CLIENT; KHALILL ABDULLA GHALOOM ABDULLA AL MAZMI CONSULTAST ;EAST CONSULTANT ENGINEERINGANT MAINT CONTRACTOR ; ULTRA SPAN GEN

CONSULTAST ;EAST CONSULTANT ENGINEERINGANT MAINT CONTRACTOR ; ULTRA SPAN GEN , CONT & MAIT

# Activity ID Activity Name Original Start Finish Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018 Qtr 3, 2018 Qtr 4, 2018 Qtr 1, 2019
Duration
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
1 A10 KHALIL ABDUL GALOOM ABDULLA AL MAZMI 391 01-Jul-17 29-Sep-18 29-Sep-18, A10 KHALIL ABDUL GALOOM ABDULLA AL MAZMI
2 A10.0 PRILIMINARY WORK 2 01-Jul-17 02-Jul-17 02-Jul-17, A10.0 PRILIMINARY WORK
3
A1000 TEMPRARY OFFICE 2 01-Jul-17 02-Jul-17 TEMPRARY OFFICE
4 A10.1 SUB STRUCTURE 18 06-Jul-17 26-Jul-17 26-Jul-17, A10.1 SUB STRUCTURE
5
A1010 EXCAVATION 4 06-Jul-17 10-Jul-17 EXCAVATION
6
A1020 FOUNDATION 14 11-Jul-17 26-Jul-17 FOUNDATION
7 A10.2 SUPER STRUCTUR 90 27-Jul-17 08-Nov-17 08-Nov-17, A10.2 SUPER STRUCTUR
8
A1040 GROUND SLAB 6 27-Jul-17 02-Aug-17 GROUND SLAB
9
A1050 FIRST FLOOR COLUM 7 03-Aug-17 10-Aug-17 FIRST FLOOR COLUM
10
A1060 FIRST FLOOR SLAB 20 12-Aug-17 03-Sep-17 FIRST FLOOR SLAB
11
A1070 ROOF FLOOR COLUM 5 04-Sep-17 09-Sep-17 ROOF FLOOR COLUM
12
A1080 ROOF SLAB 20 10-Sep-17 02-Oct-17 ROOF SLAB
13
A1090 TOP ROOF COLUN 5 03-Oct-17*08-Oct-17 TOP ROOF COLUN
14
A1100 TOP ROOF SLAB 15 11-Oct-17* 28-Oct-17 TOP ROOF SLAB
15
A1105 PARAPET 10 29-Oct-17*08-Nov-17 PARAPET
16 A10.3 BLOCK WORK 46 20-Sep-17 12-Nov-17 12-Nov-17, A10.3 BLOCK WORK
17
A1110 GROUND FLOOR BLOCK 10 20-Sep-17*01-Oct-17 GROUND FLOOR BLOCK
18
A1120 FIRST FLOOR BLOCK 25 02-Oct-17*30-Oct-17 FIRST FLOOR BLOCK
19
A1130 ROOF FLOOR BLOCK 10 01-Nov-17*12-Nov-17 ROOF FLOOR BLOCK
20 A10.4 PLASTER WORK 52 19-Oct-17 18-Dec-17 18-Dec-17, A10.4 PLASTER WORK
21
A1140 GROUND FLOOR PLASTER 25 19-Oct-17*16-Nov-17 GROUND FLOOR PLASTER
22
A1150 FIRST FLOOR PLASTER 15 18-Nov-17*04-Dec-17 FIRST FLOOR PLASTER
23
A1160 ROOF FLOOR PLASTER 12 05-Dec-17*18-Dec-17 ROOF FLOOR PLASTER
24 A10.5 PAINT WORK 100 18-Nov-17 13-Mar-18 13-Mar-18, A10.5 PAINT WORK
25
A1170 GROUND FLOOR PAINT 40 18-Nov-17*02-Jan-18 GROUND FLOOR PAINT
26
A1180 FIRST FLOOR PAINT 40 03-Jan-18*18-Feb-18 FIRST FLOOR PAINT
27
A1190 ROOF FLOOR PAINT 20 19-Feb-18*13-Mar-18 ROOF FLOOR PAINT
28 A10.6 STONE WORK 110 15-Nov-17 22-Mar-18 22-Mar-18, A10.6 STONE WORK
