Sunteți pe pagina 1din 5

QUIZ QUESTION DEOM 330 (OPERATION MANAGEMENT)

CHAPTER 3

1. The three phases involved in the management of 5. PERT analysis computes the variance of the total
large projects are project completion time as

a. scheduling, operating, evaluating. a. the sum of the variances of all


b. planning, scheduling, evaluating. activities in the project.
c. scheduling, designing, operating. b. the sum of the variances of all
d. planning, scheduling, controlling. activities not on the critical path.
c. the variance of the final activity of
2. With respect to PERT and CPM, slack the project.
a. is a task or subproject that must be d. the sum of the variances of all
completed. activities on the critical path.
b. marks the start or completion of a
6. The critical path of a network is the
task.
c. is the latest time an activity can be a. longest time path through the
started without delaying the entire network.
project. b. shortest time path through the
d. is the amount of time a task may be network.
delayed without changing the c. path with the most activities.
overall project completion time. d. path with the fewest activities.

3. A dummy activity is required when 7. Which of the following is a direct responsibility of


the project manager?
a. two or more activities have different
ending events. a. Calculating completion probabilities
b. the network contains two or more for all tasks in the project.
activities that have identical starting b. Drawing the network diagram.
and ending events. c. Making sure that the people
c. two or more activities have the assigned to the project receive the
same ending events. motivation, direction, and
d. two or more activities have the information needed to do their jobs.
same starting events. d. Performing all of the activities in the
project.
4. Which of the following is a basic assumption of
PERT? 8. Dummy activities

a. Activity completion times are known a. are found in both AOA and AON
with certainty. networks.
b. Only critical path activities in the b. are used when two activities have
network must be performed. identical starting and ending events.
c. No activity in the network must be c. have a duration equal to the
repeated. shortest non-dummy activity in the
d. There is only one complete route network.
from the start of a project to the end d. cannot be on the critical path.
of a project.
QUIZ QUESTION DEOM 330 (OPERATION MANAGEMENT)
CHAPTER 3

9. Which of the following is a limitation of PERT and 13. A project's critical path is composed of activities
CPM? A, B, and C. Activity A has a standard deviation of 2,
activity B has a standard deviation of 1, and activity
a. They can be used only to monitor C has a standard deviation of 2. What is the standard
schedules.
deviation of the critical path?
b. The graphical nature of a network
delays comprehension of the activity a. 25
list's interrelationships. b. 9
c. They are applicable to only a narrow c. 5
variety of projects and industries. d. 3
d. There is inherent danger of too
much emphasis being placed on the 14. What is the probability that a project with a
mean completion time of 23.9 days and a variance of
critical path.
6 days will be finished in 26 days?
10. An activity has an optimistic time of 15 days, a
a. 0.20
most likely time of 18 days, and a pessimistic time of
27 days. What is its expected time? b. 0.63
c. 0.80
a. 19 days d. 0.37
b. 20 days
c. 18 days 15. The EF of an activity is the
d. 60 days a. Min{LS of all immediate following
11. An activity has an optimistic time of 11 days, a activities}.
most likely time of 15 days, and a pessimistic time of b. Max{EF of all immediate
predecessors}.
23 days. What is its variance?
c. ES + Activity time.
a. 16.33 d. LF-Activity time.
b. 2
c. 4 16. The ethical issue of divulging confidential
information to some bidders to give them an unfair
d. 15.6
advantage is known as
12. Activities A and B are both 6 days long and the
only immediate predecessors to activity C. Activity A a. expense account padding.
has ES=8 and LS=8 and activity B has ES=7 and LS=10. b. bid rigging.
c. low balling.
What is the ES of activity C?
d. bribery.
a. 15
b. 13 17. PERT requires three estimates of activity
c. 16 completion time, while CPM only requires a single
d. 14 estimate.

o True
o False
QUIZ QUESTION DEOM 330 (OPERATION MANAGEMENT)
CHAPTER 3

18. The optimistic time is the greatest amount of


time that could be required to complete an activity.

 True
 False

19. The expected completion time of a PERT project


is the sum of the most likely times of the activities
on the critical path.

o True
o False

20. Work breakdown structure is the division of a


project into more and more detailed components.

o True
o False
QUIZ QUESTION DEOM 330 (OPERATION MANAGEMENT)
CHAPTER 3

Essay Question

Question 1.

What is the probability that this project is completed in 28 days? All activity lengths are given in days.

Activity Predecessor Optimistic Most Likely Pessimistic


A -- 1 2 3
B A 2 4 6
C A 5 8 11
D A 3 4 5
E B 10 14 18
F D 6 8 10
G C, E, F 7 9 13

Question 2.

Describe at least four of the ethical issues faced in project management.

Question 3.

Use the crash costs, regular activity durations and precedence requirements in the table to determine
the cheapest completion time and cost for this project if the project has a fixed cost of $1000 per day.
All activity lengths are given in days.

Regular Minimum
Activity $/day crash fee Predecessor
Time Time
A 10 6 $500 --
B 6 5 $300 --
C 2 2 -- B
D 4 2 $500 C
E 6 3 $600 A
F 8 5 $1200 D, E
QUIZ QUESTION DEOM 330 (OPERATION MANAGEMENT)
CHAPTER 3

Question 4.

Complete this table of activity lengths and early and late start and finish times based on the indicated
precedence requirements. All times are in days.

Activity Predecessor Early Start Early Finish Late Start Late Finish Length
A -- 0 5
B A 11 11
C A 9 14
D B 18 18 7
E B, C 11 15
F D, E 3

S-ar putea să vă placă și