T D S DESCRIPTION

A. Sub Structure
1. Excavation and Earth Work
1.1 Site Clearing
32 A= (20*30) m2
22 1m working space on each side
704
TOTAL 704 m2 total area of site clearance

1.2 Bulk Excavation for main house


16.35 main house area
14.3 A=(16.35*14.3) m2
0.4 H=0.4 m
TOTAL 93.52 m3 bulk Excavation

1.3 Pit Excavation for main house for Footing pad


T D S
working space each side 0.25 m
1 1.6 L=1.1+(2*0.25)=1.6 m
2.1 W=1.6+(2*0.25)=2.1m
1.5 H=1.5
5.04 m3 F(chimney)
-0.45 m3 Diduction of bulk
F1 A= (0.80 x 0.80)m2
2 1.30 L = 0.80+(2*0.25) = 1.30m
1.30 W = 0.80+(2*0.25) = 1.30m
1.50 H=1.50m
5.07 m3
Diduction, F1 (Footing bulk excavation)
-2 0.45 L = 0.20+0.25= 0.45m
0.45 W = 0.20+0.25= 0.45m
0.40 H=0.40m
-0.16 m3
F2 A= (1.40 x 1.40)m2
8 1.90 L = 1.40+ (2*0.25) = 1.90m
1.90 W = 1.40+(2*0.25) = 1.90m
1.50 H=1.5 m
28.88 m3
Diduction, F2 (Footing bulk excavation)
-14 0.85 L =0.06+0.25= 0.85m
0.85 W = 0.06+0.25= 0.85m
0.40 H=0.40m
-4.05 m3
F3 A= (1.65 x 1.65)m2
8 1.65 L = 1.65+(2*0.25) = 2.15m
1.65 W = 1.65+(2*0.25)= 2.15m
1.50 H=1.50m
32.67 m3
Diduction, F3 (Footing bulk excavation)
-26 0.98 L = 0.725+0.25=0.975m
0.98 W = 0.725+0.25=0.975m
0.40 H=0.40m
-9.99 m3

TOTAL 57.01 m3 total volume of pit excavation.


1.4 Trench Excavation for main house
T D S
between axis Y1 - Y4 & X4 -X2
1 17.25 0.25m working space each side
1.25
21.56 m3
axis X4 - entrance of car port.
2 15.65 0.25m working space each side
1.25
19.56 m3
Y1 - Y2
1 5.7 0.25m working space each side
1.25
7.13 m3
Y3 - Y4
1 6 0.25m working space each side
1.25
7.5 m3
entrance of car port - X1
2 0.98 0.25m working space each side
1.25
2.45 m3
Y2 - Y3
1 1.6 0.25m working space each side
1.25
2 m3

TOTAL 60.2 m3 of total trench excavation

1.5 Back fill around foundation From the site.


T D S
F1 A= (0.80 x 0.80)m2
2 1.30 L = 0.80+(2*0.25)= 1.30m
1.30 W = 0.80+(2*0.25) = 1.30m
2.10 H=2.10m
7.10 m3
Diduction (Footing, Column & Masonry)
-2 0.80 Footing L = 0.80m
0.80 W= 0.80m
0.20 H=0.20m
-0.26 m3
-2 0.40 Column L =0.40 m
0.20 W= 0.20m
1.90 H=2.10 - 0.20 = 1.90m
-0.30 m3
-2 1.00 Masonry L=0.20+0.30+( 2*0.25)=1.00m
0.50 W= 0.50m
1.25 H=1.20+0.05 = 1.25m
-1.25 m3
F2 A=(1.40 x 1.40)m2
8 1.90 L = 1.40+(2*0.25) = 1.90m
1.90 W = 1.40+( 2*0.25) = 1.90m
2.10 H=2.10m
60.65 m3
Diduction (Footing, Column & Masonry)
-8 1.40 Footing L = 1.40m
1.40 W=1.40m
0.40 H=0.35+0.05=0.40m
-6.27 m3
-6 0.30 Column, C1 L =0.30 m
0.20 W= 0.20m
1.75 H=2.10 - 0.35 = 1.75m
-0.63 m3
-4 1.60 Masonry L=1.40 - 0.30+(2*0.25)=1.60m
0.50 W= 0.50m
1.25 H=1.20+0.05 = 1.25m
-4.00 m3
-2 1.65 Masonry L=1.40-0.15-0.10+(2*0.25)=1.65m
0.50 W= 0.50m
1.25 H=1.20+0.05 = 1.25m
-2.06 m3
-2 0.20 Column, C4 L =0.20 m
0.20 W= 0.20m
1.75 H=2.10 - 0.35 = 1.75m
-0.14 m3
-2 1.70 Masonry L=1.40 - 0.20+(2*0.25)=1.70m
0.50 W= 0.50m
1.25 H=1.20+0.05 = 1.25m
-2.13 m3
Bulk excavation
-14 0.85 L =0.06+0.25= 0.85m
0.85 W = 0.06+0.25= 0.85m
0.40 H=0.40m
-4.05 m3
F3 A= (1.65 x 1.65)m2
8 2.15 L = 1.65+(2*0.25) = 2.15m
2.15 W = 1.65+(2*0.25) = 2.15m
2.10 H=2.10m
77.66 m3
Diduction (Footing, Column & Masonry)
-8 1.65 Footing L = 1.65m
1.65 W=1.65m
0.35 H=0.30+0.05=0.35m
-7.62 m3
-2 0.30 Column, C2 L =0.30 m
0.20 W= 0.20m
1.75 H=2.10 - 0.35 = 1.75m
-0.21 m3
-2 1.85 Masonry L=1.65 - 0.30+( 2*0.25)=1.85m
0.50 W= 0.50m
1.25 H=1.20+0.05 = 1.25m
-2.31 m3
-6 0.20 Column, C4 L =0.20 m
0.20 W= 0.20m
1.75 H=2.10 - 0.35 = 1.75m
-0.42 m3
Bulk excavation
-26 0.98 L = 0.725+0.25=0.975m
0.98 W = 0.725+0.25=0.975m
0.40 H=0.40m
-9.99 m3
F (chimney) A=(1.10 x 1.60)m2
1 2.10 L = 1.60+(2*0.25)= 2.10m
1.60 W = 1.10+( 2*0.25)= 1.60m
1.50 H=2.10m
5.04 m3
T D S
Diduction (Footing, Column & Masonry)
-1 1.60 Footing L = 1.60m
1.10 W=1.10m
0.20 H=0.15+0.05=0.20m
-0.35 m3
-1 0.20 Column, L =0.20 m
0.20 W= 0.20m
1.90 H=2.10 - 0.20 = 1.90m
-0.08 m3
-1 1.90 Masonry L=1.60 - 0.20+(2*0.25)=1.90m
0.50 W= 0.50m
1.25 H=1.20+0.05 = 1.25m
-1.19 m3
Bulk excavation
-1 1.60 L = 1.60m
0.70 W =0.45+0.25= 0.70m
0.40 H=0.40m
-0.45 m3

