A. Sub Structure
1. Excavation and Earth Work
1.1 Site Clearing
32 A= (20*30) m2
22 1m working space on each side
704
TOTAL 704 m2 total area of site clearance
3
TOTAL 106.74 m total volume of backfill around foundation.
2
TOTAL 237.39 m total area of hard core.
A.SUB-STRUCTURE
2. CONCRETE WORK
Along GB6'
1 3.95 L = 4.15 - 2*0.10=3.95m
0.60 W = 0.60m
(2*0.05) side increase
2.37 m2 lean concrete
2
TOTAL 57.18 m total area of lean concrere under
Stone masonary.
2.4 lean concrete for Hard core
F3 A= (1.65 x 1.65)m2
8 1.65 L = 1.65m
1.65 W=1.65m
0.30 H=0.3
6.53 m3 C-25 concrete
C2 A= (0.30 x 0.20)m2
2 0.30 L = 0.30m
0.20 W= 0.20m
1.80 H=2.10 - 0.30=1.80m
0.22 m3 of concrete
C3 A= (0.40 x 0.20)m2
2 0.40 L = 0.40m
0.20 W= 0.20m
1.95 H=2.10 - 0.15=1.95m
0.31 m3 of concrete
GB1
L=13.275 m
3 13.275 W=0.2m
0.2 H=0.4m
0.4
3.19 m3 of concrete
GB2
L=5.425 m
1 5.425 W=0.2m
0.2 H=0.4m
0.4
0.43 m3 of concrete
GB2'
L=7.85 m
1 7.85 W=0.2m
0.2 H=0.4m
0.4
0.63 m3 of concrete
GB3
L=5.725 m
1 5.725 W=0.2m
0.2 H=0.4m
0.4
0.46 m3 of concrete
GB4
L=2.125 m
1 2.125 W=0.2m
0.2 H=0.4m
0.4
0.17 m3 of concrete
GB5
L=14.55 m
1 14.55 W=0.2m
0.2 H=0.4m
0.4
1.16 m3 of concrete
GB5'
L=15.88 m
1 15.88 W=0.2m
0.2 H=0.4m
0.4
1.27 m3 of concrete
GB6
L=15.43 m
2 15.43 W=0.2m
0.2 H=0.4m
0.4
2.47 m3 of concrete
GB6' SERVICE
L=13.325 m
2 13.325 W=0.2m
0.2 H=0.4m
0.4
2.13 m3 of concrete
GB6'
L=3.875 m
1 3.875 W=0.2m
0.2 H=0.4m
0.4
0.31 m3 of concrete
GB7 SERVICE
L=2.525 m
4 2.525 W=0.2m
0.2 H=0.4m
0.4
0.81 m3 of concrete
F1 A=(0.80 x 0.80)m2
2 3.20 Perimeter P=(0.8+0.8+0.8+0.8)= 3.20m
0.15 H=0.15m
0.96 m2 of formwork
F2 A=( 1.40 x 1.40)m2
8 5.60 Perimeter P=(1.4+1.4+1.4+1.4)= 5.6m
0.35 H=0.35m
15.68 m2 of formwork
F3 A= (1.65 x 1.65)m2
8 6.60 P=(1.65+1.65+1.65+1.65)= 6.6m
0.30 H=0.30m
15.84 m2 of formwork
PERIMETER P=(2*0.2)+(2*0.4)=1.2m
1 146.985
1.2
TOTAL 176.382 m2 formwork for grade beam
4. MASONARY WORKS
3
TOTAL 41.55 m total volume 50cm thick Msonary.
