Sunteți pe pagina 1din 15

Nakpil and Sons vs CA, 160 SCRA 334 (1988)

In the case at bar, although the damage was


Facts
ultimately caused by the earthquake which was an
Private respondents – Philippine Bar Association act of God, the defects in the construction, as well
(PBA) – a non-profit organization formed under the as the deviations in the specifications and plans
corporation law decided to put up a building in aggravated the damage, and lessened the
Intramuros, Manila. Hired to plan the specifications preventive measures that the building would
of the building were Juan Nakpil & Sons, while otherwise have had.
United Construction was hired to construct it. The
PFIC Inc. vs. Wallem, 582 SCRA 457 (2009)
proposal was approved by the Board of Directors
and signed by the President, Ramon Ozaeta. The Facts
building was completed in 1966.
October 1995, Anhui Chemicals Import and Export
Corp. loaded on board M/S Offshore Master a
In 1968, there was an unusually strong earthquake shipment consisting of sodium sulphate anhydrous,
which caused the building heavy damage, which led complete and in good order for transportation to
the building to tilt forward, leading the tenants to and delivery at the port of Manila for consignee,
vacate the premises. United Construction took covered by a clean bill of lading.
remedial measures to sustain the building.

On October 16, 1995, the shipment arrived in port


PBA filed a suit for damages against United
of manila and was discharged which caused various
Construction, but United Construction subsequently
degrees of spillage and losses as evidence by the
filed a suit against Nakpil and Sons, alleging defects
turn over survey of the arrastre operator. Asia Star
in the plans and specifications.
Freight delivered the shipments from pier to the
consignees in Quezon City, during the unloading, it
Technical Issues in the case were referred to Mr. was found by the consignee that the shipment was
Hizon, as a court appointed Commissioner. PBA damaged and in bad condition.
moved for the demolition of the building, but was
opposed. PBA eventually paid for the demolition
after the building suffered more damages in 1970 April 29, 1996, the consignee filed a claim with
due to previous earthquakes. The Commissioner Wallem for the value of the damaged shipment, to
found that there were deviations in the no avail. Since the shipment was insured with Phil.
specifications and plans, as well as defects in the First Insurance against all risks in the amount of
construction of the building. P2,470,213.50. The consignee filed a claim against
the First Insurance. First insurance after examining
the turn-over survey, the bad order certificate and
Issue Whether or not an act of God (fortuitous other documents paid the consignee but later on
event) exempts from liability parties who would sent a demand letter to Wallem for the recovery of
otherwise be due to negligence the amount paid to the consignee (in exercise of its
right of subrogation). Wallem did not respond to
Ruling
the claim.
Art. 1723 dictates that the engineer/architect and
contractor are liable for damages should the
building collapse within 15 years from completion. First Insurance then instituted an action before RTC
for damages against Wallem. RTC held the shipping
company and the arrastre operator solidarily liable
Art. 1174 of the NCC, however, states that no
since both are charged with the obligation to deliver
person shall be responsible for events, which could
the goods in good order condition.
not be foreseen. But to be exempt from liability due
to an act of God, the ff must occur:

The CA reversed and set aside the RTC's decision.


1) cause of breach must be independent of the will CA says that there is no solidary liability between
of the debtor the carrier and the arrastre because it was clearly
2) event must be unforeseeable or unavoidable established that the damage and losses of the
3) event must be such that it would render it shipment were attributed to the mishandling by the
impossible for the debtor to fulfill the obligation arrastre operator in the discharge of the shipment.
4) debtor must be free from any participation or
aggravation of the industry to the creditor.
Issue discharging wharf at the port of unloading, unless
agreed otherwise.
1. Whether or not the Court of Appeals erred in not
holding that as a common carrier, the carriers
duties extend to the obligation to safely discharge
COGSA provides that under every contract of
the cargo from the vessel;
carriage of goods by sea, the carrier in relation to
2. Whether or not the carrier should be held liable the loading, handling, stowage, carriage, custody,
for the cost of the damaged shipment; care, and discharge of such goods, shall be subject
to the responsibilities and liabilities and entitled to
3. Whether or not Wallems failure to answer the
the rights and immunities set forth in the Act.
extra judicial demand by petitioner for the cost of
Section 3 (2) thereof then states that among the
the lost/damaged shipment is an implied admission
carriers responsibilities are to properly and carefully
of the formers liability for said goods;
load, handle, stow, carry, keep, care for, and
4. Whether or not the courts below erred in giving discharge the goods carried.
credence to the testimony of Mr. Talens.

Ruling
On the other hand, the functions of an arrastre
(1) Yes, the vessel is a common carrier, and thus the operator involve the handling of cargo deposited on
determination of the existence or absence of the wharf or between the establishment of the
liability will be gauged on the degree of diligence consignee or shipper and the ship's tackle. Being the
required of a common carrier. (2) The first and custodian of the goods discharged from a vessel, an
second issue will be resolved concurrently. arrastre operator's duty is to take good care of the
goods and to turn them over to the party entitled to
their possession.
(3) The damage of the shipment was documented
by the turn0over survey and request for bad order
survey, with these documents, petitioner insist that Handling cargo is mainly the arrastre operator's
the shipment incurred damages while still in the principal work so its drivers/operators or employees
care and responsibility of Wallem before it was should observe the standards and measures
turned over to the arrastre operator. However, RTC necessary to prevent losses and damage to
found the testimony of Mr. Talens (cargo surveyor) shipments under its custody. Thus, in this case the
that the loss was caused by the mishandling of the appellate court is correct insofar as it ruled that an
arrastre operator. This mishandling was affirmed by arrastre operator and a carrier may not be held
the CA which was the basis for declaring the solidarily liable at all times. But the precise question
arrastre operator solely liable for the damage. is which entity had custody of the shipment during
its unloading from the vessel?

It is established that damage or losses were


incurred by the shipment during the unloading. As The records are replete with evidence which show
common carrier, they are bound to observe that the damage to the bags happened before and
extraordinary diligence in the vigilance over the after their discharge and it was caused by the
goods transported by them. Subject to certain stevedores of the arrastre operator who were then
exceptions enumerated under Article 1734 of the under the supervision of Wallem.
Civil Code, common carriers are responsible for the
loss, destruction, or deterioration of the goods. The
extraordinary responsibility of the common carrier It is settled in maritime law jurisprudence that
lasts from the time the goods are unconditionally cargoes while being unloaded generally remain
placed in the possession of, and received by the under the custody of the carrier. In the instant case,
carrier for transportation until the same are the damage or losses were incurred during the
delivered, actually or constructively, by the carrier discharge of the shipment while under the
to the consignee, or to the person who has a right supervision of the carrier. Consequently, the carrier
to receive them. is liable for the damage or losses caused to the
shipment. As the cost of the actual damage to the
subject shipment has long been settled, the trial
For marine vessels, Article 619 of the Code of courts finding of actual damages in the amount of
Commerce provides that the ship captain is liable P397,879.69 has to be sustained.
for the cargo from the time it is turned over to him
(4) Mr Talens credibility must be respected.
at the dock or afloat alongside the vessel at the port
of loading, until he delivers it on the shore or on the CA's decision is set aside. Wallem is liable.
Yao vs. Matel, 500 SCRA 136 (2006) townhouses based on the agreed specifications. As
such, he cannot be discharged from his obligations
FACTS:
by mere delivery of the same to the spouses Yao.
Spouses Yao contracted the services of Matela, a The agreed construction cost of the project was
licensed architect, to manage and supervise the P5M, however, the amounts reflected in the
construction of a two-unit townhouse at a total cost Building Permit, the Certificate of Completion and
of P5M. The construction started in the first week of the Certificate of Occupancy are far less.
April 1997 and was completed in April 1998, with
In the Building Permit, the total cost was pegged at
additional works costing P300K. Matela alleged that
P2.1M; in the Certificate of Completion, the actual
the spouses Yao paid him the amount of P4.6M,
cost of construction was P2.3M; while in the
thereby leaving a balance of P741k. When his
Certificate of Occupancy the cost of the project as
demand for payment went unheeded, Matela filed
built was declared at P2.31M. Considering the
a complaint for sum of money with the RTC.
discrepancies, the conclusiveness of the said
In their answer, the spouses Yao denied that the documents fall when arrayed against the pieces of
project was completed in April 1998. Instead, they evidence introduced by the spouses Yao.
alleged that Matela abandoned the project without
However, we find that the spouses Yao likewise
notice. They claimed that they paid Matela the sum
failed to comply with their undertakings. As alleged
of P4.7M which should be considered as sufficient
by Matela, the spouses Yao made periodic
payment considering that Matela used sub-standard
payments to him based on progress billings.
materials causing damage to the project which
However, the spouses Yao refused to pay the
needed a substantial amount of money to repair.
balance of the agreed construction cost despite
RTC rendered judgment in favor of Matela, based demands.
on documents issued by the Building Official of
The spouses Yao justified their non-payment by
Makati City. The Court of Appeals affirmed the
arguing that Matela abandoned the project and that
decision of the lower court but modified the
there were defects in its construction. Evidently,
amount of actual damages to P391k. Thereafter,
both parties in this case breached their respective
another case was filed by Matela, regarding the
obligations. The well entrenched doctrine is that the
collection of the P300k additional construction cost.
law does not relieve a party from the effects of an
ISSUE: WON MATELA MAY COLLECT ACTUAL unwise, foolish or disastrous contract, entered into
DAMAGES AND THE ADDITIONAL CONSTRUCTION with full awareness of what he was doing and
COST? entered into and carried out in good faith.

