Documente Academic
Documente Profesional
Documente Cultură
With vast experience in mining projects and the engineering expertise to allow clients to
explore more cost-effective construction methods and mining operations, ALE can provide
complete solutions to the challenges faced in this industry.
ALE is always looking at innovative solutions and designing bespoke equipment to ensure
that the best result for the client is found, this innovative thinking and close working with
the client can often change the project to save on time and costs.
This typically includes manoeuvring crushers, conveyers, excavators, draglines and other
process equipment when the mine or process facilities are being expanded or relocated
according to the mining strategy. Our innovative equipment fleet allows us to reduce
downtime of the tracked plant and relocate items safely between locations and provide
cost savings on road preparation and maintenance. We also have the innovative solutions
to work within confined spaces and to industry-leading safety standards.
Our high capacity cranes, lift’n’lock lifting systems and jacking systems are a more favourable option to
traditional mobile jacking systems as mobilisation costs are reduced and safety risks are mitigated as loads
are statically supported, alleviating any risk of working under suspended loads. Our unique and innovative
Mega Jack, Mega Jack 800 and Mega Jack 300 systems provide a quicker and safer option as they are
remote-controlled and minimise personal interaction and manual handling.
CASE STUDY
Transportation and installation of flow enhancement hoppers, Australia
OVERVIEW: ALE has completed the transportation and ALE had to overcome the challenges of operating in a
installation of two 145t hoppers for the TLO Fines Flow live BHP mine site, complying with very strict safety and
Enhancement Project in Western Australia. environmental requirements. There was limited ground
preparation permitted (levelling and compaction), due to
SERVICES REQUIRED: The hoppers had to be transported the short time of the shutdown. Flexibility was needed to
from a storage position of 1,100mm stool height, which accommodate a limited site area and many interferences
was located 100m from the foundations, along a sloped with other contractor activities.
path. The transport also included a 90° carousel to align
the hoppers to the foundations. There was no allowance for the installation of tracks
onto the ground, beside the foundations, because of the
A multiple lashing system ensured the stability of the interference with the client activities on the foundations
system for stand-by, including storm and wind issues, as of the hoppers. Subsequently, the hoppers were installed
well as for service condition. Spirit levels were installed just under the existing conveyor in a very small installation
to monitor the levelling of the assembly. The installation area. This avoided the use of any crane for the installation
assembly was designed to minimise the work at height and and the derigging of the hoppers.
other typical risks related to lifting operations.
This was the first time this methodology had been
To provide the flexibility and manoeuvrability needed, ALE executed so efficient engineering and operational
used 24 axle lines of SPMT in a 2 x 2 file 12 configuration experience was needed to obtain the permit to proceed
to transport the hoppers. ALE used a lift‘n’lock system from FAST and BHP.
mounted onto the trailers to install the hopper.
Movements of this nature, involving large mobile plant on They were then loaded-out onto a heavylift vessel, along with
SPMTs, results in significant savings in maintenance of the the SPMTs, and shipped to Port Pirie in South Australia.
running gear of the plant and in down-time of high-value
equipment on operating mine sites. Once they arrived at the port, ALE loaded-in the autoclaves
using the same SPMT configuration and transported them
into storage.
CASE STUDY
TURNKEY RGP6 Jimblebar mine project in Port Hedland, Australia
OVERVIEW: ALE were tasked with the in convoy from Port Hedland to Boodarie
receiving, storage, and land transportation – a staging area located 25km outside
of 230 modules, with weights ranging of Port Hedland. From here convoys to
ALE is a full solutions provider and the between 5t and 240t. the Jimblebar site are formed, with the
turnkey service includes full engineering highest priority items given precedence
assessment and design of any bespoke SERVICES REQUIRED: The 230 over-sized in earlier convoys to site.