3
TOTAL 106.74 m total volume of backfill around foundation.

1.6 Ditto item 1.5 but under Ground Floor Slab


16.35
14.3
0.4
93.522 m3 total backfill under ground floor slab
1.7 Cart away

A= 704 m2 Site clearance


H=20 cm
704
0.2
140.8 m3 of site clearance
93.52 m3 of bulk excavation
57.01 m3 of pit excavation
60.2 m3 of trench excavation

-1 106.74 Deduction of excavated soil which is


-106.74 used as backfill around foundation.

TOTAL 244.79 m3 of total volume carted away

1.9 200mm thick Hard core.


T D S
B/n axis X1 & X2 and Y1 & Y2.
13.50 L = 13.50m
5.80 W = 5.80m
78.30 m2
B/n axis X2 & X3 and Y1 & Y4
13.50 L = 13.50m
3.95 W= 3.95m
53.33 m2
B/n axis X3 & X4 and Y1 & Y4
13.50 L = 13.50m
3.80 W = 3.80m
51.30 m2
B/n axis X1 & X1 and Y1 & Y3 .
7.70 L = 7.70m
1.25 W = 1.25m
9.63 m2
B/n axis X1 & X1 and Y1 & Y4.
7.70 L = 5.80m
1.05 W =1.05m
8.09 m2
B/n axis X1 & X1 and Y2 & Y3.
2.20 L = 2.20m
0.75 W = 0.75m
1.65 m2
B/n axis X1 & X2 and Y1 & Y4.
13.50 L = 13.50m
2.60 W = 2.60m
35.10 m2

2
TOTAL 237.39 m total area of hard core.
A.SUB-STRUCTURE
2. CONCRETE WORK

2.1 lean concrete under footing


5mm thick lean concrete
T D S
F (chimney)
A= (1.1*1.6) m2
L =1.1+(2*0.05) = 1.2 m
W=1.6+(2*0.05)=1.7 m
1 1.2 (2*0.05) side increase
1.7
2.04 m2 lean concrete
F1
A= (0.8*0.8) m2
L =0.8+(2*0.05) = 0.9 m
W=0.8+(2*0.05)= 0.9 m
2 0.9 (2*0.05) side increase
0.9
1.62 m2 lean concrete
F2
A= (1.4*1.4) m2
L =1.4 +(2*0.05) = 1.5 m
W=1.4 +(2*0.05)=1.5 m
8 1.5 (2*0.05) side increase
1.5
18 m2 lean concrete
F3
A= (1.65*1.65) m2
L =1.65 +(2*0.05) = 1.75 m
W=1.65 +(2*0.05)=1.75 m
8 1.75 (2*0.05) side increase
1.75
24.5 m2 lean concrete

TOTAL 46.16 m2 Lean concrete under footing

2.2 lean concrete under Grade beam


T D S
GB1
L=13.275 m
W=0.2+(2*0.05) m=0.3 m
3 13.275 (2*0.05) side increase
0.3
11.95 m2 lean concrete
GB2
L=5.425 m
W=0.2+(2*0.05) m=0.3 m
1 5.425 (2*0.05) side increase
0.3
1.63 m2 lean concrete
GB2'
L=7.85 m
W=0.2+(2*0.05) m=0.3 m
1 7.85 (2*0.05) side increase
0.3
2.36 m2 lean concrete
GB3
L=5.725 m
W=0.2+(2*0.05) m=0.3 m
1 5.725 (2*0.05) side increase
0.3
1.72 m2 lean concrete
GB4
L=2.125 m
W=0.2+(2*0.05) m=0.3 m
1 2.125 (2*0.05) side increase
0.3
0.64 m2 lean concrete
GB5
L=14.55 m
W=0.2+(2*0.05) m=0.3 m
1 14.55 (2*0.05) side increase
0.3
4.37 m2 lean concrete
GB5'
L=15.88 m
W=0.2+(2*0.05) m=0.3 m
1 15.88 (2*0.05) side increase
0.3
4.76 m2 lean concrete
GB6
L=15.43 m
W=0.2+(2*0.05) m=0.3 m
2 15.43 (2*0.05) side increase
0.3
9.26 m2 lean concrete
GB6' SERVICE
L=13.325 m
W=0.2+(2*0.05) m=0.3 m
2 13.325 (2*0.05) side increase
0.3
8.00 m2 lean concrete
GB6'
L=3.875 m
W=0.2+(2*0.05) m=0.3 m
1 3.875 (2*0.05) side increase
0.3
1.16 m2 lean concrete
GB7 SERVICE
L=2.525 m
W=0.2+(2*0.05) m=0.3 m
4 2.525 (2*0.05) side increase
0.3
3.03 m2 lean concrete

TOTAL 48.86 m2 lean concrete under footing

2.3 lean concrete for stone masonary


Along axis X1 B/n axis Y1 & Y3.
1 2.02 L = 2.02m
0.60 W = 0.50+(2*0.05)= 0.60m
(2*0.05) side increase
1.21 m2 lean concrete
Along axis X4 B/n axis Y1 & Y4.
L =5.70+2.40+6.00 - 2*0.40 -2*0.20=12.9m
1 12.90 =12.90m
0.60 W = 0.60m
(2*0.05) side increase
7.74 m2 lean concrete

B/n axis X1 & X1, Y1 & Y2 , Y3 & Y4.