HELD: NO, BOTH PARTIES ARE GUILTY OF BREACH. However, in situations such as the one discussed
Reciprocal obligations are those which are created above, where it cannot be conclusively determined
or established at the same time, out of the same which of the parties first violated the contract,
cause, and which result in mutual relationships of equity calls and justice demands that we apply the
creditor and debtor between the parties. These solution provided in Article 1192 of the Civil Code:
obligations are conditional in the sense that the “Art. 1192. In case both parties have committed a
fulfilment of an obligation by one party depends breach of the obligation, the liability of the first
upon the fulfilment of the obligation by the other. infractor shall be equitably tempered by the courts.
In reciprocal obligations, the general rule is that
If it cannot be determined which of the parties first
fulfilment by both parties should be simultaneous
violated the contract, the same shall be deemed
or at the same time.
extinguished, and each shall bear his own
The rule then is that in reciprocal obligations, one damages.” In the instant case, the losses to be
party incurs in delay from the moment the other incurred by the parties will come, as far as Matela is
party fulfills his obligation, while he himself does concerned, in the form of the alleged unpaid
not comply or is not ready to comply in a proper balance of the construction cost that he is seeking
manner with what is incumbent upon him. If neither to collect from the spouses Yao.
party complies or is ready to comply with what is
For the latter, the losses that they will bear is the
incumbent upon him, the default of one
cost of repairing the defects in the project. We
compensates for the default of the other. In such
consider the amount of P4,699,610.93 which
case, there can be no legal delay. Both the trial
Matela has already received from the spouses Yao,
court and the Court of Appeals found that Matela’s
as sufficient payment for his services and the
“delivery” of the project constitutes a faithful
materials used in the project.
discharge of his duties. We find otherwise. Our
evaluation of the records reveal that Matela failed
to comply with his obligation to construct the
PEFLGC vs VP Eusebio, 434 SCRA 202 (2004) renewed or extended to 9 February 1983 and 9
March 1983, respectively.[17] The surety bond was
FACTS:
also extended for another period of one year,
the State Organization of Buildings (SOB), Ministry from 12 May 1982 to 12 May 1983.[18] The
of Housing and Construction, Baghdad, Iraq, Performance Bond was further extended twelve
awarded the construction of the Institute of times with validity of up to 8 December
Physical TherapyMedical Rehabilitation Center, 1986,[19] while the Advance Payment Guarantee was
Phase II, in Baghdad, Iraq, (hereinafter the Project) extended three times more up to 24 May
to Ajyal Trading and Contracting Company 1984 when the latter was cancelled after full refund
(hereinafter Ajyal), a firm duly licensed with the or reimbursement by the joint venture
Kuwait Chamber of Commerce for a total contract contractor.[20] The surety bond was likewise
price of ID5,416,089/046 (or about extended to 8 May 1987.[21]
US$18,739,668).[2]
As of March 1986, the status of the Project was 51%
On 7 March 1981, respondent spouses Eduardo and accomplished, meaning the structures were already
Iluminada Santos, in behalf of respondent 3-Plex finished. The remaining 47% consisted in electro-
International, Inc. (hereinafter 3-Plex), a local mechanical works and the 2%, sanitary works,
contractor engaged in construction business, which both required importation of equipment and
entered into a joint venture agreement with Ajyal materials
wherein the former undertook the execution of the
ISSUE: whether the respondent contractor
entire Project, while the latter would be entitled to
has defaulted in the performance of its obligations
a commission of 4% of the contract price.[3] Later, or
under the service contract.
on 8 April 1981, respondent 3-Plex, not being
accredited by or registered with the Philippine HELD: NO.
Overseas Construction Board (POCB), assigned and
However, since that foreign law was not properly
transferred all its rights and interests under the
pleaded or proved, the presumption of identity or
joint venture agreement to VPECI, a construction
similarity, otherwise known as the processual
and engineering firm duly registered with the
presumption, comes into play. Our law, specifically
POCB.[4] However, on 2 May 1981, 3-Plex and VPECI
Article 1169, last paragraph, of the Civil Code,
entered into an agreement that the execution of
provides: “In reciprocal obligations, neither party
the Project would be under their joint
incurs in delay if the other party does not comply or
management.[5]
is not ready to comply in a proper manner with
On 11 June 1981, SOB and the joint venture VPECI what is incumbent upon him.”
and Ajyal executed the service contract[15] for the
Default or mora on the part of the debtor is delay in
construction of the Institute of Physical
fulfillment of the prestation by reason of a cause
Therapy Medical Rehabilitation Center, Phase II,
imputable to the former. It is the non-fulfillment of
in Baghdad, Iraq, wherein the joint venture
an obligation with respect to time. It is undisputed
contractor undertook to complete the Project
that only 51.7% of the total work had been
within a period of 547 days or 18 months. Under the
accomplished. As found by both the Court of
Contract, the Joint Venture would supply manpower
Appeals and the trial court, the delay or the non-
and materials, and SOB would refund to the former
completion of the Project was caused by factors not
25% of the project cost in Iraqi Dinar and the 75% in
imputable to the respondent contractor.
US dollars at the exchange rate of 1 Dinar to
3.37777 US Dollars.[16] It was rather due mainly to the persistent violations
by SOB of the terms and conditions of the contract,
The construction, which was supposed to start on 2
particularly its failure to pay 75% of the
June 1981, commenced only on the last week of
accomplished work in US Dollars. Indeed, where
August 1981. Because of this delay and the slow
one of the parties to a contract does not perform in
progress of the construction work due to some
a proper manner the prestation which he is bound
setbacks and difficulties, the Project was not
to perform under the contract, he is not entitled to
completed on 15 November 1982 as scheduled. But
demand the performance of the other party.
in October 1982, upon foreseeing the impossibility
of meeting the deadline and upon the request of Al A party does not incur in delay if the other party
Ahli Bank, the joint venture contractor worked for fails to perform the obligation incumbent upon him.
the renewal or extension of the Performance Bond In order that the debtor may be in default it is
and Advance Payment Guarantee. Petitioners necessary that the following requisites be present:
Letters of Guarantee Nos. 81-194-F (Performance (1) that the obligation be demandable and already
Bond) and 81-195-F (Advance Payment Bond) with liquidated; (2) that the debtor delays performance;
expiry date of 25 November 1982 were then and (3) that the creditor requires the performance
because it must appear that the tolerance or surety argued that the performance bond merely
benevolence of the creditor must have ended. guaranteed the 20% down payment and not the
entire obligation of Mabunay. THE CIAC ruled in
As stated earlier, SOB cannot yet demand complete
favor of JPLUS ASIA. THE CA ruled that Mabunay has
performance from VPECI because it has not yet
not yet incurred delay and that obligation was not
itself performed its obligation in a proper manner,
yet demandable because the contract was
particularly the payment of the 75% of the cost of
terminated prior to completion date.
the Project in US Dollars. VPECI cannot yet be said
to have incurred in delay. ISSUES: w/n the Mabunay had incurred delay?
(YES) w/n the delay should be reckoned only after
Even assuming that there was delay and that the
the lapse of the 1 year contract period, and
delay was attributable to VPECI, still the effects of
consequently w/n Mabunay’s liability for liquidated
that delay ceased upon the renunciation by the
damages arises only upon the happening of such
creditor, SOB, which could be implied when the
condition (DELAY MUST BE RECKONED FROM FILING
latter granted several extensions of time to the
OF COMPLAINT)
former. Besides, no demand has yet been made by
SOB against the respondent contractor. HELD: Mabunay already incurred delay at the time
the contract was terminated.
Demand is generally necessary even if a period has
been fixed in the obligation. And default generally Default or mora on the part of the debtor is the
begins from the moment the creditor demands delay in the fulfillment of the prestation by reason
judicially or extra-judicially the performance of the of a cause imputable to the former. It is the
obligation. Without such demand, the effects of nonfulfillment of an obligation with respect to time.
default will not arise. Article 1169 of the Civil Code provides that those
obliged to deliver or to do something incur in delay
J PLUS ASIA DEVELOPMENT CORPORATION V. UTII
from the time the obligee judicially or extrajudicially
TY ASSURANCECORPORATION, GR NO. 199650
demands from them the fulfillment of their
JUNE 26, 2013
obligation.
FACTS: J Plus Asia, represented by its chairman Joo
One who contracts to complete certain work within
Han lee, and Martin Mabunay, entered into a
a certain time is liable for the damage for not
CONSTRUCTION AGREEMENT whereby Mabunay
completing it within such time, unless the delay is
undertook to build the former’s
excused or waived. The following requisites must be
Condominium/hotel in Boracay. The project was to
present in order that the debtor may be in default:
be completed within 1 yr from the siigning of the
(1) that the obligation be demandable and already
NOTICE OF AWARD and receipt of 20% down
liquidated; (2) that the debtor delays performance;
payment (8.4 milllion) The down payment was fully
and (3) that the creditor requires the performance
paid on January 14, 2008. Per the agreed work
judicially or extrajudicially.
schedule, the completion date of the project was
December 31, 2008. Mabunay also submitted the Mabunay was already in delay. Article 1374 of the
required Performance Bond issued by Utility Civil Code requires that the various stipulations of
Assurance Corporation (UTASSCO) in the amount a contract shall be interpreted together,
equivalent to 20% down payment or P8.4 million. attributing to the doubtful ones that sense which