and over-mass modules were used to
lifting equipment. construct the RGP6 Jimblebar Iron As public roads were utilised for ground
Ore project. transportation, and Western Australia
law states that cargo over 8.5m wide
Our extensive equipment fleet and experiences Fabricated in China, these modules were cannot travel during daylight hours,
means we are a ‘one-stop-shop’ and have the shipped from Tianjin to Port Hedland, ALE organised and conducted night-time
capabilities to execute projects from start to finish, Western Australia. The 230 modules were convoys within a rolling road-block under
from barging and handling modules at the port, and received in over 11 shipments, with the the guidance of Police Traffic Escorts.
the transportation to site, to the on-site manoeuvres first received in June 2012 and the last ALE faced the challenge of reserving and
modules were delivered to site in Newman obstructing public roads and required
and installation.
by late February 2013. the cooperation of multiple public
stakeholders and external bodies.
The modules were received on SPMTs
at Port Hedland Port Authority (PHPA), ALE had to work alongside various
before being transported within the transport companies to determine suitable
PHPA grounds and set on stools to await transport dates and road- access into
ground transportation on conventional and out of the world’s largest bulk export
trailers. Configurations of both SPMTs harbour every night a convoy took place
and conventional trailers was dependent on the road. The route also had to negotiate
on each modules’ dimensions and weight multiple railway crossings of various mining
– the latter to accommodate for Western companies in a prompt manner as to not
Australia’s axle-loading restrictions. The cause delay to their deliveries.
largest module was 42.5m long, 13.5m
wide, 14.5m high and 227t in weight and ALE had a dedicated SPMT crew
the largest trailer configuration comprised located at the Jimblebar site on a
of a 4 file 28 row (6.3m wide, 42m long). full-time basis, equipped with 40 axle
lines of SPMT trailers and 12 axle line
Transportation from Port Hedland to the of compatible spacer decks. As modules
Jimblebar Mine site (totalling 450km) was were placed on stools upon arrival at
split into four segments, each requiring Jimblebar, SPMTs then transported
one night of travel time. The first of which the modules to various site locations –
saw the modules (one per trailer) travel sometimes up to 5km in distance.
Over the years we’ve added to our world-class engineering skills-base through the acquisition of several successful
specialist companies, and now we have more than 200 highly qualified engineers working at locations across the globe.
This experience means we’re well equipped to support the full FEED process, working through complex technical and
logistical issues at an early stage to eliminate expensive changes later on.
Our FEED capabilities form a crucial part of the service we offer. ALE has contributed to many high profile projects that have
been right at the forefront of global trends in their sector. We are able to adapt to ever-changing industry requirements,
evolving safety standards and scope changes as the project gathers definition during the design process, while at the same
time providing solutions which are as cost-effective and safe as possible. As a result, we’re able to work closely with our
clients from an early stage to establish what’s required and provide practical engineering advice. This advice can lead to
savings later, either in time or cost, as the changes are included in the design phase, instead of modifications later.
Some of our FEED services typically include, but are not limited to, the items below:
• Physical route surveys to determine maximum practical • Outline design of new build site construction jetties
equipment weight and dimension information • Selection of optimum shipping methods and identification
• Investigation of environmental conditions affecting the of suitable vessels or barges
heavy lifting and transport discipline • Logistical studies to ensure that transportation and
• Road layout and route improvement studies installation scope support the project schedule
• Advice on local regulatory issues relating to the movement • Design and input to design of transportation support steel
of large and indivisible loads to the job site and lifting and lashing/securing points
• Equipment lifting and installation studies to determine the • Assistance in modularisation studies to determine the
most cost and schedule effective methods of sizing and maximum practical extent man hours can be removed
placing equipment from the job site
• Design of rigging and lifting equipment
CIVIL MINERALS & METALS NUCLEAR BALLASTING CRANE LIFTING ENGINEERING JACKING
OFFSHORE OIL, GAS & PETROCHEMICAL PORTS LIFTING SYSTEMS LOAD-IN & LOAD-OUT LOGISTICS MARINE ENGINEERING
CRANES
SKID SYSTEMS WEIGHING SYSTEMS
SPMT SPT
HYDRO DECK MEGA JACK 800
LIFTING SYSTEMS