29
A1200 BITUMEN AND SCAFFOLDDING 15 15-Nov-17*02-Dec-17 BITUMEN AND SCAFFOLDDING
30
A1210 STONE WORK 95 03-Dec-17*22-Mar-18 STONE WORK
31 A10.7 MARBLE AND CERAMICS WORK 125 23-Nov-17 17-Apr-18 17-Apr-18, A10.7 MARBLE AND CERAMICS WORK
32
A1220 GROUND FLOOR WALLS 30 23-Nov-17*27-Dec-17 GROUND FLOOR WALLS
33
A1230 GROUND FLOOR FLOOR 20 28-Dec-17*20-Jan-18 GROUND FLOOR FLOOR
34
A1240 FIRST FLOOR WALLS 30 21-Jan-18*24-Feb-18 FIRST FLOOR WALLS
35
A1250 FIRST FLOOR FLOOR 25 25-Feb-18*25-Mar-18 FIRST FLOOR FLOOR
36
A1260 ROOF FLOOR FLOOR 10 26-Mar-18*05-Apr-18 ROOF FLOOR FLOOR
37
A1270 ROOF FLOOR TERRAZO 10 07-Apr-18*17-Apr-18 ROOF FLOOR TERRAZO
38 A10.8 ELECTRICAL WORK 338 22-Aug-17 19-Sep-18 19-Sep-18, A10.8 ELECTRICAL WORK
39
A1280 CELLINH CONDUITIES 52 22-Aug-17 21-Oct-17 CELLINH CONDUITIES
40
A1290 WALLS CONDUITIES 40 18-Oct-17*03-Dec-17 WALLS CONDUITIES
41
A1300 FLOOR CONDUITIES 45 24-Oct-17*14-Dec-17 FLOOR CONDUITIES
42
A1310 SWICHES AND SOCKETS 20 28-May-18*19-Jun-18 SWICHES AND SOCKETS
43
A1320 EXHUST FANS 8 11-Sep-18*19-Sep-18 EXHUST FANS
44
A1330 SUB-DB 15 11-Jul-18* 28-Jul-18 SUB-DB
45
A1340 MAIN-DB 15 29-Jul-18* 14-Aug-18 MAIN-DB
46 A10.9 DRAINAGE WORK 337 05-Aug-17 01-Sep-18 01-Sep-18, A10.9 DRAINAGE WORK
47
A1350 INTERNAL DRAINAGE 80 05-Aug-17*05-Nov-17 INTERNAL DRAINAGE
48
A1360 EXTERNAL DRAINAGE 40 17-Jul-18* 01-Sep-18 EXTERNAL DRAINAGE
49
A1370 VERTICAL DRAINAGE 30 24-Dec-17*27-Jan-18 VERTICAL DRAINAGE
50
A1380 INTERNAL WATER SUPPLY 35 05-Aug-17 13-Sep-17 INTERNAL WATER SUPPLY
51
A1390 EXTERNAL WATER SUPPLY 25 17-Jul-18* 14-Aug-18 EXTERNAL WATER SUPPLY
52
A1400 WATER HEATER 10 24-Mar-18*03-Apr-18 WATER HEATER
53
A1410 WATER TANK 5 19-Aug-18*23-Aug-18 WATER TANK
54
A1420 WATER PUMP 5 25-Aug-18*29-Aug-18 WATER PUMP
55
A1430 SANITARY WARES 15 24-May-18*10-Jun-18 SANITARY WARES
56
A1440 SANITARY FITTINGS 10 18-Jun-18*28-Jun-18 SANITARY FITTINGS
57 A10.10 A/C WORK 147 25-Dec-17 13-Jun-18 13-Jun-18, A10.10 A/C WORK
58
A1450 DUCTING WORK 35 25-Dec-17*03-Feb-18 DUCTING WORK
59
A1460 PIPING 15 04-Feb-18*20-Feb-18 PIPING
60
A1470 INDOOR UNIT 18 11-Apr-18* 01-May-18 INDOOR UNIT
61
A1480 OUT DOOR UNIT 15 17-May-18*03-Jun-18 OUT DOOR UNIT
62
A1490 GRILLS AND DIFFUSER 10 03-Jun-18*13-Jun-18 GRILLS AND DIFFUSER
63
A1500 CONNECTIONS 10 02-Jun-18*12-Jun-18 CONNECTIONS