may result from all of them taken jointly. Here, the
Mabunay commenced work on January 7, 2008.
work schedule approved by petitioner was
However, as evidenced by the Joint Construction
intended, not only to serve as its basis for the
Evaluation Result and Status, signed by both parties,
payment of monthly progress billings, but also for
the project was only 31.39 % complete as of
evaluation of the progress of work by the
November 14, 2008. Thus, J PLUS ASIA terminated
contractor. The Construction Agreement provided
the contract and sent demand letters to Mabunay
that the contractor shall be deemed in default, if
and the surety. J Plus Asia filed a request for
among others, it had delayed without justifiable
arbitration before the Construction Industry
cause the completion of the project by more than
Arbitration Commission (CIAC) and prayed that
30 calendar days based on official work schedule
MAbunay and Surety be ordered to pay 8.9 Million
duly approved by the owner.
as liquidated damages and 2.3 Million to the
unrecouped down payment or overpayment made The Construction Agreement authorizes petitioner
to Mabunay. to confiscate the Performance Bond to answer for
all kinds of damages it may suffer as a result of the
Mabunay’s answer alleged that the delay was
contractor’s failure to complete the building. Having
caused by retrofitting and other revision works
terminated the contract, petitioner is entitled to the
ordered by Joo Han Lee. The surety on the other
proceeds of the bond as indemnification for
hand filed a MTD for lack of cause of action. The
damages it sustained due to the breach committed
by Mabunay. Such stipulation allowing the 1956, Concepcion executed a deed of absolute sale
confiscation of the contractor’s performance bond overLot 59-C-1 in favor of Iluminada Pacetes for a
partakes of the nature of a penalty clause, which is purchase price of P21,600.00 upon which P7,500.00
an accessory undertaking to assume greater liability is to be paid upon signing of the contract and the
on the part of the obligor in case of breach of an balance of P14,100.00 to be paid upon delivery of
obligation. The Performance Bond guaranteed not the Title. On March 16, 1966, spouses Iluminada
only the 20% down payment but the full and faithful Pacetes and Agapito Pacetes executed a deed of
compliance of Mabunay’s obligations under the absolute sale over the disputed lots in favor
Construction Agreement. Nowhere in law or Constancio Maglana. And on April 22, 1980,
jurisprudence does it state that the obligation or Maglana executed a deed of sale in favor of Emilio
undertaking by a surety may be apportioned. Matulac for the purchase price of P150,000.00. And
on August 4, 1959, Concepcion died, leaving all her
The imposition of interest on the claims of
obligations to her heirs including the petitioners.
petitioner is in order. If a surety upon demand fails
to pay, he can be held liable for interest, even if in On June 11, 1993, the trial court rendered judgment
thus paying, its liability becomes more than the in favor of the defendants. The trial court ruled that
principal obligation. The increased liability is not this Court had affirmed, in G.R. No. 85538and G.R.
because of the contract but because of the default No. L-60690, the sales of the property from
and the necessity of judicial collection. Concepcion Palma Gil to Iluminada Pacetes, then to
Constancio Maglana and to Emilio Matulac; hence,
Gil vs CA, 411 SCRA 18 (2003)
the trial court was barred by the rulings of the
Facts Court. The plaintiffs appealed to the Court of
Appeals which affirmed the latter’s decision.
Concepcion Palma Gil, and her sister, Nieves Palma
Gil, married to Angel Villarica, were the co-owners ISSUE:
of a parcel of commercial land with an area of 829
Whether or not the trial court erred in not declaring
square meters in Davao City. The spouses Angel and
the sale of the properties in question from
Nieves Villarica had constructed a two-storey
Iluminada Pacetes to Constancio Maglana, thence,
commercial building on the property.
from Constancio Maglana to Emilio Matulac NULL
On October 13, 1953, Concepcion filed a complaint and VOID for there was delay incurred by
against her sister Nieves with the then Court of First Concepcion in not delivering the Title of the subject
Instance of Davao City for specific performance, to lands to Pacetes.
compel the defendant to cede and deliver to her an
RULING:
undivided portion of the said property with an area
of 256.2 square meters. After due proceedings, the Article 1191[35] in tandem with Article 1592[36] of the
court rendered judgment on April 7, 1954 in favor New Civil Code are central to the issues at bar.
of Concepcion, ordering the defendant to deliver to Under the last paragraph of Article 1169 of the New
the plaintiff an undivided portion of the said Civil Code, in reciprocal obligations, neither party
property with an area of 256.2 square meters. incurs in delay if the other does not comply or is not
Nieves appealed to the Court of Appeals which ready to comply in a proper manner with what is
affirmed the assailed decision. incumbent upon him. From the moment one of the
parties fulfills his obligation, delay in the other
The court issued a writ of execution. Nieves,
begins. Thus, reciprocal obligations are to be
however, refused to execute the requisite deed in
performed simultaneously so that the performance
favor of her sister. On April 27, 1956, the court
of one is conditioned upon the simultaneous
issued an order authorizing ex-officio Sheriff
fulfillment of the other.[37] The right of rescission of
Eriberto Unson to execute the requisite deed of
a party to an obligation under Article 1191 of the
transfer to the plaintiff over an undivided portion of
New Civil Code is predicated on a breach of faith by
the property with a total area of 256.2 square
the other party that violates the reciprocity
meters.
between them.[38]
Instead of doing so, the sheriff had the property
That the deed of absolute sale executed by
subdivided into four lots namely, Lot 59-C-1, with an
Concepcion Gil in favor of Iluminada Pacetes is
area of 218 square meters; Lot 59-C-2, with an area
an executory contract and not an executed contract
of 38square meters; Lot 59-C-3, with an area of 14
is a settled matter. In a perfected contract of sale of
square meters; and Lot 59-C-4,with an area of 560
realty, the right to rescind the said contract
square meters, all covered by a subdivision plan.
depends upon the fulfillment or non-fulfillment of
The sheriff thereafter executed a Deed of Transfer
the prescribed condition.
to Concepcion over Lot 59-C-1 and Lot59-C-2 with a
total area of 256.2 square meters.On October 24,
The vendee paid the downpayment of P7,500.00. By Although the vendee consigned with the Court only
the terms of the contract, the obligation of the the amount of P11,983.00, P2,017.00 short of the
vendee to pay the balance of the purchase price purchase price of P14,000.00, it cannot be claimed
ensued only upon the issuance of the certificate of that Concepcion was an unpaid seller because
title by the Register of Deeds over the property sold under the deed of sale, she was still obligated to
to and under the name of the vendee, and the transfer the property in the name of the vendee,
delivery thereof by the vendor Concepcion Gil to which she failed to do so. According to Article 1167
the latter. Concepcionfailed to secure a certificate of the New Civil Code:
of title over the property. When she died intestate
Art. 1167. If a person obliged to do something fails
on August 4, 1959, her obligation to deliver the said
to do it, the same shall be executed at his cost.
title to the vendee devolved upon her heirs,
including the petitioners. The said heirs, including Omengan vs PNB, 512 SCRA 305 (2007)
the petitioners failed to do so, despite the lapse of
eighteen years since Concepcions death. Facts: The Philippine National Bank (PNB) approved
petitioners-spouses’ application for a revolving
Iluminada was not yet obliged on August 8, 1977 to credit line of P3 million. The loan was secured by
pay the balance of the purchase price of the two residential lots.
property, but as a sign of good faith, she
nevertheless consigned the amount of P11,983.00, The first P2.5 million was released by Branch
part of the balance of the purchase price Manager Henry Montalvo on three separate dates.
of P14,000.00, with the court in Civil Case No. 1160. The release of the final half million was, however,
The court accepted the consignation and she was withheld by Montalvo because of a letter allegedly
issued receipts therefor. Still, the heirs of sent by Edgar’s sisters. It read:
Concepcion Gil, including the petitioners, failed to Please be informed that the property mortgaged,
deliver the said title to the vendee. Iluminada was while in the name of Edgar Omengan, is owned in
compelled to file, at her expense, a petition with co-ownership by all the children of the late
the RTC docketed as Miscellaneous Case No. 4715 Roberto and Elnora Omengan. The lawyer who
for the issuance of an owners duplicate of TCT No. drafted the document registering the subject
7450 covering the property sold which was granted property under Edgar’s name can attest to this
by the court on March 22, 1978. It was only on May fact. We had a prior understanding with Edgar in
9, 1978 that Iluminada managed to secure TCT No. allowing him to make use of the property as
61514 over the property under her name. Upon the collateral, but he refuses to comply with such
failure of the heirs to comply with the decedents arrangement. Hence, this letter. (emphasis ours)
prestation, Iluminada Pacetes was impelled to
resort to legal means to protect her rights and Montalvo was eventually replaced as branch
interests. manager by Manuel Acierto who released the
remaining half million pesos to petitioners on May
The petitioners, as successors-in-interest of the 2, 1997. Acierto also recommended the approval of
vendor, are not the injured parties entitled to a a P2 million increase in their credit line to the
rescission of the deed of absolute sale. It was Cagayan Valley Business Center Credit Committee in
Concepcions heirs, including the petitioners, who Santiago City.
were obliged to deliver to the vendee a certificate
of title over the property under the latters name, The credit committee approved the increase of
free from all liens and encumbrances within 120 petitioners’ credit line (from P3 million to P5
days from the execution of the deed of absolute million), provided Edgar’s sisters gave their
sale on October 24, 1956, but had failed to comply conformity. Acierto informed petitioners of the
with the obligation. conditional approval of their credit line.

