P u b l i c p r i vat e pa rt N e r s h i p s
P u b l i c p r i vat e pa rt N e r s h i p s
REPUBLIC OF INDONESIA
MINISTRY OF NATIONAL DEVELOPMENT PLANNING/
NATIONAL DEVELOPMENT PLANNING AGENCY
PUBLIC-PRIVATE
PARTNERSHIPS
INFRASTRUCTURE PROJECTS PLAN IN INDONESIA
2018
i
P u b l i c p r i vat e pa rt N e r s h i p s
II
ii
P u b l i c p r i vat e pa rt N e r s h i p s
Foreword
by MINISTER OF NATIONAL DEVELOPMENT PLANNING/
HEAD OF NATIONAL DEVELOPMENT PLANNING AGENCY (BAPPENAS)
Infrastructure Development 2015 – 2019
Making PPP Works
The Government of Indonesia continues to evaluate and strengthen the policy in order to support
acceleration and improvement of PPP preparation process. For the purposes, Government of Indonesia
has enacted Presidential Regulation 38/2015 on Cooperation between Government and Business Entity
in Infrastructure Provision as the new regulation for PPP implementation in Indonesia.
Started from 2009, BAPPENAS - as national development planning agency in Indonesia who responsible
for PPP planning and implementation – issues PPP Book to provide the information on available
infrastructure investment in Indonesia for potential investors or any other PPP stakeholders. Projects
listed in PPP Book are results of rigorous review and screening process by BAPPENAS in compliance
with Ministerial Regulation of National Development Planning 4/2015. The projects are organized into
two categories based on their readiness level, those are ready to offer projects and under preparation
projects. PPP Book also provides information related projects have already moved to tender process
(already tendered) and success story of PPP projects in Indonesia.
This PPP Book 2018 is prepared to provide the latest preview and information about infrastructure PPP
projects plan. Total projects in this PPP Book have 15 projects with 14 under preparation projects and 1
ready to offer projects also 8 already tendered projects. By the third year of Joko Widodo – Jusuf Kalla
Presidency within the period 2015-2019, there are 12 PPP infrastructure projects under construction.
These projects show PPP scheme can be a solution and also a challenge for acceleration of infrastructure
development in Indonesia.
Last, we hope this PPP book can be a useful reference to any party involved in the PPP development in
Indonesia.
Prof. Bambang P.S. Brodjonegoro, Ph.D.
Minister of National Development Planning/
Head of National Development Planning Agency
iii
P u b l i c p r i vat e pa rt N e r s h i p s
TABLE OF CONTENTS
Foreword by Minister of National Development Planning/ Head of National Development
Planning Agency (BAPPENAS) iii
iv
P u b l i c p r i vat e pa rt N e r s h i p s
ALREADY TENDER 15
Jakarta – Cikampek II South Toll Road 17
Probolinggo – Banyuwangi Toll Road 18
Serang – Panimbang Toll Road (51km) 19
Serang – Panimbang Toll Road (33km) 20
Cileunyi – Sumedang-Dawuan Toll Road 21
Nambo Regional Waste Management 22
Bandar Lampung Water Supply 23
Jatiluhur Reginonal Water Suply I 24
READY TO OFFER 25
West Semarang Water Supply 27
UNDER PREPARATION 33
1 Medan Municipal Transport 36
2 Semarang – Demak Toll Road 44
3 Yogya - Bawen Toll Road 49
4 Surabaya - Madura Toll Bridge 54
5 Pekanbaru Regional Water Supply 60
6 Multifunction Satellite 68
7 National Integrated Welfare System 73
8 Surakarta Street Lighting 80
9 University of Sam Ratulangi Teaching Hospital 86
10 The Development of Pirngadi Hospital 92
11 Indonesia National Cancer Center Dharmais Hospital 97
12 Sidoarjo General Hospital 103
13 Nusakambangan Industrial Correctional Facility 110
14 Relocation of Salemba Correctional Facility to Ciangir 115
v
P u b l i c p r i vat e pa rt N e r s h i p s
Indonesia, known as a large country with the land area of 1,904,569 square kilometers,
is the 14th largest country in the world. The ranks increased to the 7th largest country in
terms of land and sea area combined, this country consists of 34 provinces. Indonesia’s
population — which at 261 million makes it the world’s fourth-most-populous country,
and the most populous in Southeast Asia. According to World Bank, Indonesia’s GDP per
capita has steadily risen, from $857 in the year 2000 to $13,120 in 2017. Indonesia is the
member of the G-20 which is representative of development country that gives economic
impact towards the world.
Due to its sheer size and population, The Government of Indonesia estimates that the
country will need USD 359.2 billion investment for infrastructure development. However,
it is estimated that only 73.5% of the investment value will be delivered through State
budget and State-owned Enterprises project (KPSRB Bappenas, 2017).
When the state of infrastructure is weak it implies that the economy runs in a highly
inefficient manner such as logistics costs are high, businesses are lack competitiveness
(because the costs of doing business are high), and there exists a high degree of social
injustice when, for example, it is difficult for part of the population to reach healthcare
facilities, or, for children to reach a school.
The government of Indonesia is fully aware of the importance to offer a more attractive
investment and business climate by improving the nation’s infrastructure. To resolve the
need for Infrastructure investment in Indonesia, The Government of Indonesia is offering
Public-Private Partnership scheme in developing infrastructure projects.
vi
P u b l i c p r i vat e pa rt N e r s h i p s
At the moment the investment climate for PPP projects is quite good, as Indonesia is
having an increase of 19 points in Ease of Doing Business (EoDB) Ranks by World Bank.
Indonesian EoDB rank arises from 91 in 2017 to 72 in 2018. At the moment, Indonesia is
the Top 3 Asian Best Investment Destination according to the Economist and also the
Top 3 of Japan Investment destination (JBIC rating).
The Government of Indonesia (GOI) has taken a series of major step to refine the
PPP Policies and regulatory framework in order to improve the attractiveness and
competitiveness of GOI’s PPP program. There are:
• Presidential Regulation Number 38 Year 2015, issued by the government as replacement
of presidential regulation number 67 year 2005 and its revised, establishing the cross-
sector regulation framework for implementing PPPs in the provision of infrastructure. The
successive amendments have established clearer and more detailed stipulations about
unsolicited proposal, cooperation agreement, return on investment with the payment by
the user in the form of tariffs (user charge) or availability payment, government support
and guarantee to project, among other points;
• Presidential Regulation Number 78 year 2010 regarding government guarantee on
PPP infrastructure project. Ministry of Finance Regulation Number 260 Year 2010 as
amended by Ministry of Finance Regulation Number 8 year 2016 regarding guideline
on the government guarantee, whereas Ministry of Finance Regulation number 30 Year
2012 regarding contingency liability fund. It has applied to Palapa Ring Project, Umbulan
Water Supply Project, Central Java Power Plan Project, Toll Road Projects and Bandar
Lampung Water Supply Project.
• Ministry of National Development Planning/Head of National Development Planning
Agency Regulation Number 4 Year 2015 regarding operational guideline for the PPP in
infrastructure provision.
• Head of National Procurement Agency (LKPP) Regulation Number 19 Year 2015 regarding
guideline for procurement of business entity on PPP in infrastructure provision.
• Ministry of Finance Regulation Number 190 Year 2015 Regarding Availability Payment on
PPP in Infrastructure Provision.
• Ministry of Home Affair Regulation Number 96 Year 2016 Regarding Availability Payment
using the local budget (APBD) on PPP in Infrastructure Provision.
• Ministry of Finance Regulation Number 223 Year 2012 Regarding Viability Gap Funding.
vii
P u b l i c p r i vat e pa rt N e r s h i p s
Full details of the regulatory framework are available for consultation on the website at
http://kpsrb.bappenas.go.id
viii
P u b l i c p r i vat e pa rt N e r s h i p s
a. Planning
Preliminary study is the initial study conducted by the Ministry/ Head of Institutions/
Head of Region/ Director of State Owned Enterprise/ Director of Regional Owned
Enterprise to provide the description of the requirement for the infrastructure
provision and also its benefits if it is delivered under the cooperation with the Special
Purpose Company (SPC) through PPP mechanism. It shall explain the plan of PPP
form; plan of PPP financing and the source of the fund; also plan of PPP tenders
which consist of schedule, process, and procedure. Furthermore, the Preliminary
Study should consist of a study on:
ix
P u b l i c p r i vat e pa rt N e r s h i p s
c. PPP location compliance with the Spatial Plan (if needed in accordance with
the type of Infrastructure needed to have cooperated); and
d. Relating to the infrastructure sector and inter-region (if needed in accordance
with the type of Infrastructure needed, to have cooperated).
3. Deciding factor criteria of Value for Money of business entity participation,
includes:
a. Private sector having an advantage on PPP implementation including risk
management;
b. Ensuring the effectiveness, accountability and equitable distribution of
service for the long-term;
c. Transfer of knowledge and technology; and
d. Ensuring fair competition, transparency, and efficiency in the procurement
process.
4. Analysis of potential revenue and project fund scheme, includes:
a. User capability to pay;
b. Fiscal capability of the central government, regional government, SOE/ ROE
in conducting PPP;
c. Other potential revenues; and
d. Perspective on government support.
5. Recommendation and follow-up plan, includes:
a. Recommendation of the form of PPP;
b. Recommendation on the main criteria of the business entities; and
c. Schedule plan of preparation and PPP transaction activity.
b. Preparation
The PPP preparation stage comprises the Pre-feasibility Study activities, which
consist of:
1. Preparation of Outline Business Case (OBC), consisting of:
a. Legal and institutional study;
b. Technical study;
c. Economic and commercial study;
d. Environmental and social study;
e. Study of cooperation form and structure in infrastructure provision;
f. Risk management study;
g. Study of Government Support and/or Government Guarantee needs; and
h. Study of follow-up issues.
x
P u b l i c p r i vat e pa rt N e r s h i p s
2. Preparation of Final Business Case (FBC) which consist of the data adjustment
based on the current conditions and updates of the feasibility and readiness of
the PPP referred to the Outline Business Case. FBC includes the fulfillment of all
requirements of the Pre-feasibility Study including follow-up issues; approval of
the PPP by stakeholders; and certainty on whether Government Support and/or
Government Guarantee is required or not.