1 10.70 L =5.70+6.00-2*0.40-2*0.10= 10.70m
0.60 W = 0.60m
(2*0.05) side increase
6.42 m2 lean concrete

Along axis Y2 & Y3 and B/n axes X1 & X1.


2 1.25 L =(2.20 -1.35)+0.50 - 0.1=1.25m
0.60 W = 0.60m
(2*0.05) side increase
1.50 m2 lean concrete

Along axis Y1 B/n axis X1 & X4.


L =14.45m
1 14.45 W = 0.60m
0.60 (2*0.05) side increase

8.67 m2 lean concrete

Along axis Y4 B/n axis X1 & X4.


L =14.45m
1 14.45
0.60 W = 0.60m
(2*0.05) side increase
8.67 m2 lean concrete

Along GB6'
1 3.95 L = 4.15 - 2*0.10=3.95m
0.60 W = 0.60m
(2*0.05) side increase
2.37 m2 lean concrete

Along axis X5 & X6 B/n axis Y5 & Y8.


2 13.50 L = 14.30-4*0.20=13.50m
0.60 W = 0.60m
(2*0.05) side increase
16.20 m2 lean concrete

Along axis Y5 & Y8 B/n axis X5 & X6.


2 2.00 L = 2.00m
0.60 W= 0.60m
(2*0.05) side increase
2.40 m2 lean concrete

Along axis Y6 & Y7 B/n axis X5 & X6.


2 2.00 L = 2.00m
0.50 W = 0.40+(2*0.05) = 0.50m
(2*0.05) side increase
2.00 m2 lean concrete

2
TOTAL 57.18 m total area of lean concrere under
Stone masonary.
2.4 lean concrete for Hard core

1 237.39 The same as Total area of Hard core.


TOTAL 237.39 m2 total area of lean concrere under hard core

2.5 CONCRETE WORK FOR FOOTING PAD


T D S

F1 A=( 0.80 x 0.80 )m2


2 0.80 L = 0.80m
0.80 W= 0.80m
0.15 H=0.15m
0.19 m3 C-25 concrete

F2 A=( 1.40 x 1.40 )m2


8 1.40 L = 1.40m
1.40 W=1.40m
0.35 H=0.35m
5.49 m3 C-25 concrete

F3 A= (1.65 x 1.65)m2
8 1.65 L = 1.65m
1.65 W=1.65m
0.30 H=0.3
6.53 m3 C-25 concrete

TOTAL 12.02 m3 volume C-25 concrete for footing pad

2.6 CONCRETE FOR SHORT COLUMN


T D S
C1 A= (0.30 x 0.20 )m2
6 0.30 L = 0.30m
0.20 W= 0.20m
1.75 H=2.10 - 0.35=1.75m
0.63 m3 of concrete

C2 A= (0.30 x 0.20)m2
2 0.30 L = 0.30m
0.20 W= 0.20m
1.80 H=2.10 - 0.30=1.80m
0.22 m3 of concrete

C3 A= (0.40 x 0.20)m2
2 0.40 L = 0.40m
0.20 W= 0.20m
1.95 H=2.10 - 0.15=1.95m
0.31 m3 of concrete

C4 on F2 A= (0.20 x 0.20 )m2


2 0.20 L = 0.20m
0.20 W= 0.20m
1.75 H=2.10 - 0.35=1.75m
0.14 m3 of concrete
C4 on F3 A= ( 0.20 x 0.20 )m2
6 0.20 L = 0.20m
0.20 W= 0.20m
1.80 H=2.10 - 0.30=1.80m
0.43 m3 of concrete
TOTAL 1.73 m3 total volume of C-25 for short column.
2.7 CONCRETE FOR GRADE BEAM COLUMN
T D S

GB1
L=13.275 m
3 13.275 W=0.2m
0.2 H=0.4m
0.4
3.19 m3 of concrete

GB2
L=5.425 m
1 5.425 W=0.2m
0.2 H=0.4m
0.4
0.43 m3 of concrete

GB2'
L=7.85 m
1 7.85 W=0.2m
0.2 H=0.4m
0.4
0.63 m3 of concrete

GB3
L=5.725 m
1 5.725 W=0.2m
0.2 H=0.4m
0.4
0.46 m3 of concrete

GB4
L=2.125 m
1 2.125 W=0.2m
0.2 H=0.4m
0.4
0.17 m3 of concrete

GB5
L=14.55 m
1 14.55 W=0.2m
0.2 H=0.4m
0.4
1.16 m3 of concrete

GB5'
L=15.88 m
1 15.88 W=0.2m
0.2 H=0.4m
0.4
1.27 m3 of concrete

GB6
L=15.43 m
2 15.43 W=0.2m
0.2 H=0.4m
0.4
2.47 m3 of concrete
GB6' SERVICE
L=13.325 m
2 13.325 W=0.2m
0.2 H=0.4m
0.4
2.13 m3 of concrete

GB6'
L=3.875 m
1 3.875 W=0.2m
0.2 H=0.4m
0.4
0.31 m3 of concrete

GB7 SERVICE
L=2.525 m
4 2.525 W=0.2m
0.2 H=0.4m
0.4
0.81 m3 of concrete

TOTAL 13.03 m3 volume of concrete for grade beam


3.FORM WORK FOR SUB-STRUCTURE
3.1 FOR FOOTING PAD
T D S

F1 A=(0.80 x 0.80)m2
2 3.20 Perimeter P=(0.8+0.8+0.8+0.8)= 3.20m
0.15 H=0.15m
0.96 m2 of formwork
F2 A=( 1.40 x 1.40)m2
8 5.60 Perimeter P=(1.4+1.4+1.4+1.4)= 5.6m
0.35 H=0.35m
15.68 m2 of formwork
F3 A= (1.65 x 1.65)m2
8 6.60 P=(1.65+1.65+1.65+1.65)= 6.6m
0.30 H=0.30m
15.84 m2 of formwork

TOTAL 32.48 m2 total area of form work for footing pad.