The consignation by the vendee of the purchase But petitioners failed to secure the consent of
price of the property is sufficient to defeat the right Edgar’s sisters; hence, PNB put on hold the release
of the petitioners to demand for a rescission of the of the additional P2 million.
said deed of absolute sale.[45] On October 7, 1998, Edgar Omengan demanded the
It bears stressing that when the vendee consigned release of the P2 million. He claimed that the
part of the purchase price with the Court and condition for its release was not part of his credit
secured title over the property in her name, the line agreement with PNB because it was added
heirs of Concepcion, including the petitioners, had without his consent. PNB denied his request.
not yet sent any notarial demand for the rescission On March 3, 1999, petitioners filed a complaint for
of the deed of absolute sale to the vendee, or filed breach of contract and damages against PNB. The
any action for the rescission of the said deed with court decided in favor of petitioners.
the appropriate court.
The CA, reversed and set aside the RTC decision an exhaustive investigation on the history of the
dated April 21, 2001.7 mortgagor’s title. This rule is strictly applied to
banking institutions. xxx
Petitioners now contend that the CA erred when it
did not sustain the finding of breach of contract by Banks, indeed, should exercise more care and
the RTC. 8 prudence in dealing even with registered lands,
than private individuals, as their business is one
The existence of breach of contract is a factual
affected with public interest. xxx Thus, this Court
matter not usually reviewed in a petition filed under
clarified that the rule that persons dealing with
Rule 45. But since the RTC and the CA had
registered lands can rely solely on the certificate of
contradictory findings, we are constrained to rule
title does not apply to banks.12 (emphasis supplied)
on this issue.
Here, PNB had acquired information sufficient to
Issue: Was there a breach of contract?
induce a reasonably prudent person to inquire into
Ruling: There was none. the status of the title over the subject property.
Instead of defending their position, petitioners
Breach of contract is defined as follows: merely insisted that reliance on the face of the
[It] is the "failure without legal reason to comply certificate of title (in their name) was sufficient. This
with the terms of a contract." It is also defined as principle, as already mentioned, was not applicable
the "[f]ailure, without legal excuse, to perform any to financial institutions like PNB.
promise which forms the whole or part of the In truth, petitioners had every chance to turn the
contract."9 situation in their favor if, as they said, they really
In this case, the parties agreed on a P3 million credit owned the subject property alone, to the exclusion
line. This sum was completely released to of any other owner(s). Unfortunately, all they
petitioners who subsequently applied10 for an offered were bare denials of the co-ownership
increase in their credit line. This was conditionally claimed by Edgar’s sisters.
approved by PNB’s credit committee. For all intents PNB exercised reasonable prudence in requiring the
and purposes, petitioners sought an additional loan. above-mentioned condition for the release of the
The condition attached to the increase in credit line additional loan. If the condition proved
requiring petitioners to acquire the conformity of unacceptable to petitioners, the parties could have
Edgar’s sisters was never acknowledged and discussed other terms instead of making an
accepted by petitioners. Thus, as to the additional obstinate and outright demand for the release of
loan, no meeting of the minds actually occurred and the additional amount. If the alleged co-ownership
no breach of contract could be attributed to PNB. in fact had no leg to stand on, petitioners could
There was no perfected contract over the increase have introduced evidence other than a simple
in credit line. denial of its existence.