During the PPP Preparation Stage, the Government Contracting Agency (GCA)
will perform Public Consultation and Market Sounding. The purpose of Public
consultation:
• Reviewing the compliance of the social and environmental standards in
accordance with the provisions of laws and regulations in the environmental
sector;
• Obtain inputs regarding public needs related to the PPP; and
• Ensure the PPP readiness.
Meanwhile, the Market Sounding is intended to obtain inputs and response
from the PPP markets (business entities/ agencies/ institutions/ national or
international organizations).
c. Transaction
Transaction phase is basically tendering process to find the private sector to be the
winner and form a Special Purpose Vehicle to build, operate and maintain the project
after construction. This process of finding the Special Purpose Vehicle is divide in two
option.
The first option is by tendering process. The second option is by direct assignment.
However direct assignment can only be performed if there is only one bidder during the
tendering process.
In the transaction stage, during tendering process, there are some steps in the pipeline.
The steps are Pre-qualification, Request for Proposal, Bid Award, PPP Agreement Signing.
Pre-qualification: In this step, the bidders will be evaluated according to its background,
history, and ability. The objective is to get a list of the qualified bidders to do the PPP
Project.
Request for proposal: After the bidders are set, they are given all of the documents related
to the transaction process. Then the bidders will evaluate the documents and propose a
bidding proposal based on those document.
Bid award is the time when the winning bidder is announced. After the bidder was
awarded, usually the non-winner bidders were given an amount of time to show objection
or to clarify some issue.
xi
P u b l i c p r i vat e pa rt N e r s h i p s
In the next step, PPP agreement signing: the winner then have to sign some agreement
regarding that PPP project. In general, they have to sign PPP agreement with the GCA,
and also have to sign recourse agreement with IIGF.
Financial close should be obtained no longer than 12 months after signing Cooperation
Agreement and could be extended from time to time if the failure to obtain funding is not
contributable to a failure of Business Entity. Every extension being given for financial close
is no longer than 6 months. Financial close could be done gradually in accordance with the
project cycle. Financial close derived from a loan is deemed to have been implemented if:
• The loan agreement has been signed to finance the entire PPP; and
• A part of the loan can be disbursed to start the construction works
xii
P u b l i c p r i vat e pa rt N e r s h i p s
PPP project. Each of the member’s roles, timeframes, and workflows related to PPP
pipeline is shown in FIGURE 2.
Coordinating Ministry of Economic Affairs (Kementerian Kooordinator Bidang
Perekonomian) will act as a debottlenecking role.
Directorate for PPP and Financial Engineering (KPSRB) Bappenas will facilitate GCA in
project selection, identification and preparation. This directorate will ensure that the PPP
project is in line with PPP planning regulation and national development plan and policies.
Another function of Bappenas is to make sure that the project plans are executable in the
future.
Ministry of Finance is in charge in evaluating the financial and economical aspect, and
making a recommendation about government support to the GCA.
Ministry of Home Affair will evaluate the project value and the allocation of Availability
Payment regarding regional fiscal. Only PPP project with AP scheme from the regional
government will be evaluated by MOHA.
Indonesia’s Investment Coordinating Board (BKPM) role is to make sure that the investor
credibility, and also helping the GCA by inviting interested private sector in market
sounding.
National Public Procurement Agency (Lembaga Kebijakan Pengadaan Barang/Jasa
Pemerintah – LKPP), will act as transaction probity, and make sure that tendering progress
will be fair, and in the corridor of PPP framework.
Indonesian Infrastructure Guarantee Fund is responsible in evaluating the risk analysis
and its mitigation, and also examining the financial and economic calculation to provide
the guarantee for the PPP project.
Another government body, KPPIP (Committee for Acceleration of Priority Infrastructure
Delivery) is positioned as the Project Management Office (PMO) for priority projects.
KPPIP has a crucial role in project development and implementation, starting from project
selection up to groundbreaking for top priority projects. KPPIP also has a central role
in coordinating related stakeholders in project implementation through the action plan
development facilitation, monitoring and debottlenecking as well as providing incentives
and disincentives schemes to accelerate the project realization. Some of PPP projects
are included in priority projects and national strategic project (PSN).
xiii
P u b l i c p r i vat e pa rt N e r s h i p s
National Procurement
IIGF informally gives an IIGF does Agency (LKPP)
input on OBC and FBC government
development process guarantee
National Investment
process
Coordinating Board
(BKPM)
Bappenas
GCA - Bappenas PPP Unit under MoF provides
plans OBC Indonesia Infrastructure
(Planning) PDF and VGF facility
budget Guarantee Fund
Bid Finacial
Idnetification Feasibility OBC FBC Award Close
and Proposal Study Development Development
BKPM : Investment Coordinating Board MoF : Ministry of Finance RfP : Request for Proposal
IIGF : Indonesa Infrastucture Guarantee Fund LKPP : National Procurement Agency OBC : Outline Business Case
Bappenas : Ministry of National Development Planning PQ : Pre-Qualification FBC : Final Business Case
AP : Available Payment
xiv
P u b l i c p r i vat e pa rt N e r s h i p s
For solicited proposals, the PPP Project Pipeline consists of three phases, namely
Planning, Preparation, and Transaction. The duration of time needed for this pipeline
is varied from 18 months to 36 months.
Figure 3 shows the interrelation between the three phases of the PPP Projects
Pipeline. The three phases are straightforward phases, each of them consists of
another sub-process. Each of this step has their own function and not to be avoided.
Planning phases consist of Project Identification and Preliminary Study. The first
step is used to choose a viable PPP project from a list of projects. Then, during the
second step, the project will go through a series of qualitative studies to know if
the project is suitable for PPP process. In general, Planning phases will take 3 to 8
months to finish.
In the Preparation phase, the project will undergo quantitative studies in order to
see the viability of the PPP projects, in term of financial value, economic value, risk
analysis and mitigation, et cetera. In this phase, private sectors were invited to give
input in Public Consultation and Market Sounding. For both of the mentioned above
phases, the underlying regulation is National Planning and Development Minister
Regulation no 4/2015. In general, it will take 6 to 8 months to finish the preparation
phase.
Transaction phase is the last phase which facilitates the project through a transaction,
which includes Prequalification, Request for Proposal, Bid Award, PPP Agreement
Signing, and then Financial Close. It will take 4 to 8 months to finish the transaction
phase.
xv
P u b l i c p r i vat e pa rt N e r s h i p s
done by private sector, while the transaction was done by the government (GCA).
Based on National Planning and Development Minister Regulation no 4/2015, the
process for dealing with unsolicited proposals can be divided into three main stages,
namely:
o The first stage is the Approval Process. It is standard in most cases and takes
place from the time the project proponent presents the project to the government
until all internal assessments and approvals are finished and the project is ready
to be publicly tendered.
o The second stage involves a Competitive Tender Process; approaches tend
to differ in incentives or benefits to the original proponent of the project, and
bidding process up to financial close.
o The third stage is PPP Agreement Signing. This stage is quite similar to the
solicited section of the stage.
xvi
P u b l i c p r i vat e pa rt N e r s h i p s
xvii
P u b l i c p r i vat e pa rt N e r s h i p s
xviii
P u b l i c p r i vat e pa rt N e r s h i p s
7.3 Important Notes related to the Viability Gap Fund and Government Guarantee
during the Procurement Process
Government Support
• Before Prequalification stage, the GCA shall file a request for granting
initial determination of feasibility support, in accordance with the laws
and regulations;
• During bid stage, the Minister of Finance shall issue a principal approval
letter on VGF support;
• Once a tender winner has been selected, the GCA must submit the
tender results to the Minister of Finance as the basis for the Minister
of Finance to issue the final decision letter on VGF support.
• Before project bidders submit their proposals, the GCA must ensure
that BUPI has issued the approval in principle, in the form of a Letter of
Intent based on the results of BUPI’s evaluation.
xix
P u b l i c p r i vat e pa rt N e r s h i p s
xx
P u b l i c p r i vat e pa rt N e r s h i p s
PPP BOOK PPP BOOK PPP BOOK PPP BOOK PPP BOOK PPP BOOK PPP BOOK PPP BOOK
2009 2010-2014 2011 2012 2013 2015 2017 2018
Already Already
Tendered 4 projects 5 projects 12 projects 21 projects 22 projects Tendered 17 projects 8 projects
Ready of Ready to
8 projects 1 projects 13 projects 3 projects 0 projects 6 projects Offer 1 projects 1 projects
Offer
Prospective 18 projects 26 projects 21 projects 26 projects 14 projects 8 projects Under 21 projects 14 projects
Preparation
TOTAL 87 projects 100 projects 79 projects 58 projects 27 projects 38 projects 22 projects 15 projects
xxi
P u b l i c p r i vat e pa rt N e r s h i p s
The PPP Book 2018 contains those projects that have evolved or remained
unchanged from the previous edition and new projects that have succeeded in the
evaluation of the process.
12 Success story
projects
PPP
BOOK 17 already Identification of already tendered projects
8 already
2017 tendered projects (Contract Signing, Bid Award, Pre-Qualification)
tendered projects
Status
No Project Name Description (December 2017)
xxii
P u b l i c p r i vat e pa rt N e r s h i p s
Status
No Project Name Description (December 2017)
7 Serang - Panimbang The project is to unlock the potential of the Already Tender
Toll Road (33 km) area and increase investment opportunities (PQ)
in the tourism sector, agribusiness,
marine, mining, and industry. As a result,
it will promote economic growth and
development of South Banten region
xxiii
P u b l i c p r i vat e pa rt N e r s h i p s
Status
No Project Name Description
(December 2017)
4. Yogya - Bawen Toll The Development of this toll road is Under Preparation
Road important to cover the mobility of people (OBC)
who cross this city.