3.2 FORMWORK FOR GRADE BEAM

Descrption NO. LENGTH TOTAL


GB1 3 13.275 39.825
GB2 1 5.425 5.425
GB2' 1 7.85 7.85
GB3 1 5.725 5.725
GB4 1 2.125 2.125
GB5 1 14.55 14.55
GB6 2 15.43 30.86
GB6' SERVICE 2 13.325 26.65
GB6' 1 3.875 3.875
GB7 SERVICE 4 2.525 10.1
TOTAL LENGTH(m) 146.985 m

PERIMETER P=(2*0.2)+(2*0.4)=1.2m

1 146.985
1.2
TOTAL 176.382 m2 formwork for grade beam

4. MASONARY WORKS

4.1 50cm thick Masonary below NGL:-


T D S
Along axis X1 B/n axis Y2 & Y3.
1 1.12 L = 2.02 - 2*(0.25+0.20)=1.12m
0.50 W = 0.50m
1.20 H=1.20m
0.67 m3 masonary

Along axis X4 B/n axis Y1 & Y4.


1 4.30 L=4.30m
0.50 W = 0.50m
1.20 H=1.20m
2.58 m3 masonary
B/n axis X1 & X1, Y1 & Y2 , Y3 & Y4.
1 9.90 L =9.90m
0.50 W = 0.50m
1.20 H=1.20m
5.94 m3 masonary
Along axis Y2 & Y3 and B/n axis X1 &X1.
2 0.95 L =0.95m
0.50 W = 0.50m
1.20 H=1.20m
1.14 m3 masonary

Along axis Y1 B/n axis X1 & X4.


1 8.85 L=8.85m
0.50 W = 0.50m
1.20 H=1.20m
5.31 m3 masonary

Along axis Y4 B/n axis X1 & X4.


1 6.70 L=6.70m
0.50 W = 0.50m
1.20 H=1.20m
4.02 m3 masonary
Along GB6'
1 3.875 L = 3.875
0.50 W = 0.50m
1.20 H=1.20m
2.33 m3 masonary
Along axis X5 & X6 B/n axis Y5 & Y8.
2 14.30 L = 14.30m
0.50 W = 0.50m
1.20 H=1.20m
17.16 m3 masonary
Along axis Y5 & Y8 B/n axis X5 & X6.
2 2.00 L = 2.00m
0.50 W = 0.50m
1.20 H=1.20m
2.40 m3 masonary

3
TOTAL 41.55 m total volume 50cm thick Msonary.

4.2 40cm thick Masonary below NGL:-

Along axes Y6 & Y7 B/n axis X5 & X6.


2 2.00 L = 2.00m
0.50 W = 0.40m
1.20 H =1.20m
2.40 m3 masonary
3
TOTAL 2.40 m total volume 40cm thick Msonary.

4.3 Masonary below NGL for:-


A. Footing pad for chimeny
F (chimeny) A=(1.60 x 1.10)m2
1 1.60 L =1.60m
1.10 W = 1.10m
0.15 H=0.15m
0.26 m3 masonary
3
TOTAL 0.26 m total volume Msonary in footing pad.
B.SUPER-STRUCTURE
1. CONCRETE WORK FOR COLUMN
T D S 1.1 FOR GROUND TO FIRST FLOOR
C1
6 0.30 L = 0.30m
0.20 W= 0.20m
2.66 Height = Room Height - Beam depth
Height= 2.91 - 0.25 = 2.66m
0.96 m3 volume of concrete
C2
2 0.30 L = 0.30m
0.20 W= 0.20m
2.66 H=2.66
0.32 m3 volume of concrete
C3
2 0.40 L = 0.40m
0.20 W= 0.20m
2.66 H=2.66
0.43 m3 volume of concrete
C4
8 0.20 L = 0.20m
0.20 W= 0.20m
2.66 H=2.66
0.85 m3 volume of concrete
C SERVICE
8 0.25 L = 0.20m
0.20 W= 0.20m
2.15 Height = Room Height - Beam depth
Height= 2.60 - 0.25 = 2.35m
0.86 m3 volume of concrete

TOTAL 3.41 m3 volume of C-25 for Ground floor column

1.2 FOR FIRST FLOOR TO TOP TIE BEAM

C1
6 0.30 L = 0.30m
0.20 W= 0.20m
2.81 H = 2.81m
1.01 m3 volume of concrete
C2
2 0.30 L = 0.30m
0.25 W= 0.25m
2.81 H = 2.81m
0.42 m3 volume of concrete
C3
2 0.40 L = 0.40m
0.20 W= 0.20m
2.81 H = 2.81m
0.45 m3 volume of concrete
C4
8 0.20 L = 0.20m
0.20 W= 0.20m
2.81 H = 2.81m
0.90 m3 volume of concrete
TOTAL 2.78 m3 volume of C-25 for first floor column
2. CONCRETE WORK FOR BEAM
T D S 2.1 FOR FIRST FLOOR BEAM

FB1 B/N Y1 & Y2.


4 5.675 L=5.675 m
0.2 W=0.2
0.4 H=0.4
1.816 m3 volume of concrete
FB1 B/N Y2 & Y3.
4 2.4 L=2.4
0.4 W=0.4
0.15 H=0.15
0.576 m3 volume of concrete
FB1 B/N Y3 & Y4.
4 6.275 L=6.275
0.2 W=0.2
0.4 H=0.4
2.008 m3 volume of concrete
FB2
1 4.4 L=4.4
0.4 W=0.4
0.15 H=0.15
0.264 m3 volume of concrete
FB3
1 7.375 L=7.375
0.2 W=0.2
0.4 H=0.4
0.59 m3 volume of concrete
FB4
1 5.675 L=5.675
0.2 W=0.2
0.4 H=0.4
0.454 m3 volume of concrete
FB5
3 15.525 L=15.525
0.2 W=0.2
0.4 H=0.4
3.726 m3 volume of concrete

TOTAL 9.434 m3 volume of concrete first floor beam

2.2.CONCRETE WORK FOR TOP TIE BEAM


T D S
TB1
1 5.95 L=5.95m
0.2 W=0.2m
0.25 H=0.25m
0.30 m3 of concrete for tie beam

TB2
1 2.65 L=2.65m
0.2 W=0.2m
0.25 H=0.25m
0.13 m3 of concrete for tie beam
TB3
1 6.25 L=6.25m
0.2 W=0.2m
0.25 H=0.25m
0.31 m3 of concrete for tie beam
TB4
2 14.625 L=14.625m
0.2 W=0.2m
0.25 H=0.25m
1.46 m3 of concrete for tie beam