"[T]he business of a bank is one affected with public Since PNB did not breach any contract and since it
interest, for which reason the bank should guard exercised the degree of diligence expected of it, it
against loss due to negligence or bad faith. In cannot be held liable for damages.
approving the loan of an applicant, the bank WHEREFORE, the decision and resolution of the
concerns itself with proper [information] regarding Court of Appeals in CA-G.R. CV No. 71302 are
its debtors."11 Any investigation previously hereby AFFIRMED.
conducted on the property offered by petitioners as
collateral did not preclude PNB from considering Costs against petitioners.
new information on the same property as security
SO ORDERED.
for a subsequent loan. The credit and property
investigation for the original loan of P3 million did Spouses Giano vs. Makati Shangri-La, 641 SCRA 591
not oblige PNB to grant and release any additional (2011)
loan. At the time the original P3 million credit line
Facts
was approved, the title to the property appeared to
pertain exclusively to petitioners. By the time the Petitioner spouses, Luigi M. Guanio and Anna
application for an increase was considered, Hernandez-Guanio, booked respondent Makati
however, PNB already had reason to suspect Shangre-La Hotel for their wedding reception.
petitioners’ claim of exclusive
ownership.1avvphi1.net A week before their wedding reception, the hotel
scheduled a food tasting. Eventually, the parties
A mortgagee can rely on what appears on the agreed to a package where the final price was
certificate of title presented by the mortgagor and P1,150.00 per person.
an innocent mortgagee is not expected to conduct
According to the complainants, when the actual In absolving the hotel from damages, the Supreme
reception took place, ” the respondent’s Court noted that: “The appellate court, and even
representatives did not show up despite their the trial court, observed that petitioners were
assurance that they would; their guests complained remiss in their obligation to inform respondent of
of the delay in the service of the dinner; certain the change in the expected number of guests. The
items listed in the published menu were observation is reflected in the records of the case.
unavailable; the hotel’s waiters were rude and Petitioners’ failure to discharge such obligation thus
unapologetic when confronted about the delay; and excused, as the above-quoted paragraph 4.5 of the
despite Alvarez’s promise that there would be no parties’ contract provide, respondent from liability
charge for the extension of the reception beyond for “any damage or inconvenience” occasioned
12:00 midnight, they were billed and paid P8,000 thereby”
per hour for the three-hour extension of the event
Nevertheless, on grounds of equity, the High Court
up to 4:00 A.M. the next day. They further claim
awarded P50,000.00 in favour of the complainants
that they brought wine and liquor in accordance
and justified it by saying:
with their open bar arrangement, but these were
not served to the guests who were forced to pay for “The exculpatory clause notwithstanding, the Court
their drinks. They sent a letter-complaint to hotel notes that respondent could have managed the
and received an apologetic reply from the hotel’s “situation” better, it being held in high esteem in
Executive Assistant Manager in charge of Food and the hotel and service industry. Given respondent’s
Beverage. vast experience, it is safe to presume that this is not
its first encounter with booked events exceeding
They nevertheless filed a complaint for breach of
the guaranteed cover. It is not audacious to expect
contract and damages before the Regional Trial
that certain measures have been placed in case this
Court (RTC) of Makati City.
predicament crops up. That regardless of these
Answering, the hotel said that complainants measures, respondent still received complaints as in
requested a combination of king prawns and the present case, does not amuse.
salmon, hence, the price was increased to
Respondent admitted that three hotel functions
P1,200.00 per person, but discounted at P1,150.00;
coincided with petitioners’ reception. To the Court,
that contrary to their claim, the hotel
the delay in service might have been avoided or
representatives were present during the event,
minimized if respondent exercised prescience in
albeit they were not permanently stationed thereat
scheduling events. No less than quality service
as there were three other hotel functions; that
should be delivered especially in events which
while there was a delay in the service of the meals,
possibility of repetition is close to nil. Petitioners
the same was occasioned by the sudden increase of
are not expected to get married twice in their
guests to 470 from the guaranteed expected
lifetimes.”
minimum number of guests of 350 to a maximum of
380, as stated in the Banquet Event Order (BEO);2 What applies in the present case is Article 1170 of
and the Banquet Service Director in fact relayed the the Civil Code which reads:
delay in the service of the meals to complainant’s
father. Art. 1170. Those who in the performance of their
obligations are guilty of fraud, negligence or delay,
The RTC, relying heavily on the letter of the hotel’s and those who in any manner contravene the tenor
Executive Assistant ruled in favour of the thereof, are liable for damages.
complainants and awarded damages in their favour.
RCPI v. Verchez, et al. enlightens: In culpa
The Court of Appeals reversed the decision, noting contractual x x x the mere proof of the existence of
that the proximate cause of the complainant’s the contract and the failure of its compliance justify,
injury was the unexpected increase in the number prima facie, a corresponding right of relief. The law,
of their guests. recognizing the obligatory force of contracts, will
not permit a party to be set free from liability for
Issue
any kind of misperformance of the contractual
WON Makati Shangri-La Hotel may be held liable for undertaking or a contravention of the tenor thereof.
damages. A breach upon the contract confers upon the
injured party a valid cause for recovering that which
Ruling
may have been lost or suffered.
The Supreme Court reversed the Court of Appeals
The remedy serves to preserve the interests of the
decision, noting that in this case, the obligation was
promissee that may include his “expectation
based on a contract, hence, the concept of
interest ,” which is his interest in having the benefit
proximate cause has no application.
of his bargain by being put in as good a position as
he would have been in had the contract been approaching so-called deadline. Also, Engr.
performed, or his “reliance interest ,”which is his Turla (an authorized agent of the Vasquez) sent
interest in being reimbursed for loss caused by a letter to Ayala stating that they expected “the
reliance on the contract by being put in as good a development of Phase 1 to be completed by
position as he would have been in had the contract Feb 19, 1990, 3 years after the legal problems
not been made; or his”restitution interest,” which is with the previous contractor was settled.” By
his interest in having restored to him any benefit early 1990, Ayala was able to finish the
that he has conferred on the other party. Indeed, developments and offered the lots to the
agreements can accomplish little, either for their Vasquez at the prevailing price in 1990.
makers or for society, unless they are made the
 The Vasquez rejected the offer and insisted to
basis for action.
pay the 1984 price (the original date of the
The effect of every infraction is to create a new supposed 3 year develop period given by Ayala
duty, that is, to make RECOMPENSE to the one who after the agreement)
has been injured by the failure of another to
 Ayala argues that the MOA only gives the
observe his contractual obligation unless he can
petitioners a first right of refusal and can
show extenuating circumstances, like proof of his
therefore not demand Ayala to sell the
exercise of due diligence or of the attendance of
property at the 1984 price.
fortuitous event to excuse him from his ensuing
liability. Issue: 1. WON Ayala committed or merely
expressed intent to develop the property within 3
Vazquez vs Ayala Corporation, 443 SCRA 231
years of the signing of the MOA
(2004)
2. WON the MOA can properly be construed as an
Facts:
option contract or a right of first refusal
 Spouses Vasquez entered into a Memorandum
3. WON the Vasquez spouse can compel Ayala to
of Agreement (MOA) with Ayala Corporation
sell them the property at the 1984 price
for their share of stocks in Conduit
Development. The main assets of Conduit is the Held:
49.9 hectare of land (divided into Village 1, 2
and 3 of the Don Vicente Village) being  The MOA specifically said “The Buyer hereby
developed by Conduit. The development was commits that it will develop the Remaining
undertaken by G.P. Construction and Property into a first class residential subdivision
Development. of the same class as its New Alabang
Subdivision, and that it intends to complete the
 The MOA was signed on April 23, 1981, the first phase under its amended development
Closing of the agreement was to happen 4 plan within 3 years from the date of this
weeks after the signing. According to the MOA, Agreement” Also, under Art 1169 of the NCC,
Ayala intends to complete its development obligations whose fulfillment a day certain has
plan 3 years after the date of the agreement. been fixed shall be demandable only when that
Also, that Ayala agreed to give the petitioners a day comes.
first option to purchase the developed lots at
the prevailing market price at the time of the  While the first phrase uses the word commits
purchase. in reference to the development itself, the
After the execution of the MOA, Ayala word intends was used in relation to the
suspended the work on Village 1. Ayala then development of the property within 3 years. It
received a letter from Lancer General Builder, is then unmistakable that Ayala merely
informing that they were claiming the amount expressed their intention in completing the
of P1,509,558.80 as the subcontractor of GP. development within 3 years.
On March 22, 1982, GP not being able to reach  An option is a preparatory contract which one
an amicable settlement with Lancer, Lancer party grants another, for a fixed period and at a
sued GP Construction, Conduit and Ayala. GP determined price, the privilege to buy or sell,
then filed a cross-claim against Ayala. Both or to decide whether or not to enter into a
Lance and GP tried to enjoin Ayala for the principal contract. In a right of first refusal,
development of the property. The suit was only while the object might be determinate, the
terminated on February 19, 1987, after Ayala exercise of the right would be independent not
paid both GP and Lancer. only on the grantor’s eventual intention to
 The Vasquez spouses, believing that Ayala was enter into a binding juridical relation with
obligated to sell them the lots 3 years after the another but also on terms, including the price,
agreement, sent reminder letters of the that are yet to be firmed up.
 The Court held that the MOA is a mere right of II. WHETHER RESPONDENT GPS, EITHER AS A
first refusal and not an option contract. The COMMON CARRIER OR A PRIVATE CARRIER, MAY BE
phrase “at the prevailing market price at the PRESUMED TO HAVE BEEN NEGLIGENT WHEN THE
time of the purchase” connotes that there is no GOODS IT UNDERTOOK TO TRANSPORT SAFELY
definite period. WERE SUBSEQUENTLY DAMAGED WHILE IN ITS
PROTECTIVE CUSTODY AND POSSESSION.
 Since it has been established that the MOA is a
mere right of first refusal, the Vasquez spouses Ruling
cannot compel Ayala to sell them the property
On the first issue, the Court finds the conclusion of
at the 1984 price. The moment they rejected
the trial court and the Court of Appeals to be amply
the offer, petitioners lost their right to
justified. GPS, being an exclusive contractor and
purchase the property.
hauler of Concepcion Industries, Inc., rendering or
 The petition is Denied. offering its services to no other individual or entity,
cannot be considered a common carrier. Common
FGU Insurance vs GP Sarmiento Tricking, 386 SCRA,
carriers are persons, corporations, firms or
312
associations engaged in the business of carrying or
G.P. Sarmiento Trucking Corporation (GPS) transporting passengers or goods or both, by land,
undertook to deliver thirty (30) units of Condura water, or air, for hire or compensation, offering
S.D. white refrigerators aboard one of its truck, their services to the public,[8] whether to the public
driven by Lambert Eroles, from the plant site to the in general or to a limited clientele in particular, but
Central Luzon Appliances in Dagupan City. While the never on an exclusive basis.[9] The true test of a
truck was traversing it collided with an unidentified common carrier is the carriage of passengers or
truck, causing it to fall into a deep canal, resulting in goods, providing space for those who opt to avail
damage to the cargoes. themselves of its transportation service for a
fee.[10] Given accepted standards, GPS scarcely falls
FGU Insurance Corporation (FGU), an insurer of the within the term common carrier.
shipment, paid to Concepcion Industries, Inc., the
value of the covered cargoes. FGU, in turn, being The above conclusion notwithstanding, GPS cannot
the subrogee of the rights and interests of escape from liability.
Concepcion Industries, Inc., sought reimbursement
In culpa contractual, upon which the action of
of the amount it had paid to the latter from
petitioner rests as being the subrogee of
GPS. The trucking company failed to heed the claim,
Concepcion Industries, Inc., the mere proof of the
FGU filed a complaint for damages and breach of
existence of the contract and the failure of its
contract of carriage against GPS and its driver
compliance justify, prima facie, a corresponding
Lambert Eroles with the Regional Trial Court. In its
right of relief.[11] The law, recognizing the obligatory
answer, respondents asserted that GPS was the
force of contracts,[12] will not permit a party to be
exclusive hauler only of Concepcion Industries, Inc.,
set free from liability for any kind of
since 1988, and it was not so engaged in business as
misperformance of the contractual undertaking or a
a common carrier. Respondents further claimed
contravention of the tenor thereof.[13] A breach
that the cause of damage was purely accidental.
upon the contract confers upon the injured party a
The trial court, in its order of 30 April valid cause for recovering that which may have
1996,[1] granted the motion to dismiss. been lost or suffered. The remedy serves to
preserve the interests of the promisee that may
The subsequent motion for reconsideration having include his expectation interest, which is his interest
been denied,[3] plaintiff interposed an appeal to the in having the benefit of his bargain by being put in
Court of Appeals, contending that the trial court as good a position as he would have been in had the
had erred (a) in holding that the appellee contract been performed, or his reliance interest,
corporation was not a common carrier defined which is his interest in being reimbursed for loss
under the law and existing jurisprudence; and (b) in caused by reliance on the contract by being put in
dismissing the complaint on a demurrer to as good a position as he would have been in had the
evidence. contract not been made; or his restitution interest,
The Court of Appeals rejected the appeal of which is his interest in having restored to him any
petitioner and ruled in favor of GPS. benefit that he has conferred on the other
party.[14] Indeed, agreements can accomplish little,
Issues either for their makers or for society, unless they
I. WHETHER RESPONDENT GPS MAY BE are made the basis for action.[15] The effect of every
CONSIDERED AS A COMMON CARRIER AS DEFINED infraction is to create a new duty, that is, to make
UNDER THE LAW AND EXISTING JURISPRUDENCE. recompense to the one who has been injured by the
failure of another to observe his contractual
obligation[16] unless he can show extenuating date, the car was detained inside the banks
circumstances, like proof of his exercise of due compound.
diligence (normally that of the diligence of a good
On August 28, 1995, Dr. Gueco went to the bank
father of a family or, exceptionally by stipulation or
and talked with its Administrative Support, Auto
by law such as in the case of common carriers, that
Loans/Credit Card Collection Head, Jefferson
of extraordinary diligence) or of the attendance of
Rivera. The negotiations resulted in the further
fortuitous event, to excuse him from his ensuing
reduction of the outstanding loan to P150,000.00.
liability.
On August 29, 1995, Dr. Gueco delivered a
Respondent trucking corporation recognizes the
managers check in the amount of P150,000.00 but
existence of a contract of carriage between it and
the car was not released because of his refusal to
petitioners assured, and admits that the cargoes it
sign the Joint Motion to Dismiss. It is the contention
has assumed to deliver have been lost or damaged
of the Gueco spouses and their counsel that Dr.
while in its custody. In such a situation, a default on,
Gueco need not sign the motion for joint dismissal
or failure of compliance with, the obligation in this
considering that they had not yet filed their
case, the delivery of the goods in its custody to the
Answer. Petitioner, however, insisted that the joint
place of destination - gives rise to a presumption of
motion to dismiss is standard operating procedure
lack of care and corresponding liability on the part
in their bank to effect a compromise and to
of the contractual obligor the burden being on him
preclude future filing of claims, counterclaims or
to establish otherwise. GPS has failed to do so.
suits for damages.
Respondent driver, on the other hand, without
After several demand letters and meetings with
concrete proof of his negligence or fault, may not
bank representatives, the respondents Gueco
himself be ordered to pay petitioner. The driver, not
spouses initiated a civil action for damages to the
being a party to the contract of carriage between
MTCC. The Metropolitan Trial Court dismissed the
petitioners principal and defendant, may not be
complaint for lack of merit.[3]
held liable under the agreement. A contract can
only bind the parties who have entered into it or On appeal to the Regional Trial Court, the decision
their successors who have assumed their of the Metropolitan Trial Court was reversed.
personality or their juridical
position.[17] Consonantly with the axiom res inter The case was elevated to the Court of Appeals, but
alios acta aliis neque nocet prodest, such contract the CA denied the appeal.
can neither favor nor prejudice a third Ruling
person. Petitioners civil action against the driver can
only be based on culpa aquiliana, which, Fraud has been defined as the deliberate intention
unlike culpa contractual, would require the claimant to cause damage or prejudice. It is the voluntary
for damages to prove negligence or fault on the part execution of a wrongful act, or a willful omission,
of the defendant. knowing and intending the effects which naturally
and necessarily arise from such act or omission; the
International Corporate Bank vs Gueco, 351 SCRA fraud referred to in Article 1170 of the Civil Code is
516 (2001) the deliberate and intentional evasion of the normal
Facts fulfillment of obligation.[11]