5. Surabaya - Madura Suramadu Toll Bridge connects Java and Under Preparation
Toll Bridge Madura Island. Main goal of this toll bridge (FBC)
is to accelerate the economic development,
especially in Madura Island.
6. Pekanbaru Regional To expand the service coverage of the water Under Preparation
Water Supply supply system and improve the quality of
(FBC)
service of PDAM Pekanbaru.
7. Multifunction Satellite Multifunctional Satellite project is expected Under Preparation
to provide benefits for Indonesia services (OBC)
for citizens as well as education and defense
development.
xxiv
P u b l i c p r i vat e pa rt N e r s h i p s
Status
No Project Name Description
(December 2017)
xxv
P u b l i c p r i vat e pa rt N e r s h i p s
Project Estimated
Sector/Sub-sector Project Name Project Cost
Readiness
(USD Million)
Ready to Water Supply West Semarang Water Supply 34.0
Offer
Transportation
Toll Road and Toll Semarang – Demak Toll Road 583.4
Bridge Surabaya – Madura Toll Bridge 169.0
Yogya – Bawen Toll Road 1,018.9
Railway Medan Municipal Transport 353.0
Solid Waste and Sanitation
Water Supply Pekanbaru Water Supply 37.6
Under
Preparation Health
Hospital Sidoarjo General Hospital 18.7
Development of Pirngadi Hospital 40.9
Indonesia National Cancer Center
48.6
Dharmais Hospital
Social Infrastructure
Welfare System National Integrated Welfare System 176.5
xxvi
P u b l i c p r i vat e pa rt N e r s h i p s
1
P u b l i c p r i vat e pa rt N e r s h i p s
Success Story : 6.
7.
Manado - Bitung Toll Road
Pandaan - Malang Toll Road
8. Central Java Power Plant
9. Umbulan Water Supply
10. Palapa Ring West Package
11. Palapa Ring Central Package
12. Palapa Ring East Package
2
P u b l i c p r i vat e pa rt N e r s h i p s
Description:
Financial Feasibility:
FIRR : 13.78 %
NPV : USD 260.0 milion
Government Contracting Agency : Indonesia Toll Road Authority (“BPJT”) On Behalf of Ministry of Public Works
and Housing
Contact Person : Mr. Herry Trisaputra Zuna (Head of BPJT) +62-21-7258063;
e-mail: bpjt@pu.go.id or investasi2.bpjt@gmail.com
3
P u b l i c p r i vat e pa rt N e r s h i p s
Description :
This Toll Road (74.2 km) is a section of the Trans-Java Toll
Road Network that will connect Jakarta and Surabaya.
Batang is a regency on the north coast of Central Java
Province while Semarang is the largest and capital city
of Central Java Province.
Estimated Project Cost : USD 850.0 milion
Financial Feasibility :
FIRR : 13.70 %
NPV : USD 230.0 Milion
Estimated Concession Period : 45 Years
Government Contracting Agency : Indonesia Toll Road Authority (“BPJT”) On Behalf of Ministry of Public Works
and Housing
Contact Person : Mr. Herry Trisaputra Zuna (Head of BPJT) +62-21-7258063;
e-mail: bpjt@pu.go.id or investasi2.bpjt@gmail.com
4
P u b l i c p r i vat e pa rt N e r s h i p s
Description:
The project is an elevated 36.4 km toll road to be built
over the existing Jakarta - Cikampek toll road, which
is being operated by PT Jasa Marga. The Jakarta
-Cikampek road is part of the Trans-Java toll road
network connecting Jakarta and Surabaya. The existing
road’s capacity has already been reached, but there are
limitations to widening it thus the proposed solution is
to expand the road’s capacity by building over it.
Estimated Project Cost : USD 1,249.0 Milion
Financial Feasibility:
FIRR : 12.60%
NPV : USD 104.0 Milion
Estimated Concession Period : 45 Years
Government Contracting Agency : Indonesia Toll Road Authority (“BPJT”) On Behalf of Ministry of Public Works
and Housing
Contact Person : Mr. Herry Trisaputra Zuna (Head of BPJT) +62-21-7258063;
e-mail: bpjt@pu.go.id or investasi2.bpjt@gmail.com
5
P u b l i c p r i vat e pa rt N e r s h i p s
Description:
Financial Feasibility:
FIRR : 14.60%
NPV : USD 287.0 Milion
Government Contracting Agency : Indonesia Toll Road Authority (“BPJT”) On Behalf of Ministry of Public Works
and Housing
Contact Person : Mr. Herry Trisaputra Zuna (Head of BPJT) +62-21-7258063;
e-mail: bpjt@pu.go.id or investasi2.bpjt@gmail.com
6
P u b l i c p r i vat e pa rt N e r s h i p s
Description:
Financial Feasibility :
FIRR : 15.89 %
NPV : USD 231.0 Milion
Project Status:
Financial close, land acquisition and under
construction
Government Contracting Agency : Indonesia Toll Road Authority (“BPJT”) On Behalf of Ministry of Public Works
and Housing
Contact Person : Mr. Herry Trisaputra Zuna (Head of BPJT) +62-21-7258063;
e-mail: bpjt@pu.go.id or investasi2.bpjt@gmail.com
7
P u b l i c p r i vat e pa rt N e r s h i p s
Description:
This toll road is one of the longest in Northern
Sulawesi connecting from Manado City to
Bitung City, approximately 39.9 km in length.
Financial Feasibility:
FIRR : 12.20 %
NPV : USD 13.7 Million
Government Contracting Agency : Indonesia Toll Road Authority (“BPJT”) On Behalf of Ministry of Public Works
and Housing
Contact Person : Mr. Herry Trisaputra Zuna (Head of BPJT) +62-21-7258063;
e-mail: bpjt@pu.go.id or investasi2.bpjt@gmail.com
8
P u b l i c p r i vat e pa rt N e r s h i p s
Description:
Pandaan - Malang toll road is designed
to improve connectivity in the region. In
addition, the toll road is expected to facilitate
industrial transportations from Pandaan
to Malang which are connected directly to
Surabaya, and vice versa.
Estimated Project Cost : USD 461.0 Milion
Financial Feasibility:
FIRR : 13.81%
NPV : USD 99.0 Milion
Estimated Concession
Period : 35 Years
Government Contracting Agency : Indonesia Toll Road Authority (“BPJT”) On Behalf of Ministry of Public Works
and Housing
Contact Person : Mr. Herry Trisaputra Zuna (Head of BPJT) +62-21-7258063;
e-mail: bpjt@pu.go.id or investasi2.bpjt@gmail.com
9
P u b l i c p r i vat e pa rt N e r s h i p s
Description:
This project is the development of coal-
fired power plant in Batang Regency,
Central Java with capacity of 2x1,000
MW. It is considered as the largest PPP
electricity project by capacity in Asia.
Estimated Project Cost :
USD 4,200.0 million
Financial Feasibility:
FIRR : 11.12%
NPV : USD 938.7 million
Estimated Concession
Period : 25 Years
10
P u b l i c p r i vat e pa rt N e r s h i p s
Description:
The Umbulan Water Supply Project aims to
increase the water supply capacity to meet
the demand in the East Java Province. The
capacity of the drinking water is 4,000 lps
at Gresik Regency, Surabaya City, Pasuruan
City, Pasuruan Regency and PDAM (Industrial
Area) connecting approximately 320,000
households.
Estimated Project Cost : USD 140.7 milion
Financial Feasibility :
FIRR : 14.00 %
NPV : USD 34.2 milion
Estimated Concession Period : 25 Years
11
P u b l i c p r i vat e pa rt N e r s h i p s
Description:
Development of fiber optic-based
broadband telecommunication
network which will connect Riau
Province, Riau Islands and the
Natuna Island with a total length
about 2,275 km.
Estimated Project Cost :
USD 87.6 Million
Financial Feasibility:
IRR : 15.08 %
NPV : USD 8.6 Million
Estimated Concession Period :
15 Years
12
P u b l i c p r i vat e pa rt N e r s h i p s
Description:
Development of fiber optic based
broadband telecommunication
network covering 17 regencies
across Kalimantan, Sulawesi, and
Maluku.
Estimated Project Cost :
USD 71.5 Million
Financial Feasibility:
FIRR : 13.01%
NPV : USD 13.2 Million
Estimated Concession
Period : 15 Years
13
P u b l i c p r i vat e pa rt N e r s h i p s
Description:
Development of fiber optic-based
broadband telecommunication
network and microwave trans-
mission which will connect 35
regencies in East Nusa Tenggara,
Maluku, West Papua and remote
places inside Papua with a total
length of about 6,878 km.
Estimated Project Cost :
USD 386.5 Million
Financial Feasibility:
FIRR : 14.30 %
NPV : USD 22.7 milion
Estimated Concession
Period : 15 Years
14
P u b l i c p r i vat e pa rt N e r s h i p s
15
P u b l i c p r i vat e pa rt N e r s h i p s
16
P u b l i c p r i vat e pa rt N e r s h i p s
Description:
Traffic volume through the Jakarta-
Cikampek toll road capacity has exceeded
with the V/C ratio high of 1.51. The Corridor
plan of this toll road section is located in
the administrative area of the West Java
Province, namely: the city of Bekasi, Bogor
District, Bekasi District, Karawang, and
Purwakarta District.
Estimated Project Cost :
USD 1,079.5 Milion
Financial Feasibility :
FIRR : 12.32%
NPV : USD 5.0 Million
Estimated Concession Period : 35 Years
Government Contracting Agency : Indonesia Toll Road Authority (“BPJT”) On Behalf of Ministry of Public Works
and Housing
Contact Person : Mr. Herry Trisaputra Zuna (Head of BPJT); +62-21-7258063; e-mail:
investasi2.bpjt@gmail.com; bpjt@pu.go.id
Investors:
PT Jasamarga Japek Selatan
Financier :
Refinancing with syndication of BNI, BCA, and
Bank Mandiri
17
P u b l i c p r i vat e pa rt N e r s h i p s
Description:
This project is expected to play
an integral part of East Java Road
System. It is 172 km in length
which connects Probolinggo and
Banyuwangi, crossing three districts
in East Java including Situbondo
district. Each district has different
potential resources which still
should be developed.