TB5
1 14.4 L=14.4m
0.2 W=0.2m
0.25 H=0.25m
0.72 m3 of concrete for tie beam

TB6
1 2.65 L=2.65m
0.2 W=0.2m
0.25 H=0.25m
0.13 m3 of concrete for tie beam

TB7
2 16.98 L=16.98m
0.2 W=0.2m
0.25 H=0.25m
1.70 m3 of concrete for tie beam

TB8
1 7.475 L=7.475m
0.2 W=0.2m
0.25 H=0.25m
0.37 m3 of concrete for tie beam

TB9
1 4.4 L=4.4m
0.2 W=0.2m
0.25 H=0.25m
0.22 m3 of concrete for tie beam

TB10
1 4.25 L=4.25m
0.2 W=0.2m
0.25 H=0.25m
0.21 m3 of concrete for tie beam

TOTAL 5.56 m3 of concrete for top tie beam

2.3.Servic quarter Top tie Beams


TB1
2 13.50 L=13.50m
0.20 W = 0.20m
0.25 H=0.25m
1.35 m3 of concrete for tie beam
TB2
4 2.60 L =2.60m
0.20 W = 0.20m
0.25 H=0.25m
0.52 m3 of concrete for tie beam

3
TOTAL 1.87 m total volume of C-25 Rcc in servic quarter
2.4. Suspended slab
T D S
B/n axis X1 & X2 and Y1 & Y4 .
1 13.50 L = 13.50m
5.80 W = 5.80m
78.30 m2 of concrete
B/n axis X2 & X3 and Y1 & Y4 .
1 13.50 L = 13.50m
3.95 W = 3.95m
53.33 m2 of concrete
B/n axis X3 & X4 and Y1 & Y4.
1 13.50 L = 13.50m
3.80 W = 4.00-( 2*0.10)= 3.80m
51.30 m2 of concrete
B/n axis X1 & X1 and Y1 & Y3 .
1 7.70 L = 7.70m
1.25 W =1.25m
9.63 m2 of concrete
B/n axis X1 & X1 and Y3 & Y4 .
1 7.70 L = 5.80m
1.05 W = 1.05m
8.09 m2 of concrete
B/n axis X1 & X1 and Y2 & Y3 .
1 2.20 L = 2.20m
0.75 W = (2.20-1.35)-0.10 = 0.75m
1.65 m2 of concrete
B/n axis X1 & X6 and Y5 & Y8 .
1 13.50 L =13.50m
2.60 W= 2.60m
35.10 m2 of concrete
Deduction stair case area
-1 3.90 L = 3.90m
2.60 W = 2.60m
-10.14 m2 of concrete

TOTAL 227.25 m2 C-25 of concrete for slab

2.5.concrete for stair case


T D S
18 1.3 Triangular section including risers
0.17 and threads
0.3
0.6 m3
2 2.8
1.3 slab under triangular section
0.16
1.17 m3
2.6
0.97 Landings
0.15
0.38 m3
3.85 Stair Beam
0.2
0.3
0.23 m3

TOTAL 2.38 m3 volume of concrete for stairs case


2.6. 150mm slab and parapet of gutter
T D S
perimeter = 5.70+0.48+2.60+0.48+6.00+4.05+
0.30+4.35+0.30+7.25+6.00+0.95+2.60+0.95
1 63.36 +5.70+15.65 = 63.36m
0.60 W = 0.60m

38.02 m2 total area of C-25 for 150mm slab


2
TOTAL 38.02 m total area of C-25 for 150mm slab
and parapet of gutter

3. FORM WORK
3.1.FOR GROUND TO FIRST FLOOR COLUMN
T D S
C1
6 1.00 P= 2*(0.3+0.2)=1.00m
2.76 H=3.06 - 0.3 = 2.76m
16.56 m2
C2
2 1.00 P= 2*(0.3+0.2)=1.00m
2.76 H=3.06 - 0.3 = 2.76m
5.52 m2
C3
2 1.20 L = 2*(0.4+0.2)=1.20m
2.76 H=3.06 - 0.3 = 2.76m
6.62 m2
C4
8 0.80 L = 2*(0.20+0.20)=0.80m
2.76 H=3.06 - 0.3 = 2.76m
17.66 m2

2
TOTAL 46.37 m total area of form work for ground to 1st floor column

3.2.FOR FIRST FLOOR TO ROOF COLUMN


C1
6 1.00 P= 2*(0.3+0.2)=1.00m
2.75 H=3.0 - 0.25 = 2.75m
16.50 m2
C2
2 1.00 P= 2*(0.3+0.2)=1.00m
2.75 H=3.0 - 0.25 = 2.75m
5.50 m2
C3
2 1.20 L = 2*(0.4+0.2)=1.20m
2.75 H=3.0 - 0.25 = 2.75m
6.60 m2
C4
8 0.80 L = 2*(0.20+0.20)=0.80m
2.75 H=3.0 - 0.25 = 2.75m
17.60 m2

TOTAL 46.20 m2 total area of form work 1st floor column to top tie beam
3.3.FORMWORK FOR FIRST FLOOR BEAM

Descrption NO. LENGTH TOTAL


FB1 B/N Y1 & Y2. 4 5.675 22.7
FB1 B/N Y2 & Y3. 4 2.4 9.6
FB1 B/N Y3 & Y4. 4 6.275 25.1
FB2 1 4.4 4.4
FB3 1 7.375 7.375
FB4 1 5.675 5.675
FB5 3 15.525 46.575
1 107.425 FB1 B/N Y1 & Y2,FB1 B/N Y2 & Y3,FB3,FB4 & FB5
1 107.425 m2 P=0.2+(2*0.4)=1m
1 14 FB1 B/N Y2 & Y3,FB2
0.7 9.8 m2 P=0.4+(2*0.15)=0.7m

TOTAL 117.225 m2 Formwork for first floor beam

3.4.FORMWORK FOR TOP TIE BEAM


Descrption NO. LENGTH TOTAL
TB1 1 5.95 5.95
TB2 1 2.65 2.65
TB3 1 6.25 6.25
TB4 2 14.625 29.25
TB5 1 14.4 14.4
TB6 1 2.65 2.65
TB7 2 16.98 33.96
TB8 1 7.475 7.475
TB9 1 4.4 4.4
TB10 1 4.25 4.25
TOTAL (length) 111.235 m