The respondents Gueco Spouses obtained a loan We fail to see how the act of the petitioner bank in
from petitioner International Corporate Bank (now requiring the respondent to sign the joint motion to
Union Bank of the Philippines) to purchase a car. In dismiss could constitute as fraud. True, petitioner
consideration thereof, the Spouses executed may have been remiss in informing Dr. Gueco that
promissory notes which were payable in monthly the signing of a joint motion to dismiss is a standard
installments and chattel mortgage over the car to operating procedure of petitioner bank. However,
serve as security for the notes. this cannot in anyway have prejudiced Dr. Gueco.

The Spouses defaulted in payment of The motion to dismiss was in fact also for the
installments. Consequently, the Bank filed a Case benefit of Dr. Gueco, as the case filed by petitioner
for Sum of Money with Prayer for a Writ of against it before the lower court would be
Replevin. Dr. Francis Gueco was served summons dismissed with prejudice. The whole point of the
and was fetched by the sheriff and representative of parties entering into the compromise agreement
the bank for a meeting in the bank premises. After was in order that Dr. Gueco would pay his
some negotiations and computation, the amount outstanding account and in return petitioner would
was lowered to P154,000.00, However, as a result return the car and drop the case for money and
of the non-payment of the reduced amount on that replevin before the Metropolitan Trial Court. The
joint motion to dismiss was but a natural
consequence of the compromise agreement and practice to require its agents to present a validated
simply stated that Dr. Gueco had fully settled his deposit slip and, on that basis, LMC would issue to
obligation, hence, the dismissal of the the latter an acknowledgement receipt.
case. Petitioner's act of requiring Dr. Gueco to
Alice Laurel, is one of LMC’s “Educational
sign the joint motion to dismiss cannot be said to be
Consultants” or agents. On various dates covering
a deliberate attempt on the part of petitioner to
the period from May, [sic] 1991 up to August, 1992,
renege on the compromise agreement of the
Alice Laurel deposited checks to LMC’s subject
parties.
account at different branches of BPI, Each check
It should, likewise, be noted that in cases of breach thus deposited were retrieved by Alice Laurel after
of contract, moral damages may only be awarded the deposit slips were machine validated, except
when the breach was attended by fraud or bad thirteen (13) checks.
faith.[12] The law presumes good faith. Dr. Gueco
A verification with BPI by LMC showed that Alice
failed to present an iota of evidence to overcome
Laurel made check deposits with the named BPI
this presumption. In fact, the act of petitioner bank
branches and, after the check deposit slips were
in lowering the debt of Dr. Gueco from P184,000.00
machine-validated, requested the teller to reverse
to P150,000.00 is indicative of its good faith and
the transactions.
sincere desire to settle the case. If respondent did
suffer any damage, as a result of the withholding of fraudulent transactions of Alice Laurel and her
his car by petitioner, he has only himself to blame. husband was made possible through BPI teller’s
failure to retrieve the duplicate original copies of
BPI vs Lifetime Marketing, 555 SCRA 373 (2008)
the deposit slips from the former, every time they
Facts ask for cancellation or reversal of the deposit or
payment transaction.
Lifetime Marketing Corporation (LMC, for brevity),
opened a current account with the Bank of the Upon discovery of this fraud in early August 1992,
Philippine Islands (BPI, for brevity). LMC made queries from the BPI branches involved.
In reply to said queries, BPI branch managers
In this account, the sales agents of LMC would have
formally admitted that they cancelled, without the
to deposit their collections or payments to the
permission of or due notice to LMC, the deposit
latter. As a result, LMC and BPI, made a special
transactions made by Alice and her husband, and
arrangement that the formers agents will
based only upon the latter’s verbal request or
accomplish three (3) copies of the deposit slips, the
representation.
third copy to be retained and held by the teller until
LMCs authorized representatives, Mrs. Virginia Thereafter, LMC immediately instituted a criminal
Mongon and Mrs. Violeta Ancajas, shall retrieve action for Estafa against Alice Laurel and her
them on the following banking day. husband Thomas Limoanco, before the Regional
Trial Court of Makati, This case for estafa, however,
Sometime in 1986, LMC availed of the BPIs inter-
was archived because summons could not be served
branch banking network services in Metro Manila,
upon the spouses as they have absconded.
whereby the formers agents could make [a] deposit
to any BPI branch in Metro Manila under the same LMC, , filed a Complaint for Damages against BPI.
account. Under this system, BPIs bank tellers were After trial on the merits, the court a quo rendered a
no longer obliged to retain the extra copy of the Decision in favor of LMC. Only BPI filed an appeal.
deposit slips instead, they will rely on the machine- The Court of Appeals affirmed the decision of the
validated deposit slip, to be submitted by LMCs trial court but increased the award of actual
agents. For its part, BPI would send to LMC a damages to P2,075,695.50 and deleted the award of
monthly bank statement relating to the subject P100,000.00 as attorney’s fees.[3] Citing public
account. This practice was observed and complied interest, the appellate court denied reconsideration
with by the parties. in a Resolution[4] dated 30 January 2007. In this
Petition for Review[5] dated 19 March 2007,
As a business practice, the registered sales agents
or the Lifetime Educational Consultants of LMC, can Issue: Whether BPI observed the highest degree of
get the books from the latter on consignment basis, care in handling LMCs account
then they would go directly to their clients to sell.
Ruling: NO
These agents or Lifetime Educational Consultants
would then pay to LMC, seven (7) days after they Negligence in this case lies in the tellers’ disregard
pick up all the books to be sold. Since LMC have of the validation procedures in place and BPI’s utter
several agents around the Philippines, it required to failure to supervise its employees. Notably, BPI’s
remit their payments through BPI, where LMC managers admitted in several correspondences with
maintained its current account. It has been LMCs LMC
PPSI, however argued that it already
that the deposit transactions were cancelled attended to and settled claims of those who were
without LMC’s knowledge and consent and based injured in the collision and that it could not accede
only upon the request of Alice Laurel and her to the claim of Arriesgado because it was beyond
husband.[12] that of the terms of the insurance.