Estimated Project Cost :
USD 1,718.8 Million
Financial Feasibility:
FIRR : 11.17%
NPV : USD 45.9 Million
Estimated Concession
Period : 35 Years
Government Contracting Agency : Indonesia Toll Road Authority (“BPJT”) On Behalf of Ministry of Public
Works and Housing
Contact Person : Mr. Herry Trisaputra Zuna (Head of BPJT) +62-21-7258063;
e-mail: bpjt@pu.go.id or investasi2.bpjt@gmail.com
Investor :
PT Jasamarga Probolinggo Banyuwangi
Financier :
Financial close through Contractor Pre-
Financing (CPF)
18
P u b l i c p r i vat e pa rt N e r s h i p s
Description:
Serang – Panimbang Toll Road is Located in
Banten Province where the toll reach from
Jakarta to Tanjung Lesung Special Economic
Zone. Furthermore, One of the attractive
points for development of this toll road is
that it will have tremendous facilities, such
as development of residential areas and
commercial areas along the corridor.
Estimated Project Cost : USD 391.6 Million
Financial Feasibility :
FIRR : 13.96%
NPV : USD 39.1 Million
Estimated Concession Period : 40 Years
Government Contracting Agency : Indonesia Toll Road Authority (“BPJT”) On Behalf of Ministry of Public Works
and Housing
Contact Person : Mr. Herry Trisaputra Zuna (Head of BPJT) +62-21-7258063;
e-mail: bpjt@pu.go.id or investasi2.bpjt@gmail.com
Investors :
PT Wijaya Karya Serang Panimbang
Financier :
CPF (PT WIKA & PT PP)
19
P u b l i c p r i vat e pa rt N e r s h i p s
Description:
Serang–Panimbang Toll Road in Banten
Province will connect Jakarta to Tanjung
Lesung Special Economic Zone. Further-
more, one of the attractive points of this
toll road is that it will have various facilities,
such as the development of residential and
commercial areas along the corridor.
Estimated Project Cost :
USD 253.7 Million
Financial Feasibility:
FIRR : 11.40%
NPV : USD 409.0 Million
Estimated Concession
Period : 16.5 Years
Government Contracting Agency : Indonesia Toll Road Authority (“BPJT”) On Behalf Ministry of Public Works
and Housing
Contact Person : Mr. Herry Trisaputra Zuna (Head of BPJT) +62-21-7258063;
e-mail: bpjt@pu.go.id or investasi2.bpjt@gmail.com
Financier :
CPF (PT WIKA & PT PP)
Implementation Schedule
(Estimated):
1. Preparation : 2016
2. Land Acquisition : 2017
3. Construction : 2018
4. Operation : 2019
20
P u b l i c p r i vat e pa rt N e r s h i p s
Description:
The Cileunyi – Sumedang – Dawuan
Toll Road project will provide direct
access for transporting agricultural
and manufacturing goods as well as
services produced from these areas to
the port city of Cirebon. This toll road
is urgently required to shift some of
the development to the east side of
Bandung.
Estimated Project Cost :
USD 617.9 Million
Financial Feasibility:
FIRR : 13.11%
NPV : USD 17.90 Million
Estimated Concession
Period : 40 Years
Government Contracting Agency : Indonesia Toll Road Authority (“BPJT”) On Behalf of Ministry of Public Works
and Housing
Contact Person : Mr. Herry Trisaputra Zuna (Head of BPJT) +62-21-7258063;
e-mail: bpjt@pu.go.id or investasi2.bpjt@gmail.com
Investor :
PT Cipta Karya Jabar Tol
Financier :
TBC
21
P u b l i c p r i vat e pa rt N e r s h i p s
Description:
Nambo waste processing technology can
accommodate 1500-1800 tons of waste
every day. The purpose of making TPPAS
Nambo is to produce some recycled
products such as compost, RDF, recycle
materials, syntetic gas, syntetic oil and
biogas. This capacity can produce 500-600
tons of Revused Derived Fuel (RDF).
Estimated Project Cost : USD 44.4 Milion
Financial Feasibility:
FIRR : 13.60%
NPV : USD 4.8 Million
Estimated Concession Period : 25 Years
22
P u b l i c p r i vat e pa rt N e r s h i p s
Description:
It is a joint project between government and
business entity to increase the coverage
of drinking water services for the society
of Bandar Lampung, from 20% (2015) to
46% (2024), and to improve environmental
sanitation, living standards and public health.
Estimated Project Cost : USD 82.6 Million
Financial Feasibility:
FIRR : 15.30 %
NPV : USD 20.7 Milion
Estimated Concession Period : 25 Years
Government Contracting Agency : Way Rilau Regional Water Supply Company (“PDAM”)
Contact Person : Mr. Suparji (Technical director of PDAM)
+62-721-483855; e-mail: kpbuspam@pdamwayrilau.com
23
P u b l i c p r i vat e pa rt N e r s h i p s
Description:
Jatiluhur Regional Water Supply system
has an outflow of 5000 lps that will supply
Karawang Regency, Bekasi Regency, Bekasi
City and DKI Jakarta. The project covers
the construction of intake, transmission
pipeline, water treatment plant (WTP), and
the development of main network.
Estimated Project Cost : USD 142.2 Million
Financial Feasibility:
FIRR : 13.62%
NPV : USD 29.8 Million
Estimated Concession Period : 30 Years
24
P u b l i c p r i vat e pa rt N e r s h i p s
25
P u b l i c p r i vat e pa rt N e r s h i p s
Sector
26
P u b l i c p r i vat e pa rt N e r s h i p s
Description:
SPAM West Semarang project is built with a
capacity of 1,000 liters per second. The service
area is planned to be targeted to serve three (3) sub
districts divided into five (5) service zone zones.
Estimated Project Cost : USD 34.0 Million
Financial Feasibility:
FIRR : 16.00 %
NPV : USD 1.8 million
Estimated Concession Period : 27 Years
Government Contracting Agency : Tirta Moedal Regional Water Supply Company (PDAM)
Contact Person : Muhammad Farchan (Director of PDAM Tirta Moedal Semarang
Municipal) +62248315514; email: smgwater@gmail.com
27
P u b l i c p r i vat e pa rt N e r s h i p s
DIGEST PROJECTS
Project Title : West Semarang Water Supply
Government Contracting Agency : PDAM Tirta Moedal Kota Semarang
Implementing Unit : PDAM Tirta Moedal Kota Semarang
Preparation Agency : PT Sarana Multi Infrastruktur
Estimated Project Cost : USD 34.0 Million
Estimated Concession Period : 27 Years
Location : Semarang, Central Java
2. The Opportunity
2.1. Project Background
Currently PDAM Tirta Moedal Semarang City only serves 167,979 customers or
1,010,806 residents, about 62.02% of the total population of Semarang City. The
necessity of clean water can be seen from surveys showing that the population’s
interest in PDAM services is quite high, reaching 85%. However, this is constrained
by the PDAM’s water production which cannot be increased due to the limited water
production capacity from the current SPAM facility.
Given the limited current production capacity and in order to achieve the service level
target of 90%, one of the efforts made by the Semarang City Government together
with PDAM Tirta Moedal is to build and develop the Water Supply System of West
Semarang (SPAM West Semarang) in the the scheme of Government Cooperation
28
P u b l i c p r i vat e pa rt N e r s h i p s
with Business Entity which called as Public Private Partnership (known as KPBU).
SPAM West Semarang project is built with a capacity of 1000 liters per second. The
service area is planned to be targeted to serve three (3) sub districts divided into
five (5) service zone zones, namely Tugu Sub district (zone 1), part of Ngaliyan Sub
district (zone 2 and 3), and West Semarang Sub district (zone 4 and 5). Zone 1 located
in Tugu is a greenfield area whose majority population uses deep wells as water
source. Zone 2 and 3 are located in Ngaliyan, can be categorized as semi-greenfield
area with the number of customers of PDAM is very low. Zone 4 and 5 are located
in West Semarang recorded as the oldest service area which is currently already
served by PDAM Tirta Moedal.
1. Meet the requirements of drinking water for residents of West Semarang City,
whose currently met from shallow wells and deep wells.
2. Reduce the risk of environmental damage, especially the decrease of the soil
surface caused by the exploitation of deep wells. Currently, the city of Semarang
experienced a decrease in land ranging from 8-10 cm / year.
- BOT (Build – Operate – Transfer). IPA development along with a 1000 l/sec as well
as a distribution reservoir, and a water transmission pipe to each of the distribution
reservoirs to serve the service area development plan.
- Operation and maintenance of intake, grit chamber, and pump house along with
its complementary buildings and raw water network constructed by the Ministry
of Public Works and People’s Housing through the Directorate General of Water
Resources
29
P u b l i c p r i vat e pa rt N e r s h i p s
II Reservoir
30
P u b l i c p r i vat e pa rt N e r s h i p s
7. Project Structure
Estimated project cost USD 34.0 Million
Indicative debt to equity
- Debt Level 70%
- Equity Level 30%
FIRR 16.00%
31
P u b l i c p r i vat e pa rt N e r s h i p s
32
P u b l i c p r i vat e pa rt N e r s h i p s
33
P u b l i c p r i vat e pa rt N e r s h i p s
1. Railway Sector
2. Road Sector
Under
3. Water Supply Sector
4. Telecommunication & Informatics Sector
5. Energy Conservation Sector
Preparation 6.
7.
Education Research and Development Sector
Health Facility Sector
8. Correctional Facility Sector
34
P u b l i c p r i vat e pa rt N e r s h i p s
Railway Sector
1. Medan Municipal Transport
35
P u b l i c p r i vat e pa rt N e r s h i p s
Description:
The LRT system is planned to be built with
elevated structures connecting the urban sub-
centers of Lau Chi Market in the Southwest
of Medan with sub-city centers in the
northeastern part of Medan City along 21 km
and through 16 stations. BRT system will cross
Jalan Sisingamaraja to Jalan Gatot Subroto
with a length of 18.4 km.
