Documente Academic
Documente Profesional
Documente Cultură
7737A02/FICHT-13535576-v2
Table of Contents
7737A02/FICHT-13535576-v2 I
7.1.1 Load flow and reactive power capability during rated voltage 7-2
7.1.2 Load flow and reactive power capability during admissible
voltage conditions 7-3
7.2 Short Circuit Calculation 7-3
7.3 Dynamic LVRT Calculation 7-4
7737A02/FICHT-13535576-v2 II
1. Introduction
This document contains a summary of the major grid code requirement
concerning connection and operation of wind turbines in the Jordanian
power systems. The focus is on wind farms connected to the high voltage
level, i.e. 400 kV and 132 kV. The requirements are defined from the point
of view of grid operators. Wind farms as a whole can fulfill the
requirements in different ways. Therefore, implementation examples shown
in this document represent only examples and are not obligatory for the
wind farm investors. Additional equipment on the wind turbines such as
STATCOM can also be used if it is technically more favorable.
7737A02/FICHT-13535576-v2 1-1
2. Definition and Acronyms
MV: Medium voltage
HV: High voltage
WT: Wind turbine
WF: Wind farm consisting of several wind turbines connected to the point
of common coupling via a wind farm collector grid.
PCC: Point of common coupling (see Figure 2-1) located on the HV
substation side of the wind farm grid. It can reach up to the incoming cable
sealing ends.
EPC: Engineering, procurement and construction
GRID
HV PCC
Wind Farm
(WF) MV
Substation
LV MV MV LV
LV MV MV LV
LV MV MV LV
Branch 1 Branch n
7737A02/FICHT-13535576-v2 2-1
reactive power by capacitive equipment is defined negative. With respect
to synchronous generators, reactive power consumption is also
characterized as “over-excited” reactive power. The use of term
“capacitive power” is also common.
Generation Consumption
Imag
P: negative P: positive
Capacitive
Q: negative Q: negative
I I
V
Real
Inductive
I I
P: negative P: positive
Q: positive Q: positiv
Active Current:
p 1 P
iP in p.u. or IP ( VLL : the magnitude of the
v 3 VLL
symmetrical three-phase system line-to-line voltage).
Active current has always the same sign as the corresponding active power.
Reactive Current:
q 1 Q
iQ in per unit (p.u.) or IQ .
v 3 VLL
Reactive current has always the samesign as the corresponding reactive
power.
Symmetrical Components
g 1 a a ga
2
1 1 2
g 2 1 a a gb
3 1 1 1 g
g 0 c
Where the variable “g” may represent voltages and currents of the three
1 3
phase system, and the complex unity vectors are: a j and
2 2
2 1 3
a j
2 2
7737A02/FICHT-13535576-v2 2-2
The index “1”, “2” and “0” denote positive, negative and zero sequence
components, respectively.
7737A02/FICHT-13535576-v2 2-3
3. Steady State Requirements
Under system stress the range is extended to 48.75 Hz to 51.25 Hz. Under
extreme system fault conditions all generating units must be disconnected at
a frequency greater than or equal to 51.5 Hz or at a frequency less than or
equal to 47.5 Hz.
Additional requirement for active power control are described in section 3.2.
7737A02/FICHT-13535576-v2 3-1
Line-to-line voltage
level in kV
HVRT
requirement
according to
151.8 440 section 4.3
t 2 hours
145.2 420
immediate
immediate disconnection
132
400
continuous
disconnection
118.8 380
t 2 hours
112.2 360 LVRT
requirement
according to
section 4.1
Figure 3-1: Required duration of operation of a wind farm in dependency to the PCC voltage
and the nominal frequency
The ability to reduce the power feed-in is included in the EPC scope of
work and has to be implemented in such a way that during operation it is at
the plant operator’s remit.
The reduction of the power output to the respective target value must be
realized without delay, but within one minute, at the latest.
All generating units must reduce at a frequency of more than 50.5 Hz the
instantaneous active power, while in operation, with a gradient of 40% of
the generators instantaneously available capacity per Hz as fast as possible,
but within a maximum of 10 seconds. The time 10 seconds refers to the rise
7737A02/FICHT-13535576-v2 3-2
time of the active power step response to a frequency change, and may vary
in a reasonable range and has to be adjusted according to the requirements
of the transmission system operator.
50.5 frequency in Hz
f grid
P
P
% P 40% Pm per Hz
50.5 Hz f grid
P 20 Pm at 50.5 Hz f grid 51.5 Hz
50 Hz
Pm instantaneously available power
P power reduction
f grid grid frequency
Overexcited Underexcited
(Capacitive) (Inductive)
Power factor
Figure 3-3: Reactive power requirement during normal operation and nominal
active power supply
7737A02/FICHT-13535576-v2 3-3
For active power supply below the nominal power the Figure 3-4 indicates
the minimum reactive power and power factor requirements.
pPCC in p.u.
qPCC in p.u.