BPI cannot escape liability because of LMC’s failure The trial court found that the contention of
to scrutinize the monthly statements sent to it by the petitioner was invalid because the said truck
the bank. This omission does not change the fact had left it’s tail lights open and that the said road
that were it not for the wanton and reckless was well lit at the time of the accident. Hence, it
negligence of BPI’s tellers in failing to require the was the fault of the bus, for traveling at a fast pace,
surrender of the machine-validated deposit slips that the collision happened. The Petitioner, Tiu,
before reversing the deposit transactions, the loss appealed to the CA but was denied which prompted
would not have occurred. BPI’s negligence is him to seek another reconsideration.
undoubtedly the proximate cause of the loss. It is
Issue:
also true, however, that LMC should have been
more vigilant in managing and overseeing its own W/N The owner and driver of the Truck, Benjamin
financial affairs. The damages awarded to it were Condor and Sergio Pedrano, was liable due to their
correctly reduced on account of its own negligence in the lack of an early warning device
contributory negligence in accordance with Article and hence liable to the respondent as well.
1172 of the Civil Code. (Violation of Sec 34 of LTO Land traffic code.)
Tiu vs Arriesgado 437 SCRA 426 W/N Petitioner was negligent
Facts: W/N Petitioner was also liable for exemplary
damages, attorney’s fees and litigation expenses.
On March 15, 1987, a Truck marked “Condor Hollow
Blocks and General Merchandise” was on its way to W/N PPSI is also liable.
Cebu when it’s rear tire exploded. The driver Sergio
Pedrano then parked the truck on the side of the Held:
National Highway, left the rear lights on, and The court found that indeed, the petitioner,
instructed his helper, Jose Mitante, to watch over was liable for being negligent while being engaged
the truck and place a spare tire on the road a few in the business of common carriage. The SC could
meters away from the tire to serve as a warning no longer change the facts that were sustained in
device as he went and had the faulty tire the trial court and court of appeals hence, since it
vulcanized. was deemed that the bus was moving in a very fast
After Pedrano left, D’ Rough Riders speed which was the cause of the accident, the SC
passenger bus carrying the respondent, passed by will have to sustain that ruling and hold that indeed,
the same route and hit the truck. The respondent there was negligence on the part of the petitioner.
was injured in the collision and his wife, Felissa Also, the doctrine of “Last Clear Chance” is
Arriesgado eventually died after sustaining injuries inapplicable to the case because it could only apply
from the same. Hence, he filed a complaint against to a controversy between two colliding vehicles. In
the petitioner for breach of contract of carriage, this case, it was the passenger and not another
damages and for attorneys fees against the driver who was injured and thus, the said doctrine
petitioner, the owner of the bus, William Tiu and his could not be applied.
driver, Laspinas.
However, the respondents Pedrano and
However, the petitioner filed a third-party Condor was found by the court to be negligent as
complaint alleging that the said truck was parked in well. The court found that there was merit in the
a slanted manner and did not have any early contention of the petitioner that the said truck
warning devices displayed while it was left by the violated Section 34 or RA 4136, wherein they did
driver which resulted to the collision and would not have proper early warning devices in
therefore make, Benjamin Condor, the owner of the accordance with the said law.
truck liable as well.
Lastly, with regard to PPSI, the court held
Also, the petitioner included that he was that since it admitted to being bound by a contract
covered by Philippine Phoenix Surety and Insurance with the petitioner, it would be liable as well.
(PPSI) at the time of the incident which would However, the said liability would only fall within the
therefore make the same liable for part of the amount settled in the said contract.
damages that may arise as well.
Hence, the petition was partially granted.
Rodzssen Supply Company v Far East Bank and delivered by Ekman and
Trust Company G.R. No. 109087. 9 May 2001. voluntarily received and kept by petitioner.