Estimated Project Cost : USD 353.0 Million
Financial Feasibility:
FIRR : 14.46%
NPV : USD 293.4 Million
Estimated Concession Period : 35 Years
Q1 2018
Q2 2018 Q3 2018 Q2 2019 Q4 2019
Final Q2 2019 Q1 2020
Business Pre - Request Contract Financial
Qualification Bid Award Signing Close Construction
case (FBC) for Proposal
36
P u b l i c p r i vat e pa rt N e r s h i p s
DIGEST PROJECTS
Project Title : Medan Municipal Transport
Government Contracting Agency : Mayor of Medan
Implementing Unit : Regional Development Planning Agency of
Medan City
Preparation Agency : PT SMI through Project Setup Facility (Project
Development Facility) from Ministry of Finance
Estimated Project Cost : USD 353.0 Million
Estimated Concession Period : 35 years
Location : Medan City
*Note:The initial assumption is based on ideal calculation with best practice facility (Project
Cost calculation is still arranged in FBC stage)
1. Project Picture
2. The Opportunity
2.1. Project Background
The city of Medan is one of the 5 major cities in Indonesia with a population of 2
million people. It has an area of 265.10 km2 with a density of 8.130 people/ km2.
It is ranked 15th as one of the cities with a high density out of 90 other big cities in
Indonesia.
37
P u b l i c p r i vat e pa rt N e r s h i p s
38
P u b l i c p r i vat e pa rt N e r s h i p s
7. Project Structure
* Note: The initial assumption is based on ideal calculation with best practice facility
(Project Cost calculation is still arranged in FBC stage)
39
P u b l i c p r i vat e pa rt N e r s h i p s
Transportation
Public Sector Agency Service Contact
0&M • Servicer
Contract • Collecting Tariff
Bus Operator SOE
Ticketing System End User ROE
40
P u b l i c p r i vat e pa rt N e r s h i p s
41
P u b l i c p r i vat e pa rt N e r s h i p s
Road Sector 2.
3.
Yogya - Bawen Toll Road
Surabaya - Madura Toll Brigde
42
P u b l i c p r i vat e pa rt N e r s h i p s
43
P u b l i c p r i vat e pa rt N e r s h i p s
Description:
The Proposed project will connect Semarang
(Capital of Central Java Province) – Demak
(Tourism City). This Project has high traffic
volume with 25.25 Km in length, Semarang is
capital town of Central Java Province, which
is well-developed with industrial goods and
trading. On the other side, Demak is a region
that rich with its natural resources.
Estimated Project Cost : USD 583.4 Million
Financial Feasibility:
FIRR : 10.43%
NPV : USD 0.6 Million
Estimated Concession Period : 35 Years
Government Contracting Agency : Indonesia Toll Road Authority (“BPJT”) On Behalf of Ministry of Public
Works and Housing
Contact Person : Mr. Herry Trisaputra Zuna; +62-21-7258063; e-mail: bpjt@pu.go.id or
investasi2.bpjt@gmail.com
Q1 2018 Q4 2019-
Q3 2018 Q4 2018 Q3 2019
Final Q2 2019 Q1 2020 Q2 2020
Business Pre - Request Contract
Qualification Bid Award Signing Financial Construction
case (FBC) for Proposal Close
Recourse Guarantee
Budgeting Agreement Indonesia Agreement
Mechanism Infrastructure
Guarantee Fund
Ministry of
Finance
MPWH Recourse Payment
(Based on PMK 260/2019)
44
P u b l i c p r i vat e pa rt N e r s h i p s
DIGEST PROJECTS
Project Title : Semarang – Demak Toll Road
Government Contracting Agency : Indonesia Toll Road Authority (BPJT) on Behalf of
Ministry of Public Works and Housing
Implementing Unit : Indonesia Toll Road Authority (BPJT)
Preparation Agency : Indonesia Toll Road Authority (BPJT)
Estimated Project Cost : USD 583.4 Million
Estimated Concession Period : 35 years
Location : Central Java
2. The Opportunity
2.1. Project Background
Road infrastructure is one of the main factors for the improvement of economic
growth within a region. A Toll Road, being a part of a larger road infrastructure, is
used as an accelerator around stakeholders who run the economic development,
the Ministry of Public Works and Housing Cq. Indonesian Toll Road Authority plans
to accelerate the development of the Semarang – Demak Toll Road which will
accelerate Central Java’s economic development.
45
P u b l i c p r i vat e pa rt N e r s h i p s
fields, plantation, housing, and industrial area are found. It will cross two regions in
Central Java: Semarang and the Demak Regency. Semarang, the Provincial capital of
Central Java, which is well-developed with industrial goods and trading. On the other
side, Demak is a region that is rich with its natural resources.
46
P u b l i c p r i vat e pa rt N e r s h i p s
7. Project Structure
47
P u b l i c p r i vat e pa rt N e r s h i p s
48
P u b l i c p r i vat e pa rt N e r s h i p s
Description:
Yogya – Bawen Toll Road (71.56 Km) will support
Yogyakarta Solo Semarang (Joglosemar)
Tourism Area, which will become the main
tourism area in Indonesia to achieve 20 million
foreign tourist in 2020
Estimated Project Cost : USD 1,018.9 Million
Financial Feasibility:
FIRR : 11.15 %
NPV : USD 1,044.1 Million
Estimated Concession Period : 35 years
Government Contracting Agency : Indonesia Toll Road Authority (“BPJT”) On Behalf of Public Works &
Housing
Contact Person : Mr. Herry Trisaputra Zuna (Head of BPJT) +62-21-7258063;
e-mail: bpjt@pu.go.id or investasi2.bpjt@gmail.com
Q4 2018-
Q2 2018 Q3 2018 Q3 2019 Q1 2020
Q12019 Q2 2019 Q2 2020
Final Pre - Contract Financial
Business Qualification Request Bid Award Signing Close Construction
case (FBC) for Proposal
49
P u b l i c p r i vat e pa rt N e r s h i p s
DIGEST PROJECTS
Project Title : Yogya – Bawen Toll Road
Government Contracting Agency : Indonesia Toll Road Authority (BPJT) On Behalf
of Ministry of Public Works and Housing
Implementing Unit : Indonesia Toll Road Authority (BPJT)
Preparation Agency : Indonesia Toll Road Authority (BPJT)
Estimated Project Cost : USD 1,018.9 Million
Estimated Concession Period : 35 years
Location : Central Java
2. The Opportunity
2.1. Project Background
Yogya - Bawen Toll Road will connect Semarang-Solo Toll Road to Yogyakarta. It’s
planned to reduce heavy traffic on arterial road, Yogyakarta-Bawen. This toll road
will also support industrial area in Ungaran-Bawen corridor and development of
Joglosemar tourism area. Economic activity, industries and tourism in Yogya and
Semarang will encourage usage of Yogya -Bawen toll road.
50
P u b l i c p r i vat e pa rt N e r s h i p s
Length 71.56 km
Design Speed 100 - 120 km/hour
Total lanes 2 x 2 lanes (Initial)
2 x 3 lanes (Final)
Width of Lane 3,6 m
Outer Shoulder 3,0 m
Inner Shoulder 1,5 m
Median Width 5,5 m
7. Project Structure
51
P u b l i c p r i vat e pa rt N e r s h i p s
52
P u b l i c p r i vat e pa rt N e r s h i p s
53
P u b l i c p r i vat e pa rt N e r s h i p s
Description:
Suramadu Bridge is a Toll Road Project that
had been operated since 2009. The current
concession holder is PT. Jasa Marga (Persero)
Tbk, and the concession period will be ended
in 2017. The Government of Indonesia have
to conduct the tender process in order to
continue the operation and maintenance of
this project.
Estimated Project Cost : USD 169.0 Million
Financial Feasibility:
FIRR : 17.96%
NPV : USD 1,160.9 Million
Estimated Concession Period : 15 Years
Government Contracting Agency : Indonesia Toll Road Authority (“BPJT”) On Behalf of Ministry of Public
Works and Housing
Contact Person : Mr. Herry Trisaputra Zuna; +62-21-7258063; e-mail: bpjt@pu.go.id or
investasi2.bpjt@gmail.com
Q1 2018 Q1 2020
Q3 2018 Q4 2018 Q2 2019 Q4 2019
Q1 2019 Operation
Final Pre - Request Contract Financial
Business Bid Award and
Qualification for Proposal Signing Close Maintenance
case (FBC)
Public
Service Agency
(BLU) BPJT
54
P u b l i c p r i vat e pa rt N e r s h i p s
DIGEST PROJECTS
Project Title : Surabaya - Madura (Suramadu) Toll Bridge
Government Contracting Agency : Indonesia Toll Road Authority (BPJT) on Behalf
of Ministry of Public Works and Housing
Implementing Unit : Indonesia Toll Road Authority (BPJT)
Preparation Agency : Indonesia Toll Road Authority (BPJT)
Estimated Project Cost : USD 169.0 Million
Estimated Concession Period : 15 years
Location : East Java Province.
2. The Opportunity
2.1. Project Background
The Suramadu Toll Bridge connects the Province of Java and the Madura Island. The
main goal of this toll road is to accelerate the economic development, especially in
the Madura Island.