-0.62 0.33
-0.3
Table 3-1: Nominal, minimum and maximum voltage levels for normal operation
Outside the voltage range provided in Table 3-1 the WF has to be operated
in voltage control mode as explained in Section 4.1.2. As such, the voltage
controller should inject additional reactive current resulting in stabilizing the
voltage change. A controller implementation example is shown in Figure
4-4.
The grid operator can define the steady-state operating point by providing
the required values or characteristics for
7737A02/FICHT-13535576-v2 3-4
Q P C C ,ref is derived from a voltage-Var droop characteristic
cos PCC is derived from a voltage cos φ (V)
qPCC,ref
cos PCC,ref
tan arccos cos PCC,ref
individual WTs
Alternatively
Distribution to
qPCC,ref qPCC,ref qPCC
1
kI 1
s TI
vWT
WT n
qPCC,max qPCC
qPCC,ref
vPCC,ref
kDroop
qPCC,min
vPCC
Figure 3-5.
7737A02/FICHT-13535576-v2 3-5
4. Requirements during Contingency
Positive sequence
fundamental
frequency PCC Typical voltage behavior
voltage in p.u.
following fault clearance
1.0
0.9
0.8
0.4
0.2
Time in sec
0.0
0 0.25 1.5 ... 180
A voltage fall below the red line triggers the immediate disconnection of
the unit. WT must be capable of remaining connected at or above this
limit during and immediately after any short circuit which is correctly
isolated by protection schemes even in the case of action by the second
7737A02/FICHT-13535576-v2 4-1
level protection. WT must survive a voltage dip of at least the depth
shown in the solid red line at the PCC in Figure 4-1.
Wind farms must survive any incident of this severity in the voltage dip
and duration.
The wind farms shall recover, at the minimum, 90% of their generation
prior to the incident in less thanone minute after the short circuit.
Figure 4-2 demonstrates the required static gain of the voltage controller. A
controller with higher dynamic gain e.g. by implementing PD (proportional-
differential) controller characteristic is acceptable as long as the stability of
the voltage controller is guaranteed.
7737A02/FICHT-13535576-v2 4-2
Figure 4-2: Static voltage controller characteristic
The positive sequence voltage drop or rise is defined with respect to the pre-
fault 30-second-average voltage. It is allowed to calculate this value
continuously including the low/high voltage periods (moving voltage
average of the past 30 seconds).
v1 v1,Fault v1 (30 s )
The step response of the reactive current must be well damped (damping
ratio >5%) and should settle at the steady-state value
7737A02/FICHT-13535576-v2 4-3
iQ,1 iQ,1 (t 0) k1 v1
where iQ,1 (t 0) represents the reactive current before the fault occurrence.
The injected reactive current represents an addition to the steady-state
reactive current supplied before the fault.
Reactive Current
20%
-10%
Settling Time
60 ms
Rise Time
30 ms
Time
7737A02/FICHT-13535576-v2 4-4
PCC Var tracking controller
Stop if
vPCC < vPCC_min
vPCC > vPCC_max
or all WT reachediQ limit
To other WT
qPCC,ref vWT,ref within the same
1 wind farm
kI 1
s TI
-
qPCC
WT voltage controller
iQ_WT,max
vWT,ref0 1 p.u. iQ_WR,ref
To converter
kiQ control
-
vWT iQ_WT,min
In the approach shown in Figure 4-4 both steady state reactive power
generation and fast voltage control are implemented at WT level. However,
other approaches such as using STATCOM for static Var generation as well
as for fast voltage control is allowed if the described requirements are met.
In Figure 4-4 centralized wind farm controller is implemented for Var
tracking in the PCC.
In case of a single WT both PCC Var tracking and fast local control can be
implemented at the WT level.
Note that in this case (Figure 4-4) no dead band implementation is required.
One possible option for the required negative sequence reactive current
injection is visualized in Figure 4-5.
7737A02/FICHT-13535576-v2 4-5
Negative sequence
reactive current
iQ,2 in p.u.
iQ,2
0.5
Gain : k2 k2
v2 Negative Sequence
flexible setting range and has to voltage rise
be defined according to section 7.3 v2 in p.u.
0
0.05 0.1 0.2 0.3 0.4 0.5
During unbalanced grid faults the priority between positive sequence active
current, positive sequence reactive current and negative sequence reactive
current has to be determined as result of dynamic grid assessment, see
section 7.3.
7737A02/FICHT-13535576-v2 4-6
Positive sequence
fundamental frequency
voltage in p.u.
1.3
border line
1.2
1.1
1.0
Typical voltage behavior
following fault clearance
0.9
Positive sequence
fundamental frequency
voltage in p.u.
1.3
border line
1.2
1.1
1.0
Typical voltage behavior
due to a switching event
0.9
Exceeding the solid border line triggers the immediate disconnection of the
unit. Wind generators must be capable of remaining connected at or below
this limit during and immediately after any short circuit which is correctly
cleared by protection schemes even by the second level protection. Any
other disturbances as well should not result in the border line shown in
Figure 4-6 being crossed.