Facts: Respondent bank's right to seek recovery from


petitioner is anchored, not upon the inefficacious
defendant Rodzssen Supply, Inc. opened with
Letter of Credit, but on Article 2142 of the Civil
plaintiff Far East Bank and Trust Co. a 30-day
Code which reads as follows:
domestic letter of credit, LC No. 52/0428/79-D, in
the amount of P190,000.00 in favor of Ekman and "Certain lawful, voluntary and unilateral acts give
Company, Inc. (Ekman) for the purchase from the rise to the juridical relation of quasi-contract to the
latter of five units of hydraulic loaders, to expire on end that no one shall be unjustly enriched or
February 15, 1979; that subsequent amendments benefited at the expense of another."
extended the validity of said LC up to October 16,
Indeed, equitable considerations behoove us to
1979; that on March 16, 1979, three units of the
allow recovery by respondent. True, it erred in
hydraulic loaders were delivered to defendant for
paying Ekman, but petitioner itself was not without
which plaintiff on March 26, 1979, paid Ekman the
fault in the transaction. It must be noted that the
sum of P114,000.00, which amount defendant paid
latter had voluntarily received and kept the loaders
plaintiff before the expiry date of the LC; that the
since October 1979.
shipment of the remaining two units of hydraulic
loaders valued at P76,000.00 sent by Ekman was Petitioner claims that it accepted the late delivery
'readily received by the defendant' before the of the equipment, only because it was bound to
expiry date [of] subject LC; that upon Ekman's accept it under the company's trust receipt
presentation of the documents for the P76,000.00 arrangement with respondent bank.
'representing final negotiation' on the LC before the
expiry date, and 'after a series of negotiations', Granting that petitioner was bound under such
plaintiff paid to Ekman the amount of P76,000.00; arrangement to accept the late delivery of the
and that upon plaintiff's demand on defendant to equipment, we note its unexplained inaction for
pay for said amount (P76,000.00), defendant' almost four years with regard to the status of the
refused to pay ... without any valid reason'. Plaintiff ownership or possession of the loaders. Bewildering
prays for judgment ordering defendant to pay the was its lack of action to validate the ownership and
abovementioned P76,000.00 plus due interest possession of the loaders, as well as its stolidity
thereon, plus 25% of the amount of the award as over the purported failed sales transaction.
attorney's fees. Significant too is the fact that it formalized its offer
to return the two pieces of equipment only after
"In the Answer, defendant interposed, inter alia, by respondent's demand for payment, which came
way of special and affirmative defenses that plaintiff more than three years after it accepted delivery.
ha[d] no cause of action against defendant; that
there was a breach of contract by plaintiff who in When both parties to a transaction are mutually
bad faith paid Ekman, knowing that the two units of negligent in the performance of their obligations,
hydraulic loaders had been delivered to defendant the fault of one cancels the negligence of the other
after the expiry date of subject LC; and that in view and, as in this case, their rights and obligations may
of the breach of contract, defendant offered to be determined equitably under the law proscribing
return to plaintiff the two units of hydraulic loaders, unjust enrichment.
'presently still with the defendant' but plaintiff
refused to take possession thereof.

"The trial court's ruling that plaintiff [was] entitled


to recover from defendant

The CA rejected petitioner's imputation of bad faith


and negligence to respondent bank for paying for
the two hydraulic loaders, which had been
delivered after the expiration of the subject letter of
credit.

Issue: Whether or not Far East Bank can still collect


from Rodzssen despite the expiration of the letters
of Credit

Held: Be that as it may, we agree with the CA that


petitioner should pay respondent bank the amount
the latter expended for the equipment belatedly

S-ar putea să vă placă și