55
P u b l i c p r i vat e pa rt N e r s h i p s
Length 5,4 km
Design Speed 60 - 80 km/hour
Total lanes 2x2m
2 x1 m (Motor cycle)
Emergency Lane 2 x 2,25 m
Lane Width 3,5 m
3,0 m (Motor cycle)
Maximum Flateness 3%
56
P u b l i c p r i vat e pa rt N e r s h i p s
Q1 2018 Q1 2020
Q3 2018 Q4 2018 Q2 2019 Q4 2019
Q1 2019 Operation
Final Pre - Request Contract Financial
Business Bid Award and
Qualification for Proposal Signing Close Maintenance
case (FBC)
57
P u b l i c p r i vat e pa rt N e r s h i p s
Sector
58
P u b l i c p r i vat e pa rt N e r s h i p s
59
P u b l i c p r i vat e pa rt N e r s h i p s
Description:
The purpose of SPAM Pekanbaru is to provide
reliable drinking water infrastructure and to support
economic activities in Pekanbaru City as well as
to be managed efficiently. The project capacity
plan is 500 liters per second. Home Connection is
targeted at 39,000 by 2024, an additional 23,600
home connection is required during 2022-2024 or
7,890 home connection per year
Estimated Project Cost : USD 37.6 Million
Financial Feasiblity:
FIRR : 15.00%
NPV : USD 9.2 Million
Estimated Concession Period : 25 Years
Government Contracting Agency : Tirta Siak Regional Water Supply Company (PDAM) Pekanbaru City
Contact Person : Mr. Kemas Yuzferi (Director of PDAM) +62-761-23825 ;
e-mail: pdamts.kpbu@gmail.com
Pekanbaru
Municipal
IIGF
Regress Guarantee Equity
Agreement Agreement Investor
PDAM Payment
SPV
(PJPK)
PPP
Agreemenrt Financial
Payment Water Debt Institution
Supply
Services Facility
Customers
60
P u b l i c p r i vat e pa rt N e r s h i p s
DIGEST PROJECTS
Project Title : Pekanbaru Regional Water Supply
Government Contracting Agency : PDAM Tirta Siak Pekanbaru City
Implementing Unit : PDAM Tirta Siak Pekanbaru City
Preparation Agency : PT Sarana Multi Infrastruktur (Persero)
Estimated Project Cost : USD 37.6 Million
Estimated Concession Period : 25 Years
Location : Pekanbaru City
2. The Opportunity
2.1. Project Background
The city of Pekanbaru as the capital of the Province of Riau, is currently undergoing
physical development that has implications for land function and population density.
Based on the Pekanbaru Water Supply System Master Plan (PDAM), the targeted
drinking water service reached 95% in 2033. Based on the RPJMN 2015-2019,
the coverage of drinking water service throughout Indonesia by 2019 should have
reached 100% and the service level is targeted to reach 95% by the year 2019.
61
P u b l i c p r i vat e pa rt N e r s h i p s
62
P u b l i c p r i vat e pa rt N e r s h i p s
No Specification Criteria
I Intake
1. Construction Reinforced concreted
2. Capacity 550 L/ sec
63
P u b l i c p r i vat e pa rt N e r s h i p s
64
P u b l i c p r i vat e pa rt N e r s h i p s
Division of Pekanbaru, the status of land to be used for the construction site of the
reservoir in the Pekanbaru SPAM Project.
7. Project Structure
Pekanbaru
Municipal
IIGF
Regress Guarantee Equity
Agreement Agreement Investor
PDAM Payment
SPV
(PJPK)
PPP
Agreemenrt Financial
Payment Water Debt Institution
Supply
Services Facility
Customers
65
P u b l i c p r i vat e pa rt N e r s h i p s
Sector
66
P u b l i c p r i vat e pa rt N e r s h i p s
67
P u b l i c p r i vat e pa rt N e r s h i p s
MULTIFUNCTION SATELLITE
LOCATION: National
Description:
Multifunctional satellite project is expected
to provide benefits for Indonesia’s services
to citizens as well as education and defense
development. Private partner shall be
responsible to finance, design, construct,
operate, and maintain the infrastructure
assets.
Estimated Project Cost : USD 589.3 Million
Financial Feasibility:
FIRR : 8.81%
NPV : USD 75.0 Milion
Estimated Concession Period : 15 Years
USO Collaboration
USO Implementation
68
P u b l i c p r i vat e pa rt N e r s h i p s
DIGEST PROJECTS
Project Title : Multifunction Satellite
Government Contracting Agency : Minister of Communication and Informatics
Implementing Unit : Ministry of Communication and Informatics
Preparation Agency : 1. Ministry of Communication and Informatics
2. Ministry of National Development Planning
Estimated Project Cost : USD 589.3 Million
Estimated Concession Period : 15 years
Location : Indonesia
2. The Opportunity
2.1. Project Background
Currently, competition of satellite business in the Asia-Pacific region is increasing.
Asia-Pacific region, especially Southeast Asia region, still needs satellites as
telecommunications and broadcasting infrastructure (broadcasting). It caused
by several factors: the high demand for services among others cellular backhaul,
broadband backhaul, enterprise network, OUTV (Occasional Usage TV), military and
government network, DTH television, flight communication, and recovery solution at
the time of natural disasters (disaster recovery).
The usage of satellite transponder in Indonesia is growing rapidly for banking,
military, and government agencies. Satellite are required for communications, data
transfer, broadband internet, and video. This condition become harder as the fact
Indonesia is an archipelago country that it find still challenging to reach terrestrial
infrastructure network using fiber optic and microwave links.
Currently, Indonesia required 220 – 230 transponders while there are only 130 – 140
transponders which provided by local operators with USD 1 million per channel each
year.
69
P u b l i c p r i vat e pa rt N e r s h i p s
70
P u b l i c p r i vat e pa rt N e r s h i p s
71
P u b l i c p r i vat e pa rt N e r s h i p s
7. Project Structure
USO Collaboration
USO Implementation
72
P u b l i c p r i vat e pa rt N e r s h i p s
Description:
Ministry of Social Affairs has a plan to develop nationally
integrated welfare system by web-based application
with cloud computing technology. The scopes of the
PPP project are development of the information system,
software, VPN network in all districts/cities and province
in Indonesia, cloud computing service (virtual data center),
conducting technical assistance and implementation of
monitoring and evaluation system.
Estimated Project Cost : USD 176.5 Million
Financial Feasibility:
FIRR : 14.00%
NPV : USD 2,449.7 Million
Estimated Concession Period : 20 Years
Q1 2018
Q2 2018 Q3 2018 Q3 2019 Q3 2019 Q4 2019 Q1 2020
Final
Business Pre - Request Bid Award Contract Financial Construction
case (FBC) Qualification for Proposal Signing Close
GCA
Secretary General of Regress Agreement
Data Service Service Ministry Social Affair
Payment AP IOGF
PPP
Agreement Guarantee Agreement
End User
(Ministrt/Institution, NGO Equity Financing
Donor, etc) Equiry
Special Purpose
Ministry of Social Company
Affair Debt Financing Finansial
Institution
Provision, building Development of Development and
Data Center Office National Integrated Maintenance IT Financing
Maintenance Wolfare System Infrastructure
73
P u b l i c p r i vat e pa rt N e r s h i p s
DIGEST PROJECTS
Project Title : National Integrated Welfare System
Government Contracting Agency : Minister of Social Affairs
Implementing Unit : Data and Information Centre
Preparation Agency : 1. Ministry of Sosial Affairs
2. Ministry of National Development Planning
Estimated Project Cost : USD 176.5 Million
Estimated Concession Period : 20 Years
Location : DKI Jakarta
2. The Opportunity
2.1. Project Background
According to Law no. 11 Year 2009, Social Welfare Implementation is a focused,
integrated, and sustainable effort by the government, local government and society
in the form of social services to meet the basic needs of every citizen, which includes
social rehabilitation, social security, social empowerment and protection social. In
the same law in Article 5 it is mentioned that the implementation of social welfare is
directed to individuals, families, groups, and/ or the community.
The target of social welfare implementation is Social Welfare Problems (PMKS)
supported by Social Welfare Potential and Sources (PSKS). According to Minister of
Social Affair Regulation Number 8 Year 2012 on Data Collection and Management
Manual of PMKS and PSKS, there are 26 and 12 types of PMKS and PSKS respectively.
The PMKS and PSKS data are managed by each technical unit at the Ministry of Social
Affairs separately and not well coordinated. As a result of these data management,
several important issues arise, data duplication, data inconsistency, provision of data
for incomplete and inaccurate social welfare programs, and high financing for data
updating and management.
74
P u b l i c p r i vat e pa rt N e r s h i p s
75
P u b l i c p r i vat e pa rt N e r s h i p s
7. Project Structure
DFB and M
Estimated project cost USD 176.5 Million
Indicative debt to equity
- Debt Level 70%
- Equity Level 30%
FIRR 14.00%
76
P u b l i c p r i vat e pa rt N e r s h i p s
77
P u b l i c p r i vat e pa rt N e r s h i p s
Energy Conservation
1. Surakarta Street Lighting
Sector
78
P u b l i c p r i vat e pa rt N e r s h i p s
79
P u b l i c p r i vat e pa rt N e r s h i p s
Description:
The Government of Surakarta intends to
revitalize the public services of its street lighting.
The total length of the streets is estimated
at 976 km. Current studies show that the city
needs around 31,890 lamp points.
Estimated Project Cost : USD 28.4 Milion
(10 years) or 45.9
Milion (20 years)
Financial Feasibility:
FIRR : 10.17% (10 years) / 10.67% (20 years)
NPV : USD 0.9 Million (10 years) / 2.4 Million
(20 years)
Estimated Concession Period :
10 or 20 Years (will be concluded in FBC)
80
P u b l i c p r i vat e pa rt N e r s h i p s
DIGEST PROJECTS
Project Title : Surakarta Street Lighting
Government Contracting Agency : Mayor of Surakarta City
Implementing Unit : Local Government of Surakarta City
Preparation Agency : 1. Local Government of Surakarta City
2. Ministry of National Development Planning
Estimated Project Cost : USD 28.4 Million or 45.9 Million
Estimated Concession Period : 10 or 20 years
Location : Surakarta
*Note:The initial assumption is based on ideal calculation with best practice facility (Project Cost calculation is still arranged in
FBC stage)
2. The Opportunity
2.1. Project Background
Based on its vision and mission, The Municipal Government of Surakarta changes
its view on the municipal’s Public Street Lighting (Penerangan Jalan Umum, or PJU)
from merely an asset owned to the municipal to public services. The PJU illuminates
the public streets of Surakarta City. The total public roads in Surakarta are around
976 km, based on current assessment by the municipal government.
