Sunteți pe pagina 1din 2

HG Power Transmission Sdn. Bhd.

Client : Tenaga Nasional Berhad Date : 01/10/2018


Contract Title 500kV Double Circuit Transmission Line from PMU Bentong
South to PMU Lenggeng (Point L to LGNG) and 275kV Double
: Circuit Transmission Line from PMU Lenggeng to PMU Mahkota
Page : 1 Of 3
Cheras (Point L to Lenggeng)
Doc.
Contract No : TNB 369/2018 : MS-LC/01/REV1
No.
METHOD STATEMENT
Line Checking, Inspection & Handover

Description
1.0 Line Checking, Inspection and Handover

1.1 Installation of Anti-climbing Device (ACD)

1.1.1 All tower shall he fitted with anti-climbing devices. In this case it shall be
spike type of ACD. It shall be made of hot dip galvanized steel rods
bolted to angle steel member.
1.1.2 The ACD shall be installed at a height of about 3m and not more than
4.5m from nearest ground level.
1.1.3 The ACD shall be firmly attached to the tower body. Install the gate
section, as required by the respective drawing, on the leg where step
bolts are installed.

1.2 Line Checking and Inspection

Once all the major works on construction of the transmission line are completed,
line checking and inspection shall proceed this shall include minor works,
corrections and repairs on the line found during detailed checking of the
transmission line and prior to final inspection by the Client. This shall include, but
not limited to:

1.2.1 Final site clearance, grading and leveling of the area around tower legs
and disturbed portions of the working area and/or temporary access
roads or path to the tower site.
1.2.2 Installation of all danger and identification plates as required by
Specification.
1.2.3 Final checking, tightening and correcting of all found faults and/or
outstanding works on the steel tower, insulators, fittings, accessories,
conductors and earth-wires.
1.2.4 Clearing and/or trimming of all trees encroaching on the specified
clearance
1.2.5 Painting of lower steelwork (just above concrete level) by approved
bitumastic paint, if required as per Part 06: Transmission Works
Technical Specification

1.3 Final Inspection, Line Hanover (SAT and PIAT)

1.3.1 Upon completion of all works on the construction of the transmission line
or portion of the transmission line, the Contractor shall invite the Client
for joint inspection and handover of transmission line or portion of the
line.

1.3.2 These works shall include joint inspection of all ground works, steel tower,
insulators, fittings, conductors, earth-wires and all accessories installed
on transmission line. Any found faults shall be rectified immediately or at
earliest possible time and joint record of the inspection shall be taken.
HG Power Transmission Sdn. Bhd.

Client : Tenaga Nasional Berhad Date : 01/10/2018


Contract Title 500kV Double Circuit Transmission Line from PMU Bentong
South to PMU Lenggeng (Point L to LGNG) and 275kV Double
: Circuit Transmission Line from PMU Lenggeng to PMU Mahkota
Page : 2 Of 3
Cheras (Point L to Lenggeng)
Doc.
Contract No : TNB 369/2018 : MS-LC/01/REV1
No.
METHOD STATEMENT
Line Checking, Inspection & Handover

1.3.3 The inspection shall be done in accordance with TNB’s Site Acceptance
Test (SAT) procedure. The master defect list drafted by TNB’s site
inspection team/teams shall be followed and all defects specified therein
shall be rectified.

1.3.4 The next step shall be Line Test in accordance with TNB’s specification
and shall include: end to end testing of line conductors and OPGW,
phasing test and/or other test/tests that are agreed with TNB. All QA/QC
records collected during construction works, test certificates for
materials or any other relevant testing certificates, approved
construction drawings etc.