PORT OF TANJUNG PELEPAS PERFORMANCE STANDARD

No KEY PERFORMANCE INDICATOR 2012 2013 2014 2015

1. Rate of Effective Berth Utilisation (%) 64.43% 65.52% 67.22% 66.07%


2 Average Waiting Time For Pilot To Be Onboard (hour) 0.69 1.11 1.35 2.04
3 Average Steaming Time (hour) 1.34 1.18 1.34 2.04
4 Average Berth Turnaround Time (hour)
4.1 Feeder 14.31 13.89 19.14 19.17
4.2 Main Liner 19.35 21.01 22.36 22.92
4.3 Terminal 17.09 17.73 20.64 20.64
5 Average Moves Per Crane Per Hour (boxes)
5.1 Feeder 22.38 21.41 21.28 22.45
5.2 Main Liner 28.13 26.30 25.77 25.51
5.3 Terminal 26.13 25.18 24.16 24.29
6 Average Boxes Per Vessels Per Hour (boxes)
6.1 Feeder 38.28 33.53 38.25 40.93
6.2 Main Liner 82.27 74.98 79.88 91.06
6.3 Terminal 62.79 60.61 59.21 62.75
7 Average Monthly Yard Utilisation (%) 54.88% 44.49% 45.75% 53.79%
8 Dwell Time of Container at Container Yard (days)
8.1 Import 7.34 7.08 7.36 7.79
8.2 Export 3.17 3.24 3.73 3.96
8.3 Transhipment 5.32 5.48 5.83 5.83