Based on evaluation done by the municipal government in 2016, the PJU as a public
service is still not functioning optimally. Besides not saving electricity, poles and
lamps are not uniform and nonstandard. In addition, the lighting has not been evenly
distributed along the existing public roads.
Based on this background, the Government of Surakarta intends to revitalize the
public services of PJU. For this purpose, following up on last year evaluation, in 2017
the municipal government conducted a study in the preparation of Public Private
Partnership for Public Street Lighting (KPBU PJU) project.
81
P u b l i c p r i vat e pa rt N e r s h i p s
641 non-strategic or environment roads. The service level for the Street Lighting will
be determined mainly based on: illumination, lumination and glare. For this purpose,
the municipal has decided to use Indonesian National Standard (Standard Nasional
Indonesia or SNI) on Street Lighting Specification in City Streets, SNI 7391:2008.
The provision of the infrastructure will be conducted using Public Private Partnership
scheme according to Presidential Decree No. 38 Year 2015. The contract will be
signed by the Major of Municipal Government of Surakarta, as contracting agency,
and the winning bidder. Based on the PPP agreement, the winning bidder will be
responsible for financing, constructing, operating and maintaining the public service
until the end of the contract period.
The revenue of the PPP project company will be in form of Availability Payment. The
Availability payment will be given to the PPP project company based availability of
service - conducted by the company - according to service level standard stipulated
in the PPP agreement.
82
P u b l i c p r i vat e pa rt N e r s h i p s
7. Project Structure
83
P u b l i c p r i vat e pa rt N e r s h i p s
Education Research
and Development 1.
University of Sam Ratulangi
Teaching Hospital
Sector
84
P u b l i c p r i vat e pa rt N e r s h i p s
85
81
P u b l i c p r i vat e pa rt N e r s h i p s
Description:
Teaching hospital will provide doctor who
required in the learning process because
they can acknowledge students, giving
sustainable exercises or even tutoring
them privately in order to be a decent
doctor, dentist and other health examiners.
Estimated Project Cost : USD 28.7 Million
Financial Feasibility:
FIRR : 10.85 %
NPV : USD 1.8 Million
Estimated Concession Period : 20 Years
Public Service
Agency
(BLU UNSRAT)
Trustee
Bank
SPV
86
P u b l i c p r i vat e pa rt N e r s h i p s
DIGEST PROJECTS
Project Title : University of Sam Ratulangi Teaching Hospital
Government Contracting Agency : Minister of Research, Technology and
Higher Education of the Republic of Indonesia
Implementing Unit : University of Sam Ratulangi
Preparation Agency : 1. University of Sam Ratulangi
2. Ministry of National Development Planning
Estimated Project Cost : USD 28.7 Million
Estimated Concession Period : 20 years
Location : Manado, North Sulawesi
2. The Opportunity
2.1. Project Background
Sam Ratulangi Teaching Hospital is planned to support medicine student for
education and medical research matters in University of Sam Ratulangi. Furthermore,
for locals, the hospital could be one of their options in health services. Given the
fact that patients were out numbered in existing hospitals in North Sulawesi such
as Kandou Hospital, Siloam Hospital, Pancaran Kasih Hospital, Advent Hospital,
the development of this hospital could overcome this problem in providing health
services. Accordingly, based on economic and financial criteria, this hospital will
provide benefits for locals for improvement of public health services.
87
P u b l i c p r i vat e pa rt N e r s h i p s
The hospital has six levels building and laid on local government land. It occupied by
up to 300 out patients each day and around 130 inpatients every single day. In this
case approximally the hospital has 100 beds in the first year and increase to 250
beds in the seven years.
88
P u b l i c p r i vat e pa rt N e r s h i p s
7. Project Structure
LENDER
a) Banking Institutions
b) Non-Banking Institutions
(PT. SMI, IIF, etc)
89
P u b l i c p r i vat e pa rt N e r s h i p s
90
P u b l i c p r i vat e pa rt N e r s h i p s
91
P u b l i c p r i vat e pa rt N e r s h i p s
Description:
Development of a new wing, existing
building renovation, emergency and medi-
cal equipment in Regional Hospital of
Medan Municipal and also to strengthen the
hospital’s operational capacity.
Financial Feabisility:
FIRR : 12.00 %
NPV : USD 38.1 Million
Patients BPJS
92
P u b l i c p r i vat e pa rt N e r s h i p s
DIGEST PROJECTS
Project Title : The Development of Pirngadi Hospital in Medan
Government Contracting Agency : Mayor of Medan
Implementing Unit : Medan Municipal
Preparation Agency : Medan Municipal
Estimated Project Cost : USD 40.9 Million
Estimated Concession Period : 10 Years
Location : Medan
2. The Opportunity
2.1. Project Background
Along with the development of the important role of Medan City as a metropolitan
area, Medan City is expected to be able to meet the demands in providing services
decent health for the wider community. To improve the health level in Medan City
and the surrounding area, this can be done by improving the quality of the hospital.
The main problem in improving the quality of service becomes an important issue
especially related to the quality of public services in the health sector.
93
P u b l i c p r i vat e pa rt N e r s h i p s
94
P u b l i c p r i vat e pa rt N e r s h i p s
7. Project Structure
95
P u b l i c p r i vat e pa rt N e r s h i p s
96
P u b l i c p r i vat e pa rt N e r s h i p s
Description:
Ministry of Health will develop 2 tower
building to support Dharmais hospital as
the national cancer center. Tower A will
function as a service building and hospice
palliative which is the main support for
Tower B (12 floor building) to be built. Tower
B will function as an Integrated Executive
Service Building.
Estimated Project Cost : USD 48.6 Million
Financial Feasibility:
FIRR : 13.90 %
NPV : USD 18.4 Milion
Estimated Concession Period : 20 Years
Minister of Health
Delegation of Authority
Contractor Agency
Director General of Guarantee Agreement
Health Services
Public Service Agency IOGF
Dharmais Cancer AP (if Needed)
PPP
Hospital Agreement Guarantee Agreement
Payment Equity Financing Equiry
of Services
Development & (Owner’s Equity)
Health Agreement Special Purpose
Services Company
Loan Financing Financial
Patient Institutions
1. Design Consultant Medical Equipment
2. Construcition Laundry, Parking, Financing
Contractor Restaurant, etc.
97
P u b l i c p r i vat e pa rt N e r s h i p s
DIGEST PROJECTS
Project Title : Indonesia National Cancer Center Dharmais Hospital
Government Contracting Agency : Minister of Health
Implementing Unit : Ministry of Health
Preparation Agency : 1. Ministry of Health
2. Ministry of National Development Planning
Estimated Project Cost : USD 48.6 Million
Estimated Concession Period : 20 years
Location : DKI Jakarta
2. The Opportunity
2.1. Project Background
Dharmais Cancer Hospital (RSKD) located on Jl. Let. Jend. S. Parman, Kav. 84 - 86,
Slipi, West Jakarta was inaugurated on October 30, 1993. Since its inception, RSKD
has been directed as a special national cancer center hospital to answer the need
for integrated cancer services in Indonesia. In 2012 RSKD is designated as a Special
Hospital Type A Cancer through the determination of Minister of Health Decree No.
037/ MENKES/ SK/ II/ 2012. The purpose of making RSKD as National Cancer Center
(INCC: Indonesian National Cancer Center) under the Directorate General of Health
Services Ministry of Health has several functions, namely:
• Comprehensive cancer health care center (DHCCC: Dharmais Hospital Comprehen-
sive Cancer Center) National Cancer Education and Information Center (NCEIS:
98
P u b l i c p r i vat e pa rt N e r s h i p s
99
P u b l i c p r i vat e pa rt N e r s h i p s
Tower B
FLOOR LARGE (M2) FUNCTION CAPACITY
Floor 12 1,728 Inpatient VIP 24 TT
Floor 11 1,728 Inpatient VIP 24 TT
Floor 10 1,728 Inpatient VIP 24 TT
Floor 9 1,728 Inpatient Chlildren 32 TT
Floor 8 1,728 Inpatient CT, ICU Clinical Trial 28 TT
Floor 7 1,728 ODC, Chemotherapy 104 Seats
Floor 6 2,232 ICU, PICU, HCU, AHU Room 32 TT
Floor 5 2,232 Surgical Instalation, Staff Changing Room 12 OK
Floor 4 2,232 Surgery ODC, Therapy Sel, Procedur, Laboratory
Floor 3 2,232 Polyclinic, Side of the Lab 28 Clinic
Floor 2 2,232 Polyclinic, Side of the Lab 26 Clinic
Floor 1 2,232 Lobby, Admision, Business Center, Pharmacy
Basement 2,592 Parking, Transit Space Corpse, GWT, CSSD,
Locker Staff
Total Area 26,352 164 TT
100
P u b l i c p r i vat e pa rt N e r s h i p s
7. Project Structure
101
P u b l i c p r i vat e pa rt N e r s h i p s
102
P u b l i c p r i vat e pa rt N e r s h i p s
Description:
Sidoarjo Central Hospital is the second
hospital owned by the Government of
Sidoarjo Regency which aims to provide
health service facilities to the community
in the western part of Sidoarjo Regency.
Sidoarjo Central Hospital is planned as a
type C hospital.
Estimated Project Cost : USD 18.7
Million
Financial Feasibility:
FIRR : 9.90%
NPV : USD 14.0 Million
Estimated Concession Period : 10 Years
Regress
Agreement
GCA
Income
Availability PPP
IIGF Payment Agreement
Regional Goverment
SPV Collecting Unit
Guarantee
Agreement Services
Payment
Tariff Claim
Patiens
BPJS/Insurance
103
P u b l i c p r i vat e pa rt N e r s h i p s
DIGEST PROJECTS
Project Title : Sidoarjo General Hospital
Government Contracting Agency : Regent of Sidoarjo
Implementing Unit : Public Health Agency
Preparation Agency : PT Sarana Multi Infrastruktur (Persero)
Estimated Project Cost : USD 18.7 Million
Estimated Concession Period : 10 years
Location : Sub-District of Tambak Kameraan, District of West
Krian, Regency of Sidoarjo, East Java
2. The Opportunity
Health profile of Sidoarjo Regency shows that currently Sidoarjo only has one
Regional General Hospital, namely RSUD Sidoarjo class B which is located on Jalan
Mojopahit, Sub-District of Sidoarjo. Since the establishment of BPJS in 2014, the
number of visitors in RSUD Sidoarjo has increased, which is about 1,200 to 1,300
104
P u b l i c p r i vat e pa rt N e r s h i p s
patients each day. In 2015, there are 990,000 residents out of 2,129,463 inhabitants
in Sidoarjo Regency who participated in BPJS, and the number will continue to grow.
