eds),
be established near the roof surface by the excavation. Balkema, Rotterdam.
Stjern, G. 1995. Practical performance of rock bolts. Ph.D.
Pattern short and closely spaced fully grouted rockbolts are
efficient to reinforce the jointed and fractured rock masses Thesis, Norwegian University of Science and Technology,
and to avoid tensile stress and sliding along the rock joints Trondheim, Norway.
Wang, X. & Solymar, Z. V. 1997. Design and Underground
in the roof, in combining with reinforced shotcrete.
In the case of the Xiaolangdi powerhouse roof where a Construction at the Xiaolangdi Mutipurpose Dam Site.
natural and reinforced roof arch has already been formed, Tunnelling and Underground Space Technology, Vol. 12,
the additional use of systematic tensioned cables may not No. 4 pp. 461-472.
Westergaard, H.M. 1964. Theory of elasticity and
be rational to the stability of the roof. The cables are neither
efficient nor safe due to inducing stress concentration and plasticity, 176p. Dover Publications, New York.
triggering the mechanism of coupling of the roof

554 ISRM 2003 – TECHNOLOGY ROADMAP FOR ROCK MECHANICS

S-ar putea să vă placă și