C1
6 0.30 L = 0.30m
0.20 W= 0.20m
2.81 H = 2.81m
1.01 m3 volume of concrete
C2
2 0.30 L = 0.30m
0.25 W= 0.25m
2.81 H = 2.81m
0.42 m3 volume of concrete
C3
2 0.40 L = 0.40m
0.20 W= 0.20m
2.81 H = 2.81m
0.45 m3 volume of concrete
C4
8 0.20 L = 0.20m
0.20 W= 0.20m
2.81 H = 2.81m
0.90 m3 volume of concrete
TOTAL 2.78 m3 volume of C-25 for first floor column
2. CONCRETE WORK FOR BEAM
T D S 2.1 FOR FIRST FLOOR BEAM
TB2
1 2.65 L=2.65m
0.2 W=0.2m
0.25 H=0.25m
0.13 m3 of concrete for tie beam
TB3
1 6.25 L=6.25m
0.2 W=0.2m
0.25 H=0.25m
0.31 m3 of concrete for tie beam
TB4
2 14.625 L=14.625m
0.2 W=0.2m
0.25 H=0.25m
1.46 m3 of concrete for tie beam
TB5
1 14.4 L=14.4m
0.2 W=0.2m
0.25 H=0.25m
0.72 m3 of concrete for tie beam
TB6
1 2.65 L=2.65m
0.2 W=0.2m
0.25 H=0.25m
0.13 m3 of concrete for tie beam
TB7
2 16.98 L=16.98m
0.2 W=0.2m
0.25 H=0.25m
1.70 m3 of concrete for tie beam
TB8
1 7.475 L=7.475m
0.2 W=0.2m
0.25 H=0.25m
0.37 m3 of concrete for tie beam
TB9
1 4.4 L=4.4m
0.2 W=0.2m
0.25 H=0.25m
0.22 m3 of concrete for tie beam
TB10
1 4.25 L=4.25m
0.2 W=0.2m
0.25 H=0.25m
0.21 m3 of concrete for tie beam
3
TOTAL 1.87 m total volume of C-25 Rcc in servic quarter
2.4. Suspended slab
T D S
B/n axis X1 & X2 and Y1 & Y4 .
1 13.50 L = 13.50m
5.80 W = 5.80m
78.30 m2 of concrete
B/n axis X2 & X3 and Y1 & Y4 .
1 13.50 L = 13.50m
3.95 W = 3.95m
53.33 m2 of concrete
B/n axis X3 & X4 and Y1 & Y4.
1 13.50 L = 13.50m
3.80 W = 4.00-( 2*0.10)= 3.80m
51.30 m2 of concrete
B/n axis X1 & X1 and Y1 & Y3 .
1 7.70 L = 7.70m
1.25 W =1.25m
9.63 m2 of concrete
B/n axis X1 & X1 and Y3 & Y4 .
1 7.70 L = 5.80m
1.05 W = 1.05m
8.09 m2 of concrete
B/n axis X1 & X1 and Y2 & Y3 .
1 2.20 L = 2.20m
0.75 W = (2.20-1.35)-0.10 = 0.75m
1.65 m2 of concrete
B/n axis X1 & X6 and Y5 & Y8 .
1 13.50 L =13.50m
2.60 W= 2.60m
35.10 m2 of concrete
Deduction stair case area
-1 3.90 L = 3.90m
2.60 W = 2.60m
-10.14 m2 of concrete
3. FORM WORK
3.1.FOR GROUND TO FIRST FLOOR COLUMN
T D S
C1
6 1.00 P= 2*(0.3+0.2)=1.00m
2.76 H=3.06 - 0.3 = 2.76m
16.56 m2
C2
2 1.00 P= 2*(0.3+0.2)=1.00m
2.76 H=3.06 - 0.3 = 2.76m
5.52 m2
C3
2 1.20 L = 2*(0.4+0.2)=1.20m
2.76 H=3.06 - 0.3 = 2.76m
6.62 m2
C4
8 0.80 L = 2*(0.20+0.20)=0.80m
2.76 H=3.06 - 0.3 = 2.76m
17.66 m2
2
TOTAL 46.37 m total area of form work for ground to 1st floor column
TOTAL 46.20 m2 total area of form work 1st floor column to top tie beam
3.3.FORMWORK FOR FIRST FLOOR BEAM
1 111.235 P=0.2+(2*0.25)=0.7m
0.7
TOTAL 77.86 m2 Formwork for top tie beam
1 37.4 P=0.2+(2*0.25)=0.7m
0.7
TOTAL 26.18 m2 Formwork for top tie beam
2
TOTAL 63.36 m form work for slab and parapet of gutter
4.Masonory Work
4.1.HCB wall