64 A10.11 WATER PROOFING WORK 21 10-Dec-17 02-Jan-18 02-Jan-18, A10.11 WATER PROOFING WORK
65
A1510 BATHS AND KITCHEN 8 10-Dec-17*18-Dec-17 BATHS AND KITCHEN
66
A1520 BALCONY AND ROOF 8 19-Dec-17*27-Dec-17 BALCONY AND ROOF
67
A1530 TOP ROOF 5 28-Dec-17*02-Jan-18 TOP ROOF
68 A10.12 ALUMINUM WORK 52 26-May-18 24-Jul-18 24-Jul-18, A10.12 ALUMINUM WORK
69
A1540 FRAMES 22 26-May-18*19-Jun-18 FRAMES
70
A1550 SHUTTER 20 20-Jun-18*12-Jul-18 SHUTTER
71
A1560 ACCESARY AND SEEALEANT 12 10-Jul-18* 23-Jul-18 ACCESARY AND SEEALEANT
72
A1570 KITCHENS CABENTS 20 02-Jul-18* 24-Jul-18 KITCHENS CABENTS
73 A10.13 WOOD WORK 212 16-Oct-17 19-Jun-18 19-Jun-18, A10.13 WOOD WORK
74
A1580 SUB FRAMES 53 16-Oct-17*16-Dec-17 SUB FRAMES
75
A1590 FRAMES 20 29-Jan-18*20-Feb-18 FRAMES
76
A1600 SHUTTER AND PAINT 60 21-Feb-18*01-May-18 SHUTTER AND PAINT
77
A1610 HANDLES AND LOCKS 10 05-May-18*15-May-18 HANDLES AND LOCKS
78
A1620 WARDOBES 30 16-May-18*19-Jun-18 WARDOBES
79 A10.14 LIFT WORK 293 17-Aug-17 24-Jul-18 24-Jul-18, A10.14 LIFT WORK
80
A1630 CONCRETE 62 17-Aug-17 28-Oct-17 CONCRETE
81
A1640 MECHINICAL WORK 15 22-Feb-18*11-Mar-18 MECHINICAL WORK
82
A1745 TESTING 2 23-Jul-18* 24-Jul-18 TESTING
83 A10.15 SWIMMING POOL WORK 344 12-Jul-17 16-Aug-18 16-Aug-18, A10.15 SWIMMING POOL WORK
84
A1650 WAER PROOF AND CONCRETE 8 12-Jul-17 20-Jul-17 WAER PROOF AND CONCRETE
85
A1655 CERAMICS 12 03-Dec-17*16-Dec-17 CERAMICS
86
A1660 MECHINCAL AND ELECTRICAL 8 24-Mar-18*01-Apr-18 MECHINCAL AND ELECTRICAL
87
A1670 TESTING 2 15-Aug-18*16-Aug-18 TESTING
88 A10.16 FALES CELLING AND GYPSIM BOARD 55 03-Dec-17 04-Feb-18 04-Feb-18, A10.16 FALES CELLING AND GYPSIM BOARD
89
A1680 HANGING SYSEM 30 03-Dec-17*06-Jan-18 HANGING SYSEM
90
A1690 TILES AND GYPSIM BORAD 25 07-Jan-18*04-Feb-18 TILES AND GYPSIM BORAD
91 A10.17 EXTERNAIL WORK 206 27-Dec-17 23-Aug-18 23-Aug-18, A10.17 EXTERNAIL WORK
92
A1700 BASSCO 20 19-Jul-18* 11-Aug-18 BASSCO
93
A1710 MAIN GATE 7 12-Aug-18*19-Aug-18 MAIN GATE
94
A1720 LAND SCAPE 20 01-Aug-18*23-Aug-18 LAND SCAPE
95
A1730 BOUNDARY WALL 90 27-Dec-17*10-Apr-18 BOUNDARY WALL
96 A10.18 CLEANING AND HAND OVER 5 24-Sep-18 29-Sep-18 29-Sep-18, A10.18 CLEANING AND HAND OVER
97
A1740 FINAL HOUSE KEEPING 5 24-Sep-18*29-Sep-18 FINAL HOUSE KEEPING

Actual Level of Effort Remaining Work Milestone


Page 1 of 1 MUHAMMAD KHALIL
Actual Work Critical Remaining Work summary