This condition will cause difficulty in RSUD Sidoarjo if there is no supported from
RSUD class C or D, which can serve as a feeder and/ or screening in order to better
pre-hospital/ pre-referral handling. On the other hand, for West Sidoarjo residents
will take more time to reach RSUD Sidoarjo which located in the easter of West
Sidoarjo.
It is planned that RSUD Krian is a Hospital Class C with a 150-bed capacity and
excellent service in handling trauma of accident and orthopedic which is supported
by specialization services from Orthopedic-Traumatology Surgery and ability to
stabilize the condition of head injured patient and lung service. The location of the
Krian Hospital construction project is located on Jl. Raya Kemeraan, Sub-District of
Tambak Kemeraan Kecamatan Krian with the land area of Sidoarjo regency with the
status of the former Land of Cash Village (ex TKD) available that is equal to 1.31 Ha,
the hospital plan will be built vertically.
The construction of RSUD Krian in the West Region of Sidoarjo is planned to use
a KPBU with a return on investment of a business entity through the Availability
Payment Service, and is offered to a business entity that has the potential to
finance, design, build, operate and operate (all medical and non-medical services),
maintaining hospital facilities and infrastructure, as well as business entities re-
delivering the hospital at the end of the term of cooperation.
Design - Build - Financing - Procurement of Medical & Non-Medical Equipment - All Service
Operations (Basic and specialist medical services, medical support and non-clinical
services) - Maintenance - Transfer. Including the provision of standard human resources
of type C hospitals such as specialists, general practitioners, dentists / specialists, health
workers and other non-health workers; or Design - Build - Financing - Procurement of
Medical & Non-Medical Equipment -Operation (Superior service - Traumatology Center
& Lung Center) - Maintenance - Transfer.
105
P u b l i c p r i vat e pa rt N e r s h i p s
• Indicative of Building & Land Requirement: 13,620 m2 Floor Level Requirement for
150 beds and Medical & non-medical support, and Vertical Development 2 - 4 Floor.
Land owned by the Government of Sidoarjo Regency with Ex-Village Land Country status.
7. Project Structure
106
P u b l i c p r i vat e pa rt N e r s h i p s
107
P u b l i c p r i vat e pa rt N e r s h i p s
Sector
to Ciangir
108
P u b l i c p r i vat e pa rt N e r s h i p s
109
P u b l i c p r i vat e pa rt N e r s h i p s
Description:
The Project will combine correctional facility
with productive activities such as livestock
breeding. The project aims to increase
the value of prison by adding economic
production which is expected to promote
regional economic growth.
Estimated Project Cost : USD 36.6 Million
Financial Feabisility:
FIRR : 13.57%
NPV : US$ 83.0 Million
Estimated Concession Period : 25 years
Ministry of Ministry of
Agriculture Commerce
GCA
Regrees Agreement
104
110
P u b l i c p r i vat e pa rt N e r s h i p s
DIGEST PROJECTS
Project Title : Nusa Kambangan Industrial Correctional Facility
Government Contracting Agency : Minister of Law and Human Rights
Implementing Unit : Directorate General of Correctional Facility
Preparation Agency : 1. Directorate General of Correctional Facility
2. Ministry of National Development Planning
Estimated Project Cost : USD 36.6 million
Estimated Concession Period : 25 years
Location : Nusakambangan, Cilacap, Central Java Province
2. The Opportunity
2.1. Project Background
Correctional facilities not only aim as a prison but also to serve and accommodate
inmates prior to their release and socialize to the people afterward. Nusakambangan
correctional facility located in Tambakreja Village, Regency of Cilacap in Central
Java Province with the area for about 216 km2. Indonesia government initiates a
partnership of this facility by optimizing correctional institution assets through open
prison concept. It is a minimum security prison where inmates get training and skills
of farming and/or breeding livestock.
111
P u b l i c p r i vat e pa rt N e r s h i p s
112
P u b l i c p r i vat e pa rt N e r s h i p s
7. Project Structure
Ministry of Ministry of
Agriculture Commerce
GCA
Regrees Agreement
113
P u b l i c p r i vat e pa rt N e r s h i p s
114
P u b l i c p r i vat e pa rt N e r s h i p s
Description:
The relocation of the correctional facility in
Salemba that is located in Central Jakarta
to Ciangir, Banten Province (around 40 km
from Jakarta) has the following objectives:
(i) to solve the overcapacity in Salemba’s
prison; (ii) DKI Jakarta Spatial Plan did not
accomodate current prison location; (iii) to
accommodate the Government’s budget
constraint for building prisons.
Estimated Project Cost : USD 91.0 Million
Financial Feasiblity:
FIRR : 14.77%
NPV : USD 26.4 Million
Estimated Concession Period : 15 Years
Ministry of Law
and Human Rights
Contracting Agency
Correctional Technical Director General or Recourse
Correctional Services Agreement
Implementing Agency
Guidance PPP
Assisted Citizens
Coaching Agreement Guarantee Agreement
EQUITY
Skills
Training Equity (Owner’s Equity)
Correctional Technical Financing
Assisted Citizens Implementing Agency
Loan
Financing Financial
Institutions
Contractor, Design Contractor, Design
Maintenance, Ciangir Maintenance, Property
Correctional Facility Management Salemba
User (Tenant)
115
P u b l i c p r i vat e pa rt N e r s h i p s
DIGEST PROJECTS
Project Title : Relocation of Salemba Correctional Facility to Ciangir
Government Contracting Agency : Minister of Law and Human Right
Implementing Unit : Directorate General of Correctional
Preparation Agency : Ministry of Law and Human Right and Ministry of
National Development Planning
Estimated Project Cost : USD 91.0 Million
Estimated Concession Period : 15 Years
Location : Tangerang, Province of Banten, and Cempaka
Putih, Central Jakarta
*Note:The initial assumption is based on ideal calculation with best practice facility (Project
Cost calculation is still arranged in FBC stage)
116
P u b l i c p r i vat e pa rt N e r s h i p s
2. The Opportunity
2.1. Project Background
The project “The transfer of prison technical prison units from the center of the city to
the outskirts aims to reduce overcrowding. In the January-January period of 2017, the
average number of assisted people around 1,300 people has exceeded the capacity of
the prison for just 572 people (an average over 130% capacity level). as can be seen in
the following table.
% Over
No. Period Prisoner Capacity %
Capacity
1. January 1,300 572 227 127
2. February 1,334 572 233 133
3. March 1,368 572 239 139
4. April 1,310 572 229 129
5. May 1,349 572 236 136
6. June 1,380 572 241 141
In addition, along with the development of urban areas in Jakarta, there is a mismatch of
placement of buildings with the General Plan Spatial (RUTR) in each area located in the
middle of urban areas will indirectly affect the security and order in prison Salemba.
117
P u b l i c p r i vat e pa rt N e r s h i p s
118
P u b l i c p r i vat e pa rt N e r s h i p s
7. Project Structure
119
P u b l i c p r i vat e pa rt N e r s h i p s
Ministry of Law
and Human Rights
Contracting Agency
Correctional Technical Director General or Recourse
Correctional Services Agreement
Implementing Agency
Guidance PPP
Assisted Citizens
Coaching Agreement Guarantee Agreement
EQUITY
Skills
Training Equity (Owner’s Equity)
Correctional Technical Financing
Assisted Citizens Implementing Agency
Loan
Financing Finacial
Institutions
Contractor, Design Contractor, Design
Maintenance, Ciangir Maintenance, Property
Correctional Facility Management Salemba
User (Tenan)
120
P u b l i c p r i vat e pa rt N e r s h i p s
121
P u b l i c p r i vat e pa rt N e r s h i p s
122
P u b l i c p r i vat e pa rt N e r s h i p s
123
P u b l i c p r i vat e pa rt N e r s h i p s
124
P u b l i c p r i vat e pa rt N e r s h i p s
125
P u b l i c p r i vat e pa rt N e r s h i p s
126
P u b l i c p r i vat e pa rt N e r s h i p s
127
123
P u b l i c p r i vat e pa rt N e r s h i p s
128
P u b l i c p r i vat e pa rt N e r s h i p s
129
P u b l i c p r i vat e pa rt N e r s h i p s
Glossary
TERM MEANING
130
P u b l i c p r i vat e pa rt N e r s h i p s
TERM MEANING
131
P u b l i c p r i vat e pa rt N e r s h i p s
132
P u b l i c p r i vat e pa rt N e r s h i p s
133
P u b l i c p r i vat e pa rt N e r s h i p s
134
P u b l i c p r i vat e pa rt N e r s h i p s
135
P u b l i c p r i vat e pa rt N e r s h i p s
136
P u b l i c p r i vat e pa rt N e r s h i p s
137
P u b l i c p r i vat e pa rt N e r s h i p s
138
P u b l i c p r i vat e pa rt N e r s h i p s
139
P u b l i c p r i vat e pa rt N e r s h i p s
140
P u b l i c p r i vat e pa rt N e r s h i p s
141
P u b l i c p r i vat e pa rt N e r s h i p s
142
P u b l i c p r i vat e pa rt N e r s h i p s
143
P u b l i c p r i vat e pa rt N e r s h i p s
144
P u b l i c p r i vat e pa rt N e r s h i p s
P u b l i c p r i vat e pa rt N e r s h i p s
P u b l i c p r i vat e pa rt N e r s h i p s
115
P u b l i c p r i vat e pa rt N e r s h i p s