1 111.235 P=0.2+(2*0.25)=0.7m
0.7
TOTAL 77.86 m2 Formwork for top tie beam

3.5. Servic quarter Top tie Beams


Descrption NO. LENGTH TOTAL
TB1 2 13.5 27
TB2 4 2.6 10.4
TOTAL 37.4 m

1 37.4 P=0.2+(2*0.25)=0.7m
0.7
TOTAL 26.18 m2 Formwork for top tie beam

3.6. Suspended slab


T D S
1 5.5 soffit between X1' and X1 & Y1 and Y2
0.996
5.48 m2
1 2.2 soffit between X1' and X1 & Y2 and Y3
0.996
2.19 m2
1 5.8 soffit between X1' and X1 & Y3 and Y4
0.996
5.78 m2
1 5.5 soffit between X1 and X2 & Y1 and Y2
5.7
31.35 m2
1 2.2 soffit between X1 and X2 & Y2 and Y3
5.7
12.54 m2
1 5.8 soffit between X1 and X2 & Y3 and Y4
5.7
33.06 m2
1 3.85 soffit between X2 and X3 & Y1 and Y2
5.5
21.18 m2
1 3.85 soffit between X2 and X3 & Y2 and Y3
2.2
8.47 m2
1 3.85 soffit between X2 and X3 & Y3 and Y4
5.8
22.33 m2
1 3.7 soffit between X3 and X4 & Y1 and Y2
5.5
20.35 m2
1 3.7 soffit between X3 and X4 & Y2 and Y3
2.2
8.14 m2
1 3.7 soffit between X3 and X4 & Y3 and Y4
5.8
21.46 m2
Deduction stair case area
-1 3.90 L = 3.90m
2.60 W = 2.60m
-10.14 m2
2
TOTAL 208.36 m total area of form work for suspended slab

3.7. Stair case and landing


T D S
Inclined Soffit form work
2 3.10 L = 3.10m
1.30 8.06 W = 1.30m
Inclined Side form work
4 3.10 L = 3.10m
0.16 1.98 D =0.16m
Riser form work
18 1.30 L = 1.30m
0.17 3.98 D =0.17m
intermideate landing soffit form work
1 2.60 L = 2.60m
1.30 3.38 W = 1.30m
intermideate landing beam side form work
external side
1 3.85 L = 4.15-0.30=3.85m
0.30 1.16 D=0.30m
internal side
1 3.85 L = 4.15-0.30=3.85m
0.15 0.58 D=0.30-0.15=0.15m
intermideate landing beam soffit form work
1 3.85 L = 4.15-0.30=3.85m
0.20 0.77 W = 0.20m
Side form work for setp
16 0.30 L = 0.30m
0.17 0.82 D = 0.17m
TOTAL 20.72 m2 form work for Stair case and landing
3.8. 150mm slab and parapet of gutter
Soffit form work

1 63.36 Perimeter = 63.36m


0.60 38.02 W = 0.60m
Top form work o(for inclined slab)
1 63.36 Perimeter = 63.36 m
0.40 25.34 W = 0.40m

2
TOTAL 63.36 m form work for slab and parapet of gutter

4.Masonory Work
4.1.HCB wall
H=6.06m
4.1.1.Front Elevation
T D S
1 5.9 between Y1 - Y2
6.06
35.75 m2
1 6.06 between Y2 - Y3
2.2
13.33 m2
1 6.2 between Y3 - Y4
6.06
37.57 m2
-1 2.1 Deduct Doors
2.66 between Y2 - Y3
-5.59 m2
-1 5.5 Car Port
2.66
-14.63 m2
windows
-1 2.3 between Y3 - Y4 Ground Floor
3.72
-8.56 m2
-1 2.25 between Y1 - Y2 First Floor
3.7
-8.33 m2
-1 2.25 between Y2 - Y 3 First Floor
1.5
-3.38 m2
-1 2.25 between Y3 - Y4 First Floor
3.7
-8.33 m2

TOTAL 33.21 m2 20 cm thick of HCB on Front Elevation

4.1.2. Right Elevation


1 14.7 First Floor level
3.06
44.98 m2
1 14.7 Top Tie Beam level
3
44.10 m2
Deduct Doors and Windows
First Floor level
-1 2.3
2.1 window b/n X1 & X2
-4.83 m2
-1 2.3
3.37 window b/n X2 & X3
-7.75 m2
-1 2.3 Top Tie Beam Level
1.6 window b/n X2 & X3
-3.68 m2
-1 2.5
3.3 window b/n X3 & X4
-8.25 m2

TOTAL 64.57 m2 20 cm thick of HCB on Right Elevation

4.1.3. Left Elevation


First Floor level
1 14.45
3.06
44.22 m2
1 15.15 TTB level
3
45.45 m2
Deduct Windows and car port
-2 1
1.05 window b/n X1 & X2 and X2 & X3.
-2.10 m2
-2 2.3
1.05 window b/n X2 & X3.
-4.83 m2
-1 1.3
1.05 window b/n X1 & X2.
-1.37 m2
-1 2.66
4.4 Car Port
-11.70 m2

TOTAL 73.35 m2 20 cm thick of HCB on Left Elevation

4.1.4. Rear Elevation


1 5.9 between Y1 - Y2
6.06
35.75 m2
1 6.06 between Y2 - Y3
2.2
13.33 m2
1 6.2 between Y3 - Y4
6.06
37.57 m2
Deduct Windows and doors
windows
-2 1.76
3.3 window b/n Y1 & Y2.
-11.62 m2
-1 1.76
3.3 window b/n Y3 & Y4.
-5.81 m2
-1 1.05
1.3 window b/n Y2 & Y3.
-1.37 m2
door
-1 2.81
1.2 door b/n Y2 & Y3
-3.37 m2
-1 2.68
1.23
-3.30 m2