H=6.06m
4.1.1.Front Elevation
T D S
1 5.9 between Y1 - Y2
6.06
35.75 m2
1 6.06 between Y2 - Y3
2.2
13.33 m2
1 6.2 between Y3 - Y4
6.06
37.57 m2
-1 2.1 Deduct Doors
2.66 between Y2 - Y3
-5.59 m2
-1 5.5 Car Port
2.66
-14.63 m2
windows
-1 2.3 between Y3 - Y4 Ground Floor
3.72
-8.56 m2
-1 2.25 between Y1 - Y2 First Floor
3.7
-8.33 m2
-1 2.25 between Y2 - Y 3 First Floor
1.5
-3.38 m2
-1 2.25 between Y3 - Y4 First Floor
3.7
-8.33 m2
5.PARTITION
T D S 5.1.Ground Floor
1 14.7 between Y1 - Y2
3.06
44.98 m2
1 1.08
3.06 between Y2 -Y3
3.30 m2
1 8.8 on Y3
3.06
26.93 m2
1 8.5
3.06 between Y3 - Y4
26.01 m2
5.2.First Floor Level
1 18.4
3 between Y1 - Y2
55.20 m2
1 10.2 on Y2
3
30.60 m2
1 1.6 between Y2 - Y3
3
4.80 m2
1 12.7 on Y3
3
38.10 m2
1 16.6 between Y3 - Y4
3
49.80 m2
6. Dressed Stone
Front Elevation
3 6.06
0.72
13.09 m2
1 9.15 Right Elevation
2.4
21.96 m2
1 6.06 Rear Elevation
0.9
5.45 m2
-1 1.60
1.40
-2.24 m2
-1 1.30
0.70
-0.91 m2
-1 2.50
1.40
-3.50 m2
DOOR
-4 0.90
2.40
-8.64 m2
-5 0.20
2.60
-2.60 m2 column
7.2. PARTITION
2 6.40
6.06
77.57 m² verenda walls on the front side
2 74.84
TOTAL 149.68 m² net plastered area
1 20.00 On X4
2.60
52.00 m2
1 20.00 On X5
3.20
64.00 m2
5 3.00 On Y6,Y7,Y8,Y9 & Y10
3.20
48.00 m2
Deduct WINDOW
-1 0.60 on axis X5 b/n Y6 and Y10
0.60
-0.36 m2
-1 1.50
1.40
-2.10 m2
-1 1.60
1.40
-2.24 m2
-1 1.30
0.70
-0.91 m2
-1 2.50
1.40
-3.50 m2
DOOR
-4 0.90
2.40
-8.64 m2
2 146.25
TOTAL 292.5 m² net plastered area
10.stair case
1 4.00
2.60
10.40 m2 stair sofit
16 0.60
0.17
1.63 m2 side of stair-rectangular part
16 0.30
0.17
0.82 m2 side of stair-triangular part
TOTAL 799.48 ml
T D S 14.1. 50 x 70 mm Zigba purlin .
1 7.84 7.84
2 8.48 16.97
2 9.13 18.25
2 9.77 19.54
2 10.41 20.83
2 11.06 22.11
2 11.70 23.40
2 12.34 24.69
2 12.99 25.97
2 13.63 27.26
2 6.96 13.93
2 7.00 14.00
2 1.04 2.08
2 7.08 14.16
T D S 14.1. 50 x 70 mm Zigba purlin .
2 7.12 14.23
2 7.12 14.23
2 0.70 1.40
2 1.40 2.81
2 2.08 4.16
2 2.68 5.36
2 2.69 5.38
2 3.51 7.02
2 4.21 8.42
2 4.91 9.83
2 5.62 11.23
2 6.32 12.64
2 7.02 14.04
2 7.72 15.44
2 8.42 16.85
2 9.13 18.25
2 9.83 19.66
1 14.27 14.27
1 14.92 14.92
1 15.56 15.56
1 16.20 16.20
1 16.85 16.85
1 17.49 17.49
TOTAL 527.27 ml Perlin for main house
2
TOTAL 273.44 m Total area of roof covering
17.2. WINDOWS
window 1.50*1.40m 5mm glass
1 pcs
window 1.60*1.40m 5mm glass
1 pcs
window 1.30*0.70m 5mm glass
1 pcs
window 2.50*1.40m 5mm glass
1 pcs
window 3.00*1.46m 5mm glass
2 pcs
window 0.75*1.06m 5mm glass
2 pcs
window 0.75*1.10m 5mm glass
2 pcs
window 3.00*1.50m 5mm glass
1 pcs
window 0.75*1.00m 5mm glass
2 pcs
window 2.00*1.60m 5mm glass
1 pcs
TOTAL 14.00 pcs of window