Sharing Session on Application of Precast Elements at

T220 Great World Station


T220 – Tiong Seng– Dongah
Land Transport Authority jointly with Joint Venture (TSDA)

Contract T220: Construction and Completion Of Great World Station And Tunnels for Thomson Line. 1
Presentation Outline

• Project Overview
• T220 Productivity Initiatives
• Design Considerations for Precast Elements
• Brief Installation Procedures of Precast Elements
• Advantages and Learning Points
• Safety Induction

2
Project Overview

Yong An Park

Cosmopolitan

3
Milestones of Productivity Initiatives

LTA Construction Productivity Installation of Tubular Struts Installation of S2 level


Steering Committee (CPSC) at Station Roof Slab completed. Tubular Struts completed
was introduced to Tubular Omission of kingposts and with assistance from EOT
Struts during the trip to bracings largely freed up space. cranes.
London in June 2014, the idea
was raised to TSDA in Dec 2014.
Dec, 2014 Jun, 2017 Mar, 2018

Jun, 2014 Jul, 2017


Oct, 2016

Installation of Electrical Overhead Mass installation of


Conceptualization of a Precast
Holistic System to enable Travelling (EOT) cranes at soffit of
Cable Basement level of Station. Underplatform Walls
implementation of all
Enhanced mechanized material commenced.
productivity initiatives.
handling with higher capacity.
4
T220 Productivity Initiatives
Optimize the Cycle of Construction
Mechanized Material Handling (Enhanced Capacity)
• Electrical Overhead Travelling (EOT) cranes
• Gantry cranes

Modular Temporary Propping System (Free up Space)


• Tubular Struts
• Modular Shoring System

Prefabricated Elements (Increased Efficiency)


• Precast Underplatform Wall and Platform Slab
• Carpet Reinforcement
5
Gantry Cranes

6
Electrical Overhead Travelling (EOT) cranes

7
Tubular Struts

8
Precast Elements Layout Plan

Platform Slab

Under Platform Wall

9
Precast Elements Sectional Plan

Roof Level

Upper Concourse Level

EOT Crane
Concourse Level

Cable basement Level Precast Wall & Slab

Platform Level

Under Platform Level 10


Design Considerations

• Fixity of the precast element connections adheres to original AE Design


• Standardization and repetition of the precast elements are maximized to
optimize the production and the site installation
• Temporary and permanent loadings are considered in the connection details
• Precast Slab is designed to act as the temporary formwork support for the
topping concrete
• Topping concrete detailed with reinforcement and the slab is designed as a
continuous element
11
Typical Connection Details
150mm Reinforced
Corrugated Pipes topping concrete

Typical Starter Bar Typical Connection Details 12


Connection Details @ PC Wall & Slab
Typical Connection Details

Reinforced topping
concrete
Wall Stiffener

Typical Wall Stiffener Details Typical Slab Connection Details


13
Brief Installation Sequence

1) Off-site Fabrication and Inspection by LTA/QPS @ Robin Village’s Precast Yard

14
Brief Installation Sequence

2) Preparation Works – Delivery of Precast Panels & Installation of Starter bars

15
Brief Installation Sequence

3) Installation of Precast Panels by EOT cranes

16
Brief Installation Sequence

4) Installation of Temporary Props and Grouting Works

17
Brief Installation Sequence
5) Installation of Falsework for Precast Slab

18
Brief Installation Sequence

6) RC Topping & Stiffeners of Walls

19
Advantages of Application

• Elimination of risks by reducing the work activities on sites


SAFETY - Scaffold & WAH platforms
- Liftings, transfers and installations of rebar & formwork & concrete
- Noise and dust pollution associated with CIS works in confined space

• Higher efficiency with substantial man-hour saving ~ 33 %


PRODUCTIVITY
• Immediate reduction in waste on formworks

• Better workmanship ensured by centralized quality control at


fabrication yard.
QUALITY
• Reduction in common defects also expedite progress at site
20
Learning Points
• Early involvement of LTA, AE, Main Contractor and Pre-caster in
conceptualisation, advanced planning, design, fabrication and site preparation
is utmost importance and crucial

• High repetition and low variation of panels to reap the economy of scales

• Installation of Precast Elements within confined space required predetermine


lifting methodology. EOT cranes can be a solution to facilitate the heavy lifting

21
Safety Induction

• Observe all warning signage's when entering and leaving from the site

• Emergency alarm will be activated in case of any emergency situations

• Emergency response team will be activated

• Follow the designated access and escape route to reach assembly area

• Visitors will be guided to assembly area during emergency situation

22
Safety Induction
DESIGNATED ACCESS

23
Safety Induction

24
Thank you