TOTAL 61.20 m2 20 cm thick of HCB on Rear Elevation

5.PARTITION
T D S 5.1.Ground Floor
1 14.7 between Y1 - Y2
3.06
44.98 m2
1 1.08
3.06 between Y2 -Y3
3.30 m2
1 8.8 on Y3
3.06
26.93 m2
1 8.5
3.06 between Y3 - Y4
26.01 m2
5.2.First Floor Level
1 18.4
3 between Y1 - Y2
55.20 m2
1 10.2 on Y2
3
30.60 m2
1 1.6 between Y2 - Y3
3
4.80 m2
1 12.7 on Y3
3
38.10 m2
1 16.6 between Y3 - Y4
3
49.80 m2

TOTAL 279.72 m2 15 cm thick of HCB on Partitions

6. Dressed Stone

Front Elevation
3 6.06
0.72
13.09 m2
1 9.15 Right Elevation
2.4
21.96 m2
1 6.06 Rear Elevation
0.9
5.45 m2

TOTAL 40.49 m2 of Dressed Stone area


7. HCB FOR SERVICE
T D S 7.1. FOR WALL
1 20.00 on X4
2.60
52.00 m2
1 20.00 On X5
3.20
64.00 m2
5 3.00 On Y6,Y7,Y8,Y9 & Y10
3.20
48.00 m2

deduction window,door and column


2 0.20 on axis Y5 b/n X5 and X6
2.66
-1.06 m² column
5 0.20 on axis X5 b/n Y5 and Y8
2.60
-2.60 m² column
WINDOW
-1 0.60 on axis X5 b/n Y6 and Y10
0.60
-0.36 m2
-1 1.50
1.40
-2.10 m2

-1 1.60
1.40
-2.24 m2

-1 1.30
0.70
-0.91 m2
-1 2.50
1.40
-3.50 m2
DOOR
-4 0.90
2.40
-8.64 m2
-5 0.20
2.60
-2.60 m2 column

TOTAL 139.99 m² 20cm thick HCB

7.2. PARTITION

4 2.60 b/n X5 & X6


2.60
27.04 m2 column

-1 0.80 deduction door


2.40
-1.92 m2

TOTAL 25.12 m² 15cm thick HCB


8. FINISHING WORK
8.1 plastering
T D S 8.1.1 FRONT SIDE
1 14.30
6.06
86.66 m2

2 6.40
6.06
77.57 m² verenda walls on the front side

-1 2.1 Deduct Doors


2.66 between Y2 - Y3
-5.59 m2
-1 5.5 Car Port
2.66
-14.63 m2
WINDOWS
-1 2.3 between Y3 - Y4 Ground Floor
3.72
-8.56 m2
-1 2.25 between Y1 - Y2 First Floor
3.7
-8.33 m2
-1 2.25 between Y2 - Y 3 First Floor
1.5
-3.38 m2
-1 2.25 between Y3 - Y4 First Floor
3.7
-8.33 m2
-1 2.32
6.06
-14.06 m² stone cover

TOTAL 101.37 m² net plastered area


BUT coat is applied to both side
2 101.37
TOTAL 202.74 m² net plastered area

8.1.2. right side wall


1 14.45
6.06
87.57 m2
Deduct Doors and Windows
First Floor level
-1 2.3
2.1 window b/n X1 & X2
-4.83 m2
-1 2.3
3.37 window b/n X2 & X3
-7.75 m2
-1 2.3 Top Tie Beam Level
1.6 window b/n X2 & X3
-3.68 m2
-1 2.5
3.3 window b/n X3 & X4
-8.25 m2
TOTAL 63.06 m² net plastered area BUT coated both side
126.112 m² net plastered area
T D S 8.1.3. Left Elevation
1 15.65
6.06
94.84 m2
Deduct Windows and car port
-2 1
1.05 window b/n X1 & X2 and X2 & X3.
-2.10 m2
-2 2.3
1.05 window b/n X2 & X3.
-4.83 m2
-1 1.3
1.05 window b/n X1 & X2.
-1.37 m2
-1 2.66
4.4 Car Port
-11.70 m2

TOTAL 74.84 m² net plastered area BUT coated both side

2 74.84
TOTAL 149.68 m² net plastered area

T D S 8.1.4. Rear Elevation


1 14.30
6.06
86.66 m2
Deduct Windows and doors
windows
-2 1.76
3.3 window b/n Y1 & Y2.
-11.62 m2
-1 1.76
3.3 window b/n Y3 & Y4.
-5.81 m2
-1 1.05
1.3 window b/n Y2 & Y3.
-1.37 m2
Door
-1 2.81
1.2 door b/n Y2 & Y3
-3.37 m2
-1 2.68
1.23
-3.30 m2

TOTAL 61.2 m² net plastered area BUT coated both side


2 61.2
TOTAL 122.4 m² net plastered area

8.2. Partition wall

279.72 m² total partition wall area


-13 0.90 Deduct door
2.66
-31.12 m² door on partition wall area

TOTAL 248.60 m² net plastered area but coated both side


497.2 m² net plastered area
9. PLASTERING FOR SERVICE QUARTER
T D S 9.1. External wall

1 20.00 On X4
2.60
52.00 m2
1 20.00 On X5
3.20
64.00 m2
5 3.00 On Y6,Y7,Y8,Y9 & Y10
3.20
48.00 m2
Deduct WINDOW
-1 0.60 on axis X5 b/n Y6 and Y10
0.60
-0.36 m2
-1 1.50
1.40
-2.10 m2

-1 1.60
1.40
-2.24 m2

-1 1.30
0.70
-0.91 m2
-1 2.50
1.40
-3.50 m2
DOOR
-4 0.90
2.40
-8.64 m2

TOTAL 146.25 m² net plastered area BUT coated both side

2 146.25
TOTAL 292.5 m² net plastered area

10.stair case
1 4.00
2.60
10.40 m2 stair sofit
16 0.60
0.17
1.63 m2 side of stair-rectangular part
16 0.30
0.17
0.82 m2 side of stair-triangular part

TOTAL 12.85 m² net plastered area


11. Floor Finish
11.1. Parquate
26.65 m² ground family room
24.00 m² ground dainning room
33.65 m² ground living room
69.35 m² frist floor bed room
13.40 m² first floor dressing room
14.30 m² sevice family room

