PROJECT EVALUATION FORM

To fill in this form, please refer to the interim report of the High Level Group, chapter 4 on the
methodology and criteria to select priority projects.

Project title and GAZELA BRIDGE


a short summary Main city bridge on E75 motorway.
Reconstruction of existing steel an concrete
structures.
Map (please attach) Map attached

Technical description of project


If sections are to be upgraded (length, location Bridge has been constructed in 1970. So far no
etc.) please provide the below information for major rehabilitation has been done. Existing
the current situation and for the situation with structures are heavily damaged due to the
the project corrosion of structure steel and reinforcement in
concrete and lack of maintenance.
If sections are to be built (length, location, etc.) 1.
please provide the below information for the
project
Main tunnels and bridges involved Bridges:
Structures on left shore of river Sava
Approaching structures KI – KVIII and exiting
structures KIX and KX. All structures are box
type casted in prestressed concrete. Total length is
1384 m and area is 17,712 m2.

Structure over river Sava


Frame type steel strucuture with main span of 332
m and two approaching steel structures of 68 m.
Total length is 468 m and area is 12,884 m2

Structures on right shore of river Sava


Approaching structures KXI – KXIX and exiting
structures KXX and KXXXI. All structures are
box type casted in prestressed concrete. Total
length is 2145 m and area is 23,400 m2.

Structures on Mostar Interchange


Viaduct Savska and Kneza Milosa and Tram
bridge. Total length is 463 m and area is 5,561
m2.
Lock, depth and width of navigation -
section for waterways in the current
situation and after implementation of
proposed project

Capacity of the infrastructure in the 2000 vehicles / lane / hour or 12,000


1
current situation and after the vehicles/hour.
implementation of proposed project Some improvements in capacity could be done on
approaching structures
Number of lanes, tracks, etc. in the Current : 6 lane
current situation and after the Final: 6 lane
implementation of proposed project

Length of lanes, tracks, etc. in the Current: Total length 3122 m


current situation and after the
implementation of proposed project

Design and interoperability standards JUS, DIN


(EU, UN-ECE standards)

Existing facilities -

New facilities -

Other Final design of rehabilitation under working


process. Dead line September or October this
year.

2
First stage – pre-selection

PHASE I

Pan-European interest
On which major axis the project is located? CORRIDOR X,
International Road E75
TEM network
City motorway
Significance
Cost of the project 25,000,000 – 30,000,000 depending of type of
works (rehabilitation or reconstruction)

Type of investment Rehabilitation

Comparison of proposed technical option No alternative solutions, current traffic is passing


with alternative solutions through centre of the City of Belgrade, and over
bridge “Gazela” with over 140,000 vehicles
AADT.
Firm commitment
Start – completion date for studies and works Urgent reinforcement works on concrete
structures - 10% of total value of works.
Other works in 2006 and 2007.
Has a strategic environmental assessment No
(SEA) been made?

Priority given in the national plan Highest

Planned financing of the project Combined CARDS with IFI loans


(national funding, loans, user charging,…)
Please include a financial plan.

3
Second stage – evaluation

PHASE II

Improving economic efficiency


Cost savings to all freight operators, Cannot be evaluated because of short section of
to international operators motorway. Congested with city and transit traffic.
Traffic conditions are not to be improved until
new bridge adjacent to existing one will be
constructed.
Cost savings to all passengers, See above
to international passengers

Time savings to all freight operators See above


to international operators

Time savings to all passengers, See above


to international passengers

What user charging options have been No


considered?

Impact on economic growth and


employment

Enhancing environmental sustainability


Reduction in air pollutants No reduction

Reduction in green house gases No reduction

Reduction of noise nuisances No reduction

How does the project affect biodiversity? -

Are there environmentally sensitive No


zones to be considered?

4
How have the results of SEA/EIA been -
taken into account in the detailed project plan?

How much traffic will be shifted from -


other modes?

Improving safety and security


Reduction in accidents Some reduction could be achieved. Presently few
- number of fatalities accident daily
- severity

How does the project contribute to No data


reduce security incidents to international
operators and passengers?

How much traffic will be shifted from No data


other modes?

18/03/2005