7737A02/FICHT-13535576-v2 4-7
5. Requirements concerning Harmonics Emission and
Grid Resonances
The current inrush acting over the Network impedance is the mechanism
that produces the voltage dip (sudden fall) and the corresponding voltage
swell (sudden rise) when the Apparatus concerned is offloaded.
5.2 Harmonics
Harmonics are generating waveforms that distort the fundamental 50 Hz
wave. The limits for harmonic distortion levels are given in the following
documents:
7737A02/FICHT-13535576-v2 5-1
c) IEC/TR3 61000-3-6 “Assessment of emission limits for distorting loads
in MV and HV power systems”.
d) IEC 61400-21 “Measurement and assessment of power quality
characteristics of grid connected wind turbines”
7737A02/FICHT-13535576-v2 5-2
6. Required data and simulation studies
The Contractor is required to provide information, which are listed in the
following sections and tables.
Manufacturer
Typ []
Rated Voltage [kV]
Apparent Power (@ 25°C) [kVA]
Apparent Power (@ 50°C) [kVA]
Active Power (@ 25°C) [kW]
Active Power (@ 50°C) [kW]
Maximum Current [A]
Power factor []
(@maximum Active power)
Maximum Power factor []
(overexcited/lagging)
Maximum Power factor []
(underexcited/leading)
7737A02/FICHT-13535576-v2 6-1
Table 6-2: Closed loop WF plant controller data
Manufacturer []
WF Plant controller Type []
closed loop control of the WF Plant [yes/no]
foreseen to control the Power
Factor at the PCC on 33 kV
Ability to control a fixed power [yes/no]
factor
Ability to control a variable power [yes/no]
factor
Ability to control the Power Factor [yes/no]
to a characteristic curve P(cosφ)
Ability to control a fixed power in [yes/no]
kvar
Ability to control a power/voltage [yes/no]
characteristic Q(U)
Manufacturer []
WT controller Type []
closed loop control of the WT Plant [yes/no]
foreseen to control the Power
Factor at the PCC on 33 kV
Ability to control a fixed power [yes/no]
factor
Ability to control a variable power [yes/no]
factor
Ability to control the Power Factor [yes/no]
to a characteristic curve P(cosφ)
Ability to control a fixed power in [yes/no]
kvar
Ability to control a power/voltage [yes/no]
characteristic Q(U)
7737A02/FICHT-13535576-v2 6-2
6.5 Transformer Data
Following necessary information about the 33 kV transformer have to be
provided as listed in Table 6-5.
7737A02/FICHT-13535576-v2 6-3
7. Studies
Following steady state analyses have to be performed by a power system
analysis software such as PSSE/E or DIgSILENT, taking into account the
electrical equipment and configuration. The final results and the used
models, including the validated user model for the LVRT have to be handed
over to the grid operator.
Table 7-1: Transformer tap settings and loading for steady state simulations for
scenario 1
For the load flow scenario 1 to 13 the reactive power capability of the
participating WF at the PCC should be presented graphically as indicated in
Figure 7-1 and Table 7-3.
The ordinate (y-axis) in Figure 7-1 indicates the active power, pavailable in
p.u. at PCC. The abscissa (x-axis) indicates the reactive power, qPCC in p.u.
at the PCC. The sign convention defined in Section 2 is used.
7737A02/FICHT-13535576-v2 7-1
Reactive power requirement for a wind farm
for upcc = 0.95, 1.0, 1.05 p.u.
pPCC in p.u.
qPCC in p.u.
3
-0.62 0.33
5 2 7
-0.3
4 1 6
Overexcited -1 Underexcited
(Capacitive) (Inductive )
7.1.1 Load flow and reactive power capability during rated voltage
Table 7-4 lists the load flow scenarios during rated voltage at the PCC:
7737A02/FICHT-13535576-v2 7-2
7.1.2 Load flow and reactive power capability during admissible voltage
conditions
Table 7-5 lists the load flow scenarios during admissible voltage conditions
(± 10%) at the PCC, where the WF operates in a stable mode without any
equipment tripping.
7737A02/FICHT-13535576-v2 7-3
7.3 Dynamic LVRT Calculation
A dynamic LVRT calculation analysis should be performed for the WF and
all related AC equipment. The controlling scheme of the WTs and the WF
and of any other dynamic controlled equipment, if any, should be
implemented in such a simulation. The gain k1 for the positive sequence
voltage control (see section 4.12) and the optional gain k2 for the negative
sequence current injection (see section 4.2) should be adjusted according to
the results of the dynamic LVRT calculation analysis. The following
scenarios and results should be presented.
7737A02/FICHT-13535576-v2 7-4
8. Commissioning Tests
The contractor has to prove during the commissioning tests that the installed
equipment is fully functional in relation to the grid code and this document.
The testing scheme has to be submitted with the Quality Assurance and will
be agreed on during the detailed engineering phase.
The following tests will be required but not necessarily limited to:
reactive power
set points
operating range
control times
active power
set points
control (by given frequency changes)
protection functions.
7737A02/FICHT-13535576-v2 8-1