TOTAL 181.35 m² total parquate area

11.2. Ceramic tile


19.38 m² ground kitchen
26.65 m² ground toilet
13.55 m² first floor bath room
12.45 m² first floor master bath room
25.00 m² service toilet
4.20 m² service laundary

TOTAL 101.23 m² total parquate area

11.3. Terrazo tile


11.18 m² service local kitchen
7.70 m² service store
8.50 m² service maids room

TOTAL 27.38 m² total parquate area

11.4. Marble tile


19.95 m² ground verandah
37.15 m² ground lobby
29.12 m² first corridor
18.60 m² first balcony
49.40 m² stair

TOTAL 154.22 m² total parquate area

11.5. Concrete tile


32.45 m² ground car port

TOTAL 32.45 m² total concrete tile


12. CARPENTRY & JOINERY
12.1. 8 mm thick chip wood ceiling and
40 x 50 mm zigba wood battens
T D S
B/n axis X1 & X2 and Y1 & Y4 .
1 13.50 L =13.50m
5.80 W = 5.80m
78.30 m2
B/n axis X2 & X3 and Y1 & Y4 .
1 13.50 L =13.50m
3.95 W = 3.95m
53.33 m2
B/n axis X3 & X4 and Y1 & Y4.
1 13.50 L = 13.50m
3.80 W 3.80m
51.30 m2
B/n axis X1 & X1 and Y1 & Y2 .
1 5.50 L = 5.50m
1.25 W = 1.25m
6.88 m2
B/n axes X,01&X,01 and Y,02 & Y,03 .
1 2.20 L = 2.20m
1.25 W =1.25m
2.75 m2
B/n axis X1 & X1 and Y3 & Y4 .
1 7.70 L =5.80m
1.05 W =1.05m
8.09 m2
B/n axis X1 & X1 and Y2 & Y3 .
1 2.20 L = 2.20m
0.75 W = 0.75m
1.65 m2
Along axis X4 and Y2 & Y3 .
1 2.20 L = 2.20m
0.28 W= 0.28m
0.62 m2
B/n axis X5 & X6 and Y5 & Y8.
1 13.50 L = 13.50m
2.60 W = 2.60m
35.10 m2

TOTAL 238.00 m2 total area of 8 mm thick chip wood ceiling


and 40 x 50 mm zigba wood battens

12.2. Wooden Frames(Joinery)


No. Doors
8 D1(2100 *900)
3 D2(2100*800)
4 D3(3400*2100)
1 D4(700*2100)
1 D5(2200*2100)
1 D6(3000*2100)
Windows
3 W1(3000*1400)
2 W2(750*1100)
13. Service Truss Members
ф10 eucalyptus Upper chord
11 3.45
37.95
ф10 eucalyptus lower
11 3.40
37.40

TOTAL 75.35 ф10 eucalyptus member

11 0.42 ф10 eucalyptus vertical member


4.62
ф10 eucalyptus diagonal member
11 1.10
12.10

TOTAL 16.72 total ф10 eucalyptus member


13.1. 50*70 Zigba purlins
11 14.30
157.30

14. Main house truss members dia 100


6 52.28
313.68 ml T-1
2 51.15
102.29 ml T-2
4 12.49
49.94 ml T-3
4 19.50
78.01 ml T-4
4 10.48
41.91 ml T-5
4 4.37
17.47 ml T-6
2 26.00
52.00 ml T-7
4 19.30
77.20 ml T-8
4 9.07
36.26 ml T-9
4 7.68
30.72 ml T-10

TOTAL 799.48 ml
T D S 14.1. 50 x 70 mm Zigba purlin .
1 7.84 7.84
2 8.48 16.97
2 9.13 18.25
2 9.77 19.54
2 10.41 20.83
2 11.06 22.11
2 11.70 23.40
2 12.34 24.69
2 12.99 25.97
2 13.63 27.26
2 6.96 13.93
2 7.00 14.00
2 1.04 2.08
2 7.08 14.16
T D S 14.1. 50 x 70 mm Zigba purlin .
2 7.12 14.23
2 7.12 14.23
2 0.70 1.40
2 1.40 2.81
2 2.08 4.16
2 2.68 5.36
2 2.69 5.38
2 3.51 7.02
2 4.21 8.42
2 4.91 9.83
2 5.62 11.23
2 6.32 12.64
2 7.02 14.04
2 7.72 15.44
2 8.42 16.85
2 9.13 18.25
2 9.83 19.66
1 14.27 14.27
1 14.92 14.92
1 15.56 15.56
1 16.20 16.20
1 16.85 16.85
1 17.49 17.49
TOTAL 527.27 ml Perlin for main house

891.55 Total ml of truss members


527.27 Total ml of purlin

15. Roof covering


15.1.For main house
Decra roof tile
1 16.35
14.10
2
230.54 m roof covering
15.2. For service
1 14.30
3.00
2
42.90 m roof covering

2
TOTAL 273.44 m Total area of roof covering

16. Down Pipe


16.1.For main house
PVC pipe dia. 10cm
6 6.06
36.36 ml down pipe
16.2. For service
3 2.60
7.80 ml down pipe

TOTAL 44.16 ml total down pipe


17.Metal work
17.1. Doors
door 0.90*2.10m 5mm glass
12 pcs
door 0.80*2.10m 5mm glass
4 pcs
door 0.90*2.66m 5mm glass
2 pcs
door 3.00*2.10m 5mm glass
1 pcs
door 3.40*2.10m 5mm glass
3 pcs
door 3.00*2.50m 5mm glass
1 pcs
door 0.70*2.10m 5mm glass
1 pcs
door 2.20*2.10m 5mm glass
1 pcs
TOTAL 25 pcs of door

17.2. WINDOWS
window 1.50*1.40m 5mm glass
1 pcs
window 1.60*1.40m 5mm glass
1 pcs
window 1.30*0.70m 5mm glass
1 pcs
window 2.50*1.40m 5mm glass
1 pcs
window 3.00*1.46m 5mm glass
2 pcs
window 0.75*1.06m 5mm glass
2 pcs
window 0.75*1.10m 5mm glass
2 pcs
window 3.00*1.50m 5mm glass
1 pcs
window 0.75*1.00m 5mm glass
2 pcs
window 2.00*1.60m 5mm glass
1 pcs
TOTAL 14.00 pcs of window